Lessons Learned for a Transit Public-Private Partnership. Phillip A. Washington, General Manager Regional Transportation District
|
|
- Howard Holmes
- 6 years ago
- Views:
Transcription
1 Lessons Learned for a Transit Public-Private Partnership Phillip A. Washington, General Manager Regional Transportation District Feb. 7, 2011
2 The RTD FasTracks Plan 122 miles of new light rail and commuter rail 18 miles of Bus Rapid Transit (BRT) service 31 new park-n-rides; over 21,000 new spaces Enhanced Bus Network & Transit Hubs (FastConnects) Redevelopment of Denver Union Station 2 2
3 FasTracks Construction Progress 48 miles of new rail lines are currently in construction or under contract to begin construction U.S. 36 BRT Corridor Phase I: First FasTracks project was completed in May Eight projects will be under construction this year: Elati Light Rail Maintenance Facility: Complete in 2011 West Corridor: 72% complete Denver Union Station: 30% complete East Corridor (to DIA): Broke ground in August 2010 Commuter Rail Maintenance Facility: Groundbreaking in 2011 Gold Line: Groundbreaking in 2011 Northwest Rail (to south Westminster): Groundbreaking in 2011 US 36 BRT Phase 2 Projects (Table Mesa Pedestrian Bridge and Queue Jumps): Groundbreaking in 2011
4 Other FasTracks Progress 4 Environmental processes complete East Corridor Gold Line I-225 Corridor US 36 BRT Southwest Corridor Extension Southeast Corridor Extension Central Corridor Extension Northwest Rail Environmental process wrapping up on final corridor North Metro RTD signed agreements with BNSF and UPRR $308 M federal New Starts funding for West Corridor Federal loans for Denver Union Station RRIF loan - $155 M TIFIA loan - $146 M Submitted all information required by FTA to apply for $1.03 B federal grant for the Eagle Project
5 Federal Funding for FasTracks Federal New Starts funding $1.3 billion anticipated West Corridor, East Corridor and Gold Line Transportation Infrastructure Finance and Innovation Act (TIFIA) and Railroad Rehabilitation and Improvement Financing Program (RRIF) loans for Denver Union Station $300 million American Recovery and Reinvestment Act (ARRA) $28.8 million for FasTracks and $18.6 million for Denver Union Station Transportation Investments Generating Economic Recovery (TIGER) $10 million and eligible for $50 million TIFIA loan 5 Other funding alternatives being pursued
6 Eagle P3 Project Includes East Corridor, Gold Line, Commuter Rail Maintenance Facility and segment 1 of Northwest Rail (from DUS to 71st Ave./Lowell) 36 miles of rail included in Eagle P3 Project Capital Budget - $2.1 Billion Includes seeking $1 billion in federal funds
7 East Corridor 22.8 miles electric commuter rail Connects downtown Denver to Denver International Airport Complete in
8 Gold Line 11.2 miles electric commuter rail Connects downtown Denver, Arvada and Wheat Ridge Complete in
9 Northwest Rail (to south Westminster) 5.8 miles electric commuter rail Connects downtown Denver with South Westminster Complete in
10 Eagle P3 Project Status Project divided into Two Phases Phase I East Corridor, Maintenance Facility, Vehicles Phase II Gold Line, short segment of Northwest Rail Phase I Groundbreaking on Aug. 26, 2010 with full construction beginning this year Seeking Full Funding Grant Agreement (FFGA) from FTA ($1 billion) 10 Phase II will be awarded upon receipt of FFGA
11 RTD s Public-Private-Partnership (P3) First full transit P3 in the United States Project is part of FTA s Public-Private-Partnership- Pilot Program (Penta P) DBFOM design-build-finance-operate-maintain 34-year term (6 years design/build; 28 years O&M) Availability payment model Includes incentives and penalties RTD retains ownership of assets Performance requirements Appropriate risk sharing 11
12 Eagle P3 Procurement Process Approximately three years from concept to contract Request for Qualifications process Summer 2008 Draft Request for Proposals (RFP) December 2008 Extensive industry review Early 2009 Final RFP September 2009 Final Proposals Received May 2010 Eagle P3 Team Selection June 2010 Financial Close/NTP August
13 P3 Lessons Learned Hire a project director with extensive P3 experience Get a solid financial consultant Hire an experienced legal team Create an internal Management Steering Committee and sub-committees to develop various parts of the RFP Release an RFQ first and short-list qualified teams 13
