I-225 Light Rail Design/Build/Finance Staff Recommendation. RTD FasTracks Monitoring Committee July 3, 2012

Size: px
Start display at page:

Download "I-225 Light Rail Design/Build/Finance Staff Recommendation. RTD FasTracks Monitoring Committee July 3, 2012"

Transcription

1 I-225 Light Rail Design/Build/Finance Staff Recommendation RTD FasTracks Monitoring Committee July 3, 2012

2 FasTracks Guiding Principles Staff relied heavily on our Guiding Principles to develop our recommended action for I-225 Ensure every step contributes to the full vision Focus money available to the greatest good Spend public money wisely Maximize i outside funding before going to taxpayers Deliver key investments in all corridors Build As Much As We Can As Fast As We Can Until It Is All Done! 2

3 I-225 Light Rail Corridor 10 ½ mile light rail extension 8 stations Starts at existing Nine Mile Station Serves the Aurora City Center Serves the Anschutz / Fitzsimons Campus Provides additional mobility to military veterans and transit dependents Provides regional connectivity to East Commuter Rail Line at the Peoria Station ti 3

4 Timeline March 8 RTD received an unsolicited proposal from Kiewit Infrastructure Company for the I-225 Light Rail Project April 17 RTD Board authorized staff to proceed with a competitive bidding process May 8 RTD advertised d a Request for Proposals (RFP) to provide a Design-Build approach to construct the I-225 Rail Line beyond the Iliff Station with a financial solution that is within RTD s financial i capacity June 14 RTD received competitive bids from two teams: 1. Kiewit Infrastructure 2. Balfour Beatty/Ames JV June 27 Staff provided update to the Board during Executive Session 4

5 RTD Evaluation Team Board of Directors Patterned After Eagle Project Evaluation Team General Manager Evaluation Committee Technical Subcommittee Stakeholder Group Financial Subcommittee Technical Approach Working Group Systems Utilities Drainage Structures General Civil and Track Stations Traffic Control Traffic Signals ROW Management Approach Working Group Project Management Plan Quality Management Plan Safety Management Plan Technical Management Approach Schedule SBE Plan Experience of Team Experience of Key Staff 5

6 Evaluation Criteria and Weighting g Financial Solutions and Design/Build Cost Proposal (60 Points Total) - Cost Effectiveness - Strength of Financing Structure Technical Proposal Criteria (40 Points Total) - Technical Approach - Right of Way Team and Approach - Quality of Team and Approach - SBE/WIN Approach NOTE: These criteria were included in the Instructions to Proposers document, as part of the Request for Proposals 6

7 Kiewit Team 7

8 Kiewit Proposal Highlights Offers construction of entire I-225 corridor to Peoria Station by November 2015 Capital cost bid within RTD s internal engineering estimate Incorporates approved Alternative Technical Concepts that reduce cost Right-of-Way (ROW) team includes local companies ROWP Project tmanager experienced din both thstate t and dfederal regulations, and design-build Excellent project safety record, well beyond industry averages Very good design-build experience with proven history of success; including T-REX and DUS Proven design and construction management approaches 8

9 Kiewit Proposal Highlights (cont.) ISO 9001 quality program registration for key team members Commitment to collaboration with RTD, design and construction personnel, and stakeholders Kiewit, AECOM, and financer RBC have all worked with RTD previously Experienced key staff, familiar with RTD requirements Proposes to exceed the 25% SBE and 8% WIN goals SBE: Capacity Building Workshops; Diversity and Inclusion Council; existing relationships from DUS; outreach events; work packages; strong SBE Liaison WIN: WIN Executive Committee experience; committed to additional training; i opportunities in contract t administration, i ti public information, carpentry and traffic control 9

10 BBA Team 10

11 BBA Proposal Highlights Offers construction of I-225 corridor to logical terminus at City Center Station by September 2015 Capital cost bid within RTD s internal engineering estimate Traction Power Substation (TPSS) & Signal Systems will integrate into existing systems seamlessly Good Maintenance of Traffic plan Recent West Rail Line experience demonstrates systems integration expertise Strong ROW lead, with large project delivery experience Good safety record Design-build experience on comparable projects, including RTD s Eagle Project 11

12 BBA Proposal Highlights (cont.) Design-Build Coordinator will facilitate communication between construction and design team Interdisciplinary and constructability design reviews Good collaboration approach that includes stakeholders and public outreach Commitment to multi-level partnering Many key personnel have recent experience on RTD projects, including I-225 Environmental Evaluation/Preliminary Engineering Proposes to exceed the 25% SBE and 8% WIN goals SBE: Technical Guidance Workshops, Mentor-Protégé program, commitments t that t already exceed goal WIN: Founding members on Eagle project 12

13 Overall Evaluation Kiewit/MEC BBA Technical Score Financial Score Total Score

14 Recommended Action It is recommended by the FasTracks Monitoring Committee that the RTD Board of Directors authorize the General Manager to award the design build contract and negotiate final terms for a financial solution agreement to contract with Kiewit Infrastructure Company to serve as the Contractor for the I-225 Rail Line Project. The Project consisting of a portion of I-225 Rail Line from the Nine Mile Station to Peoria Station, which will be constructed for a lump sum amount of US$350 million, to be financed in accordance with the terms of the final financial agreement. 14

15 Benefits of Recommended Action High level of interest from the business community who are seeking innovative ways to partner with RTD to complete the I-225 corridor Proposal is consistent with the stated goals of the FasTracks program to seek innovative approaches to delivering the program Provides a firm, fixed price commitment to complete a key part of the FasTracks program at a favorable capital cost The commitment to this cost and scope is not likely to be available at a later time (due to current economic conditions and the fact that parts of the team are already mobilized for RTD s DUS project) Receipt of two solid proposals and successful award of the contract demonstrates the private sector's s interest in investing in another RTD project and speaks to the agency's respect in the industry. Could encourage the pursuit of similar proposals in other projects Will provide clean, safe, reliable, accessible and cost effective transportation in keeping with RTD s overall mission 15

