Southern Natural Gas Company 2017 Outage Review Meeting. Customer con call and Webex April 19, 2017
|
|
- Cory Bond
- 6 years ago
- Views:
Transcription
1 Southern Natural Gas Company 2017 Outage Review Meeting Customer con call and Webex April 19,
2 Welcome 2
3 Agenda Review of current and upcoming notable Outages April/May/June Contacts Unscheduled outages North System South System South Louisiana Elba Island/EEC 3
4 Disclaimers Anticipated Impacts are estimates. Actual nominations, market demand, weather and pipeline conditions, etc. will determine if, and through what level, restrictions become necessary. Unless otherwise stated, all scheduled dates represent gas days as defined in the Southern Natural Gas Pipeline tariff to mean a period of twenty four consecutive hours, beginning and ending at 9:00 a.m. (Central Clock Time). Scheduled dates are subject to change. Projects may be added, altered, delayed or cancelled. SNG will provide notice of such additions or changes via Southern s electronic bulletin board postings. Dates as posted on the EBB should be deemed correct in the event of conflicts between the EBB posted dates and dates within this presentation. 4
5 Color Key for Maps Green No Impact Anticipated Yellow Restrictions are possible With extended duration, restrictions could be necessary from time to time Meter(s) affected are noted with (PIN #) Red Restrictions are probable 5
6 Southern Natural Gas Pipeline Chattanooga Bear Creek Onward Bienville Logansport LA South Louisiana White Castle MS Muldon Louisville Pickens Reform Rankin Bay Springs York Gallion Enterprise Gwinville Pearl River Franklinton Toca North System McConnells South System FL GA Bell Mills Tarrant Atlanta Pell City DeArmanville Providence Ocmulgee Auburn Selma Elmore Rome Hartwell Ellerslie Hall Gate Thomaston Holy Trinity Albany Pavo SC Aiken Wrens Brookman Elba Riceboro Shady Side LNG 6
7 Southern Natural Gas Pipeline Unscheduled Outage Update Chattanooga Logansport Bear Creek Onward Bienville LA South Louisiana White Castle Pickens Rankin Gwinville Franklinton Toca MS Louisville Bay Springs Pearl River Muldon York Enterprise North System Tarrant McConnells Reform Providence Gallion Selma Bell Mills Pell City Auburn Elmore Holy Trinity South System FL GA Atlanta DeArmanville Hall Gate Ocmulgee Ellerslie Rome Thomaston Albany Hartwell Pressure restriction on 20 Wrens Savannah 2 nd loop line Restriction end date into July Seg Mdt/d reduced to 145 Mdth/d Pavo SC Aiken Wrens Brookman Elba Riceboro Shady Side LNG 7
8 SNG North System Maint. Review April/May/June Chattanooga Huntsville Bear Creek Shut in test to DIQ and DWQ allocated 64% MS Pickens Louisville Muldon Storage Reform McConnells Tarrant Providence Maint. Pigging Rome Calhoun line and Pell City Bell Mills DeArmanville Rome GA Atlanta Logansport Bear Creek Storage Bienville LA Onward Rankin Pressure test on NMLL to Segment 120 capacity of 643 Mdth/d reduced up to 90 Mdth/d Southern will be conducting other general maintenance during this period 8
9 SNG South System Maint. Review April/May/June MS Maint. At Plant Talbot (PIN ) to Hartwell Atlanta Aiken GA Wrens Remediation on SMLL on to York Gallion Selma Elmore Auburn Holy Trinity Ellerslie Thomaston Ocmulgee Hallgate Riceboro Elba Enterprise Bay Springs Gwinville Albany Brookman Pavo LNG Southern will be conducting other general maintenance during this period 9
10 SNG South Louisiana System Maint. Review April/May/June Gwinville Pearl River White Castle unit maintenance to LA Segment 350 capacity of 701 Mdth/d impacted as much as 150 Mdth/d MS Franklinton Maint. Pigging on 16 Erath line Sabine to Sea Robin in the 2 nd or 3 rd quarters, dates TBD Maint. Pigging on 20 Erath to SS 28 line in the 2 nd or 3 rd quarters, dates TBD West Leg White Castle East Leg Toca Maint. Pigging on 20 SS 28 line to White Castle in the 2 nd or 3 rd quarters, dates TBD Shadyside Southern will be conducting other general maintenance during this period 10