14 P3 Lessons Learned (cont.) Prepare a Draft RFP and conduct a detailed industry review Set a schedule that includes time to work through issues Hold team members to deadlines and military silence Have all team members involved in the procurement process sign confidentiality agreements 14
15 P3 Lessons Learned (cont.) Wrap up railroad agreements as soon as possible Give bidding teams the opportunity to propose Alternative Technical Concepts for staff review and approval prior to submission of final proposals Allow key stakeholders to participate in the evaluation process Hold outreach events for the bidding teams to network with small and disadvantaged businesses 15 Be open and transparent throughout the process
16 Questions? 16
Eagle Project Update
Construction of Peña Bridge November 2012 Eagle Project Update Eagle P3 Project Update Rick Clarke Assistant General Manager, Capital Programs March 5, 2014 Regional Transportation District (RTD) Performs
More informationThe RTD FasTracks Plan
Citizens Advisory Committee Quarterly Meeting June 16, 2010 The RTD FasTracks Plan 122 miles of new light rail and commuter rail 18 miles of Bus Rapid Transit (BRT) 31 new park-n-rides with over 21,000
More informationCITY COUNCIL STUDY SESSION MEMORANDUM
City and County of Broomfield, Colorado CITY COUNCIL STUDY SESSION MEMORANDUM To: From: Prepared By: Mayor and City Council George Di Ciero, City and County Manager Debra Baskett, Transportation Manager
More informationConstruction of Peña Bridge - March 2013 Jersey Cutoff Bridge October Eagle Project Update. East Corridor Stakeholder Committee April 23, 2013
Construction of Peña Bridge - March 2013 Jersey Cutoff Bridge October 2012 Eagle Project Update East Corridor Stakeholder Committee April 23, 2013 FasTracks Plan 122 miles of new light rail and commuter
More informationI-225 Light Rail Design/Build/Finance Staff Recommendation. RTD FasTracks Monitoring Committee July 3, 2012
I-225 Light Rail Design/Build/Finance Staff Recommendation RTD FasTracks Monitoring Committee July 3, 2012 FasTracks Guiding Principles Staff relied heavily on our Guiding Principles to develop our recommended
More informationFinancing Transit Projects with Traditional and Innovative Sources And Mechanisms
Financing Transit Projects with Traditional and Innovative Sources And Mechanisms Exploring the Potential for Bus Rapid Transit and Transit- Oriented Development in the I- 287/Tappan Zee Bridge Corridor
More informationNorth Metro Rail Line Quarterly Briefing. November 7, 2013
North Metro Rail Line Quarterly Briefing November 7, 2013 Agenda Welcome and Introductions Phil Washington North Metro Update Phil Washington and Jim Starling Northwest Area Mobility Study update Chris
More informationMay 22, Pamela Bailey-Campbell. Vice President - North America Infrastructure Consultancy Jacobs Engineering, Inc.
May 22, 2013 Pamela Bailey-Campbell Vice President - North America Infrastructure Consultancy Jacobs Engineering, Inc. Public Partners Arizona Department of Transportation Office of P3 Initiatives City
More informationBeth Day Director, FTA Office of Project Planning RailVolution October 2011
Beth Day Director, FTA Office of Project Planning RailVolution October 2011 What is a New or Small Start? New fixed guideways and extensions to existing systems Includes light rail, heavy rail, commuter
More informationADDENDUM #2 FOR CONSTRUCTION MANAGEMENT CONSULTANT (CMC) THIS ADDENDUM #2 IS ISSUED: AUGUST 15, 2017
ADDENDUM #2 FOR 17-054 CONSTRUCTION MANAGEMENT CONSULTANT (CMC) THIS ADDENDUM #2 IS ISSUED: AUGUST 15, 2017 QUESTIONS AND ANSWERS The following questions were posed by firms that indicated an interest
More informationPUBLIC-PRIVATE PARTNERSHIP PROGRAM, HIGH DESERT CORRIDOR
29 One Gateway Plaza Los Angeles, CA 90012-2952 213.922.2000 l metro. net PLANNING AND PROGRAMMING COMMITTEE MARCH 20, 2013 SUBJECT: ACTION: PUBLIC-PRIVATE PARTNERSHIP PROGRAM, HIGH DESERT CORRIDOR RECEIVE
More informationInnovative Project Finance
Innovative Project Finance National Governor s Association Utah State Planning Retreat on Public-Private Partnerships Ivan Marrero, P.E. Division Administrator, FHWA Utah October 7, 2016 The Status Quo:
More informationBuild America Transportation Investment Center. Office of the Secretary U.S. Department of Transportation
Build America Transportation Investment Center Office of the Secretary U.S. Department of Transportation Background On July 17, 2014 the President announced the Build America Investment Initiative: a government-wide
