1 Agenda Item 10 Tuesday 17 April 2018 Report of Priority 7: All Wales Accelerating Cardiac Informatics (AWACI) Project Paper prepared by Michelle Cook, Project Manager, AWACI Project, NWIS Action/Decision Required The HCIG are asked to: RECEIVE and NOTE the Project Closure Summary.

2 PCR-ID PROJECT CLOSURE SUMMARY All Wales Accelerating Cardiac Informatics Version No. 0.3 Status: Draft Date: 22/03/2018 Tŷ Glan-yr-Afon 21 Heol Ddwyreiniol Y Bont-Faen, Caerdydd CF11 9AD 21 Cowbridge Road East, Cardiff CF11 9AD Ffôn/Tel: Page 2 of 15

3 TABLE OF CONTENTS 1 DOCUMENT HISTORY Revision History Reviewers Authorisation Document Location PURPOSE BACKGROUND REASON FOR CLOSING THE PROJECT PROJECT PERFORMANCE Against Objectives Against Costs Challenges Continuation Activities Project Staff Project Scope Financial Management POST PROJECT REVIEW Membership Quorum Frequency of Meeting Reporting Arrangements Draft Agenda RECOMMENDATIONS REFERENCES GLOSSARY Page 3 of 15

4 1 DOCUMENT HISTORY 1.1 Revision History Date Version Author Revision Summary Michelle Cook Initial draft Michelle Cook Amendments following DS review Michelle Cook Amendments following TH review 1.2 Reviewers This document requires the following reviews: Date Version Name Position David Sheard Deputy Director of Implementation, NWIS Tracey Hill Transformation Lead, Wales Cardiac Network 1.3 Authorisation Signing of this document indicates acceptance of its contents. Author s Name: Role: Signature: Michelle Cook Project Manager Date: Approver s Name: Role: Signature: David Sheard Deputy Director of Implementation Date: 1.4 Document Location Type Electroni c Location litems.aspx Page 4 of 15

5 2 PURPOSE The All Wales Accelerating Cardiac Informatics (AWACI) project submitted an application to the Efficiency with Technology Fund (ETTF) in August 2017 to supplement the existing bid which would continue to build upon the achievements from the original bid awarded in The project has received confirmation that it has not been successful in attaining these funds, but it continues to pursue alternative funding streams. However, this does result in the end of a contractual relationship with the ETTF programme. This summary report aims to provide assurance of the achievement over the past twenty-two months through utilisation of the funds, insight into the challenges faced so future projects can benefit and provides the opportunity to demonstrate the future movement of the project. 3 BACKGROUND In the original bid submitted to the ETTF in autumn 2015, the project set out to act as a trailblazer to bring about efficiencies and improvements to cardiac services through the application of informatics. It focussed on accelerating the implementation and adoption of electronic referrals, diagnostic requests and results and clinical communications between primary, secondary and tertiary care, which is essential to enable efficient management of patients through the cardiology pathway. The AWACI project was initiated on 14 th June The overall objective was to enable patients to receive diagnosis and care in the most appropriate setting, from the right clinician, in the shortest possible time and in a safe and auditable pathway. To achieve this, cardiac services need to move to a paperless electronic referral process for patients along the cardiac care pathway. This should markedly reduce the time patients wait to be seen for their referral, diagnosis and treatment. This is essential to enable and maximise the benefits from new community cardiology services. First year monies were lost due to delayed release of funds, which left inadequate timescales for the recruitment activity required. The project carried underspend in 2016/17 due to its inability to recruit into a number of the technical and clinical vacancies despite continued efforts to raise awareness and prioritise recruitment for the necessary posts. Following successful recruitment of technical and clinical roles in 2017/18, the project preceded to get back on track with its delivery, with a balanced finance forecasted for 2017/18. 4 REASON FOR CLOSING THE PROJECT As outlined above, the projects contractual obligations and financial commitments with the ETTF will end in March However, due to the trailblazing ethos of the AWACI project and the perceived service need to deliver electronic mechanisms like hospital to hospital referrals, NWIS has continued project delivery against a revised scope. Page 5 of 15

6 5 PROJECT PERFORMANCE 5.1 Against Objectives The table below lists the original objectives for the project, comments on achievements with reasons for non-achievements: Objective Status Comment Electronic referral management of GP referrals to Cardiology national deployment Electronic clinical dialogue with Primary Care colleagues which enables care closer to home rather than hospital settings (community cardiology) Secondary to Tertiary electronic referrals and communication Uplift Cardiology as a priority specialty for Welsh Patient Referral Service (WPRS) implementation Incorporate Practitioners with Special Interest into WPRS Ongoing Priority delivery completed in Cwm Taf and ABMU (East) Go-Live scheduled in ABMU (West) on Go-Live TBC in Hywel Dda, however priority status achieved. Go-Live TBC in BCU, dependency on initial WAP deployment. Clinical Champion identified to lead on local readiness activities. Priority status for Cardiology. Cardiology maintains priority specialty for all new Health Board WPRS uplifts. Ongoing Inclusion of Practitioners with Special Interest as part of ABMU (East) deployment. Extension to ABMU (West) outlined for deployment, however both roles have since resigned. Parked Additional WPRS development has allowed for interim test request solution providing better visibility and management of diagnostics. During early project planning and a result of the number of project vacancies, this deliverable was parked to allow focus on the extension of the Welsh Patient Referral Service for hospital activity. Ongoing Agreement for national standardised outpatient referral electronic document (process attached in Appendix B) Page 6 of 15

7 (internal and external) across health board boundaries. Inclusion of mandated Pathway Start Date field with supporting clinical justification to allow for better identification and improved tracking. All development has completed across the four applications, Welsh Clinical Portal, Welsh Admin Service, Welsh Clinical Communications Gateway and Welsh Patient Administration Service. System Integration Testing underway with User Acceptance Testing scheduled in May. Deployment scheduled as part of v of WCP in June Electronic requesting of Cardiac diagnostic services at point of clinical prioritisation when required Ongoing National consensus for standardised cardiac service electronic request (attached in Appendix B) Electronic reporting of Cardiac diagnostic services at point of clinical prioritisation when required Visibility of cardiac related activity to other clinical specialities to enrich patient record and point on the clinical pathway is visible to all clinicians Ongoing Deployment of National messaging service linked to the Welsh Results Report Service with interfaces for each Health Board Visibility of MEDCON, MUSE and HD Clinical reports within Cwm Taf Delivery of National Technical Specification for ORU and ORM messages, which will be adopted across all Welsh Results Report Service (WRRS) integrations. Ongoing The All Wales organisational constraint was lifted in December 2017, enabling WCP users to view documents about their patient regardless of where in Wales they were created. Visibility of the following Health Boards clinical documentation: BCU epoc ABHB Medsecs ABMU DMS WCCG referrals (all Health Boards) Successful rollout of the WRRS to Cwm Taf, Powys, Velindre, Cardiff & Vale, ABMU, Hywel Dda and ABHB. BCU to go-live w/c Page 7 of 15

