1 Redesigning the Acute Coronary Syndrome (NSTE- ACS) pathway at Morriston Cardiac Centre - The case for change 4 th July 2012 Dr D Smith & Dr S Dorman Introduction... 2 NSTE-ACS Where are we now?... 2 NSTE-ACS - Proposed future model of care... 6 How do we get there?... 8 The case for change Immediate action required Conclusion... 11

2 Introduction In a recent report by the Office of National Statistics Ischaemic heart disease was recognised to be the biggest cause of avoidable death in England & Wales as a whole. The report goes on to highlight that in 2010 whilst the age-standardised avoidable mortality rate for England was per 100,000 population, the rate of avoidable mortality in Wales was significant higher at Contemporary management of Acute Coronary Syndromes is a key component in reducing this avoidable mortality and inequity of access to timely revascularisation in Wales remains a major factor accounting for this. The situation is particulary acute in Mid & West Wales where patient s will currently wait an average of 7 days before they can be transferred to the Morriston Cardiac Centre to undergo angiography and revascularisation. Whilst the introduction of a 24/7 region wide Primary PCI service has transformed the care of patient s with ST elevation myocardial infarction( STEMI), these only represent one third of patient s with Acute Coronary Syndromes. The Non ST elevation Acute Coronary Syndromes ( NSTE-ACS) represent the majority of patient s and the quality of care that this patient group currently receives in Mid & West Wales is sub standard by all international comparisons. NSTE-ACS does not carry the same high initial risk of adverse events (such as death, stroke or recurrent heart attack) as STEMI, but contrary to popular belief, it does carry the same long term risk for adverse events if optimum treatment is not carried out urgently within a 96 hour time frame from initial admission to hospital (NICE recommended treatment time target). Therefore our current heart attack service is optimal for only the minority of our heart attack patients, with the majority of patients with NSTE-ACS having sub-optimal treatment with the greater likelihood of consequent adverse outcomes. This paper makes the case for structural changes to our historic model of care for patients with NSTE-ACS in order to transform the quality of care delivered to this patient group. As a by product it is likely that significant savings will be realised at a health board level because of the inherent inefficiencies of the current model of care. NSTE-ACS Where are we now? Current model of care in Mid & West Wales Morriston Cardiac Centre serves a secondary and tertiary catchment population of just under 1 million people. As well as the local Swansea population this results in over 800 referrals from surrounding hospital for patient s with NSTE-ACS per year.

3 A patient will typically be risk stratified in the referring hospital using the GRACE scoring system and then electronically referred after a minimum of 24 hours. The GRACE scoring system is the preferred tool recommended by NICE & 1000 lives plus for patient risk stratification.

4 If the patient is admitted to the referring hospital at the weekend they will frequently not be referred until the Monday ward round.

5 Equally at the current time, whilst we provide a 24/7/365 PPCI service for STEMI patients, we do not provide angiography and angioplasty at the weekend for NSTE-ACS. Therefore if an NSTE-ACS patient arrives in Morriston after 5pm on a Friday they will not receive angiography until Monday 9am at the earliest (a gap of 65 hours). Once the patient has been electronically referred there is an average wait of 6.8 days in the referring hospital before the patient can be transferred to Morriston hospital. There is no clinical utility in this waiting period and it is positively detrimental clinically, economically and socially. A complex set of reasons underpins the inability to transfer patient s more quickly. The principal determinants are however insufficient Catheter lab capacity, local bed pressures at Morriston, and limitations of Ambulance transport outside of normal working hours. Morriston Cardiac Centre has not expanded it s Cath lab capacity since 2005 despite increasing demands on the service from complex coronary intervention, electrophysiological procedures and most recent structural interventions such as TAVI. In addition bed pressures from the acute medical take, infection control outbreaks, long surgical waiters provide added complexity in physically accommodating these patients. Once patient s do undergo angiography + PCI they will usually go home either that evening or the next day, with the exception of patient s requiring surgical revascularisation. Within the Cardiac centre we have a dedicated team of Cardiac Nurse practitioners who have historically supported the transfer process. There are however competing demands on their time and they are not currently able to devote sufficient time to streamlining the transfer arrangements.

6 The delays within the NSTE-ACS transfer system are now so profound that the annual UK audit of PCI by the British Cardiovascular Intervention Society (BCIS) identifies Morriston as being one of the worst performing units in the country in this respect. NSTE-ACS - Proposed future model of care Evidence based management of NSTE-ACS There is currently a wealth of evidence based guidelines from which to choose for the contemporary management of NSTE-ACS patients. There include the European society of Cardiology guidelines 2011, NICE guidelines (CG94) and 1000 lives plus ACS guidelines. All of these guidelines contain common themes and advocate safe, effective, patient centred care. Essentially NSTE-ACS patient s require early diagnosis, appropriate pharmacotherapy and risk stratification to assess the likelihood of future cardiac events. Those found to be at medium to high risk of events need to be referred for coronary angiography with a view to either: continued medical therapy (drugs), coronary angioplasty or coronary bypass surgery, depending on the results of angiography and other clinical findings. This whole process needs to take place ideally within 48 hours (European guidance) or at least within 96 hours (NICE guidance).

7 The 2010 NICE algorithm for the management of NSTE-ACS patients is provided below. Whilst this business case discusses NSTE-ACS inter hospital transfers which represent 70% of the total interhospital transfer work it must be recognised that there are equally important issues concerning the long inter hospital transfer times for Non ACS patients. In particular patients awaiting permanent pacemaker implantation and treatment for endocarditis are undoubtedly receiving an inferior service and any solution to the inter hospital transfer issues should try to accommodate this equally important patient group who are currently waiting an average of 9.2 days. It has been quoted by the ABM health board executive that our Heart attack service would bear comparison to any service worldwide. This only applies to the minority of heart attack patients which present as ST elevation MI, our current service to NSTE-ACS patients is amongst the worst in the UK.