11 SNG North System Maint. Review remainder of year Chattanooga Maintenance At Logansport and Bienville stations Sept/Oct. dates TBD Logansport Bear Creek Storage Bienville LA Maint. Pigging Logansport Loop line , , & Bear Creek Shut in test to DIQ and DWQ allocated 64% Muldon Shut in test to DIQ and DWQ allocated MS36% Onward Pickens Rankin Station Maint. At Rankin Comp. sta to Segment 400 Capacity of 234 Mdth/d impacted up to 159 Mdth/d going south, no restriction north Louisville Maintenance at Alagasco Central Roebuck meter station( PIN ) 3 rd /4 th Qtr., dates TBD Muldon Storage Reform McConnells Huntsville Tarrant Providence Pell City Bell Mills DeArmanville Rome GA Station Maint. At Bell Mills September/October, dates TBD. Segment 170 capacity of 232 Mdth/d impacted up to 109 Mdth/d Atlanta Southern will be conducting other general maintenance during this period 11
12 SNG South System Maint. Review Remainder of year MS P/L Maint. Graniteville Mills line to Atlanta Hartwell Aiken Gwinville Bay Springs Enterprise York Gallion Selma Elmore Auburn Holy Trinity Ellerslie Maint. At AGL Hazlehurst(PIN ) 2 nd /3 rd Qtr. Dates TBD Thomaston Albany GA Ocmulgee Hallgate Wrens Maint. At Plant Washington (Tiger Creek)(PIN ) 2 nd /3 rd Qtr. Dates TBD Maintenance Unadilla #1 (PIN ) 3 rd /4 th Qtr., dates TBD Maintenance pigging 20 Wrens Savannah 2 nd Loop line in August, dates TBD Riceboro Elba Pavo Brookman Maintenance International Paper (PIN ) to LNG Southern will be conducting other general maintenance during this period 12
13 SNG South Louisiana System Maint. review Remainder of year Gwinville Pearl River Maintenance pigging on SS 28 line to White Castle in October, dates TBD LA Maintenance SNG/FGT West meter station last half of year, dates TBD. MS Franklinton P/L maintenance on the SS 28 line to West Leg White Castle Toca P/L maintenance on the SS 28 line to SNG will not be able to accept receipts Shadyside East Leg Southern will be conducting other general maintenance during this period 13
14 Gas Control Contacts Ganesh Venkateshan Manager (713) (office) (832) (cell) Kal Dankovich Outage Coordinator (713) (office) Jimmy Reese Lead Controller (713) (office) Daniel Mitchell Lead Controller (713) (office) 14
15 Questions? 15
GEORGIA URBAN AREAS. TN Legend. Robins Air Force Base AL. ,2 Fort Benning. ,3 Fort Gordon. ,4 Fort Stewart. ,5 Hunter Army Airfield
GEORGIA TN Legend NC 59 FLORENCE # Installations 75 STRAHNET 85 575 ROME 985 ATHENS ATLANTA 2 Fort Benning 3 Fort Gordon 4 Fort Stewart 5 Hunter Army Airfield 6 Marine Corps Logistics Base Albany 7 Naval
More informationNon-Pipeline Solutions Pre-RFP Webinar. January 24, 2018
Non-Pipeline Solutions Pre-RFP Webinar January 24, 2018 Agenda Con Edison s Need for Non-Pipeline Solutions Con Edison s Smart Solutions for Natural Gas Customers initiative Con Edison s Non-Pipeline Solutions
More informationSocial Studies Pacing Guide 2nd Grade. Unit 2: Our Georgia 10 days (2 weeks) August 17 August 28, 2015
Q1 Unit 1: Connecting Themes 5 days (1 week) Days Aug. 10-14, 2015 o Overview of all themes o Rituals and Routines SS2CG1 The student will define the concept of government and the need for rules and laws.
More informationNotice of Network Change Homestead, Florida Replacing Copper Facilities with Fiber and Digital Loop Carrier Systems
Notice of Network Change Homestead, Florida Replacing Copper Facilities with Fiber and Digital Loop Carrier Systems Carrier BellSouth Telecommunications, Inc. 675 West Peachtree Street NE Atlanta, Georgia
More information57TH INDIANA INFANTRY REGIMENT RECORDS,
Collection # M 0037 57TH INDIANA INFANTRY REGIMENT RECORDS, 1862 1865 Collection Information Historical Sketch Scope and Content Note Box and Folder Listing Processed By: Paul Brockman 14 February 1997
More informationTOWN CREEK, ALA.,.. APRIL 28, LEY S. ROME CROSS. SHERMAN S MARCH TO THE SEA. THREE YEARS SERVICE. SAVANNAH, GA. (Siege of), ATLANTA, GA.
