1 IRVINE UNIFIED SCHOOL DISTRICT RESPONSE TO COMMENTS FOR THE PLANNING AREA 6 NORTH ELEMENTARY SCHOOL Prepared for: IRVINE UNIFIED SCHOOL DISTRICT Facilities Planning & Construction Services Departments 2015 Roosevelt Ave Irvine, CA Prepared by: CHAMBERS GROUP, INC. 5 Hutton Centre Drive, Suite 750 Santa Ana, California (949) January 2017 ii
2 RESPONSE TO COMMENTS 1.1 CEQA REQUIREMENTS REGARDING COMMENTS AND RESPONSES CEQA Guidelines Section (b) outlines parameters for submitting comments and reminds persons and public agencies that the focus of review and comment of negative declarations should be, on the proposed finding that the project will not have a significant effect on the environment. If persons and public agencies believe that the project may have a significant effect, they should: (1) Identify the specific effect; (2) Explain why they believe the effect would occur, and; (3) Explain why they believe the effect would be significant. CEQA Guidelines Section (c) further advises, Reviewers should explain the basis for their comments, and should submit data or references offering facts, reasonable assumptions based on facts, or expert opinion supported by facts in support of the comments. Pursuant to Section 15064, an effect shall not be considered significant in the absence of substantial evidence. Section (d) also states, Each responsible agency and trustee agency shall focus its comments on environmental information germane to that agency s statutory responsibility. Section (e) states, This section shall not be used to restrict the ability of reviewers to comment on the general adequacy of a document or of the lead agency to reject comments not focused as recommended by this section. In accordance with Public Resources Code (b) of the CEQA Guidelines, the lead agency shall notify any public agency which comments on a negative declaration of the public hearing or hearings, if any, on the project for which the negative declaration was prepared. If notice to the commenting public agency is provided pursuant to Section 21092, the notice shall satisfy the requirement of this subdivision. 1.2 COMMENTS AND RESPONSE TO COMMENTS RECEIVED ON THE DRAFT MND This section provides responses to written comments received during the 30 day public review period. Table 2: Commenting Agencies provides a list of agencies that submitted comments on the Draft MND during the public review period. Table 1: Commenting Agencies Comment Letter No. Commenting Agency Date of Comment 1 Department of Fish and Wildlife January 6, City of Irvine Community Development January 9, 2017
3 COMMENT LETTER #1 Department of Fish and Wildlife Comment 1-1
4 Comment 1-1 cont. Comment 1-2 Comment 1-3 Comment 1-4
5 Comment 1-4 cont. Comment 1-5
6 Response to Comment Letter #1 1: Because the project site has undergone active grading operations as part of the Northern Sphere Project, measures to reduce offsite impacts are already included in the planned development of the PA 6 North project. Temporary hay bale sound walls to protect nesting birds from construction noise have been set up onsite and will remain during construction of PA 6 North. Further, these will protect the sensitive area against the spread of invasive species. For additional responses regarding spread of invasive species, please see the Response to Comment Letter #1 4. Response to Comment Letter #1 2: Comment noted. As the project moves through advanced design, the District and their architect will investigate incorporating these guidelines, consistent with District design requirements. Response to Comment Letter #1 3: The project will not include a significant amount of ground disturbance. The project is located on a site that has been previously graded as part of development of the Northern Sphere Project and as such is considered a previously disturbed site. That said, as the project moves through advanced design, the District will investigate incorporating these features, consistent with District design requirements. Response to Comment Letter #1 4: During construction, heavy equipment will be inspected before delivery to the project site. The District will ensure that all the equipment being delivered is weed free, including: earth moving equipment and project associated vehicles that could present a risk for spreading weeds (vegetation clearing has been previously completed so no further vegetation clearing and associated vehicles is not expected to be required). Response to Comment Letter #1 5: Comment noted. As the project moves through advanced design, the District and their architect will investigate including native plants to the maximum extent possible, consistent with District design requirements.
7 COMMENT LETTER #2 City of Irvine Community Development
8 Comment 2-1 Comment 2-2 Comment 2-3 Comment 2-4 Comment 2-5 Comment 2-6 Comment 2-7 Comment 2-8 Comment 2-9
9 Comment 2-10 Comment 2-11 Comment 2-12 Comment 2-13 Comment 2-14 Comment 2-15 Comment 2-16 Comment 2-17 Comment 2-18 Comment 2-19
10 Comment 2-20 Comment 2-21 Comment 2-22 Comment 2-23 Comment 2-24 Comment 2-25
11 Irvine Unified School District Response to Comments for Planning Area 6 North Elementary School
12 Irvine Unified School District Response to Comments for Planning Area 6 North Elementary School
13 Response to Comment Letter #2 1: To the best of the District s knowledge, Tomato Springs Road and Pear Blossom ( L Street ) will be built prior to the school opening. Response to Comment Letter #2 2: Comment noted. As the project moves through advanced design, a detailed site plan will be developed and provided to the City. District will meet with the City for review and input. Access from the sidewalks along Tomato Springs to the entrance of the school will be provided. Response to Comment Letter #2 3: Comment noted. As the project moves through advanced design, a detailed site plan compliant with Title V requirements will be developed and provided to the City. District will meet with the City for review and input. Response to Comment Letter #2 4: Comment noted. As the project moves through advanced design, a detailed site plan will be developed and provided to the City. District will meet with the City for review and input. Response to Comment Letter #2 5: Comment noted. As the project moves through advanced design, the District will collaborate with the developer on a site plan which will be provided to the City. District will meet with the City for review and input. Response to Comment Letter #2 6: Access points to the school are shown in Figure 7 of the IS/MND. As the project moves through advanced design, a detailed site plan will be developed and provided to the City. District will meet with the City for review and input. General Response to Comment Letter #2 7 through #2 25: District has reviewed the City s comments provided for the Traffic Study (study). In review of these comments, it was determined that the District, as the lead agency under CEQA, did not require implementation of the suggested edits in order to comply with the requirements of the statute and guidelines. Addressing the suggested edits will not identify a new effect nor alter the conclusions in the study. However, District will prepare updates to the study, as requested by the City, for their review and input. Further detail is provided in the below responses to comments describing how revisions to the study will be prepared. Response to Comment Letter #2 7: Access points to the school are shown in Figure 7 of the IS/MND. As the project moves through advanced design, a detailed site plan will be developed and provided to the City. District will
