1 City Council Report 915 I Street, 1 st Floor Sacramento, CA File ID: August 9, 218 Consent Item 1 Title: Supplemental Agreement with AECOMHunt for PreConstruction Services for the Ballroom for the Sacramento Convention Center Renovation and Expansion Project Location: 14 J Street, District 4 Recommendation: Pass a Resolution authorizing the City Manager or the City Manager s designee to: 1) execute Supplemental Agreement No. 3 with Hunt Construction Group, Inc. for an amount nottoexceed 395,529, for a new total nottoexceed amount of 1,83,895 in the Convention Center Complex Renovation Project (M1711) for additional preconstruction services for the new ballroom and prefunction area; and 2) increase expenditure budget in the Convention Center Complex Renovation Project (M1711) with a transfer of 395,592 in Community Center Fund (Fund 1) from the AudioVisual Improvement Project (M1713). Contact: Sabrina Tefft, Project Manager, ; Desmond Parrington, Senior Development Project Manager, ; Fran Halbakken, Assistant City Manager/Project Executive, ; Office of the City Manager Presenter: None Attachments: 1Description/Analysis 2Background 3Resolution 4Exhibit A Supplemental Agreement with Hunt Construction Group Susana Alcala Wood, City Attorney Mindy Cuppy, City Clerk John Colville, City Treasurer Howard Chan, City Manager Page 1 of

2 File ID: Consent Item 1 Description/Analysis Issue Detail: On July 25, 217, City Council approved a contract with Hunt Construction Group, Inc. (Hunt) for preconstruction services for the Convention Center Renovation and Expansion Project (Convention Center). However, the new ballroom was not part of the original project since at that time the new ballroom was to be part of a later phase. On December, 217, City Council authorized the City Manager to proceed with the design of the full program for the Convention Center, including the new ballroom. Council s decision was based on the proposal from the local hotel community to pay for the cost of the ballroom so that it could be built simultaneously with the rest of the project. On June 19, 218, the Council approved the design for Convention Center including the ballroom, which is to be funded by bond proceeds from an assessment district formed by the hotels. The hotels in the City and the unincorporated County are in the process of establishing that district. Since the ballroom and associated prefunction area add approximately 7, square feet to the project and extend the duration, additional funding is needed to allow Hunt to complete the preconstruction services and costestimating work for this additional area. Policy Considerations: The renovation and expansion of the Convention Center along with the new ballroom will allow the facility to remain attractive and competitive into the future, while providing a nationallyrecognized convention venue for residents, visitors and convention attendees. It is also anticipated to grow TOT revenue as more events will likely lead to more hotel night stays and may generate the need for additional hotel development in the Downtown. The requested actions support the following City General Plan policy: ERC The City shall support renovation and expansion of Convention Center facilities and adjacent supportive infrastructure, including hotels, to attract top tier national and international events. Economic Impacts: Not applicable Environmental Considerations: On June 19th, City Council passed a resolution certifying the Environmental Impact Report and adopting the Mitigation Monitoring Program, Findings of Fact, and a Statement of Overriding Consideration for the Sacramento Convention Center Renovation and Expansion Project. Sustainability: The Convention Center project will be designed to meet LEED Silver certification in accordance with City policy LU LEED Standard for CityOwned Buildings, Commission/Committee Action: Not Applicable City of Sacramento August 9, 218 powered by Legistar Page 2 of

3 File ID: Consent Item 1 Rationale for Recommendation: The approval of the additional scope of work for the ballroom is necessary to keep the project on track. It is also needed to ensure the City has accurate cost estimates for the ballroom as well as necessary preconstruction services so that the plans are ready for construction. Financial Considerations: Supplemental Agreement No. 3 with Hunt Construction Group, Inc will be funded by the transfer of 395,529 from the AudioVisual Improvement Project (M1713) to the Convention Center Complex Renovation Project (M1711) in the Community Center Fund (Fund 1). This will increase the agreement s original nottoexceed amount of 1,441,3 to a new nottoexceed amount of 1,83,895. There is sufficient funding in M1713 to make the transfer. Under Resolution No. 2173, this expenditure is eligible for reimbursement and the funds will be restored to M1713 once the bonds for the project are issued in October 218. The background section of this report identifies all prior financial actions associated with the project as well as those associated with the Community Center Theater project and the Memorial Auditorium project. Local Business Enterprise (LBE): Hunt Construction Group, Inc. is an LBE since it is part of AECOM, which has an office in Sacramento. City of Sacramento August 9, 218 powered by Legistar Page 3 of

4 Background Projects History and Council Actions: The following is the current history including Council actions and financing transactions associated with the Convention Center, Community Center Theater and Memorial Auditorium projects: On March 9, 21, the City Council in City Resolution No. 215 suspended competitive bidding, approved a designassist delivery method, approved a 3 facility fee charged on each ticket sold, and directed staff to proceed with the renovation of the CCT. On March 15, 21, the City issued an RFQ for designassist support services for the CCT project and Kitchell CEM, Inc. was selected as the most qualified firm. On August 1, 21, Council approved the selection of Kitchell CEM, Inc. in City Resolution No for the CCT renovation. On March 2, 213, the City Council in City Resolution No approved 8.5 million toward the CCT Renovation Project. However, on November 19, 213, the City Treasurer recommended that Council defer financing of the CCT renovation given the use of some of the TOT revenue for the Entertainment and Sports Center project (now Golden 1 Center) and the outstanding debt on the facilities. As a result, in Motion No Council directed 1) staff to return immediately with a plan to address deferred maintenance; 2) the City Attorney s Office to return with a memo on the City s legal obligations and concerns; and 3) staff to return with three renovation options to include financing: a) minimum requirements for basic ADA compliance plan; b) an alternative 1year facility plan to include public engagement; c) a 3 year plan to consider either a new facility or the complete improvement plan to include public engagement. A Performing Arts Task Force was established and provided updates to the City Council in November 214 and again in April 215 on potential development options for the CCT. However, sufficient funding was not identified to provide for the construction of a new CCT. On May 3, 21, Council approved City Resolution No appropriating, from the Community Center Fund's fund balance; 2) modifying the scope and name of M1711 to include the SCC Complex; 3) approving professional services agreements with DLR/Westlake Reed Leskosky in the Page 4 of

5 amount of 98,825 (for initial design of the CCT during the project definition phase), Populous in the amount of 27, (for initial design of the SCC during the project definition phase), and Pfocus/Rider Levett Bucknall (for owner s representation and advisory services during the project definition phase) in the amount of 15,; and 4) directing staff to proceed with the project definition phase of an integrated project to renovate the CCT and expand the SCC. On October 18, 21, City Council directed staff to proceed with the design of the CCT Renovation Project and Memorial Auditorium Project, suspended competitive bidding for the SCC project to allow for a designassist method of delivery, but recommended staff explore other options for the design and financing of the SCC and to return at a later date. Council also directed staff to select a consultant to design the Memorial Auditorium upgrades and a consultant to perform preconstruction services for the Memorial Auditorium upgrades, and to bring proposed contracts to City Council for consideration as this would allow CCT events to shift to the Auditorium for one year to allow for a much quicker renovation of Theater. On January 24, 217, City Council approved City Resolution No. 2173, which declared the City Council s official intent to reimburse the City from bond proceeds for design and other predevelopment costs associated with the CCT, Memorial Auditorium, and SCC projects. On January 24, 217, City Council approved City Resolution No , which suspended competitive bidding for the Memorial Auditorium project and authorized: (1) the release of 5.5 million of the 8.5 million commitment of fund balance for the Convention Center Complex projects in the General Fund (Fund 11) to the Convention Center Complex Renovation Project (M1711); (2) a 1,,738 contract with Architectural Nexus for the design of the improvements; and (3) a 187, contract with Rider Levett Bucknall for owner representation and advisory services. On February 14, 217, City Council approved City Resolution No which authorized a 5 million loan from available fund balance in the Community Center Fund (Fund 1). This is to be repaid when bonds are issued. On May 1, 217, City Council approved City Resolution No that authorized the purchase of the VAMPS acoustic shell for Memorial Auditorium that was needed for performances with the use of 35, from the Community Center Fund (Fund 1). On May 3, 217, Populous presented the conceptual design for the SCC identifying how the project would be built in two phases. The first phase would include new exhibit space, a multipurpose room, a new kitchen, east and west Page 5 of