8 In addition to achieving the aforementioned objectives, the project has made significant progress in bringing together experts within cardiac services from across NHS Wales to agree national standards ultimately reducing unwarranted variation in patient care. Understandably, corralling opinion across such a geographical and culturally diverse area has been a challenge yet has afforded us opportunities to utilise these groups for future service and pathway redesign, it has also been utilised by some of the project s partnership organisations. Following the WHSCC commissioned Delivery Unit evaluation in October 2017, which highlighted areas of concerns with regards to accurate pathway and waiting times reporting across Cardiac Services, the AWACI project were able to demonstrate an electronic referral solution, ultimately providing a solution for the concerns raised in the evaluation. Further enhancing the AWACI position as an innovative, dynamic and transformational project across NHS Wales. The project has been reflexive in its development and pursued the opportunity to utilise the Wales Cardiac Networks National Informatics Manager to support the development of robust and trustworthy data generation. 5.2 Against Costs The table below highlights budget against actual cost, the variance at year end and total costs for the duration of the Efficiency Through Technology funded project: 2015/ / /18 Total Project Costs Budget - 367, , , Actual - 312, , , Variance , , , Comments Underspend returned to Welsh Government Awaiting confirmation of final position 5.3 Challenges One of the key challenges throughout the lifespan of the project has been the recruitment of both technical and clinical resource to be able to deliver the project objectives as per the agreed timetable of delivery. Key learning point; A collaborative approach for recruitment for clinical positions (Wales Cardiac Network and NWIS) is likely the most effective method to recruit the strongest candidates with the relevant clinical background. Given the challenges, this should be considered as a priority on project initiation to secure resource for project delivery. The period of employment offered must be considered as it may present itself as a barrier if under 2 years. Page 8 of 15

9 Key learning point; The project lacked dedicated Business Analyst support - projects must be mindful that management of business requirements should be robust to prevent several iterations, avoid high level requirements and ensure corresponding use cases are drafted. Key learning point; Collaborative working across NWIS/Wales Cardiac Network has prompted challenges to align conflicting priorities and management of resource across two organisation boundaries. Positive and fruitful opportunities have occurred because of having resource across the two organisations, including closer links to policy leads in Welsh Government, Clinical Leads and Directors. Key learning point; Limited release of Health Board clinical staff for Clinical Reference Group attendance hindered discussions and impacted on productivity due to the requirement to revisit discussions. 6 Continuation Activities The following sub-sections cover the various activities required to continue the project. 6.1 Project Staff NWIS has extended agency staff for the following durations against the revised scope: 3 month extension: - Software Developer (National Operational Database and Integration) 6 week extension: - Technical Architect (Applications Design) Substantive posts remain assigned but will be reviewed further once other funding understood: - Project Manager (Implementation) - Test Analyst (Test) - Software Developer (Hospital Applications) - Software Developer (NODI) Additionally, Heart Conditions Implementation Group (HCIG) approved a 3 month extension for both the Clinical Programme Manager and Service Transformation Manager. 6.2 Project Scope With the current funding position unknown, the AWACI Project Board proposed a revised scope for 2018/19 delivery, which would reduce resource requirements and ultimately associated costs. Given that the initial follow up bid for ETTF exceeded 1 million across a two year period, the project board were realistic in their expectations in seeking alternative funding sources both to NWIS and HCIG. Page 9 of 15

10 Given the political pressures associated with the WHSCC commissioned Delivery Unit evaluation of the transition point along the referral to treatment pathway and the national consensus from the clinical communities, it was agreed that the revised scope would include Hospital to Hospital, electronic Requesting and electronic Reporting in support of the benefits that will be realised through the delivery of these work-streams: Hospital-to-Hospital Electronic Referrals (reduced scope): As previously mentioned, the development for hospital to hospital has completed across a number of applications. A pilot for Cardiology and Cardiac Surgery outpatient activity is due to commence in June 2018, which will include Abertawe Bro Morgannwg, Cardiff and Vale and Cwm Taf University Health boards. The pilot will run and an evaluation completed over a 3-month basis. During the pilot and evaluation, continued efforts to sustain the well-established Clinical Reference Group and utilise the Subject Matter Experts to further define requirements for the extension to inpatient activity including ward reviews. If no further funding for the project is secured, following pilot evaluation, progression would form part of the existing Welsh Patient Referral Service roadmap. Electronic Requesting (reduced scope) As per the deliverables outlined in 5.1 Against Objectives, the intention with electronic requesting was to develop a full end-to-end electronic workflow with third party integration. Due to the timescales and resource available, the AWACI Project Board proposed to de-scope any third party integration, in favour of the creation of electronic work lists. This would enable the receipt of the nationally standardised electronic document already agreed through use of the electronic Requesting Clinical Reference Group which would be completed within the Welsh Clinical Portal. To date this would include all cardiac diagnostics, which do not require any form of vetting by a Consultant Cardiologist. The AWACI project team have identified two senior Cardiologist who have volunteered to undertake a thorough proof of concept to evaluate the clinical acceptance of this prototype. The project will continue efforts to sustain the well-established Clinical Reference Group and utilise the Subject Matter Experts within to further define requirements for the extension of requesting to include diagnostics which require a vetting process. Additionally, continuing collaboration with the radiology requesting project team to ensure inclusion of requirements, design and delivery for Cardiac MRI and CT. Electronic Reporting (reduced scope): The National Standards for ORU and ORM messages will be further utilised for welsh Results Report Service (WRRS) integrations, in particular the completion of: MEDCON (McKesson) and HD Clinical in Abertawe Bro Morgannwg and Aneurin Bevan UHB s Cardiobase South Wales Congenital Heart Unit (diagnostics) MUSE (GE) across all remaining Health Boards Additionally, integration with the Welsh Care Record Service (WCRS) for: Cardiobase - South Wales Congenital Heart Unit (clinical letters) Dendrite PATS (Cardiac Surgery) Operation notes within Abertawe Bro Morgannwg and Cardiff & Vale UHB s Page 10 of 15

11 The AWACI project team will ensure this work-stream is achieved by maintaining priority for Cardiac Service content. Creation of robust and trustworthy data The project will continue to collaborate with the SNOMED-CT Implementation team to understand and map clinical coding requirements to underpin certain data items within the e-forms developed. Further to discussions held at the Network and Implementation Group Informatics Priorities meeting in March 2018, the project will ensure it continues it collaborative efforts with other clinical networks. This will further maintain AWACI as a trailblazer and ensure that delivery meets the wider service needs. 6.3 Financial Management In addition to the resource secured within NWIS, the project submitted a bid for the reallocation of the Heart Conditions Implementation Group Delivery Plan monies. Outcomes from this process will be reported back to HCIG in April. 7 POST PROJECT REVIEW The primary purpose of the Post Project Review is to assess what happened throughout the Project what went well and what didn t go according to plan. Additionally, to establish lessons that can be passed on to future Project Teams. The output from this meeting goes into the Post Project Review report. Each participant in a Post Project Review meeting has different responsibilities for the preparation, procedures, and follow-up of the Post Project Review but there are also some responsibilities that may be shared or common to participants. Representatives from Local Health Boards, NWIS Project Management and AWACI Project Board will be involved in the meeting to determine the overall Project s Success and whether functionality has successfully integrated into the Local Health Boards. 7.1 Membership Name Organisation Role Robert Bleasdale Cwm Taf University Health Board Senior Responsible Owner (Executive) Richard Cowell Betsi Cadwaladr University Health Board Senior User (Representative) Navroz Masani Cardiff & Vale University Health Board Senior User (Representative) Paul Das Betsi Cadwaladr University Health Board Senior User (Representative) Dave Tyler Cwm Taf University Health Board Senior User (Representative) James Barry ABM University Health Board Senior User (Representative) Tracey Hill Wales Cardiac Network Project Assurance Mike Ogonovsky Aneurin Bevan University Health Board Project Assurance Page 11 of 15

12 David Sheard NHS Wales Informatics Service Senior Supplier Robert Jones NHS Wales Informatics Service Senior Supplier Rebecca Cook NHS Wales Informatics Service Senior Supplier Michelle Cook NHS Wales Informatics Service Project Manager 7.2 Quorum The quorum of the Post Project Review meeting is defined as follows: Senior Responsible Owner; At least 2 Senior Users or agreed delegates 1 ; At least 2 Senior Suppliers or agreed delegates 1 ; Project Manager; At least 1 Project Assurance or agreed delegates; Project Support (for Notes). 7.3 Frequency of Meeting The initial meeting will take place after final project closure, following delivery of the reduced scope. Any benefits/objectives unable to be completed, an additional meeting can take place by agreement of Post Project Review members (by majority vote). 7.4 Reporting Arrangements The Post Project Review meeting provides a Report to the Heart Conditions Implementation Group and Welsh Clinical Informatics Council for review/comments. 7.5 Draft Agenda An example Agenda of the Post Project Review meeting is defined in Appendix A. 8 RECOMMENDATIONS NOTE the content of this report 9 REFERENCES Document Efficiency through technology application form September 2015 Version V ETTF NWIS Devt of Cardiology ereferrals Grant Award 1 Delegates are agreed by the Senior Responsible Owner Page 12 of 15