8 How do we get there? The principal issue for providing safe, effective, patient centred care for our NSTE-ACS cohort is to improve the currently unacceptable transfer times. The essential requirement is to provide the right care for the NSTE-ACS patient at the right time in the right place. This will undoubtedly necessitate changes to current working practices which have historically been organised around a pattern of Monday to Friday, 9-5 working. How do we improve transfer times? Timely transfer of patient s with NSTE-ACS is dependent on a number of key variables, and requires that the service has the potential to operate 24/7 365 days a year. The key variables are: Early recognition & prompt referral from surrounding hospitals Bed availability at Morriston Cardiac Centre to receive the patients Ambulance availability to facilitate patient transfer A trained Cath lab team & Cath lab capacity to perform angiography + intervention Flexing capacity to deal with the significant variations in weekly referrals Volume of Primary PCI workload Only when deficiencies in all variables are correctly identified and treated and the service is reorganised around a 7 day working week will significant improvements be made. The dependencies are now discussed in more detail. Early recognition & prompt referral Early recognition is highly dependent on the skill mix and availability of staff in referring units. In an ideal world all NSTE-ACS patient s would be seen and risk stratified by a Consultant Cardiologist within 24 hours of admission. This is a stated requisite of the Welsh National Service Framework for Cardiovascular disease. This is not however currently practical in many referring units within Mid & West Wales and so novel solutions will be required involving the use of Cardiac nurse practitioners, automated scoring systems and early discussion with the Cardiac Centre. The Cardiac network is currently facilitating this piece of work.

9 Bed availability at Morriston Cardiac Centre Availability of limited beds in the cardiac centre is heavily dependent on a number of factors Ward closures due to D& V & Norovirus outbreaks Acute medical bed pressures Upskilling of medical & nursing staff on Ward R Delays in repatriation Cardiac surgical workload and CITU bed availability Bed management policy & practical thereof In practice it is often the case that when there are hospital wide bed pressures the first group of patients to suffer are the cardiac interhospital transfers. This is in part related to the current bed management arrangements and the natural tendency to prioritise the patient who is in front of you. There have already been 2 cases of cardiac patients who appear to have died whilst awaiting transfer and it is no longer acceptable for the bed management arrangements to remain as they do currently Ambulance transfer Ambulance transfer arrangements are complicated and have been extensively reviewed previously. The dependencies include the funding arrangements for the Jumbulance, the ability to use 999 ambulances when needed, and the ability to access private ambulances. The large travel times to hospitals in West Wales have a particularly profound impact on capacity. Cath lab capacity Morriston Cardiac Centre is currently failing to operate a region wide emergency ACS revascularisation service, elective revascularisation & EP service and a structural heart disease service for a population of around 1 million from 2 Catheter laboratories and 1 pacing room. It is not uncommon for a UK district general hospital to have similar facilities for half the size of population with no EP or structural heart disease service. It is abundantly clear that currently Cath lab capacity is a major limiting factor in meeting contemporary ACS revascularisation targets. In the long term there will need to be a significant expansion in the Cardiac Centre however realistically in the short term extended hours of operation of the existing Cath labs or a mobile facility are likely to be most appropriate. Flexing capacity

10 Whilst the average number of ACS & General Cardiology referrals is around 16 per week, there is significant weekly variation from 6 to 25 referrals. This poses logistical challenges and mandates a degree of flexibility to match demand and capacity. Volume of Primary PCI workload There is significant variation in this areas which affects not only bed capacity within the Cardiac Centre but also the capcity of the on call interventional team to perform additional out of hours revascularisation workload The case for change Continuing with the status quo is unacceptable on clinical, economic and social grounds. Whilst the current system undoubtedly is delivering inferior clinical outcomes it is also highly expensive in terms of wasted bed days and the social cost to the patient of inappropriately long hospital stays. If we were to achieve a 48 hour transfer window for all cardiac inter hospital transfers this would save ABMU and Hywel Dda health boards around 4000 bed days recurrently per annum with an estimated financial savings of over 1 million.

11 Immediate action required Preliminary analysis has suggested that the most significant deficiencies in the system are currently the Cath lab capacity and ensuring a transfer bed is available. A composite of different solutions is likely to be required including but not limited to: 7 day working week system for the Cath lab team Extended opening hours of Cardiac Short stay Up skilling and appropriate resourcing of nursing & medical staff on Ward R Greater autonomy in bed management of Ward R Use of a mobile Catheter lab system Ringfencing of prioritised Inter hospital transfer beds Greater nurse practitioner involvement in co-ordinating transfers Due to the complex and dynamic interdependencies described previously we strongly advocate a move away from the traditional pattern of 9-5 service provision. In order to fine tune the exact operational requirements we would propose a 6 month pilot of extended Cath lab working including evening and weekend sessions. This mandates a change in the health board s approach to bed management to one that prioritises cardiac inter hospital transfers. By doing this we are more likely to realise greater bed efficiencies across the whole of this health board as well as Hywel Dda. Conclusion Cardiac disease remains the biggest killer in Wales and a significant proportion of this is avoidable. The current model of service provision for the majority of heart attacks in Mid & West Wales is inequitable, clinically outdated and financially unsustainable in the current climate. Whilst we have made successful progress with Primary PCI in treating ST elevation myocardial infarction, NSTE-ACS remains the elephant in the room in attempting to provide contemporary management of Acute Coronary Syndromes. Delays in inter hospital transfers remain the single biggest failing of the system

12 and pose an ongoing and ever present clinical risk to patient s and the health board. The financial, emotional and social cost of the current system cannot be allowed to continue any longer. We strongly advocate a long term structural solution which will involve increasing Cardiac Centre capacity allied to 7 day working. However an immediate interim solution is required that increases Cath lab capacity in conjunction with increased bed availability for inter hospital transfers. It should be recognised that such an interim solution may be necessary for the next couple of years until sufficient additional capital infrastructure has been realised. Succesful implementation of this enhanced service will be of undisputed benefit to patients but also has the potential to save over 4000 bed days recurrently per annum across ABMU & Hywel Dda health boards.