More informationIT TAKES A VILLAGE AND MULTIPLE SOURCES OF REVENUE: A CASE STUDY OF THE DENVER UNION STATION REDEVELOPMENT PROJECT
IT TAKES A VILLAGE AND MULTIPLE SOURCES OF REVENUE: A CASE STUDY OF THE DENVER UNION STATION REDEVELOPMENT PROJECT CATHERINE C. GALE, ESQ. EMMA R. KEYSER, ESQ. BROWNSTEIN HYATT FARBER SCHRECK, LLP I. Introduction
More informationMassachusetts Department of Transportation (MassDOT) The South Coast Rail Project DRAFT FOR DISCUSSION PURPOSES ONLY
Massachusetts Department of Transportation (MassDOT) The High Level P3 Project Suitability Assessment Report September 11, 2013 Contents Proposed Project Description Project Background and Status Commonwealth
More informationTOD Pilot Program Recommendations
TOD Pilot Program Recommendations Transit Oriented Communities TOD can create communities for RTD riders Mixed income communities Station/development integrated within community setting Jobs: creation
More informationHR&A Advisors. TOD Financing: The Reality of Today. Eric Rothman President HR&A Advisors, Inc. OCTOBER 2016
HR&A Advisors TOD Financing: The Reality of Today OCTOBER 2016 Eric Rothman President HR&A Advisors, Inc. The 30 th Street Station District Plan is a long-term TOD vision and strategy to create a mixed-use
More informationTower 55 Rail Reliever Study
Tower 55 Rail Reliever Study Technical Advisory Group June 19, 2009 Meeting Agenda Welcome & Introductions Approval of the April 17, 2009 Meeting Minutes Review of Project s s Goals & Objectives Status
More informationAppendix 5 Freight Funding Programs
5. Chapter Heading Appendix 5 Freight Programs Table of Contents 4.1 Surface Transportation Block Grant (STBG);... 5-1 4.2 Transportation Investment Generating Economic Recovery Discretionary Grant Program
More informationOpportunities and Roles for Consulting Engineers on P3 Projects
2 Opportunities and Roles for Consulting Engineers on P3 Projects Natasha Velickovic and Mike McArdle Introduction 37 Consulting Engineers for Project Owners and the Public Sector 38 Formulating and Presenting
More informationAtlanta BeltLine, Inc.
Atlanta BeltLine, Inc. Quarterly Briefing Agenda Welcome & Open House ABI CEO Update Community Engagement Update Design & Construction Update Transit Update Atlanta BeltLine Partnership Update Q&A June
More informationPuget Sound Gateway Program
Puget Sound Gateway Program SR 167 Completion Project Tacoma Transportation Commission April 18, 2018 THOMAS SLIMAK, PE SR 167 ASSISTANT PROJECT MANAGER Agenda Puget Sound Gateway Program Overview Program
More informationPublic-Private Partnership Program May 2015 Transit Coalition Update
Public-Private Partnership Program May 2015 Transit Coalition Update Los Angeles County Metropolitan Transportation Authority Mark Linsenmayer Director Presentation Agenda Overview of Metro Public Private
More informationCommuter Rail Expansion and Transit Oriented Development in Northwest Indiana. Northwest Indiana Regional Development Authority
Commuter Rail Expansion and Transit Oriented Development in Northwest Indiana Northwest Indiana Regional Development Authority REGIONAL DEVELOPMENT AUTHORITY TEAM RDA was created in 2006 to catalyze key
More informationRegional Transit System Plan. Regional Task Force Meeting No. 1
Regional Transit System Plan Regional Task Force Meeting No. 1 Thursday, December 2, 2010 James Wagner Welcome! Introductions Venue Packet Displays Opening Session 1 Agenda (5 mins) (20 mins) What is a
More informationSUMMARY OF THE GROW AMERICA ACT As Submitted to Congress on April 29, 2014
SUMMARY OF THE ACT As Submitted to Congress on April 29, 2014 The U.S. Department of Transportation (USDOT) submitted the Generating Renewal, Opportunity, and Work with Accelerated Mobility, Efficiency,
More informationTRB/AASHTO Environment & Energy Research Conference June 6-9, 2010 Session 47: Lessons Learned from P3 Public Involvement Initiatives
TRB/AASHTO Environment & Energy Research Conference June 6-9, 2010 Session 47: Lessons Learned from P3 Public Involvement Initiatives Lessons Learned from Virginia P3 Projects Dana C. Nifosi, Venable LLP
More informationREGIONAL TRANSIT FEASIBILITY PLAN
REGIONAL TRANSIT FEASIBILITY PLAN The Regional Transit Feasibility Plan continues to make progress, having completed Steps One and Two of the process to evaluate opportunities for premium transit within
More informationSAN IPSE CAPITAL OF SILICON VALLEY ?/2W/(T. Memorandum TO: HONORABLE MAYOR AND CITY COUNCIL. FROM: Kim Walesh Jim Ortbal
