ENERGY SECTOR ROADWAY REPAIR PROJECT & OTHER HOUSE BILL FUNDED PROJECTS
|
|
- Dorcas Maxwell
- 5 years ago
- Views:
Transcription
1 ENERGY SECTOR ROADWAY REPAIR PROJECT & OTHER HOUSE BILL FUNDED PROJECTS Texas Transportation Commission Meeting December 19, 2013
2 Scope Base Scope Reconstruction, rehabilitation, restoration and/or resurfacing of roadways and/or bridges Design plans provided by TxDOT for optional use Four Districts Corpus Christi, Laredo, San Antonio and Yoakum 31 Locations Total Maximum 540 days after Notice to Proceed (NTP) 1 substantial completion schedule 2
3 Procurement History August 2, 2013 Issued Request for Qualifications (RFQ) September 23, 2013 Short-listed four of the seven proposers September 27, 2013 Issued Request for Proposals (RFP) November 20, 2013 Received four technical proposals December 4, 2013 Received four price proposals Recommend Conditional Award 3
4 Submitted Proposal Austin-Angel, JV* Equity owner: Austin-Angel, JV - Austin Bridge and Road, L.P. - Angel Brothers Enterprises, LTD Major non-equity members and other team members: Burns & McDonnell Engineering Company Inc. Fugro Consultants Inc. A.L. Helmcamp Inc. Bay Ltd. H.L. Zumwalt James Construction Group Salinas Construction Technologies ACI Consulting Gorronda & Associates Inc. ETTL Engineers & Consultants Inc. *alphabetical order 4
5 Submitted Proposal Hunter Anderson Joint Venture* Equity owner: Hunter Anderson Joint Venture - Hunter Industries, Ltd. - Anderson Columbia Co., Inc. Major non-equity members and other team members: LNV Inc. Pave Tex Engineering and Testing Inc. Brannon Paving Company Ltd. Foremost Paving Inc. Rock Engineering and Testing Laboratory Inc. Costello Inc. Haas-Anderson Construction Ltd. Ray Faris Inc. Rexco Inc. Don Durden Inc. dba Civil Engineering Consultants Colorado Materials, Ltd. *alphabetical order 5
6 Submitted Proposal Kiewit Infrastructure South, Co.* Equity owner: Kiewit Infrastructure South, Co. Major non-equity members and other team members: H.W. Lochner Inc. Lamb Star Engineering LP Intermountain Slurry Seal Inc. Corsair Consulting Cox McLain Environmental Consultant Cobb Fendley & Associates Inc. CivilCorp *alphabetical order 6
7 Submitted Proposal Zachry-Parsons Eagle Ford Infrastructure Partners* Equity owner: Zachry-Parsons Eagle Ford Infrastructure Partners - Zachry Construction Corporation - Parsons Transportation Group, Inc. Major non-equity members and other team members: Poznecki Camarillo Inc. Arias & Associates Inc. Transtec Group Inc. Kleinfelder Central Inc. *alphabetical order 7
8 Evaluation Implemented a pre-established and rigorous procedure to evaluate and select the proposal that offers the best value Separate pass/fail, technical and price evaluations Evaluation subcommittees provided scoring recommendations to the Evaluation Selection Recommendation Committee (ESRC) ESRC provided scoring recommendations to the Project Steering Committee Project Steering Committee reviewed ESRC recommendation 8
9 Scoring Price includes design and construction Technical score is based upon Technical Solutions as well as the Project Management, Quality Management, Delivery Schedule and Safety & Health Plans. Best Value Scoring: Price 90 points + Technical 10 points Maximum 100 points 9
10 Scoring DB Price Score = 90 points 70% number of Base Scope Locations 15% Base DB Price 15% Total Scope DB Price Technical Score = 10 points 40% Preliminary Project Baseline schedule 60% Project Development Plan & Safety 10
11 Evaluation Results Summary Detailed evaluations resulting in 11
12 Best Value Recommendation Equity owner: Austin-Angel, JV (Score of pts) - Austin Bridge and Road, L.P. - Angel Brothers Enterprises, LTD Major non-equity members and other team members: Burns & McDonnell Engineering Company Inc. Fugro Consultants Inc. A.L. Helmcamp Inc. Bay Ltd. H.L. Zumwalt James Construction Group Salinas Construction Technologies ACI Consulting Gorronda & Associates Inc. ETTL Engineers & Consultants Inc. 12
13 Evaluation Results Summary Austin-Angel, JV pts Hunter Anderson Joint Venture pts Kiewit Infrastructure South, Co pts Zachry-Parsons Eagle Ford Infrastructure Partners pts 13
14 Evaluation Results Summary Austin-Angel, JV Base Scope Design-Build Price (27 of 31 Locations): $ 149,995,000 Additional Locations Design-Build Price (4 Locations): $ 32,875,500 Total Price: $ 182,870,500 14
15 Evaluation Results Summary Austin-Angel, JV Base bid of 27 Locations: Total bid of 31 Locations: 540 Days 540 Days 15
