1 OWNER S PROJECT MANAGER (OPM) FOR MARIA WESTON CHAPMAN MIDDLE SCHOOL JANUARY 18, 2017

2

3 January 18, 2017 John MacLeod, Director of Municipal Assets and Procurement Weymouth School Building Committee c/o Mayor s Office Weymouth Town Hall 75 Middle Street Weymouth, MA Subject: Dear Mr. MacLeod and Members of the School Building Committee: Hill International, Inc. 330 Congress Street 6th Floor Boston, MA Tel: Fax: We are excited to present our qualifications to provide owner s project management (OPM) services to the Town of Weymouth (Town) based on our positive experiences working as the OPM for numerous MSBA funded middle schools, and the potential to leverage what we have learned since then to help make the Maria Weston Chapman Middle School project an even greater success. Among the most important decisions a building committee will make is the selection of the people entrusted to protect their interests during the life of the building project. Thoughtful consideration of the individual talents, experiences and relationships each team member brings to the table is critical to assembling a balanced, efficient and effective team, with the greatest potential for achieving optimal results. With this in mind, we have assembled a team that will work harmoniously with the Town and the larger project community, to deliver the highest degree of shared success. Our proposed team members each possess a balance of talent in the building industry, experience with similar building types and relationships with the Massachusetts School Building Authority. Joseph Naughton, AIA, our proposed Principal-in-Charge has worked as an architect, contractor and an owner s project manager for last 25 years. Joe has worked on over 20 MSBA funded school building projects, including four middle schools. Our team is led by Project Director Paul Kalous, AIA, MCPPO, who brings more than 26 years of relevant experience including the award winning Lexington Estabrook Elementary School. Simon Tempest, AIA, LEED GA, MCPPO, will serve as Senior Project Manager and your day to day contact from start to finish of the project. Simon has more than 35 years of experience managing and leading projects for a variety of building types, and is also well-versed in the permitting process for similar buildings and has worked with a number of historic commissions and local boards to develop acceptable solutions and approvable projects. Inger Hamre-Foley, MCPPO, has a long working history with Paul and Simon, including on the Southeastern Regional Vocational Technical High School, and will serve as Project Manager. Joe, Paul, Simon and Inger form the core of our proposed OPM team for the Maria Weston Chapman Middle School project. We have worked together on similar projects with great success and we are excited to have the opportunity to repeat that success again in Weymouth. We will work diligently with the entire project team to promote a robust development process that responds to the unique needs of the Weymouth community, and advance a plan for excellence that will continue to set it apart. Sincerely, Joseph A. Naughton, AIA Senior Vice President and New England Regional Manager Tel: josephnaughton@hillintl.com Page 1 of 2

4 Cover Letter Requirements 1a. We have not received any Addendum with regard to this Request for Services (RFS). We are in receipt of the Walk Thru list. 1b. We have read and accept the RFS. 1c. We have read and accept the Standard Contract. 1d. We comply with the minimum requirements set forth in Item 4 of the RFS. Project Director Paul Kalous, AIA, MCPPO is a registered architect in the state of Massachusetts (License #9327). He also holds a current MCPPO certificate, which has an expiration date of 12/31/2019. A copy of his certification is included below our Contact Person s information and signature. Paul has more than 26 years of construction industry experience. 1e. Hill s Boston Office currently employs 34 staff. We have the expertise and experience to manage projects from concept to successful completion. Our Massachusetts-based personnel bring extensive expertise working on MSBA K-12 facilities as well as on numerous public buildings types including both new construction and renovation. We also have worked on a wide range of local CM-at-Risk projects. Over the years Hill has helped deliver more than 30 K-12 projects in Massachusetts. 1f. Joseph Naughton, AIA, is authorized to negotiate and execute the Contract for Project Management Services, in the form that is attached to the RFS, on behalf of the Hill team. Senior Vice President and New England Regional Manager 1g. Contact Person and Information: Joseph A. Naughton, AIA, Senior Vice President and New England Regional Manager Tel: Address: 330 Congress St., 6th Fl, Boston, MA josephnaughton@hillintl.com Project Director MCCPO Certificate Page 2 of 2

5 SELECTION CRITERIA Relevant Experience and Results 1 Past Performance Hill s resume of school projects includes new construction, modernization, renovation and addition projects throughout Massachusetts. This work includes owner s representation for program, project and construction management; project controls management, including all phases of estimating, budget controls and CPM schedule development and analysis; FF&E management; value engineering; constructability reviews; and claims avoidance. Our Boston office has managed a total of 131 projects. We have completed 96% of these on time, with zero accidents/safety violations and zero legal actions. Per year, our project managers complete an average of two projects. The projects detailed below highlight school district s successes resulting from the Hill team s experience in working with the MSBA on projects that closely parallel the Town s own project requirements. These projects demonstrate our quality of work and level of performance. We will apply the best practices to the project to help meet the Town s objectives. Our total number of projects managed, project dollar value, number completed on time and number and dollar value of change orders are provided in Attachment C. Jonas Clarke Middle School Lexington, MA Client Name: Town of Lexington Service Provided: Owner s Project Management Project Cost: $21.6 Million Completion Date: 2017 (estimated) PROJECT DESCRIPTION Hill, led by Joe Naughton and Paul Kalous, is providing owner s project management services to the Town of Lexington for additions to Jonas Clarke Middle School to accommodate student growth. Additions comprise nine new classrooms, including two for science, one for each general education class and space to support the English Language Learner Program, the Individual Learning Program, the Developmental Learning Program as well as the engineering, art and drama programs. The renovations will also create a new exterior traffic flow plan and a patio area for students waiting for buses. The project site is constrained by site conditions, including topography and environmental conditions. In addition, the building area is very limited. Therefore, a critical project issue involves expediting both the design and construction processes to bring the new facilities into operational capacity as quickly as possible. Hill, partnering with the Town, designer and CM, will utilize past experience and knowledge of Massachusetts school construction to help accelerate the design process and facilitate early construction packages under the Chapter 149A CM at Risk process to meet Lexington s August 2017 completion goal. Diamond Middle School Lexington, MA Client Name: Town of Lexington Service Provided: Owner s Project Management Project Cost: $44.9 Million Completion Date: 2018 (estimated) PROJECT DESCRIPTION Hill, led by Joe Naughton and Paul Kalous, is providing owner s project management services to the Town of Lexington for additions to Diamond Middle School to support increasing student enrollment. The renovation plans for the 131,000 SF school are designed to maximize space, including the redesign of storage areas to expand existing classrooms. The renovations will also include exterior work to Page 1

6 create a new traffic pattern outside of the school. Additions comprise seven new classrooms, including two for general education, three for science, one for each international language, one for the English Language Learner program, teacher planning space and a larger cafeteria. Work also requires a $10 million heating, ventilation and air conditioning system. A critical issue involves expediting the design and construction processes to bring the new facilities in operational capacity as quickly as possible. Hill, partnering with the Town, designer and CM, will utilize past experience and knowledge of Massachusetts school construction to help accelerate the design process and facilitate early construction packages under the Chapter 149A CM at Risk process to meet Lexington s August 2017 completion goal. Park Avenue School Webster, MA Client Name: Town of Webster Service Provided: Owner s Project Management Project Cost: $46.8 Million Completion Date: 2014 PROJECT DESCRIPTION Hill provided owner s project management services for the construction of the new 109,597 SF Park Avenue Elementary School. The new school is a three-story, steel-framed building with masonry veneer. The three-phase project began with the demolition of the upper portion of the existing building, followed by construction of the new building, then the demolition of the lower portion of the existing building once the new building was complete. Site work included all utilities, parking lots and roadways throughout the site. The procurement method for this project was M.G.L The new school achieved LEED Gold certification. One of the unique services Hill brought to the table was to help Webster advocate for a slight adjustment to the initially approved MSBA grade configuration of the new building. By expanding the K-3 configuration to a K-4, Webster was able to free up space in its middle school and bring the 7th and 8th grades out of its high school to form a traditional 5-8 middle school addressing parental concerns. This also relieved space and separation challenges it was facing at the high school. We were able to realize tangible benefits across the entire district by fine tuning a singular project resulting in widespread support for the project and an 87% yes vote at the polls. Southeastern Regional Vocational Technical High School South Easton, MA Client Name: Southeastern Regional Vocational Technical School District Service Provided: Owner s Project Management Project Cost: $33 Million Completion Date: 2013 PROJECT DESCRIPTION Hill, led by Paul Kalous and Inger Hamre Foley, provided OPM services for the new addition and phased renovation project. The school s capacity was at a maximum and the district had students on a waiting list for acceptance from its nine sending communities. The project was divided into nine main phases. The first phase was the construction of a new gymnasium, the renovation of old locker rooms and the creation of a dental suite which included an exam room, darkroom, casting and sterilization lab with a separate room for the compressor. The exterior renovation included all new windows and doors and a new Sarnafil roof. New canopies were installed at the entrance to the gymnasium and the main entrance to the school. New HVAC units were placed on the roof, and a new chiller was installed on the ground. The interior renovation included ADA upgrades and a new sprinkler and HVAC system. Unit ventilators were replaced in order to Page 2

7 accommodate air conditioning. Electrical and fire alarm was also upgraded. A new elevator was installed, and the existing elevator was renovated. The renovation of the school varied from full renovation to only minor renovation in both general classrooms and shops. As the new gymnasium was completed, the former gymnasium was transformed into the new media center, classrooms and copy room. The upgrade to the drama room included the addition of a green room and video editing. The music room received additional acoustics and a separate room for instrument storage. The administrative area, guidance and school nurse also received renovation of their space. The project also included the renovation of the Southeastern Technology Institute section of the school. When the current library moved to the new media center, the school arranged for a large tent outside the school and served the students their lunches through the automotive shop for the last month of the school calendar. This enabled the team to take over the library, kitchen, cafeteria, industrial kitchen and culinary kitchen for a full renovation during the summer. A large portion of the project was completed during occupied school hours which made the logistics plan and communication between all parties very important. Demolition was often done after school hours until early morning and cleaned up for when the students returned. The students in the cabinet shop constructed the display cases in the new gymnasium lobby and the circulation desk in the media center. The security system students and teachers assisted with the removal and re-installation of existing security systems as the team renovated various areas of the school. East Bridgewater Junior/Senior High School East Bridgewater, MA Client Name: Town of East Bridgewater Service Provided: Owner s Project Management Project Cost: $77 Million Completion Date: 2014 PROJECT DESCRIPTION Hill, led by Joe Naughton and Simon Tempest, provided owner s project management services for the $77 million construction of a 214,000 SF high school for grades 7 through 12, associated site works and a new wastewater treatment plant. The existing high school, which was located adjacent to the new high school, was demolished and removed after the students and staff moved into the new high school in The former school site was transformed with athletic fields and an accessible path linking the new school to the downtown core. A highlight is the unique 7-12 grade configuration, with separate entrances for junior school and upper school students. Though all grades share common spaces and facilities, the design enables the facility to maintain a separation of the different grade configurations with the fiscal benefits of reduced capital, maintenance and operations costs of a single facility. One of the successful elements completed by our team was the website maintained during the design phase that offered daily responses to questions from the community about the project. The site was so popular that by the time we got to the town meeting we had registered over 26,000 hits which we believe contributed to the 86% yes vote at the polls. > Working Relationships Our Boston-based Hill team is proud of the working relationships we have garnered and maintained throughout the Commonwealth as a result of our collaborative approach to project execution. We are honored to have a continuing multi-project relationships with the MSBA and other public agencies such as UMass Building Authority and Massport and very diverse communities such as Revere, Lexington, Middleton and Braintree. We strive to bring all appropriate stakeholders into the decision-making process which enables the project team to share in the success of the decisions made. Additionally, our team has over 15 years of relationship building as a Page 3

