Bangladesh: Export Competitiveness for Jobs (IDA 6042-BD) Implementation Support Review January 14-21, 2018 Aide Memoire

Size: px
Start display at page:

Download "Bangladesh: Export Competitiveness for Jobs (IDA 6042-BD) Implementation Support Review January 14-21, 2018 Aide Memoire"

Transcription

1 Bangladesh: Export Competitiveness for Jobs (IDA 6042-BD) Implementation Support Review January 14-21, 2018 Aide Memoire 1. During January 14-21, 2018, a World Bank Task Team 1 conducted an Implementation Support Review of the Export Competitiveness for Jobs Project (EC4J). This Aide Memoire (AM) summarizes the findings on the status of project implementation and presents the recommendations and agreements reached with the implementing agency (IA) during the mission. The AM was discussed at a wrap-up meeting on January 21, 2018, chaired by the Additional Secretary, Mrs. Mahmuda Begum, from the Economic Relations Division (ERD). The Task Team is grateful to the Ministry of Commerce (MoC) for its collaboration and organization of the mission and facilitating meetings with key stakeholders, including the Business Promotion Council (BPC), and the Bangladesh Economic Zones Authority (BEZA). As agreed, this AM will be classified as public under the World Bank s Access to Information policy. OVERALL STATUS AND KEY PROJECT DATA 2. The project was approved by the World Bank Group s Boards of Governors on June 1, It was subsequently approved at the Executive Committee of the National Economic Council (ECNEC) on August 9, The project was signed on November 5, 2017, and it was declared effective on December 11, The Project Implementation Unit (PIU), led by the Additional Secretary of the MoC as Project Director (PD), and comprising of two Deputy Project Directors (DPDs), is currently in the process of establishing a project office and recruiting technical and support staff for key positions in the PIU. Several of the agreed actions from the previous Implementation Support Mission (on September 2017), including some of the covenants per Schedule 2 Section 1.A.2 of the signed Financing Agreement, are yet to be achieved. However, the overall progress is satisfactory since the project has been effective only for one month. Table 1: Project Data Board Approval June 1, 2017 Effectiveness date December 11, 2017 Closing Date of IDA Credit June 30, 2023 IDA Credit Amount US$100 million Amount Disbursed so far US$0 KEY POINTS DISCUSSED AND AGREED ACTIONS Component 1: Market Access Support Program 3. The PIU, BPC and the mission agreed upon specific implementation activities required under Subcomponents 1.1 and 1.3, and the distribution of responsibilities for undertaking each activity. For example, the PIU, in coordination with BPC, will prepare action plans for selected activities (see Annex 2 1 Hosna Sumi (Private Sector Specialist/TTL), Thomas Farole (Lead Economist), Yasuo Konishi (Consultant), Mrinal Kanti Sircar (Consultant), M. Masrur Reaz (Senior Economist), Arafat Istiaque (Procurement Specialist), Hasib Ehsan Chowdhury (Financial Management Specialist), Sabah Moyeen (Senior Social Development Specialist), Nadia Sharmin (Environmental Specialist), Dr Khaliquzzaman (Environmental Consultant), Mostofa Hamza Mehedi (Program Assistant),Mehar Akhter Khan (Program Associate) and Nahid Sharmin (Team Associate). Michael Engman (Sr. Economist/TTL) supported the Mission from Washington, D.C.

2 for the detailed list). In addition, the mission provided technical comments at a review of the draft Grant Manual for the Export Readiness Fund (ERF). The template to be used for Environmental, Social and Quality (ESQ) compliance assessment is currently being drafted by technical expert and will be shared with PIU by Feb 28, Request for Expression of Interest (REOI) for ERF manager was reviewed by the Bank. Issues arising and actions proposed during the mission were as follows. In coordination with the PIU, the BPC will prepare draft action plans and prioritize detailed activities identified under Subcomponents 1.1 and 1.3 (see Annex 2). BPC to take stock and prepare an itemized list of ESQ compliance activities currently undertaken by member associations in the light engineering, plastics and leather sectors. The list should include: title of the activity; key issues covered; number of participants; and duration of each activity. For training, seminars and awareness raising activities, member associations will be required to provide copies of materials used for these activities, and for BPC to develop a physical and/or digital library (searchable) of the materials. BPC to develop an itemized list of data currently collected by the member associations, and identify how the data are collected and updated, stored, analyzed and disseminated. PIU to prepare draft strategic communication plan and activities to implement national ESQ awareness raising. PIU to submit the draft ERF Grant Manual for clearance from the Bank. Task team to finalize draft of the Export Road Map, which is being supported by the complementary advisory project, for review and comments. Task team to finalize template for ESQ assessments and share with PIU and industry associations for review and comments. Component 2: Productivity Enhancement Program 4. Understanding the long term functional value of Technology Centers (TCs) in industrial zones, BEZA expressed their interest and support to allocate lands for TCs, following the lease-agreement procedure. Two potential locations, Mirsarai (Chittagong) and Keraniganj (outskirt of Dhaka), for general engineering TCs within the economic zones were discussed. The PIU was advised to formally apply for land allocation at the economic zone in Mirsarai and submit a formal proposal for Keranigonj (pending decision to allocate land to plastics and associated industries) highlighting potential economic contribution of such TCs. 5. The feasibility study for the leather goods and footwear TC has been initiated by the firm Consulting Services International (CSI). Key informant and expert (local and international) interviews have been completed. The PIU was advised to follow up with the Prime Minister s Office and ERD for confirmation of available land options, which is essential for the feasibility assessment to proceed. The draft assessment result is expected by April The REOI for the feasibility assessment of general engineering TCs has been cleared by the WB, awaiting advertisement. Advisory Committee for TC was formed by PIU. Component 3: Public Investment Facility for Infrastructure Constraints (PIFIC) 6. The draft operating guideline for PIFIC has been discussed in detail during working session with PIU. The mission agreed to discuss and review the draft guideline further regarding the core content, including adjustment to the selection procedures; use of industry associations for outreach; the technical assistance agreement between PIFIC and the sub-project sponsors; and management firm selection. The final draft is expected by Feb 28, 2018 for the Bank s clearance. The REOI for the PIFIC TA firm has been reviewed by the Bank.