16 Benefits of Recommended Action (cont.) Completion of the I-225 corridor provides additional mobility to key job centers for military veterans and transit dependents and has a high measure of cost effectiveness per rider Projected ridership is 34,400 riders per day by 2035 I-225 corridor serves es the key employment e and regional destination of the Anschutz/Fitzsimons Medical Campus, which includes University of Colorado Health Sciences Center Children s Hospital Soon-to-be completed Veterans Administration Regional Hospital which will serve the seven state Rocky Mountain region and provide medical services to approximately 57,000 military veterans on an annual basis The complete extension connects with the East Line (between Denver Union Station and Denver International Airport) at the Peoria Station and provides regional connectivity to a major portion of the metro area 16

17 Recommended Action Impacts If the RTD Board accepts the recommended action, the following actions would remain financially feasible: $305 M Projects: All projects identified to be completed using the $305 M remaining from the Eagle P3 project will be completed on schedule US 36 Managed Lane Project: Provide $15 M (in the timeframe) as requested by the Colorado HPTE to complete the managed lane project on US36 to Table Mesa. This will enable the highway h infrastructure t component of the US 36 BRT project to be completed 17

18 Recommended Action Impacts (cont.) If the RTD Board accepts the staff recommendation, the following actions would remain financially feasible: North Metro: RTD would pursue, as a top priority, any funding available to move forward with the design and construction of North Metro from the National Western Stock Show to 72 nd Avenue, allowing for the aggressive pursuit of a federal grant of up to 50% of the remaining cost to complete the corridor Southeast Corridor Extension: RTD would move forward with the first of several steps required to apply for a federal New Starts grant. Application for this grant would be a placeholder to allow RTD to enter into the FTA process 18

19 Next Steps July 10 Public Comment Period; FasTracks Monitoring Committee action July 17 Public Comment Period; RTD Board of Directors committee action July 24 RTD Board of Directors formal action Summer 2012 Financial Close and Notice to Proceed (Pending Board action) 19

20 Questions? 20

North Metro Rail Line Quarterly Briefing. November 7, 2013

North Metro Rail Line Quarterly Briefing. November 7, 2013 North Metro Rail Line Quarterly Briefing November 7, 2013 Agenda Welcome and Introductions Phil Washington North Metro Update Phil Washington and Jim Starling Northwest Area Mobility Study update Chris

More information

Lessons Learned for a Transit Public-Private Partnership. Phillip A. Washington, General Manager Regional Transportation District

Lessons Learned for a Transit Public-Private Partnership. Phillip A. Washington, General Manager Regional Transportation District Lessons Learned for a Transit Public-Private Partnership Phillip A. Washington, General Manager Regional Transportation District Feb. 7, 2011 The RTD FasTracks Plan 122 miles of new light rail and commuter

More information

The RTD FasTracks Plan

The RTD FasTracks Plan Citizens Advisory Committee Quarterly Meeting June 16, 2010 The RTD FasTracks Plan 122 miles of new light rail and commuter rail 18 miles of Bus Rapid Transit (BRT) 31 new park-n-rides with over 21,000

More information

Eagle Project Update

Eagle Project Update Construction of Peña Bridge November 2012 Eagle Project Update Eagle P3 Project Update Rick Clarke Assistant General Manager, Capital Programs March 5, 2014 Regional Transportation District (RTD) Performs

More information

CITY COUNCIL STUDY SESSION MEMORANDUM

CITY COUNCIL STUDY SESSION MEMORANDUM City and County of Broomfield, Colorado CITY COUNCIL STUDY SESSION MEMORANDUM To: From: Prepared By: Mayor and City Council George Di Ciero, City and County Manager Debra Baskett, Transportation Manager

More information

Construction of Peña Bridge - March 2013 Jersey Cutoff Bridge October Eagle Project Update. East Corridor Stakeholder Committee April 23, 2013

Construction of Peña Bridge - March 2013 Jersey Cutoff Bridge October Eagle Project Update. East Corridor Stakeholder Committee April 23, 2013 Construction of Peña Bridge - March 2013 Jersey Cutoff Bridge October 2012 Eagle Project Update East Corridor Stakeholder Committee April 23, 2013 FasTracks Plan 122 miles of new light rail and commuter

More information

Financing Transit Projects with Traditional and Innovative Sources And Mechanisms

Financing Transit Projects with Traditional and Innovative Sources And Mechanisms Financing Transit Projects with Traditional and Innovative Sources And Mechanisms Exploring the Potential for Bus Rapid Transit and Transit- Oriented Development in the I- 287/Tappan Zee Bridge Corridor

More information

MULTIMODAL TRANSPORTATION DISTRICT ALTERNATIVES ANALYSIS. Executive Summary

MULTIMODAL TRANSPORTATION DISTRICT ALTERNATIVES ANALYSIS. Executive Summary MULTIMODAL TRANSPORTATION DISTRICT ALTERNATIVES ANALYSIS Executive Summary February 2015 Executive Summary 1. Define the Problem This Alternatives Analysis report is submitted as a deliverable for the

More information

Request for Proposal Number #512-11

Request for Proposal Number #512-11 Request for Proposal Number #512-11 Traffic and Transportation Feasibility Study Due: January 24, 2012 at 4:00pm Buyer: Steve Boyd Purchasing and Contracts Manager 831 Grand Avenue Glenwood Springs, CO

More information

Disadvantaged Business Enterprise Program and Triennial DBE Goal Setting Methodology and Rationale

Disadvantaged Business Enterprise Program and Triennial DBE Goal Setting Methodology and Rationale Disadvantaged Business Enterprise Program and Triennial DBE Goal Setting Methodology and Rationale Kenn Hardin Senior Manager Civil Rights Division RTD Small Business Office August 14, 2013 Agenda Introductions

More information

Public-Private Partnership Program May 2015 Transit Coalition Update

Public-Private Partnership Program May 2015 Transit Coalition Update Public-Private Partnership Program May 2015 Transit Coalition Update Los Angeles County Metropolitan Transportation Authority Mark Linsenmayer Director Presentation Agenda Overview of Metro Public Private

More information

Fixing America s Surface Transportation Act: FAST Act Implications for the Region

Fixing America s Surface Transportation Act: FAST Act Implications for the Region Fixing America s Surface Transportation Act: FAST Act Implications for the Region Connie Kozlak Metropolitan Transportation Services Mark Fuhrmann Metro Transit Ed Petrie Metro Transit Metropolitan Council

More information

Summary of Committee Discussion/Questions Chris Beckwith, Senior Project Manager from the Gold Line Project Office, presented this item.