16 Next Steps Negotiate final terms of design-build contract and assemble other documents necessary for commercial close Execute DB contract at commercial close Issue NTP1 Base Scope (27 Locations) construction substantial completion within 540-days after NTP1 Total Scope (31 Locations) construction substantial completion within 540-days after NTP1 16
17 Other House Bill 1025-Funded Project Status District Let Projects $75M allocated 5 Districts 11 Projects Award Amount Amarillo 1 project (September) $16.9M Corpus Christi 1 project (October) $7.7M Lubbock TOTAL AWARD AMOUNT $ 83,196,808 2 projects (October) $6.4M Odessa 3 projects (November) $18.0M San Angelo 4 projects (October, November, December) $34.2M 17
18 Questions? Staff recommends and requests Commission approval of this minute order. 18
Design-Build Procurement Overview Manual. Alternative Project Delivery
Design-Build Procurement Overview Manual Alternative Project Delivery Table of Contents Chapter 1: Introduction to Design-Build Procurements... 1 1.1 Introduction... 1 1.2 Scope... 1 1.3 Acronyms... 2
More informationMonthly Review of the Texas Economy November 2013
Monthly Review of the Texas Economy November 3 By Ali Anari and Mark G. Dotzour The Texas economy gained 67,9 nonagricultural jobs from October to October 3, an annual growth rate of. percent compared
More informationMonthly Review of the Texas Economy
AT TEXAS A&M UNIVERSITY Monthly Review of the Texas Economy By Ali Anari, Research Economist Mark G. Dotzour, Chief Economist TECHNICAL REPORT 1 8 APRIL 13 TR Monthly Review of the Texas Economy April
More informationRAMP Session Amy Slaughter RAMP Grant Program Manager TxDOT Aviation Division March 28, 2018
TxDOT Aviation RAMP Session Amy Slaughter RAMP Grant Program Manager TxDOT Aviation Division March 28, 2018 Conference Evaluations A member of staff will be walking around to gather your conference evaluations.
More informationOperations & Maintenance
SUMMARY STATEMENT ITEM NO.: DRPA-17-049 COMMITTEE: SUBJECT: Design Services for Benjamin Franklin Bridge Deck Resurfacing Operations & Maintenance COMMITTEE MEETING DATE: July 11, 2017 BOARD ACTION DATE:
More informationMonthly Review of the Texas Economy May 2012
Monthly Review of the Texas Economy May 1 The Texas economy created 1,5 nonagricultural jobs from April 11 to April 1, an annual growth rate of percent compared with 1.3 percent for the United States (Table
More informationAT TEXAS A&M UNIVERSITY. By Ali Anari, Research Economist Mark G. Dotzour, Chief Economist TECHNICAL REPORT
AT TEXAS A&M UNIVERSITY Monthly Review of the Texas Economy By Ali Anari, Research Economist Mark G. Dotzour, Chief Economist TECHNICAL REPORT 1 8 6 APRIL 11 TR Monthly Review of the Texas Economy April
More informationNEPA PUBLIC INVOLVEMENT
NEPA PUBLIC INVOLVEMENT Anita Bradley, Environmental Affairs Division TxDOT Environmental Conference 2017 Table of Contents 1 What is TxDOT role in NEPA and What is Public Involvement 2 85 th State Legislature
More informationAugust 2007 Thomas Bohuslav Texas Department of Transportation
Public Private Partnerships Activities in Texas AASHTO SOC 2007 Summer Meeting Biloxi Mississippi August 2007 Thomas Bohuslav Texas Department of Transportation Topics The Problem (Needs) Comprehensive
More informationTexas Department of Transportation
Texas Department of Transportation DEWITT C. GREER STATE HIGHWAY BLDG 125 E. 11TH STREET AUSTIN, TEXAS 78701-2483' (512) 463-8585 September 28, 2009 Mary Katherine Stout Director of Budget, Planning &
More informationMassachusetts Bay Transportation Authority. POLICIES & PROCEDURES Design Build Procurement Procedures April 2016
Massachusetts Bay Transportation Authority POLICIES & PROCEDURES Design Build Procurement Procedures April 2016 Design Build Procurement Procedures April 2016 Massachusetts Bay Transportation Authority
More informationREQUEST FOR QUALIFICATIONS CONSULTING ENGINEERING SERVICES LLANO COUNTY
REQUEST FOR QUALIFICATIONS FOR CONSULTING ENGINEERING SERVICES 18-401-02 LLANO COUNTY LLANO COUNTY 1447 E. State Highway 71, Unit B Llano, TX 78643 325-247-3783 1 TABLE OF CONTENTS Page Introduction 3
More informationTransportation Planning Policy Manual
Transportation Planning Policy Manual September 2001 Transportation Planning Policy Manual September 2001 Manual Notices Manual Notice 2001-1 To: From: Manual: Districts, Divisions and Offices Kirby W.
