1 Light Rail Transit Construction Impact Mitigation Strategies: Case Studies and Recommendations for the Central Corridor 21 December 2007

2 Light Rail Transit Construction Impact Mitigation Strategies: Case Studies and Recommendations for the Central Corridor A MURP Professional Paper In Partial Fulfillment of the Master of Urban and Regional Planning Degree Requirements The Hubert H. Humphrey Institute of Public Affairs The University of Minnesota Reuben R. Collins 21 December 2007 Professor Carissa Schively Slotterback Paper Advisor Professor Xinyu Cao Jim Alexander CCPO Design Manager Metropolitan Council Date

3 TABLE OF CONTENTS INTRODUCTION...1 CASE STUDIES...2 Portland...2 Seattle...5 Salt Lake City...8 Phoenix...11 Denver...13 Houston...15 San Jose...16 SUMMARY AND RECOMMENDATIONS...20 NOTE: The views and opinions expressed in this report are those of the author and do not necessarily state or reflect those of the Metropolitan Council or the paper advisors. The signatures of Professor Schively Slotterback, Professor Jason Cao, and Jim Alexander do not imply endorsement of the material contained in this report or an agreement to abide by the recommendations contained therein. This report is intended as an academic exercise only, and the signatures of Professor Schively Slotterback, Professor Jason Cao and Jim Alexander are only intended to certify that the paper is of academic quality sufficient to satisfy the Professional Paper requirement for the Master of Urban and Regional Planning degree at the University of Minnesota. i

4 INTRODUCTION The proposed Central Corridor Light Rail Transit (LRT) line stretching from downtown Minneapolis to downtown Saint Paul has the potential to revitalize the neighborhoods it passes through. Projected to carry nearly 43,270 passengers daily by the year 2030, the line is an opportunity for significant investment in the local economy through transportation infrastructure improvements. When completed, the increased mobility and accessibility along the corridor will provide opportunities for increased economic activity and provide existing businesses with the ability to reach new markets. Many of the business owners along the corridor, however, are concerned about the negative impacts the construction process may bring. The proposed transit line is scheduled to begin a three year construction phase in Construction of light rail, like any large construction process, can significantly disrupt the normal business operations along a corridor. Potential impacts include the interruption of electricity and utility services, removal of sidewalks and pedestrian access points, and a diversion of automobile traffic or lane configurations. In addition, the mere presence of construction activities can often be a significant psychological barrier for customers, whether or not there is actual decrease in physical access. Businesses of various types and sizes are located along the Central Corridor and several business districts have emerged, each with a unique mixture of retail, service, industrial, and other types of businesses. In Minneapolis, for example, the proposed alignment along Washington Avenue will pass through the Stadium Village neighborhood, a lively neighborhood catering to students at the nearby University of Minnesota. The area is home to restaurants, clothing shops, taverns, and other convenience retail stores that depend on pedestrian access for much of their business. In Saint Paul, the proposed alignment passes through a wide variety of business districts. Towards the western end of University Avenue, many of the nearby light industrial businesses depend on large trucks to send and receive products. Several large shopping centers with both small businesses and big-box retailers are situated along the corridor. Stores such as Target, Wal-Mart, Office Max, Cub Foods, and Rainbow Foods depend mostly on accessibility via automobile with some accessibility from local bus service. Traffic diversion during construction, both intentional and unplanned, is likely to present a major hardship to these businesses. There are many small businesses located immediately adjacent to University Avenue in Saint Paul that will be particularly vulnerable to disruptions caused by the construction process. Many of the businesses along the corridor cater specifically to the needs of immigrants and those with culturally diverse backgrounds. In many cases, these small businesses are owned by members of the community without formal training in business management and without large 1

5 capital budgets to absorb the impact of a construction season. Many of the businesses depend almost entirely on convenient storefront accessibility to draw customers. The purpose of this report is to provide case studies from other light rail construction projects that may provide insight into the Central Corridor LRT construction process. Understanding the mitigation measures used during the construction of other recent LRT projects will provide a better understanding of the options available for use in the Twin Cities. In the next section, this report will consider the mitigation efforts utilized throughout the construction of LRT in seven cities: Portland, Seattle, Salt Lake City, Phoenix, Denver, Houston, and San Jose. For each case study, this report provides a general overview of the project characteristics and a summary of construction mitigation strategies utilized during each project. In addition, this report provides insight from project public outreach coordinators regarding the effectiveness of the mitigation strategies. The final section of this paper provides a summary and brief comparison of efforts used in the seven cities along with a set of recommendations for the Central Corridor LRT in the Twin Cities. These seven cities were chosen because they have something in common with the Twin Cities metropolitan area. The Portland, Seattle, and Denver, and Phoenix are often considered peer cities with the Twin Cities because of their relatively similar size. Salt Lake City, Houston, and San Jose, although somewhat larger or smaller than the Twin Cities metropolitan area, were chosen because each of these systems feature a center-running alignment along an arterial street similar to that proposed for Central Corridor. For each of the case studies information is drawn from other written reports, community outreach materials, and direct communication with representatives from each transit property. CASE STUDIES Portland Tri-Met began operating the Interstate MAX - Yellow Line in April The newest addition to the Portland LRT network, the Interstate line is 5.8 miles long and was constructed at a cost of $350 million. The alignment begins in downtown Portland and extends to the North with center-running alignment extending along most of Interstate Avenue. The Interstate area of Portland represents 20% of Portland s total population, but includes 65% of the African- American residents of the city. In total, 38% of the Interstate area population is represented by various minority groups, compared to 18% of the population citywide (Tri-Met 2007). To reach out and connect with the diverse population in the area, Tri-Met sought and hired key community outreach representatives that live in or near the corridor and who represent ethnic minority groups in the area. The community outreach representatives made a special effort to interact with business owners using door-to-door canvassing and telephone call-downs in 2

6 addition to mailings and local advertisements. Tri-Met used bilingual communications to invite Latino families from schools and other organizations to meetings about the Interstate MAX project. The extra effort made by the community outreach staff led to a successful public involvement process where residents and business owners were encouraged to contribute in meaningful ways to the project. The final design includes a number of elements inspired by the public involvement process. Developing strong working relationships and trust between the outreach staff and the business organizations and area residents was a critical component of minimizing the negative construction impacts. When construction began, 105 businesses were located along the corridor. According to Tri- Met, only 1 business failed as a direct result of construction-related disruptions, and 3 businesses relocated to another location. In addition, over 50 new businesses have been added along the corridor either during or immediately after construction (Tri-Met 2007). Tri-Met and the Portland Development Commission teamed up with Cascadia Revolving Fund, a private non-profit community development financial institution to provide financial help to businesses affected by light rail construction. Businesses that could demonstrate construction had affected their revenues were eligible to receive low-interest loans and business consulting services. The 8-year loans offered an interest rate of 3 percent with interest only payments for the first year. Loans were between $5,000 and $25,000. In addition to loans, Cascadia helped recipients to use the loans to their best advantage by offering on-going consultation on business practices such as finance, accounting, marketing, personnel and general management issues. In total, Cascadia provided over 800 hours of personalized technical assistance to 59 businesses along Interstate Avenue (Portland Development Commission 2007). The Portland Development Commission provided a Storefront Improvement Grant program aimed to assist property and business owners in rehabilitating their storefronts. In total, 18 businesses have received Storefront Improvement grants (Portland Development Commission 2007). Tri-Met staff used a wide range of strategies to distribute construction information to stakeholders along the corridor. Business owners were invited to attend workshops teaching business management skills and were paired with personal mentors who were skilled in giving business strategy advice to help businesses throughout the construction process. Staff attended meetings and gave presentations at a wide range of meetings including the Interstate MAX Advisory Committee, Interstate Corridor Urban Renewal Area Committee, various business associations, N/NE Portland Coalition meetings, and local neighborhood association meetings. Tri-Met Community Affairs also distributed 12 seasonal newsletters to a mailing list of 7,500 residents throughout North Portland. Tri-Met s web site included an extensive section 3