March 28, 2018 For Decision Board of Directors Item 9.0 Comprehensive Regional Cardiac Program Plan

March 28, 2018 For Decision Board of Directors Item 9.0 Comprehensive Regional Cardiac Program Plan BRIEFING NOTE March 28, 2018 For Decision Board of Directors Item 9.0 Comprehensive Regional Cardiac Program Plan PURPOSE To provide the WWLHIN Board of Directors with a recommendation to endorse the proposed

More information

The PCT Guide to Applying the 10 High Impact Changes

The PCT Guide to Applying the 10 High Impact Changes The PCT Guide to Applying the 10 High Impact Changes This Guide has been produced by the NHS Modernisation Agency. For further information on the Agency or the 10 High Impact Changes please visit www.modern.nhs.uk

More information

Acceleration for ACS. NSTEMI Event 09 November. Outputs from Table Discussions

Acceleration for ACS. NSTEMI Event 09 November. Outputs from Table Discussions Acceleration for ACS NSTEMI Event 09 November Outputs from Table Discussions 1 1. What mechanism do we need to have to identify patients early (within 6 hours of admission to hospital)? Have identification

More information

Background Paper For the Cardiology Audit and Registration Data Standards (CARDS) Conference during Ireland s Presidency of the European Union

Background Paper For the Cardiology Audit and Registration Data Standards (CARDS) Conference during Ireland s Presidency of the European Union Background Paper For the Cardiology Audit and Registration Data Standards (CARDS) Conference during Ireland s Presidency of the European Union Executive Summary The Minister for Health and Children aims

More information

Home administration of intravenous diuretics to heart failure patients:

Home administration of intravenous diuretics to heart failure patients: Quality and Productivity: Proposed Case Study Home administration of intravenous diuretics to heart failure patients: Increasing productivity and improving quality of care Provided by: British Heart Foundation

More information

Acute myocardial infarction: Tracking patients journeys and outcomes in a complex, acute healthcare system

Acute myocardial infarction: Tracking patients journeys and outcomes in a complex, acute healthcare system Acute myocardial infarction: Tracking patients journeys and outcomes in a complex, acute healthcare system NHS Greater Glasgow and Clyde, Golden Jubilee National Hospital, University of Glasgow, DataLab

More information

Ambulance Operations Procedure Appropriate Hospital Access for ST Elevation Myocardial Infarction Patients. National Ambulance Service (NAS)

Ambulance Operations Procedure Appropriate Hospital Access for ST Elevation Myocardial Infarction Patients. National Ambulance Service (NAS) Ambulance Operations Procedure Appropriate Hospital Access for ST Elevation Myocardial Infarction Patients National Ambulance Service (NAS) Document reference number Revision number Approval date NASCG017

More information

Intermediate Coronary Care Unit Rotation

Intermediate Coronary Care Unit Rotation 1 Intermediate Coronary Care Unit Rotation Section of Cardiology Dartmouth-Hitchcock Medical Center (2008-2009) I. Overview of Rotation The cardiology-specific critical care experience is in the Intermediate

More information

CWM TAF LOCAL HEALTH BOARD

CWM TAF LOCAL HEALTH BOARD CWM TAF LOCAL HEALTH BOARD TOGETHER FOR HEALTH - A HEART DISEASE DELIVERY PLAN A DELIVERY PLAN UP TO 2016 FOR CWM TAF LHB AND ITS PARTNERS DECEMBER 2013 Page 1 of 24 1. BACKGROUND AND CONTEXT Together

More information

Specialised Services Service Specification. Adult Congenital Heart Disease

Specialised Services Service Specification. Adult Congenital Heart Disease Specialised Services Service Specification Adult Congenital Heart Disease Document Author: Executive Lead: Approved by: Issue Date: Review Date: Document No: Specialised Planner Director of Planning Insert

More information

The PCT Guide to Applying the 10 High Impact Changes. A guide from NatPaCT

The PCT Guide to Applying the 10 High Impact Changes. A guide from NatPaCT The PCT Guide to Applying the 10 High Impact Changes A guide from NatPaCT DH INFORMATION READER BOX Policy HR/Workforce Management Planning Clinical Estates Performance IM&T Finance Partnership Working

More information

EP15: Describe and demonstrate interdisciplinary collaboration using continuous quality and process improvement.

EP15: Describe and demonstrate interdisciplinary collaboration using continuous quality and process improvement. 1 EP15: Describe and demonstrate interdisciplinary collaboration using continuous quality and process improvement. Interdisciplinary collaboration is an essential component of Riverside Medical Center

More information

Salisbury NHS Foundation Trust Individual Placement (Job) Descriptions for Foundation Year 1

Salisbury NHS Foundation Trust Individual Placement (Job) Descriptions for Foundation Year 1 Salisbury NHS Foundation Trust Individual Placement (Job) Descriptions for Foundation Year 1 Placement The department The type of work to expect and learning opportunities F1 Cardiology The Department

More information

SIMPLE SOLUTIONS. BIG IMPACT.

SIMPLE SOLUTIONS. BIG IMPACT. SIMPLE SOLUTIONS. BIG IMPACT. SIMPLE SOLUTIONS. BIG IMPACT. QUALITY IMPROVEMENT FOR INSTITUTIONS combines the American College of Cardiology s (ACC) proven quality improvement service solutions and its

More information

PURPOSE: The purpose of this policy is to establish requirements for designation as a STEMI Receiving Center (SRC) in San Joaquin County.

PURPOSE: The purpose of this policy is to establish requirements for designation as a STEMI Receiving Center (SRC) in San Joaquin County. PURPOSE: The purpose of this policy is to establish requirements for designation as a STEMI Receiving Center (SRC) in San Joaquin County. AUTHORITY: Health and Safety Code, Division 2.5, Sections 1797.67,

More information

NHS Improvement advice to the Competition and Markets Authority Proposed merger of Burton Hospitals NHS Foundation Trust and Derby Teaching Hospitals

NHS Improvement advice to the Competition and Markets Authority Proposed merger of Burton Hospitals NHS Foundation Trust and Derby Teaching Hospitals NHS Improvement advice to the Competition and Markets Authority Proposed merger of Burton Hospitals NHS Foundation Trust and Derby Teaching Hospitals NHS Foundation Trust: Annex 1 February 2018 We support

More information

STEMI SYSTEM RECEIVING CENTER STANDARDS AND DESIGNATION

STEMI SYSTEM RECEIVING CENTER STANDARDS AND DESIGNATION POLICY NO: FAC - 9 DATE ISSUED: 11/2016 DATE TO BE REVIEWED: 11/2019 STEMI SYSTEM RECEIVING CENTER STANDARDS AND DESIGNATION Purpose: To define the criteria for designation as a STEMI Receiving Center