14 meet with the City for review and input. The updated study will include as much information as is known at this time to identify the school s access points. Response to Comment Letter #2 8: A forecast for traffic on Tomato Springs was not currently available at the time the IS/MND was circulated. The road and surrounding residences have not yet been built and there was no volume forecast in the Northern Sphere EIR. The updated study will analyze the Pearblossom ( L Street)/Tomato Springs intersection. The volumes for this intersection will be comprised of the cumulative traffic volumes only as the intersection does not currently exist. Response to Comment Letter #2 9: As requested by the City, the Pearblossom ( L Street)/Portola Parkway intersection will be analyzed as a traffic signal in the Existing With Project, Opening Year (2019), and Opening Year (2019) with Project scenarios. It should be noted that based on the analysis, the signal is not needed to accommodate school traffic. Further, development of this intersection is being performed by The Irvine Company as part of the Northern Sphere Project and is not within the scope of the Planning Area 6 North ES Project. Response to Comment Letter #2 10: A discussion on the trail network system and pedestrian and bicycle volumes will be added to the report. Response to Comment Letter #2 11: A figure illustrating future geometrics for the 2019 year will be added to the study. It is not expected that the project will be specifically adding, changing, or mitigating any roadway or intersection geometry. Therefore, theses geometrics will also be assumed for the Baseline scenarios. Response to Comment Letter #2 12: A 15 percent growth rate will be added per the City s traffic model. The volumes at the Portola Springs/Portola Parkway intersection may appear lower than other studies in the area because of the lack of development in the area. The volumes and graphics will be updated accordingly. Response to Comment Letter #2 13: The City of Irvine s Transportation Design Procedures were consulted for the school driveways and will be discussed in the updated study. Response to Comment Letter #2 14: A Build Out scenario would not be necessary as this project is already consistent with the City s General Plan and would have been evaluated in the General Plan EIR. Response to Comment Letter #2 15:
15 Childcare will be provided on site consistent with other K 6 schools in the District. IUSD has a Joint Powers Agreement with Irvine Childcare Project to provide on site childcare before and after school. Additionally, a childcare facility is planned east of the elementary school. The discussion of the existing setting will be revised to note that a child care facility is proposed east of Pearblossom ( L Street). Response to Comment Letter #2 16: The Pearblossom ( L Street)/Tomato Springs intersection will be included in the updated study. The volumes for this intersection will be comprised of the approved/pending projects in the area. Response to Comment #2 17: Table 3 in the study will be updated to reflect this comment as the study is revised. Response to Comment #2 18: The only school in the vicinity of the project is the existing Portola Springs Elementary School. To account for the existing school traffic, the traffic volumes generated by the Portola Springs Elementary School will be added to the existing traffic counts and included in the updated study. Response to Comment #2 19: As noted in Comment 2 12, a 15 percent growth rate will be used in the updated study. Response to Comment #2 20: The approved/pending (cumulative) projects within the study area were derived from a list provided by City of Irvine Staff in July In addition, a map of Planning Area 6 (PA6) prepared by Stantec in October 2015 was also used to derive traffic volumes from cumulative projects. This map contained dwelling unit counts and other information needed to estimate trips. If additional projects or an updated map are available, please provide them so that they can be included in the updated study. Response to Comment #2 21: Figure 7 has been updated to better illustrate the trip distribution through the study area. Response to Comment #2 22: The SR 241 Ramps were included in this study as some school employees are expected to use these ramps to commute to the site. The Pearblossom ( L Street)/Portola Parkway intersection will be analyzed as a traffic signal for the existing with project, opening year and opening year with project scenarios. Response to Comment #2 23: The number of left turns will be confirmed in the updated study. There are a total of 1,000 elementary school students (although, for the purposes of this analysis, a total of 1,200 students were assumed to provide a conservative estimate). This does not mean that all 1,000 students
16 will be driven to school individually. Based on the trip generation estimates, 540 AM peak hour trips are expected with 297 inbound trips. Some of this traffic is expected to come from the residential developments south of Portola Parkway and use Portola Springs to access the elementary school. Not all traffic for the school is expected to use Pearblossom ( L Street). Response to Comment #2 24: The westbound right turns at the Pearblossom ( L Street)/Portola Parkway intersection will be confirmed in the updated study. The westbound right turns are expected to come from the residential developments to the east of Pearblossom ( L Street). This traffic is expected to use a street east of Pearblossom ( L Street). Response to Comment #2 25: All tables in the study will be updated to show the Pearblossom ( L Street)/Portola Parkway intersection as a signalized intersection.