CITY OF 7 S3 SAN IPSE CAPITAL OF SILICON VALLEY TO: HONORABLE MAYOR AND CITY COUNCIL STUDY SESSION: 3/30/2017 Memorandum FROM: Kim Walesh Jim Ortbal SUBJECT: DIRIDON STATION PLAN AND REGIONAL RAIL PROJECTS
More informationREQUEST FOR QUALIFICATIONS (RFQ)
REQUEST FOR QUALIFICATIONS (RFQ) Public-Private Partnership Legal Advisor Services for the Diversion Channel and Associated Infrastructure Work Package of the Fargo-Moorhead Area Diversion Project Issue
More informationKANSAS CITY REGIONAL TIGER PROJECT PMOC PROGESS REPORT 2014 Fiscal Quarter 1 October 1 December 31, 2013
KANSAS CITY REGIONAL TIGER PROJECT PMOC PROGESS REPORT 2014 Fiscal Quarter 1 October 1 December 31, 2013 January 16, 2014 PROJECT TYPE: Multimodal (bicycle, pedestrian, roadway, transit) LOCATION: Kansas
More informationPHILLIP A. WASHINGTON CHIEF EXECUTIVE OFFICER
Metro Los Angeles County One Gateway Plaza 213.922.2000 Tel Metropolitan Transportation Authority Los Angeles, CA 90012-2952 metro.net February 9, 2018 TO: THROUGH: BOARD OF DIRECTORS PHILLIP A. WASHINGTON
More informationMassachusetts Bay Transportation Authority. POLICIES & PROCEDURES Design Build Procurement Procedures April 2016
Massachusetts Bay Transportation Authority POLICIES & PROCEDURES Design Build Procurement Procedures April 2016 Design Build Procurement Procedures April 2016 Massachusetts Bay Transportation Authority
More informationA REQUEST FOR QUALIFICATIONS (RFQ) FOR DENVER UNION STATION HISTORIC BUILDING RE-USE
A (RFQ) FOR DENVER UNION STATION HISTORIC BUILDING RE-USE REGIONAL TRANSPORTATION DISTRICT (RTD) 1600 BLAKE STREET DENVER, COLORADO 80202-1399 RFQ NO. 11DH014 MAY, 2011 DENVER UNION STATION BUILDING RE-USE
More informationTucson Modern Streetcar
Tucson Modern Streetcar Framework for Project Management Oversight Mayor & Council Presentation April 20, 2010 Project Goals An element of region s seamless transit system Create permanent & short term
More informationGEORGE MASSEY TUNNEL REPLACEMENT PROJECT
COMBINED MONTHLY AND QUARTERLY PROGRESS REPORT FOR QUARTER ENDING JUNE 30, 2014 GEORGE MASSEY TUNNEL MONTHLY STATUS REPORT JANUARY 2017 FINAL PROJECT STATUS DASHBOARD Scope Status* Reference concept includes
More informationConstruction Careers Policy and Project Labor Agreement. AC Transit s Bus Rapid Transit Project. February 23, 2014
Construction Careers Policy and Project Labor Agreement AC Transit s Bus Rapid Transit Project San Francisco, CA Palm Springs, CA AC Transit s Bus Rapid Transit Project 9.5 mile arterial corridor through
More informationTable of Contents. Hudson Tunnel Project and Concrete Casing 2 Request for Information No Gateway Program Development Corporation
Table of Contents 1. Project Briefing... 4 A. Program Overview... 4 B. Project Components of Phase 1B... 5 (1) New Hudson River Tunnel... 5 (2) Rehabilitation of the Existing North River Tunnel... 6 (3)
More informationMetro Mobility Agency Contract Award. Transportation Committee April 23, 2018
Metro Mobility Agency Contract Award Transportation Committee April 23, 2018 Metro Mobility Contract Structure Contract Type Service Area Customer Description Trip Purpose Demand Contracts Agency Council
More informationITEM 12 - Information March 18, 2015
ITEM 12 - Information March 18, 2015 Briefing on the Implementation of the TPB Regional Priority Bus Project under the Transportation Investments Generating Economic Recovery (TIGER) Program Staff Recommendation:
More informationREQUEST FOR INFORMATION
REQUEST FOR INFORMATION OKLAHOMA TURNPIKE AUTHORITY GILCREASE EXPRESSWAY RFI Issue Date: January 2, 2018 RFI Response Due Date: January 31, 2018 The Oklahoma Turnpike Authority ( Authority ) is seeking
More informationCity of Seattle Partnering Agreement. December 2017
City of Seattle Partnering Agreement December 2017 Agenda System Expansion Plan West Seattle and Ballard Link Extensions Partnering Agreement System expansion Sound Transit s system expansion means every
More informationCRENSHAW/LAX TRANSIT CORRIDOR PROJECT: A New Beginning for the Crenshaw Corridor Through Use of Innovative Procurement Strategies
CRENSHAW/LAX TRANSIT CORRIDOR PROJECT: A New Beginning for the Crenshaw Corridor Through Use of Innovative Procurement Strategies Robert Ball, PE Kimberly Ong, PE Los Angeles Metropolitan Transportation
More informationDenver s Lessons Learned in Developing Transit Initiatives
Denver s Lessons Learned in Developing Transit Initiatives II. Successfully Passing a Transit Initiative Smart Growth Conference Three Pillars of Strength Public Private Non-Gov t Organizations FasTracks