7 on Interstate MAX construction and community outreach, including an information section in Spanish (Tri-Met 2007). Tri-Met sponsored special media and social events along the corridor to encourage people to visit the local businesses. The events received much media attention and helped draw a crowd to the construction site and the impacted businesses. Events included the Vanport Bridge dedication, the Expo Center art dedication, the First Tree Planting Ceremony, an Interstate Avenue Street Fair, an Intersections book dedication, and a 50% Milestone event. Similar to a strategy used in Seattle, Tri-Met sponsored a lunch bus program to ferry city officials and transportation workers to Interstate Avenue restaurants that were affected by the construction. Tri-Met employed a wide range of strategies as part of the Open for Business program. Four community relations staff and construction supervisors had a strong commitment to initiating daily contact with each business when construction was immediately adjacent and a no surprises strategy provided information to business owners in advance (Tri-Met 2007). There was also a 24 hour construction hotline with a live operator at all times. The operator had the ability to page community relations staff for after-hours issues, and over 2 dozen construction staff were available on a 24 hour basis. Tri-Met contractors employed a construction method that aimed to minimize the amount of time the street was under construction immediately in front of businesses. Construction progressed in reaches, each about 4 blocks long, and each phase of construction was completed in one reach before starting that phase in the next reach. In total, a period of about 8 weeks per reach was required to rebuild the outside lane and replace the sidewalks. The street and sidewalk were temporarily restored if there was ever a gap between phases of construction. Tri-Met had a firm commitment to provide access into businesses at all times. Vehicle and pedestrian routes that would allow businesses to be accessed were open at all times. Driveway and doorway reconstruction was scheduled before or after business hours whenever possible to accommodate the needs of the businesses. At least one of the sidewalks remained open on each reach at all times. Tri-Met provided an extensive advertising and marketing campaign on behalf of the Interstate businesses. The Interstate Avenue is Open for Business campaign was designed to attract customers to Interstate Avenue through advertising, direct mail, and customer incentives. Signs featured businesses names and stated, Open For Business or gave parking, entrance, or detour directions to businesses. Ads were placed on buses, in local papers, and flyers were distributed to customers to help in wayfinding. 4

8 Full-page advertisements featuring groups of Interstate retail businesses were used to tell stories of the businesses and their owners. Businesses were grouped with other businesses located nearby, and the placement of the advertisements was timed to coincide with the construction in front of the businesses. Tri-Met developed a marketing campaign called Doing Business on Interstate that was mailed to 16,000 homes in North Portland. Special flyers were direct mailed and hand delivered in nearby neighborhoods. Tri-Met also gave away monthly passes to winners of monthly drawings from those with Interstate business receipts and placed advertisements on many local buses with information on how to access the businesses (Becklund 2007). Multiple direct mailings to residents in the surrounding area with coupons and advertisements were successful in bringing customers to businesses. While in the process of developing the coupons, the TriMet communications and graphics staff assisted several small businesses in developing attractive logos to make the advertisements more effective (Becklund 2007). Ann Becklund, Director of Community Affairs at TriMet believes the most important and effective aspect of lessening the impact of the construction on local businesses was providing the business owners somebody to talk to. She stated that TriMet community affairs staff provided a one-stop shop for business owners to get information, express concerns, and provide feedback. TriMet provided business owners with a single point of contact and built a strong relationship of trust early in the planning process so that business owners were comfortable contacting community affairs staff with concerns. She believes that having the community affairs and public relations staff housed within the TriMet organization was critical to the project because it allowed business owners to feel as though they had an advocate within the organization (Becklund 2007). Seattle Sound Transit is currently implementing the first light rail line in the Seattle metropolitan area. The Central Link, a 15.7 mile line connecting downtown Seattle with the Sea-Tac Airport via the Rainier Valley is expected to begin service in The Central Link will travel under downtown Seattle in a transit tunnel completed in 1990 and used only by buses until Much of the alignment is either underground, elevated, or travels along the 5 th Avenue Busway or freeway alignments where disruption to businesses will be minimal. The largest impact to downtown Seattle is the increased number of buses using surface streets while the tunnel is undergoing renovations. However, the Central Link follows an at-grade alignment along Martin Luther King Jr. Way (MLK) for 4.3 miles, a wide urban corridor through one of the most diverse neighborhoods in Seattle. This portion of the alignment features a center-running alignment 5

9 and the project scope includes reconstruction of the entire avenue from building face to building face. The Rainier Valley neighborhood in Southeastern Seattle is considered a multi-ethnic community where 83% of the residents are non-white. In addition to being culturally diverse, the neighborhood is also one of the poorest neighborhoods in Seattle. Surrounding the avenue is a diverse mix of residential, commercial, and light industrial uses (CDF 2002). As planning begun on the Central Link, Sound Transit recognized the need for an effective construction mitigation plan, especially along Martin Luther King Jr. Way. The Sound Transit web site states, Sound Transit works hard to ease the impacts of construction on local neighborhoods and businesses. A big part of our mitigation is making sure that businesses remain open during the construction of light rail and other projects. In addition to an extensive public involvement program, Sound Transit utilized many common business impact mitigation techniques (Sound Transit Mitigation 2007). Sound Transit s first objective was to maintain access to businesses for customers and employees. Staff worked with businesses to arrange alternate access when the usual access was blocked for construction purposes. Off-street parking for the construction workers vehicles was provided to preserve on-street parking for customers. Open for business signs were posted at businesses directly impacted by construction. The city also provided detour signs to help customers access businesses during construction. Kiosks and businesses directories were placed where appropriate. In addition, temporary public art was applied to temporary construction fencing in places along the corridor. Sound Transit also places a large emphasis on helping to promote the businesses along the route. One of the most innovative strategies used to assist businesses along the corridor is the Lunch Bus campaign. Once a month, a bus shuttles Sound Transit and city employees and members of the general public to a local restaurant along the corridor. In addition to simply supporting the restaurant, the program helps to raise awareness of the construction progress and sends the message that local businesses are still operating. Sound Transit also created a marketing campaign titled The World At Your Doorstep to encourage individuals throughout the Rainier Valley to shop at businesses along the LRT corridor. This campaign utilizes several advertising techniques including a web site, mailers to local residents, and flyers. As part of the campaign, each month several impacted businesses are featured in a monthly construction newsletter. 6

