1 Appendix B Meeting Presentation PowerPoint Presentation Informational Boards
2
3 PowerPoint Presentation
4
5 VTA s BART Silicon Valley Program VTA s BART Silicon Valley Phase II Extension Project Environmental Scoping Meetings February 2015
6 Meeting Schedule Open house 5:30 p.m. to 6:30 p.m. Presentation and comment period 6:30 p.m. to 7:30 p.m. 2
7 Meeting Agenda Welcome/Meeting purpose Project overview Environmental process Public comments on scope of environmental document Next steps Adjournment 3
8 What is Scoping? The process of determining the focus and content (scope) of an environmental document through public outreach. Provides notice to the public and other agencies that a draft environmental document is being prepared, and initiates their involvement in the process. 4
9 Scoping ~ Environmental Kick-off Scoping period January 30, March 2, 2015 Scoping Meetings: February 12, 2015, 5:30 p.m. 7:30 p.m. City of Santa Clara Council Chambers February 17, 2015, 5:30 p.m. 7:30 p.m. VTA Customer Service Center, Downtown San Jose February 19, 2015, 5:30 p.m. 7:30 p.m. School of Arts and Culture at Mexican Heritage Plaza 5
10 Scoping ~ Environmental Kick-off Submittal of comments to VTA: In person: Verbal comments during formal comment period of Scoping Meeting or submittal of comment card Mail: Tom Fitzwater Environmental Programs and Resources Management, Bldg B-2 Valley Transportation Authority 3331 North First Street San Jose, CA BARTPhase2EIS-EIR@vta.org Comments must be received by 5:00 P.M. on March 2,
11 Public Comments at Scoping Meetings Verbal comments at the scoping meetings will be recorded by a court reporter Please submit a speaker card if you wish to speak Speakers will be called up in order Comments will be recorded 7
12 Project Overview 8
13 Approved California Environmental Quality Act (CEQA) Project Berryessa Extension Project 10-mile extension under construction Two stations: (Milpitas and Berryessa) Forecast opening: Fall 2017 Anticipated opening day ridership: 23,000 Phase II Extension 6-mile extension Four stations (Alum Rock, Downtown San Jose, Diridon, Santa Clara), and Newhall Yard maintenance facility Anticipated year 2035 ridership: 55,000 9
14 Project Purpose Improve public transit service Enhance regional connectivity Increase transit ridership Support transportation solutions that will maintain the economic vitality and continuing development of Silicon Valley Improve mobility options Enhance level and quality of transit service to areas of existing and planned affordable housing Improve regional air quality Support local and regional land use plans 10
15 Alternatives to be Evaluated No-Build Alternative (Berryessa Extension Project) Build Alternative (Six-mile, 4-Station extension with maintenance facility) 11
16 Build Alternative: Phase II Extension Project 12
17 Build Alternative: Phase II Extension Project 6-mile extension 4 Stations Alum Rock (underground) Downtown San Jose (underground) Diridon (underground) Santa Clara (at-grade) Maintenance Facility in San Jose/Santa Clara Anticipated ridership of 55,000 13
18 Build Alternative: Phase II Extension Project 14
19 Alum Rock Station 15
20 Downtown San Jose Station West Option 16
21 Downtown San Jose Station East Option 17
22 Diridon Station 18
23 Santa Clara Station 19
24 Phase II Project Delivery 20
25 Future Community Engagement Activities Ongoing community outreach and engagement during environmental process Focused Outreach Sessions Spring 2015, some topics may include: Economic and Community Benefits Funding Station Planning Transportation connectivity Station walking tours Construction Methods 21
26 Environmental Process 22
27 Project History Environmental Studies 2004 State clearance (CEQA) on Final Environmental Impact Report (EIR): 16-mile project 2007 CEQA clearance on Final Supplemental EIR (SEIR): 16-mile project 2010 Federal clearance National Environmental Policy Act (NEPA) on Final Environmental Impact Statement (EIS): 10-mile project 2011 CEQA clearance on 2 nd SEIR: 10-mile project 2015 Joint CEQA and NEPA document (SEIS/SEIR3): 6-mile project 23
28 Supplemental EIS/3 rd Supplemental EIR Minor changes to project Integration with updated land-use and development plans Changed laws and regulations FTA real estate process 24
29 Purpose of Scoping Meeting Describe proposed project and environmental review process Early consultation process to solicit input on document scope to address potential major environmental issues Scoping does not result in the ultimate decision or selection of an alternative 25
30 Objectives of the Environmental Document Document environmental impacts from project features Gather public input Coordinate with federal, state, and other agencies Provide decision makers with environmental information 26