More informationEagle Project Update
Construction of Peña Bridge November 2012 Eagle Project Update Eagle P3 Project Update Rick Clarke Assistant General Manager, Capital Programs March 5, 2014 Regional Transportation District (RTD) Performs
More informationExhibit A DEFINITIONS AND ACRONYMS
Exhibit A DEFINITIONS AND ACRONYMS Addenda/Addendum means supplemental additions, deletions, and modifications to the provisions of the RFP after the release date of the RFP. Alternative Technical Concepts
More informationCONTRACTING AND PURCHASING
CONTRACTING AND PURCHASING 2017 Educational Series CONTRACTING AND PURCHASING INTRODUCTION GOODS AND SERVICES Texas Department of Transportation (TxDOT) contracting activities are established and controlled
More informationHigher Education continues to grow at record paces Preliminary fall enrollment figures indicate record growth in 2009 was no fluke
Andy Kesling External Relations (512) 427-6119 (512) 427-6111 1200 East Anderson Lane P.O. Box 12788, Austin, Texas 78711-2788 www.thecb.state.tx.us Higher Education continues to grow at record paces Preliminary
More informationConstruction Management (CM) Procedures
Chapter 28. Construction Management (CM) Procedures Summary This chapter outlines the procedures to be followed by all departments, agencies, and institutions of the County (each of which is hereinafter
More informationAn ongoing research program at the Real Estate Center. Texas Job Market Outpaces Nation's
Texas Job Market Outpaces Nation's Ali Anari June, 2015 Publication 2104 An ongoing research program at the Real Estate Center monitors the performance of the Texas economy visà-vis the U.S. economy and
More informationDPW Highways Program Updates Presentation to the Guam Contractors Association Membership June 16, 2010
+ DPW Highways Program Updates 2010-2011 Presentation to the Guam Contractors Association Membership June 16, 2010 + DPW Highways Vision Statement To provide a safe, efficient and sustainable transportation
More informationREQUEST FOR QUALIFICATIONS (RFQ) AIRPORT ARCHITECTURAL AND ENGINEERING SERVICES AGREEMENT MINOT INTERNATIONAL AIRPORT
REQUEST FOR QUALIFICATIONS (RFQ) AIRPORT ARCHITECTURAL AND ENGINEERING SERVICES AGREEMENT MINOT INTERNATIONAL AIRPORT 2016-2021 GENERAL The intent and purpose of this Request for Qualifications (RFQ) is
More informationA DEFINITIONS AND ACRONYMS
Exhibit A DEFINITIONS AND ACRONYMS Addenda/Addendum means supplemental additions, deletions, and modifications to the provisions of the RFP after the release date of the RFP. Adjusted Available Public
More informationA DEFINITIONS AND ACRONYMS
Exhibit A DEFINITIONS AND ACRONYMS Addenda/Addendum means supplemental additions, deletions, and modifications to the provisions of the RFP after the release date of the RFP. Adjusted Available Public
More informationTexan Club. Are we satisfied being a top regional institution (in all respects) if provided the opportunity to become nationally relevant?
Texan Club A University support group of more than 400 corporate and individual members providing scholarships and other support of Tarleton athletics and student pride for 30 years. Texan Club Board is
More informationInternal Audit Follow-Up Report
Internal Audit Follow-Up Report Local Government Project Oversight TxDOT Internal Audit Division Objective Assess the status of corrective actions for high-risk Management Action Plans (MAPs) previously
More informationVista Ridge Integration Project Owner s Representative
Vista Ridge Integration Project Owner s Representative Andrea Beymer, P.E. Director Plants & Major Projects Rosalee Arcos Contract Administrator Marisol Robles SMWB Program Administrator SOQ Pre-Submittal
More informationTexas Department of Transportation Corpus Christi District
Texas Department of Transportation Corpus Christi District U.S. 181 Harbor Bridge Project Environmental Documentation and Schematic Development Public Scoping Meeting August 9, 2011 Welcome John A. Casey,
More informationCRENSHAW/LAX TRANSIT CORRIDOR PROJECT: A New Beginning for the Crenshaw Corridor Through Use of Innovative Procurement Strategies
CRENSHAW/LAX TRANSIT CORRIDOR PROJECT: A New Beginning for the Crenshaw Corridor Through Use of Innovative Procurement Strategies Robert Ball, PE Kimberly Ong, PE Los Angeles Metropolitan Transportation
More informationState Supported Living Centers
State Supported Living Centers A. Provide the following information at the beginning of each program description. Name of Program or Function State Supported Living Centers (SSLCs) Location/Division 701