Summary of Committee Discussion/Questions Chris Beckwith, Senior Project Manager from the Gold Line Project Office, presented this item. Committee Report Business Item No. 2017-241 Transportation Committee For the Metropolitan Council meeting of November 29, 2017 Subject: Gold Line BRT Project Management/Environmental Contract Proposed

More information

CITY OF MIAMI SECTION 3 ECONOMIC OPPORTUNITY PLAN QUESTIONS

CITY OF MIAMI SECTION 3 ECONOMIC OPPORTUNITY PLAN QUESTIONS CITY OF MIAMI SECTION 3 ECONOMIC OPPORTUNITY PLAN QUESTIONS The Section 3 Economic Opportunity Plan must describe the proposed strategies for achieving the Section 3 training and employment numerical goals,

More information

Massachusetts Department of Transportation (MassDOT) The South Coast Rail Project DRAFT FOR DISCUSSION PURPOSES ONLY

Massachusetts Department of Transportation (MassDOT) The South Coast Rail Project DRAFT FOR DISCUSSION PURPOSES ONLY Massachusetts Department of Transportation (MassDOT) The High Level P3 Project Suitability Assessment Report September 11, 2013 Contents Proposed Project Description Project Background and Status Commonwealth

More information

3. Award and execute contract modifications for up to $1,200,000.

3. Award and execute contract modifications for up to $1,200,000. One Gateway Plaza Los Angeles, CA 90012-2952 213 922.2C metro.net REGULAR BOARD MEETING SEPTEMBER 23,2010 SUBJECT: ACTION: 1-605 "HOT SPOTS" FEASIBILITY STUDY AND PROJECT STUDY REPORTS (PSRs) APPROVE RECOMMENDATIONS

More information

Table of Contents. Page 2

Table of Contents. Page 2 Sixth Avenue Transportation Demand Management Construction Mitigation Plan August 2014 Table of Contents Table of Contents... 2 1.0 Introduction... 3 Development of Recommendations... 6 2.0 Recommendations...

More information

May 22, Pamela Bailey-Campbell. Vice President - North America Infrastructure Consultancy Jacobs Engineering, Inc.

May 22, Pamela Bailey-Campbell. Vice President - North America Infrastructure Consultancy Jacobs Engineering, Inc. May 22, 2013 Pamela Bailey-Campbell Vice President - North America Infrastructure Consultancy Jacobs Engineering, Inc. Public Partners Arizona Department of Transportation Office of P3 Initiatives City

More information

REQUEST FOR PROPOSALS (RFP) FIRE STATION FEASIBILITY STUDY. Borough of Phoenixville. July 15, 2016

REQUEST FOR PROPOSALS (RFP) FIRE STATION FEASIBILITY STUDY. Borough of Phoenixville. July 15, 2016 REQUEST FOR PROPOSALS (RFP) FIRE STATION FEASIBILITY STUDY Borough of Phoenixville 351 Bridge Street Second Floor Phoenixville, PA 19460 Chester County, Pennsylvania July 15, 2016 Borough of Phoenixville

More information

NCDOT Planning Summary for NCTA Projects

NCDOT Planning Summary for NCTA Projects NCDOT Planning Summary for NCTA Projects Page 1 Triangle Expressway Southeast Extension Wake and Johnston Counties (STIP Projects R-2721, R-2828, and R-2829) The Triangle Expressway Southeast Extension

More information

Massachusetts Bay Transportation Authority. POLICIES & PROCEDURES Design Build Procurement Procedures April 2016

Massachusetts Bay Transportation Authority. POLICIES & PROCEDURES Design Build Procurement Procedures April 2016 Massachusetts Bay Transportation Authority POLICIES & PROCEDURES Design Build Procurement Procedures April 2016 Design Build Procurement Procedures April 2016 Massachusetts Bay Transportation Authority

More information

Construction Careers Policy and Project Labor Agreement. AC Transit s Bus Rapid Transit Project. February 23, 2014

Construction Careers Policy and Project Labor Agreement. AC Transit s Bus Rapid Transit Project.  February 23, 2014 Construction Careers Policy and Project Labor Agreement AC Transit s Bus Rapid Transit Project San Francisco, CA Palm Springs, CA AC Transit s Bus Rapid Transit Project 9.5 mile arterial corridor through

More information

Denver s Lessons Learned in Developing Transit Initiatives

Denver s Lessons Learned in Developing Transit Initiatives Denver s Lessons Learned in Developing Transit Initiatives II. Successfully Passing a Transit Initiative Smart Growth Conference Three Pillars of Strength Public Private Non-Gov t Organizations FasTracks

More information

Regional Transit System Plan. Regional Task Force Meeting No. 1

Regional Transit System Plan. Regional Task Force Meeting No. 1 Regional Transit System Plan Regional Task Force Meeting No. 1 Thursday, December 2, 2010 James Wagner Welcome! Introductions Venue Packet Displays Opening Session 1 Agenda (5 mins) (20 mins) What is a

More information

On-call Geotechnical Consultant

On-call Geotechnical Consultant On-call Geotechnical Consultant Request for Proposal Iowa Department of Transportation Introduction The Office of Design for the Iowa Department of Transportation (the Department) is interested in securing

More information

CRENSHAW/LAX PILOT BUSINESS SOLUTION CENTER (BSC} and METRO'S PILOT BUSINESS INTERRUPTION FUND (BIF} MONTHLY REPORT

CRENSHAW/LAX PILOT BUSINESS SOLUTION CENTER (BSC} and METRO'S PILOT BUSINESS INTERRUPTION FUND (BIF} MONTHLY REPORT One Gateway Plaza Los Angeles, CA 90012-2952 213.922.2000 Tel metro. net CONSTRUCTION COMMITTEE EXECUTIVE MANAGEMENT COMMITTEE January 15, 2015 SUBJECT: ACTION: CRENSHAW/LAX PILOT BUSINESS SOLUTION CENTER

More information

Planning Sustainable Places Program

Planning Sustainable Places Program Planning Sustainable Places Program ADVANCING A SUSTAINABLE REGION PLACE BY PLACE 2019 Pre-Bid Workshop October 8, 2019 PSP Schedule Reminder Meeting Agenda Welcome RFP General Overview RFP Specifics Overview