31 Environmental Review Steps Initiate Environmental Process Early Consultation/Scoping Prepare Draft Environmental Document Comment Period & Public Hearings VTA Board Defines Project Prepare Final Environmental Document/Respond to Comments VTA Board of Directors Approves the Project Federal Record of Decision for the Project 27
32 Environmental Topics Air Quality Biological Resources and Wetlands Community Services Construction Cultural Resources Electromagnetic Fields Energy Geology, Soils, & Seismicity Greenhouse Gas Emissions Hazardous Materials Land Use Noise and Vibration Security & System Safety Socioeconomics Transportation Utilities Visual Quality/Aesthetics Water Resources, Water Quality, and Floodplains 28
33 Environmental Process State (CEQA) and Federal (NEPA) Environmental Process Timeline 29
34 Public Comment 30
35 Speaker Guidelines Please submit a speaker card if you wish to speak Moderator will call speakers Speakers will have 2 minutes to present Yellow Card 30 seconds remaining Red Card speaking time is over Tonight, we will not be responding to your comments We will document your comments in the Scoping Report Time slots will not be traded or yielded Please, no interruptions of speaker, side conversations, applause, etc. Please turn off cell phones Thank you for your cooperation! 31
36 Opportunity for Public Comment Submittal of comments to VTA: In person: Verbal comments during formal comment period of Scoping Meeting or submittal of comment card Mail: Tom Fitzwater Environmental Programs and Resources Management, Bldg B-2 Valley Transportation Authority 3331 North First Street San Jose, CA Comments must be received by 5:00 P.M. on March 2,
37 Informational Boards
38
39 Welcome to VTA s BART Silicon Valley Phase II Extension Project Scoping Meeting 5:30 PM 6:30 PM Open House 6:30 PM 7:30 PM Formal Presentation and Comments To submit comments: Written comments will be accepted until Monday, March 2, 2015 and may be submitted via mail or with attention to: Attn: Tom Fitzwater Mail: VTA Environmental Programs & Resources Management, Building B North First Street, San Jose, CA BARTPhase2EIS-EIR@vta.org Project website: VTA s BART Silicon Valley Phase II Extension Project
40 Environmental Review Steps Initiate Environmental Process Early Consultation/Scoping Prepare Draft Environmental Document Comment Period & Public Hearings VTA Board De nes Final Project Prepare Final Environmental Document/Respond to Comments VTA Board of Directors Approves the Project Federal Record of Decision for the Project VTA s BART Silicon Valley Phase II Extension Project
41 Environmental Topics Air Quality Biological Resources and Wetlands Community Services Construction Cultural Resources Electromagnetic Fields Energy Geology, Soils, & Seismicity Greenhouse Gas Emissions Hazardous Materials Land Use Noise and Vibration Security & System Safety Socioeconomics Transportation Utilities Visual Quality/Aesthetics Water Resources, Water Quality, and Floodplains VTA s BART Silicon Valley Phase II Extension Project
42 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Release Notice of Preparation Draft SEIS/SEIR3 Final SEIS/SEIR3 VTA Board Approves Project NEPA/CEQA Environmental Process Scoping Meetings End of Scoping Period Circulate Draft SEIS/SEIR3 Document Draft SEIS/SEIR3 Public Meetings VTA Board De nes Final SEIS/SEIR3 Project Circulate Final SEIS/SEIR3 Document FTA Record of Decision New Starts Funding Process Entry into NSPD Submit Application to enter New Starts Project Development (NSPD) Entry into New Starts Engineering FTA Letter of No Prejudice Receive Full Funding Grant Agreement from FTA Community Engagement * Scoping Period Public Meetings and Stakeholder Outreach *Community engagement will include scoping meetings, stakeholder outreach, and targeted community forums that ful ll Title VI requirements. A community outreach plan and strategy will be developed to have targeted community forums at all the station areas. NEPA/CEQA and New Starts Milestone Schedule
43 101 Berryessa Station Santa Clara Station Santa Clara St Alum Rock Station Diridon Station Downtown San Jose Station VTA s BART Silicon Valley Phase II Extension Project
44 101 PARKING/PUBLIC FACILITY/DEVELOPMENT (1,200 PARKING SPACES) STATION BELOW Legend N Underground Station Parking/Public Facility/Development Systems Facilities Access Circulation Key Pedestrian Linkage Vehicle Access Bus Access Station Entrance Options New/Modi ed Signalized Intersection Bike Facilities Alum Rock Station Conceptual Site Plan Phase II Extension Project February 2015
45 N. 2ND STREET S. 2ND STREET TRANSIT MALL S. 3RD STREET N. 3RD STREET N. 4TH STREET N. 5TH STREET N. 6TH STREET STATION BELOW N S. 4TH STREET S. 6TH STREET Legend Underground Station Systems Facilities Crossover Facility Station Entrance Options Downtown Station East Option Conceptual Site Plan Phase II Extension Project February 2015