8 project management group. We are proud of the excellent working relationships we have with both leading and up-and-coming firms in the design and construction communities. These relationships will be very beneficial to Weymouth as the project planning and design process takes place. Knowledge of Codes, Procurement and Sustainability 2 Knowledge of Massachusetts State Building Code Regulations The Hill team is comprised of licensed architects, professional engineers, planners, real estate professionals and builders who are all well-versed in the latest Massachusetts Building codes and regulations. As registered architects, Joe Naughton, AIA, Paul Kalous, AIA, and Simon Tempest, AIA, remain current on MA Codes and regulations through AIA, CSI and NCARB continuing education coursework. Fred Scibelli, CSL, is a certified Construction Supervisor in the Commonwealth of Massachusetts who has pulled numerous building permits and understands, first hand, the importance of strict adherence to building codes and regulations to successful project outcomes. Hill has presented before numerous regulatory boards and committees in the Commonwealth of Massachusetts, further enhancing our knowledge of applicable codes and regulations. This depth of expertise will help our team verify that the project meets the relevant building codes and requirements prior to construction, which will help the project steer clear of potential delays and costs, and maximize the overall quality of the project. Americans with Disabilities Act. All of our new school projects constructed in Massachusetts and presented herein are fully compliant with the requirements of the Americans with Disabilities Act and the Massachusetts Architectural Access Board (MAAB). We have also managed K-12 renovation projects where a variance had been granted by MAAB due to existing structural limitations of a building and site. 3 Knowledge of Commonwealth Construction Procurement Laws Our core team members Paul Kalous, MCPPO, Simon Tempest, MCPPO, and Inger Hamre-Foley are Massachusetts Certified Public Purchasing Officials (MCPPO). An additional 15 MCPPO certified personnel are available to support this assignment, if needed. In total, Hill has completed more than 30 projects under Commonwealth Construction Procurement Requirements. Our knowledge of these requirements will help ensure Weymouth s project adheres to state requirements. We also routinely utilize Chapter 7 for designer selection, Chapter 30 for horizontal construction and Chapter 30B for real property procurement. Knowledge of CM-at-Risk. Hill s personnel promoted and contributed to the legislation for the Construction Reform Act of 2004 resulting in the Chapter 149A (CM-at-Risk) alternative delivery system. We have experience with CM-at-Risk and support the practice of bringing the design and construction teams on-board at, or near, the same time to find the best solutions early. In Massachusetts, we have utilized the CM-at-Risk delivery method under Chapter 149A on 12 projects including Southeastern Regional Vocational Technical School, the Estabrook Elementary School, the Diamond Middle School and the Clarke Middle School. We are also teaching a CH149A CM at Risk introductory classes at Massport, in which approximately 20 project managers attend for training and continuing education. 4 Familiarity with NE-CHPS and LEED Building sustainability, as measured by NE-CHPS or Leadership in Energy and Environmental Design (LEED), is becoming the standard for public school design. Our teams have helped deliver both NE-CHPS and LEEDcertified schools, including projects across Massachusetts with similar characteristics to the Chapman Middle School project. Hill views sustainability as an inherent and pervasive component of the building process. We Page 4

9 have successfully managed LEED-certified projects, ranging from Certified to Platinum. Our proposed team has worked on more than 10 public, K-12 projects that are either NE-CHPS or LEED-certified, including Webster Park Avenue School, Revere Hill School, Lexington Estabrook Elementary School, Natick High School, Middleton Howe Manning Elementary School, Southeastern Regional Vocational Technical High School and Everett High School. Principal-in-Charge Joe Naughton is skilled with the LEED process and has worked on multiple versions of projects for both new construction and renovations of existing educational facilities. We are ready to advance the goals for sustainability articulated by Weymouth and will assure that the measures adopted are understood by Weymouth prior to construction and after completion. As OPM, we will oversee the design team s coordination and followthrough of the LEED or NE-CHPS paperwork including adherence to the new LEED v4 (if LEED is the preferred measure) which supercedes LEED v3/2009 which closed on October 31, Additionally, we make sure that this process is completed with the building committee s awareness of the cost and value of selected features. Understanding the cost of including a green feature versus the eventual payback is important and we confirm you have this information. Hill takes an integrated approach to sustainable projects, and will work closely with Weymouth to evaluate and establish sustainability goals early in the planning process to avoid unnecessary costs and delays. Our inhouse LEED professionals will work closely with the design team and the project cost estimating consultants to provide comprehensive evaluation tools to enable evaluation of the project s potential for LEED certification levels. The Hill project management team will participate with the design team and project cost estimating consultants throughout design development and design charrette(s), providing real-time budgeting scenarios. Hill has an in-house cost estimating team that was one of the first to incorporate published green building cost data with its own extensive internal historic project data. With this data, Hill can provide the team with the tools to quickly surmise a project s certification potential by identifying the low hanging fruit at the concept level, then providing the data necessary to consider cost and scheduling scenarios for definite elements to incorporate into the design ( yes ); probable or low-cost elements to incorporate ( maybe ); and elements to discard ( no ) according to the LEED scorecard. From early in the planning stages, we will work with the project team to address the top challenges when seeking sustainable certification utilizing the following resources and tools: Extensive Green Building Project Experience and Lessons Learned Green Building Cost Database using Published and Historic Data Accurate Preparation of Independent Cost Estimate in Early Planning Stages Initial LEED Scorecard Provided with Conceptional Cost Estimate, if applicable Reduced Possibility of Sustainability Criteria in Construction Documents Real-time Analysis of Cost and Schedule Implications during Charrette Progress Updates Generated at Cost Estimate Revision 5 Experience with Life Cycle Cost Estimating and Value Engineering As mentioned above in the project understanding section of our proposal, one of the critical components of success for the Chapin Street Elementary School project will be developing an understanding of the existing building short term and long term costs on the district budget, and how current technologies can be leveraged to shift dollars saved from O&M improvements back toward educational programs. Preserving value and function while finding savings through more effective systems and materials and less labor intensive methods Page 5

10 allows us to optimize the final design trading project savings for additional value added initiatives. Below are examples of how we have created value to the owner by implementing v life cycle cost analysis and value engineering ideas to tailor our buildings to our clients desires: 1 Lexington Estabrook Elementary School. At the Estabrook Elementary School, we compared a number of HVAC systems to find a balance between cost and comfort in the classrooms zones to provide a measure of cooling relief during the warmer months. We compared: 1. direct-expansion air conditioning. 2. fourpipe fan coil 3. active chilled beams and 4. displacement air. We compared the capital costs, operations costs, maintenance costs, degradation costs and decomissioning costs of all four alternatives using a present value calculation for each. Based on the data provide, the owner chose the displacement air system as the ideal option for their needs due in part to its compatible up front costs and its relatively low operations and maintenance costs over its lifetime compared with the others. 2 Park Avenue Elementary School. Hill worked with the project team to create a number of value added refinements, including an idea by Hill aimed at creating a building orientation and site construction plan to minimize cut and fill operations, saving $250,000 in site costs. Our team also suggested implementing a unique door hardware and electronic access control system to enhance the Town of Webster s districtwide security system that both saved capital costs to the job due to a larger town wide procurement program, and saved on maintenance costs due to a less expensive sole source maintenance contract for the town. The Hill team proposed and worked with National Grid to find an alternative route for a high capacity gas line to feed the project, saving more than $100, Stoughton School Repairs. For the window replacement project, the originally proposed design approach and construction details called for removing and reconstruction of the exterior masonry veneer around the perimeter of each window to allow for removal of the existing window, storefront systems and attachment of the new systems. Based on our coordination of third party review and inspection, it was determined that the existing masonry did not need to be removed and reconstructed to achieve the originally planned objective of replacing the windows. This approach is saved the client over $700, Revere Police/Fire Station. Prior to Hill joining the project team, the foundation design approach was to conduct a complete 10 deep removal of unsuitable soil below the building footprint and restore with structural fill upon which spread footings would be placed followed by a slab on grade. Our team inquired if the owner would consider an alternate plan in which rammed aggregate piers could be used to improve the bearing capacity of the soil for column loads and utilize a structural slab at the first floor to compensate for under-slab settlement between the column lines. The owner agreed to this approach which resulted in a savings to the project of over $277,000. > Cost Estimating Hill s in-house estimating capacity includes all sitework, architectural, structural, plumbing, fire protection, mechanical, electrical and low voltage disciplines. For the Feasibility Study and Schematic Design of the Maria Weston Chapman Middle School project our standard estimating and cost management services include: master budget setup, conceptual budget estimates and, detailed quantity takeoff estimates for each of the schematic plans produced in the Feasibility Study phase as well as the Preferred Schematic that will be included in the final submission to the MSBA. We also provide project work schedules, constructability reviews, value engineering and alternating change orders review, long lead item identification and control systems. All this information is condensed, so Weymouth will be able to make timely, informed decisions. Page 6

11 6 Knowledge of Building Commissioning Consultants All of our assignments involve a professional commissioning agent. Our K-12 MSBA projects include commissioning agent services provided by the MSBA. We coordinate the commissioning agent activities, including design phase duties such as design peer review at design milestones, value management assistance and the provision of specifications describing contractor duties for commissioning. During construction, we coordinate the commissioning agent for kick-off and other meetings, transmittal of appropriate contractor submittals as well as informing the commissioning agent of equipment start-up dates, tests, etc. In the design phase, we work with commissioning agent, owner and design team to assist in defining Weymouth s requirements and verify those requirements are met in the basis of design and onto the construction documents. Commissioning agents provide a valuable role as peer reviewers during design. Commissioners benefit from lessons learned and can convey these lessons to design engineers at a technical level. During the construction phase, we monitor the installation of the materials, equipment and systems and review supporting documentation to help ensure the systems are commissionable when the time comes. Hill s approach includes a review of the Fundamental Performance Checklist (FPC) and the Commissioning Plan (CP). We work with the construction team on final inspections and review of turnover packages. Prior to start-up, we review the documentation associated with construction quality control activities such as duct leak testing, weld inspections and electrical checks. During start-up, we serve as witnesses to site acceptance testing, verifying documentation of the Functional Performance Testing to Weymouth. Project Understanding and Approach 7 Management Approach > Project Understanding From our review of the RFS, and the onsite briefing, the Hill team understands of the importance the Maria Weston Chapman Middle school project has to the Town of Weymouth and the entire Weymouth community. The project will allow Weymouth to address current building deficiencies and the very real possibility of enrollment increases from construction at Union Point and other developments, as well as reducing the number of transitions between schools. Hill understands the importance of fine and performing arts programs to the project and the need to incorporate these into the overall project program. In addition we understand the project will amongst other things, need to provide a learning environment for a diverse population of students some with special education needs. Successful delivery of the Chapman Middle School project will start with establishment of the following objectives: Page 7

12 Review Plan Assess Develop 1 Review all materials developed to date around the planning of the Chapman School project and review the existing building conditions, and potential alternative sites to have a full understanding of the project priorities and what is needed for the project to succeed. 2 Provide comprehensive planning to manage the project and the project s overall impact on the Community the Owner and Students. We have demonstrated this ability on numerous other MSBA projects achieving positive outcomes on numerous complicated challenging projects 3 Assess actual and formulaic enrollment trends to manage the project scope and confirm that the project meets the educational needs of the Weymouth community into the foreseeable future. 4 Develop a plan for presenting project information to the community, including community presentations, creating a project web site and social media outreach. As the project progresses we will assess the effectiveness of the outreach effort and create a strategy to broaden support if necessary. > Project Approach Project Goals: Completing the Feasibility Study for the School as established by the Weymouth School Building Committee in partnership with the MSBA, represents the first step in the design process. The decisions during the Feasibility and Schematic Design will determine how the Town ultimately proceeds with the proposed design and construction of the Chapman Middle School project. The Hill team understands the feasibility study will have a lasting impact on the quality of education in Weymouth Schools for years to come. As stated above, we need establish a clear understanding of the goals and objectives of the project so that the work we do in the feasibility phase covers all the necessary topics for discussion and addresses the Owners needs and concerns. Specifically, we propose to: Identify community concerns that will impact the study options. Review existing inadequate space configurations and explore new educational spaces that foster new pedagogies and reinforce the existing strengths of Chapman School. Review Owners policies and objectives. Identify the needs of the School Department for appropriate functional teaching spaces. Capture the goals and objectives of the feasibility study into a Project Charter that will serve as a reference point and guide as we move forward keeping our design process efficient and focused. Feasibility Study: The Hill team will work with the Weymouth School Building Committee and identified Weymouth School Department and Town leaders effectively manage the Feasibility Study. One of our first tasks will be soliciting the services of the architect to research and document existing conditions, assist in developing a detailed educational program, and create a series of alternative design options to address the project requirements. We will work closely with the larger project team to better understand existing conditions, refine the educational program solution, capture additional priorities of the community, and develop multiple solutions for solving the problem. We will review this material with the Building Committee for further refinement and publish a draft report comprising the following major study categories. 1. Site Planning 2. Educational Programming 3. Project Schedule 4. Total Project Budget (Including construction budget) 5. Project Delivery Method (CM at Risk) 6. Project Communication Page 8