More information

Met r 0 Met"'fKK'ibn Transportation Authority

Met r 0 Met'fKK'ibn Transportation Authority ~ Los Angeles County Met r 0 Met"'fKK'ibn Transportation Authority One Gateway Plaza Los Angeles, CA 90012-2952 213.922.2000 Tel metro.net CONSTRUCTION COMMITTEE MARCH 19, 2015 SUBJECT: ACTION: ROSECRANS/MARQUARDT

More information

WORK SESSION ITEM City Council

WORK SESSION ITEM City Council DATE: STAFF: October 25, 2016 Mark Jackson, PDT Deputy Director WORK SESSION ITEM City Council SUBJECT FOR DISCUSSION I-25 Northern Colorado Improvements. EXECUTIVE SUMMARY The purpose of this item is

More information

Historically Underutilized Business (HUB) Strategic Plan

Historically Underutilized Business (HUB) Strategic Plan The University of Texas MD Anderson Cancer Center Historically Underutilized Business (HUB) Strategic Plan Fiscal Years 2015 2016 Prepared November 2015 FINAL.doc page 1 of 9 FINAL.doc page 2 of 9 EXTERNAL

More information

PRE-PROPOSAL CONFERENCE Tuesday, October 19, 2010 SOUTH CENTRAL CORRIDOR HIGH CAPACITY TRANSIT FEASIBILITY STUDY

PRE-PROPOSAL CONFERENCE Tuesday, October 19, 2010 SOUTH CENTRAL CORRIDOR HIGH CAPACITY TRANSIT FEASIBILITY STUDY PRE-PROPOSAL CONFERENCE Tuesday, October 19, 2010 SOUTH CENTRAL CORRIDOR HIGH CAPACITY TRANSIT FEASIBILITY STUDY Meeting Overview Sign-In Sheets: Be sure to sign in. Sign-In sheets will be available on

More information

VERMONT AGENCY OF TRANSPORTATION. FY2018 Budget. Joe Flynn, Secretary of Transportation House Appropriations Committee February 27, 2017

VERMONT AGENCY OF TRANSPORTATION. FY2018 Budget. Joe Flynn, Secretary of Transportation House Appropriations Committee February 27, 2017 VERMONT AGENCY OF TRANSPORTATION FY2018 Budget Joe Flynn, Secretary of Transportation House Appropriations Committee February 27, 2017 Today s Presentation FY2018 Governor s Recommended overview and program

More information

Request for Proposals

Request for Proposals Request for Proposals I-75/85 Connector Transformation Project: Atlanta Bridgescape Competition Public Relations and Communications Services Contact: Wilma Sothern Vice President of Marketing Central Atlanta

More information

REPORT TO THE DULLES CORRIDOR COMMITTEE RECOMMENDATION TO AWARD A CONTRACT FOR CLAIMS CONSULTING SERVICES FOR THE DULLES CORRIDOR METRORAIL PROJECT

REPORT TO THE DULLES CORRIDOR COMMITTEE RECOMMENDATION TO AWARD A CONTRACT FOR CLAIMS CONSULTING SERVICES FOR THE DULLES CORRIDOR METRORAIL PROJECT REPORT TO THE DULLES CORRIDOR COMMITTEE RECOMMENDATION TO AWARD A CONTRACT FOR CLAIMS CONSULTING SERVICES FOR THE DULLES CORRIDOR METRORAIL PROJECT FEBRUARY 2018 PURPOSE Staff requests that the Dulles

More information

METRO Orange Line Extension Planning and Implementation

METRO Orange Line Extension Planning and Implementation METRO Orange Line Extension Planning and Implementation December 9, 2015 Planning has begun for an extension of METRO Orange Line south from Burnsville to the Kenrick Avenue park and ride in Lakeville.

More information

Iowa DOT Update 2016 APWA Fall Conference JOHN E. DOSTART, P.E.

Iowa DOT Update 2016 APWA Fall Conference JOHN E. DOSTART, P.E. Iowa DOT Update 2016 APWA Fall Conference JOHN E. DOSTART, P.E. Hilton Garden Inn September 29, 2016 Member of the Day Personal Updates M.J. Charlie Purcell Promoted to Project Delivery Bureau Director

More information

Client: Boulder County Transportation Project: SH 119 Bus Rapid Transit & Bikeway Facility Design

Client: Boulder County Transportation Project: SH 119 Bus Rapid Transit & Bikeway Facility Design Client: Boulder County Transportation Project: SH 119 Bus Rapid Transit & Bikeway Facility Design I. Applicant (Client) Information Organization Name and Address Boulder County Transportation, 2525 13th

More information

REQUEST FOR PROPOSALS

REQUEST FOR PROPOSALS REQUEST FOR PROPOSALS Town of Hope Mills Multi-Modal Congestion Management Plan September 19, 2016 Fayetteville Area Metropolitan Planning Organization Proposal Due Date: 3:00 PM Eastern Time, 28 th October,

More information

Historically Underutilized Business (HUB) Strategic Plan

Historically Underutilized Business (HUB) Strategic Plan The University of Texas MD Anderson Cancer Center Historically Underutilized Business (HUB) Strategic Plan Fiscal Years 2011 2012 Prepared June 2010 page 1 of 7 EXTERNAL AND INTERNAL ASSESSMENT The University

More information

November 4, 2013 Office of Transportation Public Private Partnerships

November 4, 2013 Office of Transportation Public Private Partnerships November 4, 2013 Office of Transportation Public Private Partnerships Dear Sirs, Via email: i66ppta@vdot.virginia.gov Re: Response of Shikun & Binui Ltd. (a member of the Arison Group) to the Request for

More information

System Access & Parking. Citizens Oversight Panel March 1, 2018

System Access & Parking. Citizens Oversight Panel March 1, 2018 System Access & Parking Citizens Oversight Panel March 1, 2018 System Access Program assumptions 21,000 sf/.48 ac System Access Fund Allocated based on an evaluation of customer needs at ST s existing

More information

Historically Underutilized Business (HUB) Strategic Plan

Historically Underutilized Business (HUB) Strategic Plan The University of Texas MD Anderson Cancer Center Historically Underutilized Business (HUB) Strategic Plan Fiscal Years 2013 2014 Prepared June 2012 F:\Files\My Docs\Documents\HUB\2013 Strategic Plan\Strategic