10 The contractor also played an important role in the mitigation process. The contractor was required to keep garbage, dust, and debris to a minimum and wash the windows of businesses in active construction areas once every three months (Sound Transit Mitigation 2007). Sound Transit remains committed to quickly distributing up-to-date information to business owners and residents along the corridor. They have made several outreach commitments to the community that apply not only to construction of Link light rail, but also to Sounder commuter rail. Sound Transit has committed to provide advance notification of construction activities and to maintain a 24-hour construction hotline as a single point of contact along the corridor and as a method of communication during emergencies or unexpected circumstances. In addition, Sound Transit provides many other opportunities for those along the corridor to stay informed through regular construction meetings for impacted neighborhoods, regular written construction updates that are mailed to surrounding neighborhoods, maintaining up-todate information on the Sound Transit web site, assisting individuals with limited English skills by providing an interpreter and translation services for written materials and community meetings, and working with businesses and residents to find solutions to construction related problems (Sound Transit Community Outreach 2007). A Community Development Fund (CDF) officially became part of the Link Light Rail project in November 1999 when the Sound Transit Board unanimously passed a resolution establishing the alignment and station locations for the project. Public involvement in establishing the fund was substantial with several community forums and a community steering committee established in Sound Transit, King County, and the City of Seattle all contributed to the Rainier Valley CDF. The public investment in the CDF is funded primarily through a federal block grant with the balance coming from the general funds of each entity. According to the CDF, the majority of funds are revolving loans and include terms and conditions that serve as incentives for the borrower to achieve the Fund s community development goals. Eligibility for the loans and the loan terms vary depending on the degree of operation impairment experienced by an individual business. The fund has three distinct avenues for distributing assistance: 1. Supplemental Mitigation Assistance for businesses impacted by Light Rail Construction in the Rainier Valley ($16 million) This fund includes mitigation payments related to moving and re-establishment costs, increased operating costs, and decreased revenues. It also includes mitigation advances related to increasing working capital, tenant improvement, and equipment upgrades. The fund also provides technical assistance related to small business marketing and customer cultivation, basic accounting, and using the internet. 7

11 2. Workforce Training for Rainier Valley residents in construction related jobs ($2 million) This program is a partnership with Seattle Jobs Initiative and is a time-limited program that will last through This program attempts to help bring residents into the workforce and monitors retention placements for 24 months. 3. Community Development Program (CDP) on-going community development lending for small businesses and real estate projects. ($32 million) This program is a long-term revolving loan fund in which 25% of the program funds are set aside for business lending and 75% set aside for real estate lending. The Fund s Operating Plan states, The CDF may support any project that preserves and strengthens cultural and economic diversity, long-term livability, and economic opportunity for Rainier Valley residents, businesses, and institutions (CDF 2002). Despite the efforts of Sound Transit to minimize the impact on local businesses, many businesses are still having a difficult time surviving the construction period. The Seattle Times reported in September, 2005, that 97 of 274 eligible businesses along MLK had received business interruption grants from the fund, 41 of which reported a decline in sales of 50 percent or more. Another article stated, As of February 2006, 44 of the 274 businesses along Martin Luther King Jr. Way, where much of the line's construction is taking place, were no longer operating, despite $7.5 million in "mitigation funds" from the Rainier Valley Community Development Fund. In addition, local minority construction workers have staged rallies protesting that African Americans were not receiving an equitable share of construction work for the project. As of March 2007, the CDF programs distributed $9.3 million and assisted 157 businesses. The workforce training program has enrolled 172 individuals, placing 109 with an average wage of $16 per hour plus benefits. The community development program has approved 3 business and 2 real estate loans with 17 more loans pending (CDF 2007). Salt Lake City The Utah Transit Authority (UTA) completed the first light rail line in Salt Lake City in Called the North/South Line, the alignment follows an existing rail alignment for most of the project length and is surrounded by low intensity industrial land uses for much of the alignment. The north end of the alignment, however, featured center-running track along Main Street, 700 South, and 200 West in downtown Salt Lake City. Many storefronts and locally owned businesses were located along this portion of the project alignment. Many buildings in downtown Salt Lake City have ground-floor retail businesses with offices located above. UTA utilized relatively few business impact mitigation strategies throughout the construction of the North/South Line. Construction activities were coordinated with unrelated development occurring along the line to minimize the amount of time Main Street would be under 8

12 construction. In addition, construction activities could only take place on two adjacent blocks at any time to minimize the amount of time construction would be immediately in front of a single business. The construction period was extremely difficult for many main street businesses and nearly 30% of the businesses permanently closed during this time (Knowles, 2007). After receiving significant criticism for the lack of assistance offered to businesses during construction, UTA and Salt Lake City were prepared to be more proactive during the next LRT expansion project. The University Line is a 2.5 mile extension of the existing line connecting downtown Salt Lake City with the University of Utah to the East. The University alignment departs from the mainline alignment on 400 South, a wide arterial running East/West with many businesses and storefronts. The project cost a total of $118.5 million and began service on December 15, 2001, nearly two years ahead of schedule. Over 100 business are located along the project alignment ( UTA, 2007). An Interlocal Agreement between the Utah Department of Transportation (UDOT), UTA, the University of Utah, and Salt Lake City provided a forum to discuss alignment and traffic issues. Salt Lake City played a key role in establishing a public forum and process that would allow residents and business owners along the project alignment to voice their concerns, especially regarding the disruption to business operations during construction. The project was unique in that the contractor shouldered much of the responsibility of minimizing the disruption to local businesses. The public participation process for mitigating construction impacts was included as a part of the construction documents. Six months before construction began, a Community Coordination Team (CCT) was established composed of residents and business representatives from along the project alignment. The CCT included one business representative and one residential representative from each of the 13 blocks in the corridor and two at-large representatives appointed by each stakeholder agency. The CCT was tasked with establishing a contractor evaluation incentive fee system. The construction documents mandated a minimum level of mitigation measures to be performed by the contractor, but additional compensation was made available to the contractor for performance above and beyond the minimum requirements. Each three month period, the CCT could choose to award the contractor up to $200,000 beyond the base compensation for construction mitigation activities beyond what the contract required. The exact amount awarded to the contractor during each three month period was determined by an intricate evaluation system. First, the public was allowed to evaluate the contractor s public involvement activities. At the beginning of the project, the public was asked to complete lengthy written surveys, but this proved too time consuming and ineffective. The CCT members 9

