1 FIRST QUARTER (JANUARY - MARCH, 2012) PROGRESS REPORT - BUREAU OF NATIONAL FISHERIES, LIBERIA Activities Sub-activities Achievements and status Challenges and constraints Recommended ations and by whom Component 1 Good governance and sustainable management of the fisheries SUB-COMPONENT 1.1 Development of the capacity, rules, procedures and practices for good governance of the fisheries Strengthening of policy and regulatory framework for use of the fish resources i. Development of long-term policy vision and institutional arrangements, including MCS plans and strategies As part of the on-going policy consultative process the first fisheries and aquaculture dialogue was held in Monrovia from 15th to 17th February, The workshop brought together 25 major fisheries stakeholders to share ideas on long term fisheries policy. The draft report was prepared and reviewed for finalization. NFDS to submit workshop final report for circulation ii. New Fisheries Act is passed At the policy workshop a presentation was made on the status of the New Fisheries Act. The general outline was shown to be dependent on the policy statements and strategies that would be formulated by the consultative processes. Accordingly, later the Fisheries Regulations would be revised to conform to the New Act when completed. NFDS to complete policy document before initiating the preparation and passing of Act. iii. Commencement of work by firm to research into social and economic benefits of access agreement Not yet initiated iv. External training in governance and policy for 5 BNF staff (2 long and 3 short courses) 2 staff of BNF were nominated by the Ministry of Agriculture for Master of Science programs at the Department of Fisheries and Oceanography of the University of Ghana: one for fisheries management; and the other for coastal management. 3 other BNF staff were proposed for short courses at the Wageningen Centre for Development Innovation in the Netherlands for training in the echosystem approach to fisheries and fisheries governance. The short courses are awaiting the TTL review and no objection. Challenges in securing TTL to give no objection for short institutions in the sub-region courses. offering the desired programs
2 External training in maritime law and law of the sea for 2 legal persons One of the Ministry's nominees for the Masters of laws program, Elizabeth-Rose Amidjogbe received admission to the Institute of Intermational Maritime Law in Malta. The documents were submitted to the TTL for no objection to proceed with the arrangements for placements. There was still no news from the other nominated candidate. Still one nominee could not secure admission TTL to give no objection for course. v. Human capacity building (on the job and formal lectures) vi. Development and management of a website to enhance transparency in fisheries management vii. Declaration of country s Exclusive Economic Zone (EEZ) in the sea, with UNCLOS viii. Facilitation of implementation of Fisheries Management Advice by the Minister of Agriculture in support of application of the New Fisheries Regulations, 2010 as follows: Lectures were given by the co-management consultant on strategic planning and certificates awarded to BNF/WARFP staff who successfully completed the lecture series. The website was up but final touches including proof reading, checking the contents of other linked sites were being undertaken to enable the official commissioning of the website on the 12th of April at the Ministry of Agriculture. The Executive Order for declaration of the maritime zones of Liberia was signed on the 12th of January by the President. By close of the quarter, the National Oil Company of Liberia being the secretariat of the Maritime Zones Commission was advised by the project to further seek international recognition by getting DOALAS to gazete the declaration. BNF was still in the process of vetting for approval a request for fishing licenses for 21 vessels submitted by an agency called the Mbambali Fishing Company. Due deligence revealed that 6 of the vessels were implicated previously for illegal fishing which was therefore making the approval processes problematic. Final decision was expected in the first week of April. Delay caused by absence of website consultant Lack of knowledgeof the processes for declaration by NOCAL, the Secretariat to the Liberia Maritime Zone Declaration Commission is delaying the process How to deal with the vessels implicated in illegal fishing is delaying the approval process Website development team to make final preparations for outdooring on 12th April at the conference room of Ministry of Agriculture NOCAL to work with Ministry of Foreign Affairs for gazetting of maritime declaration by Liberia The license committee required to request for damages/reparations for fish stocks caught illegally to pave way for licensing for this year
3 1.1.2 Registration of all fishing vessels i. Registration of fishing vessels, data input, analyses, restitution and finalization of database on vessel registration Registration of industrial fishing vessels commenced and so far only 2 have been registered. Other requests were being considered. The artisanal register was being reviewed to reflect additional data colleced. A plan was been formulated for the data to be managed using Geographical Information Systems (GIS). Contact was being made with the Centre for Remote Sensing and Geographical Information Systems (CERGIS) of the University of Ghana. It is expected that new maps of the counties and Liberia in general would be produced showing fishing villages using the GIS. Contact to be made by Coordinator with CERGIS on introduction of GIS and training opportunities Assessment of the status of key fish stocks i. Evaluation of technical and financial proposals completed for selection of international university for long-term contract to provide research and training support to BNF and establishment of fisheries curriculum ii. Recruitment of university for research and training support The much delayed financial evaluation was concluded on the 11th of March and at the close of the quarter, the combined evaluation report was submitted for no objection to enable a contract to be prepared and signed for commencement of work by the university in May. Dependent on no objection for the combined evaluation report and contract TTL to give no objection for negotiations and contracting iii. First research and training campaigns started (details of programs to be worked out by the selected university) i. RCU to recruit firm for design of dashboard, Transparency and design completed and accessibility of fisheries ii. IT platform for dashboard installed, engagement of operators, and training See above No activity No activity RCU activity RCU activity