MAY EIGHTY-FIRST REGIMENT OHIO VOLUNTEER INFANTRY, THREE YEARS SERVICE. This Regiment was organized in the State of Ohio, at large, in August and September, 1861, to serve three years. The original members
More informationTentative Project Schedule. Non-Discrimination i i Laws. Para Preguntas en español
Florida Department of Transportation, District Seven Project Newsletter Number 1 October 2012 The Florida Department of Transportation (FDOT) is conducting a Project Development & Environment (PD&E) study
More information2003 LHSAA FOOTBALL PLAYOFF BRACKETS - CLASS 5A
Carencro* Northshore Slidell* Destrehan East St. John* St. Augustine Jesuit* St. Amant Fontainebleau Barbe* South Lafourche O.P. Walker* (Sat.) G.W. Carver West Jefferson* L.W. Higgins Catholic, BR* Acadiana
More informationBox File Contents: Time Tables: Various Lines, Atlanta and West Point Railroad and The Western Railway of Alabama Time Tables
Southern Museum of Civil War And Locomotive History Archives and Library Wallace Haywood Collection Time Tables: Various Lines, 1926 1982 MS2010.017 Provenance: Wallace Haywood donated this collection
More informationA THRIVING MIDDLE GEORGIA
Plan for A THRIVING MIDDLE GEORGIA Presentation of Regional Assessment & Stakeholder Involvement Program September 3, 2015 Why Regional Planning? Challenges cross traditional city and county boundaries
More informationAlabama History Portfolios
2015-2016 Alabama History Portfolios Over the course of the year you will work on an ongoing Alabama History project. Students will be required to gather information on Alabama to create a portfolio. The
More informationDOD Native American Regional Consultations in the Southeastern United States. John Cordray NAVFAC, Southern Division Charleston, SC
DOD Native American Regional Consultations in the Southeastern United States John Cordray NAVFAC, Southern Division Charleston, SC Report Documentation Page Form Approved OMB No. 0704-0188 Public reporting
More informationDivision of Early Care and Education. Child Care Emergency Plan Template
Division of Early Care and Education Child Care Emergency Plan Template South Carolina Department of Social Services regulations require child care facilities to have a plan in place that addresses emergency
More informationCOLONIAL PIPELINE COMPANY. Index of FERC Tariffs. Updated: October 25, 2017
COLONIAL PIPELINE COMPANY Index of FERC Tariffs Updated: October 25, 2017 Published FERC Tariffs shall supersede this Index in the event of any discrepancy. PREPARED BY S. Green (678)762-2330 Rules and
More informationCollege Profiles - Navy/Marine ROTC
Page 1 of 6 The U.S. Navy and Marine Corps are a team that provides for our national defense. The men and women who serve are called on to provide support at sea, in the air and on land. The Navy-Marine
More informationARKANSAS 2015 SCHEDULE ALABAMA 2015 SCHEDULE FEBRUARY FEBRUARY MARCH MARCH APRIL APRIL MAY MAY
ALABAMA 13 U. OF MARYLAND - E. SHORE W, 6-0 14 U. OF MARYLAND - E. SHORE W, 11-0 15 U. OF MARYLAND - E. SHORE W, 19-0 20 AT HOUSTON L, 1-3 21 AT HOUSTON L, 9-14 22 AT HOUSTON W, 8-3 24 SAVANNAH STATE [DH-1]
More informationON THE ECONOMIC, BUSINESS AND POLITICAL CLIMATE
ON THE ECONOMIC, BUSINESS AND POLITICAL CLIMATE Roger Tutterow, Ph.D. Coles College of Business Kennesaw State University rtuttero@kennesaw.edu 2017 Spring Workshop May 25, 2017 Buford, GA Expansion Getting
More informationFlorida Power & Light Company s Firm Gas Transportation Request for Proposals Pre-Proposal Workshop. January 16, 2013
Florida Power & Light Company s Firm Gas Transportation Request for Proposals Pre-Proposal Workshop January 16, 2013 Important Dates Request for Proposals Q & A Agenda 2 FPL has established the following
More informationPart 1: Applicant Information
Environmental Stewardship and Climate Change Producer Program Application Form: Category A Grazing Management Environmental Stewardship and Climate Change Program - Application Year 2018-2023 Personal
More informationivolut!on STUDENT CONFERENCE ATLANTA, GA Take Risks. Leverage Resources. Seize Control. SEPTEMBER 20-22, TH ANNUAL NABA SOUTHERN REGION
ATLANTA, GA SEPTEMBER 20-22, 2018 ATLANTA MARRIOTT MARQUIS 39TH ANNUAL NABA SOUTHERN REGION ivolut!on Take Risks. Leverage Resources. Seize Control. WHY PARTNER WITH THE SRSC? When you partner with the
More informationDivision of Early Care and Education. Child Care Emergency Plan Template for Exempt Providers
Division of Early Care and Education Child Care Emergency Plan Template for Exempt Providers Federal law requires child care facilities that receive federal funds to have a plan in place that addresses
More informationON THE GLOBAL, REGIONAL & LOCAL ECONOMIC CLIMATE
ON THE GLOBAL, REGIONAL & LOCAL ECONOMIC CLIMATE ARC Regional Leadership Institute Roger Tutterow, Ph.D. Professor of Economics Mercer University Tutterow_RC@Mercer.edu Saint Simons Island, GA September
More informationWorkSource Georgia: Yesterday Today Tomorrow
WorkSource Georgia: Yesterday Today Tomorrow Menelik R. Alleyne, Esq. WIOA Services Director Georgia Department of Economic Development Workforce Division Question Yesterday - Workforce 9 Year Unemployment
More informationLEADERSHIP ANNUAL GIVING: KEY COMPONENTS OF A SUCCESSFUL PROGRAM
LEADERSHIP ANNUAL GIVING: KEY COMPONENTS OF A SUCCESSFUL PROGRAM August 6-7, 2018 New Orleans, LA Strengthen your donor pipeline and build your mid-level giving program. OVERVIEW Learn how to successfully
More informationREQUEST FOR PROPOSALS FOR THE PROVISION OF DAM BREAK ANALYSES AND INUNDATION MAPPING SERVICES FOR SOUTH FEATHER WATER AND POWER AGENCY S
REQUEST FOR PROPOSALS FOR THE PROVISION OF DAM BREAK ANALYSES AND INUNDATION MAPPING SERVICES FOR SOUTH FEATHER WATER AND POWER AGENCY S LITTLE GRASS VALLEY, SLY CREEK AND LOST CREEK DAMS Issued: December
More information10 th Annual Southern Obesity Summit November 13-15, 2016 JW Marriott Houston Houston, Texas
10 th Annual Southern Obesity Summit November 13-15, 2016 JW Marriott Houston Houston, Texas www.southernobesitysummit.org We invite you to support the 10 th Annual Southern Obesity Summit (SOS) as an
More informationInvitation to Submit Expression of Interest and Proposal
REPÚBLICA DEMOCRÁTICA DE TIMOR LESTE MINISTÉRIO DAS FINANCAS Invitation to Submit Expression of Interest and Proposal I. INTRODUCTION 1. The Government of Timor-Leste is inviting interested eligible Power
More informationAtlanta BeltLine, Inc.