46 Legend Underground Station Systems Facilities Crossover Facility Station Entrance Options N Downtown Station West Option Conceptual Site Plan Phase II Extension Project February 2015
47 STATION BELOW Legend Underground Station Systems Facilities Access Circulation Key Pedestrian Linkage Vehicle Access Bus Access Station Entrance Options New/Modi ed Signalized Intersection N Diridon Station Conceptual Site Plan Phase II Extension Project February 2015
48 EAST OPTION PARKING/ PUBLIC FACILITY/ DEVELOPMENT (500 SPACES) STATION BROKAW ROAD N WEST OPTION PARKING/ OPTION 2 PUBLIC 3 FACILITY/ LEVEL DEVELOPMENT PARKING (500 STRUCTURE SPACES) PEDESTRIAN UNDERCROSSING Legend At-grade Station Parking/Public Facility/Development Systems Facilities Access Circulation Transit Plaza Maintenance Facility with Vehicle Storage Key Pedestrian Linkage Vehicle Access Bus Access Station Entrance New/Modi ed Signalized Intersection Bike Facilities Santa Clara Station Conceptual Site Plan Phase II Extension Project February 2015
VTA s BART Silicon Valley Extension BART Phase II Project Update
VTA s BART Silicon Valley Extension BART Phase II Project Update December 1, 2014 VTA s BART Silicon Valley Alignment 2 VTA s BART Phase I Berryessa Extension 10-mile extension under construction Two Stations:
More informationVTA s Capital Projects Program & BART Phase II Procurement Opportunities. VTA s Procurement Fair and Workshop. November 1, 2016
VTA s Capital Projects Program & BART Phase II Procurement Opportunities VTA s Procurement Fair and Workshop November 1, 2016 Capital Projects Program Capital Projects Program Major Projects in Construction
More informationVTA s BART Silicon Valley Phase II Extension Project
VTA s BART Silicon Valley Phase II Extension Project Alum Rock Community Working Group November 15, 2017 1 Agenda Follow-up Items Phase I Update Phase II Update San Jose Diridon Integrated Station Concept
More informationSILICON VALLEY RAPID TRANSIT CORRIDOR BART EXTENSION TO MILPITAS, SAN JOSE AND SANTA CLARA POLICY ADVISORY BOARD MEETING MINUTES
SILICON VALLEY RAPID TRANSIT CORRIDOR BART EXTENSION TO MILPITAS, SAN JOSE AND SANTA CLARA POLICY ADVISORY BOARD MEETING Wednesday, April 25, 2007 MINUTES 1. The Regular Meeting of the Silicon Valley Rapid
More informationVTA s BART Silicon Valley Phase II Extension Project
VTA s BART Silicon Valley Phase II Extension Project Downtown/Diridon Community Working Group February 6, 2018 1 Agenda Follow-up Items Phase I Update Phase II Update Financial Update San Jose Diridon
More information2016 Measure B Program Areas
2016 Measure B Program Areas 2016 Measure B Programwide Topics 2 Program Areas 3 2016 Measure B Program Areas Program Category BART Phase II Bicycle/Pedestrian Caltrain Corridor Capacity Improvements Caltrain
More informationVTA s BART Silicon Valley Phase II Extension Project
VTA s BART Silicon Valley Phase II Extension Project Alum Rock/28 th Street Community Working Group February 7, 2018 1 Follow-up Items Agenda Trails Overview Phase I Update Phase II Update Financial Update
More informationATTACHMENT A: DRAFT PROPOSED SCOPE OF WORK
6 Harris Court Monterey, CA 93940 831 649-5225 Fax 831 373-5065 ATTACHMENT A: DRAFT PROPOSED SCOPE OF WORK FORA has prepared this proposed scope of work to be used as a guide for consultants as they submit
More informationSAN IPSE CAPITAL OF SILICON VALLEY ?/2W/(T. Memorandum TO: HONORABLE MAYOR AND CITY COUNCIL. FROM: Kim Walesh Jim Ortbal
CITY OF 7 S3 SAN IPSE CAPITAL OF SILICON VALLEY TO: HONORABLE MAYOR AND CITY COUNCIL STUDY SESSION: 3/30/2017 Memorandum FROM: Kim Walesh Jim Ortbal SUBJECT: DIRIDON STATION PLAN AND REGIONAL RAIL PROJECTS
More informationDiridon Station Joint Policy Advisory Board MINUTES
CALL TO ORDER Diridon Station Joint Policy Advisory Board Friday, December 17, 2010 MINUTES The Regular Meeting of the Diridon Station Joint Policy Advisory Board ( Committee ) was called to order at 3:06
More informationRegional Transportation Activities Report. VTA Funding Measure
Regional Transportation Activities Report VTA Funding Measure Transportation and Environment Committee June 6, 2016 VTA Proposed Funding Measure Funding Category BART Phase II Bicycle/Pedestrian Program
More informationC81st Avenue Library December 18, 2014 OLISEUM AREA SPECIFIC PLAN
C81st Avenue Library December 18, 2014 OLISEUM AREA SPECIFIC PLAN TONIGHT S AGENDA 1. Presentation by City of Oakland staff and consultants: -- Ed Manasse, Oakland Strategic Planning Manager -- Ed McFarlan,
More informationWESTERN SLOPE CIP AND TIM FEE UPDATE
WESTERN SLOPE CIP AND TIM FEE UPDATE 12/6/16 BOARD OF SUPERVISORS STUDY SESSION B O A R D S T U D Y S E S S I O N # 8 2015 14-0245 Revised 22M 1 of 53 AGENDA 1. Background 2. Programmatic EIR 3. General
More informationUNIVERSITY OF CALIFORNIA, SANTA CRUZ