3 Component 4: Project Management, Monitoring and Evaluation 7. The PIU is currently staffed with one PD and two DPDs, pending appointment of the third DPD. The Project Steering Committee (PSC) and the Project Implementation Committee (PIC) have been formed. The Project Implementation Manual (PIM) has been drafted and reviewed by the Bank and the PIU will submit a final version for Bank clearance by January 31, Office space for the project is yet to be finalized, which until date has impeded daily work. Terms of References (ToR) for all technical staff has been prepared and cleared by the Bank and they should now be advertised. Having the PIU only partially staffed, added with key selections pending advertisement, results in significant delay to initiate on-theground implementation of key components of the project. The PIU was advised to fast track the selection process to have the fully functional PIU team in place. 8. The PIU requested the mission to provide technical support to develop project management skills with required tools and techniques. The task team plans to conduct a 3-day technical implementation workshop, preferably during early March 2018, to develop a detailed action plan, finalize and establish priorities required for implementing the project components, and provide the PIU with project management training. The session may also include capacity building on monitoring and evaluation, financial management and procurement, and safeguards issues. FIDUCIARY COMPLIANCE 9. Procurement Performance: During the mission, project procurement was discussed thoroughly. The PIU is advised to prepare the procurement packages for all the procurements that are expected to be tendered in the year 2018, and upload in STEP by Feb 15, PIU is advised to expedite the hiring of the Procurement Specialist, as several bids are ready to be advertised. To this end, the ToR for the Procurement Specialist was reviewed and cleared by the Bank, and the PIU has agreed to advertise this position by end of January Overall, the project s progress in procurement is limited since effectiveness, and the PIU is advised to initiate the key procurements at the earliest. 10. Financial Management (FM) Performance: The project has opened a CONTASA, with Janata Bank, which will be the Designated Account to receive Bank financing. Authorized specimen letters, with alternative signatory arrangement between the PD and the DPD, will be sent to the ERD on January 17 for endorsement. The project will follow up with the ERD to ensure that the endorsed signatory letter reaches the Bank by January 22. The mission requested the PIU to initiate the recruitment process for the Financial Management Specialist (FMS), as well as the accountant at the earliest. Meanwhile, the Bank has reviewed and provided comments to the TOR for the recruitment of the FMS. The mission informed that to ensure efficient management of IDA financing, a robust set up of financial management should be in place at the very outset. 11. Disbursements Status: The project is effective as of December 11, 2017, and awaiting ERD s letter on designated signatory. First disbursement of fund will be made soon after receiving the withdrawal application from the client. SAFEGUARD MANAGEMENT 12. Environmental Safeguards: Each sub-project will need to be screened for potential environmental impact and subjected to appropriate Environmental Impact Assessment (EIA) prior to implementation as outlined in the Environmental Management Framework (EMF). The mission recommended and it was

4 agreed that PIFIC Guidelines will include expected environmental impact and associated management plan of proposed projects as one of the considerations for project selection. The PIU will be responsible to obtain the site clearance for the technology center from the Department of Environment (DoE). After obtaining the site clearance, the PIU will share the ToR of the EIA for the technology center for the World Bank clearance. The mission reiterated that it is urgent to appoint an environmental specialist (consultant) with appropriate qualifications at the earliest, as implementation of sub-projects will otherwise be delayed. For example, site selection for the technology centers cannot be finalized without preliminary environmental screening, and the PIFIC cannot incorporate appropriate environmental guidelines. The ToR for hiring the environmental specialist was reviewed and cleared by the Bank and the specialist is expected to be on board by February 28, Social Safeguards: Although the project has been declared effective, no sub-projects have been taken on board yet. The project will not fund any activities that require land acquisition and/or resettlement, or impact indigenous communities. The main social issues to be assessed and mitigated for (where necessary) are labor standards, redundancy of workers due to new technology (and relevant HR policies), gender issues, worker health and safety issues, influx management (as and where necessary) etc. The client will develop in-house capacity for the screening process, preparation of documents/mitigation plans, operation of the grievance redress mechanism, monitoring and evaluation, amongst other activities such as training delivery, review and assessment of sub-project proposals etc. The ToR for hiring social and environmental specialist was reviewed by the Bank and the relevant specialists are expected to be on board by Feb NEXT REVIEW 14. The next regular Implementation Support Review Mission is scheduled for July Table 2: Summary of Agreed Actions Actions Responsibility Agreed timeline 1 A central data storage system with official addresses created for the project PIU Feb 28, Final PIM sent for Bank clearance PIU Feb 07, ERF manual revised and shared with PIU WB Feb 15, PIFIC operating guideline revised and shared with PIU WB Feb 20, BPC shared detailed action plan for sub-component 1.1 and 1.3, list of current ESQ activities with industry associations 6 List of activities for national level ESQ awareness activities prepared 7 Draft template for ESQ assessment finalized and shared with PIU BPC, PIU Feb 20, 2018 PIU Jan 31, 2018 WB Feb 28, Letter to BEZA for TC land in Mirsharai sent PIU Jan 31, Draft application shared with BEZA for TC land in Keranigonj PIU Jan 31, Decision obtained from PMO for leather TC land option MoC Feb 15, Project management workshop organized WB, PIU Feb 28, Procurement plan updated in STEP for all procurements initiated PIU Mar 07, 2018

5 in STEP training organized for PIU staff WB Feb 07, PIU will form evaluation committee and share with Bank PIU Feb 10, Procurement consultant hiring process completed PIU Feb 28, Training conducted on World Bank Procurement Regulations for PIU staffs WB April 25, Authorized signatory letter (ASL) sent to ERD PIU Jan 17, ASL reached from ERD to the Bank (PIU to follow up) ERD Jan 22, Financial Management Specialist s hiring process completed PIU Feb 28, Accountant hiring process completed PIU Feb 28, Environmental and Social safeguards specialist hiring process completed PIU Feb 28, Project office hire/ lease process completed PIU March 31, REOI for ERF manager and PIFIC manager submitted for the Bank clearance PIU Jan 31, 2018

6 Annex 1: List of persons met Economic Relations Division Mrs. Mahmuda Begum, Additional Secretary Mr. Zahid Hossain Munshi, Deputy Secretary Ministry of Commerce Mr. Shubhashish Bose, Secretary Mr. Munshi Shafiul Haque, Additional Secretary Mr. Md. Obaidul Azam, Additional Secretary, PD, EC4J Project Mr. Musleh Uddin, Deputy Chief Mr. Khaled Mamun Chowdhury, Deputy Secretary, DPD, EC4J Project Mr. Md. Abu Sayed Joarder, Deputy Secretary, DPD, EC4J Project Business Promotion Council Mr. Fakir Firoz Ahmmad, Coordinator Mr. Noor Md. Mahbubul Haq, Deputy Coordinator Ms. Ishrat Jahan, Executive Officer, LSBPC Ms. Fathama Nargis, Executive Officer, MPHPBPC Mr. Md. Kamruzzaman, Executive Officer, LEPBPC Department for International Development Ms. Narissa Haider, Deputy Team Leader, Growth and Private Sector Development Mr. Mashfique Ibne Akbar, Private Sector Development Advisor Bangladesh Economic Zones Authority (BEZA) Dr. M. Emdadul Haque, Executive Members Mr. Md. Harunur Rashid, Additional Secretaries Consulting Service International Ltd. Mr. Joseph Strasser, Consultant

OVERALL STATUS AND KEY PROJECT DATA

OVERALL STATUS AND KEY PROJECT DATA Bangladesh: Urban Resilience Project (Cr. 55990) Implementation Support Review October 8 to 12, 2017 Aide Memoire 1. A World Bank Team 1 carried out an Implementation Support Review of the Urban Resilience

More information

PROJECT PREPARATORY TECHNICAL ASSISTANCE

PROJECT PREPARATORY TECHNICAL ASSISTANCE A. Justification PROJECT PREPARATORY TECHNICAL ASSISTANCE 1. A project preparatory technical assistance (PPTA) is required to support the Ministry of New and Renewable Energy (MNRE) and Solar Energy Corporation