More informationAPTA RAIL CONFERENCE. WORKSHOP The American Recovery and Reinvestment Act of 2009
APTA RAIL CONFERENCE WORKSHOP The American Recovery and Reinvestment Act of 2009 Mary Martha Churchman Richard Steinmann Federal Transit Administration June 18, 2009 1 TOTAL DOT ARRA FUNDS : $48.1B Highways:
More informationCorridor Management Committee. September 5, 2012
Corridor Management Committee September 5, 2012 2 Today s Topics SWLRT DEIS Process Overview and Outreach Preliminary Engineering Services Procurement Update Communications and Outreach Update BAC Report
More informationLocal Taxes and Highway Tolls: The New Normal
Local Taxes and Highway Tolls: The New Normal Los Angeles County Metropolitan Transportation Authority Public-Private Partnership Program August 16, 2012 Transportation and Infrastructure Summit Michael
More informationCorridor Management Committee. March 28, 2018
Corridor Management Committee March 28, 2018 1 Today s Topics Chair s Update Proposed Corridor Protection Wall Update Environmental Update 2018 Look Ahead Eden Prairie Video 2 Chair s Update 3 Recent Activities
More informationClient: Boulder County Transportation Project: SH 119 Bus Rapid Transit & Bikeway Facility Design
Client: Boulder County Transportation Project: SH 119 Bus Rapid Transit & Bikeway Facility Design I. Applicant (Client) Information Organization Name and Address Boulder County Transportation, 2525 13th
More informationTransit-Oriented Development and Land Use Subarea Plan for Central Lake Forest Park
CITY OF LAKE FOREST PARK REQUEST FOR PROPOSALS Transit-Oriented Development and Land Use Subarea Plan for Central Lake Forest Park PROJECT DESCRIPTION The City of Lake Forest Park is seeking qualified
More informationIn This Issue CANCELED. and businesses. Meeting. regional recovery. Shelby Counties. The. commute, and 1-87-RIDEMA
CONNECTIONS A newsletter from the Regionall Planning Commission of Greater Birmingham June 2011 In This Issue RPCGB Assists in Tornado Disaster Recovery RPCGB Assists in Tornadoo Disaster Recovery RPCGB
More informationPARTNERSHIPS ACCELERATE ECONOMIC DEVELOPMENT & JOB CREATION. J. Douglas Koelemay, Director
PARTNERSHIPS ACCELERATE ECONOMIC DEVELOPMENT & JOB CREATION J. Douglas Koelemay, Director VIRGINIA LEADERSHIP IN PUBLIC-PRIVATE PARTNERSHIPS PPTA enabling legislation 1995 2001, 2005, 2008 Revisions to
More informationRequest for Proposals - Asset Management
City of Beacon One Municipal Plaza Beacon, New York 12508 Mayor Randy Casale City Council George Mansfield, At Large Lee Kyriacou, At Large Terry Nelson, Ward One John Rembert, Ward Two Jodi McCredo, Ward
More informationMassachusetts Department of Transportation (MassDOT) Route 3 South Managed Lanes Project DRAFT FOR DISCUSSION PURPOSES ONLY
Massachusetts Department of Transportation (MassDOT) Project High Level P3 Project Suitability Assessment Report September 11, 2013 Contents Proposed Project Description Project Background and Status Commonwealth
More informationPartnership Financing: Improving Transportation Through Public Private Partnerships
Partnership Financing: Improving Transportation Through Public Private Partnerships Executive Summary Long-term funding sources for transportation are uncertain, and innovative alternatives for both financing
More informationREQUEST FOR QUALIFICATIONS TO DESIGN, BUILD, OPERATE AND MAINTAIN AN INTEGRATED PREMIUM TRANSIT SYSTEM FOR THE DISTRICT OF COLUMBIA
REQUEST FOR QUALIFICATIONS TO DESIGN, BUILD, OPERATE AND MAINTAIN AN INTEGRATED PREMIUM TRANSIT SYSTEM FOR THE DISTRICT OF COLUMBIA Pre-SOQ Conference February 18, 2014 Presentation Outline 1. Introductions
More informationMay 17, To: From: Subject: Program continues to. Overview. Step Two. fixed-guideway. Program. for. Background
May 17, 2010 To: From: Subject: Transportation 2020 Committee Will Kempton, Chief Executive Officer Go Local Fixed-Guideway Program Update Overview The Go Local Fixed-Guidewaof the program, the City of
More informationPRE-SUBMITTAL CONFERENCE DESIGN/BUILD PARK & RIDE. RFQ No. LRT DBPNR September 1, 2009
PRE-SUBMITTAL CONFERENCE DESIGN/BUILD PARK & RIDE RFQ No. LRT-10-135-DBPNR September 1, 2009 Meeting Overview Sign-In Sheets: Be sure to sign in. Sign-In sheets will be available on the VMR website. Questions:
More informationSummary of Committee Discussion/Questions Chris Beckwith, Senior Project Manager from the Gold Line Project Office, presented this item.