Atlanta BeltLine, Inc. Quarterly Briefing Agenda Welcome & Open House ABI CEO Update Community Engagement Update Design & Construction Update Transit Update Atlanta BeltLine Partnership Update Q&A June
More informationGraduating Class Profile Summer 2001, Fall 2001, Spring 2002
Graduating Class Profile Summer 2001, Fall 2001, Spring 2002 Type of Degrees Awarded Associates 106 Bachelors 1,593 Masters 288 Total 1,987 Note: The rest of the information is for baccalaureate students
More informationsunshine tariff customer information
sunshine tariff customer information about the trial The trial is called the Sunshine Tariff project and is only being trialled in Wadebridge. The trial is unique and all learning will be shared with other
More information2005 Hurricane Response
2005 Hurricane Response Office of Electricity Delivery and Energy Reliability U.S. Department of Energy Jim McGlone 2005 Hurricane Response Timeline Hurricane impacts to energy infrastructure DOE s emergency
More informationRequest for Proposals (RFP) An Alternative Fuels Assessment & Feasibility Study
Request for Proposals (RFP) An Alternative Fuels Assessment & Feasibility Study VTA Project # 2016-01 From: Subject: Angela E. Grant, Administrator Project VTA #2016-01 Request for Proposals An Alternative
More informationTEMPORARY ROOFING CONUS ACI CONTRACTS 2015
TEMPORARY ROOFING CONUS ACI CONTRACTS 2015 ThomCo Enterprises Inc. SDVO Frederick Thomas Phone: 850 244 0811 745 Hollywood Blvd. NW Fort Walton Beach, FL 32548 W9128F 11 D 0003 $50M 05 JAN 2011 04 JAN
More informationFeed-In Tariff (FIT) Statement of Terms
Feed-In Tariff (FIT) Statement of Terms 1 This FIT Statement of Terms for the provision of Generation and Export (where applicable) Feed-in-Tariffs by SSE Electricity Limited (trading as Southern Electric,
More informationCity of Portsmouth Portsmouth, New Hampshire Public Works Department RFP #68-14 REQUEST FOR PROPOSAL
City of Portsmouth Portsmouth, New Hampshire Public Works Department RFP #68-14 REQUEST FOR PROPOSAL DESIGN ENGINEERING SERVICES NEW CASTLE WATER LINE IMPROVEMENTS INVITATION Sealed Proposals, plainly
More informationTranscontinental Gas Pipe Line Company, LLC Leidy Southeast Project Docket No. RP15-
Gas Pipeline Transco 2800 Post Oak Boulevard (77056) P.O. Box 1396 Houston, Texas 77251-1396 713/215-4060 January 29, 2015 Federal Energy Regulatory Commission 888 First Street, N.E. Washington, D.C. 20426
More informationDOING BUSINESS WITH THE NASA JOHN C. STENNIS SPACE CENTER STENNIS BUSINESS CONSORTIUM Robert Watts September 9, 2014
National Aeronautics and Space Administration DOING BUSINESS WITH THE NASA JOHN C. STENNIS SPACE CENTER STENNIS BUSINESS CONSORTIUM Robert Watts September 9, 2014 www.nasa.gov NASA Office of Small Business
More informationDEPARTMENT OF TRANSPORTATION STATE OF GEORGIA
MAY 2, 2014 DEPARTMENT OF TRANSPORTATION STATE OF GEORGIA AWARD ANNOUNCEMENT APRIL 18, 2014 LETTING AWARD IS MADE ON MAY 02, 2014 TO THE ON THE FOLLOWING CONTRACTS UNLESS OTHERWISE INDICATED. DBE PARTICIPANTS
More informationCivil Rights Bus Tour
Civil Rights Bus Tour Sponsored by Massachusetts College of Liberal Arts March 7-16, 2014 Schedule is subject to change. March 7 5:00 am Depart from MCLA Washington DC (8 hrs) (Arlington, VA area) Hotel
More informationAre you ready to lead?