More informationOHIO TURNPIKE AND INFRASTRUCTURE COMMISSION
OHIO TURNPIKE AND INFRASTRUCTURE COMMISSION REQUEST FOR PROPOSALS ( RFP ) PROFESSIONAL ENGINEERING AND CONSTRUCTION ADMINISTRATION AND INSPECTION SERVICES REF: REHABILITATION OF VARIOUS BRIDGES AT MILEPOSTS
More informationCity of Arlington, Texas LOCAL & MWBE POLICY
City of Arlington, Texas LOCAL & MWBE POLICY December 3, 2013 LOCAL & MWBE POLICY TABLE OF CONTENTS SECTION HEADING PAGE NO. 1.0 Governing Authority 2 2.0 Purpose and Scope 2 3.0 Objectives 2 3.1 General
More information2017 TxDOT Professional Engineering Procurement Services Conference November 3, 2017
2017 TxDOT Professional Engineering Procurement Services Conference November 3, 2017 Omni Austin Hotel Southpark 4140 Governor s Row Austin, Texas 78744 MORNING SCHEDULE 7:30 a.m. 8:30 a.m. REGISTRATION,
More informationFIS RENOVATION AND EXPANSION CONSTRUCTION MANAGER AT RISK (CMAR) SERVICES RFQ No.: H37-FISCMAR Table of Contents
FIS RENOVATION AND EXPANSION Table of Contents PART I GENERAL INFORMATION... 3 1.0 GENERAL INFORMATION... 3 2.0 PROGRAM BACKGROUND... 3 3.0 SCHEDULE... 6 4.0 SOLICITATION SCHEDULE... 6 PART II SCOPE OF
More informationUC Merced 2020 Project Overview. California Partnership for the San Joaquin Valley March 20, 2015
UC Merced 2020 Project Overview California Partnership for the San Joaquin Valley March 20, 2015 What was the rationale for establishing UC Merced? 1. Accommodate demand for the UC System 2. Enhance Higher
More informationREQUEST FOR STATEMENTS OF QUALIFICATIONS CONSTRUCTION MANAGEMENT AND INSPECTION SERVICES FOR CSJ: PASS-THROUGH FINANCE PROJECT
REQUEST FOR STATEMENTS OF QUALIFICATIONS CONSTRUCTION MANAGEMENT AND INSPECTION SERVICES FOR FM 471 (CULEBRA ROAD) KALLISON LANE TO FM 1560 CSJ: 0849-01-046 PASS-THROUGH FINANCE PROJECT Bexar County Public
More informationPART VI EVALUATION OF PROPOSALS, CONTRACT AWARD AND CONTRACT EXECUTION
PART VI EVALUATION OF PROPOSALS, CONTRACT AWARD AND CONTRACT EXECUTION SECTION TITLE N O P Evaluation of Proposals Contract Award Contract Execution 52 SECTION N EVALUATION OF PROPOSALS N.1 GENERAL Proposals
More informationTEXAS. Legend STRAHNET URBAN AREAS LA Gulf of Mexico. Last Updated: June Installations. Interstate STRAHNET Non-Interstate STRAHNET
TEXAS # Installations STRAHNET AMARILLO 40 Non- 287 27 WICHITA FALLS LUBBOCK 277 84 13 8 MIDLAND 10 1 NAVAL AIR STATION FORT WORTH JRB 2 NAVAL AIR STATION KINGSVILLE 3 RANDOLPH AIR FORCE BASE 4 FORT HOOD
More informationPublic Universities Peace Officer Exemption List
Public Universities Peace Officer Exemption List Universities Angelo State University Lamar University Midwestern State University Prairie View A&M University Specialization) Sam Houston State University
More informationThe University of Tennessee REQUEST FOR QUALIFICATIONS (RFQ)
The University of Tennessee REQUEST FOR QUALIFICATIONS (RFQ) DESIGNER for Energy and Environmental Science Research Bldg. (Ellington) (Planning) SBC No. 540/001-04-2013 UT Institute of Agriculture August
More information12% 6% 30% 12% 22% $ 8.0 - Statutory Tuition $15.4 - Fees $27.6 - Contracts & Grants $21.6 - Sales & Services $.8 - Investment Income $38.4 - State Appropriations $15.6 - Designated Tuition 1% 17% 10%
More informationREQUEST FOR PROPOSALS
REQUEST FOR PROPOSALS RFP # 17-03-14 MINOR MAINTENANCE AND REPAIRS (LIKE FOR LIKE) NOTE: This RFP replaces RFP #16-10-34 previously cancelled by the District. PART II The Houston Independent School District
More information8/30/ American Public Works Association (APWA) International Congress and Exposition. August 30, 2015
The Louisiana Department of Transportation and Development s Submerged Roads and Paths to Progress Programs: A Model for Future Disaster Recovery Efforts 2015 American Public Works Association (APWA) International
More informationRFP No.1-17-C033 Hydrant Fueling Cathodic Protection Phase I March 30, :00 PM
PRE-PROPOSAL CONFERENCE RFP No.1-17-C033 Hydrant Fueling Cathodic Protection Phase I March 30, 2017 1:00 PM Disclaimer The information contained in this presentation is for informational purposes only
More informationReport ALC/Review Subcommittee of the Arkansas Legislative Council
Report ALC/Review Subcommittee of the Arkansas Legislative Council November 21 st, 2014 Co-Chairs: The Review Subcommittee met on Monday, November 17 th, 2014 in Room A of the Big Mac Building and after