More information

Main body of report Integrating health and care services in Norfolk and Waveney

Main body of report Integrating health and care services in Norfolk and Waveney Item 18.73a ii Norfolk and Waveney Sustainability and Transformation Plan Update for governing bodies and trust boards September 2018 Purpose of report The purpose of this paper is to update members of

More information

Together for Health A Delivery Plan for the Critically Ill

Together for Health A Delivery Plan for the Critically Ill Together for Health A Delivery Plan for the Critically Ill 2013-2016 March 2015 Approved at CPG Board 25 th March 2015 1. BACKGROUND AND CONTEXT Together for Health a Delivery Plan for the Critically Ill

More information

NHS. Challenges and improvements in diagnostic services across seven days. Improving Quality

NHS. Challenges and improvements in diagnostic services across seven days. Improving Quality NHS Improving Quality NHS Improving Quality working in partnership with NHS England Challenges and improvements in diagnostic services across seven days 2 Foreword Across the country, hospitals and primary

More information

STEMI RECEIVING CENTER

STEMI RECEIVING CENTER Monterey County EMS System Policy Policy Number: 5150 Effective Date: 5/1/2012 Review Date: 12/31/2016 STEMI RECEIVING CENTER I. PURPOSE To define requirements for designation as a Monterey County STEMI

More information

Specialised Services Commissioning Policy: CP160 Specialised Paediatric Neurological Rehabilitation

Specialised Services Commissioning Policy: CP160 Specialised Paediatric Neurological Rehabilitation Specialised Services Commissioning Policy: CP160 Specialised Paediatric Neurological Rehabilitation April 2018 Version 4.0 Document information Document purpose Document name Author Policy Specialised

More information

Wales Critical Care & Trauma Network (North)

Wales Critical Care & Trauma Network (North) Wales Critical Care & Trauma Network (North) CRITICAL CARE ADMISSION & DISCHARGE GUIDELINES Revised 2016 1 CONTENTS: 1.0 Introduction 1.1 Scope of the Guideline 1.2 Levels of Care 2.0 Admission Guidance

More information

Seven Day Services Clinical Standards September 2017

Seven Day Services Clinical Standards September 2017 Seven Day Services Clinical Standards September 2017 11 September 2017 Gateway reference: 06408 Patient Experience 1. Patients, and where appropriate families and carers, must be actively involved in shared

More information

Using mortality data to improve the quality and safety of patient care December 2015

Using mortality data to improve the quality and safety of patient care December 2015 Using mortality data to improve the quality and safety of patient care December 2015 Version Date Published Notes 12.0 18/12/2015 12 th publication 11.0 18/09/2015 11 th publication 10.0 19/06//2015 10

More information

REPORT 1 FRAIL OLDER PEOPLE

REPORT 1 FRAIL OLDER PEOPLE REPORT 1 FRAIL OLDER PEOPLE Contents Vision f-3 Principles / Parameters f-4 Objectives f-6 Current Frail Older People Model f-8 ABMU Model for Frail and Older People f-11 Universal / Enabling f-12 Specialist

More information

Your Care, Your Future

Your Care, Your Future Your Care, Your Future Update report for partner Boards April 2016 Introduction The following paper has been prepared for the Board members of all Your Care, Your Future partner organisations: NHS Herts

More information

Committee of Public Accounts

Committee of Public Accounts Written evidence from the NHS Confederation AMBULANCE SERVICE NETWORK/NATIONAL AMBULANCE COMMISSIONING GROUP KEY LINES ON FUTURE MODELS FOR AMBULANCE SERVICE COMMISSIONING Executive Summary Equity and

More information

CARDIAC CARE UNIT CARDIOLOGY RESIDENCY PROGRAM MCMASTER UNIVERSITY

CARDIAC CARE UNIT CARDIOLOGY RESIDENCY PROGRAM MCMASTER UNIVERSITY CARDIAC CARE UNIT CARDIOLOGY RESIDENCY PROGRAM MCMASTER UNIVERSITY ROTATION SUPERVISOR: DR. CRAIG AINSWORTH OVERVIEW The Cardiac Care Unit (CCU) at the Hamilton General Hospital is a busy 14-bed, Level

More information

Taking Organ Transplantation to 2020 Abertawe Bro Morgannwg University Local Health Board Action Plan

Taking Organ Transplantation to 2020 Abertawe Bro Morgannwg University Local Health Board Action Plan Taking Organ Transplantation to 2020 Abertawe Bro Morgannwg University Local Health Board Action Plan Foreword In 2008 the Department of Health (DH), with the support from the Welsh Assembly Government,

More information

Integrated heart failure service working across the hospital and the community

Integrated heart failure service working across the hospital and the community Integrated heart failure service working across the hospital and the community Lynne Ruddick Professional Lead (South) British Heart Foundation 31st October 2017 Heart Failure is an epidemic. NICE has

More information

SERVICE SPECIFICATION 2 Vascular Access

SERVICE SPECIFICATION 2 Vascular Access SERVICE SPECIFICATION 2 Vascular Access Table of Contents Page 1 Key Messages 1 2 Introduction & Background 2 3 Relevant Guidelines & Standards 2 4 Scope of Service 3 5 Interdependencies with other specialties

More information

GOVERNING BODY MEETING in Public 27 September 2017 Agenda Item 5.2

GOVERNING BODY MEETING in Public 27 September 2017 Agenda Item 5.2 GOVERNING BODY MEETING in Public 27 September 2017 Paper Title Report Author Neil Evans Turnaround Director Referral Management s Contributors John Griffiths Date report submitted 20 September 2017 Dean

More information

Golden Jubilee National Hospital. Leading Quality, Research. and. Innovation

Golden Jubilee National Hospital. Leading Quality, Research. and. Innovation Golden Jubilee National Hospital Leading Quality, Research and Innovation W ELCOME to the Golden Jubilee National Hospital campus As Scotland s flagship health facility, the Golden Jubilee National Hospital

More information

21 March NHS Providers ON THE DAY BRIEFING Page 1

21 March NHS Providers ON THE DAY BRIEFING Page 1 21 March 2018 NHS Providers ON THE DAY BRIEFING Page 1 2016-17 (Revised) 2017-18 (Revised) 2018-19 2019-20 (Indicative budget) 2020-21 (Indicative budget) Total revenue budget ( m) 106,528 110,002 114,269