Nob Hill Pipeline Improvements Project
Nob Hill Pipeline Improvements Project Final Environmental Impact Report Volume I of III State Clearinghouse No. 2013041037 June 2014 San Diego County Water Authority 4677 Overland Avenue San Diego, California
More informationENVIRONMENTAL IMPACT REPORT
City of Redlands General Plan Update and Climate Action Plan ENVIRONMENTAL IMPACT REPORT Final July 21, 2017 SCH: #2016081041 City of Redlands General Plan Update and Climate Action Plan ENVIRONMENTAL
More information1 Introduction. 1.1 Specific Plan Background
Introduction 1 Introduction This document is an Environmental Impact Report (EIR) that evaluates the potential environmental effects associated with implementation of the Bay Fair Transit Oriented Development
More informationUNIVERSITY OF CALIFORNIA, SANTA CRUZ
UNIVERSITY OF CALIFORNIA, SANTA CRUZ BERKELEY DAVIS IRVINE LOS ANGELES MERCED RIVERSIDE SAN DIEGO SAN FRANCISCO SANTA BARBARA SANTA CRUZ PHYSICAL PLANNING, DEVELOPMENT & OPERATIONS UC SANTA CRUZ, CALIFORNIA
More informationREQUEST FOR CITY COUNCIL ACTION
REQUEST FOR CITY COUNCIL ACTION MEETING DATE: MARCH 14, 2017 TITLE: SCOPING SESSION FOR A GENERAL PLAN AMENDMENT REQUEST REPRESENTING AN EXCHANGE OF NON RESIDENTIAL BUILDING SQUARE FOOTAGE FOR NEW RESIDENTIAL
More information2.0 COMMENTS AND RESPONSES TO COMMENTS
2.0 COMMENTS AND RESPONSES TO COMMENTS A list of those agencies, organizations, and interested parties, which have commented on the Draft EIR, is provided below. A copy of each comment letter or a summary
More informationCITY OF ORANGE LOCAL CEQA GUIDELINES
CITY OF ORANGE LOCAL CEQA GUIDELINES Prepared by: City of Orange Community Development Department, Advance Planning Division 300 East Chapman Avenue, Orange, CA 92866 April 11, 2006 Page 2 TABLE OF CONTENTS
More informationSubject: Request for Proposal Route 99 Interchanges at Hammett Road and Kiernan Avenue
DEPARTMENT OF PUBLIC WORKS Matt Machado Director 1010 10 th Street, Suite 3500, Modesto, CA 95354-0847 Phone: 209.525.6550 Date «FirstName» «LastName» «Company» «Address1» «City», «State» «PostalCode»
More informationPresented by: James Moose Remy, Thomas, Moose and Manley, LLP. With: Stephen L. Jenkins, AICP Michael Brandman Associates
CEQA FUNDAMENTALS for LAFCo s Presented by: James Moose With: Stephen L. Jenkins, AICP Michael Brandman Associates 455 Capitol Mall, Suite 210 Sacramento, California 95814 (916) 443-2745 Fax: (916) 443-9017
More informationTraffic Impact Analysis (TIA) POLICY
Ascension Parish Planning Commission Traffic Impact Analysis (TIA) POLICY This policy establishes requirements for studies that provide information on traffic projected to be generated by all proposed
More informationRiverside County Transportation Department. Traffic Impact Analysis Preparation Guide
Riverside County Transportation Department Traffic Impact Analysis April 2008 Juan C. Perez Director of Transportation Date 1.0 INTRODUCTION The Riverside County Transportation Department ( Transportation
More informationGuidelines for the Implementation of the California Environmental Quality Act of 1970 As Amended
Guidelines for the Implementation of the California Environmental Quality Act of 1970 As Amended Adopted by the Santa Barbara County Board of Supervisors September 12, 1988 Revised November 12, 1991 Revised
More informationKaiser Riverside-Cirby Medical Office Building Project
Final Environmental Impact Report for the Kaiser Riverside-Cirby Medical Office Building Project SCH 2016062020 P R E PA R E D B Y: 1102 R Street Sacramento, California 95811 Date Completed: May 2017 P
More informationMETHODOLOGY - Scope of Work
The scope of work for the Truckee West River Site Redevelopment Feasibility Study will be undertaken through a series of sequential steps or tasks and will comprise four major tasks as follows. TASK 1:
More informationCOASTAL CONSERVANCY. Staff Recommendation June 16, 2005 MALIBU ACCESS: DAN BLOCKER BEACH. File No Project Manager: Marc Beyeler
COASTAL CONSERVANCY Staff Recommendation June 16, 2005 MALIBU ACCESS: DAN BLOCKER BEACH File No. 03-163 Project Manager: Marc Beyeler RECOMMENDED ACTION: Authorization to augment the Conservancy s January
More informationFiscal Year 2014 TRANSPORTATION ALTERNATIVES PROGRAM (TAP) INSTRUCTIONS AND GUIDELINES
Fiscal Year 2014 TRANSPORTATION ALTERNATIVES PROGRAM (TAP) INSTRUCTIONS AND GUIDELINES TABLE OF CONTENTS Pages 1. Instructions for Submitting a Transportation Alternatives Program Application. 1 2. Transportation
More informationWESTERN SLOPE CIP AND TIM FEE UPDATE
WESTERN SLOPE CIP AND TIM FEE UPDATE 12/6/16 BOARD OF SUPERVISORS STUDY SESSION B O A R D S T U D Y S E S S I O N # 8 2015 14-0245 Revised 22M 1 of 53 AGENDA 1. Background 2. Programmatic EIR 3. General
More informationCAIS Trustee Head Conference 2014 Developing a Successful Project Entitlements Team & Strategy
Todays Topics: Overview of Entitlement Components and Team Case Study: The Urban School Academic and Athletic Building Lessons Learned Questions and Answer Session What are project entitlements and why
More informationADMINISTRATIVE CODE BOARD OF COUNTY COMMISSIONERS
ADMINISTRATIVE CODE BOARD OF COUNTY COMMISSIONERS CATEGORY: DEVELOPMENT/PLANNING/ZONING TITLE: TRANSPORTATION PROPORTIONATE SHARE CALCULATIONS FOR NEW DEVELOPMENT PROJECTS CODE NUMBER: AC-13-16 ADOPTED:
More informationThe next steps outlined at the end of this section are the key requirements as we can best envision them at this stage.