UNIVERSITY OF CALIFORNIA, SANTA CRUZ BERKELEY DAVIS IRVINE LOS ANGELES MERCED RIVERSIDE SAN DIEGO SAN FRANCISCO SANTA BARBARA SANTA CRUZ PHYSICAL PLANNING, DEVELOPMENT & OPERATIONS UC SANTA CRUZ, CALIFORNIA
More informationEastside Transit Corridor Phase 2 Draft EIS/EIR Public Hearings
Eastside Transit Corridor Phase 2 Draft EIS/EIR Public Hearings Agenda Registration/Open House (30 minutes) Draft EIS/EIR Presentation (30 minutes) Public Comment (90 minutes) 1 Purpose of Today s Meeting
More informationSUBJECT: SEE BELOW DATE: May 26, 2016
COUNCIL AGENDA: 06-07-16 ITEM: A. CI CITY OF C: 3- SAN JOSE CAPITAL OF SILICON VALLEY TO: HONORABLE MAYOR AND CITY COUNCIL Memorandum FROM: Barry Ng SUBJECT: SEE BELOW DATE: Approved IL2_PS^ Date 5 ^ lip
More informationCentral City Line Kick-off and Tour
Central City Line Kick-off and Tour Phase C Preliminary Engineering, Environmental Documentation and Small Starts Submittal Kickoff Meeting Agenda Time Item 1:00 PM Welcome, Introductions and Agenda Review
More informationCITY OF SACRAMENTO COMMUNITY DEVELOPMENT CALIFORNIA 300 Richards Blvd. DEPARTMENT
CITY OF SACRAMENTO COMMUNITY DEVELOPMENT CALIFORNIA 300 Richards Blvd. DEPARTMENT 3 rd Floor Sacramento, CA 95811 DATE: April 12, 2013 TO: FROM: RE: Interested Persons Tom Buford, Senior Planner Community
More informationAttendees: Members in Attendance: Asn Ndiaye, Charlie Faas, Deborah Arant, Bert Weaver, Jim Goddard, Adina Levin, Scott Knies, and Jaclyn Tidwell
Downtown/Diridon Community Working Group Meeting Date of Meeting: June 12, 2018 (4:00 p.m. to 6:00 p.m.) Attendees: Members in Attendance: Asn Ndiaye, Charlie Faas, Deborah Arant, Bert Weaver, Jim Goddard,
More informationNOTICE OF PREPARATION OF AN ENVIRONMENTAL IMPACT REPORT AND SCOPING MEETING FOR THE DOWNTOWN SPECIFIC PLAN COMMENT PERIOD
DATE: February 15, 2017 TO: FROM: RE: Interested Persons Tom Buford, Senior Planner Community Development Department NOTICE OF PREPARATION OF AN ENVIRONMENTAL IMPACT REPORT AND SCOPING MEETING FOR THE
More informationMay 17, To: From: Subject: Program continues to. Overview. Step Two. fixed-guideway. Program. for. Background
May 17, 2010 To: From: Subject: Transportation 2020 Committee Will Kempton, Chief Executive Officer Go Local Fixed-Guideway Program Update Overview The Go Local Fixed-Guidewaof the program, the City of
More information1 Introduction. 1.1 Specific Plan Background
Introduction 1 Introduction This document is an Environmental Impact Report (EIR) that evaluates the potential environmental effects associated with implementation of the Bay Fair Transit Oriented Development
More informationVTA s BART Silicon Valley Phase II Extension Project
VTA s BART Silicon Valley Phase II Extension Project Downtown/Diridon Community Working Group September 12, 2017 1 Agenda Follow-up Items CWG Workplan BART Fare Setting Process & Background Future Intermodal
More informationPublic and Agency Involvement. 8.1 Scoping Meetings and Noticing. Chapter 8
8.1 Scoping Meetings and Noticing Chapter 8 As described in Chapter 1, Section 1.7, Scope and Content of this Environmental Impact Report, the scoping process for this EIR was formally initiated on June
More information2000 Measure A Transit Improvement Program
2000 Measure A Transit Improvement Program Citizens Watchdog Committee Annual Report on Fiscal Year 2012 2000 Measure A Transit Improvement Program Citizens Watchdog Committee Annual Report on Fiscal Year
More informationVTA s BART Silicon Valley Phase II Extension Project
VTA s BART Silicon Valley Phase II Extension Project Alum Rock Community Working Group September 13, 2017 1 Agenda Follow-up Items CWG Work Plan Five Wounds Trail Discussion BART Fare Setting Process &
More informationCHAPTER 6 PUBLIC AND AGENCY OUTREACH
CHAPTER 6 PUBLIC AND AGENCY OUTREACH This chapter documents the Westside Purple Line Extension Project (the Project) Public Participation Plan for the Draft Supplemental Environmental Impact Statement
More informationFresno County Little Bear Solar Project EIR SCOPING MEETING Thursday, September 14, :30 pm - 7:30 pm
Fresno County Little Bear Solar Project EIR SCOPING MEETING Thursday, September 14, 2017 5:30 pm - 7:30 pm Agenda Introductions Purpose of the Meeting Project Overview The CEQA Process Proposed Schedule
More informationSubject: Request for Proposal Route 99 Interchanges at Hammett Road and Kiernan Avenue
DEPARTMENT OF PUBLIC WORKS Matt Machado Director 1010 10 th Street, Suite 3500, Modesto, CA 95354-0847 Phone: 209.525.6550 Date «FirstName» «LastName» «Company» «Address1» «City», «State» «PostalCode»
More informationAPPENDIX B.3 SCOPING SUMMARY REPORT
APPENDIX B.3 SCOPING SUMMARY REPORT Solid Waste Integrated Resources Plan Program Environmental Impact Report Scoping Meetings Summary Report August 26, 2010 1:30 p.m. and 6: 30 p.m. City of Los Angeles,
More informationREQUEST FOR PROPOSALS EASTERN COACHELLA VALLEY S ACTION PLAN FOR CLIMATE RESILIENCE BACKGROUND AND GENERAL DESCRIPTION