6 lobbies and new meeting rooms. The second later phase would include a new ballroom. The City Council adopted City Resolution No which authorized a 3.8 million interfund loan from the General Fund (Fund 11) to the Convention Center Complex Project (the Project), a 3.8 million interfund loan from the Innovation and Growth Fund (Fund 231) to the Project, and a 3.4 million internal loan from Fund 1 to the Project. These loans are to be repaid when bonds are issued. Council also authorized the preparation of an EIR for the SCC project and executed a contract with ESA for preparation of the EIR. On June, 217, City Council approved Motion No which authorized a 177, Preconstruction Services Agreement with an option for Guaranteed Maximum Price for Construction with Kitchell CEM, Inc. for the Memorial Auditorium project. On December 5, 217, City Council agreed to move forward with the full program for the SCC which would allow the new 4, square foot ballroom to be built at the same time as the rest of the project contingent upon funding provided by the hotel community to cover the cost of the ballroom. On March 2, 218, Council approved Motion No for a supplemental agreement with Kitchell for additional services related to local hiring in the construction of the Memorial Auditorium project for an amount nottoexceed 49,57, bringing the total agreement to a new nottoexceed amount of 7,374. On March 27, 218, Council approved Motion No for a supplemental agreement with Rider Levett Bucknall, Ltd. to extend the term of their contract for owner s representation services through April 3 th and pay 24, for their services for a new total contract amount of,. That agreement was later extended by the City Manager again until May 31 st at an additional cost of,333 for a total contract amount of 238,999. Due to the size of the last increase, that supplemental agreement was done under City Manager authority and did not require staff to return to Council. On April 3, 218, City Council approved Motion No for the removal of four trees along I Street and 15 th Street for the Memorial Auditorium project to allow for the construction of improvements there. May, 218, City Council approved a resolution that authorized (1) the City Manager or his designee to execute Supplemental Agreement No. 2 to City Agreement No with Kitchell CEM, Inc., in the amount of 1,739,19 for the construction of improvements to Memorial Auditorium (M1711), for a new nottoexceed total contract amount of 1,9,543; (2) an interfund loan Page of

7 between the Water Fund (Fund 5) and the Community Center Fund (Fund 1); and (3) the transfer of 11,75,17 from Fund 5 to Fund 1. On May 29, 218, City Council approved Motion Nos and which approved contracts for Architectural Nexus for construction administration services and for construction management services, respectively for the Memorial Auditorium project. On June 19, 218, City Council approved Resolution No certifying the Environmental Impact Report for the Sacramento Convention Center (SCC) Renovation and Expansion Project. In addition, Council also approved Resolution No and Resolution No that approved the design for the SCC and CCT projects, respectively, and directed the City Manager to proceed with the projects. Council also rescinded Resolution No , which authorized the City to apply for a 15 million loan from the California Infrastructure and Economic Development Bank (IBank) for Memorial Auditorium project. City Council then approved Resolution No and Resolution No authorizing staff to submit two applications to the California Infrastructure and Economic Development Bank (IBank) in an amount not to exceed million. Finally, City Council passed Resolution No as amended directing the City Manager to return to City Council to present local hiring and local business involvement programs prior to the start of the projects. On July 3, 218, Council passed Resolution No which increased Populous contract by 35,944, for a new total not to exceed amount of 1,91,19 for additional design services for the Convention Center Complex Renovation Project. It also approved an agreement with Enovity for an amount not to exceed 27, to provide enhanced commissioning and other services necessary for LEED Silver Certification for the Convention Center Complex Renovation Project; and transferred 278,53 from the Community Center Improvements Project (M171) in Community Center Fund (Fund 1) to the Convention Center Complex Renovation Project to fund these agreements. On July 1, 218, the City Manager approved a modification to the City s agreement with AECOMHunt (Contract No. 211) that moved funds from travel expenses to be used for designassist services from trade contractors during the preconstruction phase in order to inform the final construction documents. There was no change to the overall contract amount. Also, on July 1, 218, the City Manager approved a modification to the City s contract with DLR/Westlake Reed Leskosky (Contract No ) to update the invoicing schedule for the Theater project. There was no change in the contract amount. Page 7 of

8 On August 2, 218 the City Manager approved another modification to the City s agreement with AECOMHunt (Contract No. 212), which included the scope of work for designassist services from three trade contractors dealing with piles, precast and vertical transportation services (elevators and escalators). There was no change to the overall contract amount. Page 8 of

9 RESOLUTION NO. 218 Adopted by the Sacramento City Council AUTHORIZING A SUPPLEMENTAL AGREEMENT AND FUNDING FOR PRECONSTRUCTION SERVICES FOR THE NEW BALLROOM IN THE SACRAMENTO CONVENTION CENTER RENOVATION AND EXPANSION PROJECT A. On July 25, 217, City Council in Motion No. 217 approved a contract with Hunt Construction Group, Inc. for preconstruction services for the Convention Center Renovation and Expansion Project, but that contract did not include the new ballroom as that was originally to be part of a later phase of the project. B. On December, 217 City Council directed staff in Motion No to proceed with the design of the full program for the renovation and expansion of the Sacramento Convention Center (SCC), which added the future ballroom to the current phase of work. C. In order to allow Hunt to do the work on the ballroom needed for Construction Document (CD) and Guaranteed Maximum Price (GMP) phases of the project, additional funding is required. D. Funding is needed presently from specific CIPs in the Community Center Fund to pay for the additional preconstruction services for the new ballroom in the Convention Center and Community Center Theater projects. E. The funding is being advanced until the bonds for the project are issued, at which time the will be reimbursed. In the event the City Council does not authorize construction of this project, the funds will not be repaid. F. On January 24, 217, City Council approved Resolution No which allows for bonds issued for the Community Center Theater, Memorial Auditorium and Convention Center projects to be used to cover design, preconstruction services, and other soft costs associated with these projects. BASED ON THE FACTS SET FORTH IN THE BACKGROUND, THE CITY COUNCIL RESOLVES AS FOLLOWS: Section 1. The City Manager or his designee is authorized to execute Supplemental Agreement No. 3 with Hunt Construction Group, Inc. for an amount nottoexceed 395,529, for a new total nottoexceed Page 9 of

10 Section 2. amount of 1,83,895 in the Convention Center Complex Renovation Project (M1711) for additional preconstruction services for the new ballroom and prefunction area. The City Manager or his designee is authorized to increase expenditure budget in the Convention Center Complex Renovation Project (M1711) with a transfer of 395,592 in Community Center Fund (Fund 1) from the AudioVisual Improvement Project (M1713). Exhibit A Supplemental Agreement with Hunt Construction Group, Inc. Page 1 of