5 Implementation 5.1 Anticipated Caltrans Review Process... 2 5.1.1 Project Initiation Document and Project Report... 2 5.1.2 Environmental Review Process... 4 5.1.3 Right of Way Acquisition Process...
More informationSOUTHWEST LRT (METRO GREEN LINE EXTENSION)
10 Joint Development This chapter describes potential long-term direct and indirect and short-term (construction) direct and indirect effects that would result from the Southwest Light Rail Transit (LRT)
More informationCity of Lynwood MODIFIED REQUEST FOR PROPOSALS FOR
City of Lynwood MODIFIED REQUEST FOR PROPOSALS FOR AN URBAN PLANNING FIRM TO PREPARE A SPECIFIC PLAN AMENDMENT TO THE LYNWOOD TRANSIT AREA SPECIFIC PLAN AND REQUIRED CEQA SUPPORTING DOCUMENTS (SUPPLEMENTAL
More informationExisting Site Issues & Site Certification. Presented By: Jim Bush President, School Site Solutions, Inc. (916)
Existing Site Issues & Site Certification Presented By: Jim Bush President, School Site Solutions, Inc. (916) 257-2530 Outline CDE Site Approval for Existing Sites CDE Site Certification CEQA / DTSC Facility
More informationCITY OF DANA POINT AGENDA REPORT KYLE BUTTERWICK, DIRECTOR OF COMMUNITY DEVELOPMENT BRAD FOWLER, DIRECTOR OF PUBLIC WORKS DEPARTMENT
01/17/12 Page 1 Item #14 CITY OF DANA POINT AGENDA REPORT Reviewed By: DH _X CM _X CA X DATE: JANUARY 17, 2012 TO: FROM: THE HONORABLE CITY COUNCIL KYLE BUTTERWICK, DIRECTOR OF COMMUNITY DEVELOPMENT BRAD
More informationComprehensive Plan 2009
Comprehensive Plan 2009 2.14 PUBLIC SCHOOLS FACILITIES Goal: Coordinate and maintain a high quality education system. Collaborate and coordinate with the Okaloosa County School Board (School Board) to
More informationCOUNTY OF VENTURA ADMINISTRATIVE SUPPLEMENT TO THE STATE CEQA GUIDELINES
COUNTY OF VENTURA ADMINISTRATIVE SUPPLEMENT TO THE STATE CEQA GUIDELINES Amended by the Board of Supervisors on July 13, 2010 This page intentionally left blank. Table of Contents 1. Introduction... 1
More informationREPORT. To the Honorable Mayor and City Council From the City Manager. May 9, 2016
REPORT To the Honorable Mayor and City Council From the City Manager May 9, 2016 SUBJECT Study Session for Consideration of the Draft Inner Harbor Specific Plan, Draft Inner Harbor Specific Plan Environmental
More informationNOTICE OF PREPARATION OF AN ENVIRONMENTAL IMPACT REPORT AND SCOPING MEETING FOR THE DOWNTOWN SPECIFIC PLAN COMMENT PERIOD
DATE: February 15, 2017 TO: FROM: RE: Interested Persons Tom Buford, Senior Planner Community Development Department NOTICE OF PREPARATION OF AN ENVIRONMENTAL IMPACT REPORT AND SCOPING MEETING FOR THE
More informationAPPENDIX 1 BROWARD COUNTY PLANNING COUNCIL PLAN AMENDMENT REQUIREMENTS AND PROCEDURES
APPENDIX 1 BROWARD COUNTY PLANNING COUNCIL PLAN AMENDMENT REQUIREMENTS AND PROCEDURES Broward County Land Use Plan Amendment Requirements Amendments which are not within the rules of flexibility or more
More informationPRESENTATION ITEMS. 1. Furniture, Fixtures and Equipment (FF&E) Program
PRESENTATION ITEMS 1. Furniture, Fixtures and Equipment (FF&E) Program 2. California Environmental Quality Act (CEQA) for Vacaville Biotechnology Building 3. Science Project, Fairfield Campus Furniture,
More informationPublic Scoping Meeting for the Environmental Impact Report
Public Scoping Meeting for the Environmental Impact Report Solana Highlands Revitalization Project November 20, 2014 @ 5:30pm 1 Scoping Meeting Agenda Welcome and Introductions Purpose of the Notice of
More informationENVIRONMENTAL PRACTICE FORUM:
ENVIRONMENTAL PRACTICE FORUM: TIERING VS WITHIN THE SCOPE P RESENTED BY : C ORI RESHA N OVEMBER 22, 2016 CEQA STREAMLINING PROVISIONS u Public Resources Section (PRC) Section 21093 EIRs shall be tiered
More informationCITY OF SACRAMENTO COMMUNITY DEVELOPMENT CALIFORNIA 300 Richards Blvd. DEPARTMENT
CITY OF SACRAMENTO COMMUNITY DEVELOPMENT CALIFORNIA 300 Richards Blvd. DEPARTMENT 3 rd Floor Sacramento, CA 95811 DATE: April 12, 2013 TO: FROM: RE: Interested Persons Tom Buford, Senior Planner Community
More informationSTAFF REPORT. MEETING DATE: August 21, 2008 AGENDA ITEM: 9
STAFF REPORT SUBJECT: Draft Regional Transportation Plan MEETING DATE: August 21, 2008 AGENDA ITEM: 9 STAFF CONTACT: Aubrey Spilde, Michael Powers RECOMMENDATION: Hold public hearing to receive public
More informationOrder of Business. D. Approval of the Statement of Proceedings/Minutes for the meeting of August 2, 2017.