More information

Sue Brown Clinical Audit and Effectiveness Manager. Safety and Quality Committee

Sue Brown Clinical Audit and Effectiveness Manager. Safety and Quality Committee Report to Trust Board of Directors Date of Meeting: 24 June 2014 Enclosure Number: 11 Title of Report: Clinical Audit Plan for 2014/15 Author: Executive Lead: Responsible Sub- Committee (if appropriate):

More information

Cardiac patient workshop Pre-read document extended version - Proposed interventions (detailed) - Background to programme - Glossary

Cardiac patient workshop Pre-read document extended version - Proposed interventions (detailed) - Background to programme - Glossary Cardiac patient workshop Pre-read document extended version - Proposed interventions (detailed) - Background to programme - Glossary Please note that we do not expect you to have read this fully, however

More information

Specialised Services Service Specification: Inherited Bleeding Disorders

Specialised Services Service Specification: Inherited Bleeding Disorders Specialised Services Service Specification: Inherited Bleeding Disorders Document Author: Assistant Specialised Services Planner Cardiac and Cancer Specialised Services Planner Cancer and Blood Executive

More information

Curriculum Cardiac Catheterization

Curriculum Cardiac Catheterization Curriculum Cardiac Catheterization Description of Rotation or Educational Experience The goals of this rotation are for the cardiology fellow to develop effective technical skills in the performance of

More information

THE HEART DISEASE DELIVERY PLAN OF POWYS TEACHING HEALTH BOARD

THE HEART DISEASE DELIVERY PLAN OF POWYS TEACHING HEALTH BOARD THE HEART DISEASE DELIVERY PLAN OF POWYS TEACHING HEALTH BOARD 2013 2016 CONTENTS PAGE List of abbreviations 2 1. Background and Context 3 National Context 3 The Vision 3 The Drivers 4 Local Context 5

More information

Transforming Cancer Services In South East Wales

Transforming Cancer Services In South East Wales Transforming Cancer Services In South East Wales Clinical Service Model January 2016 Cancer survival rates are increasing. But the number of people getting cancer is increasing too. At Velindre NHS Trust

More information

NORTH OF SCOTLAND PLANNING GROUP

NORTH OF SCOTLAND PLANNING GROUP Meeting: IPG Date: 21st December 2010 Item: 67 10 (ii) NORTH OF SCOTLAND PLANNING GROUP Status Unapproved Version & Date Authors Dr Malcolm Metcalfe & Fiona MacDonald Introducing Optimal Reperfusion Therapy

More information

INFORMATION STANDARDS GOVERNANCE PROCESS. INFORMATION STANDARD Draft FINAL PROPOSAL FOR NEW OR CHANGED (INCLUDING RETIRED) INFORMATION STANDARD

INFORMATION STANDARDS GOVERNANCE PROCESS. INFORMATION STANDARD Draft FINAL PROPOSAL FOR NEW OR CHANGED (INCLUDING RETIRED) INFORMATION STANDARD INFORMATION STANDARDS GOVERNANCE PROCESS INFORMATION STANDARD Draft FINAL PROPOSAL FOR NEW OR CHANGED (INCLUDING RETIRED) INFORMATION STANDARD Project to develop dataset to inform KPIs / AOF targets for

More information

Buchanan, 1996; Knaus, Felton, Burton, Fobes, & Davis 1997, J. of Nsg Administration

Buchanan, 1996; Knaus, Felton, Burton, Fobes, & Davis 1997, J. of Nsg Administration Can Patients with Moderate to High Risk Acute Coronary Syndromes Be Cared For safely in a Cardiac Acute Care Unit (ACU) Introduction Several studies have evaluated the safety of managing g patient with

More information

Delivering the QIPP programme: making existing services improve patient outcomes

Delivering the QIPP programme: making existing services improve patient outcomes Delivering the QIPP programme: making existing services improve patient outcomes Produced by Glyn Davies MP, Chair All-Party Parliamentary Group on AF in association with the Atrial Fibrillation Association

More information

DUFFERIN COUNTY PARAMEDIC SERVICE

DUFFERIN COUNTY PARAMEDIC SERVICE DUFFERIN COUNTY PARAMEDIC SERVICE 2015-2016 ANNUAL REPORT Table of Contents Patient Stories... 2 Vision, Mission, Values... 3 Our Service... 4 Our People... 5 System Performance... 6 Program Development...

More information

Clinical Cardiology Adult Congenital Heart Disease Clinical Service (1 month)

Clinical Cardiology Adult Congenital Heart Disease Clinical Service (1 month) Clinical Cardiology Adult Congenital Heart Disease Clinical Service (1 month) During this rotation, the Cardiovascular Diseases (CD) fellow functions as an independent Cardiologist. The subspecialty trainee

More information

STEMI Receiving Center Designation Process

STEMI Receiving Center Designation Process PURPOSE STEMI Receiving Center Designation Process Rev. 2-6-2013 To define requirements for designation of a hospital as a ST-elevation myocardial infarction (STEMI) receiving center for the Austin-Travis

More information

STEMI ALERT! Craig M. Hudak, MD, FACC,FACP 24 January 2015

STEMI ALERT! Craig M. Hudak, MD, FACC,FACP 24 January 2015 STEMI ALERT! Craig M. Hudak, MD, FACC,FACP 24 January 2015 STEMI Overview ST segment Elevated Myocardial Infarction Patient Outcome Goals: Save myocardium Reduce CHF Reduce arrhythmias Improve quality

More information

South East Coast Complex Cardiology Services

South East Coast Complex Cardiology Services South East Coast Complex Cardiology Services Dr Adam Jacques Clinical Director SEC CVD SCN June 4 th 2014 SEC Cardiovascular SCN Vision Cardiovascular Centres of Excellence Patients being diagnosed as

More information

NHS WAITING TIMES IN WALES EXECUTIVE SUMMARY

NHS WAITING TIMES IN WALES EXECUTIVE SUMMARY NHS WAITING TIMES IN WALES EXECUTIVE SUMMARY Report by Auditor General for Wales, presented to the National Assembly on 14 January 2005 Contents NHS waiting times - the big picture 1 The waiting time position

More information

JOB DESCRIPTION. The post holder will take a key role in leading and developing the Stroke specialist nursing service across the organisation.