13 Schematic Design: During the schematic design phase, Hill will continue to work with the architects and the project team to help ensure that the Owners programming needs are incorporated into the design, that the cost estimates are accurate and complete and that a realistic master project schedule is developed. Much of our work in the schematic design phase is focused on fine tuning the project scope and in documenting it in detail to achieve accurate estimates for the cost of the anticipated project. This is critical as the schematic design submission serves as the basis for the Scope and MSBA Budget Agreement, which is the vehicle to obtain MSBA approval for funding. Hill understands the importance of forward planning and will also focus at this early stage on: Potential impacts on traffic and abutters. Availability of alternate sites and their relative advantages/disadvantages. Schedule regulatory reviews and confirm incorporation into the design. Make certain safety procedures are developed and incorporated into the design documents A communication plan is developed to inform the community, teachers, students and staff during the construction process. > Proposed Project Management Systems and Effective Information Management As described above, we will work with the project team early on to establish a Project Charter that serves as the agreed upon reference for the project s goals. The Project Charter, along with all other documentation and information, will be located in the project management portal that Hill will create for the Feasibility Study. Secure access will be granted to all stakeholders so that all project documents and information can be viewed from a computer or mobile device. Incorporating this technology and the project management portal will save time and allow information to be current and easily accessible for reference. MSBA Procedures: Hill has been working with the MSBA since its founding, and is intimately familiar with their policies and procedures. Our experience representing communities that partner with the MSBA on many school projects has provided us with a set of best practices and lessons learned. We will use this knowledge to provide the best owner s project management representation to the School Building Committee for the ideal project outcome for Weymouth. Community Information: The entire Weymouth community is a key stakeholder for this project. Our approach incorporates the community into the project plan by providing a public forum for the collection and dissemination of important information. Under the direction of the Building Committee, we hold informational meetings to address concerns and inform the community of upcoming plans. Involving the larger community builds awareness of the project within the community and through its transparency lends credibility to the process used and the conclusions drawn about the building project which helps propagate support for project. Project Team / Commitment / Availability 8 Key Personnel As outlined in our cover letter, we are particularly excited about the team we are able to deliver to the Chapman Middle School building project based on their unique talents, experiences and relationships, which will promote a rich project environment and superior project. The organizational chart illustrates the interrelationship of our proposed personnel. Time commitment for this project and experience in the supervision of construction of projects similar in type, size, dollar value and complexity to the project is included in Attachment C. Page 9

14 > Organizational Chart PRINCIPAL-IN-CHARGE Joseph Naughton AIA PROJECT DIRECTOR Paul Kalous AIA, MCPPO PROJECT MANAGER Inger Hamre-Foley MCPPO SENIOR PROJECT MANAGER Simon Tempest, AIA, LEED GA, MCPPO SITE PROJECT MANAGER Frederick Scibelli CSL SCHEDULING Mark McDowell AIA, CCM, MCPPO ESTIMATING Frank Murphy MRICS MEP REVIEW Richard Anderson MCPPO > Proposed Key Staff Principal-in-Charge Joseph Naughton, AIA. Joe has more than 24 years of experience in the construction and architectural design industries. He has extensive experience on municipal projects, both complex additions renovations and new construction. He will be responsible for project oversight and management of the core team. He will use his lessons learned and best practices to advise his team and owners to facilitate successful completion of projects. Reference: Town of Lexington, Pat Goddard, Director of Facilities, Tel: Project Director Paul Kalous, AIA, MCPPO. Paul brings more than 26 years of experience working on projects similar to the District s High School. He has provided similar leadership role on large scale projects with multiple stakeholders, including the $33 million phased renovation of the SRVTHS and $41 million Estabrook Elementary School in Lexington. As Project Director, Paul will lead the project team to confirm the District s project is delivered on time and on budget. Reference: Town of Dracut, Dracut High School, Andrew Graham, Facilities Director, Tel: Senior Project Manager Simon Tempest, AIA, LEED GA, MCPPO. Simon has more than 30 years of experience in the construction industry, and he will serve as your day to day contact from start to finish of the project. His expertise includes architecture, identifying and resolving errors and omissions, QA/QC, asbestos abatement and project procurement. Simon s responsibilities have included project team management, service delivery and administration. Simon has successfully managed major school projects across Massachusetts. As an architect, he was involved in the master planning of two major regional school campuses as well as several individual elementary and secondary schools. Reference: City of Revere Public Schools, Dr. Paul Dakin, Superintendent Emeritus, Tel: Page 10

15 Project Manager Inger Hamre-Foley. As Project Manager, Inger will be the primary day-today contact for the District. She is responsible for directing projects from conception through design, permitting, construction, occupancy and post-occupancy. Inger s experience include the $33 million phased renovation of the SRVTHS and her current work on the $55 million School for Marine Science and Technology at UMass Dartmouth in New Bedford. Reference: Southeastern Regional School District, Voc Tech High School, Luis Lopes, Superintendent, Tel: Site Project Manager Fred Scibelli. Fred has more than 36 years of experience in the construction industry. His projects include construction site management for a number of similar projects, including SRVTHS, Dracut High School, East Bridgewater Jr/Sr High School and on the Everett High School project in Everett, MA, where he was awarded the Unsung Hero award by the Mayor. Reference: Hatfield Public Schools, John F. Robert, Superintendent of Schools, Tel: Firm Qualifications /Capacity 9 Capacity and Skills Locally, Hill has more than 250 resources available, as-needed, in the New England region to support Weymouth s project. The table below provides a breakdown of our firm-wide professional staff by discipline. PROFESSIONAL STAFF BY DISCIPLINE Accounting 101 Contract Administrators 167 Project Managers 847 Administration 688 Electrical Engineers 109 QA/QC 103 Architects 166 Environmental Engineers 24 Safety Engineers 38 Chemical Engineers 8 Estimators 213 Schedulers 145 Civil Engineers 305 Interior Designers 7 Structural Engineers 27 Claims Analysts/Attorneys 292 Landscape Architects 11 Surveyors 97 Communication Engineers 24 Mechanical Engineers 127 Technicians 53 Computer Specialists 127 Planners: Urban/Regional 7 Transportation Engineers 15 Construction Inspectors 202 Procurement 21 Other 149 Construction Managers 218 Project Controls 93 TOTAL 4, Current and Projected Workload The following table outlines the current and projected relevant workload in our Educational Practice for our Boston office. DESIGN PHASE City of Quincy, School Boiler Replacement Projects Town of Braintree, Renovations to East Middle School Auburn Public Schools, Pakachoag School Roof Replacement University of Rhode Island, New College of Engineering Building University of Massachusetts Boston, Renovations to Academic Buildings University of Massachusetts Lowell Renovations to Pasteur Hall Page 11

16 CONSTRUCTION PHASE CLOSEOUT PHASE City of Gardner, School Window and Boiler Replacement Town of Lexington, Clarke Middle School Town of Lexington, Diamond Middle School University of Massachusetts, Dartmouth School of Marine Science and Technology Building Northeastern University, Integrated Science and Engineering Complex City of Peabody, School Roof and Window Replacement Town of Dracut, Addition/Renovation to Existing HS Town of East Bridgewater, New East Bridgewater JR/SR High School Town of Middleton, School Roof and HVAC Replacement City of Revere, Hill Elementary School Town of Webster, Park Avenue Elementary School Town of Stoughton, Roof and Window Replacement, 3 Elementary Schools University of Massachusetts Amherst, South College Academic Facility University of Massachusetts Amherst, Design Building 11 Financial Stability Founded in 1976, Hill is incorporated in the State of Delaware and is a publicly traded company listed on the New York Stock Exchange (NYSE). For detailed Financial Information and Annual Reports, please visit our website at Copies of our most recent balance sheet and income statement are included below. The data presented below is in thousands, except for earnings (loss) per share data. December31, Assets Cashandcashequivalents $ 24,089 $ 30,124 Cash restricted 4,435 8,851 Accountsreceivable,lessallowancefordoubtfulaccountsof$63,748and$60, , ,098 Accountsreceivable affiliates 5,205 3,993 Prepaidexpensesandothercurrentassets 10,299 14,277 Incometaxesreceivable 4,146 4,246 Totalcurrentassets 291, ,589 Propertyandequipment,net 23,751 11,643 Cash restricted,netofcurrentportion 259 7,156 Retainagereceivable 2,638 3,300 Acquiredintangibles,net 14,659 19,282 Goodwill 74,893 80,437 Investments 8,386 5,083 Deferredincometaxassets 19,724 20,220 Otherassets 6,662 9,187 Totalassets $ 442,563 $ 412,897 LiabilitiesandStockholders'Equity Currentmaturitiesofnotespayableandlong-termdebt 4,357 6,361 Accountspayableandaccruedexpenses 112,457 93,637 Incometaxespayable 9,064 9,306 Deferredrevenue 11,310 19,896 Othercurrentliabilities 5,860 10,044 Totalcurrentliabilities 143, ,244 Notespayableandlong-termdebt,netofcurrentmaturities 140, ,163 Retainagepayable 1,929 2,448 Deferredincometaxes 16,341 18,117 Deferredrevenue 11,919 12,193 Otherliabilities 10,661 3,732 Totalliabilities 324, ,897 Commitmentsandcontingencies Stockholders'equity: Preferredstock,$0.0001parvalue;1,000sharesauthorized,noneissued Commonstock,$0.0001parvalue;100,000sharesauthorized,58,335sharesand56,920sharesissued atdecember31,2015and2014,respectively 6 6 Additionalpaid-incapital 188, ,912 Retainedearnings(deficit) 1,205 (5,726) Accumulatedothercomprehensiveloss (46,866) (32,600) 143, ,592 Lesstreasurystockof6,743sharesand6,546sharesatDecember31,2015and2014,respectively,at cost (29,245) (28,304) HillInternational,Inc.shareofequity 113, ,288 Noncontrollinginterests 4,070 8,712 Totalequity 118, ,000 Totalliabilitiesandstockholders'equity $ 442,563 $ 412,897 YearsEndedDecember31, IncomeStatementData: Consultingfeerevenue $ 630,951 $ 577,117 $ 512,085 $ 417,598 $ 399,254 Reimbursableexpenses 89,654 64,476 64,596 63, ,202 Totalrevenue 720, , , , ,456 Costofservices 362, , , , ,991 Reimbursableexpenses 89,654 64,476 64,596 63, ,202 Totaldirectexpenses 452, , , , ,193 Grossprofit 268, , , , ,263 Selling,generalandadministrativeexpenses 237, , , , ,312 Shareofloss(earnings)ofequitymethodaffiliates 237 (190) Operatingprofit(loss) 30,844 33,938 34,698 (43,302) (3,859) Interestandrelatedfinancingfees,net 14,663 30,485 22,864 18,150 7,262 Earnings(loss)beforeincometaxes 16,181 3,453 11,834 (61,452) (11,121) Incometaxexpense(benefit) 8,442 8,300 6,350 13,442 (6,186) Netearnings(loss) 7,739 (4,847) 5,484 (74,894) (4,935) Less:netearnings noncontrollinginterests 808 1,301 1,922 1,872 1,082 Netearnings(loss)attributabletoHillInternational,Inc. $ 6,931 $ (6,148) $ 3,562 $ (76,766) $ (6,017) Basicearnings(loss)percommonshare Hill International,Inc. $ 0.14 $ (0.14) $ 0.09 $ (1.99) $ (0.16) Basicweightedaveragecommonsharesoutstanding 50,874 44,370 39,098 38,500 38,414 Dilutedearnings(loss)percommonshare Hill International,Inc. $ 0.14 $ (0.14) $ 0.09 $ (1.99) $ (0.16) Dilutedweightedaveragecommonsharesoutstanding 51,311 44,370 39,322 38,500 38,414 Page 12

17 ATTACHMENT C Owner s Project Manager Application Form May Project Name/Location for Which Firm is Filing: Maria Weston Chapman Middle School, Weymouth, MA 1a. MSBA Project Number: N/A 2a. Respondent, Firm (Or Joint-Venture) Name And Address Of Primary Office To Perform The Work: 2b. Name And Address Of Other Participating Offices Of The Prime Applicant, If Different From Item 3a Above: 2c. Hill International, Inc. 330 Congress Street, 6 th Fl, Boston, MA Date Present And Predecessor Firms Were Established: 2013 Hill International, Inc. (100% acquisition of CPI) 2011 collaborative partners, Inc. (CPI) N/A 2d. Name And Address Of Parent Company, If Any: N/A 2e. Federal ID #: f. Name of Proposed Project Director: Paul Kalous, AIA, MCPPO 3. Personnel From Prime Firm Included In Question #2 Above By Discipline (List Each Person Only Once, By Primary Function -- Average Number Employed Throughout The Preceding 6 Month Period. Indicate Both The Total Number In Each Discipline): Hill International, Inc. has over 4,500 employees. The numbers below reflect full time positions in the Massachusetts office. Admin. Personnel 2 Cost Estimators 1 Other Total: 34 Architects 7 Electrical Engrs. Acoustical Engrs. Environmental Community Civil Engrs. Licensed Site 6 Proj.Mgr./Asst. PM 18 Code Mechanical Engrs. Financial Analyst 4. Has this Joint-Venture previously worked together? Yes No N/A 5. List ONLY Those Prime and Sub-Consultant Personnel identified as Key personnel in the Response to Request for Services. 13