Are you ready to lead? ATA is now seeking applicants Since 1933, trucking executives across the country have joined the American Trucking Associations to represent our industry to lawmakers and regulators,
More information2017 Spring Memphis NCF Memphis, TN Start Date: 04/26/2017 End Date: 04/27/2017. Exhibitor Listing
2017 Spring Memphis NCF Memphis, TN Start Date: 04/26/2017 End Date: 04/27/2017 Exhibitor Listing Albany State University 128 http://www.asurams.edu Auburn University 325 http://www.auburn.edu/admissions
More informationMarine Protection Rules Part 130B Oil Transfer Site Marine Oil Spill Contingency Plans
Marine Protection Rules Part 130B Oil Transfer Site Marine Oil Spill Contingency Plans ISBN 978-0-478-35460-7 Published by Maritime New Zealand, PO Box 27006, Wellington 6141, New Zealand Maritime New
More informationSAME INDUSTRY DAY MOBILE DISTRICT PROGRAM
SAME INDUSTRY DAY MOBILE DISTRICT PROGRAM 255 255 255 237 237 237 COL JAMES A. DELAPP DISTRICT COMMANDER 0 0 0 217 217 217 163 163 163 200 200 200 131 132 122 PETER F. TAYLOR, JR., P.E. DEPUTY DISTRICT
More informationThe Power of Collaboration: Working with LEPC s. Jeff Suggs, CEM Emergency Management Coordinator City of La Porte
The Power of Collaboration: Working with LEPC s Jeff Suggs, CEM Emergency Management Coordinator City of La Porte Intro La Porte: Located in Harris County, on Galveston Bay Entrance to the Houston Ship
More informationBand Camp. July 18 th August 3 rd, Adam Brooks, Band Director office cell
NORTH ATLANTA HIGH SCHOOL Center for the Arts Band Camp July 18 th August 3 rd, 2011 NORTH ATLANTA HIGH SCHOOL 2875 NORTHSIDE DRIVE ATLANTA GA 30305 Adam Brooks, Band Director 404 802 4747 office 386 235
More informationThe Future of the African Upstream Sector: EMERGENCE OF INDIGENOUS INDEPENDENTS. Presentation by Wale Tinubu Group Chief Executive 3 rd November 2010
The Future of the African Upstream Sector: EMERGENCE OF INDIGENOUS INDEPENDENTS Presentation by Wale Tinubu Group Chief Executive 3 rd November 2010 Agenda I. Introduction II Regional Disparity III. Spotlight
More informationAuburn University Office of Trademark Management and Licensing
Auburn University Office of Trademark Management and Licensing Retailer List Local, State, Regional LOCAL AUBURN/OPELIKA RETAILERS Anders Bookstore Ron Anders P.O. Box 350 212 W. Magnolia Avenue Auburn,
More informationBx23. Pelham Bay and Co-op City. Between. Local Service. Bus Timetable. Effective Fall MTA Bus Company
Bus Timetable Effective Fall 2018 MTA Bus Company Bx23 Local Service a Between Pelham Bay and Co-op City If you think your bus operator deserves an Apple Award our special recognition for service, courtesy
More informationJOB DEVELOPMENT CREDIT
SCEDA ECONOMIC DEVELOPMENT 101 May 8, 2014 NEXSEN PRUET April C. Lucas Tushar V. Chikhliker Nexsen Pruet, LLC Nexsen Pruet, LLC 1230 Main Street, Suite 700 1230 Main Street, Suite 700 Columbia, SC 29201
More informationPOLICY MANUAL. Subject: Disaster Policy Effective Date: October 24, 2008
Cumberland Heights Treatment Center POLICY MANUAL Subject: Disaster Policy Effective Date: October 24, 2008 Initiated By: Russell E. Taylor Approved By: Safety Director Review Dates: 11/11 RET, 10/13 RT
More informationHigher Education Provider Charts Undergraduate Students from Alabama by County (With a focus on Lawrence, Limestone, Madison and Morgan Counties)
Higher Education Provider Charts Undergraduate Students from Alabama by County (With a focus on Lawrence, Limestone, Madison and Morgan Counties) Calhoun Community College Fall 215 Compiled by Office of
More informationComparing the College of Charleston to Other Institutions: Comparative Institutions Overview
Peer List Graduation Public Appalachian State NC Town: D Master's/L 68.3% 7136 21652 18295 87.0% 71.8% University of Mary Washington VA Suburb: M Master's/L 74.4% 11630 26220 4726 82.5% 71.6% Private Elon
More informationPerformance-Based Regulation: The Power of Outcomes
October 5, 2017 Performance-Based Regulation: The Power of Outcomes RAP/CESC Webinar, Part 2 David Littell Principal The Regulatory Assistance Project (RAP) 550 Forest Avenue, Suite 203 Portland, Maine
More informationScotland Island and West Pittwater energy reliability project Community feedback summary
Scotland Island and West Pittwater energy reliability project Community feedback summary June 2017 Contents 1 Introduction...3 2. Community engagement overview...3 3. Community engagement summary (January
More informationAlysen Heil (Athens Tech) was unable to attend because of weather, so Dr. Hicks, Wilhelmina (Central GA) agreed to take minutes for the meeting.