13 also attempted to complete the forms by visiting neighborhood businesses in person. Ultimately, the CCT determined that it was most effective to hire a consulting business to administer telephone surveys to those along the corridor to evaluate the contractor s public involvement activities. After the public had an opportunity to provide feedback, the contractor presented a selfevaluation to the CCT followed by a presentation by UTA regarding the contractors mitigation strategies. Each CCT member individually rated the contractor, and the total scores were compared to the scores provided by the contractor and UTA. The CCT executive director had the ability to make any necessary adjustments to the overall rating. Throughout the construction period, the average CCT recommendation was 89.8% of the total possible incentive compensation (Bott 2007). The CCT was also tasked with allocating $300,000 of the $500,000 budget to implement business impact mitigation programs coordinated with the Contractor s public information staff. The CCT and the contractor s public relations consultants used the funds in four ways: 1. 4 th South Bucks. The 4 th South Bucks Program distributed over $75,000 in coupons (each worth $1) that could be redeemed at businesses along 400 South. The program was believed to be an acceptable way to randomly disseminate the coupons through a radio station campaign. It was anticipated that business patrons would spend additional money beyond the 4 th South Bucks. 2. Go Fourth Radio Advertisement Campaign. The Go Fourth radio advertising campaign was chosen because it was determined to be an effective means of reaching the intended customer demographics of the businesses along the project alignment. The contractor s public information specialist assisted a CCT subcommittee in developing a radio campaign. The CCT developed a set of criteria used to evaluate all of the businesses along the corridor (preference was given to independent businesses) to create a priority list for radio spots. Each month, six businesses were featured on the radio. In addition, a remote broadcast featured the six chosen businesses on the 4 th of each month. The radio remote broadcasts would feature prizes including Fourth South Bucks. 3. Catalyst Advertisements. Sixteen businesses were given advertisement space on the back cover of Catalyst Magazine each month. Catalyst Magazine, a local publication, was chosen because its reader demographic closely matched the radio station s demographics. 4. The CCT recognized that media coverage is often perceived as more credible than advertisements. In coordination with the contractor s public information staff, the CCT encouraged UTA and the contractor to use media events to distribute the message that 10

14 businesses were accessible during construction. Accessibility was emphasized in several media campaigns, including the First Rail Weld and the Half-time Celebration. In addition to establishing a CCT, Salt Lake City sponsored a low interest loan program available to impacted businesses and administered by the Salt Lake City Community and Economic Development Department. Loans up to $10,000 were available to businesses located within one-half block from the project alignment were eligible to apply. Applicants were also required to provide profit loss statements. In total, 19 loans were distributed to businesses during the construction period, primarily to less established businesses such as independent restaurants. Five of the loan recipients defaulted on their loan (SLC 2006). Phoenix The Central Phoenix LRT line, the first to be implemented in Phoenix, is currently under construction and scheduled to open for service in December, The project alignment is 20 miles in length and has a $1.4 billion construction budget. Valley Metro Rail has estimated that there are over 3,500 businesses located along the project alignment. The alignment is composed almost entirely of center-running trackway with relatively little grade separation or separated right-of-way. The core of the Valley Metro Rail business impact mitigation plan relies on distributing up-todate information and receiving feedback from business owners. Valley Metro uses a 24-hour, 7 day per week project hotline with a live voice during the construction period, as well as a project web site to help interact with the public during construction. Cell phone numbers and photographs of the Valley Metro Rail and Public Involvement staff are also published and made available to businesses along the corridor to help business owners recognize the outreach staff. All street closure information is made known to businesses using flyers, s, and the project web site. Periodic construction update meetings are also used to inform business owners of future construction plans and provide an opportunity for feedback (VMR 2003). Before construction began, Valley Metro created a Business Outreach Plan to inform business owners of the assistance that would be available throughout construction. To help prepare business owners for the upcoming disruption, Valley Metro invited business owners who have survived LRT construction in other cities to speak with the local business owners, give advice, and share lessons learned (VMR 2003). A Community Advisory Board (CAB) for each line section is composed of business and neighborhood leaders from along the line section. The CAB is tasked with providing input to Valley Metro Rail representatives on contractor community relations to be used as a measure for contractor performance. A total of five CABs serve as the voice of the community throughout the 20 mile corridor. Monthly construction review meetings for each section are 11

15 facilitated by the public involvement coordinators. The contractor and several engineers from the Project Team are also present at the meetings. CAB members evaluate the contractor s performance using forms provided by the agency. CAB members also distribute incident report forms to all the stakeholders they represent to gain an understanding of contractor performance. CAB members use the incident report forms and personal observation to compete the contractor evaluation form. The evaluation form provides feedback regarding the contractors performance providing advance notification of construction activities, maintaining access to stakeholder properties along the light rail alignment, maintaining traffic guide and business courtesy signage, controlling dust and noise, and maintaining adequate pedestrian/bicycle crosswalks in the light rail construction zone. The resident engineer considers the evaluation submitted by the CAB in determining contractor payment (Steere 2007). The Valley Metro Rail Construction Signage Program is another tool used to minimize the disruption to businesses along the corridor. Two types of signs are available: traffic guide signs and courtesy signs. Traffic guide signs are intended to direct traffic to the businesses. The courtesy signs may be used for advertising, marketing, or directional purposes. All courtesy signage is available to businesses within 48 hours from the time it is requested. While there is no limit to the amount of signage available, the area coordinator and business owners will work together to ensure an appropriate amount is used. This program is possible because of the assistance of the Cities of Phoenix, Mesa, and Tempe, which have temporarily waived existing signage ordinances along the corridor (VMR 2003). To help coordinate efforts along the corridor and improve the level of service provided to business owners, the corridor has been divided into five sections, and each section has been assigned a Community Outreach Representative. This representative is responsible for interacting with all businesses located within that alignment section. This helps to personalize the process for the business owners by providing a single point of contact with Valley Metro. Valley Metro created the Metro MAX shopping card, which can be used to receive discounts from businesses along the corridor. The program is designed to increase patronage of retail businesses along the project alignment. Businesses that wish to participate in the program are free to decide what promotional discount or special offer they wish to include in a brochure listing all of the participating businesses and their offers. Cards and brochures are distributed by the public involvement staff and by the businesses themselves. In addition, the cards may be downloaded off the Valley Metro web site. Valley Metro also provides free pre-printed postcards to businesses along the alignment. The postcards include a space for each business to personalize the postcards, though business owners must cover the costs of custom printing and postage to mail the cards. 12

16 In addition to the business assistance programs made available through Valley Metro, each municipality through which the alignment passes (Phoenix, Tempe, & Mesa) has created additional assistance programs available only to the businesses within their jurisdiction. In addition, individual cities have engaged in additional advertising campaigns as well. The City of Phoenix created the Shop the Line advertising campaign with on-site radio promotions and advertising (City of Phoenix 2003). Howard Steere, Public Involvement Manager for Valley Metro, said that loans have been available through a number of organizations, but that they have not been as successful as they would have liked. The requirements to qualify for the loans were more strict than many businesses are able to meet, and many of the businesses that need the most financial assistance are not eligible. Various banks, chambers of commerce, credit unions, and non-profit organizations like Chicanos Por La Causa provide loans for as little as $200 available to businesses along the corridor. The terms and details of the loans depend on the location and individual needs of the business. Phoenix has focused its efforts on providing free consultations to business owners to help them recognize their strengths and weaknesses and formulate action plans to weather the construction period. Phoenix has hired a Business Advocate dedicated for this purpose, and three private sector consultants are also available at no charge to provide technical assistance with marketing, web page maintenance, workforce recruitment and development, accounting, and other technical aspects of business ownership. In addition, the Arizona State University Spirit of Enterprise Center provides business owners with a full market analysis of economic conditions to help business owners identify their target market. Overall, Howard Steere stated that Valley Metro has not been able to do as much mitigation as they would have liked because of regulations on money received from the Federal Government, but that the City of Phoenix and other organizations were able to fill that role. The most popular and successful program utilized was the free signage. He believes that the Valley Metro mitigation program has been very successful, but that the key to success was involving the partner cities and non-profit organizations to provide assistance beyond what Valley Metro was able to provide (Steere 2007). Denver Denver s Regional Transportation District (RTD) has implemented light-rail transit in four waves. The Central Corridor line, completed in 1994, consisted of 5.3 miles of at-grade trackway, including a section through downtown Denver. The line features a side-running alignment along surface streets for approximately half of the distance and utilizes an existing railway right- 13

