1 Implementing Carecast: The UCLH Experience Kevin Jarrold Director of Information Management & EPR Project Director
2 Issues to Address Communications and getting staff on-board The effect of having a new build going on at the same time: has it helped or hindered? Technical matters such as configuration, data migration, functionality, etc. The supplier's understanding of the NHS Resourcing and training
3 Planned Agenda Some background on UCLH Overview of the new hospital scheme The EPR project Progress to date UCLH EPR and the CRS Key issues moving forwards
4 Overview of UCLH The Middlesex Hospital University College Hospital The Obstetric Hospital & Elizabeth Garrett Anderson Hospital National Hospital for Neurology & Neurosurgery Eastman Dental Hospital Hospital for Tropical Diseases The Heart Hospital Royal London Homeopathic Hospital
5 Eight Hospitals - One Vision
6 Key Facts Annual turnover of circa 400m Staff employed 6, beds One of the largest NHS Trusts National specialities - some world class One of the largest build projects in the NHS Association with University College London Part of the North London hospital network
7 New Hospital The Middlesex Hospital University College Hospital The Obstetric Hospital & Elizabeth Garrett Anderson Hospital Hospital for Tropical Diseases National Hospital for Neurology & Neurosurgery. Eastman Dental Hospital The Heart Hospital Royal London Homeopathic Hospital
8 New Hospital - the Vision Where we are now World class health care delivered from Victorian buildings Huge underinvestment in maintenance Struggle to meet modern standards Green screen technology Where we want to be m PFI scheme for state of the art hospital Vision for a University/Health campus Designed on the assumption that it will be paper light Clinical commitment
9 The New Hospital The Reality
10
11 IT The Challenge Work to a fixed date for the opening of the New Hospital Deliver paper light operation to fit with the vision and design assumptions Retain four existing hospitals so it is not green field Do it under PFI and traditional procurement process Change software part way through the project Do it while the National Programme is emerging and changing the world
12 EPR Project Scope EPR environment Organisation-wide scheduling Clinical noting and alerts Electronic ordering and results reporting Delivery of Managed IM&T Service Provide the Trust IT Department Network the new hospital Data and voice
13 Selection process & timetable No OJEC Advert responses July Preliminary Invite to Negotiate (ITN) Sept Long List for demos & discussions Oct Shortlist agreed, ITN issued May Responses, Negotiations, Demos Jun-Dec 02 3 Final Negotiations, visits Jan-April 03 2 Preferred supplier July Contract signed Sept
14 Aims of the deal Robust specification of what will be delivered Solution that meets user needs Provides value for money Is affordable Can be delivered in time for the new hospital Provides a migration path to CRS
15 Trust commitment... Clinical buy-in to the EPR - seen as critical to the vision of world class patient care Resources for project - procurement costs were over 1m Plan to commit at least 85m of trust resources over 10 years
16 Key Features of the Contract IDX are prime contractor LogicaCMG provide managed IT service 20 staff TUPED from McKesson to LCMG LCMG now employ 40 staff plus 20 on EPR work 24/7 helpdesk Marconi are installing active network in the new hospital Wireless LAN has gone into retained hospitals 2,400 new PCs plus 1,000 upgrades Standardised on XP with Active Directory Refresh every 4 years
17 Original EPR Phase Plan Phase 1 PAS plus Maternity and A&E Phase 2 Orders/Results, Theatres, TTOs Phase 3 Clinical applications for movers Move into New Hospital Phase 4 Clinical applications the rest Phase 5 Electronic Prescribing July/August 2004 October 2004 December 2004 April 2005 October 2005 December 2005
18 UCLH IDX EPR Project Board EPR Implementation Steering Group EPR Project Team Chief Exec (Chair) Finance Director Medical Director Director of Cap. Invest HR Director Senior Clinician UCLH Project Director Clinical Boards x3 Nurse lead Consultant lead Corporate Services UCLH Project Director UCLH Project Manager Phase leads and stream leads MD for IDX UK Chief Operating Officer for IDX US IDX Project Director IDX Project Manager IDX Project Director IDX Project Manager Phase leads and stream leads
19 Streams Application development Application tailoring Training Testing Data Migration Interfaces Management Information PC roll out Disaster Recovery Security Cut-Over Plan
20 Streams Application development Application tailoring Data Migration Training Testing Interfaces Management Information PC roll out Disaster Recovery Security Cut-Over Plan
21 Application Development Key issues: Lastword to Carecast migration Anglicisation of the Carecast product IDX software development process
22 Lastword to Carecast Made the decision to migrate to Carecast in Feb/March 2004 IDX gave an assurance it would have no impact on timescales London and the South were doing it The product is better It has saved re-training But IDX seriously underestimated the effort needed
23 Anglicisation C&W had concentrated on clinical benefits rather than admin functionality Key issues Real time commissioning Compliance with NHS data model and production of Clearnet extract Outpatient scheduling
24 IDX Software Development An implementation project turned into a software development project Challenges have included: Fully communicating NHS needs Development effort split between London and Seattle Product integration Ensuring tight project management so that the software that gets delivered matches expectations
25 Where we are now We do now have a product Code Drop 9 has delivered most of the go live software for Phase 1 Final delivery in December will complete the picture Software Development project now turning back into an Implementation Project Other streams like data migration and interfaces can now plan in earnest.. Currently re-cutting plan for Q go live