13 PID-AWACI-Project Initiation Document V GLOSSARY Term Electronic Requesting Electronic Reporting Welsh Clinical Communication Gateway (WCCG) Welsh Patient Administration System (WPAS) Welsh Clinical Portal (WCP) Welsh Patient Referral System (WPRS) Welsh Results Report Service (WRRS) Welsh Care Record Service (WCRS) Explanation A request to the Cardiac Service diagnostic department for a cardiac service investigation such as ambulatory monitoring or exercise testing. The transfer and storage of diagnostics and clinical letters to the Welsh Care Record Service and Welsh Result Report Service for visibility by authorised users of the Welsh Clinical Portal The Welsh Clinical Communication Gateway (WCCG) is a secure clinical messaging service and is used to send e-referrals between GP practices and hospitals. It is also used to send e-discharges from hospitals to GP practices. The Welsh Patient Administration System (WPAS) holds patient ID details, outpatient appointments, letters and notes. The WCP is a secure health space, uniting key patient information from the different computer systems and databases used in NHS Wales. It gives doctors and nurses a single immediate view of the important data needed to support vital clinical decisions and functionality for key tasks. The Portal s current functionality includes patient lists, electronic pathology test requesting and results viewing, and Radiology Reporting. WCP provides a patient record associated with all patients registered on the local Patient Administration System. The Welsh Patient Referral System (WPRS) refers to the combined systems and processes that make up a patient referral from a GP practice to a Hospital Consultant. The Service uses the Welsh Clinical Communications Gateway (WCCG) to make the referral in the GP practice, and then the Welsh Administration Portal (WAP) in the medical records department of a hospital receives the referral and matches it with patient details from the Welsh Patient Administration System (WPAS). The Welsh Clinical Portal (WCP) is used by the consultant to view the referrals for prioritisation The Welsh Results Report Service (WRRS) is a database which provides WCP users with the ability to view diagnostic reports and test requests for their patients. The Welsh Care Record Service (WCRS) is an electronic document repository which stores the many different clinical documents that make up a patients record. Page 13 of 15

14 Welsh Administration Portal (WAP) User Acceptance Testing (UAT) The Welsh Administration Portal (WAP) is used by medical and health records staff in hospitals. When the referral arrives at the hospital the administration portal is used to verify the patient s administration details, create a record on the hospital s Patient Administration System or to link the referral to an existing record on the PAS. If the Health Board is live with full WPRS (clinical prioritisation) the referral is then directed electronically to the relevant consultant. If the Health Board is not yet live with full WPRS including Clinical Prioritisation, this is known as WAP Lite. User acceptance testing (UAT) is the last phase of the software testing process. During UAT, actual software users test the software to make sure it can handle required tasks in real-world scenarios, according to specifications. UAT is one of the final and critical software project procedures that must occur before newly developed software is rolled out to the market. UAT is also known as beta testing, application testing or end user testing. Appendix A AG-PRG-AWACIPost Project Review Agen Appendix B Cardiac Service Request Hospital to Hospital Referral GEN-AWACI-Cardia c Diagnostic Reques PRS-AWACI Hospital to Hospital Page 14 of 15

15 Appendix C Health Board Readiness Table Organisation Welsh Clinical Communication Gateway WAP Full Clinical Prioritisation Welsh Patient Referral Service Primary Care Welsh Patient Referral Service Hospital to Hospital Patient Administration System Welsh Clinical Portal Software Clinical letters WCRS integration AB Yes No No No WPAS Pilot - v3.9.2 Convergence Plan Medsec Yes ABM Yes Yes East: Yes West: Apr 18 Pilot Jun 18 WPAS Pilot - v3.9.1 Convergence Plan Cellma DMS Yes C&V Yes Completed Pilot Jun 18 PMS v3.9.2 Generic Letters Yes HD Yes Yes May 18 No WPAS v3.9.2 Cellma WPAS Jun 18 CT Yes Completed Pilot Jun 18 WPAS v3.9.2 WPAS Apr 18 BCU Yes Spring 18 TBC No Mixed v East - epoc Central & West PiMS Yes No Powys Yes No No No WPAS v3.9.1 WCCG Referrals Yes Vel Yes No No No WPAS V3.9.2 Canisc No 2 Scheduled to receive release v3.9.2 of WCP on Page 15 of 15

NHS WALES INFORMATICS SERVICE DATA QUALITY STATUS REPORT ADMITTED PATIENT CARE DATA SET

NHS WALES INFORMATICS SERVICE DATA QUALITY STATUS REPORT ADMITTED PATIENT CARE DATA SET NHS WALES INFORMATICS SERVICE DATA QUALITY STATUS REPORT ADMITTED PATIENT CARE DATA SET Version: 1.0 Date: 1 st September 2016 Data Set Title Admitted Patient Care data set (APC ds) Sponsor Welsh Government

More information

Laboratory Information Management System (LIMS) Replacement

Laboratory Information Management System (LIMS) Replacement Laboratory Information Management System (LIMS) Replacement 1. Introduction The Health Board is to transition from its current LIMS to the new national LIMS in late March 2014. This is a significant change

More information

NHS WALES INFORMATICS MANAGEMENT BOARD

NHS WALES INFORMATICS MANAGEMENT BOARD NHS WALES INFORMATICS MANAGEMENT BOARD Draft minutes of part 1 of the meeting Wednesday 28 April 2016 14:00 15:00 Attendees: Andrew Goodall (AGD), Chair - Welsh Government Steve Ham (SH) - Velindre NHS

More information

NHS WALES INFORMATICS SERVICE DATA QUALITY STATUS REPORT ADMITTED PATIENT CARE DATA SET

NHS WALES INFORMATICS SERVICE DATA QUALITY STATUS REPORT ADMITTED PATIENT CARE DATA SET NHS WALES INFORMATICS SERVICE DATA QUALITY STATUS REPORT ADMITTED PATIENT CARE DATA SET Version: 1.0 Date: 17 th August 2017 Data Set Title Admitted Patient Care data set (APC ds) Sponsor Welsh Government

More information

Implementation of Quality Framework Update

Implementation of Quality Framework Update Joint Committee Meeting 26 January 2016 Title of the Committee Paper Framework Update Executive Lead: Director of Nursing & Quality Assurance Author: Director of Nursing & Quality Assurance Contact Details

More information

Continuing NHS Health Care Quarterly Update April 2015

Continuing NHS Health Care Quarterly Update April 2015 SUMMARY REPORT ABM University Health Board Subject Prepared by Approved by Continuing NHS Health Care Quarterly Update April 2015 Date of Meeting: 30 th July 2015 Agenda item: 7 (ii) Christine Williams

More information

Newsletter Spring 2017

Newsletter Spring 2017 Newsletter Spring 2017 Primary Care's important role in cancer services I m a GP, with a practice in Ebbw Vale and for the last few years I ve been involved with initiatives that look at the role of primary

More information

Title of the Health Board Report

Title of the Health Board Report AGENDA ITEM 3.2 Title of the Health Board Report IMPLEMENTING THE OUTCOME OF THE SOUTH WALES PROGRAMME THROUGH ACUTE CARE ALLIANCES AND DEVELOPMENT OF THE SOUTH WALES HEALTH COLLABORATIVE Executive Lead:

More information

AGENDA ITEM 17b Annex (i)

AGENDA ITEM 17b Annex (i) QUALITY AND PATIENT SAFETY COMMITTEE Minutes of the meeting held on 10 th April 2014 Welsh Health Specialised Services Committee Offices Unit 3a, Van Road Caerphilly Business Park Caerphilly CF83 3ED Present

More information

cc: Emergency Ambulance Services Committee Members EMERGENCY AMBULANCE SERVICES COMMITTEE ANNUAL GOVERNANCE STATEMENT 2015/16

cc: Emergency Ambulance Services Committee Members EMERGENCY AMBULANCE SERVICES COMMITTEE ANNUAL GOVERNANCE STATEMENT 2015/16 EASC Agenda Item 4.5 Appendix 1 To: Mrs Allison Williams, Chief Executive, Cwm Taf University Health Board cc: Emergency Ambulance Services Committee Members EMERGENCY AMBULANCE SERVICES COMMITTEE ANNUAL

More information

GOVERNANCE REVIEW. Contact Details for further information: Pam Wenger, Committee Secretary.