11 ontractor Page 11 of

12 Attachment 1 Revised PreConstruction Cost DesignAssist Preconstruction to GMP Revision to include new timeline and Phase 2 Estimating EXHIBIT B PRECONSTRUCTION COST PROPOSAL Sacramento Convention Center Renovation and Expansion Aug 217 Sep 217 Oct 217 Nov 217 Dec 217 Concept Concept Concept Concept Schematic Original Original Original Original Original Position Rate PrincipalinCharge Jan 218 Feb 218 Mar 218 Apr May 218 Jun 218 Jul 218 Aug 218 Credit Sep 218 Oct 218 Nov 218 Dec 218 Design Design Design Design Backlog Design GMP & GMP & Permitting SUMMARY 119 Project Executive. 8 18,885 2,4 17, ,4 2 4,4 2, , 2 4,4 2 4,4 17, , ,772 17, ,19 28,72 2,4 11 2, ,77 243,218 Sr. Project Manager ,9 4,428 32, ,38 3 7,38 4, ,52 3 7,38 3 7,38 32, , ,49 32,251 17,138 11, , , Preconstruction Manager ,297 4,2 3, ,2 3 7,2 4, ,8 3 7,2 3 7,2 3, , ,423 3,77 1,32 1,74 4,2 21 4, ,441 Project Manager ,118 1,14 4 7, ,9 1 1,9 1,135 3, 1 1,9 1 1,9 15,48 1,197 1,197 29,891 15,8 1,488 4, , ,5 Local Procurement Manager , , ,8 15,48 14, , , ,71 General Superintendent , ,33 4,2 4 7,7 15, , ,382 2, , , MEP Project Manager ,94 1,32 4, ,72 1 1,72 1,28 3, ,72 1 1, ,173 1, 1, 39, ,19 9,494 1, ,439 Engineering Manager / Operations Coordinator ,913,77 8, ,1 QA/QC Manager ,8 39 7, 14,27 Program Manager ,19 23,913 97,77 8, ,285 Sr. Estimator ,8 7 1,34 29,21 2,244 2, , ,928 2,244 2,244 29,21 8 1, ,414 29,419 15,33 1,3 7 1,34 7 1, ,745 Estimator ,21 14, ,235 29,21 29,419 15,33 1,3 9 13,2 (18,43) (14,744) Estimator ,83 4 5, , , , ,88 15, BIM/VDC Manager ,8 13 1,3 8 1,7 44 5,774 Scheduler , , ,5 1 1, ,8 1 1,5 1 1,5 48 7,1 1,4 1,4 47 7, , , ,59 Safety Manager. 24 2, , , ,38 8, Invoiced Amount (From current contract) , , , , , , , , , ,314 15,788 14,182 2,314 2,314 28,945 2,52 17,53 1,578 Difference 13,2 2,153 81,2 (9,73) Running Difference (1) (1) 13,2 33, ,597 14,81 (14,853) 43,471 3, , ,15 745,472 Running Total of Invoices 141,928 Running Total of Hours, ,898 1,72 (1) 348,2 1, 374,52 1,978 2, 3,35 3,173 3, ,81 17, , , ,59 97 (33,174) ,37 5 3,458 1, ,85 14,57 7,199 19,37 254,57 (211,29) 13,373 () () () (14,853) 17,54 (13,375) () (1) () () 1,33,135 4,82 72,5 4,913 4,999 1,173,72 7,39 1,243,91,5 1,413,538 7,815 1,53,99 8,528 23,24 1,5,2 8, ,873 (251,714) (1) 3, ,24 21, ,92 1,581,895 Proposed New Contract Value 1,18,3 Existing Contract Value 395,529 Amount of Supplemental 1,581,893 8,771 This proposal includes estimating, scheduling, and GMP services for Phase1 and the added Phase 2 Ballroom level which was not included in the original Contract estimate. Total SF of building to be estimated has increased from 159,5 SF to 232, SF, or roughly a 4% increase in building size. Duration of services has increased from 13 months to 18 months. Revised Hunt's Preconstruction Fee Estimate 1,581,895 Original Contract 1,18,3 DA Consulting Allowance 2, 1, Travel Allowance, 1, Total Precon Fee 1,83, ,529. 1,441,3 Page 1 of 2 Page of

City Council Report 915 I Street, 1 st Floor Sacramento, CA

City Council Report 915 I Street, 1 st Floor Sacramento, CA City Council Report 915 I Street, 1 st Floor Sacramento, CA 95814 www.cityofsacramento.org File ID: 2018-00852 June 19, 2018 Public Hearing Item 32 Title: Sacramento Convention Center Renovation and Expansion

More information

City Council Report 915 I Street, 1 st Floor Sacramento, CA

City Council Report 915 I Street, 1 st Floor Sacramento, CA City Council Report 915 I Street, 1 st Floor Sacramento, CA 95814 www.cityofsacramento.org File ID: 2018-00834 June 12, 2018 Consent Item 10 Title: Grant: Gang Violence Suppression Grant Funding Location:

More information

City Council Report 915 I Street, 1 st Floor Sacramento, CA

City Council Report 915 I Street, 1 st Floor Sacramento, CA City Council Report 915 I Street, 1 st Floor Sacramento, CA 95814 www.cityofsacramento.org File ID: 2017-01310 Published for 10-Day Review 11/17/2017 Review Item 02 Title: (Agreement/Contract for 10-Day

More information

City Council Report 915 I Street, 1 st Floor Sacramento, CA

City Council Report 915 I Street, 1 st Floor Sacramento, CA City Council Report 915 I Street, 1 st Floor Sacramento, CA 95814 www.cityofsacramento.org File ID: 2017-01692 January 9, 2018 Consent Item 13 Title: Affordable Housing and Sustainable Communities Grant

More information

Law and Legislation Committee Report 915 I Street, 1 st Floor Sacramento, CA

Law and Legislation Committee Report 915 I Street, 1 st Floor Sacramento, CA Law and Legislation Committee Report 915 I Street, 1 st Floor Sacramento, CA 95814 www.cityofsacramento.org File ID: 2017-01511 Discussion Item 07 Title: Ordinance Establishing an Equity Program for Cannabis

More information

Subject: Audit Report 16-14, Spartan Complex Renovation, San Jose State University

Subject: Audit Report 16-14, Spartan Complex Renovation, San Jose State University Larry Mandel Vice Chancellor and Chief Audit Officer Office of Audit and Advisory Services 401 Golden Shore, 4th Floor Long Beach, CA 90802-4210 562-951-4430 562-951-4955 (Fax) lmandel@calstate.edu April

More information

Personnel and Public Employees Committee Report 915 I Street, 1 st Floor, Sacramento, CA

Personnel and Public Employees Committee Report 915 I Street, 1 st Floor, Sacramento, CA Personnel and Public Employees Committee Report 915 I Street, 1 st Floor, Sacramento, CA 95814 www.cityofsacramento.org File #: 2017-00041 January 10, 2017 Discussion Item 04 Title: Conduct Interviews

More information

Subject: Audit Report 17-74, Taylor II Replacement Building, California State University, Chico

Subject: Audit Report 17-74, Taylor II Replacement Building, California State University, Chico Larry Mandel Vice Chancellor and Chief Audit Officer Office of Audit and Advisory Services 401 Golden Shore, 4th Floor Long Beach, CA 90802-4210 562-951-4430 562-951-4955 (Fax) lmandel@calstate.edu July

More information

REPORT OF THE CHIEF LEGISLATIVE

REPORT OF THE CHIEF LEGISLATIVE REPORT OF THE CHIEF LEGISLATIVE ANALYST DATE: December 4, 2013 TO: FROM: Honorable Members of the Economic Development GerryF.Miller ~~~ L. Chief Legi a ive Committee A TERNATIVE MODERNIZATION OPTIONS

More information

CSU CONSTRUCTION. The California State University Office of Audit and Advisory Services. California State Polytechnic University, Pomona

CSU CONSTRUCTION. The California State University Office of Audit and Advisory Services. California State Polytechnic University, Pomona CSU The California State University Office of Audit and Advisory Services CONSTRUCTION California State Polytechnic University, Pomona Bronco Recreation and Intramural Complex Audit Report 15-10 June 16,

More information

Loyola University Chicago ~ Archives and Special Collections

Loyola University Chicago ~ Archives and Special Collections UA1980.04-.16, 1980.18-.23 Treasurer s Office Records - Ledgers Dates: 1904-1969 Creator: Loyola University (1870-) Extent: 124 volumes Level of description: Item Processor & date: John L. Daniels, June

More information

REQUEST FOR QUALIFICATIONS FOR CONSTRUCTION MANAGER-AT-RISK

REQUEST FOR QUALIFICATIONS FOR CONSTRUCTION MANAGER-AT-RISK REQUEST FOR QUALIFICATIONS FOR CONSTRUCTION MANAGER-AT-RISK DANBURY INDEPENDENT SCHOOL DISTRICT Project: Danbury I.S.D. Elementary School Issue Date: March 2, 2018 Submission Due Date: March 20, 2018 Table

More information

PPEA Guidelines and Supporting Documents

PPEA Guidelines and Supporting Documents PPEA Guidelines and Supporting Documents APPENDIX 1: DEFINITIONS "Affected jurisdiction" means any county, city or town in which all or a portion of a qualifying project is located. "Appropriating body"