26 Data Migration Is part of the scope of the services IDX have to deliver Users PMI inc address history & GP history Waiting List A&E Outpatients Inpatients Casenote movements Some manual and some electronic transfer For example: Outpatient clinic templates will be manual Appointments electronic DM is now on critical path Additional UCLH testing resources
27 Training Train the trainer training was part of scope End user training an option Have gone for mixed economy 20 Deverills trainers 10 UCLH Suite of 12 training rooms (x12 training places) dedicated for the purpose Developing training materials to reflect UCLH processes Training mandatory On line assessment
28 Security Two factor authentication part of scope Keen to use NPfIT approach as it becomes available Have team in place: 1wte IT 0.5wte HR Setting up Registration Authority Issue card to the right person Complete competency test Have authorised access
29 Resources Planned investment of 85m over ten years IDX contract value is circa 70-75m Balance is investment within the Trust
30 UCLH Resource Project Manage ment Process Review Manage ment Reporting Tailoring Training Project Director & Manager Phase Project Managers Process Review Lead Process Analysts x 5 Information Analysts x2 Tailoring Lead Tailoring Analysts x 4 Training Manager UCLH Trainers x10 Deverills Trainers x 20 Admin support x2
31 UCLH Resource (2) Other Key Roles Clinical Board QA Communications PC Roll Out Clinical Advisor Interfaces Security x1.5 Testing x3 Data Quality x4 Clinical Board Implementation Lead Key Users and Super Users Testers and Trainers Leads on Training and PC roll out
32 User Engagement Key to clinical engagement is: A product that supports the workflow Is easy to use Ready to deliver Flexible to tailor For UCLH EPR supports the vision of modernisation Input from PR team Regular items in staff paper and briefing Roadshows to explain what will happen and when Clinical input to process NB they are the paymasters
33 UCLH and NPfIT IDX only have one product UCLH has wider scope and earlier delivery Anglicisation issues are generic NHS issues NPfIT is taking UCLH output to build on UCLH will migrate from local database Working closely with BT to ensure integrated approach
34 Key issues going forwards Final delivery of software for Phase1 Developments for Phase 2 on Orders Re cutting the plan for Q go live Delivering Phase 1 and 2 before the New Hospital opens Moving forwards the clinical functionality Planning work in: A&E Urology Diabetes Delivering electronic Prescribing Integration with NPfIT
35 Issues to Address Communications and getting staff on-board The effect of having a new build going on at the same time: has it helped or hindered? Technical matters such as configuration, data migration, functionality, etc. The supplier's understanding of the NHS Resourcing and training
Background and progress
the voice of NHS management briefing MARCH 2004 ISSUE 96 Electronic booking an initial guide to implementation Keeping abreast of IT Everyone who plays a leading or frontline role in the delivery of high-quality
More informationNational Programme for IT. Ken Lunn Head of Comms and Messaging OMG/HL7 workshop October 2005
National Programme for IT Ken Lunn Head of Comms and Messaging OMG/HL7 workshop 25-27 October 2005 Contents Context Our aims What is the National Programme for IT? Implementation Benefits Questions In
More informationUniversity College London Hospitals NHS Foundation Trust
University College London Hospitals NHS Foundation Trust Members Event Simon Knight, Nina Griffith, planning and performance Jonathan Gardner, strategic development Purpose of this session To give you
More informationBackground. The informatics review set out to do three things:
the voice of NHS leadership briefing AUGUST 2008 ISSUE 170 The 2008 Health Informatics Review Key points Lack of progress with key aspects of the National Programme for IT, particularly the NHS Care Records
More informationResuscitation Training Policy
Resuscitation Training Policy Approved by & date HMB 12 November 2003 Date of Publication February 2003 Review date February 2005 Creator & telephone details Christopher Gabel, Senior Resuscitation Officer
More informationAcute Care Solutions. A range of modern, intuitive and marketleading solutions for the next generation of hospital IT
Acute Care Solutions A range of modern, intuitive and marketleading solutions for the next generation of hospital IT Our acute care suite is a modern, fully-modular, NHS solution, which can be built to
More informationApprove Ratify For Discussion For Information
NHS North Cumbria CCG Governing Body Agenda Item 4 October 2017 11 Implementation of Digital road Map Update Purpose of the Report To update the Governing Body as to progress in meeting national targets
More informationInformation Technology (IT) Strategy
Information Technology (IT) Strategy Name of Meeting: Trust Board Item: 16 Date of Meeting: 25th January 2017 Enclosure: L Purpose of the Report / Paper: To seek approval from the Board for the IT Strategy
More informationService Transformation Report. Resource and Performance
SUMMARY REPORT Meeting Date: 31 May 2018 Agenda Item: 9.1 Enclosure Number: 9 Meeting: Trust Board (Part 1) Title: Author: Accountable Director: Other meetings presented to or previously agreed at: Service
More informationCarePlus Child Health. An all-embracing interactive child health record, from child to adult
CarePlus Child Health An all-embracing interactive child health record, from child to adult What CarePlus Child Health does... CarePlus Child Health is a browser-based child health administration solution,
More informationPersonal health record (PHR) case study.