17 of-way for the remainder. While traveling through downtown, the tracks split into a one-way pair on adjacent streets. The Southwest Corridor opened in 2000 as an extension of the Central Corridor into the southwest suburbs. The 8.7 mile trackway was constructed entirely on existing freight rail right-of-way and features only two at-grade street crossings both on relatively low traffic streets. The third installment of LRT in Denver was the Central Platt Valley Corridor. The 1.8 mile trackway provided access to several large venues including Auraria Campus, Invesco Field at Mile High Stadium, the Pepsi Center, Six Flags, Union Station and Coors Field. Construction of the line was completed in 2002 and was constructed almost entirely within existing freight rail right-of-way. The latest LRT project in Denver, the T-REX project completed in 2006, added 19.1 miles of grade separated trackway located immediately adjacent to I-225. The T-REX project combined construction of LRT with a major expansion and renovation of I-225, which resulted in both the trackway and the freeway being entirely grade separated from surface streets. Overall, most of the 35 miles of LRT in Denver are separated from traffic using overpasses or tunnels. As the alignment follows mostly existing freight rail and freeway right-of-way, there are very few street crossings. The notable exception is in downtown Denver where the LRT operates within surface street right-of-way. Since the rail alignment follows existing rail lines and freeways for much of the alignment, the construction impact mitigation strategies utilized serve a different purpose than those in other cities. Many of the businesses impacted are larger, automobile-oriented businesses. Much of the disruption caused by construction is caused by the reconfiguration and reconstruction of freeway ramps and bridges. In general, there are very few locations outside of downtown Denver where businesses experienced construction on their front doorstep. At a focus group meeting, business owners said that their biggest concern was their ability to maintain and recruit employees, and decreased productivity of employees because of traffic delays. Given this context, the business impact mitigation techniques used throughout this project were focused on reducing traffic congestion so that employees and customers would not experience significant delays. One of the key strategies used by RTD was to work with the Transportation Demand Management service providers to develop educational campaigns for impacted employees, businesses, and commuters. The purpose of the campaigns was to provide information about how employees and customers could avoid traffic congestion. Special emphasis was placed on encouraging travel at non-peak hours and using alternative modes of transportation (TransOptions 2007). 14

18 RTD committed to having a single contact person for information regarding business impacts. Providing an easy way for businesses to voice concerns and ask questions with a single point of contact helped to open lines of communication between the business owners and RTD. In addition, RTD committed to providing up-to-date information using newsletters, informational materials distributed periodically to businesses, and a project web-site (RTD 2000). Houston The Metropolitan Transit Authority of Harris County, Texas (METRO) began construction on the Red Line in 2001 with service beginning in December, The Red line extends 7.5 miles from the north edge of downtown near the University of Houston-Downtown Campus to the southwest suburbs. The downtown segment of the alignment features a center-running alignment on Main Street. The construction of LRT included complete reconstruction of the street right-of-way. The transformed Main Street features ornamental paving materials and sidewalk furniture. Although automobile traffic is still permitted on Main Street, the reconstruction efforts aimed at transforming the right-of-way into a pedestrian friendly environment. South of downtown Houston, the alignment remains at grade, but separates into a one-way pair on adjacent streets with side-running trackway before once again joining together to form center-running trackway. At one major intersection, the alignment, along with several lanes of through traffic, are grade separated from crossing traffic, however most of the line is at-grade. Overall, METRO utilized a more modest set of construction mitigation strategies than the other cities discussed in this study. Much of the construction mitigation efforts were aimed at reducing the total amount of time construction would be immediately adjacent to any single business. A complex phasing plan was implemented to ensure that construction was completed in one part of the line before moving on to the next portion. In addition, traffic control plans placed regulations on when key intersections could be closed. In general, intersections were required to remain open at all times to allow access to local businesses. When intersections were closed, however, no two streets with the same directional cross traffic could be closed at the same time. When Main Street on the north end of downtown was blocked off for construction, an extra lane was added to an adjacent street to help move traffic downtown and allow access to businesses (Gulf Coast Institute 2006). Houston utilized many of the most common mitigation techniques including open for business signage and wayfinding signage to ensure that customers were aware of how to access local businesses. METRO maintained an up-to-date web page to provide businesses with updates and future plans. Weekly s, mailers, community meetings, newsletters, and small advertising campaigns were also utilized to increase awareness of construction activities. 15

19 METRO conducted individual business surveys to determine the needs of each business during construction and to establish solid communication lines. A coupon book was distributed to households along the project corridor, however the campaign was not very successful. Very few of the coupons were redeemed (Chou 2007). Downtown Houston experienced significant hardships during the construction period of , but the METRO is quick to note that there were several other events aside from LRT construction that were partially responsible for the difficulties. Tropical Storm Allison (June 2001) causing $5 billion in property damages to central Houston, the World Trade Center terrorist attacks (September 2001) damaging Continental Airlines and the overall airline industry, and the collapse of Enron (December 2001) resulting in the layoff of over 4,000 employees all share some of the responsibility for economic downturn (RTD 2007). Ernest Chou, one of the community outreach coordinators on the project, stated that the most successful strategies of the construction mitigation program were to work directly with each business along the rail construction line. The personal interaction between business owners and multi-lingual outreach staff allowed for accurate information to be distributed to business owners along the line. The line was divided into 5 sections and each section consisisted of a team that worked to address day to day issues related to construction. Periodic community meetings in the construction zone with the Community Outreach Coordinators provided additional information to business owners immediately surrounding the construction zone. METRO developed lists of business owners along the corridor by line section. Community Outreach Coordinators ensured that all businesses were contacted and identified by walking the project alignment and interacting directly with business owners (Chou 2007). Ernest Chou also stated that METRO learned some important lessons throughout the construction process. The strategy used to perform construction in sequential segments rather than all at once was appreciated by many of the smaller businesses along the corridor. One of the most significant impacts to smaller businesses was the periodic disruption of utility services during construction. By minimizing the need for utility disruptions, and coordinating the times of disruption with businesses, the impact can be reduced. METRO also realized the benefits of using temporary asphalt walkways and driveways for improved access. San Jose The Santa Clara Valley Transportation Authority (VTA) in San Jose has developed an LRT system consisting of 42.2 miles of trackway with 62 stations. The system has three lines; two of the lines have 14 stations in common and one of the lines is a short, two-station offshoot of the system. The system began construction in 1985 when VTA created a downtown Transit Mall. The construction of the Transit Mall included a complete reconstruction of 1 st Street and 2 nd 16