4 SUB-COMPONENT 1.2 Introduction of fishing rights (US$0.6 m GEF) Introduction of fishing rights through a system of comanagement i. Complete Robertsport CMA plan i. A strategic plan was prepared by John Parks, the co-management consultatnt, for further action by the Robertsport CMA. Also the consultant assisted the CMA to initiate a review of the bye-laws which were later validated and finalized at a one day workshop held at Robertsport by the CMA. At this workshop a draft constitution was reviewed and adopted. The CMA itself started operations by setting up 6 subcommittees whose capacity would be built by resources specialist to be identified by the project in Monrovia. The sub-committees comprise: 1. Planning, Development and Social Committee 2. Membership and RecruitmentCcommittee 3. Conflict Management Committee 4. Community Surveillance Committee 5. Community Science Committee and 6. Business Management Committee. The one day workshop was attended by 30 members. ii. A collaboration was entered into for the Environmental Justice Foundation to partner the project in establishing and building capacity of the CMA. In this regard the ii. Specialized training (measurement of atmospheric temperature, fish length, tidal waves, beach hygiene, erosion etc) for the CMAs to be established at Robertsport and provision of equipment for monitoring the health of beach and inshore environments. On going. Activities would be conducted in the future by the community science group now referred to as the Sub-committee for Community Science Roberstport team to identify resource personnel to provide capacity building to the 6 subcommittees. Also the comanagement consultant to initiate the preparation of the comanagement plan to kick start operations of the CMA
5 SUB-COMPONENT 1.4 Social marketing, communication and transparency (US$0.2 m GEF) Social marketing and communication xiii. Preparation of an implementation plan for the nets exchange program to replace 25% of illegal fishing gear from the Turf to be established at Robertsport in the first year. xiv. Implementation of net exchange program vii. Design and technical specifications for construction of 4 Community Fisheries Centers (CFC) for Robertsport MPA/TURFs completed and validated by communities. i. Preparation of supporting material and coordination for the Co-management and MCS teams. iv. Radio advertising campaign to promote fisheries and WARFP. Ads to run on 9 costal counties local radio stations. i. After the co-management consultant's submission of a draft report on experiences of net exchange programs in 3 countries together with proposals and recommendations, the project now awaits the draft strategy document which he promised to present as part of his end of consultancy report. ii. The CMA executive visited all 15 communites to be involved with the nets exchange program for sensitization and setting up of 3 member core groups to manage the program in each fishing community. iii. A one day workshop was planned for the 11th of April to build the capacity of the community core groups on methodologies to be applied and on the fisheries regulations to enhance work. See above Preliminary designs were submitted for review and it was expected that the final would be presented together with bill of quantities to proceed with preparation of tender documents. i. After shortlisting 5 applicants out of 8 for the post of Communications Specialist an interview was conducted for selection of the deserving candidate on the 29th of March. The report of selection was to be sent to the TTL for no objection for preparation of contract. ii. More documents were sent out to Robertsport to support sentization visits to the 15 communities to participate in the net exchange program. Various brochures and posters were distributed during meetings The radio programs would be assessed to determine effectiveness and future direction if need be to be continued Co-management consultant to provide the strategy document for implementation of the nets exchange program LAMDA to provide final architectural and engineering designs and bill of quantities for preparation of tender documents Process for recruitment to be expedited by Procurement Component 2 Reduction of illegal fishing (US$5.4 m IDA) v. Finalization of social and marketing surveys report and presentation and dissemination LISGIS was sent the revised report for finalization but as at the close of the quarter the final report had not been received LISGIS to be given final warning for final report to be expedited