GOVERNANCE REVIEW. Contact Details for further information: Pam Wenger, Committee Secretary. Joint Committee Meeting 26 January 2016 Title of the Committee Paper GOVERNANCE REVIEW Executive Lead: Chair Author: Committee Secretary Contact Details for further information: Pam Wenger, Committee Secretary.

More information

WELSH HEALTH SPECIALISED SERVICES COMMITTEE ANNUAL GOVERNANCE STATEMENT 2014/15

WELSH HEALTH SPECIALISED SERVICES COMMITTEE ANNUAL GOVERNANCE STATEMENT 2014/15 Agenda Item 19b Annex (ii) To: Mrs Allison Williams, Chief Executive, Cwm Taf University Health Board cc: Joint Committee Members WELSH HEALTH SPECIALISED SERVICES COMMITTEE ANNUAL GOVERNANCE STATEMENT

More information

Follow-up Outpatient Appointments Summary of Local Audit Findings

Follow-up Outpatient Appointments Summary of Local Audit Findings May 2016 Archwilydd Cyffredinol Cymru Auditor General for Wales Follow-up Outpatient Appointments Summary of Local Audit Findings Briefing Paper for the NHS Wales Planned Care Programme Board I have prepared

More information

IMPLEMENTING THE OUTCOME OF THE SOUTH WALES PROGRAMME THROUGH ACUTE CARE ALLIANCES AND DEVELOPMENT OF THE SOUTH WALES HEALTH COLLABORATIVE

IMPLEMENTING THE OUTCOME OF THE SOUTH WALES PROGRAMME THROUGH ACUTE CARE ALLIANCES AND DEVELOPMENT OF THE SOUTH WALES HEALTH COLLABORATIVE AGENDA ITEM 3.3 9 September 2014 IMPLEMENTING THE OUTCOME OF THE SOUTH WALES PROGRAMME THROUGH ACUTE CARE ALLIANCES AND DEVELOPMENT OF THE SOUTH WALES HEALTH COLLABORATIVE Executive Lead: Chief Executive

More information

Agenda Item 3.3 IMPLEMENTATION OF SETTING THE DIRECTION - WHOLE SYSTEMS CHANGE PROGRESS UPDATE

Agenda Item 3.3 IMPLEMENTATION OF SETTING THE DIRECTION - WHOLE SYSTEMS CHANGE PROGRESS UPDATE FOR INFORMATION UHB Board Meeting: 17 January 2012 IMPLEMENTATION OF SETTING THE DIRECTION - WHOLE SYSTEMS CHANGE PROGRESS UPDATE Report of Paper prepared by Executive Summary Director of Public Health

More information

Corporate slide master. Frank Atherton Chief Medical Officer October 2017

Corporate slide master. Frank Atherton Chief Medical Officer October 2017 Corporate slide master Prudent With guidelines Healthcare for corporate presentations in Wales Frank Atherton Chief Medical Officer October 2017 communication CITIZENS National Assembly for Wales Welsh

More information

Clinical Coding Communication

Clinical Coding Communication CCC Ref. 2015/02 Date of Issue: 30th April 2015 Clinical Coding Communication Subject: Interpretation of NHS England Data Definitions for the Purposes of Clinical Classification Coding Introduction This

More information

A Review of the Impact of Private Practice on NHS Provision

A Review of the Impact of Private Practice on NHS Provision 11 February 2016 Archwilydd Cyffredinol Cymru Auditor General for Wales A Review of the Impact of Private Practice on NHS Provision I have prepared this report for presentation to the National Assembly

More information

CCIG(17)02 - Draft Minutes

CCIG(17)02 - Draft Minutes All Wales Critical Care Implementation Group Agenda Tuesday 6 th September 2016, 2.00-4.00pm Caerdydd 3, Welsh Government, Cathays Park, Cardiff VC dial 521971 from NHS Videoconferencing Network 1. Welcome

More information

1000 Lives Improvement

1000 Lives Improvement 1000 Lives Improvement 1000 Lives Improvement is the national quality improvement service for NHS Wales delivered by Public Health Wales. Our aim is to support the NHS to improve outcomes for people using

More information

National Imaging Programme Board Held on 19 th June 2013 At Programme Management Unit, Churchill House, Churchill Way, Cardiff

National Imaging Programme Board Held on 19 th June 2013 At Programme Management Unit, Churchill House, Churchill Way, Cardiff National Imaging Programme Board Held on 19 th June 2013 At Programme Management Unit, Churchill House, Churchill Way, Cardiff Present: Paul Roberts (PR) Chief Executive, Abertawe Bro Morgannwg UHB Claire

More information

VELINDRE NHS TRUST PUBLIC TRUST BOARD REPORT. Procurement Services. Andy Butler, Director of Finance, NWSSP

VELINDRE NHS TRUST PUBLIC TRUST BOARD REPORT. Procurement Services. Andy Butler, Director of Finance, NWSSP VELINDRE NHS TRUST PUBLIC TRUST BOARD REPORT Meeting Date: 24 th September 2015 Agenda Item: 2.5 Report Author: Executive Sponsor: Presented by: Matthew Perrott, Senior Category Manager, NWSSP Procurement

More information

THE PAPER IS ALIGNED TO THE DELIVERY OF THE FOLLOWING STRATEGIC OBJECTIVE(S) AND HEALTH AND CARE STANDARD(S):

THE PAPER IS ALIGNED TO THE DELIVERY OF THE FOLLOWING STRATEGIC OBJECTIVE(S) AND HEALTH AND CARE STANDARD(S): AGENDA ITEM: 4.1 MENTAL HEALTH AND LEARNING DISABILITIES COMMITTEE DATE OF MEETING: 29 JANUARY 2018 Subject : REPATRIATION PROJECT Approved and Alan Lawrie, Director of Primary and Community Presented

More information

106,717 people accessed mental health. 192,192 access A&E. 1,011,942 patient contacts with community staff. 2,245,439 patient contacts

106,717 people accessed mental health. 192,192 access A&E. 1,011,942 patient contacts with community staff. 2,245,439 patient contacts Employs 15,285 2,245,439 patient contacts 192,192 Assisted 91,360 Dispensed 13,598,605 prescription items** 38,107 1,011,942 patient contacts with Across 11 clusters, 540,850 people are registered with

More information

PATIENT ACCESS POLICY (ELECTIVE CARE) UHB 033 Version No: 1 Previous Trust / LHB Ref No: Senior Manager, Performance and Compliance.