REQUEST FOR PROPOSALS EASTERN COACHELLA VALLEY S ACTION PLAN FOR CLIMATE RESILIENCE NOTICE BACKGROUND AND GENERAL DESCRIPTION The Coachella Valley Association of Governments (CVAG), in partnership with
More informationCONNECTING AND TRANSFORMING CALIFORNIA. Ben Tripousis, Northern California Regional Director SPUR Tuesday, October 25, 2016 San Jose, California
CONNECTING AND TRANSFORMING CALIFORNIA Ben Tripousis, Northern California Regional Director SPUR Tuesday, October 25, 2016 San Jose, California HIGH-SPEED RAIL STATEWIDE OVERVIEW 2 CONNECTING CALIFORNIA
More informationFor the Fiscal Year Ended June 30, 2016
SANTA CLARA VALLEY TRANSPORTATION AUTHORITY 2000 Measure A Transit Improvement Program [A Fund of the Santa Clara Valley Transportation Authority] Independent Accountant s Report on Compliance Examination
More informationNational Environmental Policy Act/California Environmental Quality Act Scoping Meeting Summary
Redwood City Harbor Navigation Improvement Integrated Feasibility Study & EIS/EIR Appendix K National Environmental Policy Act/California Environmental Quality Act Scoping Meeting Summary December 2014
More informationPublic Scoping Meeting for the Environmental Impact Report
Public Scoping Meeting for the Environmental Impact Report Solana Highlands Revitalization Project November 20, 2014 @ 5:30pm 1 Scoping Meeting Agenda Welcome and Introductions Purpose of the Notice of
More informationRequest for Proposals For General Plan Update
Request for Proposals For General Plan Update Issued: Monday, December 18, 2017 Proposals Due: Tuesday, January 16, 2018, 5:00 pm PREPARED BY: 330 W. 20 th Avenue San Mateo, CA 94403 CONTACT: Planning
More informationSOUTHWEST LRT (METRO GREEN LINE EXTENSION)
10 Joint Development This chapter describes potential long-term direct and indirect and short-term (construction) direct and indirect effects that would result from the Southwest Light Rail Transit (LRT)
More informationDowntown Oakland Specific Plan Frequently Asked Questions
Downtown Oakland Specific Plan Frequently Asked Questions 1. What is the Downtown Oakland Specific Plan? A Specific Plan is a regulatory tool that local governments can use to implement the general plan
More informationREPORT. To the Honorable Mayor and City Council From the City Manager. May 9, 2016
REPORT To the Honorable Mayor and City Council From the City Manager May 9, 2016 SUBJECT Study Session for Consideration of the Draft Inner Harbor Specific Plan, Draft Inner Harbor Specific Plan Environmental
More informationFor the Fiscal Year Ended June 30, 2014
SANTA CLARA VALLEY TRANSPORTATION AUTHORITY 2000 Measure A Transit Improvement Program [A Fund of the Santa Clara Valley Transportation Authority] Independent Accountant s Report on Compliance Examination
More informationREQUEST FOR PROPOSALS
REQUEST FOR PROPOSALS ENGINEERING/ARCHITECTURAL DESIGN SERVICES FOR THE NORTHEAST STOCKTON LIBRARY AND RECREATION CENTER CITY PROJECT NO. PW1724 City of Stockton Public Works Department 22 E. Weber Avenue,
More information2.0 COMMENTS AND RESPONSES TO COMMENTS
2.0 COMMENTS AND RESPONSES TO COMMENTS A list of those agencies, organizations, and interested parties, which have commented on the Draft EIR, is provided below. A copy of each comment letter or a summary
More informationPRESENTATION ITEMS. 1. Furniture, Fixtures and Equipment (FF&E) Program
PRESENTATION ITEMS 1. Furniture, Fixtures and Equipment (FF&E) Program 2. California Environmental Quality Act (CEQA) for Vacaville Biotechnology Building 3. Science Project, Fairfield Campus Furniture,
More informationMeeting Minutes. Project: Subject: Date: Wednesday, December 16, 2015 Location: Attendees:
Meeting Minutes Project: Subject: DART D2 Stakeholder Work Group for D2 Date: Wednesday, December 16, 2015 Location: Attendees: DART, 1401 Pacific Avenue, Dallas, TX Steve Salin, DART Ernie Martinez, DART
More informationCapitol Expressway Light Rail Project SCOPING SUMMARY REPORT. Federal Transit Administration Santa Clara Valley Transportation Authority
Capitol Expressway Light Rail Project SCOPING SUMMARY REPORT Federal Transit Administration Santa Clara Valley Transportation Authority January 2010 TABLE OF CONTENTS Introduction... 1 General Description
More informationMOBILITY PARTNERSHIP AGENDA
1. CALL TO ORDER/ROLL CALL MOBILITY PARTNERSHIP Wednesday, October 11, 2017 9:00 a.m. to 10:30 a.m. Gilroy City Council Chambers 7351 Rosanna Street, Gilroy, CA AGENDA 2. PUBLIC PRESENTATIONS: This portion
More informationCentral City Line Steering Committee
Central City Line Steering Committee Meeting #1 Thursday, Spokane Intermodal Center Great Northern Room, #310 221 W. First Ave. Spokane, WA 1 Agenda Welcome, Introductions and Agenda Review Review of Steering
More informationOrder of Business. D. Approval of the Statement of Proceedings/Minutes for the meeting of January 24, 2018.