More information

Bangladesh: Forest Investment Program (FIP) Technical Mission, October 16-20, 2016 Aide Memoire

Bangladesh: Forest Investment Program (FIP) Technical Mission, October 16-20, 2016 Aide Memoire Bangladesh: Forest Investment Program (FIP) Technical Mission, October 16-20, 2016 Aide Memoire 1. A World Bank team 1 carried out a technical mission to support the Government of Bangladesh (GoB) for

More information

Bangladesh Rural Electricity Transmission and Distribution (T&D) Project (IDA Cr BD) Implementation Review Mission March 15-25, 2015

Bangladesh Rural Electricity Transmission and Distribution (T&D) Project (IDA Cr BD) Implementation Review Mission March 15-25, 2015 Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Bangladesh Rural Electricity Transmission and Distribution (T&D) Project (IDA Cr. 5381-BD)

More information

PROJECT PREPARATORY TECHNICAL ASSISTANCE

PROJECT PREPARATORY TECHNICAL ASSISTANCE 12 Appendix 5 A. Justification PROJECT PREPARATORY TECHNICAL ASSISTANCE 1. The project preparatory technical assistance (PPTA) is needed for preparing the investment program and conducting technical, economic,

More information

PROJECT PREPARATORY TECHNICAL ASSISTANCE

PROJECT PREPARATORY TECHNICAL ASSISTANCE Appendix 3 11 A. Justification PROJECT PREPARATORY TECHNICAL ASSISTANCE 1. The government has identified the priority areas to be covered under the ensuing project. A PPTA is necessary to provide sound

More information

Public Disclosure Copy

Public Disclosure Copy Public Disclosure Authorized AFRICA Ethiopia Finance & Markets Global Practice IBRD/IDA Investment Project Financing FY 2016 Seq No: 4 ARCHIVED on 06-Dec-2017 ISR30229 Implementing Agencies: National Bank

More information

OFFICIAL r0 4 DOCUMENTS

OFFICIAL r0 4 DOCUMENTS Public Disclosure Authorized OFFICIAL r0 4 DOCUMENTS The World Bank 1818 H Street N.W. (202) 473-1000 INTERNATIONAL BANK FOR RECONSTRUCTION AND DEVELOPMENT Washington, D.C. 20433 Cable Address: INTBAFRAD

More information

United Nations Peace Building Fund Grant Agreement

United Nations Peace Building Fund Grant Agreement Public Disclosure Authorized OFFICIAL DOCUMENTS Public Disclosure Authorized GRANT NUMBER TF018255 United Nations Peace Building Fund Grant Agreement (Additional Financing for the Productive Social Safety

More information

Assurance at Country Level: External Audit of Grant Recipients. High Impact Asia Regional Report. GF-OIG August 2013

Assurance at Country Level: External Audit of Grant Recipients. High Impact Asia Regional Report. GF-OIG August 2013 Assurance at Country Level: External Audit of Grant Recipients High Impact Asia Regional Report 20 August 2013 TABLE OF CONTENTS A. EXECUTIVE SUMMARY... 1 B. MESSAGE FROM THE EXECUTIVE DIRECTOR OF THE

More information

FRAMEWORK FINANCING AGREEMENT. (National Highway Development Sector Investment Program Project 1) between ISLAMIC REPUBLIC OF PAKISTAN.

FRAMEWORK FINANCING AGREEMENT. (National Highway Development Sector Investment Program Project 1) between ISLAMIC REPUBLIC OF PAKISTAN. FRAMEWORK FINANCING AGREEMENT (National Highway Development Sector Investment Program Project 1) between ISLAMIC REPUBLIC OF PAKISTAN and ASIAN DEVELOPMENT BANK DATED 29 October 2005 FRAMEWORK FINANCING

More information

Afghanistan Reconstruction Trust Fund Grant Agreement

Afghanistan Reconstruction Trust Fund Grant Agreement Public Disclosure Authorized OFFICIAL DOCUMENTS ARTF GRANT NUMBER TFOAO730 Public Disclosure Authorized Public Disclosure Authorized Afghanistan Reconstruction Trust Fund Grant Agreement (Higher Education

More information

Global Partnership on Output-based Aid Grant Agreement

Global Partnership on Output-based Aid Grant Agreement Public Disclosure Authorized CONFORMED COPY GPOBA GRANT NUMBER TF096551-BD Public Disclosure Authorized Global Partnership on Output-based Aid Grant Agreement (Rural Electrification and Renewable Energy

More information

FOR OFFICIAL USE ONLY RESTRUCTURING PAPER ON A

FOR OFFICIAL USE ONLY RESTRUCTURING PAPER ON A Public Disclosure Authorized Document of The World Bank FOR OFFICIAL USE ONLY Report No: RES22380 Public Disclosure Authorized Public Disclosure Authorized RESTRUCTURING PAPER ON A PROPOSED PROJECT RESTRUCTURING

More information

TERMS OF REFERENCE TECHNICAL COMMITTEE BUSINESS DEVLEOPMENT EXPERT

TERMS OF REFERENCE TECHNICAL COMMITTEE BUSINESS DEVLEOPMENT EXPERT This Trust Fund is funded by the European Union EU Local and Regional Competitiveness Project This Trust Fund is administered by the World Bank TERMS OF REFERENCE TECHNICAL COMMITTEE BUSINESS DEVLEOPMENT

More information

ENHANCED INTEGRATED FRAMEWORK EXECUTIVE SECRETARIAT FOR THE EIF (ES) AND EIF TRUST FUND MANAGER (TFM) PROCEDURES FOR FEASIBILITY STUDIES.

ENHANCED INTEGRATED FRAMEWORK EXECUTIVE SECRETARIAT FOR THE EIF (ES) AND EIF TRUST FUND MANAGER (TFM) PROCEDURES FOR FEASIBILITY STUDIES. ENHANCED INTEGRATED FRAMEWORK EXECUTIVE SECRETARIAT FOR THE EIF (ES) AND EIF TRUST FUND MANAGER (TFM) PROCEDURES FOR FEASIBILITY STUDIES October 2012 Selected EIF countries have requesting the undertaking

More information

Public Disclosure Copy. Implementation Status & Results Report Second Private Sector Competitiveness and Economic Diversification Prj (P144933)

Public Disclosure Copy. Implementation Status & Results Report Second Private Sector Competitiveness and Economic Diversification Prj (P144933) Public Disclosure Authorized AFRICA Lesotho Finance, Competitiveness and Innovation Global Practice IBRD/IDA Investment Project Financing FY 2014 Seq No: 10 ARCHIVED on 08-May-2018 ISR30476 Implementing

More information

Terms of Reference. Consultancy to support the Institutional Strengthening of the Frontier Counties Development Council (FCDC)

Terms of Reference. Consultancy to support the Institutional Strengthening of the Frontier Counties Development Council (FCDC) Terms of Reference Consultancy to support the Institutional Strengthening of the Frontier Counties Development Council (FCDC) 1. Introduction August 2016 to August 2018 1. Supporting Kenya s devolution