6 SUB-COMPONENT 2.2 Monitoring, Control and Surveillance (MCS) systems (US$5.4 m IDA) Implementing sustainable surveillance systems i. Preparation of technical specifications and bidding documents for new BNF headquarters, FMC and competent authority lab, Robertsport landing site as well as coastal stations and equipment ii. MCS capacity building a. Study tour to Namibia No yet initiated b. Regional workshop on MCS Not yet initiated iii. MCS strategic and operational planning and manual a. Strategic international intelligence support on targeting IUU owners, vessels etc iv. Technical support to establish a MCS national centre v. Technical support to establish two coastal MCS centres Final designs and bill of quantities expected from the consultant early next month. The consultant appealed for help from the international ports consultant who initiated work on the design of the industrial landing and export terminal but failed to submit the detailed needs for assistance before the end of the quarter. The CV and TOR of an international intelligence expert (Mr. Album Gunnar) was sent to the TTL for no objection for recruitment. The expert was expected to undertake training also for capacity building of the FMC. The MCS consultant built capacity of the FMC on radio communications and use of cameras for air surveillance. The design of a model coastal station was prepared for adoption in Buchanan and Harper vi. Equipping Liberia with air and sea surveillance capacity a. air surveillance - patrols i. The UNMIL was provided a GPS camera with a powerful lens to assist in the detailed gathering of evidence for effective prosecution of fisheries cases. The flight operations officer was given training on the use of the equipment. ii. 4 air surveillance patrols were conducted during the quarter b. sea patrols i. The necessary funds for mounting of the tank on the saddles to be constructed and subsequent protection with concrete walls was released. It is expected that early next month the fuel tank at Buchanan would be completed. With the lessons learnt it is expected that the Harper project would be rapid. ii. Only one sea patrol was conducted in search of EROS which was suspected to be engaged in illegal fishing Frequent change of headship of LCG on fellowships abroad LAMDA to provide final architectural and engineering designs and bill of quantities for preparation of tender documents and also to provide details of asistance sought from the international posts consultant TTL to grant no objection for recruitment MCS consultant to initiate further action on technical support SP Oil Marketing Co. engineer to expedite action to mount fuel tank at Buchanan The Liberia Army Chief of Staff to be consulted to address the decrease in sea patrols
7 vii. Developing a national observer programme NOAA was working hard to prepare the observer data for analyses by an expert to be fielded in April. In this regard, corrections and cleaning of the observer data was being undertaken by the oberver management team viii Observer communications equipment ix. Support to community monitoring and enforcement A Liberian Communications company was requested to remedy the inadequacy in performance of the FMC communications equipment which unabled it to establish effective communications with observers and vessels at sea. The HF radios were now able to make contact as far as Russia and Japan. It has started already to repair the VHF radios for land based operations. The sub-committee for surveillance was established at Robertsport and the MCS consultant was tasked with the responsibility of capacity building of the members. It was expected that a capacity building program would be prepared and implemented next quarter Component 3 Increasing the contribution of the Marine Fish Resources to the local economies(us1.9 m IDA) SUB-COMPONENT 3.1 Fish i. Capacity building and facilitation of training Not yet initiated landing site clusters (US$1.3 m and extension for product development IDA) ii. Preparation of an investment package and call for expression of interest from potentially interested private companies for a concession from BNF for use of the pier, as partner with Government The lease for the Mesurado fishing pier was being adjusted from years with the preparation of an addendum. IFC has indicated its interest in securing partners in the establishment and management of the industrial fish landing and export terminal. Component 4 Coordination, monitoring and evaluation and program management (US$1.7 m IDA, US$.8 GEF) SUB-COMPONENT 4.1 National implementation (US$1.1 m IDA, US$0.8 m GEF) i. Arrangements for construction of BNF HQ Preliminary designs were submitted for review and it was expected that the final would be presented together with bill of quantities to proceed with preparation of tender documents. ii. Recruitment of focal person for value addition Not yet initiated NOAA to set up a credible mechanism to analyze and use data collected by observers instead of data collected at the port by fisheries inspectors which often is underestimated MCS consultant to initiate action now that the Robertsport surveillance committee is in place Legal Department of NPA to expedite action on preparation of addendum LAMDA to provide final architectural and engineering designs and bill of quantities for preparation of tender documents iii. Recruitment of assistant accountant ii. Study tour iii. Short courses for the FMO staff Report of selection process submitted to TTL for no objection before recruitment Not yet initiated The project accountant attended a two- week capacity building course in South Africa TTL to grant no objection for recruitment
8 iv. Steering Committee meetings. The first steering committee meeting was BNF/FMO held in February and the annual report, budget and workplan including the Aide memoir were presented. Also there were reports presented on Liberia's attempt to curb IUU fishing by the LCG and Ministry of Justice.
ANNUAL PROGRESS REPORT (JANUARY - DECEMBER, 2012) - WARFP/BNF - LIBERIA
1 ANNUAL PROGRSS RPORT (JANUARY - DCMBR, 2012) - WARFP/BNF - LIBRIA Activities Sub-activities Achievements Status Challenges and constraints Recommended actions and by whom Component 1 Good governance
More informationMinistry of Fisheries / Indian Ocean Commission (IOC)
Ministry of Fisheries / Indian Ocean Commission (IOC) Regional Fisheries Monitoring Plan in the South West Indian Ocean: Regional Strategy for the Sustainable Management of Marine Resources (Tuna) Daroomalingum
More informationPMR PROJECT IMPLEMENTATION STATUS REPORT (ISR)
1. SUMMARY INFORMATION Implementing Country/Technical Partner: PMR PROJECT IMPLEMENTATION STATUS REPORT (ISR) South Africa. Reporting Period: From 1/10/2017 to 30/09/2018 Report Date: 4 October 2018 Implementing
More informationIntegration of marine spatial data in Japan: "Japan's Marine Cadastre"
Integration of marine spatial data in Japan: "Japan's Marine Cadastre" Masayuki FUJITA The Secretariat of the Headquarters for Ocean Policy Cabinet Secretariat, Government of Japan MSDI Open Forum, Tokyo