JOB DESCRIPTION. The post holder will take a key role in leading and developing the Stroke specialist nursing service across the organisation. JOB DESCRIPTION Job Title Advanced Nurse Practitioner for Stroke Salary Scale BAND 7 DIRECTORATE Elderly PROFESSIONALLY RESPONSIBLE TO: Matron MANAGERIALLY ACCOUNTABLE TO: Matron JOB SUMMARY The post holder

More information

BARIATRIC SURGERY SERVICES POLICY

BARIATRIC SURGERY SERVICES POLICY BARIATRIC SURGERY SERVICES POLICY Please note that all Central Lancashire Clinical Commissioning Policies are currently under review and elements within the individual policies may have been replaced by

More information

September Workforce pressures in the NHS

September Workforce pressures in the NHS September 2017 Workforce pressures in the NHS 2 Contents Foreword 3 Introduction and methodology 5 What professionals told us 6 The biggest workforce issues 7 The impact on professionals and people with

More information

Pre-hospital emergency care key performance indicators for emergency response times

Pre-hospital emergency care key performance indicators for emergency response times Pre-hospital emergency care key performance indicators for emergency response times Item Type Report Authors (HIQA) Publisher (HIQA) Download date 05/09/2018 21:43:37 Link to Item http://hdl.handle.net/10147/324297

More information

Key Objectives To communicate business continuity planning over this period that is in line with Board continuity plans and enables the Board:

Key Objectives To communicate business continuity planning over this period that is in line with Board continuity plans and enables the Board: Golden Jubilee Foundation Winter Plan 2016/2017 Introduction This plan outlines the proposed action that would be taken to deliver our key business objectives supported by contingency planning. This plan

More information

POSITION STATEMENT ON THE FUTURE MODEL OF NEUROSCIENCES IN MID AND SOUTH WALES. Chief Executive

POSITION STATEMENT ON THE FUTURE MODEL OF NEUROSCIENCES IN MID AND SOUTH WALES. Chief Executive AGENDA ITEM 5.2 23 October 2009 POSITION STATEMENT ON THE FUTURE MODEL OF NEUROSCIENCES IN MID AND SOUTH WALES Report of Chief Executive Paper prepared by Purpose of Paper Action/Decision required Link

More information

Consultation on Congenital Heart Disease PAPER C

Consultation on Congenital Heart Disease PAPER C Consultation on Congenital Heart Disease PAPER C Summary NHS England is currently formally consulting on its proposals to implement the national standards for congenital heart disease. These include the

More information

Plan for investment of retained marginal rate payment for emergency admissions in Gloucestershire

Plan for investment of retained marginal rate payment for emergency admissions in Gloucestershire Plan for investment of retained marginal rate payment for emergency admissions in Gloucestershire 1. Purpose of document This document summarises and explains how Gloucestershire CCG has used the funds

More information

Objective Measurement

Objective Measurement STEMI Designation Contract HOSPITAL SERVICES A. Current license to provide Basic Emergency Services in Contra Costa County Copy of License B. Cardiac Catheterization Laboratory services Copy of License.

More information

Two Hospitals-One Heart: World Class Heart Care through Multi-Disciplinary Collaboration

Two Hospitals-One Heart: World Class Heart Care through Multi-Disciplinary Collaboration Two Hospitals-One Heart: World Class Heart Care through Multi-Disciplinary Collaboration American Nurses Association Susie Schnitker RN, BSN, CEN 7 th Annual Nursing Quality Conference Director of Critical

More information

NHS Grampian. Intensive Psychiatric Care Units

NHS Grampian. Intensive Psychiatric Care Units NHS Grampian Intensive Psychiatric Care Units Service Profile Exercise ~ November 2009 NHS Quality Improvement Scotland (NHS QIS) is committed to equality and diversity. We have assessed the performance

More information

Marginal Rate Emergency Threshold. Executive Summary

Marginal Rate Emergency Threshold. Executive Summary Part 1 meeting of the Castle Point and Rochford CCG Governing Body held on 29 th September 2016 Agenda item 16 Marginal Rate Emergency Threshold Submitted by: Prepared by: Status: Robert Shaw, Joint Director

More information

Integrated Performance Report

Integrated Performance Report To provide a safe and effective healthcare service to all our communities in the East of England Integrated Performance Report Meeting Date: July 2016 Data: The month of June (May for Clinical & HART)

More information

Commissioning for Quality and Innovation (CQUIN) Specialised Scheme Guidance for November 2016

Commissioning for Quality and Innovation (CQUIN) Specialised Scheme Guidance for November 2016 Commissioning for Quality and Innovation (CQUIN) Specialised Scheme Guidance for 2017-2019 November 2016 CQUIN Schemes for Prescribed Specialised Services for April 2017 to March 2019 National PSS CQUIN

More information

STROKE AND HEART ATTACK PROJECT WORLD HEALTH ORGANIZATION/ MILLENIUM CHALLENGE ACCOUNT- MONGOLIA

STROKE AND HEART ATTACK PROJECT WORLD HEALTH ORGANIZATION/ MILLENIUM CHALLENGE ACCOUNT- MONGOLIA STROKE AND HEART ATTACK PROJECT 2010-2013 WORLD HEALTH ORGANIZATION/ MILLENIUM CHALLENGE ACCOUNT- MONGOLIA THE PROJECT GOAL To improve care delivery framework for comprehensive medical care to the patients

More information

Evaluation of the Hywel Dda Community Pharmacist pilot optimising medicines treatment in heart failure.