COUNTY OF SAN DIEGO BOARD OF SUPERVISORS REGULAR MEETING MEETING AGENDA WEDNESDAY, SEPTEMBER 13, 2017, 9:00 AM BOARD OF SUPERVISORS NORTH CHAMBER 1600 PACIFIC HIGHWAY, SAN DIEGO, CALIFORNIA Order of Business
More informationATTACHMENT A. Nova Homes Residential Project. Initial Study/Mitigated Negative Declaration City Council Resolution
ATTACHMENT A Nova Homes Residential Project Initial Study/Mitigated Negative Declaration City Council Resolution RESOLUTION NO. 2017- A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF WILDOMAR, CALIFORNIA,
More informationAddendum. Final Environmental Impact Report for North Campus Project. California State University Los Angeles SCH# March 2018.
Addendum Final Environmental Impact Report for North Campus Project to SCH#2016111038 California State University Los Angeles March 2018 Lead Agency The Board of Trustees of the California State University
More informationNOW THEREFORE, the parties enter into the following Agreement:
Interlocal Agreement Between the Board of County Commissioners of St. Johns County, Florida, City of St. Augustine, City of St. Augustine Beach, Town of Hastings and the School Board of St. Johns County,
More information4.b. 6/22/2017. Local Agency Formation Commission. George J. Spiliotis, Executive Officer
4.b. 6/22/2017 TO: FROM: SUBJECT: Local Agency Formation Commission George J. Spiliotis, Executive Officer LAFCO 2014-09-5 SPHERE OF INFLUENCE AMENDMENT TO THE CITY OF BEAUMONT (ADDITION) AND AMENDMENT
More information2. Transportation Alternatives Program Activities Regulations and Guidelines... 4, 5 & Eligible and Ineligible Items...
FY 2018 TRANSPORTATION ALTERNATIVES PROGRAM INSTRUCTIONS, GUIDELINES AND APPLICATION TABLE OF CONTENTS Page(s) 1. Instructions for Submitting a Transportation Alternatives Program Application.. 1 2. Transportation
More informationCEDARS-SINAI MEDICAL CENTER WEST TOWER PROJECT
A. PROPOSED PROJECT A. PROPOSED PROJECT The Cedars-Sinai Medical Center (CSMC or the Applicant ) proposes to develop a new inpatient/medical support facility on the approximately 24.1-acre CSMC Campus
More informationNassau County 2030 Comprehensive Plan. Public School Facilities Element (PSF) Goals, Objectives and Policies. Goal
(PSF) Goal Work closely with the School District of Nassau County to ensure a high quality, fiscally sound public school system which meet the needs of Nassau County s population by providing and maintaining
More informationTransportation Alternatives Program Application For projects in the Tulsa Urbanized Area
FFY 2015-2016 Transportation Alternatives Program Application For projects in the Tulsa Urbanized Area A Grant Program of Moving Ahead for Progress in the 21st Century (MAP-21) U.S. Department of Transportation
More informationREQUEST FOR PROPOSALS
REQUEST FOR PROPOSALS ENGINEERING/ARCHITECTURAL DESIGN SERVICES FOR THE NORTHEAST STOCKTON LIBRARY AND RECREATION CENTER CITY PROJECT NO. PW1724 City of Stockton Public Works Department 22 E. Weber Avenue,
More informationFlorida Communities Trust Grant Award Project Annual Stewardship Report
Florida Communities Trust Grant Award Project Annual Stewardship Report Name of Project: FCT Project Number: 92-018-P2A Local Government: Indian River County For Period: November 2015 November 2016 Date
More informationREQUEST FOR PROPOSALS
Community Development Department Planning & Zoning Division REQUEST FOR PROPOSALS COMBINED ACTIVE TRANSPORTATION/ SAFE ROUTES TO SCHOOL PLAN State Project No. ATPL-5169 (048) RELEASE DATE: SEPTEMBER 23,
More informationComprehensive Planning Grant. Comprehensive Plan Checklist
Comprehensive Planning Grant Comprehensive Plan Checklist This form was updated April 2010 Comprehensive Planning Grant Program Department of Administration Division of Intergovernmental Relations 101
More informationExhibit B. Plumas County Non-Motorized Transportation Plan SCOPE OF WORK
Exhibit B Plumas County Non-Motorized Transportation Plan SCOPE OF WORK PROJECT INTRODUCTION: The proposed project is the development of a legally compliant Plumas County Non- Motorized Transportation
More informationTransport NI York Street Interchange APPENDIX A PROJECT BRIEF
Transport NI York Street Interchange APPENDIX A PROJECT BRIEF PROPOSED SCHEME REPORT: PART 2 VOLUME 2 January 2015 Roads Service Consultancy Framework Contract BRIEF FOR MAJOR WORKS SCHEMES, EASTERN DIVISION
More informationNevada Department of Transportation Traffic Operations Policy Memorandum Traffic Signal Warrant Approval Process
Nevada Department of Transportation Traffic Operations Policy Memorandum 2015-01 This document establishes procedures for the preparation of traffic signal warrant studies that meet NDOT requirements,
More informationPublic and Agency Involvement. 8.1 Scoping Meetings and Noticing. Chapter 8