More informationCountry profile Namibia
Country profile Namibia 1- General information Full name of the country Capital city Official language(s) Namibia Windhoek English Main ports Walvis Bay Luderitz Coastline (km) 1570 2- Competent National
More informationCATALOGUE OF TRAINING COURSES PROPOSED BY EFCA 2017 version CATALOGUE OF TRAINING COURSES PROPOSED BY EFCA (2017)
CATALOGUE OF TRAINING COURSES PROPOSED BY EFCA (2017) 1 Contents How to deliver a training based on the EFCA Core Curriculum for fisheries inspectors... 3 Inspection at sea/port inspection... 4 Introduction
More informationFIRST MEETING OF THE AD HOC WORKING GROUP ESTABLISHED UNDER ARTICLE 21 OF THE FAO AGREEMENT ON PORT STATE MEASURES. Oslo, Norway, 1-2 June 2017
May 2017 PSMA_WG/2017/2 E FIRST MEETING OF THE AD HOC WORKING GROUP ESTABLISHED UNDER ARTICLE 21 OF THE FAO AGREEMENT ON PORT STATE MEASURES Oslo, Norway, 1-2 June 2017 WORKING ARRANGEMENTS AND PRELIMINARY
More informationGuideline: Administrative & Logistic Arrangement in Supporting The Joint Multi-Sectoral Outbreak Investigation & Response in ASEAN
Guideline: Administrative & Logistic Arrangement in Supporting The Joint Multi-Sectoral Outbreak Investigation & Response in ASEAN I. Introduction Emerging infectious diseases respect no boundaries. Most
More informationTERMS OF REFERENCE FOR CONSULTANTS
TERMS OF REFERENCE FOR CONSULTANTS A. Consulting Firm The Asian Development Bank (ADB) will engage a consulting firm in accordance with its Guidelines on the Use of Consultants (2013, as amended from time
More informationForty-first Annual Conference of the Center for Oceans Law & Policy. Yogyakarta, Indonesia May 16-19, 2017
Forty-first Annual Conference of the Center for Oceans Law & Policy Yogyakarta, Indonesia May 16-19, 2017 The Korean Coast Guard's Law Enforcement Concerning Chinese IUU Vessels KIM Wonhee Senior Researcher
More informationFISHERIES SERVICES JAPAN
FISHERIES SERVICES JAPAN Value chain element Services provided by (fisheries) administrations Privately provided services Services provided to all value chain elements Fund for construction of port facilities
More informationChecklist of requirements for licensing under Section 31 of the Trade Regulation Code (GewO)
Checklist of requirements for licensing under Section 31 of the Trade Regulation Code (GewO) I. Operational framework 1. Senior executive 1.1 Company management has selected a senior executive as designated
More informationCATALOGUE OF TRAINING COURSES PROPOSED BY EFCA 21/01/2016 version CATALOGUE OF TRAINING COURSES PROPOSED BY EFCA (2016)
CATALOGUE OF TRAINING COURSES PROPOSED BY EFCA (2016) 1 Contents 1. SPECIFIC TRAININGS BASED ON THE CORE CURRICULA (ON REQUEST)... 3 Specific inspection training based on the EFCA Core Curricula:... 3
More informationTerms of Reference for Resource Mobilization Support to IPPF Member Association in Nepal, (Family Planning Association of Nepal-FPAN)
Terms of Reference for Resource Support to IPPF Member Association in Nepal, (Family Planning Association of Nepal-FPAN) 1. Situational Analysis Funding for international aid in general and for IPPF in
More informationCARIBBEAN DEVELOPMENT BANK PROCEDURES FOR THE SELECTION AND ENGAGEMENT OF CONSULTANTS BY RECIPIENTS OF CDB FINANCING
CARIBBEAN DEVELOPMENT BANK PROCEDURES FOR THE SELECTION AND ENGAGEMENT OF CONSULTANTS BY RECIPIENTS OF CDB FINANCING P.O. Box 408, Wildey, St. Michael BB11000 Barbados, West Indies Telex: WB 2287 Tel:
More informationTERMS OF REFERENCE RWANDA LESSONS LEARNED ON DISASTER RECOVERY
TERMS OF REFERENCE RWANDA LESSONS LEARNED ON DISASTER RECOVERY Job Title: Category: Duty Station: Type of contract: Expected starting date: Duration of assignment: Individual Consultancy Communications
More informationTERMS OF REFERENCE (ToR)
Funded by the European Union TERMS OF REFERENCE (ToR) SETUP OF A REVOLVING FUND SYSTEM, IMPROVED ACCESS TO FINANCE AND WITH BUSINESS ADVISORY SUPPORT SERVICES TO COCOA PRODUCERS AND SERVICE DELIVERY ENTITIES
More informationWorld Bank Iraq Trust Fund Grant Agreement
Public Disclosure Authorized Conformed Copy GRANT NUMBER TF054052 Public Disclosure Authorized World Bank Iraq Trust Fund Grant Agreement Public Disclosure Authorized (Emergency Disabilities Project) between
More informationTBT Institutional Infrastructure
UGANDA THE TBT-NEP Structure TBT INSTITUTIONAL INFRASTRUCTURE TBT NEP USE OF EPING COMMENTS ON EPING OTHER SIMILAR TB/SPS INITIATIVES BY INTERNATIONAL PARTNERS CAPACITY CONSTRAINTS REMEDIES TBT Institutional
More informationPPEA Guidelines and Supporting Documents
PPEA Guidelines and Supporting Documents APPENDIX 1: DEFINITIONS "Affected jurisdiction" means any county, city or town in which all or a portion of a qualifying project is located. "Appropriating body"
More informationPART I: PROJECT INFORMATION 1. PROJECT LINKAGE TO NATIONAL PRIORITIES, ACTION PLANS AND PROGRAMS
PART I: PROJECT INFORMATION 1. PROJECT LINKAGE TO NATIONAL PRIORITIES, ACTION PLANS AND PROGRAMS The GEF initial support on the implementation of the Stockholm Convention focuses on assisting Vietnam to
More informationRegional meeting on the Strategic Approach to International Chemicals Management
Distr.: General 18 January 2018 English only Regional meeting on the Strategic Approach to International Chemicals Management Update on the Special Programme to support institutional strengthening at the
More informationJOB ADVERTISEMENT. Eastern and Southern Africa Higher Education Centers of Excellence Project (ACE II) 1. Project Background
Eastern and Southern Africa Higher Education Centers of Excellence Project (ACE II) 1. Project Background JOB ADVERTISEMENT Launched in October 2016 and financed by the World Bank, the ACE II Project supports
More informationSTATUTORY INSTRUMENTS SUPPLEMENT No th June, 2016 STATUTORY INSTRUMENTS SUPPLEMENT
STATUTORY INSTRUMENTS SUPPLEMENT No. 18 24th June, 2016 STATUTORY INSTRUMENTS SUPPLEMENT to The Uganda Gazette No. 45, Volume CIX, dated 24th June, 2016 Printed by UPPC, Entebbe, by Order of the Government.