PATIENT ACCESS POLICY (ELECTIVE CARE) UHB 033 Version No: 1 Previous Trust / LHB Ref No: Senior Manager, Performance and Compliance. Reference No: PATIENT ACCESS POLICY (ELECTIVE CARE) UHB 033 Version No: 1 Previous Trust / LHB Ref No: Trust 364 Documents to read alongside this Policy. Ministerial Letter EH/ML/004/09 WAG Rules for Managing

More information

Mental Health Act Committee - Deprivation of Liberty Safeguards, Recruitment of Best Interest Assessors in Health Boards in Wales

Mental Health Act Committee - Deprivation of Liberty Safeguards, Recruitment of Best Interest Assessors in Health Boards in Wales Betsi Cadwaladr University Health Board Mental Health Act Committee Meeting 15 July 2014 Item 14/029.2 Subject: Situation Mental Health Act Committee - Deprivation of Liberty Safeguards, Recruitment of

More information

NHS Wales Informatics Service

NHS Wales Informatics Service NHS Wales Informatics Service Annual Review Delivering information and technology for better patient care 3 FOREWORD It s a pleasure to be able to present to you a summary of our achievements during the

More information

Non-emergency patient transport: the picture across Wales

Non-emergency patient transport: the picture across Wales Non-emergency patient transport: the picture across Wales January 2018 0 P a g e Accessible formats If you would like this publication in an alternative format and/or language, please contact us. You can

More information

AGENDA ITEM: JANUARY 2018 MENTAL HEALTH SERVICE REPATRIATION: PROJECT CLOSURE. Subject :

AGENDA ITEM: JANUARY 2018 MENTAL HEALTH SERVICE REPATRIATION: PROJECT CLOSURE. Subject : AGENDA ITEM: 2.5 BOARD MEETING Subject : Approved and Presented by: Prepared by: Other Committees and meetings considered at: Considered by Executive Committee on: DATE OF MEETING: 31 JANUARY 2018 MENTAL

More information

Audit and Primary Care

Audit and Primary Care 10 th June 2013 Delivering Change through Clinical Audit & Quality Improvement Audit and Primary Care Primary Care Quality and Information Service Laura Jones, Primary Care Quality Team Lead Primary Care

More information

Agenda Item 5.1 Appendix 11 CWM TAF UNIVERSITY LOCAL HEALTH BOARD

Agenda Item 5.1 Appendix 11 CWM TAF UNIVERSITY LOCAL HEALTH BOARD CWM TAF UNIVERSITY LOCAL HEALTH BOARD MINUTES OF THE MEETING OF THE PRIMARY CARE COMMITTEE HELD ON 26 AUGUST 2015 AT YNYSMEURIG HOUSE, ABERCYNON PRESENT: Professor D Mead Mr J Palmer Mr G Bell Cllr C Jones

More information

Health Board Report INTEGRATED PERFORMANCE DASHBOARD

Health Board Report INTEGRATED PERFORMANCE DASHBOARD AGENDA ITEM 4.4 2 nd March 2016 Health Board Report INTEGRATED PERFORMANCE DASHBOARD Executive Lead: Director of Planning and Performance Author: Assistant Director of Performance and Information Contact

More information

ANEURIN BEVAN HEALTH BOARD CLINICAL FUTURES STRATEGY AND SPECIALIST CRITICAL CARE CENTRE: BRIEFING

ANEURIN BEVAN HEALTH BOARD CLINICAL FUTURES STRATEGY AND SPECIALIST CRITICAL CARE CENTRE: BRIEFING ANEURIN BEVAN HEALTH BOARD Aneurin Bevan Health Board CLINICAL FUTURES STRATEGY AND SPECIALIST CRITICAL CARE CENTRE: BRIEFING 1 PURPOSE The purpose of this paper to is to brief Board members on the proposed

More information

Transforming Welsh Ambulance Service: scrapping times, supporting patients!

Transforming Welsh Ambulance Service: scrapping times, supporting patients! Transforming Welsh Ambulance Service: scrapping times, supporting patients! Dr Brendan Lloyd Medical Director Welsh Ambulance Services Trust Founding Senior Fellow FMLM Dr John Kotter: Leading Change 8-stage

More information

Specialised Commissioning Oversight Group. Terms of Reference

Specialised Commissioning Oversight Group. Terms of Reference Specialised Commissioning Oversight Group Terms of Reference Specialised commissioning oversight group terms of reference 1 1.1 Purpose NHS England is responsible for commissioning specialised services

More information

ADULT MENTAL HEALTH NHS MANAGEMENT ARRANGEMENTS. To approve. This paper supports the standards

ADULT MENTAL HEALTH NHS MANAGEMENT ARRANGEMENTS. To approve. This paper supports the standards BOARD MEETING 25 FEBRUARY 2015 AGENDA ITEM 2.1 ADULT MENTAL HEALTH NHS MANAGEMENT ARRANGEMENTS Report of Paper prepared by Purpose of Paper Action/Decision required Link to Doing Well, Doing Better: Standards

More information

ABMU Health Board Research and Development Strategy

ABMU Health Board Research and Development Strategy Appendix 1 ABMU Health Board Research and Development Strategy 2015-18 Policy Owner: Medical Director Approved by: ABMU Health Board Issue Date: January 2015 Review Date: January 2016 1 Contents Section

More information

CAMHS/ED Network Steering Group Meeting. Tuesday 2 nd June 2015 WHSSC, Caerphilly. Specialist CAMHS Manager, Hywel Dda UHB

CAMHS/ED Network Steering Group Meeting. Tuesday 2 nd June 2015 WHSSC, Caerphilly. Specialist CAMHS Manager, Hywel Dda UHB CAMHS/ED Network Steering Group Meeting Tuesday 2 nd June 2015 WHSSC, Caerphilly Present: Carol Shillabeer (CHAIR) Glyn Jones (GJ) Carl Shortland (CSh) Daniel Phillips (DP) Jason Pollard (JP) Menna Jones

More information

POSITION STATEMENT ON THE FUTURE MODEL OF NEUROSCIENCES IN MID AND SOUTH WALES. Chief Executive

POSITION STATEMENT ON THE FUTURE MODEL OF NEUROSCIENCES IN MID AND SOUTH WALES. Chief Executive AGENDA ITEM 5.2 23 October 2009 POSITION STATEMENT ON THE FUTURE MODEL OF NEUROSCIENCES IN MID AND SOUTH WALES Report of Chief Executive Paper prepared by Purpose of Paper Action/Decision required Link

More information

Written Response by the Welsh Government to the report of the Health, Social Care and Sport Committee entitled Primary Care: Clusters

Written Response by the Welsh Government to the report of the Health, Social Care and Sport Committee entitled Primary Care: Clusters Written Response by the Welsh Government to the report of the Health, Social Care and Sport Committee entitled Primary Care: Clusters I am grateful to the Committee for its inquiry into primary care. Clusters

More information

PRIORITISATION AND DECISION MAKING FRAMEWORK

PRIORITISATION AND DECISION MAKING FRAMEWORK 1 PRIORITISATION AND DECISION MAKING FRAMEWORK Classification of Document: Executive Sponsors: Planning Framework Mr Mark Scriven, Executive Medical Director & Director of Clinical Services Mr Andrew Jones,

More information

Ruth Treharne RT Director Of Planning and Performance/Deputy Chief Executive Cwm Taf UHB. Minutes: (JF) Corporate Governance Officer, WHSSC

Ruth Treharne RT Director Of Planning and Performance/Deputy Chief Executive Cwm Taf UHB. Minutes: (JF) Corporate Governance Officer, WHSSC Minutes of the Welsh Health Specialised Services Committee Meeting of the Joint Committee held on, 9.30am at Health and Care Research, Castlebridge 4, Cowbridge Road East, Cardiff Members Present Ann Lloyd

More information

Prescribed Connections to NHS England

Prescribed Connections to NHS England Prescribed Connections to NHS England NHS England INFORMATION READER BOX Directorate Medical Commissioning Operations Patients and Information Nursing Trans. & Corp. Ops. Commissioning Strategy Finance