COUNTY OF SAN DIEGO BOARD OF SUPERVISORS REGULAR MEETING MEETING AGENDA WEDNESDAY, FEBRUARY 14, 2018, 9:00 AM BOARD OF SUPERVISORS NORTH CHAMBER 1600 PACIFIC HIGHWAY, SAN DIEGO, CALIFORNIA Order of Business
More informationAction / Decisions Pending / Follow up
Meeting Location Via Telephone 70 W. Hedding Street Lower Level Conference Room Meeting Date and/or Time 03.08.2017 Meeting Subject Community Meeting #02 Meeting Number 1 File 1MN This is page 1 of 5 Present
More informationBilling Code P DEPARTMENT OF ENERGY. Federal Energy Regulatory Commission. [Docket No. PF ] Notice of Intent to Prepare an
This document is scheduled to be published in the Federal Register on 07/29/2014 and available online at http://federalregister.gov/a/2014-17756, and on FDsys.gov Billing Code 6717-01-P DEPARTMENT OF ENERGY
More informationUNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION
UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION Tennessee Gas Pipeline Company, L.L.C. Docket No. PF14-22-000 NOTICE OF INTENT TO PREPARE AN ENVIRONMENTAL IMPACT STATEMENT FOR THE PLANNED
More informationUNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION
UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION Transcontinental Gas Pipe Line Company, LLC Docket No. PF16-5-000 NOTICE OF INTENT TO PREPARE AN ENVIRONMENTAL IMPACT STATEMENT FOR THE PLANNED
More informationVan Ness Avenue Bus Rapid Transit (BRT) Citizens Advisory Committee (CAC) Meeting 13
1 AGENDA Van Ness Avenue Bus Rapid Transit (BRT) Citizens Advisory Committee (CAC) Meeting 13 Date: 5:00 p.m., Tuesday, October 27 th, 2009 Location: 100 Van Ness Avenue, 26 th Floor 5:00 1. Committee
More informationFrom: To: Cc: Subject: Date: Attachments: Dave Baker Wolff, Greg Coe, Tony Sidewalk Monday, March 2, 2015 5:21:13 PM Hungry Hunter sidewalk 10 feet from face of curb, 1.JPG Hungry Hunter sidewalk 10 feet
More informationPresentation. I. HMGP Overview II. III. IV. Application Review Process Post Obligation Information Common Errors
1 Presentation I. HMGP Overview II. III. IV. Application Review Process Post Obligation Information Common Errors 2 Hazard Mitigation Grant Program (HMGP) Activities that will reduce or eliminate future
More informationRegional Transportation Plan & Sustainable Communities Strategy. Public Participation Plan
Regional Transportation Plan & Sustainable Communities Strategy Public Participation Plan September 17, 2015 Table of Contents I. Introduction... 1 II. Phases of the Public Participation Process... 2
More informationPeninsula Corridor Joint Powers Board Legislative Program
Peninsula Corridor Joint Powers Board 2018 Legislative Program Purpose Legislative and regulatory actions have the potential to significantly benefit Peninsula Corridor Joint Powers Board (JPB) programs
More informationSAFETY, SECURITY, AND TRANSIT PLANNING AND OPERATIONS AGENDA
SAFETY, SECURITY, AND TRANSIT PLANNING AND OPERATIONS Thursday, February 16, 2017 3:00 PM VTA Conference Room B-106 3331 North First Street San Jose, CA AGENDA CALL TO ORDER 1. ROLL CALL 2. PUBLIC PRESENTATIONS:
More informationTHE CITY OF SAN MATEO/ESTERO MUNICIPAL IMPROVEMENT DISTRICT WASTE WATER TREATMENT PLANT Request for Qualification 2015 Design Theme Competition San
THE CITY OF SAN MATEO/ESTERO MUNICIPAL IMPROVEMENT DISTRICT WASTE WATER TREATMENT PLANT Request for Qualification 2015 Design Theme Competition San Mateo, CA sustainable Sustainable Nature Innovation DESIGN
More informationMETHODOLOGY - Scope of Work
The scope of work for the Truckee West River Site Redevelopment Feasibility Study will be undertaken through a series of sequential steps or tasks and will comprise four major tasks as follows. TASK 1:
More information8/9/2012. SWLRT Community Advisory Committee. Today s Agenda. CAC Issue Topics: Survey Results
SWLRT Community Advisory Committee August 9, 2012 2 Today s Agenda Welcome/Approve Minutes Project Updates CAC Issues Survey Results DEIS Process Overview and Outreach Plan FEIS/Next Steps Reports CAC
More informationUnited Fresh Start Foundation Joins Silicon Valley Leaders at 3 rd Annual 5K Run to Support Salad Bars for California Schools
NEWS RELEASE For Immediate Release, March 15, 2016 Contact: Andrew Marshall amarshall@unitedfresh.org (202) 303-3407 United Fresh Start Foundation Joins Silicon Valley Leaders at 3 rd Annual 5K Run to
More informationCity of Lynwood MODIFIED REQUEST FOR PROPOSALS FOR
City of Lynwood MODIFIED REQUEST FOR PROPOSALS FOR AN URBAN PLANNING FIRM TO PREPARE A SPECIFIC PLAN AMENDMENT TO THE LYNWOOD TRANSIT AREA SPECIFIC PLAN AND REQUIRED CEQA SUPPORTING DOCUMENTS (SUPPLEMENTAL
More informationCHAPTER 7 KAHUKU TRAINING AREA/ KAWAILOA TRAINING AREA