Math Consortia February 17, 2015 10 am 1:30 pm Central Georgia Technical College, Macon The meeting began with a welcome from Dr. Benita Moore, Curriculum Program Specialist at TCSG. Chair Emily Phillips
More informationNSTC COMPETITIVE AREA DEFINITIONS. UIC Naval Service Training Command (NSTC), Great Lakes, IL
NSTC COMPETITIVE AREA DEFINITIONS UIC 00210 Naval Service Training Command (NSTC), Great Lakes, IL UIC 00210 NSTC, N8, Pensacola, FL UIC 0763A Recruit Training Command, Great Lakes, IL NSTC Pensacola Programs,
More informationBrownsville Treatment Plant after 1 million gallon per day upgrade. 100,000 gallon Storage Tank behind Office Building on KY 259 N.
HISTORY In August 1966, the North Edmonson Water District was created to serve all of the county west of Nolin River and north of Green River with Roger Rich, Gilbert Webb and Haskell Lane as commissioners
More informationArmy Director, Acquisition Career Management (DACM) Acquisition, Education, Training (AET) Opportunity
Army Director, Acquisition Career Management (DACM) Acquisition, Education, Training (AET) Opportunity Call for Nominations FY19 Acquisition Leadership Challenge Program (ALCP) Offerings in October, November
More informationNumber of Graduates Continuing their Education by Institution Class of St. Cloud State University
Class of 0- ARIZONA STATE UNIVERSITY-MAIN CAMPUS TEMPE AZ MIDWESTERN UNIVERSITY GLENDALE AZ UNIVERSITY OF PHOENIX PHOENIX AZ COLORADO STATE UNIVERSITY PUEBLO CO UNIVERSITY OF COLORADO BOULDER CO SACRED
More information339 New Leicester Highway, Suite 140 Asheville. NC Long-Range Transportation Plan Transportation Improvement Program Highway
MPO staff will provide an update on work being done on the Congestion Management Process (CMP). MPO staff has been undertaking an update of the CMP with the Prioritization Subcommittee as the plan s steering
More informationTERMS & CONDITIONS. 1. The maintenance work should be carried out at Pondicherry University campus and Guest House, kalapet, Puducherry.
TERMS & CONDITIONS 1. The maintenance work should be carried out at Pondicherry University campus and Guest House, kalapet, Puducherry. 2. The work should be carried out strictly in accordance with CPWD
More informationYear Round Pell Overview
A Guide to Year-Round s David Bartnicki March 26-28, 2018 U.S. Department of Education SCASFAA Annual Conference Year Round Pell Overview 2 1 Legislative Background The Consolidated Appropriations Act
More informationDescription of Company Operations. System Overview
Page 1 of 5 Description of Company Operations System Overview Great Lakes Gas Transmission Limited Partnership (Great Lakes) is engaged in the business of transporting natural gas in interstate commerce
More informationTapping Your Entrepreneurial Culture
Tapping Your Entrepreneurial Culture Presented by Michael Dalby, CCE Columbus Chamber of Commerce Sean Kennedy St. Petersburg Chamber of Commerce Penny Lewandowski Edward Lowe Foundation Christa Tinsley
More informationArts and Culture in Metro Atlanta: By the Numbers. February 21, 2018
Arts and Culture in Metro Atlanta: By the Numbers February 21, 2018 Graphic of numbers The Internet, 2014 Most Populous Metro Regions 01. New York 02. Los Angeles 03. Chicago 04. Dallas 05. Houston 06.
More informationVolume 10 Issue 03 March 2010 THE IFTA NEWS
International Fuel Tax Association Inc. 912 W Chandler Blvd. Suite B-7 Chandler, AZ 85225 480-839-4382 (ph) 480-839-8821 (fax) www.iftach.org Volume 10 Issue 03 March 2010 THE IFTA NEWS TAX RATE CHANGES
More informationUnit 3 Revolution, Statehood, and Westward Expansion. Lesson 4: Westward Expansion. Study Presentation
Georgia Studies Unit 3 Revolution, Statehood, and Westward Expansion Lesson 4: Westward Expansion Study Presentation Lesson 4: Westward Expansion Essential Question How do political policies and new technologies
More informationApplication Standardization
Application Standardization Georgia Student Financial Aid Application System (GSFAPPS) USG Joint Enrollment Meeting April 13, 2005 GSFAPPS Introduction Primary Means of applying for financial aid Scholarships
More informationIndustry Day. U.S. Department of Defense Mission Support. U.S. Army Mission Support. The Baltimore District
The Baltimore District Industry Day Sheraton Baltimore City Center Hotel November 5, 2013 Baltimore, MD US Army Corps of Engineers U.S. Department of Defense Mission Support Defense Distribution Susquehanna
More information$1.7 million. Last year the New Orleans UNCF Mayor s Masked Ball raised over
NEW ORLEANS 2018 HOST COMMITTEE The Honorable Mitchell J. Landrieu Mayor, City of New Orleans Michael L. Lomax, Ph.D. President and CEO, UNCF Therese M. Badon Vice President of Development Southern Division,
More information1.4 On 19 May 2011 the WA State Government announced a reduction in the Subsidy rate from 40c/kWh to 20c/kWh effective from 1 July 2011.