More information

Peninsula Corridor Joint Powers Board Legislative Program

Peninsula Corridor Joint Powers Board Legislative Program Peninsula Corridor Joint Powers Board 2018 Legislative Program Purpose Legislative and regulatory actions have the potential to significantly benefit Peninsula Corridor Joint Powers Board (JPB) programs

More information

REQUEST FOR PROPOSALS PROFESSIONAL SERVICES FOR INSTALLATION & UPGRADE OF BICYCLE FACILITIES (CLASS II & CLASS III) Issued by:

REQUEST FOR PROPOSALS PROFESSIONAL SERVICES FOR INSTALLATION & UPGRADE OF BICYCLE FACILITIES (CLASS II & CLASS III) Issued by: REQUEST FOR PROPOSALS PROFESSIONAL SERVICES FOR INSTALLATION & UPGRADE OF BICYCLE FACILITIES (CLASS II & CLASS III) City Project No. PW1517 Federal Project No. CML-5008(150) Issued by: City of Stockton

More information

TxDOT Funding and Accelerated Construction Program

TxDOT Funding and Accelerated Construction Program TxDOT Funding and Accelerated Construction Program RANDY C. HOPMANN, P.E. DIRECTOR OF DISTRICT OPERATIONS TXAPA s 42nd Annual Meeting September 22, 2016 Highway Transportation in Texas: Today and Our Future

More information

APPENDIX B BUS RAPID TRANSIT

APPENDIX B BUS RAPID TRANSIT APPENDIX B BUS RAPID TRANSIT Table of Contents TABLE OF CONTENTS What is Bus Rapid Transit?... 2 BRT Features... 2 BRT Variations... 3 Where is BRT Currently Located?... 4 How Much Does BRT Cost?... 4

More information

Prospective firms may also arrange a 15-minute conversation prior to the deadline.

Prospective firms may also arrange a 15-minute conversation prior to the deadline. REQUEST FOR PROPOSAL Magazine design and production January 3, 2018 Submit Proposals to: Kris Mattera, Executive Director Basalt Chamber of Commerce PO Box 514 Basalt, CO 51621 970-927-4031 director@basaltchamber.org

More information

TAMPA BAY PUBLIC TRANSIT INITIATIVES: A Response to Questions of the MPO citizens advisory committee

TAMPA BAY PUBLIC TRANSIT INITIATIVES: A Response to Questions of the MPO citizens advisory committee TAMPA BAY PUBLIC TRANSIT INITIATIVES: A Response to Questions of the MPO citizens advisory committee How can we address our future needs with transit? Projected Growth of the Network 2010-2040 200% 180%

More information

Request for Proposals. Housing Study Consulting Services. Proposals DUE: January 6, City of Grandview. Economic Development Department

Request for Proposals. Housing Study Consulting Services. Proposals DUE: January 6, City of Grandview. Economic Development Department Request for Proposals Housing Study Consulting Services Proposals DUE: January 6, 2017 City of Grandview Economic Development Department Leonard Jones, Mayor Cory Smith, City Administrator REQUEST FOR

More information

WESTERN STATE COLLEGE of COLORADO ATHLETIC DEPARTMENT FUND-RAISING POLICY. Updated: December 10, Drafted by: Greg Waggoner, Athletic Director

WESTERN STATE COLLEGE of COLORADO ATHLETIC DEPARTMENT FUND-RAISING POLICY. Updated: December 10, Drafted by: Greg Waggoner, Athletic Director WESTERN STATE COLLEGE of COLORADO ATHLETIC DEPARTMENT FUND-RAISING POLICY Updated: December 10, 2008 Drafted by: Greg Waggoner, Athletic Director Clarification This policy is specifically designed for

More information

East Harlem Commercial Opportunity RFP

East Harlem Commercial Opportunity RFP East Harlem Commercial Opportunity RFP Site Description 2321-2325 3rd Avenue (MN Block 1791 Lot 46) Convenient access via subway, Metro North, bus, and highway Located in a fast growing neighborhood Component

More information

To: From: Subject: Program continues to. Overview. the City of. Background. began the. As part of with both

To: From: Subject: Program continues to. Overview. the City of. Background. began the. As part of with both September 8, 2010 To: From: Subject: Transportation 2020 Committee Will Kempton, Chief Executive Officer Go Local Fixed-Guideway Program Update Overview The Go Local Fixed-Guideway Program continues to

More information

PART VI EVALUATION OF PROPOSALS, CONTRACT AWARD AND CONTRACT EXECUTION

PART VI EVALUATION OF PROPOSALS, CONTRACT AWARD AND CONTRACT EXECUTION PART VI EVALUATION OF PROPOSALS, CONTRACT AWARD AND CONTRACT EXECUTION SECTION TITLE N O P Evaluation of Proposals Contract Award Contract Execution 52 SECTION N EVALUATION OF PROPOSALS N.1 GENERAL Proposals

More information

BUSINESS DIVERSITY OUTREACH PROGRAM

BUSINESS DIVERSITY OUTREACH PROGRAM BUSINESS DIVERSITY OUTREACH PROGRAM December 14, 2011 OVERVIEW OF DPS BUSINESS DIVERSITY OUTREACH PROGRAM The DPS Business Diversity Program was started in 1999 to outreach to minority, women owned and

More information

8, 2018 REQUEST FOR PROPOSALS (RFP): G

8, 2018 REQUEST FOR PROPOSALS (RFP): G ADDENDUM NO. 2 DATE: June 8, 2018 REQUEST FOR PROPOSALS (RFP): G180026673 Design Professional Services Richmond Public Schools George Mason Elementary School DATED: May 15, 2018 PROPOSAL DUE DATE & TIME:

More information

PUBLIC-PRIVATE PARTNERSHIP PROGRAM, HIGH DESERT CORRIDOR

PUBLIC-PRIVATE PARTNERSHIP PROGRAM, HIGH DESERT CORRIDOR 29 One Gateway Plaza Los Angeles, CA 90012-2952 213.922.2000 l metro. net PLANNING AND PROGRAMMING COMMITTEE MARCH 20, 2013 SUBJECT: ACTION: PUBLIC-PRIVATE PARTNERSHIP PROGRAM, HIGH DESERT CORRIDOR RECEIVE