More information

Multi Use Entertainment Venue Venue Development Agreement Discussion

Multi Use Entertainment Venue Venue Development Agreement Discussion Multi Use Entertainment Venue Venue Development Agreement Discussion June 17, 2014 1 Multi Use Entertainment Venue Related Agreements Venue License Agreement First Reading 3/4, Second Reading 4/8 (covers

More information

FY 2016 Capital Development Plan. Northern Arizona University. Revised April 2016

FY 2016 Capital Development Plan. Northern Arizona University. Revised April 2016 FY 2016 Capital Development Plan Northern Arizona University Revised April 2016 Item #7 EXECUTIVE SUMMARY Page 4 of 11 Project Board Approval Status Gross Square Footage Project Cost Amount Financed Funding

More information

CSU CONSTRUCTION. The California State University Office of Audit and Advisory Services. California State University, East Bay

CSU CONSTRUCTION. The California State University Office of Audit and Advisory Services. California State University, East Bay CSU The California State University Office of Audit and Advisory Services CONSTRUCTION California State University, East Bay Warren Hall Replacement Building Audit Report 16-10 August 15, 2016 EXECUTIVE

More information

Agenda Item No. 3.3 AGENDA ITEM BRIEFING

Agenda Item No. 3.3 AGENDA ITEM BRIEFING Agenda Item No. 3.3 AGENDA ITEM BRIEFING Submitted by: Billy Hamilton, Executive Vice Chancellor and Chief Financial Officer The Texas A&M University System Subject: Approval to Amend the FY 2016-FY 2020

More information

BOROUGH OF ROSELLE PUBLIC NOTICE ANNUAL NOTICE OF CALENDAR YEAR 2018 WORKSHOP SESSIONS, PRE-AGENDA MEETINGS AND REGULAR MEETINGS

BOROUGH OF ROSELLE PUBLIC NOTICE ANNUAL NOTICE OF CALENDAR YEAR 2018 WORKSHOP SESSIONS, PRE-AGENDA MEETINGS AND REGULAR MEETINGS BOROUGH OF ROSELLE PUBLIC NOTICE ANNUAL NOTICE OF CALENDAR YEAR 2018 WORKSHOP SESSIONS, PRE-AGENDA MEETINGS AND REGULAR MEETINGS BE IT RESOLVED, by the Mayor and Borough Council of the Borough of Roselle,

More information

Friday, June 21, 13. Building better communities through the arts

Friday, June 21, 13. Building better communities through the arts Building better communities through the arts ABOUT ARTSPACE > Established in 1979 > A national leader in creative placemaking -- the leveraging of cultural assets to strengthen the social fabric of a community

More information

Transition Review of the Greater Fort Lauderdale Convention & Visitors Bureau

Transition Review of the Greater Fort Lauderdale Convention & Visitors Bureau Exhibit 1 Transition Review of the Greater Fort Lauderdale Convention & Visitors Bureau February 16, 2017 Report No. 17-2 Office of the County Auditor Kathie-Ann Ulett, CPA Interim County Auditor Table

More information

Miami Beach Approves Construction Contract for Miami Beach Convention Center Project -- Renovations to Building Begin in December

Miami Beach Approves Construction Contract for Miami Beach Convention Center Project -- Renovations to Building Begin in December City of Miami Beach, 1700 Convention Center Drive, Miami Beach, FL 33139, www.miamibeachfl.gov OFFICE OF COMMUNICATIONS, Nannette Rodriguez Tel: 305.673.7575, E-mail: nrodriguez@miamibeachfl.gov PRESS

More information

Subject: Audit Report 17-75, Extended Learning Building, California State University, Northridge

Subject: Audit Report 17-75, Extended Learning Building, California State University, Northridge Office of Audit and Advisory Services 401 Golden Shore, 4th Floor Long Beach, CA 90802-4210 Larry Mandel Vice Chancellor and Chief Audit Officer 562-951-4430 562-951-4955 (Fax) lmandel@calstate.edu October

More information

City of Sacramento City Council 915 I Street, Sacramento, CA,

City of Sacramento City Council 915 I Street, Sacramento, CA, City of Sacramento City Council 915 I Street, Sacramento, CA, 95814 www.cityofsacramento.org 14 Meeting Date: 11/1/2011 Report Type: Staff/Discussion Title: Winter Shelter Overflow Funding Report ID: 2011-00932

More information

FEMA Hazard Mitigation Grant Application for Seismic Retrofit of Live Oak Community Center

FEMA Hazard Mitigation Grant Application for Seismic Retrofit of Live Oak Community Center Page 1 of 7 14 Office of the City Manager CONSENT CALENDAR October 17, 2017 To: From: Honorable Mayor and Members of the City Council Dee Williams-Ridley, City Manager Submitted by: Scott Ferris, Director,

More information

Mandatory Site Visit: Thursday, July 13, :00 PM (Pierson Library, Shelburne, VT)

Mandatory Site Visit: Thursday, July 13, :00 PM (Pierson Library, Shelburne, VT) Request for Proposal for Construction Management (CM) Services for the Shelburne Community Center and Public Library Shelburne, Vermont. Request for Proposal Issued: Friday, Mandatory Site Visit: Thursday,

More information

NATIONAL OCEANIC AND ATMOSPHERIC ADMINISTRATION NOAA ADMINISTRATIVE ORDER SERIES TABLE OF CONTENTS. as of December 8, 2008

NATIONAL OCEANIC AND ATMOSPHERIC ADMINISTRATION NOAA ADMINISTRATIVE ORDER SERIES TABLE OF CONTENTS. as of December 8, 2008 NATIONAL OCEANIC AND ATMOSPHERIC ADMINISTRATION NOAA ADMINISTRATIVE ORDER SERIES TABLE OF CONTENTS as of December 8, 2008 Attached is a revision to the Table of Contents for the NOAA Administrative Order

More information

Compliance Division Staff Report

Compliance Division Staff Report Compliance Division Staff Report Polygraph Advisory Board Meeting Tuesday, September 26, 2017 Public Outreach Compliance Division routinely attends annual industry meetings held by TALEPI (Texas Association

More information

City of Batavia Downtown Improvement Grant

City of Batavia Downtown Improvement Grant City of Batavia Downtown Improvement Grant INTRODUCTION The Downtown Improvement Grant Program is designed to enhance the overall economic viability and appearance of downtown Batavia by assisting in the

More information

Request for Proposals Construction Services Workplace Excellence Project

Request for Proposals Construction Services Workplace Excellence Project Request for Proposals Construction Services Workplace Excellence Project December 5, 2014 INTRODUCTION Atlanta BeltLine, Inc. (ABI) invites you to submit a response to this Request for Proposals (RFP)

More information

JAIL UPDATE MEETING June 27, 2018

JAIL UPDATE MEETING June 27, 2018 JAIL UPDATE MEETING June 27, 2018 1. Update to questions raised at the May 31, 2018 Meeting 2. Anticipated Project Schedule 3. Project Funding Options 4. Project Schedule Impact 5. Single Story Jail Design

More information

Connect NC Bond Information. The Connect NC Bond Act was passed by the General Assembly in 2015 and approved by the Voters in March 2016

Connect NC Bond Information. The Connect NC Bond Act was passed by the General Assembly in 2015 and approved by the Voters in March 2016 Connect NC Update Joint Legislative Oversite Committee on Capital Improvements Prepared by: The Office of State Budget and Management October 11, 2017 Mark Bondo Monica Scott Andrew Shaw Jim Lora Connect

More information

REQUEST FOR QUALIFICATIONS CONSULTING EXECUTIVE LANDSCAPE ARCHITECT HOPKINS LANE BIKE & PEDESTRIAN IMPROVEMENT UNIVERSITY OF CALIFORNIA, SAN DIEGO

REQUEST FOR QUALIFICATIONS CONSULTING EXECUTIVE LANDSCAPE ARCHITECT HOPKINS LANE BIKE & PEDESTRIAN IMPROVEMENT UNIVERSITY OF CALIFORNIA, SAN DIEGO REQUEST FOR QUALIFICATIONS CONSULTING EXECUTIVE LANDSCAPE ARCHITECT FOR HOPKINS LANE BIKE & PEDESTRIAN IMPROVEMENT FD&C Project No. 4952 Proposals due THURSDAY, JUNE 4, 2015 Issue Date May 19, 2015 I.