More information

All Wales Physician Associate Governance Framework

All Wales Physician Associate Governance Framework All Wales Physician Associate Governance Framework Physician Associate Task and Finish Group Membership Richard Quirke Deputy Medical Director Cwm Taf University Health Board Charlette Middlemiss Associate

More information

Vanguard Programme: Acute Care Collaboration Value Proposition

Vanguard Programme: Acute Care Collaboration Value Proposition Vanguard Programme: Acute Care Collaboration Value Proposition 2015-16 November 2015 Version: 1 30 November 2015 ACC Vanguard: Moorfields Eye Hospital Value Proposition 1 Contents Section Page Section

More information

Methods: Commissioning through Evaluation

Methods: Commissioning through Evaluation Methods: Commissioning through Evaluation NHS England INFORMATION READER BOX Directorate Medical Operations and Information Specialised Commissioning Nursing Trans. & Corp. Ops. Commissioning Strategy

More information

CT Scanner Replacement Nevill Hall Hospital Abergavenny. Business Justification

CT Scanner Replacement Nevill Hall Hospital Abergavenny. Business Justification CT Scanner Replacement Nevill Hall Hospital Abergavenny Business Justification Version No: 3 Issue Date: 9 July 2012 VERSION HISTORY Version Date Brief Summary of Change Owner s Name Issued Draft 21/06/12

More information

Committee is requested to action as follows: Richard Walker. Dylan Williams

Committee is requested to action as follows: Richard Walker. Dylan Williams BetsiCadwaladrUniversityHealthBoard Committee Paper 17.11.14 Item IG14_60 NameofCommittee: Subject: Summary or IssuesofSignificance StrategicTheme/Priority / Valuesaddressedbythispaper Information Governance

More information

Your local NHS and you

Your local NHS and you South Wales Programme Local Engagement Document Your local NHS and you Local NHS services in Cardiff and the Vale of Glamorgan are run by Cardiff and Vale University Health Board (UHB). The UHB is one

More information

All Wales Fundamentals of Care Audit

All Wales Fundamentals of Care Audit All Wales Fundamentals of Care Audit A summary of the NHS organisations compliance with the standards based on 2011 audit Author: Nursing Directorate, Welsh Government February 2012 i Digital ISBN 978

More information

Prescription for Rural Health 2011

Prescription for Rural Health 2011 Foreword Prescription for Rural Health is the Welsh NHS Confederation s contribution to the debate on health in rural Wales. This document has been published alongside Prescription for Health 2011, which

More information

Aneurin Bevan Health Board. Improving Theatre Performance

Aneurin Bevan Health Board. Improving Theatre Performance Aneurin Bevan Health Board Improving Theatre Performance 1 Introduction This report provides an overview on actions being taken to improve theatre performance within the Health Board. The report provides

More information

THE WORKFORCE THE BEST CONFIGURATION OF HOSPITAL SERVICES FOR WALES: A REVIEW OF THE EVIDENCE. Michael Ponton, Marcus Longley and Katie Norton

THE WORKFORCE THE BEST CONFIGURATION OF HOSPITAL SERVICES FOR WALES: A REVIEW OF THE EVIDENCE. Michael Ponton, Marcus Longley and Katie Norton THE BEST CONFIGURATION OF HOSPITAL SERVICES FOR WALES: A REVIEW OF THE EVIDENCE THE WORKFORCE Michael Ponton, Marcus Longley and Katie Norton with assistance from Amy Simpson and Susan Kimani Welsh Institute

More information

Health Board Report SOCIAL SERVICES AND WELL-BEING ACT (WALES) 2014: REVISED REGIONAL IMPLEMENTATION PLAN

Health Board Report SOCIAL SERVICES AND WELL-BEING ACT (WALES) 2014: REVISED REGIONAL IMPLEMENTATION PLAN Agenda Item 3.3 27 JANUARY 2016 Health Board Report SOCIAL SERVICES AND WELL-BEING ACT (WALES) 2014: REVISED REGIONAL IMPLEMENTATION PLAN Executive Lead: Director of Planning & Performance Author: Assistant

More information

MINUTES OF THE JOINT COMMITTEE MEETING HELD 7 JULY 2015 AT MEETING ROOM, BOWEL SCREENING WALES, LLANTRISANT

MINUTES OF THE JOINT COMMITTEE MEETING HELD 7 JULY 2015 AT MEETING ROOM, BOWEL SCREENING WALES, LLANTRISANT /~, GIG ~~/~~ CYMRU ~~#,..." NHS,~/ WALES Pwyllgor Gwasanaethau lechyd Arbenigol Cymru (PGIAC) Welsh Health Specialised Services Committee (WHSSC) MINUTES OF THE JOINT COMMITTEE MEETING HELD 7 JULY 2015

More information

WELSH RENAL CLINICAL NETWORK TERMS OF REFERENCE

WELSH RENAL CLINICAL NETWORK TERMS OF REFERENCE INTRODUCTION WELSH RENAL CLINICAL NETWORK TERMS OF REFERENCE In accordance with WHSSC Standing Order 3, the Joint Committee may and, where directed by the LHBs jointly or the Welsh Government must, appoint

More information

Powys Health Board Safety Closure Report

Powys Health Board Safety Closure Report Appendix 1 Powys Board Safety Closure Report Welsh Community Care Information System (WCCIS) Version 0.5 Jason Crowl RN.PGDip BSC(Hons) MSc Head of Nursing, project & Clinical Safety Officer Contents Content

More information

NHS DORSET CLINICAL COMMISSIONING GROUP GOVERNING BODY MEETING ADULT AND CHILDREN CONTINUING HEALTHCARE ANNUAL REPORT

NHS DORSET CLINICAL COMMISSIONING GROUP GOVERNING BODY MEETING ADULT AND CHILDREN CONTINUING HEALTHCARE ANNUAL REPORT 9.6 NHS DORSET CLINICAL COMMISSIONING GROUP GOVERNING BODY MEETING ADULT AND CHILDREN CONTINUING HEALTHCARE ANNUAL REPORT Date of the meeting 18/07/2018 Author Sponsoring Board member Purpose of Report

More information

Discharge Planning Cardiff and Vale University Health Board

Discharge Planning Cardiff and Vale University Health Board Discharge Planning Cardiff and Vale University Health Board Date issued: December 2017 Document reference: 166A2017-18 This document has been prepared as part of work performed in accordance with statutory

More information

STEP 1: STEP 2: STEP 3: STEP 4: STEP 5: Version: 1.0 Document Reference: 7716

STEP 1: STEP 2: STEP 3: STEP 4: STEP 5: Version: 1.0 Document Reference: 7716 Welsh Ambulance Services NHS Trust National Collaborative Commissioning: Quality and Delivery Framework Ambulance Quality Indicators: October - December 2017 STEP 1: STEP 2: STEP 3: STEP 4: STEP 5: AQI

More information

A meeting of NHS Bromley CCG Governing Body 25 May 2017

A meeting of NHS Bromley CCG Governing Body 25 May 2017 South East London Sector A meeting of NHS Bromley CCG Governing Body 25 May 2017 ENCLOSURE 4 SOUTH EAST LONDON 111 AND GP OUT OF HOURS MEMORANDUM OF UNDERSTANDING SUMMARY: The NHS England Commissioning

More information

CHAPTER TWO: WAITING LISTS AND BOOKING

CHAPTER TWO: WAITING LISTS AND BOOKING TWO: INTRODUCTION Managing waiting lists 2.1 Sometimes it seems that the NHS is primarily about waiting lists. Public perception focuses on waiting lists. Waiting lists provide media headlines. For those

More information

In this edition we will showcase the work of the development of a model for GP- Paediatric Hubs