More information

OFFICIAL DOCUMENTS I

OFFICIAL DOCUMENTS I Public Disclosure Authorized OFFICIAL DOCUMENTS I GPEF GRANT NUMBER TF016558 Public Disclosure Authorized Global Partnership for Education Grant Agreement (Second Education Sector Support Project) Public

More information

Global Environment Facility Trust Fund Grant Agreement

Global Environment Facility Trust Fund Grant Agreement CONFORMED COPY GEF TRUST FUND GRANT NUMBER TF099857 Global Environment Facility Trust Fund Grant Agreement (Nyika Transfrontier Conservation Area Project) between REPUBLIC OF MALAWI and INTERNATIONAL BANK

More information

Project Administration Instructions

Project Administration Instructions Project Administration Instructions PAI 1.01 Page 1 of 5 INITIAL PROJECT ADMINISTRATION ACTIVITIES A. Introduction 1. The Project Administration Instructions (PAIs) outline ADB s policies and procedures

More information

INTERNATIONAL AGRICULTURE AND FORESTRY EXPERT TERMS OF REFERENCE

INTERNATIONAL AGRICULTURE AND FORESTRY EXPERT TERMS OF REFERENCE INTERNATIONAL AGRICULTURE AND FORESTRY EXPERT TERMS OF REFERENCE Country/Location: UNDP Office, Vientiane, Lao PDR Description of assignment: Short Term to develop the Environmental Impact Assessment Agriculture

More information

DIME-GAFSP First Quarterly Progress Report

DIME-GAFSP First Quarterly Progress Report DIME-GAFSP First Quarterly Progress Report Feburary 24, 2012 The World Bank s Development Impact Evaluation Initiative (DIME) has been contracted to lead in-depth impact evaluations on a subset of GAFSP

More information

GRANT AGREEMENT (ADB Strategic Climate Fund) (Greater Mekong Subregion Biodiversity Conservation Corridors Project Additional Financing)

GRANT AGREEMENT (ADB Strategic Climate Fund) (Greater Mekong Subregion Biodiversity Conservation Corridors Project Additional Financing) GRANT NUMBER 0426-CAM (SCF) GRANT AGREEMENT (ADB Strategic Climate Fund) (Greater Mekong Subregion Biodiversity Conservation Corridors Project Additional Financing) (Cambodia Component) between KINGDOM

More information

Final MRP Endorsement Date. Implementing Country/Technical Partner. Comments/Remarks

Final MRP Endorsement Date. Implementing Country/Technical Partner. Comments/Remarks Implementing Country/Technical Partner Argentina Final MRP Endorsement Date Planned: intersessional period prior to PA19 Comments/Remarks Argentina joined as a PMR Implementing Country Participant at PA15

More information

EU Grant Agreement DOC8UMEW. Public Disclosure Authorized GRANT NUMBER TF0A2379. Public Disclosure Authorized. (Access to Sustainable Energy Project)

EU Grant Agreement DOC8UMEW. Public Disclosure Authorized GRANT NUMBER TF0A2379. Public Disclosure Authorized. (Access to Sustainable Energy Project) Public Disclosure Authorized DOC8UMEW GRANT NUMBER TF0A2379 Public Disclosure Authorized Public Disclosure Authorized EU Grant Agreement (Access to Sustainable Energy Project) between INTERNATIONAL BANK

More information

Public Disclosure Copy

Public Disclosure Copy Public Disclosure Authorized AFRICA Ethiopia Finance & Markets Global Practice IBRD/IDA Investment Project Financing FY 2016 Seq No: 3 ARCHIVED on 25-May-2017 ISR27984 Implementing Agencies: National Bank

More information

Assurance at Country Level: External Audit of Grant Recipients. High Impact Africa 2 Regional Report. GF-OIG August 2013

Assurance at Country Level: External Audit of Grant Recipients. High Impact Africa 2 Regional Report. GF-OIG August 2013 Assurance at Country Level: External Audit of Grant Recipients High Impact Africa 2 Regional Report 20 August 2013 TABLE OF CONTENTS A. EXECUTIVE SUMMARY... 1 B. MESSAGE FROM THE EXECUTIVE DIRECTOR OF

More information

Aide-Memoire for Scaling-up Renewable Energy Program in Low Income Countries (SREP) Joint MDB Scoping Mission to Zambia April 8-10, 2015

Aide-Memoire for Scaling-up Renewable Energy Program in Low Income Countries (SREP) Joint MDB Scoping Mission to Zambia April 8-10, 2015 I. Introduction Aide-Memoire for Scaling-up Renewable Energy Program in Low Income Countries (SREP) Joint MDB Scoping Mission to Zambia April 8-10, 2015 1. A joint World Bank Group (WBG), including the

More information

Public Private Partnerships (PPPs) to promote Cluster Development and Research and Skills Development. PPP Implementation Manual

Public Private Partnerships (PPPs) to promote Cluster Development and Research and Skills Development. PPP Implementation Manual Public Private Partnerships (PPPs) to promote Cluster Development and Research and Skills Development PPP Implementation Manual May, 2015 i Contents List of Acronyms... iii Clarification of Terms... iv

More information

This document is being disclosed to the public in accordance with ADB s Public Communications Policy 2011.

This document is being disclosed to the public in accordance with ADB s Public Communications Policy 2011. Technical Assistance Report Project Number: 51336-001 Knowledge and Support Technical Assistance (KSTA) February 2018 Capacity Building Support for Asia-Pacific Economic Cooperation Financial Regulators

More information

Financing Agreement. (Zanzibar Basic Education Improvement Project) between THE UNITED REPUBLIC OF TANZANIA. and

Financing Agreement. (Zanzibar Basic Education Improvement Project) between THE UNITED REPUBLIC OF TANZANIA. and Public Disclosure Authorized CONFORMED COPY CREDIT NUMBER 4293-TA Public Disclosure Authorized Financing Agreement (Zanzibar Basic Education Improvement Project) between Public Disclosure Authorized THE

More information

Argentine Republic's Readiness Preparation - Readiness Fund for Forest Carbon Partnership Facility (FCPF) FCPFR - Forest Carbon Partnership Facility

Argentine Republic's Readiness Preparation - Readiness Fund for Forest Carbon Partnership Facility (FCPF) FCPFR - Forest Carbon Partnership Facility Assignment: TF019086 Argentine Republic's Readiness Preparation - Readiness Fund for Forest Carbon Partnership Facility (FCPF) FCPFR - Forest Carbon Partnership Facility Task Team Leader: 00000232745 Approving

More information

Lao PDR: Trade Development Facility Project Procurement Plan (April 2012 March 2013)

Lao PDR: Trade Development Facility Project Procurement Plan (April 2012 March 2013) I. General Lao PDR: Trade Development Facility Project Procurement Plan (April 2012 March 2013) 1. Project information: Country: Lao P.D.R. Borrower/Recipient: Lao P.D.R. Project Name: Trade Development