More information

FY 2018 Capital Development Plan Northern Arizona University

FY 2018 Capital Development Plan Northern Arizona University FY 2018 Capital Development Plan Northern Arizona University EXECUTIVE SUMMARY Page 1 of 11 Item Name: FY 2018 Capital Development Plan (NAU) Action Item Committee Recommendation to Full Board First Read

More information

Status of Convention Center Hotel Project. Briefing to the Economic Development Committee August 15, 2008

Status of Convention Center Hotel Project. Briefing to the Economic Development Committee August 15, 2008 Status of Convention Center Hotel Project Briefing to the Economic Development Committee August 15, 2008 Purpose 2 Bring Committee up to date on negotiations with Matthews Southwest (MSW) Update Good Faith

More information

City of Sacramento City Council 915 I Street, Sacramento, CA,

City of Sacramento City Council 915 I Street, Sacramento, CA, City of Sacramento City Council 915 I Street, Sacramento, CA, 95814 www.cityofsacramento.org Meeting Date: 2/22/2011 Report Type: Public Hearing Title: Pell Circle Billboard Relocation (P10-065) Report

More information

REQUEST FOR QUALIFICATIONS (RFQ) FOR ARCHITECTURAL SERVICES

REQUEST FOR QUALIFICATIONS (RFQ) FOR ARCHITECTURAL SERVICES REQUEST FOR QUALIFICATIONS (RFQ) FOR ARCHITECTURAL SERVICES The City of Waller, TX is requesting Statements of Qualifications from firms and individuals desiring to perform various space needs assessment,

More information

Request for Statements of Qualifications Construction Management and General Contractor at Risk San Mateo County Replacement Correctional Facility

Request for Statements of Qualifications Construction Management and General Contractor at Risk San Mateo County Replacement Correctional Facility Request for Statements of Qualifications Construction Management and General Contractor at Risk San Mateo County Replacement Correctional Facility San Mateo County Sheriff s Office Issued: December 21,

More information

CONSTRUCTION CALIFORNIA POLYTECHNIC STATE UNIVERSITY, SAN LUIS OBISPO RECREATION CENTER EXPANSION. Audit Report April 30, 2013

CONSTRUCTION CALIFORNIA POLYTECHNIC STATE UNIVERSITY, SAN LUIS OBISPO RECREATION CENTER EXPANSION. Audit Report April 30, 2013 CONSTRUCTION CALIFORNIA POLYTECHNIC STATE UNIVERSITY, SAN LUIS OBISPO RECREATION CENTER EXPANSION Audit Report 13-09 April 30, 2013 Henry Mendoza, Chair Lupe C. Garcia, Vice Chair Rebecca D. Eisen Steven

More information

Smithsonian Institution

Smithsonian Institution Smithsonian Institution Recovery Act, 2009 Agency-wide and Program-specific Plan Updated May 2010 Smithsonian Institution American Recovery and Reinvestment Act of 2009 Agency-wide and Program-specific

More information

CITY OF SACRAMENTO COMMUNITY DEVELOPMENT CALIFORNIA 300 Richards Blvd. DEPARTMENT

CITY OF SACRAMENTO COMMUNITY DEVELOPMENT CALIFORNIA 300 Richards Blvd. DEPARTMENT CITY OF SACRAMENTO COMMUNITY DEVELOPMENT CALIFORNIA 300 Richards Blvd. DEPARTMENT 3 rd Floor Sacramento, CA 95811 DATE: April 12, 2013 TO: FROM: RE: Interested Persons Tom Buford, Senior Planner Community

More information

Calendar of Key Deadlines for Apportionments July 18, 2016

Calendar of Key Deadlines for Apportionments July 18, 2016 Mary Jane Burke Marin County Superintendent of Schools Business Services Department Business Bulletin 17 04 Calendar of Key Deadlines for 2016 2017 Apportionments July 18, 2016 Please find the Calendars

More information

District Office Building Seismic Retrofit At Contra Costa Community College District 500 Court St. Martinez, CA March 21, 2016

District Office Building Seismic Retrofit At Contra Costa Community College District 500 Court St. Martinez, CA March 21, 2016 REQUEST FOR QUALIFICATIONS (RFQ) ARCHITECT/ENGINEER (A/E) PROFESSIONAL SERVICES For the At Contra Costa Community College District 500 Court St. Martinez, CA March 21, 2016 PART 1 GENERAL INTRODUCTION

More information

Downtown Retail Interior Improvement Award Program Application Packet

Downtown Retail Interior Improvement Award Program Application Packet VILLAGE OF GLEN ELLYN Downtown Retail Interior Improvement Award Program Application Packet Village Manager s Office 535 Duane Street Glen Ellyn, IL 60137 Telephone 630.547.5345 Fax 630.547.8849 1 VILLAGE

More information

City of Racine, Wisconsin. Frequently Asked Questions about Financing for the Event Center and Hotel Project

City of Racine, Wisconsin. Frequently Asked Questions about Financing for the Event Center and Hotel Project Frequently Asked Questions about Financing for the Event Center and Hotel Project 1. What does the event center project cost? The Master Project Budget has a range from $51.4 million to $61.2 million.

More information

DoD Mentor Protégé Program. Shannon C. Jackson, Program Manager DoD Office of Small Business Programs

DoD Mentor Protégé Program. Shannon C. Jackson, Program Manager DoD Office of Small Business Programs DoD Mentor Protégé Program Shannon C. Jackson, Program Manager DoD Office of Small Business Programs 1 People underestimate their capacity for change. There is never a right time to do a difficult thing.

More information

Galesburg Public Library, Galesburg, IL

Galesburg Public Library, Galesburg, IL Galesburg Public Library, Galesburg, IL Request for Qualifications ( RFQ ) Architectural, Engineering, Construction Management and Related Services I. OVERVIEW The Galesburg Public Library is seeking architectural,

More information

Minnehaha County, South Dakota 415 N Dakota Avenue Sioux Falls, South Dakota 57104

Minnehaha County, South Dakota 415 N Dakota Avenue Sioux Falls, South Dakota 57104 Minnehaha County, South Dakota 415 N Dakota Avenue Sioux Falls, South Dakota 57104 NOTICE OF REQUEST FOR PROPOSALS: Jail Expansion Request for Proposals (RFP) for Architect/Engineer Services Minnehaha

More information

Subject: Audit Report 16-13, Student Housing Phase II, California State University, Northridge

Subject: Audit Report 16-13, Student Housing Phase II, California State University, Northridge Larry Mandel Vice Chancellor and Chief Audit Officer Office of Audit and Advisory Services 401 Golden Shore, 4th Floor Long Beach, CA 90802-4210 562-951-4430 562-951-4955 (Fax) lmandel@calstate.edu March

More information

New St. Petersburg Police Headquarters. City Council Committee of The Whole Schematic Design Update July 21, 2016

New St. Petersburg Police Headquarters. City Council Committee of The Whole Schematic Design Update July 21, 2016 New St. Petersburg Police Headquarters City Council Committee of The Whole Schematic Design Update July 21, 2016 1 Harvard Jolly Architecture Contract Requirements August 20, 2015: Approval of amended

More information

REQUEST FOR QUALIFICATIONS. Architectural/Engineering Design Services

REQUEST FOR QUALIFICATIONS. Architectural/Engineering Design Services REQUEST FOR QUALIFICATIONS Architectural/Engineering Design Services Logistics DISTRICT CONTACTS FOR QUESTIONS Jeff Collum Superintendent Phone: 903-668-5990 Email: jcollum@hisd.com REQUEST FOR STATEMENT

More information

REQUEST FOR QUALIFICATIONS: RFQ PROGRAM/PROJECT MANAGEMENT SERVICES TO SUPPORT MUNICIPAL FACILITIES & CAPITAL IMPROVEMENTS PROJECTS

REQUEST FOR QUALIFICATIONS: RFQ PROGRAM/PROJECT MANAGEMENT SERVICES TO SUPPORT MUNICIPAL FACILITIES & CAPITAL IMPROVEMENTS PROJECTS REQUEST FOR QUALIFICATIONS: RFQ 2018-100-1 PROGRAM/PROJECT MANAGEMENT SERVICES TO SUPPORT MUNICIPAL FACILITIES & CAPITAL IMPROVEMENTS PROJECTS The City of Cedar Hill, Texas is soliciting statements of

More information

Morgan Hill Unified School District

Morgan Hill Unified School District Facilities Department 15600 Concord Circle, Morgan Hill, CA 95037 Phone: (408) 201-6087 Fax (408) 776-0175 REQUEST FOR ARCHITECTURAL SERVICES PROPOSALS for a New Britton MS Campus and Site Master Plan

More information

Addendum No. 2 April 15, 2015 Architectural Design Services Requirements Contracts Request for Qualifications Project No.