Horizon Power Residential Net Feed-in Tariff Scheme Terms and Conditions 1. Background 1.1 The State Government has introduced a subsidy scheme to encourage the installation of residential renewable energy
More informationREQUEST FOR QUALIFICATIONS -ENGINEERING DESIGN SERVICES -
BUCKSKIN SANITARY DISTRICT Parker, Arizona PUBLIC NOTICE FOR PROFESSIONAL ENGINEERING SERVICES REQUEST FOR QUALIFICATIONS -ENGINEERING DESIGN SERVICES - PHASE 5&6 WASTEWATER CONVEYANCE SYSTEM Chairman
More informationEEMIS: Enterprise Energy Management Information System
EEMIS: Enterprise Energy Management Information System Local Government Partnership Meeting November 17, 2015 Presented by: Lena Luna Senior Project Manager, Energy SBESC and its program offerings are
More informationNew England Pipeline Safety Seminar. October 19-20, Pipeline Safety Regulatory Update Portland, Maine
New England Pipeline Safety Seminar October 19-20, 2016 Pipeline Safety Regulatory Update Portland, Maine - 1 - PIPES ACT OF 2016 The Protecting our Infrastructure of Pipelines and Enhancing Safety (PIPES)
More information$1.8 million. 7 p.m. Last year the New Orleans UNCF Mayor s Masked Ball raised over
NEW ORLEANS 2017 The UNCF Mayor's Masked Ball is a premier fundraising gala and a major social event, focusing on raising public awareness and large corporate and individual donations to support deserving
More informationALTERNATIVE FUEL MECHANIC TRAINING COMPONENT REMOVE II PROGRAM GUIDELINES, POLICIES, AND PROCEDURES
ALTERNATIVE FUEL MECHANIC TRAINING COMPONENT REMOVE II PROGRAM GUIDELINES, POLICIES, AND PROCEDURES SECTION I INTRODUCTION T he San Joaquin Valley Air Pollution Control District (SJVAPCD) is seeking applications
More informationGENERAL GOVERNMENT AWARDS COMMITTEE MEETING
1. SC-0453-08 MONITORING SECURITY/FIRE ALARM SYSTEMS PUBLIC BUILDINGS TYCO INTEGRATED SECURITY, LLC $206,857.50 REV. EST. EXP., NOT TO EXCEED $2,632,756.28 2. CS-0365-12 POOL RENOVATIONS PUBLIC WORKS BACKYARD
More informationA Guide to Year-Round Federal Pell Grants
A Guide to Year-Round s David Bartnicki March 28-30, 2018 U.S. Department of Education 2018 Annual AASFAA Conference Agenda Year-round Pell overview Legislative background General requirements Unchanged
More informationGreater Philadelphia Office, Q Suburbs Continue to Perform, Solid Fundamentals in CBD
Greater Philadelphia Office, 217 Suburbs Continue to Perform, Solid Fundamentals in CBD 243,662 sq. ft. 14.74% $25.51 2.85 Million sq. ft. Figure 1: Philadelphia CBD Office Rent vs. Direct Vacancy *Arrows
More informationAmendments to FY Transportation Improvement Program of the Coastal Region Metropolitan Planning Organization (CORE MPO) October 2017
Amendments to FY 2018-2021 Transportation Improvement of the Coastal Region Metropolitan Planning Organization (CORE MPO) October 2017 The Transportation Improvement (TIP) is the MPO s short-range programming
More information2018 Spring Nashville NCF Nashville, TN Start Date: 05/06/2018 End Date: 05/06/2018. Exhibitor Listing
2018 Spring Nashville NCF Nashville, TN Start Date: 05/06/2018 End Date: 05/06/2018 Exhibitor Listing Agnes Scott College Booth Number: 316 http://www.agnesscott.edu AMDA College & Conservatory of the
More informationGeorgia Power s Renewable Portfolio. Kings Bay Naval Solar Project. Potential Future Military Projects
Camden Roundtable February 16, 2015 Georgia Power s Renewable Portfolio Growth of Solar 3 X 30 Army Solar Projects Kings Bay Naval Solar Project Potential Future Military Projects 2 3 Hydro 72 units at
More informationUser Guide Part 13 CMMS
User Guide Part 13 Contents 1 OVERVIEW... 4 1.1 What is?... 4 1.2 Hierarchy Model... 4 1.3 Compatibility... 4 2 GETTING STARTED... 5 2.1 Running... 5 2.2 and Data Model Designer... 5 2.3 Menu... 6 2.3.1
More information3A.1 LOCKS AND DAMS UPDATE
3A.1 LOCKS AND DAMS UPDATE 2012 JOINT CONFERENCE OF HARBOR SAFETY AND AREA MARITIME SECURITY COMMITTEES RICHARD C. LOCKWOOD Operations & Regulatory Division and Great Lakes & Ohio River Division RIT US
More informationKeeping Score When It Counts: Academic Progress/Graduation Success Rate Study of 2017 NCAA Division I Men s and Women s Basketball Tournament Teams