Evaluation of the Hywel Dda Community Pharmacist pilot optimising medicines treatment in heart failure. Evaluation of the Hywel Dda Community Pharmacist pilot optimising medicines treatment in heart failure. Authors: Gareth Holyfield (Principal Pharmacist, Public Health Wales) Don Wilkes (Community Pharmacist,

More information

Angiography and Angioplasty

Angiography and Angioplasty (hosted by the ) Monday 16th and Tuesday 17th March 2015 The Beardmore Hotel and Conference Centre, Clydebank, near Glasgow A comprehensive and practical two day course for all Allied Health Professionals

More information

FULL TEAM AHEAD: UNDERSTANDING THE UK NON-SURGICAL CANCER TREATMENTS WORKFORCE

FULL TEAM AHEAD: UNDERSTANDING THE UK NON-SURGICAL CANCER TREATMENTS WORKFORCE FULL TEAM AHEAD: UNDERSTANDING THE UK NON-SURGICAL CANCER TREATMENTS WORKFORCE DECEMBER 2017 Publication date 04/12/17 Registered Charity in England and Wales (1089464), Scotland (SC041666) and the Isle

More information

PARTICULARS, SCHEDULE 2 THE SERVICES, A Service Specification. 12 months

PARTICULARS, SCHEDULE 2 THE SERVICES, A Service Specification. 12 months E09/S(HSS)/b 2013/14 NHS STANDARD CONTRACT FOR VEIN OF GALEN MALFORMATION SERVICE (ALL AGES) PARTICULARS, SCHEDULE 2 THE SERVICES, A Service Specification Service Specification No. Service Commissioner

More information

Organisational factors that influence waiting times in emergency departments

Organisational factors that influence waiting times in emergency departments ACCESS TO HEALTH CARE NOVEMBER 2007 ResearchSummary Organisational factors that influence waiting times in emergency departments Waiting times in emergency departments are important to patients and also

More information

Health Care Quality Indicators in the Irish Health System:

Health Care Quality Indicators in the Irish Health System: Health Care Quality Indicators in the Irish Health System Examining the Potential of Hospital Discharge Data using the Hospital Inpatient Enquiry System - i - Health Care Quality Indicators in the Irish

More information

Review of Follow-up Outpatient Appointments Hywel Dda University Health Board. Audit year: Issued: October 2015 Document reference: 491A2015

Review of Follow-up Outpatient Appointments Hywel Dda University Health Board. Audit year: Issued: October 2015 Document reference: 491A2015 Review of Follow-up Outpatient Appointments Hywel Dda University Health Board Audit year: 2014-15 Issued: October 2015 Document reference: 491A2015 Status of report This document has been prepared as part

More information

POSITION DESCRIPTION Job Title: Interventional Cardiology Fellow Last updated: June 2016

POSITION DESCRIPTION Job Title: Interventional Cardiology Fellow Last updated: June 2016 POSITION DESCRIPTION Job Title: Interventional Cardiology Fellow Last updated: June 2016 Reports to: Director of Cardiology 1. MISSION, VISION AND VALUES OUR VISION STATEMENT To lead transformation in

More information

Acute Coronary Syndromes (ACS) Provincial Orders Dissemination. Final Evaluation Report

Acute Coronary Syndromes (ACS) Provincial Orders Dissemination. Final Evaluation Report Acute Coronary Syndromes (ACS) Provincial Orders Dissemination Final Evaluation Report July 2014 ACS POD Evaluation - 2 This report was produced by the Clinical Analytics Team, Data Integration, Measurement

More information

NHS Bradford Districts CCG Commissioning Intentions 2016/17

NHS Bradford Districts CCG Commissioning Intentions 2016/17 NHS Bradford Districts CCG Commissioning Intentions 2016/17 Introduction This document sets out the high level commissioning intentions of NHS Bradford Districts Clinical Commissioning Group (BDCCG) for

More information

Northumberland, Tyne and Wear NHS Foundation Trust. Board of Directors Meeting. Meeting Date: 25 October Executive Lead: Rajesh Nadkarni

Northumberland, Tyne and Wear NHS Foundation Trust. Board of Directors Meeting. Meeting Date: 25 October Executive Lead: Rajesh Nadkarni Agenda item 9 ii) Northumberland, Tyne and Wear NHS Foundation Trust Board of Directors Meeting Meeting Date: 25 October 2017 Title and Author of Paper: Clinical Effectiveness (CE) Strategy update Simon

More information

Seven day hospital services: case study. South Warwickshire NHS Foundation Trust

Seven day hospital services: case study. South Warwickshire NHS Foundation Trust Seven day hospital services: case study South Warwickshire NHS Foundation Trust March 2018 We support providers to give patients safe, high quality, compassionate care within local health systems that

More information

Working to improve the delivery of services for cardiac and stroke patients and their families across Cheshire and Merseyside

Working to improve the delivery of services for cardiac and stroke patients and their families across Cheshire and Merseyside Cardiac Implantable Cardioverter Defibrillator (ICD), Cardiac Resynchronisation Therapy (CRT) & Elective Percutaneous Coronary Intervention (PCI) Review 31 st August 2010 Working to improve the delivery

More information

Duke Life Flight. Systems of Care for Time Dependent Emergencies. Disclosures. Disclosures 9/19/2017

Duke Life Flight. Systems of Care for Time Dependent Emergencies. Disclosures. Disclosures 9/19/2017 Duke Life Flight Systems of Care for Time Dependent Emergencies Claire M Corbett, MMS, NRP Manager of Neurodiagnostics and Stroke Center New Hanover Regional Medical Center Wilmington, NC Disclosures Clinical

More information

Final. Andrew McMylor / Dr Nicola Jones. Jeremy Fenwick, Battersea Healthcare CIC

Final. Andrew McMylor / Dr Nicola Jones. Jeremy Fenwick, Battersea Healthcare CIC NHS Standard Contract - Service Specification Service Specification Service Commissioner Lead Lead Final Primary Care Based 12-Lead Electrocardiogram Service Andrew McMylor / Dr Nicola Jones Jeremy Fenwick,

More information

Heart attack care in Ireland 2014

Heart attack care in Ireland 2014 Heart attack care in Ireland 2014 Item type Authors Publisher Report Acute Coronary Syndrome (ACS); Health Service Executive Acute Coronary Syndrome (ACS) Downloaded 8-Jun-2018 03:13:02 Link to item http://hdl.handle.net/10147/620576

More information

Standard of Care for MTC inpatients

Standard of Care for MTC inpatients Standard of Care for MTC inpatients The following document is intended to summarise the model of care for patients admitted under the care of the Leeds Major Trauma System. It will outline expected duties

More information

Final. Andrew McMylor / Dr Nicola Jones

Final. Andrew McMylor / Dr Nicola Jones NHS Standard Contract - Service Specification Service Specification Service Final 24hour Ambulatory Blood Pressure Monitoring (24hrABPM) Commissioner Lead Lead Andrew McMylor / Dr Nicola Jones Jeremy Fenwick,