More informationDOING OUR PART" PROGRESS REPORT March 1, 2003
DOING OUR PART" PROGRESS REPORT March 1, 2003 SOCIAL AGENDA AS A LENS RECOMMENDATION # 1: THE SOCIAL AGENDA AS POLICY FRAMEWORK AND LENS Develop a social lens for use by the GNWT (1.1.1-1.2.3) Departments,
More informationMaritime Security and Defence Cooperation Maritime Security Governance in the IOR
Maritime Security and Defence Cooperation Maritime Security Governance in the IOR Dr Sam Bateman (Australian National Centre for Ocean Resources and Security) OUTLINE Need for maritime security governance
More informationStrengths and weaknesses: existing veterinary legislation
Strengths and weaknesses: existing veterinary legislation Zimbabwe: (Website) Animal Health Act Established: 1961 2001 - Authority to organize import and export - Authority to appoint officers - Definitions
More informationTerms of Reference. Consultancy to support the Institutional Strengthening of the Frontier Counties Development Council (FCDC)
Terms of Reference Consultancy to support the Institutional Strengthening of the Frontier Counties Development Council (FCDC) 1. Introduction August 2016 to August 2018 1. Supporting Kenya s devolution
More informationDigital Bangladesh Strategy in Action
Digital Bangladesh Strategy in Action Introduction While Awami League s Charter for Change announced the concept of Digital Bangladesh as an integral component of Vision 2021, the budget 2009 10 speech
More informationGUIDELINES FOR STATE INITIATIVES FOR MICRO & SMALL ENTERPRISES CLUSTER DEVELOPMENT
GUIDELINES FOR STATE INITIATIVES FOR MICRO & SMALL ENTERPRISES CLUSTER DEVELOPMENT * * * * * 1. Short Title: Operational Guidelines for activities under State Initiatives for Micro & Small Enterprises
More informationGlobal Infrastructure Hub Update
Global Infrastructure Hub Update IWG Update Introduction Dear IWG members, Welcome to the first edition in a series of updates that the GI Hub will provide in advance of each G20 Infrastructure Working
More informationApplication for Authorisation for Fish Farming in the Sea Part 1: Applicant Details September 2008
Application for Authorisation for Fish Farming in the Sea Part 1: Applicant Details September 2008 Application for Authorisation to carry out Fish Farming in the Sea Fisheries & Marine Resources Act 2007
More informationIMPACT REPORTING AND ASSESSMENT OFFICER IN SOUTH SUDAN
Terms of Reference IMPACT REPORTING AND ASSESSMENT OFFICER IN SOUTH SUDAN BACKGROUND ON IMPACT AND REACH REACH was born in 2010 as a joint initiative of two International NGOs (IMPACT Initiatives and ACTED)
More informationEconomic and Social Council
UNITED NATIONS E Economic and Social Council Distr. GENERAL ECE/ENERGY/WP.4/2009/8 24 March 2009 Original: ENGLISH ECONOMIC COMMISSION FOR EUROPE COMMITTEE ON SUSTAINABLE ENERGY Steering Committee of the
More informationIMPLEMENTING CROATIAN VTMIS SERVICES
Concluding event PHARE 2005 Twinning Project Institutional Capacity Building in the Field of Maritime Safety & kick off event PHARE 2006 Twinning Project Institutional Capacity building for VTMIS and FSI
More informationCOMMISSION IMPLEMENTING DECISION. of
EUROPEAN COMMISSION Brussels, 16.10.2014 C(2014) 7489 final COMMISSION IMPLEMENTING DECISION of 16.10.2014 laying down rules for the implementation of Decision No 1313/2013/EU of the European Parliament
More informationNorthern Ireland Social Care Council Quality Assurance Framework for Education and Training Regulated by the Northern Ireland Social Care Council
Northern Ireland Social Care Council Quality Assurance Framework for Education and Training Regulated by the Northern Ireland Social Care Council Approval, Monitoring, Review and Inspection Arrangements
More informationwith the Corporación Andina de Fomento (CAF) for Republic of Chile 16 March 2017 Entity Support & Strategic Frameworks
with the Corporación Andina de Fomento (CAF) for Republic of Chile 16 March 2017 Entity Support & Strategic Frameworks READINESS AND PREPARATORY SUPPORT PAGE 1 OF 14 ver. 19 August 2016 Readiness and Preparatory
More informationREQUEST FOR PROPOSALS
IUCN Tel. +254 20 249 35 61/65/70 Mukoma Road Cell +254 724 256 804 P. O. Box 68200 00200 +254 734 768 770 Nairobi, Kenya Email: earo@iucn.org www.iucn.org REQUEST FOR PROPOSALS by INTERNATIONAL UNION
More informationProject Period 3/01/2016-6/30/2016 Project Location Description (from Proposal) Project Summary (from Proposal)
Easygrants ID: 49487 National Fish and Wildlife Foundation NFWF Project ID: 0302.15.049487 Coral Reef Conservation Fund 2015 - Submit Final Programmatic Report (New Metrics) Grantee Organization: Marine
More informationAEITI Country Work Plan Amended
re Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Extractive Industries Transparency Initiative (AEITI) Islamic Republic of Ministry of Finance AEITI
More informationAUSTRALIA S BORDER PROTECTION COMMAND. Interagency and Civil Military Cooperation
AUSTRALIA S BORDER PROTECTION COMMAND Interagency and Civil Military Cooperation CMDR Andrew Burnett RAN Command Legal Officer, Border Protection Command What are we? BPC is an Australian Government multiagency
More informationPORT STATE CONTROL OFFICER JOB DESCRIPTION
PORT STATE CONTROL OFFICER JOB DESCRIPTION (a) Prime Function/Purpose of Job The Port State Control Officer is answerable to the Manager Ships Inspection in the conduct of Port State Control inspections
More informationThe Government of the Republic of Trinidad and Tobago
The Government of the Republic of Trinidad and Tobago TRINIDAD AND TOBAGO EXTRACTIVE INDUSTRIES TRANSPARENCY INITIATIVE IMPLEMENTATION WORKPLAN January 2014 Approved by TTEITI Steering Committee 20 February,
More informationGuidelines. for Chaplains. in State Primary Schools. in Tasmania
Guidelines for Chaplains in State Primary Schools in Tasmania Tasmanian Department of Education Tasmanian Council of Churches Commission for Christian Ministry in State Schools 1 Tasmanian Department of