Media Contacts: Destini Orr 804-704-0195, destiniorr@knights.ucf.edu Todd Currie 561-284-0921, todd.currie@ucf.edu Keeping Score When It Counts: Academic Progress/Graduation Success Rate Study of 2017
More informationPage 1 of 6. Applicant's Name: Packet Contents
ASB Site Leader Application Due: Friday, November 3, 2017 by 4:00pm Please submit a printed and signed application with the required attachments to OSV office, SSA 14.431T, by the deadline. Applications
More informationHUGH GASTON CIVIL WAR LETTERS, , 2004
Collection # M 0833 HUGH GASTON CIVIL WAR LETTERS, 1862 1875, 2004 Collection Information Biographical Sketch Scope and Content Note Contents Cataloging Information Processed by Emily Castle 18 February
More informationHome-Based Business in Mount Pearl
Home-Based Business in Mount Pearl city of Mount Pearl As Members of Mount Pearl City Council, we are pleased to provide you with this guide to Home-Based Business in Mount Pearl. All businesses operating
More informationNew Jersey Energy Resilience Bank
New Jersey Energy Resilience Bank Overview SECTION 1 Introduction to the ERB The State of New Jersey 1 New Jersey Energy Resilience Bank (ERB) Overview The extensive damage and outages caused by Superstorm
More informationCOMSEC ACCOUNTS. Presented by: Steven R. Meaux COMSEC Custodian Raytheon Company, Garland TX April 2006
COMSEC ACCOUNTS Presented by: Steven R. Meaux COMSEC Custodian Raytheon Company, Garland TX 19-20 April 2006 AGENDA: Type of COMSEC Account DD Form 254 Requesting a COMSEC Account Nominating COMSEC Custodian
More informationNewton County. Impact Fee Annual Update FY2011
Newton County Impact Fee Annual Update FY2011 Newton County STWP Update 2011-2015 PLAN ELEMENT ITEM (ED, NOR OR ) General General DESCRIPTION Implement a Capital Improvement Plan Develop a comprehensive
More information2015 BOARD MEETING MINUTES OF THE JOINT SERVICE RESERVE COMPONENT FACILITY BOARD (JSRCFB) NEW HAMPSHIRE
A. CONVENING THE JSRCFB In accordance with DOD Directive 1225.07, dated 6 June 2001, Certified Current as of April 23, 2007 and per last years board recommended meeting format, the Board held its annual
More informationBusiness Advisory Committee. August 26, 2015
Business Advisory Committee August 26, 2015 1 Today s Topics SDEIS Comment Summary Project Update New Starts Application Submittal Municipal Consent Schedule Next Steps: 6 Month Look Ahead Southwest Corridor-wide
More informationAVAILABLE SPACE FORMER IRS STORAGE FACILITY
AVAILABLE SPACE FORMER IRS STORAGE FACILITY LOCATION Building Address - 3160 Charles Town Road Kearneysville, WV 25430 Located in City Limits - No County - Berkeley Located in Business/Industrial Park
More informationTo join the march (Rev 3)...
To join the march (Rev 3)... To join the Journey for Justice march, participants should plan to arrive at the meeting locations listed below no later than 6:30am. Each morning, AJ4J march participants
More informationRenewable Energy Subsidy Delivery Mechanism, 2013
Government of Nepal Ministry of Science, Technology and Environment Alternative Energy Promotion Centre Renewable Energy Subsidy Delivery Mechanism, 2013 April, 2013 Table of Content 1. Preface 3 2. Definition
More informationCITY OF DEERFIELD BEACH Request for City Commission Agenda
Item: CITY OF DEERFIELD BEACH Request for City Commission Agenda Agenda Date Requested: May 21, 2013 Contact Person: Charles DaBrusco, Director of Environmental Services Description: Purchase of Toyota
More informationHigher Education Procurement Summit
Higher Summit HEA Department of & Skills Higher Institutions Service Office of Government 9 th May 2017 Bedford Hall, Dublin Castle Meet the EPS team John Redfern EPS Portfolio Manager Philip Gurnett,
More informationSTUDENT FEE RATES and CONCEPTUAL BUDGET PLAN FY 2015
FC 5/15/14 Action Item 1-a BT 5/16/14 IV-9 REPORT TO THE BOARD OF TRUSTEES STUDENT FEE RATES and CONCEPTUAL BUDGET PLAN FY 2015 May 2014 Date: May 15, 2014 To: Re: The Purdue University Board of Trustees
More informationSTATE OF RHODE ISLAND AND PROVIDENCE PLANTATIONS PUBLIC UTILITIES COMMISSION
STATE OF RHODE ISLAND AND PROVIDENCE PLANTATIONS PUBLIC UTILITIES COMMISSION IN RE: THE NARRAGANSETT ELECTRIC : COMPANY d/b/a NATIONAL GRID 2017 : GAS INFRASTRUCTURE, SAFETY, AND : DOCKET NO. 4590 RELIABILITY
More information