Personal health record (PHR) case study Myhealth@QEHB Acknowledgements This case study is based on discussions with James Ferguson, consultant hepatologist and clinical lead for myhealth@qehb and with
More informationWest Mid Beds Locality Development Plan
West Mid Beds Locality Development Plan 2013-14 Contents Introduction..3 1. Key Progress 2012/13.. 4 2. Locality Objectives 2013/14.5 2.1 Commissioning.5 2.2 Performance & Finance.. 9 2.3 Engagement 11
More informationNHS Forth Valley. Annual Procurement Report 2017/18
NHS Forth Valley Annual Procurement Report 2017/18 Index Introduction & Overview...... 2 NHS Forth Valley Procurement Activity & Budget...... 3 Summary of Regulated Procurements Completed 2017 2018...
More informationANEURIN BEVAN HEALTH BOARD CLINICAL FUTURES STRATEGY AND SPECIALIST CRITICAL CARE CENTRE: BRIEFING
ANEURIN BEVAN HEALTH BOARD Aneurin Bevan Health Board CLINICAL FUTURES STRATEGY AND SPECIALIST CRITICAL CARE CENTRE: BRIEFING 1 PURPOSE The purpose of this paper to is to brief Board members on the proposed
More informationCommunity Pharmacy in 2016/17 and beyond
Community Pharmacy in 2016/17 and beyond Stakeholder briefing sessions 1 CONTENTS Contents This presentation describes our vision for community pharmacy, and outlines proposals for achieving that vision,
More informationAppendix 1: Croydon Clinical Commissioning Group Risk Register and Board Assurance Framework - 9th April 2013
Appendix 1: Croydon Clinical Register and Board Assurance Framework - 9th April 2013 Principal to Delivery Key Assurance on we have in in our are 1. To achieve financial sustainability in three years (2013-2014
More informationLaboratory Information Management System (LIMS) Replacement
Laboratory Information Management System (LIMS) Replacement 1. Introduction The Health Board is to transition from its current LIMS to the new national LIMS in late March 2014. This is a significant change
More informationAneurin Bevan Health Board. Improving Theatre Performance
Aneurin Bevan Health Board Improving Theatre Performance 1 Introduction This report provides an overview on actions being taken to improve theatre performance within the Health Board. The report provides
More informationScottish Ambulance Service
Scottish Ambulance Service Equality Impact Assessment for the Ambulance Telehealth Programme December 2015 Version 3.2 Note: This version supersedes all previous versions AmbTel_EQIA_December 2015_v3.2
More informationSeeking your views on transforming health and care in Bedfordshire, Luton and Milton Keynes. March 2017
Seeking your views on transforming health and care in Bedfordshire, Luton and Milton Keynes March 2017 Agenda 1. STP update October submission, feedback so far, about the March 2017 Discussion Paper 2.