In this edition we will showcase the work of the development of a model for GP- Paediatric Hubs Focusing on the principle of home first and designing the Perfect Locality from the lens of the community Issue 7 June 2017 Welcome to the seventh issue of Our Future Wellbeing, a regular update on the

More information

Aneurin Bevan Health Board. Living Well, Living Longer: Inverse Care Law Programme

Aneurin Bevan Health Board. Living Well, Living Longer: Inverse Care Law Programme Aneurin Bevan Health Board Living Well, Living Longer: Inverse Care Law Programme 1 Introduction The purpose of this paper is to seek the Board s agreement to a set of priority statements for an Inverse

More information

Redesigning the Acute Coronary Syndrome (NSTE- ACS) pathway at Morriston Cardiac Centre - The case for change

Redesigning the Acute Coronary Syndrome (NSTE- ACS) pathway at Morriston Cardiac Centre - The case for change Redesigning the Acute Coronary Syndrome (NSTE- ACS) pathway at Morriston Cardiac Centre - The case for change 4 th July 2012 Dr D Smith & Dr S Dorman Introduction... 2 NSTE-ACS Where are we now?... 2 NSTE-ACS

More information

EXECUTIVE SUMMARY REPORT TO THE BOARD OF DIRECTORS HELD ON 22 MAY Anne Gibbs, Director of Strategy & Planning

EXECUTIVE SUMMARY REPORT TO THE BOARD OF DIRECTORS HELD ON 22 MAY Anne Gibbs, Director of Strategy & Planning EXECUTIVE SUMMARY D REPORT TO THE BOARD OF DIRECTORS HELD ON 22 MAY 2018 Subject Supporting TEG Member Author Status 1 A review of progress against Corporate Objectives 2017/18 and planned Corporate Objectives

More information

Referral Management & Prior Approval Policy & Procedure For Services Outside of Hywel Dda University Health Board

Referral Management & Prior Approval Policy & Procedure For Services Outside of Hywel Dda University Health Board Referral Management & Prior Approval Policy & Procedure For Services Outside of Hywel Dda University Health Board Policy Number: 019 Supercedes: Previous versions Standards For Healthcare Services No/s

More information

REPORT OF THE SOUTH WALES PROGRAMME BOARD TO HEALTH BOARDS/WAST JANUARY 2014

REPORT OF THE SOUTH WALES PROGRAMME BOARD TO HEALTH BOARDS/WAST JANUARY 2014 REPORT OF THE SOUTH WALES PROGRAMME BOARD TO HEALTH BOARDS/WAST JANUARY 2014 SOUTH WALES PROGRAMME BOARD RECOMMENDATIONS FOR THE FUTURE CONFIGURATION OF CONSULTANT- LED MATERNITY AND NEONATAL CARE, INPATIENT

More information

Consultation Paper. Distributed Medical Imaging in the new Royal Adelaide Hospital Central Adelaide Local Health Network

Consultation Paper. Distributed Medical Imaging in the new Royal Adelaide Hospital Central Adelaide Local Health Network Consultation Paper Distributed Medical Imaging in the new Royal Adelaide Hospital Central Adelaide Local Health Network Issued: April 2016 TABLE OF CONTENTS TABLE OF CONTENTS 2 1. INTRODUCTION 3 2. PURPOSE

More information

Mental Health (Wales) Measure Implementing the Mental Health (Wales) Measure Guidance for Local Health Boards and Local Authorities

Mental Health (Wales) Measure Implementing the Mental Health (Wales) Measure Guidance for Local Health Boards and Local Authorities Mental Health (Wales) Measure 2010 Implementing the Mental Health (Wales) Measure 2010 Guidance for Local Health Boards and Local Authorities Januar y 2011 Crown copyright 2011 WAG 10-11316 F6651011 Implementing

More information

PEER REVIEW VISIT REPORT (MULTI-DISCIPLINARY TEAM)

PEER REVIEW VISIT REPORT (MULTI-DISCIPLINARY TEAM) PEER REVIEW VISIT REPORT (MULTI-DISCIPLINARY TEAM) Network Organisation Team YHSCN HULL AND EAST YORKSHIRE HOSPITALS Hull And East Yorkshire Hospitals Haematology MDT (13-2H-1) - 2015 Peer Review Visit

More information

Review of Emergency Ambulance Services Commissioning Arrangements

Review of Emergency Ambulance Services Commissioning Arrangements Review of Emergency Ambulance Services Commissioning Arrangements Date issued: July 2017 Document reference: 261A2017 Status of report I have prepared and published this report under section 61 of the

More information

Physiotherapy outpatient services survey 2012

Physiotherapy outpatient services survey 2012 14 Bedford Row, London WC1R 4ED Tel +44 (0)20 7306 6666 Web www.csp.org.uk Physiotherapy outpatient services survey 2012 reference PD103 issuing function Practice and Development date of issue March 2013

More information

Appendix 1: Integrated Urgent Care Service Update. 1. Purpose

Appendix 1: Integrated Urgent Care Service Update. 1. Purpose Appendix 1: Integrated Urgent Care Service Update 1. Purpose The purpose of this paper is to provide Governing Body members across the collaborative CCGs with an update on the progress of the Integrated

More information

WALES ACCORD FOR SHARING PERSONAL INFORMATION (WASPI): UPDATE. Mandy Collins, Board Secretary. Carol Phillips, Information Governance Manager None

WALES ACCORD FOR SHARING PERSONAL INFORMATION (WASPI): UPDATE. Mandy Collins, Board Secretary. Carol Phillips, Information Governance Manager None Agenda item: 3.2 INFORMATION MANAGEMENT, TECHNOLOGY & GOVERNANCE COMMITTEE Date of Meeting: Subject: Approved and Presented by: Prepared by: Other Committees and meetings considered at: Considered by Executive

More information

Health Board Report INTEGRATED PERFORMANCE DASHBOARD

Health Board Report INTEGRATED PERFORMANCE DASHBOARD AGENDA ITEM 4.2 27 th January 2016 Health Board Report INTEGRATED PERFORMANCE DASHBOARD Executive Lead: Director of Planning and Performance Author: Assistant Director of Performance and Information Contact

More information

Associate Medical Director Primary Care NHS Wales Informatics Service. Applicant Information Pack

Associate Medical Director Primary Care NHS Wales Informatics Service. Applicant Information Pack Associate Medical Director Primary Care NHS Wales Informatics Service Applicant Information Pack April 2016 1 Welcome Dear Candidate Thank you for your interest in the role of Associate Medical Director

More information

Summarise the Impact of the Health Board Report Equality and diversity

Summarise the Impact of the Health Board Report Equality and diversity AGENDA ITEM 4.1 Health Board Report INTEGRATED PERFORMANCE DASHBOARD Executive Lead: Director of Planning and Performance Author: Assistant Director of Performance and Information Contact Details for further

More information

Discharge Planning Powys Teaching Health Board

Discharge Planning Powys Teaching Health Board Discharge Planning Powys Teaching Health Board Date issued: November 2017 Document reference: 147A2017-18 This document has been prepared as part of work performed in accordance with statutory functions.