18 6. Brief Resume for Key Personnel ONLY as indicated in the Request for Services. Resumes Should Be Consistent With The Persons Listed On The Organizational Chart In Question # 5. Additional Sheets Should Be Provided Only As Required For The Number Of Key Personnel And They Must Be In The Format Provided. By Including A Firm As A Subconsultant, The Prime Applicant Certifies That The Listed Firm Has Agreed To Work On This Project, Should The Team Be Selected. a. Name And Title Within Firm: a. Name And Title Within Firm Joseph Naughton, AIA, Sr Vice President & New England Regional Paul Kalous, AIA, MCPPO, Project Director Manager b. Project Assignment: b. Project Assignment: Principal-In-Charge Project Director c. Name And Address Of Office In Which Individual Identified in 6a Resides: c. Name And Address Of Office In Which Individual Identified In 6a Resides: Hill International, Inc. 330 Congress Street, 6 th Floor, Boston, MA Hill International, Inc. 330 Congress Street, 6 th Floor, Boston, MA d. Years experience: With This Firm: 8 With Other Firms: 20 d. Years Experience: With This Firm: 11 With Other Firms: 17 e. Education: Degree(s) /Year/Specialization e. Education: Degree(s) /Year/Specialization MA/Master of Architecture/1993/ Urban Design Bachelor of Architecture/1988 Master of Architecture/1988/Architecture BS/1982/Construction Administration f. Date of MCCPO Certification: f. Date of MCCPO Certification: 11/15/2013 (recertification) g. Applicable Registration and Certifications: American Institute of Architects h. Current Work Assignments And Availability For This Project: Joe is the Principal-in-Charge for numerous Hill projects including Jonas Clarke Middle School and Diamond Middle School in Lexington. Will be available 20% i. Other Experience And Qualifications Relevant To The Proposed Project: (Identify Firm By Which Employed, If Not Current Firm): Lexington Diamond and Clarke Middle Schools, Lexington, MA James J. Hill School, Revere, MA Park Avenue Elementary School, Webster, MA Paul Revere Elementary School, City of Revere, MA Howe Manning Elementary School, Middleton, MA Dracut High School, Dracut, MA East Bridgewater Junior Senior High School, Bridgewater, MA g. Applicable Registrations and Certifications: Registered Architect, MA #9327 American Institute of Architects MCPPO Certified for the MSBA h. Current Work Assignment and Availability for this Project: Town Braintree Repair and Renovation Project Dracut High School Closeout Town of Lexington Will be available 100%, Expected need is 50% i. Other Experience And Qualification Relevant To The Proposed Project: (Identify Firm By Which Employed, If Not Current Firm): Southeastern Regional School District, Southeastern Regional Vocational Technical High School Wareham Public Schools District, Wareham High School, Wareham, MA Town of Dracut, Renovation and Addition to High School City of Everett, New High School Town of Lexington, Estabrook Elementary School Town of East Bridgewater, East Bridgewater High School a. Name And Title Within Firm: Name And Title Within Firm: Simon Tempest, AIA, LEED GA, MCPPO, Project Director a. Inger Hamre-Foley, MCPPO, Project Manager b. Project Assignment: Senior Project Manager b. Project Assignment: Project Manager c. Name And Address Of Office In Which Individual Identified in 6a Resides: c. Name And Address Of Office In Which Individual Identified in 6a Resides: Hill International, Inc. 330 Congress Street, 6 th Floor, Boston, MA c. Hill International, Inc. 330 Congress Street, 6 th Floor, Boston, MA

19 d. Years experience: With This Firm: 8 With Other Firms: 31 d. Years experience: With This Firm: 8 With Other Firms: 10 e. Education: Degree(s) /Year/Specialization Education: Degree(s) /Year/Specialization n/a e. BS/Facility Planning and Management/2009 Certificate/OSHA 10 Hour/2011 f. Date of MCCPO Certification: 03/01/2015 f. Date of MCCPO Certification: 05/21/2013 g. Applicable Registration and Certifications: American Institute of Architects Registered Architect, MA #9852 MCPPO Certified for the MSBA LEED Green Associate h. Current Work Assignment and Availability for this Project: Town of Braintree, East Middle School Rowes Wharf Plaza Restoration Project University of Mass Building Authority, UMass Dartmouth - SMAST Will be available 100%, Expected need is 50% i. Other Experience And Qualifications Relevant To The Proposed Project: (Identify Firm By Which Employed, If Not Current Firm): Town of East Bridgewater, High School City of Revere, A.C. Whelan Elementary School and Susan B. Anthony Middle School City of Revere, Paul Revere School City of Revere, Sergeant James J. Hill School a. Name And Title Within Firm: Frederick Scibelli, CSL, Construction Manager b. Project Assignment: Site Project Representative c. Name And Address Of Office In Which Individual Identified in 6a Resides: Hill International, Inc. 330 Congress Street, 6 th Floor, Boston, MA d. Years experience: With This Firm: 9 With Other Firms: 36 e. Education: Degree(s) /Year/Specialization Associates Eng/1981/Architectural Engineering Technology Certificate/1978/Architectural Drafting Technology f. Date of MCCPO Certification: n/a g. Applicable Registration and Certifications: MCPPO h. Current Work Assignment and Availability for this Project: Town of Braintree, East Middle School Repair and Renovation project UMass Dartmouth, School for Marine Science and Technology Will be available as needed and estimated 50% i. Other Experience And Qualifications Relevant To The Proposed Project: (Identify Firm By Which Employed, If Not Current Firm): Southeastern Regional School District, Southeastern Regional Vocational Technical High School, South Easton, MA Town of Braintree, East Middle School, Braintree, MA Atlantis Charter School, Study Phase 1, Fall River, MA Town of Swampscott, Hadley Elementary School, Swampscott, MA Boston College High School, Cadigan Hall, Boston, MA 15

20 g. Applicable Registration and Certifications: ACI Concrete Field Testing, Technician Grade I Construction Supervisor, MA HE-2A-Excavators License Hoisting Engineer License h. Current Work Assignments And Availability For This Project: City of Revere, Hill School, Project Manager Northeastern University, Interdisciplinary Science and Engineering Will be available as needed and estimated 100% during construction i. Other Experience And Qualifications Relevant To The Proposed Project: (Identify Firm By Which Employed, If Not Current Firm): City of Everett, High School, Everett, MA Southeastern Regional School District, Vocational Technical High School, South Easton, MA City of Revere, Sergeant James J. Hill Elementary School, Revere, MA Town of Middleton, Howe-Manning Elementary School, Middleton, MA 7a Past Performance: List all Completed Projects, in excess of $1.5 million, for which the Prime Applicant has performed, or has entered into a contract to perform Owner s Project Management Services for all Public Agencies within the Commonwealth within the past 10 years. Below is a list of projects done out of our New England based office. a. Project Name And Location b. Brief Description Of Project And c. Project Dollar d. Completion e. On Time f. Original g. Change Orders h. Number of i. Dollar j. Number Project Director Services (Include Reference To Value Date (Actual Or (Yes Or Construction Accidents Value of And Areas Of Similar Experience) Estimate) No) Contract Value and Safety Violations any Safety Outcome Of fines (1) Rumney Marsh Academy, Revere, MA, David Billings (2) Paul Revere School, Revere, MA, Joe Naughton (3) Revere Police Fire Station, Revere, MA, Joe Naughton (4) Howe-Manning School, Middleton, MA, David Billings (5) Everett High School, Everett, MA, Paul Kalous OPM for planning, design & const. of new middle school. $32.6 million 09/2008 Yes $24,584,000 $2,203,473 (incl. owner scope additions) OPM for elementary school. $17.4 million 09/2010 Yes $12,744,400 $747,200 (incl. owner scope additions) OPM for planning, design and construction of new Police HQ and Fire Station. OPM for planning, design, and construction of a new school. OPM for new high school. Project involved dismissal of architect and re-bidding. $20.4 million 06/2008 Yes $16.4 million $648,000 (incl. owner scope additions) $31 million, final $25 million 12/2011 Yes $17.9 Million $1.2 million (incl. owner scope additions) $82 million 09/2007 Yes $63,956,850 $2,240,554 (incl. owner scope additions) Legal Actions

21 (6) Abby Kelley Foster Charter Public School Worcester, MA, Paul Kalous (7) Green Repair Program, Braintree, MA, Joe Naughton (8) Natick High, Natick, MA, David Billings (9) Tri-County Regional Vocational Technical HS, Paul Kalous (10) Southeastern Regional Vocational Tech High School, Joe Naughton OPM for conversion of an industrial building for use as new high school OPM for roof and window replacements at 5 Schools OPM for planning, design & construction of new school $17 million 09/2009 Yes $15.5 Million $1.5 million (incl. owner scope additions) $3.35 million 11/2011 Yes $2.6 Million 2.6% $89 million 08/2013 Yes $63 million $2.1 million (incl. owner scope additions) OPM for new science labs $1.8 million 09/2013 Yes $942,000 $3, OPM for the addition and renovation of the Regional Technical HS (11) East Bridgewater Jr/Sr OPM for planning, design and High, East Bridgewater, construction of a new model MA, Simon Tempest high school (12) Estabrook Elementary OPM for the new Estabrook School, Lexington, MA, Elementary School Paul Kalous (13) Melrose High School,Melrose, MA, Paul Kalous $33 million 9/2013 Yes $27.2 million $889,809 (incl. owner scope additions) $77 million 10/2014 Yes $61 million $2.3 million (incl. owner scope additions) $41 million 12/2014 Yes $32.7 million $955,000 (incl. owner scope additions) OPM for new science labs $6.2 million 09/2013 Yes $3.5 million $189, b. Past Performance: Provide the following information for those completed Projects listed above in 7a for which the Prime Applicant has performed, or has entered into a contract to perform OPM Services for all Public Agencies within the Commonwealth within the past 10 years. Below is a list of projects done out of our New England based office. a. Project Name And Location Project Director b. Original Project Budget c. Final Project Budget d. If different, provide reason(s) for variance e. Original Project Completion e. Actual Project Completion On Time (Yes or No) (1) Rumney Marsh Academy, Revere, MA, David $32.6 million $32.6 million 09/2008 Yes Billings (2) Paul Revere School, Revere, MA, Joe Naughton $17.4 million $17.4 million 09/2010 Yes (3) Revere Police Headquarters and Fire Station, $20.4 million $20.4 million 06/2008 Yes Revere, MA, Joe Naughton (4) Howe-Manning School, Middleton, MA, David Billings $31 million $25.2 million Bid day savings 12/2011 Yes f. If different, provide reason(s) for variance. 17