More informationDelegated Commissioning Updated following latest NHS England Guidance
Delegated Commissioning Updated following latest NHS England Guidance 13th August 2015 Croydon, Kingston, Merton, Richmond, Sutton and Wandsworth NHS Clinical Commissioning Groups and NHS England (Direct
More informationMEETING OF THE GOVERNING BODY IN PUBLIC 7 January 2014
MEETING OF THE GOVERNING BODY IN PUBLIC 7 January 2014 Title: Bedfordshire and Milton Keynes Healthcare Review: The way forward Agenda Item: 4 From: Jane Meggitt, Director of Communications and Engagement
More informationUrgent and Emergency Care - the new offer
Urgent and Emergency Care - the new offer If it s really serious I want specialist care Help me to help myself and not bother the NHS If only they could talk to my GP? London Clinical Senate Keith Willett
More informationA Maternity Network for Wales
A Maternity Network for Wales Scoping Paper July 2013 Introduction This scoping exercise arises from a recommendation made in the Health and Social Care Committee s report One-day Inquiry into Stillbirth
More informationhealthcare Providing technology to enhance the patient experience
healthcare Providing technology to enhance the patient experience Dakota s mission within the healthcare sector is simple to be a leading provider of technology to help clinicians boost the patient experience.
More informationTitle: Climate-HIV Case Study. Author: Keith Roberts
Title: Climate-HIV Case Study Author: Keith Roberts The Project CareSolutions Climate HIV is a specialised electronic patient record (EPR) system for HIV medicine. Designed by clinicians for clinicians
More informationStrategic overview: NHS system
Strategic overview: NHS system Dr Keith Ridge, Chief Pharmaceutical Officer 1 November 2016 A collaborative approach Five Year Forward View Oct 2014 NHS planning guidance, Dec 2015: Every health and care
More informationNHS Electronic Referrals Service. Paper Switch Off an update Digital Health Webinar 4 May 2018
NHS Electronic Referrals Service Paper Switch Off an update Digital Health Webinar 4 May 2018 Aims of Session Introductions and refresh of Paper Switch Off Sharon Wilson Implementation manager NHS Digital
More informationLessons Learned from Scotland s Electronic Health Record Programme. Greater China e-health Forum 7 th October 2011
Lessons Learned from Scotland s Electronic Health Record Programme Greater China e-health Forum 7 th October 2011 InterSystems Established in 1978 Headquartered in Cambridge, MA Healthcare solutions headquartered
More informationInformation Technology Strategy Kevin Fitzgerald, Director of IM&T
Information Technology Strategy 2017 2021 Kevin Fitzgerald, Director of IM&T IM&T will enable the delivery of excellent care by providing easy access to systems and data to staff and patients wherever
More informationNHS Board Workforce Projections 2017 NHS LANARKSHIRE. Table of Contents
NHS Board Workforce Projections 2017 NHS LANARKSHIRE Table of Contents 1. Overall 1.1 Comments / Data Quality Issues / Direction of Travel 1.2 Brief Information on Workforce Cost Savings (non-staff) i.e.
More informationBoard meeting 31 January 2007
This paper is being submitted to the Trust Board for amendment and/or approval as appropriate. It should not be regarded, or published, as Trust policy until formally agreed at the Board meeting, which
More informationSupporting all NHS Trusts to achieve NHS Foundation Trust status by April 2014
TFA document Supporting all NHS Trusts to achieve NHS Foundation Trust status by April 2014 Tripartite Formal Agreement between: Hertfordshire Community NHS Trust NHS East of England Department of Health
More informationCGI e-carelogic. enhancing care across the health economy. Connected healthcare from CGI
CGI e-carelogic enhancing care across the health economy Connected healthcare from CGI cgi.com 2 Want to get the most out of your existing systems? Whether you are a clinician, administrator or manager,
More informationNHS Digital Academy Experience and Advice from Cohort 1
NHS Digital Academy Experience and Advice from Cohort 1 Zainab Hussain Lead Pharmacist Clinical Informatics Lewisham and Greenwich NHS Trust Sarah Thompson Head of EPR Clinical Deployment Stockport NHS
More informationNewham Borough Summary report
Newham Borough Summary report April 2013 Prepared on 17/04/13 by Commissioning Support team Apr-11 Jun-11 Aug-11 Oct-11 Dec-11 Feb-12 Apr-12 Jun-12 Aug-12 Oct-12 Dec-12 Feb-13 GREE N Finance and Activity
More informationThe health coaching experience in NHS Midlands and East