More information

5. Does this paper provide evidence of assurance against the Governing Body Assurance Framework?

5. Does this paper provide evidence of assurance against the Governing Body Assurance Framework? Item Number: 6.3 Governing Body Meeting: 4 February 2016 Report Sponsor Anthony Fitzgerald Director of Strategy and Delivery Report Author Anthony Fitzgerald Director of Strategy and Delivery 1. Title

More information

Quality Assurance Framework. Powys thb provided and commissioned services Quality and Safety Committee November 2013

Quality Assurance Framework. Powys thb provided and commissioned services Quality and Safety Committee November 2013 Quality Assurance Framework Powys thb provided and commissioned services Quality and Safety Committee November 2013 1 Background Together for Health vision for NHS Wales 6 domains of quality Effectiveness

More information

Clinical Commissioning Group Governing Body Paper Summary Sheet For: PUBLIC session PRIVATE session. Date of Meeting: 24 March 2015

Clinical Commissioning Group Governing Body Paper Summary Sheet For: PUBLIC session PRIVATE session. Date of Meeting: 24 March 2015 Clinical Commissioning Group Governing Body Paper Summary Sheet For: PUBLIC session PRIVATE session Date of Meeting: 24 March 205 For: Decision Discussion Noting Agenda Item and title: Author: GOV/5/03/20

More information

GUIDANCE NOTES, PROCESS & APPLICATION FORM FOR FOUNDATION YEAR 1 APPLICANTS WITH SPECIAL CIRCUMSTANCES MATCHING TO LOCATION AND PROGRAMME 2018/19

GUIDANCE NOTES, PROCESS & APPLICATION FORM FOR FOUNDATION YEAR 1 APPLICANTS WITH SPECIAL CIRCUMSTANCES MATCHING TO LOCATION AND PROGRAMME 2018/19 This document describes the allocation process for Foundation Year 1 applicants with special circumstances, once they have been allocated to the Wales Foundation School. The national process for allocating

More information

REFERRAL TO TREATMENT ACCESS POLICY

REFERRAL TO TREATMENT ACCESS POLICY Directorate of Strategy & Planning REFERRAL TO TREATMENT ACCESS POLICY Reference: DCP175 Version: 7.0 This version issued: 17/12/15 Result of last review: Major changes Date approved by owner (if applicable):

More information

Welsh Language Standards (Health Sector) Regulations

Welsh Language Standards (Health Sector) Regulations Number: WG28986 Welsh Government Consultation Document Welsh Language Standards (Health Sector) Regulations Improving services for Welsh speakers Date of issue: 14 July 2016 Action required: Responses

More information

Minor Oral Surgery Service Reconfiguration

Minor Oral Surgery Service Reconfiguration Minor Oral Surgery Service Reconfiguration 1 Introduction The purpose of this report is to inform the Board on the status of the Minor Oral Surgery Service Reconfiguration programme and request approval

More information

From left; Dave Richley (speaker), Dr Chris Eggett (speaker), Emma Rees (conference chair), Lynda McGurk (speaker)

From left; Dave Richley (speaker), Dr Chris Eggett (speaker), Emma Rees (conference chair), Lynda McGurk (speaker) Thursday, 29 th March 2012 heralded a new development for cardiac physiologists in Wales. The inaugural conference of Cardiac Physiology Cymru was hosted by Swansea University s College of Human and Health

More information

MORTALITY OF POWYS CITIZENS. Medical Director. This paper supports:

MORTALITY OF POWYS CITIZENS. Medical Director. This paper supports: MORTALITY OF POWYS CITIZENS QUALITY & SAFETY COMMITTEE 05 MAY 2016 AGENDA ITEM 2.2 Report of Medical Director Paper prepared by Safety & Quality Improvement Manager Purpose of Paper Action/Decision required

More information

Appendix 10a SBAR REPORT MARCH 2010 FREE TO LEAD FREE TO CARE, EMPOWERING WARD SISTER / CHARGE NURSE SITUATION

Appendix 10a SBAR REPORT MARCH 2010 FREE TO LEAD FREE TO CARE, EMPOWERING WARD SISTER / CHARGE NURSE SITUATION SBAR REPORT MARCH 2010 FREE TO LEAD FREE TO CARE, EMPOWERING WARD SISTER / CHARGE NURSE SITUATION The purpose of this report is to inform the Board members of the current position and progress of Cwm Taf

More information

Review of Management Arrangements within the Microbiology Division Public Health Wales NHS Trust. Issued: December 2013 Document reference: 653A2013

Review of Management Arrangements within the Microbiology Division Public Health Wales NHS Trust. Issued: December 2013 Document reference: 653A2013 Review of Management Arrangements within the Microbiology Division Public Health Issued: December 2013 Document reference: 653A2013 Status of report This document has been prepared for the internal use

More information

18 Weeks Referral to Treatment Guidance (Access Policy)

18 Weeks Referral to Treatment Guidance (Access Policy) 18 Weeks Referral to Treatment Guidance (Access Policy) CATEGORY: Guidelines CLASSIFICATION: Clinical PURPOSE: To provide guidance on the management of the 18 week referral to treatment pathway Controlled

More information

O Connell et al. Pilot and Feasibility Studies (2018) 4:90

O Connell et al. Pilot and Feasibility Studies (2018) 4:90 O Connell et al. Pilot and Feasibility Studies (2018) 4:90 https://doi.org/10.1186/s40814-018-0282-8 METHODOLOGY Open Access Requirements for the collection of electronic PROMS either in clinic or at home

More information

The Welsh NHS Confederation response to the Health, Social Care and Sport Committee Inquiry into winter preparedness 2016/17.

The Welsh NHS Confederation response to the Health, Social Care and Sport Committee Inquiry into winter preparedness 2016/17. Contact: The Welsh NHS Confederation response to the Health, Social Care and Sport Committee Inquiry into winter preparedness 2016/17. Date: 8 September 2016 Nesta Lloyd Jones, Policy and Public Affairs

More information

Introduction to GRIP Governance for Railway Investment Projects

Introduction to GRIP Governance for Railway Investment Projects Introduction to GRIP Governance for Railway Investment Projects Document Ref Status Document Owner Date Published GRIP/Intro DRAFT Mike Wright Introduction Network Rail operates in a complex environment

More information

EMERGENCY PRESSURES ESCALATION PROCEDURES

EMERGENCY PRESSURES ESCALATION PROCEDURES OP48 EMERGENCY PRESSURES ESCALATION PROCEDURES INITIATED BY: Director of Therapies & Health Sciences / Chief Operating Officer APPROVED BY: Executive Board DATE APPROVED: 21 September 2016 VERSION: 3 OPERATIONAL

More information

Stakeholder Mapping Analysis Exercise for Hywel Dda Our Big NHS Change

Stakeholder Mapping Analysis Exercise for Hywel Dda Our Big NHS Change Influence Stakeholder Mapping Analysis Exercise for Hywel Dda Our Big NHS Change 50+ Forums Advisory Groups (Stakeholder Reference Group, Health Professionals Forum, Partnership Forum) Affected staff(wider

More information

Obstetric, Maternity and Gynaecology Services

Obstetric, Maternity and Gynaecology Services Action Plan Arising from RCPCH Evaluation Recommendation Obstetric, Maternity and Gynaecology Services Strategy and Patient safety 1 Expedite the Phase Two business case and commence development to provide

More information

Delivering the Five Year Forward View Personalised Health and Care 2020

Delivering the Five Year Forward View Personalised Health and Care 2020 Paper Ref: NIB 0607-006 Delivering the Five Year Forward View Personalised Health and Care 2020 INTRODUCTION The Five Year Forward View set out a clear direction for the NHS showing why change is needed

More information

Cardiff & Vale of Glamorgan CHC Members Monitoring Visit Cardiff North Renal Unit 7 th November 2012

Cardiff & Vale of Glamorgan CHC Members Monitoring Visit Cardiff North Renal Unit 7 th November 2012 Cardiff & Vale of Glamorgan CHC Members Monitoring Visit Cardiff North Renal Unit 7 th November 2012 Cyngor Iechyd Cymuned Caerdydd a Bro Morgannwg Tydydd Llawr Tŷ r Parc, Heol Y Brodyr Llwydion CAERDYDD

More information

Implementing Carecast: The UCLH Experience. Kevin Jarrold Director of Information Management & EPR Project Director

Implementing Carecast: The UCLH Experience. Kevin Jarrold Director of Information Management & EPR Project Director Implementing Carecast: The UCLH Experience Kevin Jarrold Director of Information Management & EPR Project Director Issues to Address Communications and getting staff on-board The effect of having a new

More information