22 (5) Everett High School, Everett, MA, Paul Kalous $82 million $82 million 09/2007 Yes (6) Natick High School, Natick, MA, David Billings $89 million $78.5 million Bid day savings 08/2013 Yes (7) Tri-County Regional Vocational Technical HS, Paul $1.8 million $1.4 million 09/2013 Yes Kalous (8) Southeastern Regional Vocational Technical High School, Joe Naughton $33 million $33 million 12/2013 Yes (completed 3 months early) (9) East Bridgewater Jr/Sr High, East Bridgewater, $77 million $77 million 10/2014 Yes MA, Simon Tempest (10) Estabrook Elementary School, Lexington, MA Paul $40.8 million $39.9 million 12/2014 Yes Kalous (11) Melrose High School, Melrose, MA, Paul Kalous $6.4 million $5 million 09/2013 Yes 8. Capacity: Identify all current/ongoing Work by Prime Applicant, Joint-Venture Members or Subconsultants. Identify project participants and highlight any work involving the project participants identified in the response. Below is a list of projects done out of our New England based office. Project Name And Location Project Director 1. HS Roof Replacement, Leicester, MA, Paul Kalous 2. Gardner Accelerated Repair, Gardner, MA, Paul Kalous 3. Accelerated Repair, Peabody, MA, Emily Traversi 4. Design Building, UMass Amherst, David Billings 5. Atlantis Charter School, Fall River, MA, Paul Kalous 6. Diamond Middle School, Lexington, MA, Paul Kalous 7. Jonas Clarke Middle School, Lexington, MA, Paul Kalous b. Brief Description Of Project And Services (Include Reference To Areas Of Similar Experience) OPM for roof replacement for Leicester High School OPM: window and boiler repair with potential to include additional systems OPM for roof/window replacement-58,000 SF roof OPM for new 85,000 SF academic building for School of Architecture OPM for the design and construction for a new Charter School in Fall River OPM for the addition of middle school project. OPM for the addition of middle school project. c. Original Project Budget $2.5 million $4 million $4 million $52 million $36 million $44.9 million $21.6 million d. Current Project Budget $1.7 million $3 million $4.3 million $52 million $36 million $44.9 million $21.6 million d. Project Completion Date e. Current forecast completion date On Time (Yes Or No) f. Original Construction Contract Value 12/2016 Yes (Close-out) $1.4 million 9/2016 Yes (Close-out) $2.5 million g. Number and dollar value of Change Orders h. Number and dollar value of claims TBD 0 -$36,000 credit 12/2016 Yes $3.8 $42,426 0 million credit 3/2017 Yes $37 million $1.8 million 0 4/2018 Yes $26.5 million 2018 TBD August /2017 TBD August TBD 0 $34 million TBD 0 $16 million TBD 0 9. References: Provide the following information for completed and current Projects listed above in 7 and 8 for which the Prime Applicant has performed, or has entered into a contract to perform OPM Services for all Public Agencies within the Commonwealth within the past 10 years. Below is a list of project done out of our New England based office. 18

23 Project Name And Location Project Director 1) Revere Public Schools and Facilities Revere, MA, David Billings 4) Natick High School Natick, MA David Billings 7) Groton Dunstable Green Repair Project, Groton, MA Joseph Reilly 10) Abby Kelley Foster Charter Public Worcester, MA Paul Kalous 13) Tri-County Regional Vocational Technical HS, Paul Kalous Client s Name, Address and Phone Number. Include Name of Contact Person Paul Dakin, Spt Revere Public Schools, 101 School St, Revere, MA Tel: Dr. Peter Sanchioni, Superintendent, Natick Public Schools, 13 East Central Street Natick, MA 01760; Tel: Jared Stanton, Director of Business and Finance, Groton-Dunstable Regional Schools, 145 Main Street, Groton MA, Tel: x205 Dianne Bonaventura, Business Manager, 10 New Bond Street, Worcester, MA 01606; Tel: Stephen Dockray, Spt, Tri- County Regional Voc. Tech. HS, 147 Pond St, Franklin, MA 02038, Tel: Project Name And Location Project Director 2) Middleton Elementary Middleton, MA David Billings 5) Webster Public Schools, Webster, MA David Billings 8) East Bridgewater Junior/Senior High School East Bridgewater, MA, Paul Kalous 11) Marlborough Green Repair Marlborough, MA Paul Kalous 14) Science Lab Initiative Melrose, MA Paul Kalous Client s Name, Address and Phone Number. Include Name of Contact Person Frank Fitzgerald, Chair Middleton SBC, Town of Middleton, 28 Middleton Road, Boxford, MA 01921, Tel: Ted Avlas, Assistant to the Superint. for Business Webster Public Schools 41 East Main Street, Webster, MA 01570, Tel:: David Floeck, Chair East Bridgewater SBC, Town Hall, 175 Central Street, East Bridgewater, MA Tel: John L. Ghiloni, Public Facilities Director, Marlborough Schools, 85 Sawin St, Marlborough, MA 01752, Tel: Denise M. Gaffey, Director and City Planner, City of Melrose 562 Main St, Melrose, MA 02176, Tel: Project Name And Location Project Director 3) Everett High School Everett, MA Paul Kalous 6) Dracut Senior High School Dracut, MA Paul Kalous 9) Southeastern Regional Vocational Technical HS, South Easton, MA Joe Naughton 12) Estabrook Elementary School Paul Kalous 13) Design Building UMass Amherst Amherst, MA David Billings Client s Name, Address and Phone Number. Include Name of Contact Person Maureen DiPierro, Everett School Commission, City of Everett, 484 Broadway, Everett, MA 02149, Tel: Steven Stone, Superintendent Dracut Public Schools, 2063 Lakeview Avenue, Dracut, MA 01826, Tel: Luis Lopes, Ed.S., Supt. 250 Foundry Street South Easton, MA Tel: Pat Goddard, Director Public Facilities, Town of Lexington 201 Bedford St, Lexington, MA 02420, Tel: Burt Ewart Senior Project Manager, UMBA, 225 Franklin Street, Boston, MA 02110, Tel: Use This Space To Provide Any Additional Information Or Description Of Resources Supporting The Qualifications Of Your Firm And That Of Your Subconsultants. For more than 40 years Hill has provided OPM services to both private sector and public sector clients. We will function as an extension to the Owner, as a resource to assist in the delivery of the middle school with the anticipated quality, expected cost, and delineated schedule. 10. I hereby certify that the undersigned is an Authorized Signatory of Firm and is a Principal or Officer of Firm. The information contained in this application is true, accurate and sworn to by the undersigned under the pains and penalties of perjury. Submitted By (Signature) Printed Name And Title Joseph A. Naughton, AIA, Sr. Vice President Date 1/18/

24

25 ATTACHMENT D, REQUIRED CERTIFICATIONS Statement of Management

26 Certificate of Authority January 16, 2016

27 Certificate of Good Standing The Commonwealth of Massachusetts Secretary of the Commonwealth State House, Boston, Massachusetts William Francis Galvin Secretary of the Commonwealth Date: January 10, 2017 To Whom It May Concern : I hereby certify that according to the records of this office, HILL INTERNATIONAL, INC. a corporation organized under the laws of DELAWARE on April 02, 2004 was qualified to do business in this Commonwealth on October 06, 2008 under the provisions of the General Laws, and I further certify that said corporation is still qualified to do business in this Commonwealth. I also certify that said corporation is not delinquent in the filing of any annual reports required to date. In testimony of which, I have hereunto affixed the Great Seal of the Commonwealth on the date first above written. Secretary of the Commonwealth Certificate Number: Verify this Certificate at: Processed by:

REQUEST FOR QUALIFICATIONS. Architectural/Engineering Design Services

REQUEST FOR QUALIFICATIONS. Architectural/Engineering Design Services REQUEST FOR QUALIFICATIONS Architectural/Engineering Design Services Logistics DISTRICT CONTACTS FOR QUESTIONS Jeff Collum Superintendent Phone: 903-668-5990 Email: jcollum@hisd.com REQUEST FOR STATEMENT

More information

Owner s Project Manager Selection

Owner s Project Manager Selection Timothy P. Cahill Chairman, State Treasurer Katherine P. Craven Executive Director Owner s Project Manager Selection INTRODUCTION Selecting a qualified Owner s Project Manager is one of the most important

More information

REQUEST FOR QUALIFICATIONS AND REQUEST FOR PROPOSALS FOR ARCHITECTURAL SERVICES CROMWELL BELDEN PUBLIC LIBRARY TOWN OF CROMWELL, CONNECTICUT

REQUEST FOR QUALIFICATIONS AND REQUEST FOR PROPOSALS FOR ARCHITECTURAL SERVICES CROMWELL BELDEN PUBLIC LIBRARY TOWN OF CROMWELL, CONNECTICUT REQUEST FOR QUALIFICATIONS AND REQUEST FOR PROPOSALS FOR ARCHITECTURAL SERVICES CROMWELL BELDEN PUBLIC LIBRARY TOWN OF CROMWELL, CONNECTICUT The Town of Cromwell is seeking written responses to a Request

More information

REQUEST FOR QUALIFICATIONS PROJECT AND CONSTRUCTION MANAGEMENT CONSULTANT

REQUEST FOR QUALIFICATIONS PROJECT AND CONSTRUCTION MANAGEMENT CONSULTANT REQUEST FOR QUALIFICATIONS PROJECT AND CONSTRUCTION MANAGEMENT CONSULTANT DUE: May 4, 2018 4:00 P.M. Walla Walla Public Schools 364 S. Park Street Walla Walla, WA 99362 District Representative/Contact:

More information

REQUEST FOR PROPOSAL FOR DESIGN (ARCHITECTURAL & ENGINEERING) SERVICES

REQUEST FOR PROPOSAL FOR DESIGN (ARCHITECTURAL & ENGINEERING) SERVICES REQUEST FOR PROPOSAL FOR DESIGN (ARCHITECTURAL & ENGINEERING) SERVICES Prepared by: Middleton-Cross Plains Area School District 7106 South Avenue Middleton, Wisconsin 53562 December 22, 2011 Request for

More information

Washington County Public Works, Building Services

Washington County Public Works, Building Services Public Works Department 11660 Myeron Road North Stillwater, MN 55082 Washington County Public Works, Building Services Qualifications for Architectural and Engineering Services For Washington County Library,

More information

Design/Builder Qualifications Supplement (DBQS) Instructions. GENERAL INSTRUCTIONS UF-583, Ground Floor Renovation (Basic Science Bldg)

Design/Builder Qualifications Supplement (DBQS) Instructions. GENERAL INSTRUCTIONS UF-583, Ground Floor Renovation (Basic Science Bldg) BUSINESS AFFAIRS www.facilities.ufl.edu PLANNING DESIGN & CONSTRUCTION Design/Builder Qualifications Supplement (DBQS) Instructions GENERAL INSTRUCTIONS UF-583, Ground Floor Renovation (Basic Science Bldg)

More information

Mandatory Site Visit: Thursday, July 13, :00 PM (Pierson Library, Shelburne, VT)

Mandatory Site Visit: Thursday, July 13, :00 PM (Pierson Library, Shelburne, VT) Request for Proposal for Construction Management (CM) Services for the Shelburne Community Center and Public Library Shelburne, Vermont. Request for Proposal Issued: Friday, Mandatory Site Visit: Thursday,

More information

January 2, 2018 REQUEST FOR QUALIFICATIONS FOR ARCHITECTURAL AND ENGINEERING SERVICES

January 2, 2018 REQUEST FOR QUALIFICATIONS FOR ARCHITECTURAL AND ENGINEERING SERVICES January 2, 2018 REQUEST FOR QUALIFICATIONS FOR ARCHITECTURAL AND ENGINEERING SERVICES I. Project Forsyth County Courthouse & Administrative Building II. Goal Forsyth County requests responses from licensed

More information

Berne Knox Westerlo Central School District

Berne Knox Westerlo Central School District Berne Knox Westerlo Central School District Proposed Capital Project Progress Summary Report to the Board of Education May 8, 2017 Proposed Capital Project Background In 2015 the Board of Education and

More information

Addendum No. 2 April 15, 2015 Architectural Design Services Requirements Contracts Request for Qualifications Project No.