The health coaching experience in NHS Midlands and East Dr Penny Newman, GP, primary care adviser, commissioning development, NHS Midlands and East, NHS Institute NHS Institute for Innovation and Improvement,
More informationQuestion 1 a) What is the Annual net expenditure on the NHS from 1997/98 to 2007/08 in Scotland? b) Per head of population
NHS SPENDING - SCOTLAND Question 1 a) What is the Annual net expenditure on the NHS from 1997/98 to 2007/08 in Scotland? b) Per head of population Question 2 a) Annual real (GDP deflated) increase in net
More informationUpdate on NHS Central London CCG QIPP schemes
Update on NHS Central London CCG QIPP schemes NHS Central London CCG has identified circa 11m for QIPP during 2013/14. Commissioning Intentions approved by the governing body included transformational
More informationConsultant psychiatrist job description and person specification
Consultant psychiatrist job description and person specification The following job description is provided as a resource to the recruiting trust and may be used as a template. It is not designed to be
More informationNewham Borough Summary report
Newham Borough Summary report March 2013 Prepared on 18/03/13 by Commissioning Support team Finance and Activity Millions Apr-11 Jun-11 Aug-11 Oct-11 Dec-11 Newham Headlines March 2013 Feb-12 Apr-12 Jun-12
More informationMaking the PMO the beating heart of the NHS Change Agenda:
Making the PMO the beating heart of the NHS Change Agenda: A Special Case Study Feature We all know that information is the life blood of all organisations. Good quality, accurate, up-to-date, easily available
More informationJOB DESCRIPTION. Consultant in Palliative Medicine GENERAL
JOB DESCRIPTION JOB TITLE DEPARTMENT REPORTS TO ACCOUNTABLE TO Consultant in Palliative Medicine Medical Team Lead Consultant Director of Patient Care GENERAL ellenor is a specialist palliative care provider
More informationBT: leading the way in healthcare IT
BT: leading the way in healthcare IT BT is not only the UK s largest information and communications company it is also the largest supplier of NHS Information and CommunicationsTechnology with more than
More informationSBAR Report phase 1 Maternity, Gynaecology & Neonatal services
North Wales Maternity, Gynaecology, Neonatal and Paediatric service review SBAR Report phase 1 Maternity, Gynaecology & Neonatal services Situation The Minister for Health and Social Services has established
More informationNAME SPECIALTY PLEASE NOTE THAT THE CONSULTANT SURGEONS RUN A 4 WEEK ROLLING ROTA OF ACTIVITY. (HENCE THE 'BUSY' JOB PLAN)
CONSULTANT CONTRACT JOB PLAN NAME SPECIALTY PLEASE NOTE THIS IS INTENDED AS A GUIDE ONLY. AN FORMAL JOB PLAN WILL BE DEVISED WITH THE SUCCESFUL CANDIDATE TO TAKE ACCOUNT OF PERSONAL INTERESTS AND SPECIALTY
More informationGE1 Clinical Utilisation Review
GE1 Clinical Utilisation Review Scheme Name QIPP Reference Eligible Providers GE1 Clinical Utilisation Review QIPP 16-17 S40-Commercial 17/18 QIPP reference to be added locally. This CQUIN is supported
More informationSeven day hospital services: case study. South Warwickshire NHS Foundation Trust
Seven day hospital services: case study South Warwickshire NHS Foundation Trust March 2018 We support providers to give patients safe, high quality, compassionate care within local health systems that
More informationOptum capability landscape. Modernising infrastructure. Advancing care. Empowering consumers.
Optum capability landscape Modernising infrastructure. Advancing care. Empowering consumers. Optum is a leading health services and innovation company dedicated to helping make the health system work better
More informationExecutive Workforce Report
Executive Workforce Report (v2) Safe & Effective Kind & Caring Exceeding Expectation Agenda Item No: 9.3 The Royal Wolverhampton NHS Trust Trust Board Report Meeting Date: 27 th November 2017 Title: Executive
More informationDelivering the Five Year Forward View Personalised Health and Care 2020
Paper Ref: NIB 0607-006 Delivering the Five Year Forward View Personalised Health and Care 2020 INTRODUCTION The Five Year Forward View set out a clear direction for the NHS showing why change is needed
More informationProject Initiation Document Review of Community Nursing Services in Wyre Forest
Project Initiation Document Review of Community Nursing Services in Wyre Forest Contents Page 1. Management Summary 1 2. Introduction 1 2.1 Purpose of Document 1 2.2 Background 2 3. Project Definition
More informationCLINICAL STRATEGY IMPLEMENTATION - HEALTH IN YOUR HANDS