8.1 Scoping Meetings and Noticing Chapter 8 As described in Chapter 1, Section 1.7, Scope and Content of this Environmental Impact Report, the scoping process for this EIR was formally initiated on June
More informationCITY OF LA CENTER PUBLIC WORKS
CITY OF LA CENTER PUBLIC WORKS TRAFFIC CALMING PROGRAM APPROVED PER RESOLUTION 08-304 ON DECEMBER 10, 2008 TABLE OF CONTENTS PAGE Summary... 1 Procedures... 2 Project Eligibility... 2 Project Funding &
More informationNOTICE OF AVAILABILITY TIERED DRAFT ENVIRONMENTAL IMPACT REPORT FOR THE SAN FRANCISCO STATE UNIVERSITY CREATIVE ARTS & HOLLOWAY MIXED-USE PROJECT
PHYSICAL PLANNING & DEVELOPMENT 1600 Holloway Avenue, CY 201 San Francisco, CA 94132 Tel: 415/405-3836 Fax: 415/405-3846 NOTICE OF AVAILABILITY TIERED DRAFT ENVIRONMENTAL IMPACT REPORT FOR THE SAN FRANCISCO
More informationCrystal M. Craig, Local Government Analyst II LAFCO ANNEXATION 21 TO COUNTY SERVICE AREA 134. (SPECIFIC PLAN 327)
3.a. 2/26/2015 TO: FROM: SUBJECT: Local Agency Formation Commission Crystal M. Craig, Local Government Analyst II LAFCO 2014-12-1-ANNEXATION 21 TO COUNTY SERVICE AREA 134. (SPECIFIC PLAN 327) EXECUTIVE
More informationcoordination and collaboration between St. Mary s College and the Town of Moraga
Chapter Five Implementation The Campus Master Plan will be implemented in stages over the next 15 years (2015 2030). During this time coordination and collaboration between St. Mary s College and the Town
More informationState Project No. XXXXXX City Project No. c401807
June 29, 2017 Request for Qualifications Design and Environmental Services for the SLR Parkway Phase III Project also known as a portion of the MBSST (Rail Trail) Segment 8 (San Lorenzo River Railroad
More informationTRAFFIC IMPACT ANALYSIS IMPLEMENTATION. Richard L. Caywood, P.E. Robert W. Hofrichter
TRAFFIC IMPACT ANALYSIS IMPLEMENTATION Richard L. Caywood, P.E. Robert W. Hofrichter Chapter 527: What is it? Passed by General Assembly in 2006 adding Section 15.2-2222.1 to Code of Virginia Directs localities
More informationOrder of Business. D. Approval of the Statement of Proceedings/Minutes for the meeting of January 24, 2018.
COUNTY OF SAN DIEGO BOARD OF SUPERVISORS REGULAR MEETING MEETING AGENDA WEDNESDAY, FEBRUARY 14, 2018, 9:00 AM BOARD OF SUPERVISORS NORTH CHAMBER 1600 PACIFIC HIGHWAY, SAN DIEGO, CALIFORNIA Order of Business
More informationPENNSYLVANIA TURNPIKE COMMISSION. Reference No. E-056
PENNSYLVANIA TURNPIKE COMMISSION RETENTION OF AN ENGINEERING FIRM Southern Beltway Project U. S. Route 22 to Interstate 79 Section 55A2 West of S.R.4011 to S.R. 4012 Washington County, Pennsylvania Reference
More informationSouth Dakota Transportation Alternatives
South Dakota Transportation Alternatives Program Summary and Application Guide Updated March 2018 Connecting South Dakota and the Nation 1 Transportation Alternatives (TA) Summary 1. Overview Transportation
More informationPUBLIC SCHOOL FACILITIES ELEMENT
PUBLIC SCHOOL FACILITIES ELEMENT GOALS, OBJECTIVES, AND POLICIES GOAL 1 PUBLIC SCHOOL CONCURRENCY. The City of Plantation in coordination with Broward County Board of County Commissioners (Broward County)
More informationPurpose of Developer Fees. Developer Fees: An Overview of the Law and Recent Developments. Overview. September 19, Purpose of Developer Fees
Developer Fees: An Overview of the Law and Recent Developments September 19, 2017 Presented by: Harold M. Freiman Kelly M. Rem Overview Purpose of Developer Fees Types of Fees Accounting Requirements Replacement
More information4. IMPLEMENTATION. 4.1 Implementation Matrix
4. IMPLEMENTATION 4.1 Implementation Matrix IMPLEMENTATION MATRIX The Implementation Matrix includes the implementation items, proposed time line, potential participating parties and potential funding
More informationSouth Fulton Comprehensive Transportation Plan of Fulton County Transportation Coordinating Committee August 08, 2014
South Fulton Comprehensive Transportation Plan of Fulton County Transportation Coordinating Committee August 08, 2014 www.southfultonctp.org 1 What is a Comprehensive Transportation Plan (CTP)? Guiding
More informationMAP-21 and Its Effects on Transportation Enhancements
Date: July 13, 2012 Subject: MAP-21 and Its Effects on Transportation Enhancements The recently enacted Moving Ahead for Progress in the 21 st Century (MAP-21) includes a number of substantial changes
More informationSUBJECT: SEE BELOW DATE: May 26, 2016
COUNCIL AGENDA: 06-07-16 ITEM: A. CI CITY OF C: 3- SAN JOSE CAPITAL OF SILICON VALLEY TO: HONORABLE MAYOR AND CITY COUNCIL Memorandum FROM: Barry Ng SUBJECT: SEE BELOW DATE: Approved IL2_PS^ Date 5 ^ lip
More informationExecutive Summary EXECUTIVE SUMMARY