More informationDALLAS HORSESHOE PROJECT RFQ Q & A MATRIX #6. (February 14, 2012)
DALLAS HORSESHOE PROJECT RFQ Q & A MATRIX #6 (February 14, 2012) RFQ 1. Part A, Section 4.2(a), Page 6 2. Part A, Sections 4.2(b) & 4.2(c) Please confirm that financial requirements are to be provided
More informationTEXAS BOARD OF NURSING 333 Guadalupe #3-460 Austin, Texas REQUESTING SPECIAL ACCOMMODATIONS
333 Guadalupe #3-460 Austin, Texas 78701-3944 REQUESTING SPECIAL ACCOMMODATIONS In compliance with the Americans with Disabilities Act (ADA), the Texas Board of Nursing provides reasonable accommodations
More informationRequest for Proposal Engineering Consultant for City of Ingleside
Request for Proposal Engineering Consultant for Public Works and Building Services Departments Melissa Byrne Vossmer City Manager August 21, 2017 MAYOR AND CITY COUNCIL Luis Lamas, Mayor Oscar Adame, Mayor
More informationTRANSPORTATION RESEARCH BOARD. 85th ANNUAL MEETING
TRANSPORTATION RESEARCH BOARD 85th ANNUAL MEETING Panel on Public Private Initiatives: New Concepts in Transportation Project Delivery Recent Trends and Innovations January 23, 2006 Washington, DC GEOFFREY
More informationLSC-Kingwood. Institutions Attended, Fall 2009 Academic Students Community and Technical Colleges. LSC-Kingwood
Alamo Community College District 6 Alvin Community College 1 Angelina College 4 Austin Community College 21 Blinn College 64 Central Texas College 3 Cisco Junior College 1 Collin County Community College
More informationSmall County Outreach Program (SCOP)
State Fund Opportunities: Local Programs Small County Outreach Program (SCOP) The purpose of this program is to assist small county governments in repairing or rehabilitating county bridges, paving unpaved
More informationPost Acute Medical. Debra R Riegel, RN. Presented to: American Hospital Association
Post Acute Medical Debra R Riegel, RN Presented to: American Hospital Association 1 Introduction Debra R Riegel, RN, CRNP, MSN, CPC- Corporate Director of Appeals Management Post Acute Medical October
More informationANNUAL REQUEST FOR PROPOSAL(S) FOR SMALL URBAN AND NON URBANIZED PUBLIC TRANSPORTATION PROJECTS FOR VARIOUS PROGRAMS TABLE OF CONTENTS
ANNUAL REQUEST FOR PROPOSAL(S) FOR SMALL URBAN AND NON URBANIZED PUBLIC TRANSPORTATION PROJECTS FOR VARIOUS PROGRAMS TABLE OF CONTENTS Introduction... 2 Project Proposals and Due Dates... 3 TxDOT Contacts
More informationSTUDY AND ARCHITECTURAL DESIGN SERVICES
REQUEST FOR PROPOSALS For a FEASIBILITY STUDY AND ARCHITECTURAL DESIGN SERVICES For the Smugglers Notch Scenic Highway Corridor s Barnes Camp Visitor Center on VT Route 108 in Stowe, VT EA #: EH02030 Contract
More informationBASIN CITY WATER AND SEWER DISTRICT Request for Qualifications
BASIN CITY WATER AND SEWER DISTRICT for: LEON DRIVE AND ESTELLA DRIVE WATERLINE REPLACEMENT PROJECT Basin City Water and Sewer District (hereinafter called District ) is requesting Statements of Qualifications
More informationJob Order Contracting: An Alternative Delivery Method
Job Order Contracting: An Alternative Delivery Method 1 Construction Industry Challenges Only 2.5% of all global projects are delivered on time and on budget Only 25% of projects are completed within 10%
More informationThe funding will be provided by the Odessa Development Corporation. Business plan coaching will be provided by the SBDC.
History The idea to hold and fund a Business Plan Competition in Odessa, TX originated with the Midland Economic Development Corporation hosting an event March October 2017. Information came directly from
More informationHousing Rehabilitation Program Administration
February 3, 2016 REQUEST FOR PROPOSALS for Housing Rehabilitation Program Administration Thank you for considering the attached Request for Proposals (RFP). If you are interested in submitting a Proposal,
More informationREQUEST FOR QUALIFICATIONS FOR Energy Services Master Agreement
Request for Qualifications for Page 1 of 8 REQUEST FOR QUALIFICATIONS FOR For the RFQ Submittal Deadline: October 17, 2017 at 3:00 PM 1.1 INTRODUCTION: The is soliciting Statements of Qualifications (SOQ)
More informationSources of Funding Transit in Texas Final Report PRC
Sources of Funding Transit in Texas Final Report PRC 15-11.3 Sources of Funding Transit in Texas Texas A&M Transportation Institute PRC 15-11.3 Updated April 2018 Authors Linda Cherrington Shuman Tan Todd
More informationMay 22, Pamela Bailey-Campbell. Vice President - North America Infrastructure Consultancy Jacobs Engineering, Inc.