More informationFFA: AIR SURVEILLANCE PLANNING OFFICER (ASPO)
FFA: AIR SURVEILLANCE PLANNING OFFICER (ASPO) Job Identification Job Reference: Job Title: Air Surveillance Planning Officer (ASPO) Work Unit: Fisheries Operations Responsible To: Surveillance Operations
More informationSummary of the Meeting
Page 1 United Nations Environment Programme NOWPAP Northwest Pacific Action Plan Distribution: GENERAL UNEP/NOWPAP/RAP MALI FP/2017/3 06 October 2017 Original: English The 2017 NOWPAP Regional Action Plan
More informationUse of External Consultants
Summary Introduction The Department of Transportation and Works (the Department) is responsible for the administration, supervision, control, regulation, management and direction of all matters relating
More informationREPORT OF THE SECOND MEETING OF NOWPAP WORKING GROUP 4 (Beijing, People s Republic of China, October 2004)
Page 1 REPORT OF THE SECOND MEETING OF NOWPAP WORKING GROUP 4 (Beijing, People s Republic of China, 14-15 October 2004) Background leading to this meeting 1. The Action Plan for the Protection, Management
More informationTerms of Reference (ToR) Developing Advocacy Strategy for NCA Partners
Terms of Reference (ToR) Developing Advocacy Strategy for NCA Partners 1. Introduction Norwegian Church Aid (NCA) with its long presence (since 1979) in Afghanistan. NCA is a partner based organization
More informationPacific Urban Development Investment Planning and Capacity Development Facility
Technical Assistance Report Project Number: 51175-001 Transaction Technical Assistance Facility (F-TRTA) July 2017 Pacific Urban Development Investment Planning and Capacity Development Facility This document
More informationGuideline for Research Programmes Rules for the establishment and implementation of programmes falling under the Programme Area Research
Guideline for Research Programmes Rules for the establishment and implementation of programmes falling under the Programme Area Research EEA Financial Mechanism and Norwegian Financial Mechanisms 2014
More informationPROJECT PREPARATORY TECHNICAL ASSISTANCE
Appendix 3 11 A. Justification PROJECT PREPARATORY TECHNICAL ASSISTANCE 1. The government has identified the priority areas to be covered under the ensuing project. A PPTA is necessary to provide sound
More informationEmergency Education Cluster Terms of Reference FINAL 2010
Emergency Education Cluster Terms of Reference FINAL 2010 Introduction The Government of Pakistan (GoP), in partnership with the Humanitarian Coordinator in Pakistan, is responsible for leading and ensuring
More informationWHO s response, and role as the health cluster lead, in meeting the growing demands of health in humanitarian emergencies
SIXTY-FIFTH WORLD HEALTH ASSEMBLY A65/25 Provisional agenda item 13.15 16 March 2012 WHO s response, and role as the health cluster lead, in meeting the growing demands of health in humanitarian emergencies
More informationPresented by Captain Sylvestre FONKOUA Chief of Zone D Multinational Coordination Center
GULF OF GUINEA MARITIME SITUATIONAL AWARENESS Presented by Captain Sylvestre FONKOUA Chief of Zone D Multinational Coordination Center INTRODUCTION I. GULF OF GUINEAMARITIME REGIONALSTRATEGY a) ECCAS b)
More informationDOALOS. Technical Cooperation, Trust Funds and Capacity-Building
DOALOS Technical Cooperation, Trust Funds and Capacity-Building What do we understand by capacity building? CAPACITY-BUILDING HUMAN CAPABILITIES SCIENTIFIC CAPABILITIES TECHNOLOGICAL CAPABILITIES RESOURCE
More informationToR FOR DEVELOPING AQUACULTURE PRODUCTION STRATEGY & THEIR IMPLEMENTATION UNDER OTELP
ToR FOR DEVELOPING AQUACULTURE PRODUCTION STRATEGY & THEIR IMPLEMENTATION UNDER OTELP 1.Introduction Orissa Tribal Empowerment & Livelihoods Programme (OTELP) focuses on empowering the Tribals and enabling
More informationELEMENTS OF REQUEST FOR MARITIME SECURITY TRAINING COURSE APPROVAL
ELEMENTS OF REQUEST FOR MARITIME SECURITY TRAINING COURSE APPROVAL The elements listed below comprise a request for course approval. The request and supporting material shall be submitted electronically
More informationLAW OF THE SEA AND MARITIME LAWS. Teaching, Research and Training Project Status Thursday, 17 December 2015 POLICY RESEARCH
LAW OF THE SEA AND MARITIME LAWS Teaching, Research and Training Project Status Thursday, 17 December 2015 POLICY RESEARCH 1 Draft Deep Seabed Mining Act of India Sent to the Ministry of Earth Sciences;
More informationREQUEST FOR EXPRESS OF INTEREST (REOI)
THE SOCIALIST REPUBLIC OF VIETNAM MINISTRY OF EDUCATION AND TRAINING Loan No.: 2750-VIE/2751-VIE University of Science and Technology of Hanoi Development (New Model University) Project REQUEST FOR EXPRESS
More informationThe undertaking involves 4 NGOs/CSOs under separate contract as follows:
TERMS OF REFERENCE FOR STRENGTHENING PARTICIPATORY STRUCTURES AND CONDUCTING CAPACITY BUILDING TRAININGS TO ENHANCE STAKEHOLDER ENGAGEMENT FOR UGANDA S NATIONAL REDD+ PROGRAMME IN CENTRAL, MID-EASTERN
More informationBackground. Context for the HNP Consultative Group
DRAFT Concept Note and Terms of Reference for World Bank-Civil Society Consultative Group On Health, Nutrition, and Population (Updated as of 15 November 2010) Background The World Bank recognizes the
More information2008 Report on the Implementation of Confidence Building Measures between Belize and Guatemala
2008 Report on the Implementation of Confidence Building Measures between Belize and Guatemala 2008 Report on the Implementation of Confidence Building Measures between Belize and Guatemala I. Introduction
More informationRepublic of Latvia. Cabinet Regulation No. 50 Adopted 19 January 2016
Republic of Latvia Cabinet Regulation No. 50 Adopted 19 January 2016 Regulations Regarding Implementation of Activity 1.1.1.2 Post-doctoral Research Aid of the Specific Aid Objective 1.1.1 To increase