Addendum No. 2 April 15, 2015 Architectural Design Services Requirements Contracts Request for Qualifications Project No. Facilities Planning, Construction, and Management Office of Financial Management Procurement Services 555 West 57 th Street 16 th Floor New York, NY 10019 Tel: 646-664-2700 Addendum 2 April 15, 2015 Architectural

More information

REQUEST FOR PROPOSAL (RFP) DESIGN BUILD SERVICES. Erie Library Expansion Project

REQUEST FOR PROPOSAL (RFP) DESIGN BUILD SERVICES. Erie Library Expansion Project 7525 South Jasmine Court Centennial, CO 80112 303-378-4130 www.wemberinc.com/blog facebook.com/wemberinc wemberinc.com REQUEST FOR PROPOSAL (RFP) DESIGN BUILD SERVICES Erie Library Expansion Project September

More information

Water Conservation Industrial,Commercial,Institutional (ICI) Audit and Rebate Program. City of Dallas Water Utilities February 13, 2012

Water Conservation Industrial,Commercial,Institutional (ICI) Audit and Rebate Program. City of Dallas Water Utilities February 13, 2012 Water Conservation Industrial,Commercial,Institutional (ICI) Audit and Rebate Program City of Dallas Water Utilities February 13, 2012 Briefing Purpose To provide background on implementation of additional

More information

YPSILANTI DDA BUILDING REHABILITATION AND FAÇADE PROGRAM

YPSILANTI DDA BUILDING REHABILITATION AND FAÇADE PROGRAM YPSILANTI DDA BUILDING REHABILITATION AND FAÇADE PROGRAM Application Checklist Please provide information for the following items. Refer to Application Packet for description of requested materials. 1.

More information

Agenda (Items may be taken out of order)

Agenda (Items may be taken out of order) I. ROLL CALL LOS ANGELES COMMUNITY COLLEGE DISTRICT BOARD OF TRUSTEES FACILITIES MASTER PLANNING & OVERSIGHT COMMITTEE Educational Services Center Board Room 770 Wilshire Boulevard Los Angeles, CA 90017

More information

REQUEST FOR QUALIFICATIONS

REQUEST FOR QUALIFICATIONS REQUEST FOR QUALIFICATIONS Architectural and Engineering Services Intermodal Transportation Center Complex Greensboro, North Carolina Invitation Date: September 19, 2014 1.0 INTRODUCTION The Piedmont Authority

More information

CITY OF LANCASTER REVITALIZATION AND IMPROVEMENT ZONE AUTHORITY

CITY OF LANCASTER REVITALIZATION AND IMPROVEMENT ZONE AUTHORITY CITY OF LANCASTER REVITALIZATION AND IMPROVEMENT ZONE AUTHORITY Guidelines for Obtaining Financing for Projects in the City of Lancaster s City Revitalization and Improvement Zone Purposes of These Guidelines

More information

REQUEST FOR PROPOSAL CONSTRUCTION MANAGEMENT SERVICES DELTONA MIDDLE 250 ENTERPRISE ROAD DELTONA, FLORIDA MASTER PLAN PROJECT NO.

REQUEST FOR PROPOSAL CONSTRUCTION MANAGEMENT SERVICES DELTONA MIDDLE 250 ENTERPRISE ROAD DELTONA, FLORIDA MASTER PLAN PROJECT NO. REQUEST FOR PROPOSAL CONSTRUCTION MANAGEMENT SERVICES FOR DELTONA MIDDLE 250 ENTERPRISE ROAD DELTONA, FLORIDA 32725 MASTER PLAN PROJECT NO. 184620 School Board of Volusia County Florida Facilities Services

More information

CITY OF BELL REQUEST FOR PROPOSALS FOR ARCHITECTURAL SERVICES FOR TREDER PARK RESTROOM AND STORAGE FACILITY

CITY OF BELL REQUEST FOR PROPOSALS FOR ARCHITECTURAL SERVICES FOR TREDER PARK RESTROOM AND STORAGE FACILITY CITY OF BELL 6330 PINE AVENUE BELL, CA 90201 PH: (323) 588-6211 fx: (323) 771-9473 I. INTRODUCTION CITY OF BELL REQUEST FOR PROPOSALS FOR ARCHITECTURAL SERVICES FOR TREDER PARK RESTROOM AND STORAGE FACILITY

More information

Corporate Services Employment Report: January Employment by Staff Group. Jan 2018 (Jan 2017 figure: 1,462) Overall 1,

Corporate Services Employment Report: January Employment by Staff Group. Jan 2018 (Jan 2017 figure: 1,462) Overall 1, Corporate Services Employment Report: January Employment by Staff Group Jan (Jan 20 figure: 1,462) Jan % Overall 1,520 +58 +4.0% 8 Management (VIII+) 403 +52 4.8% Clerical & Supervisory (III to VII) 907

More information

Request for Proposals (RFP) An Alternative Fuels Assessment & Feasibility Study

Request for Proposals (RFP) An Alternative Fuels Assessment & Feasibility Study Request for Proposals (RFP) An Alternative Fuels Assessment & Feasibility Study VTA Project # 2016-01 From: Subject: Angela E. Grant, Administrator Project VTA #2016-01 Request for Proposals An Alternative

More information

DISCUSSION ITEM EXECUTIVE SUMMARY

DISCUSSION ITEM EXECUTIVE SUMMARY F4 Office of the President TO THE MEMBERS OF THE COMMITTEE ON FINANCE: For the Meeting of DISCUSSION ITEM UPDATE ON THE 2020 PROJECT, MERCED CAMPUS EXECUTIVE SUMMARY Twenty years ago, the Regents of the

More information

Lexington Center Corporation Request for Proposal for Convention Center Naming Rights Request for Proposals

Lexington Center Corporation Request for Proposal for Convention Center Naming Rights Request for Proposals Request for Proposal for Convention Center Naming Rights Request for Proposals Title: Naming Rights for the Lexington Center Corporation, New Convention Center, Lexington Kentucky Issue Date: December

More information

Request for Proposals (RFP) For Restaurant Consulting Services 1657 Ocean Avenue

Request for Proposals (RFP) For Restaurant Consulting Services 1657 Ocean Avenue Request for Proposals (RFP) For Restaurant Consulting Services 1657 Ocean Avenue The City of Santa Monica (City) Housing and Economic Development Department is soliciting this Request for Proposals from

More information

REQUEST FOR QUALIFICATIONS EXECUTIVE ARCHITECT CANYON VISTA DINING RENOVATION UNIVERSITY OF CALIFORNIA, SAN DIEGO. CPM Project No.