May 22, 2013 Pamela Bailey-Campbell Vice President - North America Infrastructure Consultancy Jacobs Engineering, Inc. Public Partners Arizona Department of Transportation Office of P3 Initiatives City
More informationCounty Transportation Infrastructure Fund Grant Program Frequently Asked Questions
County Transportation Infrastructure Fund Grant Program Frequently Asked Questions Updated Feb. 10, 2015 FREQUENTLY ASKED QUESTIONS County Transportation Infrastructure Fund Grant Program A. Deadlines
More informationTRINITY VALLEY COMMUNITY COLLEGE
1 of 5 Academic Students ACCD - Northwest Vista College 2 ACCD - San Antonio College 1 ACCD - St. Philip's College 1 Alvin Community College 2 Angelina College 5 Austin Community College 3 Blinn College
More informationPRE-SUBMITTAL CONFERENCE: AS NEEDED PUBLIC RELATIONS RFQ. Port of San Francisco, Pier 1 March 15, 2017
PRE-SUBMITTAL CONFERENCE: AS NEEDED PUBLIC RELATIONS RFQ Port of San Francisco, Pier 1 March 15, 2017 Agenda Introductions Background Scope of Work Proposal Submission Requirements Selection Process CMD
More information2007 PROFESSIONAL NURSING SHORTAGE REDUCTION PROGRAM
2007 PROFESSIONAL NURSING SHORTAGE REDUCTION PROGRAM Texas Higher Education Coordinating Board Division of Planning and Accountability P. O. Box 12788 Austin, Texas 78711 (512) 427-6138 http://www.thecb.state.tx.us
More informationREQUEST FOR QUALIFICATIONS PITTSBURGH INTERNATIONAL AIRPORT PROFESSIONAL ARCHITECTURAL AND ENGINEERING DESIGN AND CONSTRUCTION PHASE SERVICES FOR THE
REQUEST FOR QUALIFICATIONS PITTSBURGH INTERNATIONAL AIRPORT PROFESSIONAL ARCHITECTURAL AND ENGINEERING DESIGN AND CONSTRUCTION PHASE SERVICES FOR THE TERMINAL MODERNIZATION PROGRAM The Allegheny County
More informationCITY OF HONDO ENGINEERING REQUEST FOR QUALIFICATIONS
CITY OF HONDO ENGINEERING REQUEST FOR QUALIFICATIONS The City of Hondo requests the submission of qualifications statements, which will lead to the possible award of a contract to provide planning, design
More informationDesign Build Phase II Service Center Project
Design Build Phase II Service Center Project Diana L. Woltersdorf Manager, Contract Administration Julie Valadez, AIA Project Manager, Vertical Construction September 30, 2016 Pre-Submittal Meeting Pre-Submittal
More informationEDGEWOOD INDEPENDENT SCHOOL DISTRICT
EDGEWOOD INDEPENDENT SCHOOL DISTRICT RFQ 13-006 Design Build Services for Central Administration Building Owner: Edgewood Independent School District, 5358 W. Commerce Street, San Antonio, TX 78237 Contact
More informationAddendum No. 2 April 15, 2015 Architectural Design Services Requirements Contracts Request for Qualifications Project No.
Facilities Planning, Construction, and Management Office of Financial Management Procurement Services 555 West 57 th Street 16 th Floor New York, NY 10019 Tel: 646-664-2700 Addendum 2 April 15, 2015 Architectural
More informationHouse Defense and Veteran s Affairs HB 19: Military & Veteran Family Pilot Program
House Defense and Veteran s Affairs HB 19: Military & Veteran Family Pilot Program Sasha Rasco, Assistant Commissioner, PEI June 2, 2016 The mission of the Department of Family and Protective Services
More informationCAPITAL AREA METROPOLITAN PLANNING ORGANIZATION REQUEST FOR QUALIFICATIONS (RFQ)
CAPITAL AREA METROPOLITAN PLANNING ORGANIZATION REQUEST FOR QUALIFICATIONS (RFQ) SOLICITATION NO: NV-001 DATE ISSUED: March 5, 2018 SERVICE DESCRIPTION: Transportation Planning: Luling Relief Route Study
More informationRequest for Statements Qualifications(RFQ) For
Request for Statements Qualifications(RFQ) For Master List Engineering Services Civil, Structural, and Environmental Engineering and Local, State, and Federal Water Planning/Contract Execution for Water
More informationFlat Rock Greenway Feasibility Study A REQUEST FOR PROPOSALS
Flat Rock Greenway Feasibility Study A REQUEST FOR PROPOSALS The Village of Flat Rock French Broad River MPO December 11, 2017 Introduction and Overview The Village of Flat Rock and the French Broad River
More informationCALIFORNIA HIGH-SPEED RAIL DIANA GOMEZ
CALIFORNIA HIGH-SPEED RAIL HIGH-SPEED RAIL PROJECT OVERVIEW P R E S E N T E D B Y DIANA GOMEZ CENTRAL VALLEY REGIONAL DIRECTOR FRESNO COUNTY EMPLOYEES RETIREMENT ASSOCIATION SEPTEMBER 18, 2013 FRESNO,
More informationChabot-Las Positas Community College District
Chabot-Las Positas Community College District REQUEST FOR STATEMENT OF QUALIFICATIONS (RFQ) ARCHITECTURAL/ENGINEERING DESIGN SERVICES FOR THE CHABOT AND LAS POSITAS COLLEGES RFQ C-14 Proposal Due: TUESDAY,
More informationSouth Central Service Center
South Central Service Center Christopher C. Janssen, CFEI, CVFI, CFE Fire Investigator San Antonio, Texas 361-960-1769 cjanssen@uis-usa.com EDUCATION: Texas A&M University Corpus Christi, Texas Bachelor
More informationFirst Generation College Student Initiatives. A Report on the Initial Phase of the First Generation College Student Grants Program.