More informationEconomic and Social Council
United Nations Economic and Social Council Distr.: General 10 December 2001 E/CN.3/2002/19 Original: English Statistical Commission Thirty-third session 5-8 March 2002 Item 6 of the provisional agenda*
More informationIntegrated Maritime Surveillance
Integrated Maritime Surveillance How enhanced datasharing and coast-guard functions cooperation can improve the maritime surveillance efficiency fostering sustainable economic growth? DG MARE-D1 30/10/2012
More informationIntegrated Maritime Policy and Surveillance
MARITIME AFFAIRS & FISHERIES Integrated Maritime Policy and Surveillance Common Information Sharing Environment (CISE) IMP Policy Elements Blue Book: Maximising the sustainable use of the oceans and seas
More informationProject Period 6/30/ /30/2016 Project Location Description (from Proposal) Project Summary (from Proposal)
Easygrants ID: 41419 National Fish and Wildlife Foundation NFWF Project ID: 0303.14.041419 Fisheries Innovation Fund - 2014 - Submit Final Programmatic Report (New Metrics) Grantee Organization: Alaska
More informationABSTRACT. Keywords: CBFM, LBCFM-PD, decentralization of authority, people's participation, local management body
LOCALLY BASED COASTAL FISHERIES MANAGEMENT: PEOPLE'S PARTICIPATION AND LOCAL MANAGEMENT BODY TO SUSTAINABILITY OF COASTAL RESOURCES IN CASE OF THAILAND PHATTAREEYA SUANRATTANACHAI, SOUTHEAST ASIAN FISHERIES
More informationSubject: Request for tenders: Papua New Guinea National Coordinator/Environment Specialist
REQUEST FOR TENDERS File: AP_4/12/18 Date: 13 July, 2018 To: Interested Consultants From: Paul Anderson Inform Project Manager Subject: Request for tenders: Papua New Guinea National Coordinator/Environment
More informationSubject: 2018 and 2019 calls for applications to host International Jazz Day. Accept, Sir/Madam, the assurances of my highest consideration.
11/04/2017 Ref.: CL/4199 Subject: 2018 and 2019 calls for applications to host International Jazz Day Sir/Madam, I am pleased to announce the launch of the 2018 and 2019 calls for applications to host
More informationRegular Process for Global Reporting and Assessment of the State of the Marine Environment, including Socioeconomic Aspects
Regular Process for Global Reporting and Assessment of the State of the Marine Environment, including Socioeconomic Aspects Workshop under the auspices of the United Nations, in support of the Regular
More informationMARINE SAFETY MANAGEMENT SYSTEM
MARINE SAFETY MANAGEMENT SYSTEM ENVIRONMENTAL PREVENTION AND RESPONSE NATIONAL PREPAREDNESS PLAN Process Framework See Attachment Environmental Prevention and Response Program Framework. 1.0 Purpose 1.1
More informationGNLU INTERNATIONAL MARITIME ACADEMY (Theme : Maritime Industry, Naval Power and the Marine Environment) April, 2017
Information Brochure GNLU INTERNATIONAL MARITIME ACADEMY- 2017 (Theme : Maritime Industry, Naval Power and the Marine Environment) 15-22 April, 2017 In collaboration with Meet the Academic Leaders & Policy
More informationSt. Jude Church CYO Athletic Club Bylaws
St. Jude Church CYO Athletic Club Bylaws July 1st, 2015 INTRODUCTION This document has been created to provide a framework for the organization and operation of the CYO program at St. Jude Church. It is
More informationAnswers to questions following the call for tender for a Fund Operator for the EEA and Norway Grants Global Fund for Regional Cooperation
Answers to questions following the call for tender for a Fund Operator for the EEA and Norway Grants Global Fund for Regional Cooperation Question 1: Does re-granting experience refer to direct experience
More information1. Invitation. 2. Background
Critical Ecosystem Partnership Fund Call for Proposals Evaluation of Lessons Learned to Inform Reinvestment in the Caribbean Islands Biodiversity Hotspot Opening date: Friday, 8 December 2017 Closing date:
More informationAustralian Medical Council Limited
Australian Medical Council Limited Procedures for Assessment and Accreditation of Specialist Medical Programs and Professional Development Programs by the Australian Medical Council 2017 Specialist Education
More informationAnnual Report 2015 Japan's Actions against Piracy off the Coast of Somalia and in the Gulf of Aden
March 2016 The Cabinet Secretariat The Government of Japan 1 Annual Report 2015 Japan's Actions against Piracy off the Coast of Somalia and in the Gulf of Aden Somalia and the Surroundings (off the Coast
More informationFEDERAL REPUBLIC OF NIGERIA
Supplemental Letter No. 1 (Lagos Urban Transport Project) Section 9.02 of the General Conditions Financial and Economic Data In connection with the above Credit to the Republic of Nigeria for the Lagos
More informationEducational Partnerships Policy
Educational Partnerships Policy Purpose 1. The purpose of this policy is to set out the principles and processes which apply to the development, approval, monitoring and review of educational partnerships
More informationTerms of Reference. 1. Introduction. 2. Background
Terms of Reference Consultancy Services for the GEF project Strategic Platform to Promote Sustainable Energy Technology Innovation, Industrial Development and Entrepreneurship in Barbados 1. Introduction
More informationCentral Authorities Local Authorites
Sri Lanka Governmental Level Marine Environment Protection Authrity Disaster Management Center Sri Lanka Coast Guard Sri Lanka Navy Sri Lanka Ports Authority Ceylon Petroeum Coporation Sri Lanka Army At
More informationProject Design Advance. Nauru: Port Development Project. Project Number: December 2015
Project Design Advance Project Number: 48480-002 December 2015 Nauru: Port Development Project This document is being disclosed to the public in accordance with ADB s Public Communications Policy 2011.