More information

REQUIRED DOCUMENT FROM HIRING UNIT

REQUIRED DOCUMENT FROM HIRING UNIT Terms of reference GENERAL INFORMATION Title: Energy Efficiency Project Development Specialist Project Name : Advancing Indonesia s Lighting Market to High Efficient Technologies (ADLIGHT) Reports to:

More information

Terms of Reference (ToR) Jordan Innovative Startups and SMEs Fund (ISSF Company) Manager

Terms of Reference (ToR) Jordan Innovative Startups and SMEs Fund (ISSF Company) Manager Terms of Reference (ToR) Jordan Innovative Startups and SMEs Fund (ISSF Company) Manager I. ASSIGNMENT BACKGROUND 1. The Innovative Startups Fund Company (ISSF Company) aims to increase early stage equity

More information

Use of External Consultants

Use of External Consultants Summary Introduction The Department of Transportation and Works (the Department) is responsible for the administration, supervision, control, regulation, management and direction of all matters relating

More information

SCOTTISH GOVERNMENT FUNDING CONDITIONS FOR DELIVERING PROJECTS THROUGH THE NON PROFIT DISTRIBUTING MODEL

SCOTTISH GOVERNMENT FUNDING CONDITIONS FOR DELIVERING PROJECTS THROUGH THE NON PROFIT DISTRIBUTING MODEL Acting Director-General Health & Social Careand Chief Executive NHSScotland Derek Feeley T: 0131-244 2410 F: 0131-244 2162 E: dghsc@scotland.gslgov.uk ~ The Scottish Government To: NHS Board Chief Executives

More information

Multi-Donor Trust Fund for Aceh and North Sumatra Grant Agreement

Multi-Donor Trust Fund for Aceh and North Sumatra Grant Agreement Public Disclosure Authorized CONFORMED COPY GRANT NUMBER TF057657 Public Disclosure Authorized Public Disclosure Authorized Multi-Donor Trust Fund for Aceh and North Sumatra Grant Agreement (Infrastructure

More information

Mongolia: Integrated Livelihoods Improvement and Sustainable Tourism in Khuvsgul Lake National Park Project

Mongolia: Integrated Livelihoods Improvement and Sustainable Tourism in Khuvsgul Lake National Park Project Semi-Annual Progress Report June 2016 Mongolia: Integrated Livelihoods Improvement and Sustainable Tourism in Khuvsgul Lake National Park Project Prepared by the project management unit and project implementation

More information

Project Information Document/ Integrated Safeguards Data Sheet (PID/ISDS)

Project Information Document/ Integrated Safeguards Data Sheet (PID/ISDS) Project Information Document/ Integrated Safeguards Data Sheet (PID/ISDS) Concept Stage Date Prepared/Updated: 24-Mar-2017 Report : PIDISDSC20204 Public Disclosure Authorized Public Disclosure Authorized

More information

PMR PROJECT IMPLEMENTATION STATUS REPORT (ISR)

PMR PROJECT IMPLEMENTATION STATUS REPORT (ISR) 1. SUMMARY INFORMATION Implementing Country/Technical Partner: PMR PROJECT IMPLEMENTATION STATUS REPORT (ISR) South Africa. Reporting Period: From 1/10/2017 to 30/09/2018 Report Date: 4 October 2018 Implementing

More information

CIVIL ENGINEER EXPERT

CIVIL ENGINEER EXPERT This Trust Fund is funded by the European Union EU Local and Regional Competitiveness Project This Trust Fund is administered by the World Bank TERMS OF REFERENCE TECHNICAL COMMITTEE CIVIL ENGINEER EXPERT

More information

TRUST FUND FOR STATISTICAL CAPACITY BUILDING GUIDELINES AND PROCEDURES TFSCB ADMINISTRATION UNIT

TRUST FUND FOR STATISTICAL CAPACITY BUILDING GUIDELINES AND PROCEDURES TFSCB ADMINISTRATION UNIT TRUST FUND FOR STATISTICAL CAPACITY BUILDING GUIDELINES AND PROCEDURES TFSCB ADMINISTRATION UNIT DEVELOPMENT DATA GROUP THE WORLD BANK OCTOBER 2015 TRUST FUND FOR STATISTICAL CAPACITY BUILDING (TFSCB)

More information

Grant Agreement for Islamic Republic of Pakistan's Readiness Preparation Proposal Readiness Fund of the FCPF Grant No. TF018696

Grant Agreement for Islamic Republic of Pakistan's Readiness Preparation Proposal Readiness Fund of the FCPF Grant No. TF018696 The World Bank INTERNATIONAL BANK FOR RECONSTRUCTION AND DEVELOPMENT INTERNATIONAL DEVELOPMENT ASSOCIATION 1818 H Street N.W. Washington, D.C. 20433 U.S.A. (202) 473-1000 Cable Address: INTBAFRAD Cable

More information

Fiji Electricity Authority. MR 323/2017 Feasibility Study of Pumped Storage Hydropower at Monasavu Request for Prices

Fiji Electricity Authority. MR 323/2017 Feasibility Study of Pumped Storage Hydropower at Monasavu Request for Prices Fiji Electricity Authority MR 323/2017 Feasibility Study of Pumped Storage Hydropower at Monasavu Request for Prices November 2017 Fiji Electricity Authority Private Bag Suva Fiji Tel: 679-3311133 Fax:

More information

Grant Agreement for Republic of Sudan's Readiness Preparation Proposal Readiness Fund of the FCPF Grant No. TF

Grant Agreement for Republic of Sudan's Readiness Preparation Proposal Readiness Fund of the FCPF Grant No. TF The World Bank INTERNATIONAL BANK FOR RECONSTRUCTION AND DEVELOPMENT INTERNATIONAL DEVELOPMENT ASSOCIATION 1818 H Street NW. Washington, D.C. 20433 U.S.A. (202) 473-1000 Cable Address: INTBAFRAD Cable

More information

EU Local and Regional Competitiveness Project TERMS OF REFERENCE TECHNICAL COMMITTEE ARCHITECT EXPERT

EU Local and Regional Competitiveness Project TERMS OF REFERENCE TECHNICAL COMMITTEE ARCHITECT EXPERT This Trust Fund is funded by the European Union EU Local and Regional Competitiveness Project This Trust Fund is administered by the World Bank TERMS OF REFERENCE TECHNICAL COMMITTEE ARCHITECT EXPERT LOCAL

More information

Internal Grant Committee Meeting 3 November 2015

Internal Grant Committee Meeting 3 November 2015 Ministry of Foreign Affairs - MENA File no.: 2015-25992 Internal Grant Committee Meeting 3 November 2015 Agenda Item no.: 1 1. Title: Lebanon Syrian Crisis Trust Fund 2. Partners: World Bank Multi-Donor

More information

Loan No INO: POOR FARMERS INCOME IMPROVEMENT THROUGH INNOVATION PROJECT. INCEPTION MISSION May 21 June 5, 2003 MEMORANDUM OF UNDERSTANDING