CLINICAL STRATEGY IMPLEMENTATION - HEALTH IN YOUR HANDS Background People across the UK are living longer and life expectancy in the Borders is the longest in Scotland. The fact of having an increasing
More informationUrology Clinical Forum. 11 th March 2015
Urology Clinical Forum 11 th March 2015 Welcome and Introductions Justin Vale, Chair of the LCA Urology Pathway Group Progress of the Urology Pathway Group Justin Vale, Chair of the LCA Urology Pathway
More informationMilton Keynes CCG Strategic Plan
Milton Keynes CCG Strategic Plan 2012-2015 Introduction Milton Keynes CCG is responsible for planning the delivery of health care for its population and this document sets out our goals over the next three
More informationSafer Nursing and Midwifery Staffing Recommendation The Board is asked to: NOTE the report
To: Board of Directors Date of Meeting: 26 th July 20 Title Safer Nursing and Midwifery Staffing Responsible Executive Director Nicola Ranger, Chief Nurse Prepared by Helen O Dell, Deputy Chief Nurse Workforce
More informationAn Information Strategy for the modern NHS and relevance to the health system context of the Russian Federation
An Information Strategy for the modern NHS and relevance to the health system context of the Russian Federation WB Seminar on Health Information Systems, Moscow, Russian Federation Y.Samyshkin, A.Timoshkin
More informationFrom Go-Live to HIMSS Level 6 in 10 months The Royal Children s Hospital EMR experience
From Go-Live to HIMSS Level 6 in 10 months The Royal Children s Hospital EMR experience Lauren Andrew, Matthew Thatcher, Jackie McLeod, Mike South, Jennifer White, Adrian Hutchison 9 th August 2017 Royal
More informationKevin Downs and Keith Jones. The Royal Derby Hospital
Kevin Downs and Keith Jones The Royal Derby Hospital Facts About Our Hospital The Royal Derby Hospital is the newest hospital in the East Midlands 334 million has been invested in the development Annual
More informationDRAFT BUSINESS PLAN AND CORPORATE OBJECTIVES 2017/8
DRAFT BUSINESS PLAN AND CORPORATE OBJECTIVES 2017/8 West London Clinical Commissioning Group This document sets out a clear set of plans and priorities for 2017/18 reflecting West London CCGs ambition
More informationInnovating for Improvement
Innovating for Improvement Call for applications Round 3 July 2015 The Health Foundation Tel 020 7257 8000 www.health.org.uk CONTENTS 1. About the Health Foundation 3 2. Introduction to Innovating for
More informationCandidate Information Pack. Clinical Lead Plastic Surgery & Burns
Candidate Information Pack Clinical Lead Plastic Surgery & Burns Welcome from Professor Tim Briggs, National Director of Clinical Quality & Efficiency and Clinical Chair of the GIRFT Programme The original
More informationEAST KENT HOSPITALS UNIVERSITY NHS FOUNDATION TRUST
EAST KENT HOSPITALS UNIVERSITY NHS FOUNDATION TRUST REPORT TO: BOARD OF DIRECTORS MEETING DATE: 29 JANUARY 2015 SUBJECT: REPORT FROM: PURPOSE: CQC ACTION PLAN CHAIR OF IMPROVEMENT PLAN DELIVERY BOARD Discussion
More information21 March NHS Providers ON THE DAY BRIEFING Page 1
21 March 2018 NHS Providers ON THE DAY BRIEFING Page 1 2016-17 (Revised) 2017-18 (Revised) 2018-19 2019-20 (Indicative budget) 2020-21 (Indicative budget) Total revenue budget ( m) 106,528 110,002 114,269
More informationService Level Agreements for
99/06 Service Level Agreements for 2006 07 1. This paper summarises the outcome of discussions with commissioning PCTs for the year 2006 07. Whilst there are some areas of detail yet to be agreed with
More informationAneurin Bevan University Health Board. Professional Revalidation
28 th January 20 Aneurin Bevan University Health Board Professional Revalidation Purpose of the Report: The purpose of this paper is to provide the Board with an update in relation to the Nursing Revalidation
More informationNHS Vacancy Statistics. England, February 2015 to October 2015 Provisional experimental statistics
NHS Vacancy Statistics England, February 2015 to October 2015 Provisional experimental statistics Published 25 February 2016 We are the trusted national provider of high-quality information, data and IT
More informationOverall rating for this location Requires improvement
Riverdale Grange Clinic Quality Report 93 Riverdale Road Ranmoor Sheffield South Yorkshire S10 3FE Tel:0114 230 2140 Website:http://www.riverdalegrange.co.uk Date of inspection visit: 9 August 2017 Date
More informationREGISTERED NURSE Cohort Recruitment Band 5 Women & Children s Sector, Obstetrics and Gynaecology