More information

May 17, To: From: Subject: Program continues to. Overview. Step Two. fixed-guideway. Program. for. Background

May 17, To: From: Subject: Program continues to. Overview. Step Two. fixed-guideway. Program. for. Background May 17, 2010 To: From: Subject: Transportation 2020 Committee Will Kempton, Chief Executive Officer Go Local Fixed-Guideway Program Update Overview The Go Local Fixed-Guidewaof the program, the City of

More information

Hooray! My Project Is Funded. now what? The Grants Management Handbook. Southwestern Community College

Hooray! My Project Is Funded. now what? The Grants Management Handbook. Southwestern Community College Hooray! My Project Is Funded now what? The Grants Management Handbook Southwestern Community College Table of Contents: Overview... 3 Getting Started... 4 Who Does What? Key People and Places... 7 Records

More information

Transportation Planning in the Denver Region

Transportation Planning in the Denver Region The Prospectus Transportation Planning in the Denver Region TAC Draft (as of June 16, 2011) Approved December 2004 Revised November 2006 Revised August 2007 Revised March 2009 Revised 2011 Key revisions

More information

TRB/AASHTO Environment & Energy Research Conference June 6-9, 2010 Session 47: Lessons Learned from P3 Public Involvement Initiatives

TRB/AASHTO Environment & Energy Research Conference June 6-9, 2010 Session 47: Lessons Learned from P3 Public Involvement Initiatives TRB/AASHTO Environment & Energy Research Conference June 6-9, 2010 Session 47: Lessons Learned from P3 Public Involvement Initiatives Lessons Learned from Virginia P3 Projects Dana C. Nifosi, Venable LLP

More information

The Division expects to let the following FTA/ USDOT-assisted projects in FFYs :

The Division expects to let the following FTA/ USDOT-assisted projects in FFYs : Suffolk County Disadvantaged Business Enterprise (DBE) Overall Goal and Goal Setting Methodology for Federal Transit Administration Assisted Contracts FFY 2017-2019 Amount of goal The Suffolk County Department

More information

2016 I-74 General Engineering Consultant Services

2016 I-74 General Engineering Consultant Services 2016 I-74 General Engineering Consultant Services Request for Proposal Iowa Department of Transportation Introduction On behalf of the Illinois DOT and Iowa DOT, the Iowa DOT District 6 Office is interested

More information

2018 Pipelines Engineering Services Boerne Stage Road, West Avenue, and Highway 90 & General McMullen

2018 Pipelines Engineering Services Boerne Stage Road, West Avenue, and Highway 90 & General McMullen 2018 Pipelines Engineering Services Boerne Stage Road, West Avenue, and Highway 90 & General McMullen M. Antonio Leyva, P.E. Manager Engineering Angelica Mata Manager Contract Administration Marisol V.

More information

SUBCONTRACTING ON CDOT CONSTRUCTION PROJECTS Ramp Up Ridgway!

SUBCONTRACTING ON CDOT CONSTRUCTION PROJECTS Ramp Up Ridgway! SUBCONTRACTING ON CDOT CONSTRUCTION PROJECTS Ramp Up Ridgway! Connect2DOT Colorado Small Business Development Center Network (SBDC) program funded by CDOT Free training, consulting, and resources for small

More information

Request for Proposals. For NEW HOPE TO WARMINSTER PASSENGER RAIL SHUTTLE FEASIBILITY STUDY

Request for Proposals. For NEW HOPE TO WARMINSTER PASSENGER RAIL SHUTTLE FEASIBILITY STUDY Request for Proposals For NEW HOPE TO WARMINSTER PASSENGER RAIL SHUTTLE FEASIBILITY STUDY The Bucks County Transportation Management Association, Inc. (TMA Bucks), on behalf of the Borough of New Hope,

More information

REQUEST FOR PROPOSALS FOR THE FEASIBILITIY STUDY

REQUEST FOR PROPOSALS FOR THE FEASIBILITIY STUDY REQUEST FOR PROPOSALS FOR THE FEASIBILITIY STUDY Double-tracking the section(s) of the Media Trolley Line from Woodland Avenue to the Blue Route (I-476) The Delaware Valley Regional Planning Commission

More information

KEY TAKEAWAYS THE STIMULUS BREAKDOWN

KEY TAKEAWAYS THE STIMULUS BREAKDOWN S T I M U L U S F O R G R E A T E R P H I L A D E L P H I A : W H A T I T M E A N S F O R T R A N S P O R T A T I O N I N V E S T M E N T I N T H E R E G I O N KEY TAKEAWAYS Greater Philadelphia will likely

More information

AFFORDABLE FARES IN THE DENVER METRO REGION U P D A T E

AFFORDABLE FARES IN THE DENVER METRO REGION U P D A T E AFFORDABLE FARES IN THE DENVER METRO REGION 2 0 1 6 U P D A T E WHY AFFORDABLE FARES? WHY? LISTEN TO OUR COMMUNITY. RTD s low-income riders tell us the cost of fares is too high and that they are forced

More information

TRANSPORTATION IMPROVEMENT PROGRAM

TRANSPORTATION IMPROVEMENT PROGRAM Adopted - April 19, 2017 2018-2021 TRANSPORTATION IMPROVEMENT PROGRAM We make life better! ii ABSTRACT TITLE: AUTHOR: SUBJECT: 2018-2021 Transportation Improvement Program Denver Regional Council of Governments

More information

Strategic Plan for Transit Oriented Development. Revision 2, September 2010

Strategic Plan for Transit Oriented Development. Revision 2, September 2010 Revision 2, September 2010 This is a controlled document; please do not duplicate. If additional copies are required, please request them from the FasTracks Document Control. This will assure that all

More information

Request for Proposals City of Oberlin, Ohio Branding and Cultural Wayfinding Signage Plan

Request for Proposals City of Oberlin, Ohio Branding and Cultural Wayfinding Signage Plan Request for Proposals City of Oberlin, Ohio Branding and Cultural Wayfinding Signage Plan Introduction The City of Oberlin, Ohio, in association with the Firelands Association for the Visual Arts (FAVA),

More information

Santa Clara Valley Transportation Authority Disadvantaged Business Enterprise (DBE) Program