Loan No INO: POOR FARMERS INCOME IMPROVEMENT THROUGH INNOVATION PROJECT. INCEPTION MISSION May 21 June 5, 2003 MEMORANDUM OF UNDERSTANDING Loan No. 1909-INO: POOR FARMERS INCOME IMPROVEMENT THROUGH INNOVATION PROJECT I. INTRODUCTION INCEPTION MISSION May 21 June 5, 2003 MEMORANDUM OF UNDERSTANDING 1. An ADB Inception Mission (the Mission)

More information

between ARAB REPUBLIC OF EGYPT and

between ARAB REPUBLIC OF EGYPT and Public Disclosure Authorized GRANT NUMBER TF0A1553 Public Disclosure Authorized MIDDLE EAST AND NORTH AFRICA TRANSITION FUND Grant Agreement Public Disclosure Authorized Public Disclosure Authorized EQUAL

More information

TERMS OF REFERENCE FOR CONSULTANTS

TERMS OF REFERENCE FOR CONSULTANTS TERMS OF REFERENCE FOR CONSULTANTS A. Consulting Firm The Asian Development Bank (ADB) will engage a consulting firm in accordance with its Guidelines on the Use of Consultants (2013, as amended from time

More information

GOVERNMENT OF MAURITIUS MANUFACTURING AND SERVICES DEVELOPMENT AND COMPETITIVENESS PROJECT (MSDC) LOAN NO MU PROCUREMENT PLAN FOR THE PERIOD

GOVERNMENT OF MAURITIUS MANUFACTURING AND SERVICES DEVELOPMENT AND COMPETITIVENESS PROJECT (MSDC) LOAN NO MU PROCUREMENT PLAN FOR THE PERIOD Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized GOVERNMENT OF MAURITIUS MINISTRY OF BUSINESS, ENTERPRISES AND COOPERATIVES MANUFACTURING

More information

PROJECT INFORMATION DOCUMENT (PID) CONCEPT STAGE Report No.: AB5998 Project Name. Leveraging ICT for Governance, Growth and Employment Project Region

PROJECT INFORMATION DOCUMENT (PID) CONCEPT STAGE Report No.: AB5998 Project Name. Leveraging ICT for Governance, Growth and Employment Project Region Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized PROJECT INFORMATION DOCUMENT (PID) CONCEPT STAGE Report No.: AB5998 Project Name Leveraging

More information

OFFICIAL DOCUMENTS. Global Partnership for Education Fund Grant Agreement

OFFICIAL DOCUMENTS. Global Partnership for Education Fund Grant Agreement Public Disclosure Authorized OFFICIAL DOCUMENTS GRANT NUMBER TF0A4619 Public Disclosure Authorized Public Disclosure Authorized Global Partnership for Education Fund Grant Agreement (Additional Financing

More information

Office of Climate Change Guyana September, TRANSITIONING TO NATIONAL ENERGY SECURITY: Bartica as a Model Green Town TERMS OF REFERENCE

Office of Climate Change Guyana September, TRANSITIONING TO NATIONAL ENERGY SECURITY: Bartica as a Model Green Town TERMS OF REFERENCE Office of Climate Change Guyana September, 2017 TRANSITIONING TO NATIONAL ENERGY SECURITY: Bartica as a Model Green Town TERMS OF REFERENCE ENERGY AUDIT OF PUBLIC INSTITUTIONS, FACILITIES AND STREET LIGHTING

More information

FIRST QUARTER (JANUARY - MARCH, 2012) PROGRESS REPORT - BUREAU OF NATIONAL FISHERIES, LIBERIA

FIRST QUARTER (JANUARY - MARCH, 2012) PROGRESS REPORT - BUREAU OF NATIONAL FISHERIES, LIBERIA FIRST QUARTER (JANUARY - MARCH, 2012) PROGRESS REPORT - BUREAU OF NATIONAL FISHERIES, LIBERIA Activities Sub-activities Achievements and status Challenges and constraints Recommended ations and by whom

More information

Terms of Reference AUDIT OF SOLAR HOME SYSTEMS PROJECT. The assignment is to engage an auditor for the following.

Terms of Reference AUDIT OF SOLAR HOME SYSTEMS PROJECT. The assignment is to engage an auditor for the following. Note: Bank solar home systems projects receiving grant funds from the Global Environment Facility (GEF) are normally required to have their records and accounts audited by an independent entity each fiscal

More information

Letter No. CD-064/INIS/III/2014 March 26, 2014

Letter No. CD-064/INIS/III/2014 March 26, 2014 Public Disclosure Authorized THE WORLD BANK I BANK DUNIA Sharing Development Solutions for an Emerging Indonesia Rodrigo A. Chaves Country Director, Indonesia Letter No. CD-064/INIS/III/2014 March 26,

More information

CITY OF MIAMI SECTION 3 ECONOMIC OPPORTUNITY PLAN QUESTIONS

CITY OF MIAMI SECTION 3 ECONOMIC OPPORTUNITY PLAN QUESTIONS CITY OF MIAMI SECTION 3 ECONOMIC OPPORTUNITY PLAN QUESTIONS The Section 3 Economic Opportunity Plan must describe the proposed strategies for achieving the Section 3 training and employment numerical goals,

More information

TA: TRANSIT-ORIENTED DEVELOPMENT AND IMPROVED TRAFFIC MANAGEMENT IN GCC

TA: TRANSIT-ORIENTED DEVELOPMENT AND IMPROVED TRAFFIC MANAGEMENT IN GCC Greater Dhaka Sustainable Urban Transport Project (RRP BAN 42169) TA: TRANSIT-ORIENTED DEVELOPMENT AND IMPROVED TRAFFIC MANAGEMENT IN GCC A. TA Description 1. The Government of Bangladesh has requested

More information

Financing Agreement CONFORMED COPY GRANT NUMBER H603-AF. (Third Emergency National Solidarity Project) between ISLAMIC REPUBLIC OF AFGHANISTAN.

Financing Agreement CONFORMED COPY GRANT NUMBER H603-AF. (Third Emergency National Solidarity Project) between ISLAMIC REPUBLIC OF AFGHANISTAN. Public Disclosure Authorized CONFORMED COPY GRANT NUMBER H603-AF Public Disclosure Authorized Financing Agreement (Third Emergency National Solidarity Project) between Public Disclosure Authorized ISLAMIC

More information

Rajasthan Urban Sector Development Program

Rajasthan Urban Sector Development Program India: Rajasthan Urban Sector Development Program Project Name Rajasthan Urban Sector Development Program Project Number 42267-026 Country Project Status Project Type / Modality of Assistance Source of

More information

DOCUMENTS GPOBA GRANT NUMBER TF Global Partnership on Output-based Aid. Grant Agreement

DOCUMENTS GPOBA GRANT NUMBER TF Global Partnership on Output-based Aid. Grant Agreement GPOBA GRANT NUMBER TF092629 DOCUMENTS Global Partnership on Output-based Aid Grant Agreement (Extending Telecommunications in Rural Indonesia Project) between REPUBLIC OF INDONESIA and INTERNATIONAL BANK

More information

The World Bank Sustainable Rural Sanitation Services Program for Results (P154112)