CHAPTER 7 KAHUKU TRAINING AREA/ KAWAILOA TRAINING AREA 7.1 INTRODUCTION 7-1 7.2 LAND USE/RECREATION 7-6 7.3 VISUAL RESOURCES 7-24 7.4 AIRSPACE 7-30 7.5 AIR QUALITY 7-34 7.6 NOISE 7-43 7.7 TRAFFIC 7-47
More informationSAN JOSE CAPITAL OF SILICON VALLEY
CITY OF "3 SAN JOSE CAPITAL OF SILICON VALLEY COUNCIL AGENDA: 11/29/16 ITEM: Memorandum TO: HONORABLE MAYOR AND CITY COUNCIL FROM: Barry Ng Jim Ortbal SUBJECT: 7652 - ST. JOHN STREET MULTI MODAL IMPROVEMENTS
More informationCONGESTION MANAGEMENT PROGRAM & PLANNING COMMITTEE AGENDA
CONGESTION MANAGEMENT PROGRAM & PLANNING COMMITTEE Thursday, February 18, 2016 10:00 AM VTA Conference Room B-104 3331 North First Street San Jose, CA AGENDA CALL TO ORDER 1. ROLL CALL 2. PUBLIC PRESENTATIONS:
More informationThe City of San Rafael is issuing this Request for Proposals (RFP) to solicit proposals from qualified consultants to provide:
REQUEST FOR PROPOSALS (RFP) CITY OF SAN RAFAEL GENERAL PLAN 2040 TECHNICAL SUPPORT AND DOWNTOWN PRECISE PLAN Environmental Review Transportation Infrastructure Economics Community Design Meeting Facilitation,
More informationUNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION
UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION Adelphia Gateway, LLC Docket No. CP18-46-000 NOTICE OF INTENT TO PREPARE AN ENVIRONMENTAL ASSESSMENT FOR THE PROPOSED ADELPHIA GATEWAY PROJECT,
More informationCASE STUDY: OVERVIEW OF A UNIVERSITY PROGRAM
CASE STUDY: OVERVIEW OF A UNIVERSITY PROGRAM Example of Option #1: Pre-Tax Benefits Plus Secondary Measures (secondary measures not required with Option #1) San Jose State University (SJSU) is a public
More informationTo: From: Subject: Program continues to. Overview. the City of. Background. began the. As part of with both
September 8, 2010 To: From: Subject: Transportation 2020 Committee Will Kempton, Chief Executive Officer Go Local Fixed-Guideway Program Update Overview The Go Local Fixed-Guideway Program continues to
More informationAPPLICATION FOR PARCEL MAP
Public Works Number: - / 3- APPLICATION FOR PARCEL MAP Department of Public Works Development Services 200 East Santa Clara Street San Jose, California 95113 (408) 535-7802 Applicant Phone Number Fax Number
More informationIRVINE UNIFIED SCHOOL DISTRICT RESPONSE TO COMMENTS FOR THE PLANNING AREA 6 NORTH ELEMENTARY SCHOOL
IRVINE UNIFIED SCHOOL DISTRICT RESPONSE TO COMMENTS FOR THE PLANNING AREA 6 NORTH ELEMENTARY SCHOOL Prepared for: IRVINE UNIFIED SCHOOL DISTRICT Facilities Planning & Construction Services Departments
More informationThe goal of the program is to enable transit-oriented housing and employment growth in Santa Clara County s Priority Development Areas (PDAs).
PDA PLANNING GRANTS PROGRAM The Santa Clara Valley Transportation Authority (VTA) has created a planning grant program for Santa Clara County jurisdictions that will provide significant support for Priority
More informationVTP Highway Program. Semi-Annual Report April 2013
VTP Highway Program Semi-Annual Report April 2013 VTP Highway Program Semi-Annual Progress Report April 2013 Table of Contents TABLE OF CONTENTS Section Title Page 1 EXECUTIVE SUMMARY A Background... 1-2
More informationSAN IPSE CAPITAL OF SILICON VALLEY
CITY OF *3 SAN IPSE CAPITAL OF SILICON VALLEY TO: HONORABLE MAYOR AND CITY COUNCIL COUNCIL AGENDA: 6-21-16 ITEM: -7 «o Memorandum FROM: Angel Rios, Jr. SUBJECT: PARKS, RECREATION AND NEIGHBORHOOD SERVICES
More informationCommunity Advisory Panel Meeting #
Community Advisory Panel Meeting # 3 10.10.18.. Agenda Welcome and Introductions Community Conversations Review mailing in anticipation of next two community meetings Work Plan / Schedule Alternatives
More informationSanta Clara County County Home Page http://www.sccgov.org/portal/site/scc of Planning and Planning Office Services Office Building Inspection Office County Clerk/Recorder s Office Municipal/County Code
More informationModernization Program Peninsula Corridor Electrification Project (PCEP) 3 rd Quarter FY 2016 Progress Report
Modernization Program Peninsula Corridor Electrification Project (PCEP) 3 rd Quarter FY 2016 Progress Report January 1, 2016 to March 31, 2016 Funding Partners FTA Core Capacity FTA Section 5307/5337 (Environmental
More informationDraft Community Outreach Plan for the Climate Action Plan Update
Draft Community Outreach Plan for the Climate Action Plan Update PREPARED FOR 201 North Broadway Escondido, CA 92025 Project Contact Mike Strong, Assistant Planning Director (760) 839-4556 mstrong@escondido.org
More informationREQUEST FOR PROPOSALS FOR THE BAY FAIR BART TRANSIT VILLAGE TRANSIT-ORIENTED DEVELOPMENT (TOD) SPECIFIC PLAN. RFP NO.