Addendum No. 2 April 15, 2015 Architectural Design Services Requirements Contracts Request for Qualifications Project No. Facilities Planning, Construction, and Management Office of Financial Management Procurement Services 555 West 57 th Street 16 th Floor New York, NY 10019 Tel: 646-664-2700 Addendum 2 April 15, 2015 Architectural

More information

Request for Proposal (RFP) The Klamath Tribes Youth Fitness Center Klamath Tribes Housing Department (KTHD) RFP # 09-KTHD17

Request for Proposal (RFP) The Klamath Tribes Youth Fitness Center Klamath Tribes Housing Department (KTHD) RFP # 09-KTHD17 Request for Proposal (RFP) The Klamath Tribes Youth Fitness Center Klamath Tribes Housing Department (KTHD) RFP # 09-KTHD17 Introduction: This Request for Proposals (RFP) solicitation is to provide to

More information

SALADO INDEPENDENT SCHOOL DISTRICT

SALADO INDEPENDENT SCHOOL DISTRICT SALADO INDEPENDENT SCHOOL DISTRICT Request for Qualifications The Salado Independent School District ( District ) is seeking Submissions in response to this Request for Qualifications ( RFQ ) for architectural

More information

Galesburg Public Library, Galesburg, IL

Galesburg Public Library, Galesburg, IL Galesburg Public Library, Galesburg, IL Request for Qualifications ( RFQ ) Architectural, Engineering, Construction Management and Related Services I. OVERVIEW The Galesburg Public Library is seeking architectural,

More information

L1354, CENTRAL HEATING PLANT UPGRADE, LOGAN INTERNATIONAL AIRPORT, EAST

L1354, CENTRAL HEATING PLANT UPGRADE, LOGAN INTERNATIONAL AIRPORT, EAST MASSACHUSETTS PORT AUTHORITY CAPITAL PROGRAMS AND ENVIRONMENTAL AFFAIRS DEPARTMENT SUITE 209S LOGAN OFFICE CENTER SUITE 209S ONE HARBORSIDE DRIVE EAST BOSTON MA 02128-2909 REQUEST FOR QUALIFICATIONS L1354,

More information

Morgan Hill Unified School District

Morgan Hill Unified School District Facilities Department 15600 Concord Circle, Morgan Hill, CA 95037 Phone: (408) 201-6087 Fax (408) 776-0175 REQUEST FOR ARCHITECTURAL SERVICES PROPOSALS for a New Britton MS Campus and Site Master Plan

More information

District Office Building Seismic Retrofit At Contra Costa Community College District 500 Court St. Martinez, CA March 21, 2016

District Office Building Seismic Retrofit At Contra Costa Community College District 500 Court St. Martinez, CA March 21, 2016 REQUEST FOR QUALIFICATIONS (RFQ) ARCHITECT/ENGINEER (A/E) PROFESSIONAL SERVICES For the At Contra Costa Community College District 500 Court St. Martinez, CA March 21, 2016 PART 1 GENERAL INTRODUCTION

More information

Keynote Presentation. Commissioning Summit: Building Commissioning Association. Massachusetts School Building Authority

Keynote Presentation.  Commissioning Summit: Building Commissioning Association. Massachusetts School Building Authority Massachusetts School Building Authority Steven Grossman Chairman, State Treasurer Jack McCarthy Executive Director Keynote Presentation Commissioning Summit: Building Commissioning Association March 14,

More information

Request for Qualifications (Architect / Engineer) State of Ohio Standard Forms and Documents

Request for Qualifications (Architect / Engineer) State of Ohio Standard Forms and Documents Request for Qualifications (Architect / Engineer) State of Ohio Standard Forms and Documents Administration of Project: Local Higher Education Project Name Research Laboratory Renovations Response Deadline

More information

Request for Qualifications (Architect / Engineer) State of Ohio Standard Forms and Documents

Request for Qualifications (Architect / Engineer) State of Ohio Standard Forms and Documents Request for Qualifications (Architect / Engineer) State of Ohio Standard Forms and Documents Administration of Project: Local Higher Education Project Name BGSU Ice Arena Space Study Response Deadline

More information

September 5, 2018 FREQUENTLY ASKED QUESTIONS (FAQs) EPS REFERENDUM 18 VOTE, Tuesday, October 2, 2018

September 5, 2018 FREQUENTLY ASKED QUESTIONS (FAQs) EPS REFERENDUM 18 VOTE, Tuesday, October 2, 2018 September 5, 2018 FREQUENTLY ASKED QUESTIONS (FAQs) EPS REFERENDUM 18 VOTE, Tuesday, October 2, 2018 On Tuesday, October 2 nd, The Ewing Public Schools will ask the community to vote on a $59.3 million

More information

Lexington Center Corporation Request for Qualifications for PROJECT COORDINATOR SERVICES

Lexington Center Corporation Request for Qualifications for PROJECT COORDINATOR SERVICES Lexington Center Corporation Request for Qualifications for PROJECT COORDINATOR SERVICES Lexington Convention Center Renovation and Expansion I. Description of Project The Lexington Center Corporation

More information

Facilities Condition Assessment

Facilities Condition Assessment Facilities Condition Assessment (O&M 16 018) Date Issued: January 29, 2016 Date Due: Contact: March 3, 2016 at 4:00:00 pm Paul Acosta, Program Manager III paul.acosta@stocktonca.gov City of Stockton Public

More information

Q. What are we voting on? Q. How was the referendum developed?

Q. What are we voting on? Q. How was the referendum developed? Q. What are we voting on? A. On April 3rd, the voters of the Peshtigo School District will have the opportunity to vote on two referendum questions. The first question will approve $29,960,000 for the

More information

E-J Industrial Spine BOA Nomination Study

E-J Industrial Spine BOA Nomination Study Section VII. Major Recommendations A. Introduction The E-J BOA Study Area provides a number of unique opportunities to develop large-scale properties in a highly accessible urban setting. Considering the

More information

Request for Qualifications (RFQ) RFQ203: Architectural Services for Lab Design renovations

Request for Qualifications (RFQ) RFQ203: Architectural Services for Lab Design renovations Massachusetts Institute of Technology Department of Facilities Building NW23 100 77 Massachusetts Avenue Cambridge, Massachusetts 02139 4307 CQPinfo@mit.edu Request for Qualifications (RFQ) RFQ203: Architectural

More information

Massachusetts Bay Transportation Authority. POLICIES & PROCEDURES Design Build Procurement Procedures April 2016

Massachusetts Bay Transportation Authority. POLICIES & PROCEDURES Design Build Procurement Procedures April 2016 Massachusetts Bay Transportation Authority POLICIES & PROCEDURES Design Build Procurement Procedures April 2016 Design Build Procurement Procedures April 2016 Massachusetts Bay Transportation Authority

More information

This request for qualifications seeks the following type of service providers:

This request for qualifications seeks the following type of service providers: ANNOUNCEMENT REQUEST FOR STATEMENT OF QUALIFICATIONS NOTICE SAN FRANCISCO UNIFIED SCHOOL DISTRICT FACILITIES DESIGN AND CONSTRUCTION ARCHITECTURAL SERVICES The San Francisco Unified School District, Facilities,

More information

ARCHITECTURAL, LANDSCAPE, AND ENGINEERING CONSULTING SERVICES

ARCHITECTURAL, LANDSCAPE, AND ENGINEERING CONSULTING SERVICES REQUEST FOR QUALIFICATIONS # 1206-18/19 FOR ARCHITECTURAL, LANDSCAPE, AND ENGINEERING CONSULTING SERVICES Issue Date: June 26, 2018 Pre-Bid July 9, 2018 at 10:00 A.M. Conference: 1515 West Mission Road,

More information

2017 Rural Hospital Capital Improvement Grant Program Final Application Guidelines

2017 Rural Hospital Capital Improvement Grant Program Final Application Guidelines 2017 Rural Hospital Capital Improvement Grant Program Final Application Guidelines Minnesota Department of Health Office of Rural Health & Primary Care The purpose of this document is to assist you in

More information

REQUEST FOR QUALIFICATIONS AS-NEEDED EXECUTIVE ARCHITECTS

REQUEST FOR QUALIFICATIONS AS-NEEDED EXECUTIVE ARCHITECTS AS-NEEDED EXECUTIVE ARCHITECTS FOR INFRASTRUCTURE PROJECTS UC SAN DIEGO HEALTH SYSTEM - HILLCREST UNIVERSITY OF CALIFORNIA, SAN DIEGO OFFICES OF CAPITAL PROGRAM MANAGEMENT Proposals due June 5, 2018 Issue

More information

BLUE HILLS MASTER PLAN RFP OUTLINE

BLUE HILLS MASTER PLAN RFP OUTLINE BLUE HILLS MASTER PLAN RFP OUTLINE Introduction The City of Hartford is soliciting responses from qualified individuals/firms to provide professional services for creation of a Master Plan for the Blue

More information

Request for Qualifications

Request for Qualifications Request for Qualifications Architectural & Engineering Services for HUTTON ELEMENTARY SCHOOL Modernization and Additions Project Submittal Deadline: August 24, 2012, 4:00 P.M. Spokane Public Schools 2815

More information

8, 2018 REQUEST FOR PROPOSALS (RFP): G

8, 2018 REQUEST FOR PROPOSALS (RFP): G ADDENDUM NO. 2 DATE: June 8, 2018 REQUEST FOR PROPOSALS (RFP): G180026673 Design Professional Services Richmond Public Schools George Mason Elementary School DATED: May 15, 2018 PROPOSAL DUE DATE & TIME:

More information

NORTHWESTERN UNIVERSITY PROJECT NAME JOB # ISSUED: 03/29/2017

NORTHWESTERN UNIVERSITY PROJECT NAME JOB # ISSUED: 03/29/2017 SECTION 26 0800 - COMMISSIONING OF ELECTRICAL SYSTEMS PART 1 - GENERAL 1.1 SUMMARY A. The purpose of this section is to specify the Division 26 responsibilities and participation in the commissioning process.

More information

Conrad Grebel University College. Kitchen and Dining Room Expansion and Renovation Architectural Feasibility Study

Conrad Grebel University College. Kitchen and Dining Room Expansion and Renovation Architectural Feasibility Study Conrad Grebel University College Request for Proposals For the Provision of Architectural Consulting Services Conrad Grebel University College invites eligible architects to submit a proposal for the provision

More information

REFERENDUM 2018 SCHOOL DISTRICT OF PHILLIPS

REFERENDUM 2018 SCHOOL DISTRICT OF PHILLIPS REFERENDUM 2018 SCHOOL DISTRICT OF PHILLIPS Updated: 03-22-18 (Commonly Asked Questions) Commonly Asked Questions, 01-03 (as of 03-06-18) Question 01: How did we get to the need for a referendum on the

More information

REQUEST FOR QUALIFICATIONS/PROPOSAL (RFQ/P) FOR ARCHITECT/ENGINEER (A/E)

REQUEST FOR QUALIFICATIONS/PROPOSAL (RFQ/P) FOR ARCHITECT/ENGINEER (A/E) REQUEST FOR QUALIFICATIONS/PROPOSAL (RFQ/P) FOR ARCHITECT/ENGINEER (A/E) Hinsdale County School District RE-1 PO Box 39 614 N. Silver St. Lake City, CO 81235 (970) 944-2314 PROPOSAL DUE DATE/DELIVERY REQUIREMENTS-

More information

REQUEST FOR QUALIFICATIONS PITTSBURGH INTERNATIONAL AIRPORT PROFESSIONAL ARCHITECTURAL AND ENGINEERING DESIGN AND CONSTRUCTION PHASE SERVICES FOR THE

REQUEST FOR QUALIFICATIONS PITTSBURGH INTERNATIONAL AIRPORT PROFESSIONAL ARCHITECTURAL AND ENGINEERING DESIGN AND CONSTRUCTION PHASE SERVICES FOR THE REQUEST FOR QUALIFICATIONS PITTSBURGH INTERNATIONAL AIRPORT PROFESSIONAL ARCHITECTURAL AND ENGINEERING DESIGN AND CONSTRUCTION PHASE SERVICES FOR THE TERMINAL MODERNIZATION PROGRAM The Allegheny County

More information

REQUEST FOR PROPOSAL TO PROVIDE AS-NEEDED ENGINEERING SERVICES FOR THE IMPLEMENTATION OF

REQUEST FOR PROPOSAL TO PROVIDE AS-NEEDED ENGINEERING SERVICES FOR THE IMPLEMENTATION OF REQUEST FOR PROPOSAL TO PROVIDE AS-NEEDED ENGINEERING SERVICES FOR THE IMPLEMENTATION OF PURPLE LINE EXTENSION PROJECT BY LOS ANGELES COUNTY METROPOLITAN TRANSPORTATION AUTHORITY Project No. 16-34 CITY

More information

Health Care Construction Projects

Health Care Construction Projects Protecting and promoting the health and safety of the people of Wisconsin Health Care Construction Projects DHS and the Municipal AHJ Henry Kosarzycki, AIA, Director DHS Division of Quality Assurance Office

More information

REQUEST FOR QUALIFICATIONS

REQUEST FOR QUALIFICATIONS FACILITIES MANAGEMENT 4202 EAST FOWLER AVENUE / OPM 100 TAMPA, FL 33620-7550 EDITION: NOVEMBER 1, 2016 PHONE: (813) 974-2845 FAX: (813) 974-3542 REQUEST FOR QUALIFICATIONS PROJECT NAME: USF CPT REPLACE

More information

Green Building Incentive Program Guidelines & Procedures

Green Building Incentive Program Guidelines & Procedures Green Building Incentive Program Guidelines & Procedures A program of Andersonville Special Service Area #22 Administered by Andersonville Development Corporation 5153 N. Clark St., Suite 204 Chicago,

More information

Wilmington Downtown Incorporated. Facade Improvement Program POLICIES AND PROCEDURES Updated 8/30/17

Wilmington Downtown Incorporated. Facade Improvement Program POLICIES AND PROCEDURES Updated 8/30/17 Wilmington Downtown Incorporated Facade Improvement Program POLICIES AND PROCEDURES Updated 8/30/17 Wilmington Downtown Incorporated (WDI) has designed a pilot Facade Improvement Program to stimulate new