The World Bank Sustainable Rural Sanitation Services Program for Results (P154112) Public Disclosure Authorized MIDDLE EAST AND NORTH AFRICA Egypt, Arab Republic of Water Global Practice IBRD/IDA Program-for-Results FY 2016 Seq No: 1 ARCHIVED on 05-Nov-2015 ISR21200 Implementing Agencies:

More information

Trust Fund Grant Agreement

Trust Fund Grant Agreement Public Disclosure Authorized Public Disclosure Authorized GRANT NUMBER TF016392 Trust Fund Grant Agreement (Co-financing of the Women Entrepreneurship Development Project) Public Disclosure Authorized

More information

AEITI Country Work Plan Amended

AEITI Country Work Plan Amended re Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Extractive Industries Transparency Initiative (AEITI) Islamic Republic of Ministry of Finance AEITI

More information

World Bank - Grant Reporting and Monitoring (GRM) Report. Report to Donor. Ref. TF0A2303 Reporting Period: 07/01/2016 to 06/30/2017

World Bank - Grant Reporting and Monitoring (GRM) Report. Report to Donor. Ref. TF0A2303 Reporting Period: 07/01/2016 to 06/30/2017 Assignment: TF0A2303 Third Grant Agreement for Costa Rica's Readiness Preparation Proposal - Readiness Fund of Forest Carbon Partnership Facility (FCPF) FCPFR - Forest Carbon Partnership Facility Task

More information

Report on EIA twinning project between Lao PDR and Japan

Report on EIA twinning project between Lao PDR and Japan Report on EIA twinning project between Lao PDR and Japan TA 7566-REG: Strengthening and Use of Country Safeguards System: Sub-project: EIA Clearinghouse and Capacity Strengthening through Twinning Consultation

More information

GRANT APPLICATION FORM for investment grants (INV GAF)

GRANT APPLICATION FORM for investment grants (INV GAF) IDENTITY OF THE PROJECT 1 Blending Facility WBIF 2 Grant Number/code 3 Date of Steering Committee 4 Sector(s) 5 CRS-code 6 Beneficiary country 7 Name of project 8 Lead International Financial Institution

More information

Resettlement Planning Document

Resettlement Planning Document Resettlement Planning Document Resettlement Framework Document Stage: Final Project Number: 40247 May 2008 Republic of Indonesia: Rural Infrastructure Support for PNPM Mandiri Prepared by Directorate General

More information

Avian and Human Influenza Facility Grant Agreement

Avian and Human Influenza Facility Grant Agreement Public Disclosure Authorized CONFORMED COPY AHI FACILITY GRANT NUMBER TF057747-VN Public Disclosure Authorized Avian and Human Influenza Facility Grant Agreement Public Disclosure Authorized (Vietnam Avian

More information

Ethiopia: FCPF Readiness Grant FCPFR - FOREST CARBON PARTNERSHIP FACILITY

Ethiopia: FCPF Readiness Grant FCPFR - FOREST CARBON PARTNERSHIP FACILITY Assignment: TF013450 Ethiopia: FCPF Readiness Grant FCPFR - FOREST CARBON PARTNERSHIP FACILITY Task Team Leader: 00000269425 Approving Manager: 00000086248 - Stephen Danyo - Magdolna Lovei Summary Information

More information

REQUEST FOR EXPRESS OF INTEREST (REOI)

REQUEST FOR EXPRESS OF INTEREST (REOI) THE SOCIALIST REPUBLIC OF VIETNAM MINISTRY OF EDUCATION AND TRAINING Loan No.: 2750-VIE/2751-VIE University of Science and Technology of Hanoi Development (New Model University) Project REQUEST FOR EXPRESS

More information

OFFICIAL DOCUMENTS. Global Agriculture and Food Security Program Trust Fund Grant Agreement

OFFICIAL DOCUMENTS. Global Agriculture and Food Security Program Trust Fund Grant Agreement Public Disclosure Authorized OFFICIAL DOCUMENTS GAFSP GRANT NUMBER TF0A2869 Public Disclosure Authorized Public Disclosure Authorized Global Agriculture and Food Security Program Trust Fund Grant Agreement

More information

Request for Information and Qualifications RFIQ No Facility Asset Management Consulting Services

Request for Information and Qualifications RFIQ No Facility Asset Management Consulting Services City of Coquitlam Request for Information and Qualifications RFIQ No. 17-11-04 Facility Asset Management Consulting Services Issue Date: November 24, 2017 File #: 03-1220-20/17-11-04/1 Doc #: 2764584.v4

More information

Unsolicited Proposals Guidelines. Unsolicited Proposals Guidelines

Unsolicited Proposals Guidelines. Unsolicited Proposals Guidelines Unsolicited Proposals Guidelines 1 TABLE OF CONTENTS 1. PURPOSE... 3 2. CRITERIA FOR CONSIDERATION OF AN UNSOLICITED PROPOSAL... 3 3. SIMULTANEOUS PROPOSAL... 5 4. UNACCEPTABLE UNSOLICITED PROPOSALS. 5

More information

Global Partnership on Output-based Aid Grant Agreement

Global Partnership on Output-based Aid Grant Agreement Global Partnership on Output-based Aid GRANT NUMBERS TF057614 AND TF057615 Global Partnership on Output-based Aid Grant Agreement (Kenya - Microfinance for Community-Managed Water Projects) between K-REP

More information

THE WORLD BANK IBRD *IDA I WORLD BANKGROUP -

THE WORLD BANK IBRD *IDA I WORLD BANKGROUP - Public Disclosure Authorized J. HUMBERTO LOPEZ Director, Central America Latin America and the Caribbean Region THE WORLD BANK IBRD *IDA I WORLD BANKGROUP - June 20, 2016 Public Disclosure Authorized Public

More information

GRANT AGREEMENT (Special Operations) (Hairatan to Mazar-e-Sharif Railway Project) between ISLAMIC REPUBLIC OF AFGHANISTAN. and ASIAN DEVELOPMENT BANK

GRANT AGREEMENT (Special Operations) (Hairatan to Mazar-e-Sharif Railway Project) between ISLAMIC REPUBLIC OF AFGHANISTAN. and ASIAN DEVELOPMENT BANK GRANT NUMBER 0161-AFG(SF) GRANT AGREEMENT (Special Operations) (Hairatan to Mazar-e-Sharif Railway Project) between ISLAMIC REPUBLIC OF AFGHANISTAN and ASIAN DEVELOPMENT BANK DATED 30 SEPTEMBER 2009 GAS:

More information

ASEAN SECRETARIAT. Request for Proposal. Provision of Developing Document Classification/Reference System (EXTENDED)

ASEAN SECRETARIAT. Request for Proposal. Provision of Developing Document Classification/Reference System (EXTENDED) ASEAN SECRETARIAT Request for Proposal Provision of Developing Document System (EXTENDED) PROPOSAL MUST BE RECEIVED BY Thursday, 22 February 2018 before 12.00PM DELIVER PROPOSAL TO: ASEAN Secretariat Jl.