First Generation College Student Initiatives A Report on the Initial Phase of the First Generation College Student Grants Program Fiscal Year 2004 Texas Higher Education Coordinating Board Division of
More informationProject Brief. for. Kitsilano Secondary School Renewal
for Kitsilano Secondary School Renewal May 18, 2012 Page i TABLE OF CONTENTS 1 INTRODUCTION... 1 1.1 Purpose of this... 1 2 THE BUSINESS OPPORTUNITY... 2 3 THE PROJECT... 3 3.1 Background to the Project...
More informationLessons Learned for a Transit Public-Private Partnership. Phillip A. Washington, General Manager Regional Transportation District
Lessons Learned for a Transit Public-Private Partnership Phillip A. Washington, General Manager Regional Transportation District Feb. 7, 2011 The RTD FasTracks Plan 122 miles of new light rail and commuter
More informationMEMORANDUM. July 7, 2016
MEMORANDUM July 7, 2016 TO: FROM: MEMBERS, PORT COMMISSION Hon. Willie Adams, President Hon. Kimberly Brandon, Vice President Hon. Leslie Katz Hon. Eleni Kounalakis Hon. Doreen Woo Ho Elaine Forbes Interim
More informationREQUEST FOR PROPOSALS
REQUEST FOR PROPOSALS FOR CONSTRUCTION MANAGEMENT SERVICES FACILITIES MODERNIZATION PROJECTS LOS ANGELES UNIFIED SCHOOL DISTRICT FACILITIES SERVICES DIVISION March 14, 2002 REQUEST FOR PROPOSALS FOR CONSTRUCTION
More informationDBE/Small Business Workshop. June 12, 2015
DBE/Small Business Workshop June 12, 2015 Learning Objectives Benefits Purpose Eligibility Criteria Procurement Forecasts SunLine s Procurement Process Fostering Small Business What are the benefits of
More informationPARTNERSHIPS ACCELERATE ECONOMIC DEVELOPMENT & JOB CREATION. J. Douglas Koelemay, Director
PARTNERSHIPS ACCELERATE ECONOMIC DEVELOPMENT & JOB CREATION J. Douglas Koelemay, Director VIRGINIA LEADERSHIP IN PUBLIC-PRIVATE PARTNERSHIPS PPTA enabling legislation 1995 2001, 2005, 2008 Revisions to
More informationI-225 Light Rail Design/Build/Finance Staff Recommendation. RTD FasTracks Monitoring Committee July 3, 2012
I-225 Light Rail Design/Build/Finance Staff Recommendation RTD FasTracks Monitoring Committee July 3, 2012 FasTracks Guiding Principles Staff relied heavily on our Guiding Principles to develop our recommended
More informationGEORGE MASSEY TUNNEL REPLACEMENT PROJECT
COMBINED MONTHLY AND QUARTERLY PROGRESS REPORT FOR QUARTER ENDING JUNE 30, 2014 GEORGE MASSEY TUNNEL MONTHLY STATUS REPORT JANUARY 2017 FINAL PROJECT STATUS DASHBOARD Scope Status* Reference concept includes
More informationHIGHER EDUCATION REGIONAL COUNCILS
HIGHER EDUCATION REGIONAL COUNCILS 2018 REGION 1 HIGH PLAINS HIGHER EDUCATION REGIONAL COUNCIL CHAIR: Robin Satterwhite, Ed.D. President South Plains College P O Box 7 Levelland, TX 79336 (806) 716-2200
More informationREQUEST FOR INFORMATION REGARDING AN INNOVATIVE PROJECT DELIVERY APPROACH FOR FULL SERVICE COMMERCIAL DRIVER/VEHICLE SERVICES CENTER AND
REQUEST FOR INFORMATION REGARDING AN INNOVATIVE PROJECT DELIVERY APPROACH FOR FULL SERVICE COMMERCIAL DRIVER/VEHICLE SERVICES CENTER AND CAPITAL AREA TRANSIT ADMINISTRATION, OPERATION, AND MAINTENANCE
More information2017 ANNUAL CONFERENCE & LEADERSHIP MEETING REQUEST FOR PROPOSALS
2017 ANNUAL CONFERENCE & LEADERSHIP MEETING REQUEST FOR PROPOSALS Introduction This is a request for proposal (RFP) for cities interested in hosting the 2017 Sister Cities International Annual Conference.