Committee Report Business Item No. 2017-241 Transportation Committee For the Metropolitan Council meeting of November 29, 2017 Subject: Gold Line BRT Project Management/Environmental Contract Proposed
More informationCotton Belt Rail Corridor Innovative Finance Initiative
Cotton Belt Rail Corridor Innovative Finance Initiative Request for Proposals Pre-Proposal Conference #2 June 18, 2010 10 a.m. Agenda Welcome and Introductions Michael Morris, P.E. Project Purpose Michael
More informationIntegral Art MBTA REQUEST FOR QUALIFICATIONS (RFQ): SILVER LINE GATEWAY PHASE 2 - NEW CHELSEA CR STATION CALL FOR ARTISTS
MASSACHUSETTS BAY TRANSPORTATION AUTHORITY Integral Art MBTA REQUEST FOR QUALIFICATIONS (RFQ): SILVER LINE GATEWAY PHASE 2 - NEW CHELSEA CR STATION CALL FOR ARTISTS Call For Artists/RFQ: Friday, July 17,
More informationMULTIMODAL TRANSPORTATION DISTRICT ALTERNATIVES ANALYSIS. Executive Summary
MULTIMODAL TRANSPORTATION DISTRICT ALTERNATIVES ANALYSIS Executive Summary February 2015 Executive Summary 1. Define the Problem This Alternatives Analysis report is submitted as a deliverable for the
More informationTransportation Demand Management Workshop Region of Peel. Stuart M. Anderson David Ungemah Joddie Gray July 11, 2003
Transportation Demand Management Workshop Region of Peel Stuart M. Anderson David Ungemah Joddie Gray July 11, 2003 Why Transportation Demand Management (TDM)? Demand management measures support a sustainable
More informationPublic Information Plan
Metcalf Shawnee Mission Parkway Bus Corridors Transit Improvements Public Information Plan Prepared by 1 Plan Purpose The public information plan for the Metcalf Avenue/Shawnee Mission Parkway Bus Corridor
More informationMid-Coast Corridor Transit Project Construction Bench Open House November 9, 2016
Mid-Coast Corridor Transit Project Construction Bench Open House November 9, 2016 MID-COAST TRANSIT CONSTRUCTORS Clayton Gilliland, MCTC, Project Manager WELCOME! Mid-Coast Transit Constructors Construction
More informationGATEWAY PROGRAM UPDATE
September 15, 2017 GATEWAY PROGRAM UPDATE John D. Porcari, Interim Executive Director GATEWAY PROGRAM: RECENT ACCOMPLISHMENTS» Federal funding and financing submittals» Portal North Bridge Project» Hudson
More informationFTA and Tribal Transit Program Past, Present, and Future
FTA and Tribal Transit Program Past, Present, and Future NW TTAP and BIA Symposium Portland, OR March 18, 2015 Agenda FTA Overview Funding FTA funding available for Tribal Transit How to Access FTA Funding
More informationKaty Trail Extension from McCommas Boulevard to White Rock Station
Katy Trail Extension from McCommas Boulevard to White Rock Station Presented to the Quality of Life Committee By Public Works and Transportation October 26, 2009 Purpose of Briefing Provide updates on
More informationLand Development Code Update
Land Development Code Update Advisory Committee Meeting #1 September 14, 2017 We Dream Big and Deliver Agenda 1. Welcome and Introductions 2. Purpose and Objectives 3. Why Now? 4. Strategic Objectives
More informationVTA s Capital Projects Program & BART Phase II Procurement Opportunities. VTA s Procurement Fair and Workshop. November 1, 2016
VTA s Capital Projects Program & BART Phase II Procurement Opportunities VTA s Procurement Fair and Workshop November 1, 2016 Capital Projects Program Capital Projects Program Major Projects in Construction
More informationDisadvantaged Business Enterprise Program and Triennial DBE Goal Setting Methodology and Rationale
Disadvantaged Business Enterprise Program and Triennial DBE Goal Setting Methodology and Rationale Kenn Hardin Senior Manager Civil Rights Division RTD Small Business Office August 14, 2013 Agenda Introductions
More informationPROJECT DELIVERY MODELS ARKANSAS PLANNING RETREAT ON P3S. J. Douglas Koelemay, Director October 7, 2015
PROJECT DELIVERY MODELS ARKANSAS PLANNING RETREAT ON P3S J. Douglas Koelemay, Director October 7, 2015 VIRGINIA LEADERSHIP IN PUBLIC-PRIVATE PARTNERSHIPS Virginia and California first P3 legislation in