More informationHealth Cluster Performance Assessment and Monitoring Tool: partner form
Health Cluster Performance Assessment and Monitoring Tool: partner form Feedback provided by each health cluster partner agency Date: Country: (and location if at sub-national level) I. Coordination mechanisms
More informationLoan No INO: POOR FARMERS INCOME IMPROVEMENT THROUGH INNOVATION PROJECT. INCEPTION MISSION May 21 June 5, 2003 MEMORANDUM OF UNDERSTANDING
Loan No. 1909-INO: POOR FARMERS INCOME IMPROVEMENT THROUGH INNOVATION PROJECT I. INTRODUCTION INCEPTION MISSION May 21 June 5, 2003 MEMORANDUM OF UNDERSTANDING 1. An ADB Inception Mission (the Mission)
More informationRequest for Supplementary Tender (mini-competition)
Request for Supplementary Tender (mini-competition) HEA - SYSTEM OF ROLLING REVIEWS Review of Procurement Practices in HEA-funded Higher Education Institutions Terms of Reference Background As part of
More informationbetween ARAB REPUBLIC OF EGYPT and
Public Disclosure Authorized GRANT NUMBER TF0A1553 Public Disclosure Authorized MIDDLE EAST AND NORTH AFRICA TRANSITION FUND Grant Agreement Public Disclosure Authorized Public Disclosure Authorized EQUAL
More informationRole Profile Medical Officer- Medical Devices
Role Profile Medical Officer- Medical Devices ROLE SUMMARY The Medical Officer role will be within the Medical Devices department. Reporting to the Deputy Director Medical Devices, the role of the Medical
More informationBNFB Project - Reporting Period: June 1-16, 2016 CIP BI-WEEKLY UPDATES
BNFB Project - Reporting Period: June 1-16, 2016 CIP BI-WEEKLY UPDATES 1 Major accomplishments during the last two weeks Regional-Nairobi, Kenya a) Hilda Munyua Project Manager Grants and Sub-grant agreements
More informationConsultant Power Forward. Location: Abuja, Nigeria. Reports to: Country Director and Senior Support Program Manager
Title: Consultant Power Forward Location: Abuja, Nigeria Reports to: Country Director and Senior Support Program Manager Africare is a leading non-governmental organization (NGO) committed to addressing
More informationAssessment mission report Ghana
World Maritime University The Maritime Commons: Digital Repository of the World Maritime University MARENDA Project Reports 5-2015 Assessment mission report Ghana Henrik Nilsson World Maritime University,
More informationOffice of Climate Change Guyana September, TRANSITIONING TO NATIONAL ENERGY SECURITY: Bartica as a Model Green Town TERMS OF REFERENCE
Office of Climate Change Guyana September, 2017 TRANSITIONING TO NATIONAL ENERGY SECURITY: Bartica as a Model Green Town TERMS OF REFERENCE ENERGY AUDIT OF PUBLIC INSTITUTIONS, FACILITIES AND STREET LIGHTING
More informationSADCMET/MEL LM Report 19 June Presented by: Victor R Mundembe
SADCMET/MEL LM Report 19 June 2014 Presented by: Victor R Mundembe Background and Members SADC Cooperation in Legal Metrology (SADCMEL) is one of the structures that implement the SADC Technical Barriers
More informationSection 3. Organization of the MOD/SDF
Part II The Basics of Japan s Defense Policy Section 3. Organization of the MOD/SDF The Self-Defense Forces (SDF), the core of Japan s defense capability, is a specialist organization that plays the most
More informationWFP Support to Wajir County s Emergency Preparedness and Response, 2016
4 WFP Support to Wajir County s Emergency Preparedness and Response, 2016 OCTOBER 2016 Emergency preparedness and response programmes are now a shared function between Wajir County Government and the national
More informationCAIRNS SHIPPING DEVELOPMENT PROJECT. East Trinity Development Project Plan. Next Steps. Terms of Reference for an assignment to produce an
CAIRNS SHIPPING DEVELOPMENT PROJECT Next Steps Terms of Reference for an assignment to produce an East Trinity Development Project Plan 3 July 2015 Terms of Reference for an assignment to produce an East
More informationDeadline: 21 November :00h Philippine Standard Time
Small Grants Programme by the ASEAN Centre for Biodiversity(ACB): Third Party Service Provider for Small Grant Preparation and Implementation in Indonesia Deadline: 21 November 2017 17:00h Philippine Standard
More informationREQUEST FOR PROPOSALS FOR PRODUCTION OF A VIDEO DOCUMENTARY
REQUEST FOR PROPOSALS FOR PRODUCTION OF A VIDEO DOCUMENTARY EPC/PRO/RFP/005/2013-2014 TERMS OF REFERENCE MARCH, 2014 1. INTRODUCTION The Terms of Reference (TOR) serve as a Request for Proposals from firms/companies
More information