More information

Universal City Storefront Improvement Program

Universal City Storefront Improvement Program Universal City Storefront Improvement Program To encourage the enhancement of storefronts on commercial, professional, and retail buildings in Universal City. Grant Funds Available Painting Doors Windows

More information

LOCKHART INDEPENDENT SCHOOL DISTRICT

LOCKHART INDEPENDENT SCHOOL DISTRICT LOCKHART INDEPENDENT SCHOOL DISTRICT Request for Qualifications #14-011 The Lockhart Independent School District ( District ) is seeking Submissions in response to this Request for Qualifications ( RFQ

More information

REQUEST FOR PROPOSAL (RFP) SITE SELECTION AND PRELIMINARY DESIGN SERVICES FOR PARKING STRUCTURE

REQUEST FOR PROPOSAL (RFP) SITE SELECTION AND PRELIMINARY DESIGN SERVICES FOR PARKING STRUCTURE 1. INVITATION REQUEST FOR PROPOSAL (RFP) SITE SELECTION AND PRELIMINARY DESIGN SERVICES FOR PARKING STRUCTURE The Town of Brunswick (Town) is soliciting proposals, from qualified firms, to provide professional

More information

REQUEST FOR PROPOSAL (RFP) for Feasibility Study Borough of Kennett Square New Municipal Office and Police Station Joint Facility

REQUEST FOR PROPOSAL (RFP) for Feasibility Study Borough of Kennett Square New Municipal Office and Police Station Joint Facility REQUEST FOR PROPOSAL (RFP) for Feasibility Study Borough of Kennett Square New Municipal Office and Police Station Joint Facility 1 Borough of Kennett Square Request for Proposals (RFP) Feasibility Study

More information

AMENDED MEMORANDUM of UNDERSTANDING BETWEEN THE CITY OF WILLIAMSBURG AND THE WILLIAMSBURG ECONOMIC DEVELOPMENT AUTHORITY

AMENDED MEMORANDUM of UNDERSTANDING BETWEEN THE CITY OF WILLIAMSBURG AND THE WILLIAMSBURG ECONOMIC DEVELOPMENT AUTHORITY AMENDED MEMORANDUM of UNDERSTANDING BETWEEN THE CITY OF WILLIAMSBURG AND THE WILLIAMSBURG ECONOMIC DEVELOPMENT AUTHORITY SUBJECT: City of Williamsburg Funding for EDA Demolition Program and Small Business

More information

ANNUAL REQUEST FOR QUALIFICATIONS Design Related Consulting & Support Services

ANNUAL REQUEST FOR QUALIFICATIONS Design Related Consulting & Support Services 2015 ANNUAL REQUEST FOR QUALIFICATIONS Design Related Consulting & Support Services THE UNIVERSITY OF ARIZONA Planning, Design & Construction 220 West Sixth Street Tucson, Arizona 85701 www.pdc.arizona.edu

More information

MSBA Overview. Associated General Contractors. Massachusetts School Building Authority.

MSBA Overview. Associated General Contractors.  Massachusetts School Building Authority. Massachusetts School Building Authority Steven Grossman Chairman, State Treasurer Jack McCarthy Executive Director MSBA Overview Associated General Contractors March 28, 2014 www.massschoolbuildings.org

More information

Pennsylvania State System of Higher Education (PASSHE) a. The October 17, 2013, Board meeting minutes state the following:

Pennsylvania State System of Higher Education (PASSHE) a. The October 17, 2013, Board meeting minutes state the following: Pennsylvania Department of the Auditor General Bureau of Special Performance Audits 302 Finance Building Harrisburg, PA 17120 717-787-2150 Information Request-10 Page 1 of 3 Requested of: For: Pennsylvania

More information

REQUEST FOR QUALIFICATIONS (RFQ) FOR ARCHITECTURAL SERVICES FOR THE CONSTRUCTION OF A NEW PUBLIC SAFETY BUILDING/SUBSTATION

REQUEST FOR QUALIFICATIONS (RFQ) FOR ARCHITECTURAL SERVICES FOR THE CONSTRUCTION OF A NEW PUBLIC SAFETY BUILDING/SUBSTATION REQUEST FOR QUALIFICATIONS (RFQ) FOR ARCHITECTURAL SERVICES FOR THE CONSTRUCTION OF A NEW PUBLIC SAFETY BUILDING/SUBSTATION REQUEST FOR QUALIFICATIONS (RFQ) FOR ARCHITECTURAL SERVICES FOR A NEW PUBLIC

More information

FACADE IMPROVEMENTS INCENTIVE PROGRAM for EXISTING COMMERICAL BUILDINGS

FACADE IMPROVEMENTS INCENTIVE PROGRAM for EXISTING COMMERICAL BUILDINGS GAINESVILLE COMMUNITY REDEVELOPMENT AGENCY DOWNTOWN COMMUNITY REDEVELOPMENT AREA FACADE IMPROVEMENTS INCENTIVE PROGRAM for EXISTING COMMERICAL BUILDINGS 802 NW 5th Avenue Suite 200 Gainesville, FL 32601

More information

REQUEST FOR QUALIFICATIONS

REQUEST FOR QUALIFICATIONS FACILITIES MANAGEMENT 4202 EAST FOWLER AVENUE / OPM 100 TAMPA, FL 33620-7550 PHONE: (813) 974-2750 FAX: (813) 974-3542 REQUEST FOR QUALIFICATIONS FOR CONSTRUCTION MANAGEMENT (CM) SERVICES FOR USF HONORS

More information

REQUEST FOR PROPOSALS

REQUEST FOR PROPOSALS REQUEST FOR PROPOSALS ENGINEERING/ARCHITECTURAL DESIGN SERVICES FOR THE NORTHEAST STOCKTON LIBRARY AND RECREATION CENTER CITY PROJECT NO. PW1724 City of Stockton Public Works Department 22 E. Weber Avenue,

More information

Stoughton Public Library. Feasibility & Design Study Report by CBT January 28, 2011

Stoughton Public Library. Feasibility & Design Study Report by CBT January 28, 2011 Stoughton Public Library Feasibility & Design Study Report by CBT January 28, 2011 Current Library Built in 1969 Proposed Library for the Future Library Overview Stoughton Public Library opened in 1969

More information

CITY OF HONDO ENGINEERING REQUEST FOR QUALIFICATIONS

CITY OF HONDO ENGINEERING REQUEST FOR QUALIFICATIONS CITY OF HONDO ENGINEERING REQUEST FOR QUALIFICATIONS The City of Hondo requests the submission of qualifications statements, which will lead to the possible award of a contract to provide planning, design

More information

ELEVATE GRANTS DOWNTOWN FACADE GRANT PROGRAM

ELEVATE GRANTS DOWNTOWN FACADE GRANT PROGRAM ELEVATE GRANTS DOWNTOWN FACADE GRANT PROGRAM Elevate Goals: The mission of this façade restoration program is to provide grants and low interest loans to downtown property owners for revitalizing the exteriors

More information

OCTOBER 1, 2015 ADDENDUM NO. 1 FOR REQUEST FOR QUALIFICATIONS ( RFQ ) FOR DESIGN CONSULTING SERVICES (TARGET MARKET) SPECIFICATION NO.

OCTOBER 1, 2015 ADDENDUM NO. 1 FOR REQUEST FOR QUALIFICATIONS ( RFQ ) FOR DESIGN CONSULTING SERVICES (TARGET MARKET) SPECIFICATION NO. OCTOBER 1, 2015 ADDENDUM NO. 1 FOR REQUEST FOR QUALIFICATIONS ( RFQ ) FOR DESIGN CONSULTING SERVICES (TARGET MARKET) SPECIFICATION NO. 132366 For which proposals are scheduled to open in the Bid & Bond

More information

ARCHITECTURAL SERVICES COLLEGEWIDE

ARCHITECTURAL SERVICES COLLEGEWIDE DISTRICT BOARD OF TRUSTEES STATE COLLEGE OF FLORIDA, MANATEE - SARASOTA FACILITIES MANAGEMENT RFQ #FAC2017-39 ARCHITECTURAL SERVICES COLLEGEWIDE REQUEST FOR QUALIFICATIONS EVALUATION PROCEDURE EXPERIENCE

More information

TOWN OF GREENWICH Annual Department Operational Plan (FY )

TOWN OF GREENWICH Annual Department Operational Plan (FY ) TOWN OF GREENWICH Annual Department Operational Plan (FY 2012 2013) 1. Department: Inland Wetlands and Watercourses Agency 2. Divisions: N/A 3. Department Mission Statement: The Inland Wetlands and Watercourses

More information

PROGRAM OPPORTUNITY NOTICE EFFICIENCY MAINE TRUST CUSTOM INCENTIVE PROGRAM FOR ELECTRIC EFFICIENCY PROJECTS PON EM

PROGRAM OPPORTUNITY NOTICE EFFICIENCY MAINE TRUST CUSTOM INCENTIVE PROGRAM FOR ELECTRIC EFFICIENCY PROJECTS PON EM PROGRAM OPPORTUNITY NOTICE EFFICIENCY MAINE TRUST CUSTOM INCENTIVE PROGRAM FOR ELECTRIC EFFICIENCY PROJECTS PON Opening: July 1, 2017 Closing: June 30, 2018 Revised: February 6, 2018 {P1472575.1} CONTENTS

More information

Request for Qualifications Architectural Analysis Programming and Planning for the Clear Creek County Courts Wing Remodel Project Georgetown, Colorado

Request for Qualifications Architectural Analysis Programming and Planning for the Clear Creek County Courts Wing Remodel Project Georgetown, Colorado Request for Qualifications Architectural Analysis Programming and Planning for the Clear Creek County Courts Wing Remodel Project Georgetown, Colorado PURPOSE The Clear Creek Board of County Commissioners

More information

Program Community Development Block Grant (CDBG) Downtown Revitalization Program- Tier II

Program Community Development Block Grant (CDBG) Downtown Revitalization Program- Tier II Business/Building Owner 3/12/09 CDBG DT FY08 Program City of Celina / Poggemeyer Design Group Program Community Development Block Grant (CDBG) Downtown Revitalization Program- Tier II Federally funded

More information

REQUEST FOR QUALIFICATIONS: RFQ PROGRAM/PROJECT MANAGEMENT SERVICES TO SUPPORT MUNICIPAL FACILITIES & CAPITAL IMPROVEMENTS PROJECTS

REQUEST FOR QUALIFICATIONS: RFQ PROGRAM/PROJECT MANAGEMENT SERVICES TO SUPPORT MUNICIPAL FACILITIES & CAPITAL IMPROVEMENTS PROJECTS REQUEST FOR QUALIFICATIONS: RFQ 2018-100-1 PROGRAM/PROJECT MANAGEMENT SERVICES TO SUPPORT MUNICIPAL FACILITIES & CAPITAL IMPROVEMENTS PROJECTS The City of Cedar Hill, Texas is soliciting statements of

More information

CITY OF INGLEWOOD Residential Sound Insulation Program

CITY OF INGLEWOOD Residential Sound Insulation Program CITY OF INGLEWOOD Residential Sound Insulation Program REQUEST FOR QUALIFICATIONS/PROPOSALS FOR CONSTRUCTION MANAGEMENT SERVICES FOR THE CITY OF INGLEWOOD RESIDENTIAL SOUND INSULATION PROGRAM JANUARY 2008

More information

DATE IS ACTUALLY FRIDAY - MARCH 2); contact information included in RFP

DATE IS ACTUALLY FRIDAY - MARCH 2); contact information included in RFP Attendees: reference sign-in sheet. Tom Brown, Coordinator Design & Construction, opened meeting at 9:30 AM. Welcomed attendees Meeting recorded; mandatory meeting, sign-in required; leave business cards

More information

Request for Qualifications (RFQ) RFQ202: Code Consultant Services

Request for Qualifications (RFQ) RFQ202: Code Consultant Services Massachusetts Institute of Technology Office of Campus Planning Building NW23 100 77 Massachusetts Avenue Cambridge, Massachusetts 02139 4307 campusplanning.mit.edu Request for Qualifications (RFQ) RFQ202:

More information

Ricardo Flores Magón Academy New PK 8 School Architect/Engineer Services Request for Qualifications/Proposal

Ricardo Flores Magón Academy New PK 8 School Architect/Engineer Services Request for Qualifications/Proposal A. Invitation to Submit Qualifications/Proposal Ricardo Flores Magón Academy (RFMA) is inviting Architect/Engineer (A/E) firms to submit statements of qualifications and a proposal to provide architectural