EXECUTIVE SUMMARY ES INTRODUCTION AND BACKGROUND On October 14, 2011, the Army published a Notice of Availability (NOA) of a Draft Programmatic Environmental Impact Statement (PEIS) for the Modernization
More informationTOWNSHIP OF UPPER ST. CLAIR TRAFFIC CALMING PROGRAM POLICY
TOWNSHIP OF UPPER ST. CLAIR TRAFFIC CALMING PROGRAM POLICY PURPOSE AND GOALS The purpose and goal of this Traffic Calming Program is to preserve and improve the safety of residents within neighborhoods
More informationOrdinances, Resolutions, Requests for Action XI. D. Meeting Date: June 24, To: Honorable Mayor and Councilmembers
Town of Moraga Ordinances, Resolutions, Requests for Action Agenda Item XI. D. 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 Meeting
More informationCITY GATE COMMERCE PARK DRI NOTICE OF PROPOSED CHANGE IN COLLIER COUNTY
CITY GATE COMMERCE PARK DRI NOTICE OF PROPOSED CHANGE IN COLLIER COUNTY BACKGROUND The City Gate Commerce Park Development of Regional Impact (DRI) is located on 291.55 acres at the northeast corner of
More informationCHAPTER 6 Construction Traffic Management Program. Overview
Chapter 6: Construction Traffic Management Program CHAPTER 6 Construction Traffic Management Program Overview This chapter sets forth the policy and procedures to be followed by staff for the construction
More informationCalifornia State University - Stanislaus Public Review Draft Physical Master Plan Update Program Environmental Impact Report
Chapter 2 California State University - Stanislaus Public Review Draft Project Description 2.1 Introduction Section 15124 of the California Environmental Quality Act (CEQA) Guidelines require that a project
More informationMegan P. Hall, P.E. Local Programs Engineer. Federal Highway Administration Washington Division. March 14, 2017
Megan P. Hall, P.E. Local Programs Engineer Federal Highway Administration Washington Division March 14, 2017 1 Transportation Alternatives (TA) Recreational Trails Program (RTP) www.fhwa.dot.gov/environment/transportation_alternatives/overview/presentation/
More informationATTACHMENT A: DRAFT PROPOSED SCOPE OF WORK
6 Harris Court Monterey, CA 93940 831 649-5225 Fax 831 373-5065 ATTACHMENT A: DRAFT PROPOSED SCOPE OF WORK FORA has prepared this proposed scope of work to be used as a guide for consultants as they submit
More informationREQUEST FOR PROPOSALS FOR. ENVIRONMENTAL ANALYSIS and ENTITLEMENTS REPORT FOR the SFUSD ArtsCenter Campus
REQUEST FOR PROPOSALS FOR ENVIRONMENTAL ANALYSIS and ENTITLEMENTS REPORT FOR the SFUSD ArtsCenter Campus RFP Issue Date: October 2, 2017 RFP Due Date: October 27, 2017 I. Introduction The San Francisco
More informationEastside Transit Corridor Phase 2 Draft EIS/EIR Public Hearings
Eastside Transit Corridor Phase 2 Draft EIS/EIR Public Hearings Agenda Registration/Open House (30 minutes) Draft EIS/EIR Presentation (30 minutes) Public Comment (90 minutes) 1 Purpose of Today s Meeting
More informationMaster Land Use Instructions B Abutting Owner=s Notification Los Angeles City Planning Department
Revised 11/06/2008 Master Land Use Instructions B Abutting Owner=s Notification Los Angeles City Planning Department Page 1 of 5 1. The MASTER LAND USE APPLICATION FORM CP-7771 must be filled out completely,
More informationNonmotorized Transportation Pilot Program Public Workshop December 29th, 2006
Public Workshop December 29th, 2006 NTPP funds can be spent on facilities to encourage walking. Below are examples of pedestrian facility improvements. Sidewalks Streetscaping Intersection Improvements
More informationREQUEST FOR PROPOSALS
REQUEST FOR PROPOSALS Town of Hope Mills Multi-Modal Congestion Management Plan September 19, 2016 Fayetteville Area Metropolitan Planning Organization Proposal Due Date: 3:00 PM Eastern Time, 28 th October,
More informationGuidance. Historical Studies Review Procedures
Guidance Historical Studies Review Procedures This guidance document provides instructional material regarding how to review and process project activities in accordance with TxDOT s Section 106 of the
More informationNAS North Island WELCOME. Open House Public Meeting
NAS North Island WELCOME Open House Public Meeting for the Transition from C-2A to CMV-22B Aircraft at Naval Air Station North Island, CA and Naval Station Norfolk, VA January 18, 2018 4:00 PM to 6:00
More informationBoard of Supervisors' Agenda Items
A. Roll Call COUNTY OF SAN DIEGO BOARD OF SUPERVISORS REGULAR MEETING MEETING AGENDA WEDNESDAY, APRIL 13, 2016, 9:00 A.M. BOARD OF SUPERVISORS NORTH CHAMBER 1600 PACIFIC HIGHWAY, ROOM 310, SAN DIEGO, CALIFORNIA
More informationDEPARTMENT OF THE ARMY U.S. ARMY CORPS OF ENGINEERS, SAVANNAH DISTRICT 1590 ADAMSON PARKWAY, SUITE 200 MORROW, GEORGIA FEB O