More information

Redesign of Front Door

Redesign of Front Door Redesign of Front Door Transforming Acute and Urgent Care Strategic Background and Context Our Change and Improvement Programme What have we achieved and how? What did we learn? Ian Aitken, General Manager

More information

Emergency admissions to hospital: managing the demand

Emergency admissions to hospital: managing the demand Report by the Comptroller and Auditor General Department of Health Emergency admissions to hospital: managing the demand HC 739 SESSION 2013-14 31 OCTOBER 2013 4 Key facts Emergency admissions to hospital:

More information

The Cardiology Landscape

The Cardiology Landscape The Cardiology Landscape Final Draft 18 March 2011 Acknowledgement Many people contributed to this project. The sponsor and the steering group provided the necessary oversight including attending regular

More information

San Joaquin County Emergency Medical Services Agency

San Joaquin County Emergency Medical Services Agency San Joaquin County Emergency Medical Services Agency http://www.sjgov.org/ems DATE: Mailing Address PO Box 220 French Camp, CA 95231 TO: FROM: SUBJ.: All Prehospital Personnel and Providers Emergency Department

More information

IN THIS ISSUE... KEOGH REVIEW PROGRESS

IN THIS ISSUE... KEOGH REVIEW PROGRESS Sept 2013 KEOGH REVIEW PROGRESS The Keogh review has provided the Trust with a further opportunity to really scrutinise its performance and approaches to patient care. The report which was published in

More information

April Clinical Governance Corporate Report Narrative

April Clinical Governance Corporate Report Narrative April 14 - Clinical Governance Corporate Report Narrative ITEM 7B Narrative has been provided where there is something of note in relation to a specific metric; this could be positive improvement, decline

More information

Introduction. Singapore. Singapore and its Quality and Patient Safety Position 11/9/2012. National Healthcare Group, SIN

Introduction. Singapore. Singapore and its Quality and Patient Safety Position 11/9/2012. National Healthcare Group, SIN Introduction Singapore and its Quality and Patient Safety Position Singapore 1 Singapore 2004: Top 5 Key Risk Factors High Body Mass (11.1%; 45,000) Physical Inactivity (3.8%; 15,000) Cigarette Smoking

More information

THE CANADIAN CARDIOVASCULAR SOCIETY QUALITY INDICATORS E- CATALOGUE QUALITY INDICATORS FOR TRANSCATHETER AORTIC VALVE IMPLANTATION (TAVI)

THE CANADIAN CARDIOVASCULAR SOCIETY QUALITY INDICATORS E- CATALOGUE QUALITY INDICATORS FOR TRANSCATHETER AORTIC VALVE IMPLANTATION (TAVI) THE CANADIAN CARDIOVASCULAR SOCIETY QUALITY INDICATORS E- CATALOGUE QUALITY INDICATORS FOR TRANSCATHETER AORTIC VALVE IMPLANTATION (TAVI) A CCS CONSENSUS DOCUMENT FINAL V1 Last updated: September 16, 2015

More information

Improving Access to Psychological Therapies. Guidance for Commissioning IAPT Training 2012/13. Revised July 2012

Improving Access to Psychological Therapies. Guidance for Commissioning IAPT Training 2012/13. Revised July 2012 Improving Access to Psychological Therapies Guidance for Commissioning IAPT Training 2012/13 Revised July 2012 IAPT Programme Department of Health Wellington House 133-155 Waterloo Road London SE1 8UG

More information

South Warwickshire s Whole System Approach Transforms Emergency Care. South Warwickshire NHS Foundation Trust

South Warwickshire s Whole System Approach Transforms Emergency Care. South Warwickshire NHS Foundation Trust South Warwickshire s Whole System Approach Transforms Emergency Care South Warwickshire NHS Foundation Trust South Warwickshire s Whole System Approach Transforms Emergency Care South Warwickshire NHS

More information

Expert Rev. Pharmacoeconomics Outcomes Res. 2(1), (2002)

Expert Rev. Pharmacoeconomics Outcomes Res. 2(1), (2002) Expert Rev. Pharmacoeconomics Outcomes Res. 2(1), 29-33 (2002) Microcosting versus DRGs in the provision of cost estimates for use in pharmacoeconomic evaluation Adrienne Heerey,Bernie McGowan, Mairin

More information

End of Life Care. LONDON: The Stationery Office Ordered by the House of Commons to be printed on 24 November 2008

End of Life Care. LONDON: The Stationery Office Ordered by the House of Commons to be printed on 24 November 2008 End of Life Care LONDON: The Stationery Office 14.35 Ordered by the House of Commons to be printed on 24 November 2008 REPORT BY THE COMPTROLLER AND AUDITOR GENERAL HC 1043 Session 2007-2008 26 November

More information

Boarding Impact on patients, hospitals and healthcare systems

Boarding Impact on patients, hospitals and healthcare systems Boarding Impact on patients, hospitals and healthcare systems Dan Beckett Consultant Acute Physician NHSFV National Clinical Lead Whole System Patient Flow Project Scottish Government May 2014 Important

More information

Board Meeting. Date of Meeting: 28 September 2017 Paper No: 17/62

Board Meeting. Date of Meeting: 28 September 2017 Paper No: 17/62 Oxfordshire Clinical Commissioning Group Oxfordshire Clinical Commissioning Group Board Meeting Date of Meeting: 28 September 2017 Paper No: 17/62 Title of Paper: Ambulance Response Programme Paper is

More information

Welsh Government Response to the Report of the National Assembly for Wales Public Accounts Committee Report on Unscheduled Care: Committee Report

Welsh Government Response to the Report of the National Assembly for Wales Public Accounts Committee Report on Unscheduled Care: Committee Report Welsh Government Response to the Report of the National Assembly for Wales Public Accounts Committee Report on Unscheduled Care: Committee Report We welcome the findings of the report and offer the following

More information

Gwent Clinical Futures

Gwent Clinical Futures Gwent Clinical Futures Public Consultation Document Blaenau Gwent Local Health Board Caerphilly Local Health Board Monmouthshire Local Health Board Newport Local Health Board Torfaen Local Health Board

More information