REQUEST FOR QUALIFICATIONS EXECUTIVE ARCHITECT CANYON VISTA DINING RENOVATION UNIVERSITY OF CALIFORNIA, SAN DIEGO. CPM Project No. EXECUTIVE ARCHITECT FOR THE CANYON VISTA DINING RENOVATION UNIVERSITY OF CALIFORNIA, SAN DIEGO CPM Project No. 5289 Proposals due JUNE 11, 2018 Issue date May 24, 2018 I. INTRODUCTION The University of

More information

Purpose of Meeting. Informational purposes Overview of Master Plan Overview of Procurement Process Feedback from Developers

Purpose of Meeting. Informational purposes Overview of Master Plan Overview of Procurement Process Feedback from Developers Meeting Agenda Introductions and Opening Statement Introductory Comments Project Overview Procurement Solicitations and Process Small and Local Business Participation Timeline of Procurement and Project

More information

Request for Qualifications Construction Manager at Risk Contract

Request for Qualifications Construction Manager at Risk Contract Request for Qualifications Construction Manager at Risk Contract Project Owner: The MetroHealth System Project Name: Hybrid Operating Room (OR) CM 15.17 and OR Renovation Upgrade CM 16.06 Project Location:

More information

SAN DIEGO POLICE DEPARTMENT PROCEDURE

SAN DIEGO POLICE DEPARTMENT PROCEDURE SAN DIEGO POLICE DEPARTMENT PROCEDURE DATE: March 25, 2016 NUMBER: SUBJECT: RELATED POLICY: ORIGINATING DIVISION: 1.40 ADMINISTRATION GRANT PROCEDURES N/A ADMINISTRATIVE SERVICES PROCEDURE: PROCEDURAL

More information

GUIDELINES Arts Grant Program Year 2017

GUIDELINES Arts Grant Program Year 2017 City of Corpus Christi Parks and Recreation Department Arts & Cultural Commission GUIDELINES Arts Grant Program Year 2017 Application Deadline: 5:00pm October 14, 2016 Arts Grant Program Parks and Recreation

More information

PAUL R. JONES STUDENT CENTER STATEMENT OF NEED and DETAILED FUNDRAISING PLAN, April 2017

PAUL R. JONES STUDENT CENTER STATEMENT OF NEED and DETAILED FUNDRAISING PLAN, April 2017 PAUL R. JONES STUDENT CENTER STATEMENT OF NEED and DETAILED FUNDRAISING PLAN, April 2017 BROUGHT TO YOU BY: NATIONAL PINE FORGE ACADEMY ALUMNI ASSOCIATION A Student Center for Pine Forge Academy Students

More information

Bowen Island Municipality. Bowen Island Community Centre. Project Briefing Note

Bowen Island Municipality. Bowen Island Community Centre. Project Briefing Note Bowen Island Municipality Bowen Island Community Centre Project Briefing Note Presented: October 11, 2016 Sam Collins 1 of 8 1 Recommendations 1.1 That Council receive this project Briefing Note for information.

More information

Retail & Restaurant Incentive Program GUIDELINES

Retail & Restaurant Incentive Program GUIDELINES Amended April 19, 2016 Retail & Restaurant Incentive Program GUIDELINES The Program The purpose of this program is to serve as a catalyst for securing new retail, restaurant and service concepts to fill

More information

Submitted by: Paul Buddenhagen, Director, Health, Housing & Community Services

Submitted by: Paul Buddenhagen, Director, Health, Housing & Community Services Page 1 of 8 Office of the City Manager September 27, 2016 To: From: Honorable Mayor and Members of the City Council Dee Williams-Ridley, City Manager Submitted by: Paul Buddenhagen, Director, Health, Housing

More information

GOVERNMENT OF INDONESIA SCHOLARSHIP PROGRAM FOR STRENGTHENING REFORMING INSTITUTIONS (SPIRIT) PROCUREMENT PLAN

GOVERNMENT OF INDONESIA SCHOLARSHIP PROGRAM FOR STRENGTHENING REFORMING INSTITUTIONS (SPIRIT) PROCUREMENT PLAN I. General GOVERNMENT OF INDONESIA SCHOLARSHIP PROGRAM FOR STRENGTHENING REFORMING INSTITUTIONS (SPIRIT) PROCUREMENT PLAN 1. Project information: Country- Indonesia Borrower- Government of Indonesia Project

More information

681 Florida Housing Associates, L.P.: 681 Florida St SAN FRANCISCO, CA REQUEST FOR QUALIFICATIONS/PROPOSALS ( RFQ/P ) FOR GENERAL CONTRACTOR SERVICES

681 Florida Housing Associates, L.P.: 681 Florida St SAN FRANCISCO, CA REQUEST FOR QUALIFICATIONS/PROPOSALS ( RFQ/P ) FOR GENERAL CONTRACTOR SERVICES 681 Florida Housing Associates, L.P.: 681 Florida St SAN FRANCISCO, CA REQUEST FOR QUALIFICATIONS/PROPOSALS ( RFQ/P ) FOR GENERAL CONTRACTOR SERVICES Issued by: Tenderloin Neighborhood Development Corporation

More information

Office of Business and Financial Services Procurement and Contracts Division Section SUBJECT: PROCUREMENT OF CONSTRUCTION SERVICES

Office of Business and Financial Services Procurement and Contracts Division Section SUBJECT: PROCUREMENT OF CONSTRUCTION SERVICES 2510.8 SUBJECT: PROCUREMENT OF CONSTRUCTION SERVICES :1 OBJECTIVE: To establish a uniform policy and procedure for the acquisition of construction services for the City of Orlando (City), including, but

More information

CITY OF WEST CHICAGO DOWNTOWN RETAIL & RESTAURANT BUSINESS GRANT PROGRAM

CITY OF WEST CHICAGO DOWNTOWN RETAIL & RESTAURANT BUSINESS GRANT PROGRAM CITY OF WEST CHICAGO DOWNTOWN RETAIL & RESTAURANT BUSINESS GRANT PROGRAM DESCRIPTION OF PROGRAM The Retail & Restaurant Business Grant Program ( Program ) is sponsored by the City of West Chicago for the

More information

City of Poughkeepsie Main Street Program 2010

City of Poughkeepsie Main Street Program 2010 Public Information Session September 14, 2011 What is New York Main Street? A program of NYS Homes and Community Renewal $15 million dollars in grants awarded to assist 38 communities in their downtown

More information

Page 1 of 10 Chicago Infrastructure Trust Joint Public Safety Training Academy - RFQ Clarifications - November 9, 2017

Page 1 of 10 Chicago Infrastructure Trust Joint Public Safety Training Academy - RFQ Clarifications - November 9, 2017 ANSWERS TO PRE-SUBMITTAL CONFERENCE QUESTIONS AND REQUESTS FOR CLARIFICATIONS 1 Project Budget and Project Design s 1 1.3 The City and the CIT have established a Project It is intended that all necessary

More information

Request for Qualifications (RFQ) Indefinite Delivery Indefinite Quantity (IDIQ) Athletic Facility Architectural Services

Request for Qualifications (RFQ) Indefinite Delivery Indefinite Quantity (IDIQ) Athletic Facility Architectural Services The Board of Regents of the University System of Georgia & Georgia Institute of Technology Atlanta, Georgia Request for Qualifications (RFQ) For Indefinite Delivery Indefinite Quantity (IDIQ) Athletic

More information

Benchmark. Middle East hotel benchmark survey report

Benchmark. Middle East hotel benchmark survey report Benchmark Middle East hotel benchmark survey report December 214 The hotel benchmark report provides a monthly performance overview of leading hotels in the Middle East. The hotel set includes international

More information

CONSTRUCTION COMMITTEE MEETING AGENDA

CONSTRUCTION COMMITTEE MEETING AGENDA CONSTRUCTION COMMITTEE MEETING AGENDA DATE: Tuesday, August 28, 2018 TIME: 8:30 a.m. PLACE: GOAA ANNEX BUILDING, 1ST FLOOR - CONFERENCE ROOMS (APOLLO/GEMINI/TAURUS), 5855 CARGO ROAD, ORLANDO INTERNATIONAL

More information

SPORTS EVENTS & SPONSORSHIP POLICIES AND PROCEDURES

SPORTS EVENTS & SPONSORSHIP POLICIES AND PROCEDURES TOURIST DEVELOPMENT COUNCIL OPERATIONS AND PROCEDURES MANUAL & SPECIAL EVENTS GRANT POLICIES AND PROCEDURES SPORTS EVENTS & SPONSORSHIP POLICIES AND PROCEDURES May 2015 Table of Contents SECTION ONE: OPERATIONAL