REQUEST FOR PROPOSALS FOR THE BAY FAIR BART TRANSIT VILLAGE TRANSIT-ORIENTED DEVELOPMENT (TOD) SPECIFIC PLAN RFP NO. 54094A (Re-Bid) Proposal Mailing Date December 11, 2014 Proposal Submittal Due Date
More informationNOTICE OF AVAILABILITY TIERED DRAFT ENVIRONMENTAL IMPACT REPORT FOR THE SAN FRANCISCO STATE UNIVERSITY CREATIVE ARTS & HOLLOWAY MIXED-USE PROJECT
PHYSICAL PLANNING & DEVELOPMENT 1600 Holloway Avenue, CY 201 San Francisco, CA 94132 Tel: 415/405-3836 Fax: 415/405-3846 NOTICE OF AVAILABILITY TIERED DRAFT ENVIRONMENTAL IMPACT REPORT FOR THE SAN FRANCISCO
More informationCity Council Report 915 I Street, 1 st Floor Sacramento, CA
City Council Report 915 I Street, 1 st Floor Sacramento, CA 95814 www.cityofsacramento.org File ID: 2017-01692 January 9, 2018 Consent Item 13 Title: Affordable Housing and Sustainable Communities Grant
More informationSanta Clara Valley Transportation Authority Disadvantaged Business Enterprise (DBE) Program
Santa Clara Valley Transportation Authority Disadvantaged Business Enterprise (DBE) Program Three-Year Overall Goal and Methodology Report For Federal Fiscal Years 2017 2019 I. Goal Setting Methodology
More informationMetro. Board Report. File #: , File Type:Informational Report
Metro Board Report Los Angeles County Metropolitan Transportation Authority One Gateway Plaza 3rd Floor Board Room Los Angeles, CA File #:2015-1743, File Type:Informational Report Agenda Number:56. PLANNING
More informationATTACHMENT H Community Outreach Summary & Public Engagement Plan
ATTACHMENT H Community Outreach Summary & Public Engagement Plan I. II. III. APPENDIX A: OUTREACH MATERIALS I. Postcard Mailing Last Chance Grade - Summary of March 2016 Community Town Halls Page
More informationchapter 5 Action Plan
5 Action Plan Critical to the CBTP process is bridging the gap between planning and action. Implementation of the CBTP relies on multiple jurisdictions and agencies, each responsible for different strategies
More informationREQUEST FOR QUALIFICATIONS CAMPUS MASTER PLAN UPDATE MOBILITY AND WAYFINDING
REQUEST FOR QUALIFICATIONS CAMPUS MASTER PLAN UPDATE MOBILITY AND WAYFINDING San Francisco State University (SF State) Department of Physical Planning and Development is requesting qualification statements
More informationSan Francisco Transportation Plan (SFTP) and Early Action Plan
San Francisco Transportation Plan (SFTP) and Early Action Plan October 2013 SAN FRANCISCO COUNTY TRANSPORTATION AUTHORITY Purpose of the San Francisco Transportation Plan (SFTP) Regional Transportation
More informationCOUNTY OF SANTA BARBARA
COUNTY OF SANTA BARBARA PLANNING COMMISSION MARKED AGENDA 9:00 a.m. C. MICHAEL COONEY 1st District Santa Barbara County CECILIA BROWN 2nd District, Vice-Chair Engineering Building, Room 17 JOAN HARTMANN
More informationSR-86/AVENUE 50 NEW INTERCHANGE PROJECT
REQUEST FOR PROPOSALS FOR PROFESSIONAL ENGINEERING SERVICES CITY PROJECT NO. ST-81 (File No. 2015-04) FEDERAL AID PROJECT NO. HPLULN - 5294(011) FOR THE SR-86/AVENUE 50 NEW INTERCHANGE PROJECT Preparation
More informationState Project No. XXXXXX City Project No. c401807
June 29, 2017 Request for Qualifications Design and Environmental Services for the SLR Parkway Phase III Project also known as a portion of the MBSST (Rail Trail) Segment 8 (San Lorenzo River Railroad
More informationCal Poly Pomona Request for Clarification for Lanterman Development Center Land Development Consultant RFC
Cal Poly Pomona Request for Clarification for Lanterman Development Center Land Development Consultant RFC 16-006 A. INTRODUCTION California State Polytechnic University, Pomona ( Cal Poly Pomona ), is
More informationThe next steps outlined at the end of this section are the key requirements as we can best envision them at this stage.
5 Implementation 5.1 Anticipated Caltrans Review Process... 2 5.1.1 Project Initiation Document and Project Report... 2 5.1.2 Environmental Review Process... 4 5.1.3 Right of Way Acquisition Process...
More informationSEQUOIA UNION HIGH SCHOOL DISTRICT BACKGROUND INFORMATION FOR AGENDA ITEMS FOR 7/22/15, BOARD MEETING
SEQUOIA UNION HIGH SCHOOL DISTRICT BACKGROUND INFORMATION FOR AGENDA ITEMS FOR 7/22/15, BOARD MEETING 1. CALL TO ORDER Anyone wishing to address the Board on closed session matters may do so at this time.
More informationCHINA SILICON VALLEY BUSINESS DEVELOPMENT. Special Meeting of the Board of Directors
CHINA SILICON VALLEY BUSINESS DEVELOPMENT Special Meeting of the Board of Directors September 7, 2014 10:00 am Pacific Standard Time 20807 Stevens Creek Blvd, Cupertino, CA 95014 Directors Present: Directors
More informationIn developing the program, as directed by the Board (Attachment A), staff used the following framework:
_... ~ Los Angeles County ~ T~"'-"- Metro One Gateway Plaza Los Angeles, CA 90012-2952 213.922.200C metro. net 15 REVISED PLANNING AND PROGRAMMING COMMITTEE SEPTEMBER 18, 2013 SUBJECT: ACTION: OPEN STREETS
More informationBusiness Advisory Committee. August 26, 2015
Business Advisory Committee August 26, 2015 1 Today s Topics SDEIS Comment Summary Project Update New Starts Application Submittal Municipal Consent Schedule Next Steps: 6 Month Look Ahead Southwest Corridor-wide
More informationRequest for Proposals (RFP) for Professional Planning Services Burlington VT, Downtown/Waterfront Plan Transportation Study
Department of Planning and Zoning 149 Church Street Burlington, VT 05401 Telephone: (802) 865-7188 (802) 865-7195 (FAX) (802) 865-7142 (TTY) www.ci.burlington.vt.us David E. White, AICP, Director Ken Lerner,
More informationREQUEST FOR PROPOSALS FOR. Jed Smith Pipeline Replacement Project
REQUEST FOR PROPOSALS FOR Jed Smith Pipeline Replacement Project PROPOSALS DUE by 3:00 p.m., Monday, October 31, 2016 LAS VIRGENES MUNICIPAL WATER DISTRICT 4232 LAS VIRGENES ROAD CALABASAS, CA 91302 818.251.2100
More informationREQUEST FOR PROPOSALS
REQUEST FOR PROPOSALS Town of Hope Mills Multi-Modal Congestion Management Plan September 19, 2016 Fayetteville Area Metropolitan Planning Organization Proposal Due Date: 3:00 PM Eastern Time, 28 th October,
More information