More information

Review of the initial proposal approval process

Review of the initial proposal approval process Meeting of the Board 5 6 July 2017 Songdo, Incheon, Republic of Korea Provisional agenda item 15 GCF/B.17/18 5 July 2017 Review of the initial proposal approval process Summary This document presents a

More information

II. Background Information

II. Background Information II. Background Information Context of the REDD+ initiative: Indonesia is the third largest emitter of CO2 and the world s largest emitter from agriculture, forestry and other land use. Over the past five

More information

Financing Agreement CONFORMED COPY CREDIT NUMBER 4322-MOT. (Sustainable Tourism Development Project) between REPUBLIC OF MONTENEGRO.

Financing Agreement CONFORMED COPY CREDIT NUMBER 4322-MOT. (Sustainable Tourism Development Project) between REPUBLIC OF MONTENEGRO. Public Disclosure Authorized CONFORMED COPY CREDIT NUMBER 4322-MOT Public Disclosure Authorized Financing Agreement Public Disclosure Authorized (Sustainable Tourism Development Project) between REPUBLIC

More information

GOVERNMENT OF MAHARASHTRA

GOVERNMENT OF MAHARASHTRA GOVERNMENT OF MAHARASHTRA Project Management Unit (PMU), Agribusiness Infrastructure Development Investment Program (AIDIP) Maharashtra State Agriculture Marketing Board (MSAMB) PUNE 411 037 REQUEST FOR

More information

Rural Enterprise Finance Project. Negotiated financing agreement

Rural Enterprise Finance Project. Negotiated financing agreement Document: EB 2018/123/R.8/Sup.1 Agenda: 5(a)(i) Date: 6 April 2018 Distribution: Public Original: English E Republic of Mozambique Rural Enterprise Finance Project Negotiated financing agreement Executive

More information

Instructions to Bidders. Thailand Petroleum Bidding Round 2018 for Offshore Block G1/61

Instructions to Bidders. Thailand Petroleum Bidding Round 2018 for Offshore Block G1/61 Attachment 2 THAILAND PETROLEUM BIDDING ROUND 2018 FOR OFFSHORE BLOCK G1/61 Instructions to Bidders Thailand Petroleum Bidding Round 2018 for Offshore Block G1/61 Disclaimer This Instructions to Bidders

More information

UNDP-GEF Guidance GEF Annual Monitoring Process

UNDP-GEF Guidance GEF Annual Monitoring Process UNDP-GEF Guidance 2017 GEF Annual Monitoring Process Contents A. Project-level reports to be submitted as part of the 2017 GEF Annual Monitoring Process... 1 B. PIR: 2017 deadlines... 2 C. 2017 PIR: changes,

More information

Lao PDR Second Global Partnership for Education (GPE II) Project Implementation Support Mission Aide-Memoire (October 5 9, 2015)

Lao PDR Second Global Partnership for Education (GPE II) Project Implementation Support Mission Aide-Memoire (October 5 9, 2015) Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Key Project Data Original Financing Lao PDR Second Global Partnership for Education (GPE

More information

Costa Rica's Readiness Preparation Proposal Readiness Fund of the FCPF FCPFR - FOREST CARBON PARTNERSHIP FACILITY

Costa Rica's Readiness Preparation Proposal Readiness Fund of the FCPF FCPFR - FOREST CARBON PARTNERSHIP FACILITY Assignment: TF012692 Costa Rica's Readiness Preparation Proposal Readiness Fund of the FCPF FCPFR - FOREST CARBON PARTNERSHIP FACILITY Task Team Leader: 00000248567 Approving Manager: 00000483596 - Erick

More information

CONTRACTS DEPARTMENT INVITATION FOR EXPRESSION OF INVITATION EOI. For

CONTRACTS DEPARTMENT INVITATION FOR EXPRESSION OF INVITATION EOI. For ENERGY EFFICIENCY SERVICES LIMITED (A JV of PSUs of Ministry of Power, Govt. of India) A-13, IWAI Building, 4 th & 5 th Floors, Sector-1, NOIDA - 201 301. CONTRACTS DEPARTMENT INVITATION FOR EXPRESSION

More information

Fee Structure for Agencies: Part I

Fee Structure for Agencies: Part I GEF Council Meeting June 5 7, 2012 Washington, D.C. GEF/C.42/08 May 7, 2012 Agenda Item 15 Fee Structure for Agencies: Part I Recommended Council Decision The Council, having considered document GEF/C.42/08,

More information

Project Design Advance. Nauru: Port Development Project. Project Number: December 2015

Project Design Advance. Nauru: Port Development Project. Project Number: December 2015 Project Design Advance Project Number: 48480-002 December 2015 Nauru: Port Development Project This document is being disclosed to the public in accordance with ADB s Public Communications Policy 2011.

More information

Papua New Guinea: Implementation of the Electricity Industry Policy

Papua New Guinea: Implementation of the Electricity Industry Policy Technical Assistance Report Project Number: 46012 December 2012 Papua New Guinea: Implementation of the Electricity Industry Policy The views expressed herein are those of the consultant and do not necessarily

More information

March 9, Honourable Winston Dookeran Minister of Finance Eric Williams Finance Building Independence Square Port of Spain Trinidad and Tobago

March 9, Honourable Winston Dookeran Minister of Finance Eric Williams Finance Building Independence Square Port of Spain Trinidad and Tobago Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized OFM'CIAL (116 3Y) The World Bank e NW. (202) 473-1000 INTERNATIONAL BANK FOR RECONSTRUCTION

More information

Joint FIAS/World Bank FIJI investment approvals reform program

Joint FIAS/World Bank FIJI investment approvals reform program Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Joint FIAS/World Bank FIJI investment approvals reform program A donor update document 27 May 2005 Public Disclosure

More information

Ref: AIDC/CC/KP/1/2506 Date: 18/07/2017. CORIGENDUM No. II

Ref: AIDC/CC/KP/1/2506 Date: 18/07/2017. CORIGENDUM No. II Ref: AIDC/CC/KP/1/2506 Date: 18/07/2017 CORIGENDUM II Reference: Request for Proposal (RFP) for hiring of Knowledge Partner for Industries & Commerce Department, Government of Assam dated (Tender Reference

More information

(Ist Phase 18 months )

(Ist Phase 18 months ) World Bank Assisted National Agricultural Higher Education Project Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Education Division Indian Council of Agricultural

More information

The World Bank Integrated Growth Poles and Corridor Project 2 (P113971)

The World Bank Integrated Growth Poles and Corridor Project 2 (P113971) Public Disclosure Authorized AFRICA Madagascar Trade & Competitiveness Global Practice IBRD/IDA Investment Project Financing FY 2015 Seq No: 6 ARCHIVED on 27-Dec-2017 ISR30958 Implementing Agencies: Ministry

More information

The World Bank Kenya GPE Primary Education Development Project (P146797)

The World Bank Kenya GPE Primary Education Development Project (P146797) Public Disclosure Authorized AFRICA Kenya Education Global Practice Recipient Executed Activities Investment Project Financing FY 2015 Seq No: 4 ARCHIVED on 15-Feb-2017 ISR26822 Implementing Agencies:

More information