DEPARTMENT OF THE ARMY U.S. ARMY CORPS OF ENGINEERS, SAVANNAH DISTRICT 1590 ADAMSON PARKWAY, SUITE 200 MORROW, GEORGIA 30260-1777 FEB O 2 2018 Regulatory Branch SAS-2002-03090 JOINT PUBLIC NOTICE Savannah
More informationMaster Development Plan Written Report
Master Development Plan Written Report A master development plan must be accompanied by a written report, to be adopted as a part of the master development plan. The following information must be completed
More informationFrom: To: Cc: Subject: Date: Attachments: Dave Baker Wolff, Greg Coe, Tony Sidewalk Monday, March 2, 2015 5:21:13 PM Hungry Hunter sidewalk 10 feet from face of curb, 1.JPG Hungry Hunter sidewalk 10 feet
More informationLOCAL GOVERNMENT COMPREHENSIVE PLAN AMENDMENTS HENDRY COUNTY
LOCAL GOVERNMENT COMPREHENSIVE PLAN AMENDMENTS HENDRY COUNTY The Council staff has reviewed proposed changes to the Hendry County Growth Management Plan (DEO 13-1ESR). A synopsis of the requirements of
More informationFlorida Job Growth Grant Fund Public Infrastructure Grant Proposal
Florida Job Growth Grant Fund Public Infrastructure Grant Proposal Proposal Instructions: The Florida Job Growth Grant Fund Proposal (this document) must be completed by the governmental entity applying
More informationSTANDARD DRAWINGS INDEX
STANDARD DRAWINGS INDEX DESCRIPTION GENERAL DRAWING NO. Typical Layout for Improvement Plans... 1 City of Stockton Standard Border and Title Block for 8.5 x 11 Sheet.. 1A City of Stockton Standard Map
More informationBoard of Supervisors' Agenda Items
A. Roll Call COUNTY OF SAN DIEGO BOARD OF SUPERVISORS REGULAR MEETING MEETING AGENDA WEDNESDAY, MAY 13, 2015, 9:00 A.M. BOARD OF SUPERVISORS NORTH CHAMBER 1600 PACIFIC HIGHWAY, ROOM 310, SAN DIEGO, CALIFORNIA
More informationBeth Day Director, FTA Office of Project Planning RailVolution October 2011
Beth Day Director, FTA Office of Project Planning RailVolution October 2011 What is a New or Small Start? New fixed guideways and extensions to existing systems Includes light rail, heavy rail, commuter
More informationU.S. Route 202 Analysis. New Castle County Department of Land Use May 4, 2018
U.S. Route 202 Analysis New Castle County Department of Land Use May 4, 2018 Route 202 Study Area 202 Master Plan RFP 2018 Goal: Redevelop U.S. 202 as a high-quality and attractive multi-modal corridor
More informationAppendix B Meeting Presentation. PowerPoint Presentation Informational Boards
Appendix B Meeting Presentation PowerPoint Presentation Informational Boards PowerPoint Presentation VTA s BART Silicon Valley Program VTA s BART Silicon Valley Phase II Extension Project Environmental
More informationTransportation Alternatives Program (TAP) Recreational Trails Program (RTP)
Transportation Alternatives Program (TAP) Recreational Trails Program (RTP) www.fhwa.dot.gov/environment/transportation_alternatives/overview/presentation/ 1 Transportation Alternatives Program Authorized
More informationBoard of Supervisors' Agenda Items
A. Roll Call COUNTY OF SAN DIEGO BOARD OF SUPERVISORS REGULAR MEETING MEETING AGENDA WEDNESDAY, MARCH 16, 2016, 9:00 A.M. BOARD OF SUPERVISORS NORTH CHAMBER 1600 PACIFIC HIGHWAY, ROOM 310, SAN DIEGO, CALIFORNIA
More informationTO MEMBERS OF THE FINANCE AND CAPITAL STRATEGIES COMMITTEE: ACTION ITEM 1
F12(X) Office of the President TO MEMBERS OF THE FINANCE AND CAPITAL : For Meeting of ACTION ITEM 1 AUTHORITY TO ENTER INTO A GROUND LEASE AND LEASE DISPOSITION AND DEVELOPMENT AGREEMENT FOLLOWING ACTION
More informationENVIRONMENTAL ASSESSMENTS. Classification & Documentation
ENVIRONMENTAL ASSESSMENTS Classification & Documentation CLASSIFICATION What s an Environmental Assessment? Not a Categorical Exclusion (CE) Not an Environmental Impact Statement (EIS) 3 Classification
More informationCEQA Basic Training What is CEQA?
CEQA Basic Training What is CEQA? CEQA is the California Environmental Quality Act, Public Resource Code 21000 et seq. Regulations are in 14 CCR 15000 et seq. http://ceres.ca.gov/ceqa/index.html CEQA The
More informationTransportation Alternatives (TA) Northeast Minnesota Workshop
Transportation Alternatives (TA) Northeast Minnesota Workshop October 4 th, 2016 1 What are TA Projects? Federally funded community based projects o Expand travel choices o Integrate modes o Improve cultural,
More informationSR-86/AVENUE 50 NEW INTERCHANGE PROJECT
REQUEST FOR PROPOSALS FOR PROFESSIONAL ENGINEERING SERVICES CITY PROJECT NO. ST-81 (File No. 2015-04) FEDERAL AID PROJECT NO. HPLULN - 5294(011) FOR THE SR-86/AVENUE 50 NEW INTERCHANGE PROJECT Preparation
More informationLong Range Transportation Plan
Summary of Policy Governor in 2000. The baseline can The purpose of the Long Range also be considered as the scenario in Transportation Plan (LRTP) is to which no new transportation projects provide decision
More information