20 Street from building face to building face and installing a one-way pair of side-running tracks on adjacent streets. This portion of San Jose contains mostly two or three story buildings with ground-floor retail establishments. Although some efforts were made to minimize the construction impacts, the construction period from 1985 to 1988 was very disruptive for many local businesses. Despite using granite tiles as makeshift sidewalks during construction, storefront access was greatly impacted. The San Jose Downtown Association reports that 24 ground floor businesses ceased to operate during this period (Childress 2007). In many respects, the construction of the Transit Mall was much more difficult than it would have been, had additional planning taken place before construction began. The project would have benefited from a plan that anticipated construction problems ahead of time and created policies and action plans to guide construction progress. A detailed construction management plan was never completed for this project, so problems were addressed as they were encountered, resulting in unnecessary delays and additional hardships placed on businesses. Confusion regarding underground utilities and building foundations caused significant delays in progress. As the VTA planned for future system expansion, it realized that planning ahead to reduce the opportunities for unforeseen delays was an important aspect of reducing the impacts on businesses. The San Jose Redevelopment Association (RDA) funded a business loan program to assist merchants financially to alleviate the potential loss of business during the construction of the Transit Mall. The RDA contracted with the San Jose Development Corporation, a non-profit organization, to administer the loan program. Approximately 178 businesses qualified and participated in the business loan program. Qualifying businesses in the construction area secured loans by borrowing against their existing assets. The process was similar to a traditional bank loan, however RDA was the lender. Ultimately, RDA staff and merchants were dissatisfied with the program because it was administratively difficult to manage. Repayment terms differed on every loan, depending on the agreement. Because the RDA operated as the loan administrator, rather than a traditional bank, requiring the businesses to repay the loans became a difficult situation. As a result, many of the loans were not repaid, and many of the businesses ceased operations during construction (SCVTA 2003). After the initial Transit Mall program was completed, the LRT system was expanded by extending the line north and south of downtown. South of downtown, the Green Line follows an existing freight rail right-of-way, and the Blue Line travels in the median of California State Routes 87 and 85. Traveling North, the Green and Blue lines share a center-running alignment for several miles to Tasman Drive. Here, the Green Line turns West, continuing on Tasman Drive for nearly all of the remaining trackway, and the Blue Line turns East, following Tasman 17

DOWNTOWN ACCESS STRATEGY

DOWNTOWN ACCESS STRATEGY DOWNTOWN ACCESS STRATEGY July 19, 2013 Table of Contents Executive Summary... 1 I. Introduction... 4 II. Business Assistance... 5 A. Business Loans 5 B. Technical Assistance 9 III. Marketing... 11 A. Promotional

More information

CENTRAL MESA LIGHT RAIL EXTENSION

CENTRAL MESA LIGHT RAIL EXTENSION CENTRAL MESA LIGHT RAIL EXTENSION BUSINESS ASSISTANCE About the Central Mesa Light Rail Extension The 3.1-mile Central Mesa extension will travel on Main Street from the current end-of-line at Sycamore

More information

Economic Development and Employment Element

Economic Development and Employment Element Economic Development and Employment Element Element Objectives The policies and actions of the Economic Development and Employment Element are intended to achieve the following nine objectives: 1. Provide

More information

Partial Action Plan No. 5 for Tourism and Communications

Partial Action Plan No. 5 for Tourism and Communications DRAFT FOR PUBLIC COMMENT (AS OF 9/18/03) LOWER MANHATTAN DEVELOPMENT CORPORATION Overview Partial Action Plan No. 5 for Tourism and Communications The Lower Manhattan Development Corporation (LMDC) has

More information

Economic Development Element of the Arroyo Grande General Plan. Prepared by the City of Arroyo Grande Community Development Department

Economic Development Element of the Arroyo Grande General Plan. Prepared by the City of Arroyo Grande Community Development Department Economic Development Element of the Arroyo Grande General Plan Prepared by the City of Arroyo Grande Community Development Department Adopted by City Council Resolution No. 4489 on October 9, 2012 Table

More information

July Five Pages

July Five Pages July 2009 Five Pages Kwame Collins (left) of Minneapolis and Jazlyn Bradley of St. Paul talk with Hue Pham (right), a community outreach coordinator for the Central Corridor LRT Project, on July 18 at

More information

Transportation Demand Management Workshop Region of Peel. Stuart M. Anderson David Ungemah Joddie Gray July 11, 2003

Transportation Demand Management Workshop Region of Peel. Stuart M. Anderson David Ungemah Joddie Gray July 11, 2003 Transportation Demand Management Workshop Region of Peel Stuart M. Anderson David Ungemah Joddie Gray July 11, 2003 Why Transportation Demand Management (TDM)? Demand management measures support a sustainable

More information

Economic Development Subsidy Report Pursuant to Government Code Section 53083

Economic Development Subsidy Report Pursuant to Government Code Section 53083 San Joaquin Regional Rail Commission, 1/6/17 Economic Development Subsidy Report Pursuant to Government Code Section 53083 TABLE OF CONTENTS 1.0 Introduction 1.1 Introduction 1.2 Background 1.3 Legal Requirements

More information

Façade Improvement Program

Façade Improvement Program Policy Guidelines for the Façade Improvement Program Neighborhood Economic Development Entrepreneurs Discovering Opportunities Through Neighborhood Revitalization Community Development Department 2008

More information

Re: Use of San Jose Business Modernization Tax (Measure G) Revenues

Re: Use of San Jose Business Modernization Tax (Measure G) Revenues October 27, 2016 Hon. Mayor Liccardo and City Council San Jose City Hall 200 E. Santa Clara Street San Jose, CA 95113 Re: Use of San Jose Business Modernization Tax (Measure G) Revenues Dear Honorable

More information

City of Tacoma Community & Economic Development Department Business Plan: Prosperity on Purpose for the City of Destiny*

City of Tacoma Community & Economic Development Department Business Plan: Prosperity on Purpose for the City of Destiny* City of Tacoma Community & Economic Development Department Business Plan: Prosperity on Purpose for the City of Destiny* City Vision The City of Tacoma will be recognized as a livable and progressive international

More information

Transit Operations Funding Sources

Transit Operations Funding Sources Chapter 7. Funding Operations Funding Funding has increased about 56% in absolute terms between 1999 and 2008. There have been major variations in individual funding sources over this time, including the

More information

Table of Contents. Page 2

Table of Contents. Page 2 Sixth Avenue Transportation Demand Management Construction Mitigation Plan August 2014 Table of Contents Table of Contents... 2 1.0 Introduction... 3 Development of Recommendations... 6 2.0 Recommendations...