More informationTransit Operations Funding Sources
Chapter 7. Funding Operations Funding Funding has increased about 56% in absolute terms between 1999 and 2008. There have been major variations in individual funding sources over this time, including the
More informationFORMULA GRANTS 5307 Urbanized Area 5337 State of Good Repair 5339 Bus and Bus Facilities Board of Directors Committee Meeting
FORMULA GRANTS 5307 Urbanized Area 5337 State of Good Repair 5339 Bus and Bus Facilities Board of Directors Committee Meeting May 2014 What are 5307 Urbanized Area Formula Funds? Section 5307 formula funds
More informationUNFUNDED TRANSPORTATION PROJECTS OVERVIEW
UNFUNDED TRANSPORTATION PROJECTS OVERVIEW THE LIST 40 unique unfunded projects are on the list All projects are important to the future of Arvada s transportation needs. The list has developed over many
More informationThe New Incrementalism: Building and Financing US High-Speed Rail
The New Incrementalism: Building and Financing US High-Speed Rail Sharon Greene Principal, Sharon Greene and Associates, USA Sasha Page Vice President, Infrastructure Management Group, USA The New Incrementalism:
More informationDBE/Small Business Workshop. June 12, 2015
DBE/Small Business Workshop June 12, 2015 Learning Objectives Benefits Purpose Eligibility Criteria Procurement Forecasts SunLine s Procurement Process Fostering Small Business What are the benefits of
More informationMore. January Central Corridor LRT Project included in president s budget
January 2010 Central Corridor LRT Project included in president s budget A decades-long dream to link St. Paul and Minneapolis by light rail transit is a step closer to reality with the Obama Administration
More informationCONTRACT BRIEF WORKER ACCOMMODATION MARCH 4, The Worker Accommodation RFQ can be found on BC Bid at document number 1807.
CONTRACT BRIEF WORKER ACCOMMODATION MARCH 4, 2014 The RFQ can be found on BC Bid at www.bcbid.gov.bc.ca, document number 1807. TABLE OF CONTENTS 1.0 PURPOSE OF THE CONTRACT BRIEF... 3 2.0 THE BUSINESS
More informationMETRO Blue Line LRT & METRO Green Line LRT (Light Rail) Table of Contents. Operating Grant Worksheets Pages 6-17
METRO Blue Line LRT & METRO Green Line LRT (Light Rail) Table of Contents Operating Grant Application Cover Sheet Pages 1-3 Project Benchmarks and Timeline Pages 4-5 Operating Grant Worksheets Pages 6-17
More informationFlorida s Design Build Program
Florida s Design Build Program 2016 Transportation Short Course October 11 th, 2016 Larry Ritchie, Florida DOT Mike Spain, Lane Construction Phil Schwab, RS&H Florida Design Build Documents and Procedures
More informationCommunity Advisory Committee. September 11, 2017
Community Advisory Committee September 11, 2017 1 Today s Topics Hennepin County Community Works Update New Starts Update Bassett Creek Storm Sewer Update West Broadway Stations 2 Hennepin County Community
More informationREQUEST FOR QUALIFICATIONS CONSULTING SERVICES FOR WALLA WALLA REGIONAL AIRPORT (ALW) WALLA WALLA, WASHINGTON. October 2, 2018
REQUEST FOR QUALIFICATIONS CONSULTING SERVICES FOR WALLA WALLA REGIONAL AIRPORT (ALW) WALLA WALLA, WASHINGTON October 2, 2018 The Port of Walla Walla, owner and operator of the Walla Walla Regional Airport,
More informationTransportation Planning & Investment in Urban North Carolina
Transportation Planning & Investment in Urban North Carolina Using the Voice of Mayors to Advance North Carolina Almost all future NC growth projected to occur in urban areas Projected share of 2010-2035
More informationARLINGTON COUNTY CODE. Chapter 66 TECHNOLOGY ZONES* Article I. General Provisions ARTICLE I. GENERAL PROVISIONS
ARLINGTON COUNTY CODE Chapter 66 * * Editor s Note: Ord. No. 07-11, adopted September 8, 2007, amended Ch. 66, in its entirety, to read as herein set out. 66-1. Purpose. 66-1. Purpose. 66-2. Compliance.