More information

2018 Rural Hospital Capital Improvement Grant Program Request for Proposals

2018 Rural Hospital Capital Improvement Grant Program Request for Proposals Request for Proposals Minnesota Department of Health (MDH) Office of Rural Health and Primary Care Section 1 Background Information, Criteria for Funding and Submission Instruction Minnesota Statutes Section

More information

605 CMR: BOARD OF LIBRARY COMMISSIONERS 605 CMR 6.00: LIBRARY IMPROVEMENT PROGRAM - PUBLIC LIBRARY CONSTRUCTION

605 CMR: BOARD OF LIBRARY COMMISSIONERS 605 CMR 6.00: LIBRARY IMPROVEMENT PROGRAM - PUBLIC LIBRARY CONSTRUCTION 605 CMR 6.00: LIBRARY IMPROVEMENT PROGRAM - PUBLIC LIBRARY CONSTRUCTION Section 6.01: Scope and Purpose 6.02: Definitions 6.03: Administrative Procedures and Policies 6.04: Project Types 6.05: Conditions

More information

Associated with the District s Measure A Bond Program and Facilities Improvement Projects

Associated with the District s Measure A Bond Program and Facilities Improvement Projects Request for Qualifications / Proposal (RFQ/P) for Hazardous Material Assessment, Abatement Plan, Cost Estimating, and Monitoring Services Associated with the District s Measure A Bond Program and Facilities

More information

FLORIDA JOB GROWTH GRANT FUND PINELLAS COUNTY ECONOMIC DEVELOPMENT PROJECT: THE 501 BUILDING RENOVATION LIST OF ATTACHMENTS A. ATTACHMENT A RESPONSES THAT DID NOT FIT IN TEXT BOX B. ATTACHMENT B LETTERS

More information

PPEA Guidelines and Supporting Documents

PPEA Guidelines and Supporting Documents PPEA Guidelines and Supporting Documents APPENDIX 1: DEFINITIONS "Affected jurisdiction" means any county, city or town in which all or a portion of a qualifying project is located. "Appropriating body"

More information

Request for Proposal (RFP) For. Architectural Services. Lauderdale County, MS. Board of Supervisors

Request for Proposal (RFP) For. Architectural Services. Lauderdale County, MS. Board of Supervisors Request for Proposal (RFP) For Architectural Services Lauderdale County, MS Board of Supervisors 1 REQUEST FOR PROPOSAL (RFP) FOR ARCHITECTURAL SERVICES TABLE OF CONTENTS I. PURPOSE OF RFP... II. SITES

More information

Design/Builder Qualifications Supplement (DBQS) Instructions

Design/Builder Qualifications Supplement (DBQS) Instructions BUSINESS AFFAIRS www.facilities.ufl.edu PLANNING DESIGN AND CONSTRUCTION DIVISION Design/Builder Qualifications Supplement (DBQS) Instructions GENERAL INSTRUCTIONS UAA-35, Indoor Football Practice Facility

More information

Belmar Business Partnership, Inc. Business Development Committee

Belmar Business Partnership, Inc. Business Development Committee Belmar Business Partnership, Inc. Business Development Committee Façade Improvement and Renovation Grant Program 2017 To encourage existing businesses to improve the appearance of their place of business,

More information

Montgomery Housing Authority 525 South Lawrence Street Montgomery, Alabama 36104

Montgomery Housing Authority 525 South Lawrence Street Montgomery, Alabama 36104 Montgomery Housing Authority 525 South Lawrence Street Montgomery, Alabama 36104 Request For Qualification (RFQ) Number: RFQ 2017-01 Architect for the Plaza at Centennial Hill - Phase III DATE OF ISSUANCE:

More information

Request for Proposal No. RFP Consultant Services. for. Building Condition Assessment. Submittal Deadline: Date: March 1, Time: 10:00 a.m.

Request for Proposal No. RFP Consultant Services. for. Building Condition Assessment. Submittal Deadline: Date: March 1, Time: 10:00 a.m. Seattle Public Schools Contracting Services 2445 Third Avenue South Seattle, WA 98134 Telephone: (206) 252-0566 Fax: (206) 743-3018 contractingservices@seattleschools.org Request for Proposal No. RFP01838

More information

Hamilton Wenham Regional High School Auditorium Hamilton, Massachusetts APPENDIX. The following documents are included for reference purposes:

Hamilton Wenham Regional High School Auditorium Hamilton, Massachusetts APPENDIX. The following documents are included for reference purposes: Hamilton Wenham Regional High School Auditorium Hamilton, Massachusetts Feasibility Study APPENDIX The following documents are included for reference purposes: 1. Request for Designer Services 2. Feasibility

More information

Westside Community Schools Request for Qualifications Architectural Design and Engineering Services Prairie Lane Elementary School March 1, 2018

Westside Community Schools Request for Qualifications Architectural Design and Engineering Services Prairie Lane Elementary School March 1, 2018 Westside Community Schools Prairie Lane Elementary School March 1, 2018 NOTICE Westside Community Schools ( the District ) is accepting Statements of Qualifications (SOQ s) for Architectural Design and

More information

REQUEST FOR ARCHITECTURAL SERVICES ACTIVITY CENTER

REQUEST FOR ARCHITECTURAL SERVICES ACTIVITY CENTER REQUEST FOR ARCHITECTURAL SERVICES ACTIVITY CENTER Issued On: February 1, 2018 Date Due: February 23, 2018-2:00 pm CST At: 545 Academy Drive Northbrook, IL 60062 Northbrook Activity Center 180 Anets Drive

More information

Request for Qualifications No LEWIS AND CLARK HIGH SCHOOL Classroom Addition Project

Request for Qualifications No LEWIS AND CLARK HIGH SCHOOL Classroom Addition Project Request for Qualifications No. 7-1718 Architectural & Engineering Services for LEWIS AND CLARK HIGH SCHOOL Classroom Addition Project Submittal Deadline: November 10, 2017, 2:00 P.M. Spokane Public Schools

More information

CAYUGA COUNTY, NEW YORK REQUEST FOR QUALIFICATIONS STERLING NATURE CENTER CONCEPTUAL DESIGN & DESIGN SERVICES. Issue Date: March 27, 2018

CAYUGA COUNTY, NEW YORK REQUEST FOR QUALIFICATIONS STERLING NATURE CENTER CONCEPTUAL DESIGN & DESIGN SERVICES. Issue Date: March 27, 2018 CAYUGA COUNTY, NEW YORK REQUEST FOR QUALIFICATIONS STERLING NATURE CENTER CONCEPTUAL DESIGN & DESIGN SERVICES Issue Date: March 27, 2018 Qualifications Due: April 24, 2018, 3:00PM Respond to: Cayuga County

More information

CUYAHOGA COMMUNITY COLLEGE CAPITAL AND CONSTRUCTION DEPARTMENT

CUYAHOGA COMMUNITY COLLEGE CAPITAL AND CONSTRUCTION DEPARTMENT CUYAHOGA COMMUNITY COLLEGE CAPITAL AND CONSTRUCTION DEPARTMENT REQUEST FOR QUALIFICATIONS FOR PROJECT MANAGEMENT SERVICES COLLEGE-WIDE PROJECT NUMBER C20171130 BACKGROUND College Mission to provide high

More information

B. All of the documents in this RFP form the Basis-of-Design for this project.

B. All of the documents in this RFP form the Basis-of-Design for this project. SECTION 01 91 13 - PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 01 Specification Sections,

More information

REQUEST FOR PROPOSAL DESIGN BUILD PUBLIC WORKS BUILDING. March 2017

REQUEST FOR PROPOSAL DESIGN BUILD PUBLIC WORKS BUILDING. March 2017 REQUEST FOR PROPOSAL DESIGN BUILD PUBLIC WORKS BUILDING The City of Alabaster is currently accepting proposals for Design Build Services for the design and construction of a new public works facility to

More information

REQUEST FOR QUALIFICATIONS FOR DESIGN SERVICES ENGINEERING EDUCATION AND DESIGN CENTER. September 21, 2017

REQUEST FOR QUALIFICATIONS FOR DESIGN SERVICES ENGINEERING EDUCATION AND DESIGN CENTER. September 21, 2017 SECTION I: SUMMARY REQUEST FOR QUALIFICATIONS FOR DESIGN SERVICES ENGINEERING EDUCATION AND DESIGN CENTER September 21, 2017 The University of Maine (UMaine), located in Orono, Maine, desires to procure

More information

REQUEST FOR PROPOSAL. The City of Oneida, NY

REQUEST FOR PROPOSAL. The City of Oneida, NY REQUEST FOR PROPOSAL FOR A PERFORMANCE BASED ENERGY EFFICIENCY IMPROVEMENT PROJECT STREET LIGHTING TRANSFER TO OWNERSHIP AND LED CONVERSION For The City of Oneida, NY Letter of Public Notice The City of

More information

PENNSYLVANIA TURNPIKE COMMISSION

PENNSYLVANIA TURNPIKE COMMISSION PENNSYLVANIA TURNPIKE COMMISSION RETENTION OF AN ARCHITECTURAL FIRM RELOCATION OF PLYMOUTH MEETING MAINTENANCE FACILITIES Plymouth Township, Montgomery County, PA Reference No. 4-078 The Pennsylvania Turnpike

More information

Request for Qualifications (CM at Risk Contract) State of Ohio Standard Forms and Documents

Request for Qualifications (CM at Risk Contract) State of Ohio Standard Forms and Documents Project Name East Campus Quad Town Center Project Number C20182091 Project Location 4250 Richmond Road Project Manager Phillip Pallone City / County Highland Hills / Cuyahoga Owner Cuyahoga Community College

More information

Norcross Downtown Development Authority

Norcross Downtown Development Authority Norcross Downtown Development Authority Chairman Pat Eidt, Member Ed Flynn, Member Chuck Cimarick, Member Chris Collins Member Rob Girard, Member Al Karnitz, Member Tanya Moore October 8, 2013 DOWNTOWN

More information

ARCHITECTURAL/ENGINEERING SERVICES

ARCHITECTURAL/ENGINEERING SERVICES Sheriff Department Bruce Haney, Sheriff Department of Transportation Richard Tippett, Director County of Trinity REQUEST FOR STATEMENT OF QUALIFICATIONS TO PROVIDE ARCHITECTURAL/ENGINEERING SERVICES FOR

More information

Project Request and Approval Process

Project Request and Approval Process The University of the District of Columbia Information Technology Project Request and Approval Process Kia Xiong Information Technology Projects Manager 13 June 2017 Table of Contents Project Management

More information

REQUEST FOR PROPOSAL #B STRATEGIC PLANNING STUDY OF BERLIN ELEMENTARY SCHOOLS

REQUEST FOR PROPOSAL #B STRATEGIC PLANNING STUDY OF BERLIN ELEMENTARY SCHOOLS REQUEST FOR PROPOSAL #B2018-1 STRATEGIC PLANNING STUDY OF BERLIN ELEMENTARY SCHOOLS Town of Berlin Berlin Public Schools Ms. Eva Gallupe Director of Business Operations 238 Kensington Road Berlin, Connecticut

More information

PROGRAM OPPORTUNITY NOTICE EFFICIENCY MAINE TRUST CUSTOM INCENTIVE PROGRAM FOR DISTRIBUTED GENERATION PROJECTS PON EM

PROGRAM OPPORTUNITY NOTICE EFFICIENCY MAINE TRUST CUSTOM INCENTIVE PROGRAM FOR DISTRIBUTED GENERATION PROJECTS PON EM PROGRAM OPPORTUNITY NOTICE EFFICIENCY MAINE TRUST CUSTOM INCENTIVE PROGRAM FOR DISTRIBUTED GENERATION PROJECTS PON Opening: July 1, 2017 Closing: June 30, 2018 Updated: July 1, 2017 CONTENTS SECTION 1:

More information

A. Project Description

A. Project Description RFQ Letter of Interest Qualified firms who are interested in providing Architectural/Engineering/Planning (AEP) Services are invited to submit a letter of interest for an AEP On-Call service contract.

More information

The University of Tennessee REQUEST FOR QUALIFICATIONS (RFQ)

The University of Tennessee REQUEST FOR QUALIFICATIONS (RFQ) The University of Tennessee REQUEST FOR QUALIFICATIONS (RFQ) Programmer for Health Science Building Programming Project UT Chattanooga SBC No. 540/005-08-2017 November 28, 2017 The University of Tennessee

More information

City of Batavia Downtown Improvement Grant

City of Batavia Downtown Improvement Grant City of Batavia Downtown Improvement Grant INTRODUCTION The Downtown Improvement Grant Program is designed to enhance the overall economic viability and appearance of downtown Batavia by assisting in the

More information