More information

SOUTHWEST LRT (METRO GREEN LINE EXTENSION)

SOUTHWEST LRT (METRO GREEN LINE EXTENSION) 10 Joint Development This chapter describes potential long-term direct and indirect and short-term (construction) direct and indirect effects that would result from the Southwest Light Rail Transit (LRT)

More information

SAN JOSE CAPITAL OF SILICON VALLEY

SAN JOSE CAPITAL OF SILICON VALLEY CITY OF C7 S2 SAN JOSE CAPITAL OF SILICON VALLEY TO: HONORABLE MAYOR AND CITY COUNCIL COUNCIL AGENDA: 05/09/17 ITEM: 4.1 Memorandum FROM: Kim Walesh Jim Ortbal SUBJECT: SEE BELOW DATE: COUNCIL DISTRICT:

More information

FY BUDGET BY PROGRAM

FY BUDGET BY PROGRAM ECONOMIC DEVELOPMENT/REDEVELOPMENT Budget Summary CATEGORY FY 06/07 FY 05/06 FY 04/05 Proposed Year-End Actuals Budget Estimate Salaries $608,860 $686,700 $537,051 Operations & Maintenance 905,395 253,585

More information

City of Portsmouth Economic Development Commission 2011 Action Plan

City of Portsmouth Economic Development Commission 2011 Action Plan City of Portsmouth Economic Development Commission 2011 Action Plan Statement of Purpose: The City of Portsmouth Economic Development Commission (EDC) is committed to ensuring continued economic prosperity,

More information

Draft CRA Plan Amendment. Community Redevelopment Agency Advisory Board September 23, CRA Plan Amendment

Draft CRA Plan Amendment. Community Redevelopment Agency Advisory Board September 23, CRA Plan Amendment Draft Community Redevelopment Agency Advisory Board September 23, 2013 1 Project Scope Feasibility Study Public Workshops/Stakeholder Interviews Market Study 2 Schedule to Date Feasibility Study Community

More information

Beth Day Director, FTA Office of Project Planning RailVolution October 2011

Beth Day Director, FTA Office of Project Planning RailVolution October 2011 Beth Day Director, FTA Office of Project Planning RailVolution October 2011 What is a New or Small Start? New fixed guideways and extensions to existing systems Includes light rail, heavy rail, commuter

More information

NEIGHBORHOOD BUILDING IMPROVEMENT PROGRAM

NEIGHBORHOOD BUILDING IMPROVEMENT PROGRAM SALT LAKE CITY NEIGHBORHOOD BUILDING IMPROVEMENT PROGRAM Now Targeting the Poplar Grove and Central Ninth Neighborhoods Program Guidelines SALT LAKE CITY Housing and Neighborhood Development (HAND) A Division

More information

NEW YORK BUILDING CONGRESS PROGRAMS & SERVICES

NEW YORK BUILDING CONGRESS PROGRAMS & SERVICES NEW YORK BUILDING CONGRESS PROGRAMS & SERVICES PROGRAMS & SERVICES Table of Contents Who We Are... 1 Membership... 2-3 Committees & Councils... Policy & Advocacy... 4-5 6 Reports... 7 Events... 8 Sponsorship

More information

Objective 1. Research current housing issues in Avon to gain a deeper understanding of the housing market Type: Program Priority: 1 Cost: Medium

Objective 1. Research current housing issues in Avon to gain a deeper understanding of the housing market Type: Program Priority: 1 Cost: Medium Overall Comprehensive Plan Goals: Encourage growth in more suitable areas within town boundaries. These areas include sites close to existing residential, commercial, or industrial areas that are already

More information

CRENSHAW/LAX PILOT BUSINESS SOLUTION CENTER (BSC} and METRO'S PILOT BUSINESS INTERRUPTION FUND (BIF} MONTHLY REPORT

CRENSHAW/LAX PILOT BUSINESS SOLUTION CENTER (BSC} and METRO'S PILOT BUSINESS INTERRUPTION FUND (BIF} MONTHLY REPORT One Gateway Plaza Los Angeles, CA 90012-2952 213.922.2000 Tel metro. net CONSTRUCTION COMMITTEE EXECUTIVE MANAGEMENT COMMITTEE January 15, 2015 SUBJECT: ACTION: CRENSHAW/LAX PILOT BUSINESS SOLUTION CENTER

More information

APPENDIX B BUS RAPID TRANSIT

APPENDIX B BUS RAPID TRANSIT APPENDIX B BUS RAPID TRANSIT Table of Contents TABLE OF CONTENTS What is Bus Rapid Transit?... 2 BRT Features... 2 BRT Variations... 3 Where is BRT Currently Located?... 4 How Much Does BRT Cost?... 4

More information

Florida Job Growth Grant Fund Public Infrastructure Grant Proposal

Florida Job Growth Grant Fund Public Infrastructure Grant Proposal Florida Job Growth Grant Fund Public Infrastructure Grant Proposal Proposal Instructions: The Florida Job Growth Grant Fund Proposal (this document) must be completed by the governmental entity applying

More information

COMMUNITY ECONOMIC DEVELOPMENT PROGRAM

COMMUNITY ECONOMIC DEVELOPMENT PROGRAM NORTH PLATTE, NEBRASKA COMMUNITY ECONOMIC DEVELOPMENT PROGRAM "Renewing the North Platte Quality Growth Fund" 2011-2021 Mayor: City Council: City Administrator: City Attorney: Mr. Marc Kaschke Mr. Larry

More information

Order of Business. D. Approval of the Statement of Proceedings/Minutes for the meeting of January 24, 2018.

Order of Business. D. Approval of the Statement of Proceedings/Minutes for the meeting of January 24, 2018. COUNTY OF SAN DIEGO BOARD OF SUPERVISORS REGULAR MEETING MEETING AGENDA WEDNESDAY, FEBRUARY 14, 2018, 9:00 AM BOARD OF SUPERVISORS NORTH CHAMBER 1600 PACIFIC HIGHWAY, SAN DIEGO, CALIFORNIA Order of Business

More information

Construction of Peña Bridge - March 2013 Jersey Cutoff Bridge October Eagle Project Update. East Corridor Stakeholder Committee April 23, 2013

Construction of Peña Bridge - March 2013 Jersey Cutoff Bridge October Eagle Project Update. East Corridor Stakeholder Committee April 23, 2013 Construction of Peña Bridge - March 2013 Jersey Cutoff Bridge October 2012 Eagle Project Update East Corridor Stakeholder Committee April 23, 2013 FasTracks Plan 122 miles of new light rail and commuter

More information

CHAPTER 6 Construction Traffic Management Program. Overview

CHAPTER 6 Construction Traffic Management Program. Overview Chapter 6: Construction Traffic Management Program CHAPTER 6 Construction Traffic Management Program Overview This chapter sets forth the policy and procedures to be followed by staff for the construction

More information

Major in FY2013/2014 (By and ing Source) Municipal Building Acquisition and Operations Balance $1,984, Contributions from Real Estate

Major in FY2013/2014 (By and ing Source) Municipal Building Acquisition and Operations Balance $1,984, Contributions from Real Estate Major in FY2013/2014 (By and ing Source) Environmental Services Solid Waste 4200 4200 06CON 4200 SWM01 Balance $13,753,504.00 Balance $4,631,754.00 Balance $2,738,918.00 ing Source Total: $21,124,176.00