Santa Clara Valley Transportation Authority Disadvantaged Business Enterprise (DBE) Program Santa Clara Valley Transportation Authority Disadvantaged Business Enterprise (DBE) Program Three-Year Overall Goal and Methodology Report For Federal Fiscal Years 2017 2019 I. Goal Setting Methodology

More information

The information contained in this presentation is for informational purposes only

The information contained in this presentation is for informational purposes only Preproposal Conference RFP 1-11-C047 Risk Management Information System (RMIS) March 15, 2011 Disclaimer The information contained in this presentation is for informational purposes only In the event of

More information

Request for Proposals (RFP) An Alternative Fuels Assessment & Feasibility Study

Request for Proposals (RFP) An Alternative Fuels Assessment & Feasibility Study Request for Proposals (RFP) An Alternative Fuels Assessment & Feasibility Study VTA Project # 2016-01 From: Subject: Angela E. Grant, Administrator Project VTA #2016-01 Request for Proposals An Alternative

More information

REQUEST FOR PROPOSALS

REQUEST FOR PROPOSALS REQUEST FOR PROPOSALS FOR PROFESSIONAL DESIGN SERVICES INSTALL PEDESTRIAN CROSSINGS AT NINE INTERSECTIONS CITY PROJECT NO. PW1715 FEDERAL PROJECT NO. HSIPL-5008(161) CITY OF STOCKTON PUBLIC WORKS DEPARTMENT

More information

Authorize the Chief Executive Officer to award and execute the following contracts for the Eastside Phase I1 Transit Corridor Project:

Authorize the Chief Executive Officer to award and execute the following contracts for the Eastside Phase I1 Transit Corridor Project: @ Metro lob Los Angeles County One Gateway Plaza 213.922 2000 Tt Metropolitan Transportation Authority Los Angeles, CA 90012-2952 rnetro.net PLANNING AND PROGRAMMING COMMIlTEE June 20,2007 SUBJECT: ACTION:

More information

Request for Qualifications/Proposals Alameda County Redevelopment Agency Economic Development Strategic Plan

Request for Qualifications/Proposals Alameda County Redevelopment Agency Economic Development Strategic Plan Alameda County Redevelopment Agency The, a department of the Alameda County Community Development Agency, requests Qualifications and Proposals for consultant services to assist in the development of an

More information

ADDENDUM #1 LRT SS SECURITY SERVICES

ADDENDUM #1 LRT SS SECURITY SERVICES DDENDUM #1 RFP NUMBER: RFP TITLE: LRT-08-110-SS SECURITY SERVICES DDENDUM NO.: 1 DTE: July 1, 2008 CLRIFICTIONS / CORRECTIONS The following clarifications and corrections are hereby made part of and subject

More information

Request for Proposal REQUEST FOR PROPOSAL

Request for Proposal REQUEST FOR PROPOSAL REQUEST FOR PROPOSAL Consumer Research Sample, Fielding, and Analysis August 2016 INTRODUCTION Brand USA is a public-private not for profit organization created by the Travel Promotion Act of 2009. The

More information

OUTAGAMIE COUNTY REQUEST FOR PROPOSAL FOR RIGHT OF WAY RE MONUMENTATION SERVICES FOR HIGHWAY DEPARTMENT

OUTAGAMIE COUNTY REQUEST FOR PROPOSAL FOR RIGHT OF WAY RE MONUMENTATION SERVICES FOR HIGHWAY DEPARTMENT OUTAGAMIE COUNTY REQUEST FOR PROPOSAL FOR RIGHT OF WAY RE MONUMENTATION SERVICES FOR HIGHWAY DEPARTMENT DUE BY: May 26, 2015 1.0 Introduction and Background Outagamie County Highway Department is seeking

More information

CITY OF ROCHESTER, NEW HAMPSHIRE INVITATION TO BID

CITY OF ROCHESTER, NEW HAMPSHIRE INVITATION TO BID CITY OF ROCHESTER, NEW HAMPSHIRE INVITATION TO BID REQUEST FOR PROPOSALS City of Rochester, New Hampshire Office of Planning and Development The City of Rochester is accepting sealed bids for Rochester

More information

Background on Fitzsimons Army Hospital

Background on Fitzsimons Army Hospital Background on Fitzsimons Army Hospital In 1918 Army Hospital No. 21 was created near Aurora at Peoria Street and East Colfax Avenue. The site used to be a nursery where plants and trees grew. The nursery

More information

Philanthropy National Make a Difference Day October 23, 2010

Philanthropy National Make a Difference Day October 23, 2010 University of Colorado Anschutz Medical Campus Student Senate Philanthropy National Make a Difference Day October 23, 2010 Fall 2010 Fall 2010 Volunteer Series Coordinate and Move!!! Inside Step-Up for

More information

Borough of Glassboro, New Jersey. Request for Proposals. Getting Around Glassboro Transportation and Transit Study

Borough of Glassboro, New Jersey. Request for Proposals. Getting Around Glassboro Transportation and Transit Study Borough of Glassboro, New Jersey Request for Proposals Getting Around Glassboro Transportation and Transit Study RFP Release Date: October 3, 2003 Letters of Intent Due: October 17, 2003 Proposals Due

More information

I-80/I- 380 Systems Interchange Reconstruction Construction Manager/General Engineering Consultant Services

I-80/I- 380 Systems Interchange Reconstruction Construction Manager/General Engineering Consultant Services I-80/I- 380 Systems Interchange Reconstruction Construction Manager/General Engineering Consultant Services Request for Proposal Iowa Department of Transportation Introduction The Iowa DOT District 6 Office

More information

CITY OF LOMITA REQUEST FOR PROPOSAL FOR PROFESSIONAL SERVICES TO PROVIDE BID PROPOSAL FOR

CITY OF LOMITA REQUEST FOR PROPOSAL FOR PROFESSIONAL SERVICES TO PROVIDE BID PROPOSAL FOR CITY OF LOMITA REQUEST FOR PROPOSAL FOR PROFESSIONAL SERVICES TO PROVIDE BID PROPOSAL FOR CONSULTING SERVICES FOR THE REVIEW AND NEGOTIATION OF A POSSIBLE EXTENSION TO AN EXISTING SOLID WASTE FRANCHISE