REGISTERED NURSE Cohort Recruitment Band 5 Women & Children s Sector, Obstetrics and Gynaecology Job Reference: 0000051650N Closing Date: 26 th July 2018 Dear applicant, Thank you for your interest in
More informationRedesign of Front Door
Redesign of Front Door Transforming Acute and Urgent Care Strategic Background and Context Our Change and Improvement Programme What have we achieved and how? What did we learn? Ian Aitken, General Manager
More informationDebbie Vogler, Director of Business & Enterprise. Kate Shaw, Associate Director of Service Transformation
Reporting to: Trust Board 24 September 2015 Paper 5 Title Sponsoring Director Author(s) Future Configuration of Hospital Services - Post-Project Evaluation Debbie Vogler, Director of Business & Enterprise
More informationCCG authorisation Case Study Template NHS Croydon Clinical Commissioning Group. Urgent Care Redesign
CCG name: CCG authorisation Case Study Template NHS Croydon Clinical Commissioning Group Case study title: Urgent Care Redesign CCG case study number: (specify 1 to 5) Does the case study provide core
More informationA Successful Health Visitor Retention Strategy - Walsall Healthcare NHS Trust
A Successful Health Visitor Retention Strategy - Walsall Healthcare NHS Trust Health Visiting Local Picture Population of approx 21,000 under 5s 10 Health Visitor Teams across the borough New model of
More informationLessons from NHS Connecting for Health. Dr. Maureen Baker CBE DM FRCGP Clinical Director for Patient Safety NHS Connecting for Health
Lessons from NHS Connecting for Health Dr. Maureen Baker CBE DM FRCGP Clinical Director for Patient Safety NHS Connecting for Health Stuart Harrison, Senior Safety Engineer NHS Connecting for Health Overview
More informationIain Patterson. Associate Workforce Director Homerton University Hospital NHS Foundation Trust
Iain Patterson Associate Workforce Director Homerton University Hospital NHS Foundation Trust Who we are? Who we are? North East London Sector 3,800 staff spread across Hackney and beyond c. 3,000 acute
More information3. ORGANISATIONAL POSITION
JOB DESCRIPTION 1. JOB DETAILS Job Title: Responsible to: Appointment Co-ordinator, Days and Evenings Team Supervisor - Operational Department & Base: Job Reference Number: IM&T Health Information Management
More informationDELIVERING THE LONDON QUALITY STANDARDS AND 7 DAY SERVICES
Enclosure I DELIVERING THE LONDON QUALITY STANDARDS AND 7 DAY SERVICES Trust Board Meeting Item: 13 Date: 25 th May 2016 Purpose of the Report: Enclosure: I To update the Board on the Trust s current performance
More informationReducing errors with epma electronic Prescribing and Medicines Administration. Stockport NHS Foundation Trust December 2013
Reducing errors with epma electronic Prescribing and Medicines Administration Stockport NHS Foundation Trust December 2013 Introductions Helen Bennett Asst Director: IT Programme Mangement Sarah Campbell
More informationReport by Iain Ross, Head of ehealth on behalf of Deborah Jones, Director of Strategic Commissioning, Planning and Performance
UPDATE ON ehealth NHS Highland Board 28 November 2017 Item 4.1 Report by Iain Ross, Head of ehealth on behalf of Deborah Jones, Director of Strategic Commissioning, Planning and Performance The Board asked
More informationRTT Recovery Planning and Trajectory Development: A Cambridge Tale
RTT Recovery Planning and Trajectory Development: A Cambridge Tale Linda Clarke Head of Operational Performance Addenbrooke s Hospital I Rosie Hospital Apr 2014 May 2014 Jun 2014 Jul 2014 Aug 2014 Sep
More informationCranbrook a healthy new town: health and wellbeing strategy
Cranbrook a healthy new town: health and wellbeing strategy 2016 2028 Executive Summary 1 1. Introduction: why this strategy is needed, its vision and audience Neighbourhoods and communities are the building
More informationUpdate on implementation of the PPI Strategy
UNIVERSITY HOSPITALS OF LEICESTER NHS TRUST TRUST BOARD 3 DECEMBER 2015 Author: [insert] Sponsor: [insert] Date: [MM/YY] PAGE 1 OF 3 Update on implementation of the PPI Strategy Author: [insert] Sponsor:
More informationInternal Audit. Health and Safety Governance. November Report Assessment
November 2015 Report Assessment G G G A G This report has been prepared solely for internal use as part of NHS Lothian s internal audit service. No part of this report should be made available, quoted
More informationNHS SERVICE DELIVERY AND ORGANISATION R&D PROGRAMME PROGRAMME OF RESEARCH ON EVALUATING MODELS OF SERVICE DELIVERY
NHS SERVICE DELIVERY AND ORGANISATION R&D PROGRAMME PROGRAMME OF RESEARCH ON EVALUATING MODELS OF SERVICE DELIVERY EVALUATION OF CONFIGURING HOSPITALS PILOTS Background There is currently a wide-ranging