More information

ADDENDUM #2 FOR CONSTRUCTION MANAGEMENT CONSULTANT (CMC) THIS ADDENDUM #2 IS ISSUED: AUGUST 15, 2017

ADDENDUM #2 FOR CONSTRUCTION MANAGEMENT CONSULTANT (CMC) THIS ADDENDUM #2 IS ISSUED: AUGUST 15, 2017 ADDENDUM #2 FOR 17-054 CONSTRUCTION MANAGEMENT CONSULTANT (CMC) THIS ADDENDUM #2 IS ISSUED: AUGUST 15, 2017 QUESTIONS AND ANSWERS The following questions were posed by firms that indicated an interest

More information

ARCHITECTURAL/ENGINEERING SERVICES

ARCHITECTURAL/ENGINEERING SERVICES Sheriff Department Bruce Haney, Sheriff Department of Transportation Richard Tippett, Director County of Trinity REQUEST FOR STATEMENT OF QUALIFICATIONS TO PROVIDE ARCHITECTURAL/ENGINEERING SERVICES FOR

More information

JANUARY 2018 (21 work days) FEBRUARY 2018 (19 work days)

JANUARY 2018 (21 work days) FEBRUARY 2018 (19 work days) AND CORRESPONDING DATES FOR JANUARY AND FEBRUARY 2018 JANUARY 2018 ( work days) Deadline* 12-27 12-28 12-29 1-2 1-3 1-4 1-5 1-8 1-9 1-10 Benefit Hold ** 12-28 12-29 1-2 1-3 1-4 1-5 1-8 1-9 1-10 1-11 Mailing

More information

COLORADO DEPARTMENT OF EDUCATION DIVISION OF PUBLIC SCHOOL CAPITAL CONSTRUCTION ASSISTANCE 1 CCR BUILDING EXCELLENT SCHOOLS TODAY GRANT PROGRAM

COLORADO DEPARTMENT OF EDUCATION DIVISION OF PUBLIC SCHOOL CAPITAL CONSTRUCTION ASSISTANCE 1 CCR BUILDING EXCELLENT SCHOOLS TODAY GRANT PROGRAM COLORADO DEPARTMENT OF EDUCATION DIVISION OF PUBLIC SCHOOL CAPITAL CONSTRUCTION ASSISTANCE 1 CCR 303-3 BUILDING EXCELLENT SCHOOLS TODAY GRANT PROGRAM Authority 22-43.7-106(2)(i)(I) C.R.S., the Public School

More information

O HARE INTERNATIONAL AIRPORT MULTIMODAL FACILITY CONCESSIONS PRE-PROPOSAL MEETING DECEMBER 18, 2017

O HARE INTERNATIONAL AIRPORT MULTIMODAL FACILITY CONCESSIONS PRE-PROPOSAL MEETING DECEMBER 18, 2017 O HARE INTERNATIONAL AIRPORT MULTIMODAL FACILITY CONCESSIONS PRE-PROPOSAL MEETING DECEMBER 18, 2017 AGENDA I. Welcome and Introduction Kathleen Verret, Senior Director-Unison Retail Management II. III.

More information

Conducting a Comprehensive Feasibility Study

Conducting a Comprehensive Feasibility Study 2004 Athletic Business Conference Conducting a Comprehensive Feasibility Study Presented By: Brad Noyes Presentation Outline Introductions The Planning Process Seeing the Big Picture Evaluating your Starting

More information

Consultant for the Development of Specifications Management and Operation of Dallas Fair Park Request for Proposals BBZ1702

Consultant for the Development of Specifications Management and Operation of Dallas Fair Park Request for Proposals BBZ1702 Consultant for the Development of Specifications Management and Operation of Dallas Fair Park Request for Proposals BBZ1702 INTRODUCTION The City of Dallas (City) is soliciting proposals from vendors with

More information

City of Stockton. Legislation Text APPROVE NEW STOREFRONT BEAUTIFICATION MICRO GRANT PROGRAM FOR EXTERIOR IMPROVEMENTS TO LOCAL COMMERCIAL BUSINESSES

City of Stockton. Legislation Text APPROVE NEW STOREFRONT BEAUTIFICATION MICRO GRANT PROGRAM FOR EXTERIOR IMPROVEMENTS TO LOCAL COMMERCIAL BUSINESSES City of Stockton Legislation Text File #: 18-4835, Version: 1 APPROVE NEW STOREFRONT BEAUTIFICATION MICRO GRANT PROGRAM FOR EXTERIOR IMPROVEMENTS TO LOCAL COMMERCIAL BUSINESSES RECOMMENDATION It is recommended

More information

Downtown Interior Improvement Grant Program Application Packet

Downtown Interior Improvement Grant Program Application Packet VILLAGE OF GLEN ELLYN Downtown Interior Improvement Grant Program Application Packet Village Manager s Office 535 Duane Street Glen Ellyn, IL 60137 Telephone 630.547.5345 Fax 630.469.8849 X:\Plandev\PLANNING\FORMS\Downtown

More information

REQUEST FOR PROPOSAL (RFP) Police Department Building Construction Manager at Risk, Guaranteed Maximum Price August 30, 2016

REQUEST FOR PROPOSAL (RFP) Police Department Building Construction Manager at Risk, Guaranteed Maximum Price August 30, 2016 REQUEST FOR PROPOSAL (RFP) Police Department Building Construction Manager at Risk, Guaranteed Maximum Price August 30, 2016 The City of Muskego is seeking proposals for Construction Manager (CM) Services

More information

Lee County Board Of County Commissioners Ageuda riolrr Sulumary ~turs~~eet~'u

Lee County Board Of County Commissioners Ageuda riolrr Sulumary ~turs~~eet~'u 1. REQUESTED MOTION: Lee County Board Of County Commissioners Ageuda riolrr Sulumary ~turs~~eet~'u. 20041190 ACTION REQUESTED: Approve and authorize Chairman to execute interlocal agreements between Lee

More information

REQUEST FOR QUALIFICATION FOR PREPARATION OF FACILITIES MASTER PLAN AND FUTURE ARCHITECTURAL SERVICES

REQUEST FOR QUALIFICATION FOR PREPARATION OF FACILITIES MASTER PLAN AND FUTURE ARCHITECTURAL SERVICES REQUEST FOR QUALIFICATION FOR PREPARATION OF FACILITIES MASTER PLAN AND FUTURE ARCHITECTURAL SERVICES September 22,2016 Mammoth Unified School District 461 Sierra Park Road/PO Box 3509, Mammoth Lakes,

More information

ADC Annex Conversion 11/17/15

ADC Annex Conversion 11/17/15 1 ADC Annex Conversion 11/17/15 Background 2 October 6, 2015: Commissioners Court requested Facilities Management work with the Sheriff s Office to validate required renovations needed to re-allocate available

More information

REQUEST FOR QUALIFICATIONS PROJECT AND CONSTRUCTION MANAGEMENT CONSULTANT

REQUEST FOR QUALIFICATIONS PROJECT AND CONSTRUCTION MANAGEMENT CONSULTANT REQUEST FOR QUALIFICATIONS PROJECT AND CONSTRUCTION MANAGEMENT CONSULTANT DUE: May 4, 2018 4:00 P.M. Walla Walla Public Schools 364 S. Park Street Walla Walla, WA 99362 District Representative/Contact:

More information

REQUEST FOR QUALIFICATIONS AS-NEEDED CONSULTING EXECUTIVE ARCHITECT

REQUEST FOR QUALIFICATIONS AS-NEEDED CONSULTING EXECUTIVE ARCHITECT REQUEST FOR QUALIFICATIONS AS-NEEDED CONSULTING EXECUTIVE ARCHITECT For the TORREY PINES CENTER SOUTH (TPCS) FACILITY UNIVERSITY OF CALIFORNIA, SAN DIEGO OFFICES OF FACILITIES DESIGN & CONSTRUCTION Issue

More information