More informationFixing America s Surface Transportation Act: FAST Act Implications for the Region
Fixing America s Surface Transportation Act: FAST Act Implications for the Region Connie Kozlak Metropolitan Transportation Services Mark Fuhrmann Metro Transit Ed Petrie Metro Transit Metropolitan Council
More informationSFRTA/TRI-RAIL PAST, PRESENT & FUTURE
SFRTA/TRI-RAIL PAST, PRESENT & FUTURE Presented by: Joseph Giulietti, Executive Director South Florida Regional Transportation Authority July 25, 2007 Tri-Rail History OVERVIEW South Florida Regional Transportation
More informationVista Ridge Integration Project Owner s Representative
Vista Ridge Integration Project Owner s Representative Andrea Beymer, P.E. Director Plants & Major Projects Rosalee Arcos Contract Administrator Marisol Robles SMWB Program Administrator SOQ Pre-Submittal
More informationAnnual Report on Funding Recommendations
Annual Report on Funding Recommendations Fiscal Year 2019 Capital Investment Grants Program Report of the Secretary of Transportation to the United States Congress Pursuant to 49 USC 5309(o)(1) and Section
More informationCITY OF LONG BEACH DEPARTMENT OF DEVELOPMENT SERVICES REDEVELOPMENT BUREAU
CITY OF LONG BEACH DEPARTMENT OF DEVELOPMENT SERVICES REDEVELOPMENT BUREAU 333 West Ocean Blvd., 3 th Floor Long Beach, CA 90802 Phone: 570.6615 Fax: 570.6215 Introduction On November 3, 2009 the City
More informationAssociation of Metropolitan Planning Organizations Fixing America s Surface Transportation (FAST) Act
Association of Metropolitan Planning Organizations Fixing America s Surface Transportation (FAST) Act General Overview Total authorizations (Highway Trust Fund, HTF, Contract Authority plus General Funds
More informationRequest for Proposals. For NEW HOPE TO WARMINSTER PASSENGER RAIL SHUTTLE FEASIBILITY STUDY
Request for Proposals For NEW HOPE TO WARMINSTER PASSENGER RAIL SHUTTLE FEASIBILITY STUDY The Bucks County Transportation Management Association, Inc. (TMA Bucks), on behalf of the Borough of New Hope,
More informationPublic Private Partnerships and Transit Not Just for Mega Projects Karin DeMoors October 28, 2015
Public Private Partnerships and Transit Not Just for Mega Projects Karin DeMoors October 28, 2015 Presentation Overview What is a Public Private Partnership (P3)? Mega Project Focus Range of Partnerships
More informationAGC of TEXAS Highway, Heavy, Utilities & Industrial Branch
AGC of TEXAS Highway, Heavy, Utilities & Industrial Branch THOMAS L. JOHNSON, Executive Vice President Texas Transportation Commission Meeting Highlights September 18 and 24, 2014 September 18 Commissioner
More informationFunding Principles. Years Passed New Revenue Credit Score Multiplier >3 years 0% % % % After Jan %
Funding Principles I. Infrastructure Incentives Initiative: encourages state, local and private investment in core infrastructure by providing incentives in the form of grants. Federal incentive funds
More informationSouth Buffalo Brownfield Opportunity Area Step 3 Coordinator, Implementation Strategy, and Final Brownfield Opportunity Area Plan RFP Informational
South Buffalo Brownfield Opportunity Area Step 3 Coordinator, Implementation Strategy, and Final Brownfield Opportunity Area Plan RFP Informational Meeting November 16, 2012 Step 3 Coordinator, Implementation
More information! Rick Garcia! Regional Administrator! HUD, Region 8!
Rick Garcia Regional Administrator HUD, Region 8 Today s Run of Show The Partnership: Setting the Stage Snapshots from Four Grantee Communities Moderated Conversation with Grantees and Audience Participation
More informationThe ENDOW Regional Assessment. For Business Development and Innovation Zones
The ENDOW Regional Assessment For Business Development and Innovation Zones 1 Agenda About ENDOW Business development and innovation zones What is the Regional Assessment? How to use the Regional Assessment
More informationSan Francisco Transportation Plan (SFTP) and Early Action Plan
San Francisco Transportation Plan (SFTP) and Early Action Plan October 2013 SAN FRANCISCO COUNTY TRANSPORTATION AUTHORITY Purpose of the San Francisco Transportation Plan (SFTP) Regional Transportation
More informationSmart Region Smart Transportation
Smart Region Smart Transportation Joe Milazzo II, PE, RTA Executive Director Wednesday, Oct. 19, 2016 The Regional Transportation Alliance business coalition: MISSION To leverage the strength of the regional
More information