More informationLearning from Patient Deaths: Update on Implementation and Reporting of Data: 5 th January 2018
Learning from Patient Deaths: Update on Implementation and Reporting of Data: 5 th January 218 Purpose The purpose of this paper is to update the Trust Board on progress with implementing the mandatory
More informationINCENTIVE SCHEMES & SERVICE LEVEL AGREEMENTS
MAY 2007 INCENTIVE SCHEMES & SERVICE LEVEL AGREEMENTS Practice Based Commissioning North and South Essex Local Medical Committees CLARIFYING THE RELATIONSHIP BETWEEN PBC GROUPS AND PCTS AIMS The aim of
More informationJOB DESCRIPTION. Clinical Service Manager. General Manager A&C916
JOB DESCRIPTION 1. JOB DETAILS Job Title: Responsible to: Department & Base: Clinical Service Manager General Manager Primary and Community Services Roxburgh Street Date this JD written/updated: March
More informationSystmOne COMMUNITY OPERATIONAL GUIDELINES
SystmOne COMMUNITY OPERATIONAL GUIDELINES Guidelines IM&T 11 Date: August 2007 Document Management Title of document SystmOne Community Operational Guidelines Type of document Guidelines IM&T 11 Description
More informationVanguard Programme: Acute Care Collaboration Value Proposition
Vanguard Programme: Acute Care Collaboration Value Proposition 2015-16 November 2015 Version: 1 30 November 2015 ACC Vanguard: Moorfields Eye Hospital Value Proposition 1 Contents Section Page Section
More informationANEURIN BEVAN HEALTH BOARD DELIVERING END OF LIFE CARE
ANEURIN BEVAN HEALTH BOARD DELIVERING END OF LIFE CARE 2013-2016 1. INTRODUCTION The 5 Year NHS Plan, Together for Health, sets out the programme for health & healthcare in Wales and Together for Health
More informationHelping healthcare: How Clinical Desktop can enrich patient care
Helping healthcare: How Clinical Desktop can enrich patient care Microsoft UK, 2013 Technology should essentially be about delivering benefits for the whole Trust, from clinical staff using the desktop
More informationREGISTERED NURSE Cohort Recruitment Band 5 Regional Sector
REGISTERED NURSE Cohort Recruitment Band 5 Regional Sector Job Reference: 0000050985N Closing Date: 30 th March 2018 Dear applicant, Thank you for your interest in working for NHS Greater Glasgow and Clyde
More informationSuRNICC Full Business Case. Benefits Realisation Strategy and Framework
SuRNICC Full Business Case Benefits Realisation Strategy and Framework Purpose The purpose of this document is to set out the arrangements for the identification of potential benefits, their planning,
More informationSUPPORT FOR VULNERABLE GP PRACTICES: PILOT PROGRAMME
Publications Gateway Reference 04476 For the attention of: NHS England Directors of Commissioning Operations Clinical Leaders and Accountable Officers, NHS Clinical Commissioning Groups Copy: NHS England
More informationTitle Open and Honest Staffing Report April 2016
Title Open and Honest Staffing Report April 2016 File location WILJ2102 Meeting Board of Directors Date 25 th May 2016 Executive Summary This paper provides a stocktake on the position of South Tyneside
More informationLearning from adverse events. Learning and improvement summary
Learning from adverse events Learning and improvement summary November 2014 Healthcare Improvement Scotland 2014 Published November 2014 You can copy or reproduce the information in this document for use
More informationHard Truths Public Board 29th September, 2016
Hard Truths Public Board 29th September, 2016 Presented for: Presented by: Author Previous Committees Governance Professor Suzanne Hinchliffe CBE, Chief Nurse/Deputy Chief Executive Heather McClelland
More informationBriefing: NIB Priority Domains
Briefing: NIB Priority Domains Update on the Roadmaps June 2015 Following the publication of the Five Year Forward View and the Framework Personalised Health and Care 2020, the National Information Board
More informationLorenzo for clinical outcomes transformation? Ben Bridgewater
Lorenzo for clinical outcomes transformation? Ben Bridgewater Global Trends - Outcomes and Transformation: The Landscape The problems The obstacles The solutions Ageing population and consumerism Increasing
More informationStandardising Acute and Specialised Care Theme 3 Governance and Approach to Hospital Based Services Strategy Overview 28 th July 2017
Standardising Acute and Specialised Care Theme 3 Governance and Approach to Hospital Based Services Strategy Overview 28 th July 2017 Background Theme 3 builds upon previous key strategic commissioning
More information