More information

Transportation Demand Management Workshop Region of Peel. Stuart M. Anderson David Ungemah Joddie Gray July 11, 2003

Transportation Demand Management Workshop Region of Peel. Stuart M. Anderson David Ungemah Joddie Gray July 11, 2003 Transportation Demand Management Workshop Region of Peel Stuart M. Anderson David Ungemah Joddie Gray July 11, 2003 Why Transportation Demand Management (TDM)? Demand management measures support a sustainable

More information

METRO Blue Line LRT & METRO Green Line LRT (Light Rail) Table of Contents. Operating Grant Worksheets Pages 6-17

METRO Blue Line LRT & METRO Green Line LRT (Light Rail) Table of Contents. Operating Grant Worksheets Pages 6-17 METRO Blue Line LRT & METRO Green Line LRT (Light Rail) Table of Contents Operating Grant Application Cover Sheet Pages 1-3 Project Benchmarks and Timeline Pages 4-5 Operating Grant Worksheets Pages 6-17

More information

Solano County Transit (SolTrans) Overall Disadvantaged Business Enterprise (DBE) Goal FFY through FFY

Solano County Transit (SolTrans) Overall Disadvantaged Business Enterprise (DBE) Goal FFY through FFY Solano County Transit (SolTrans) Overall Disadvantaged Business Enterprise (DBE) Goal FFY 2016 17 through FFY 2018 19 Summary In accordance with the requirements of 49 C.F.R. Part 26 (Participation by

More information

TOWN OF GROVELAND REQUEST FOR PROPOSALS ENGINEER DESIGN SUPPORT FOR THE GROVELAND COMMUNITY TRAIL, A PROPOSED 3.25 MILES SHARED-USE PATH PROPOSAL DUE:

TOWN OF GROVELAND REQUEST FOR PROPOSALS ENGINEER DESIGN SUPPORT FOR THE GROVELAND COMMUNITY TRAIL, A PROPOSED 3.25 MILES SHARED-USE PATH PROPOSAL DUE: TOWN OF GROVELAND REQUEST FOR PROPOSALS ENGINEER DESIGN SUPPORT FOR THE GROVELAND COMMUNITY TRAIL, A PROPOSED 3.25 MILES SHARED-USE PATH PROPOSAL DUE: JULY 31, 2014 AT 11AM SUBMIT TO: FINANCE DIRECTOR

More information

NDOT Civil Rights DBE Program Small Business Element

NDOT Civil Rights DBE Program Small Business Element NDOT Civil Rights DBE Program Small Business Element The DBE program improvements regulations that became effective on February 28, 2011, require federal funds recipients such as NDOT must include an SBE

More information

A RESOLUTION. amended plans for the East End METRORail Expansion which resulted in the redesign

A RESOLUTION. amended plans for the East End METRORail Expansion which resulted in the redesign RESOLUTION NO. 2014-52 RESCINDING RESOLUTION 2011-70 AND AUTHORIZING AN EAST END LIGHT RAIL OVERPASS DESIGN AT HARRISBURG, WITH VEHICLE AND PEDESTRIAN WALKWAYS AT-GRADE AND OVER, WITH A LIMITED NOTICE

More information

VRE Gainesville Haymarket Extension Feasibility Study and Alternatives Analysis

VRE Gainesville Haymarket Extension Feasibility Study and Alternatives Analysis VRE Gainesville Haymarket Extension Feasibility Study and Alternatives Analysis Public Workshop Wednesday, July 30 th, 2008 6:30 9:00 pm Stonewall Jackson High School Presentation Overview Introduction

More information

OHIO TURNPIKE AND INFRASTRUCTURE COMMISSION

OHIO TURNPIKE AND INFRASTRUCTURE COMMISSION OHIO TURNPIKE AND INFRASTRUCTURE COMMISSION REQUEST FOR PROPOSALS ( RFP ) PROFESSIONAL ENGINEERING AND CONSTRUCTION ADMINISTRATION AND INSPECTION SERVICES REF: REHABILITATION OF VARIOUS BRIDGES AT MILEPOSTS

More information

REQUEST FOR PROPOSALS

REQUEST FOR PROPOSALS Community Development Department Planning & Zoning Division REQUEST FOR PROPOSALS COMBINED ACTIVE TRANSPORTATION/ SAFE ROUTES TO SCHOOL PLAN State Project No. ATPL-5169 (048) RELEASE DATE: SEPTEMBER 23,

More information

Transportation Alternatives Program Application For projects in the Tulsa Urbanized Area

Transportation Alternatives Program Application For projects in the Tulsa Urbanized Area FFY 2015-2016 Transportation Alternatives Program Application For projects in the Tulsa Urbanized Area A Grant Program of Moving Ahead for Progress in the 21st Century (MAP-21) U.S. Department of Transportation

More information

Gold Rush Circulator Study Charlotte, North Carolina REQUEST FOR PROPOSALS

Gold Rush Circulator Study Charlotte, North Carolina REQUEST FOR PROPOSALS Gold Rush Circulator Study Charlotte, North Carolina REQUEST FOR PROPOSALS September 25, 2012 for the Gold Rush Circulator Study A. Purpose Charlotte Center City Partners (CCCP) and the City of Charlotte

More information

Part I. Federal Section 5310 Program

Part I. Federal Section 5310 Program Part I. Federal Section 5310 Program ENHANCED MOBILITY OF SENIORS AND INDIVIDUALS WITH DISABILITIES FY 2017 Solicitation for Proposals 5 PROGRAM GOALS & FUND AVAILABILITY The goals of the Section 5310

More information

Allegany County, MD Request for website: Responsive website redesign and CMS rebuild.

Allegany County, MD Request for website: Responsive website redesign and CMS rebuild. Allegany County, MD Request for website: Responsive website redesign and CMS rebuild. Overview: Allegany County Tourism, located in Allegany County, Maryland is a Destination Marketing Organization that

More information

BRF-009-9(73) IA 9 Black Hawk Bridge

BRF-009-9(73) IA 9 Black Hawk Bridge BRF-009-9(73) 38-03 IA 9 Black Hawk Bridge Request for Proposal Iowa Department of Transportation Introduction The Iowa Department of Transportation s Office of Location and Environment (Department), in

More information