More informationCITY OF PORTSMOUTH NEW HAMPSHIRE Department of Public Works
CITY OF PORTSMOUTH NEW HAMPSHIRE Department of Public Works RFP #33-11 REQUEST FOR PROPOSALS ENGINEERING SERVICES MECHANIC STREET SEAWALL AT PICKERING DESIGN PROJECT The City of Portsmouth, New Hampshire
More information2018 Pipelines Engineering Services Boerne Stage Road, West Avenue, and Highway 90 & General McMullen
2018 Pipelines Engineering Services Boerne Stage Road, West Avenue, and Highway 90 & General McMullen M. Antonio Leyva, P.E. Manager Engineering Angelica Mata Manager Contract Administration Marisol V.
More informationPART G EVALUATION CRITERIA, CONTRACT AWARD AND CONTRACT EXECUTION
PART G EVALUATION CRITERIA, CONTRACT AWARD AND CONTRACT EXECUTION SECTION TITLE 22. Evaluation Criteria 23. Contract Award 24. Contract Execution 139 SECTION 22 EVALUATION CRITERIA 22.1 EVALUATION CRITERIA
More informationRequest for Interest Property Refurbishment & Ownership. La Niña Caravel Replica
Request for Interest Property Refurbishment & Ownership La Niña Caravel Replica Lawrence Street T-Head 400 A North Shoreline Blvd. Corpus Christi, Texas 78401 Deadline: September 28 th, 2018 at 5:00 pm
More informationCHESAPEAKE BAY BRIDGE AND TUNNEL DISTRICT PARALLEL THIMBLE SHOAL TUNNEL REQUEST FOR QUALIFICATIONS #PTST-15-1
CHESAPEAKE BAY BRIDGE AND TUNNEL DISTRICT PARALLEL THIMBLE SHOAL TUNNEL REQUEST FOR QUALIFICATIONS #PTST-15-1 TO: FROM: All Offerors Chesapeake Bay Bridge and Tunnel District SUBJECT: Addendum No. 1 Request
More informationAMENDMENT TO ADVERTISED CONTRACT
March 16, 2015 AMENDMENT TO VERTISED CONTRACT CONTRACT I.D. NUMBER: B14884-15-000-1 GEORGIA PROJECT NUMBER: 0010925 PCN: 0010925 COUNTY: FULTON AMENDMENT NUMBER: 7 LETTING DATE: MARCH 20, 2015 LETTING
More informationADDENDUM # /JSW Professional Engineering Services to Test, Adjust, and Balance HVAC Systems
ADDENDUM #2 537220/JSW Professional Engineering Services to Test, Adjust, and Balance HVAC Systems Bid Closing: 3/26/12 at 2:00 PM Date: March 19, 2012 BIDS MUST BE SUBMITTED ON OR ATTACHED TO THIS SIGNED
More informationMEMORANDUM July 17, 2017
MEMORANDUM July 17, 2017 To: From: Subject: Proposers Jeanne Geiger, Deputy Director Request for Proposals The Alamo Area Metropolitan Planning Organization (MPO) is seeking proposals from qualified firms
More informationHonorable Members of the Mobility Solutions, Infrastructure and Sustainability Committee
Memorandum DATE September 20, 2018 CITY OF DALLAS TO Honorable Members of the Committee SUBJECT Bond Program Project Management BACKGROUND On November 7, 2017, Dallas voters approved ten bond propositions
More informationREQUEST FOR QUALIFICATIONS CAMP HALL RAILROAD BUILD-IN DESIGN-BUILD PROJECT. Camp Hall Commerce Park (Camp Hall) Ridgeville, South Carolina
REQUEST FOR QUALIFICATIONS CAMP HALL RAILROAD BUILD-IN DESIGN-BUILD PROJECT Camp Hall Commerce Park (Camp Hall) Ridgeville, South Carolina March 1, 2018 1. INTRODUCTION Palmetto Railways, a division of
More informationREQUEST FOR STATEMENT OF QUALIFICATIONS PROFESSIONAL CONSTRUCTION INSPECTION SERVICES FOR
REQUEST FOR STATEMENT OF QUALIFICATIONS PROFESSIONAL CONSTRUCTION INSPECTION SERVICES FOR STREET, DRAINAGE AND REGIONAL FLOOD CONTROL FACILITIES PROJECTS Bexar County Public Works Department invites qualified
More informationREQUEST FOR PROPOSALS PROFESSIONAL ARCHITECTURAL FIRM FOR DESIGN & CONSTRUCTION MANAGEMENT SERVICES
REQUEST FOR PROPOSALS PROFESSIONAL ARCHITECTURAL FIRM FOR DESIGN & CONSTRUCTION MANAGEMENT SERVICES Prepared By: Ellis County Administration 718 Main Street P.O. Box 720 Hays, KS 67601 Contact: Phillip
More information