More information

Regional Transit System Plan. Regional Task Force Meeting No. 1

Regional Transit System Plan. Regional Task Force Meeting No. 1 Regional Transit System Plan Regional Task Force Meeting No. 1 Thursday, December 2, 2010 James Wagner Welcome! Introductions Venue Packet Displays Opening Session 1 Agenda (5 mins) (20 mins) What is a

More information

BUSINESS AND ECONOMICS

BUSINESS AND ECONOMICS This preliminary draft element was prepared by City staff on the basis of input from the CAC and members of the public received from January 2017 through February 2017. The Element will be reviewed by

More information

Table of Contents Introduction... 1 Summary of Study Outreach Efforts... 3 Figure No. Description Page

Table of Contents Introduction... 1 Summary of Study Outreach Efforts... 3 Figure No. Description Page Oak Ridge Road Pedestrian/Bicycle Safety Program Public Involvement and Agency Coordination Summary T Table of Contents Introduction... 1 1.1 Overview of the Project... 1 1.2 Purpose of this Report...

More information

7/23/2013. Downtown Greenville s Success. Downtown Greenville s Success

7/23/2013. Downtown Greenville s Success. Downtown Greenville s Success Downtown Greenville s Success What makes Greenville unique and successful? Community development Public space Partnerships Greenville s experience is not just about downtown Jumping off place to surrounding

More information

SAN IPSE CAPITAL OF SILICON VALLEY ?/2W/(T. Memorandum TO: HONORABLE MAYOR AND CITY COUNCIL. FROM: Kim Walesh Jim Ortbal

SAN IPSE CAPITAL OF SILICON VALLEY ?/2W/(T. Memorandum TO: HONORABLE MAYOR AND CITY COUNCIL. FROM: Kim Walesh Jim Ortbal CITY OF 7 S3 SAN IPSE CAPITAL OF SILICON VALLEY TO: HONORABLE MAYOR AND CITY COUNCIL STUDY SESSION: 3/30/2017 Memorandum FROM: Kim Walesh Jim Ortbal SUBJECT: DIRIDON STATION PLAN AND REGIONAL RAIL PROJECTS

More information

2018 Regional Project Evaluation Criteria For PSRC s FHWA Funds

2018 Regional Project Evaluation Criteria For PSRC s FHWA Funds 2018 Regional Project Evaluation Criteria For PSRC s FHWA Funds INTRODUCTION As described in the adopted 2018 Policy Framework for PSRC s Federal Funds, the policy focus for the 2018 project selection

More information

FIRST IMPRESSIONS COMMUNITY EXCHANGE TEAM MEMBER S GUIDE BOOKLET. Seeing things in a whole new light

FIRST IMPRESSIONS COMMUNITY EXCHANGE TEAM MEMBER S GUIDE BOOKLET. Seeing things in a whole new light FIRST IMPRESSIONS COMMUNITY EXCHANGE TEAM MEMBER S GUIDE BOOKLET Seeing things in a whole new light Table of Contents Visiting Team Member Information... 1 Prior to Your Visit... 5 The Five Minute Impression...

More information

Puget Sound Gateway Program

Puget Sound Gateway Program Puget Sound Gateway Program SR 167 Completion Project Tacoma Transportation Commission April 18, 2018 THOMAS SLIMAK, PE SR 167 ASSISTANT PROJECT MANAGER Agenda Puget Sound Gateway Program Overview Program

More information

Everett Wallace, James Cavallo, Norman Peterson, and Mary Nelson. March, 1997

Everett Wallace, James Cavallo, Norman Peterson, and Mary Nelson. March, 1997 -92645 The submitted manuscript has been authored by a contractor of the U.S. Government under contract No. W-31-109-ENG-38. Accordingly, the U.S.Government retains a nonexclusive, royalty-freelicense

More information

Westfield Fashion Square Restaurant Renovation Project Council File ; CPC VZC; ENV ND

Westfield Fashion Square Restaurant Renovation Project Council File ; CPC VZC; ENV ND 355 South Grand Avenue Los Angeles, California 90071-1560 Tel: +1.213.485.1234 Fax: +1.213.891.8763 www.lw.com December 12, 2016 BY HAND DELIVERY AND EMAIL Councilmember Jose Huizar, Chair Councilmember

More information

Fixing America s Surface Transportation Act: FAST Act Implications for the Region

Fixing America s Surface Transportation Act: FAST Act Implications for the Region Fixing America s Surface Transportation Act: FAST Act Implications for the Region Connie Kozlak Metropolitan Transportation Services Mark Fuhrmann Metro Transit Ed Petrie Metro Transit Metropolitan Council

More information

City Council Study Session Retail Market Analysis

City Council Study Session Retail Market Analysis November 29, 2011 City Council Study Session Retail Market Analysis November 29, 2011 Economic Development & Redevelopment City of Santa Cruz Background Robert Gibbs Founding New Urbanist Principal of

More information

PLANNING DEPARTMENT ADMINISTRATION

PLANNING DEPARTMENT ADMINISTRATION PLANNING DEPARTMENT ADMINISTRATION Support Division Planning & Community Zoning Administration Review & Compliance Land Use & Design Rezoning & Permitting Plan Review Community LDO Management Zoning &

More information

Stakeholders and Money. Donna Ann Harris, Heritage Consulting Inc. & Diane C. Williams, Business Districts Inc.

Stakeholders and Money. Donna Ann Harris, Heritage Consulting Inc. & Diane C. Williams, Business Districts Inc. Stakeholders and Money Donna Ann Harris, Heritage Consulting Inc. & Diane C. Williams, Business Districts Inc. Introduction Brief overview of Main Street Four Point Approach Integration of NYMS Housing

More information

The Public Participation Plan for Transportation Planning

The Public Participation Plan for Transportation Planning 2017 The Public Participation Plan for Transportation Planning Adopted by TCRPC Commission on April 26, 2017 3135 Pine Tree Road, Suite 2C Lansing, Michigan 48911 Toll Free: 1.800.619.6676 Phone: 517.393.0342

More information

NC General Statutes - Chapter 136 Article 19 1

NC General Statutes - Chapter 136 Article 19 1 Article 19. Congestion Relief and Intermodal 21 st Century Transportation Fund. 136-250. Congestion Relief and Intermodal Transportation 21 st Century Fund. There is established in the State treasury the

More information

CITY OF ANN ARBOR ECONOMIC COLLABORATIVE TASK FORCE REPORT

CITY OF ANN ARBOR ECONOMIC COLLABORATIVE TASK FORCE REPORT CITY OF ANN ARBOR ECONOMIC COLLABORATIVE TASK FORCE REPORT Background Ann Arbor City Council has determined that economic health is one of its key priority areas. Economic sustainability and growth create

More information

City of Palo Alto (ID # 4425) Planning & Transportation Commission Staff Report

City of Palo Alto (ID # 4425) Planning & Transportation Commission Staff Report City of Palo Alto (ID # 4425) Planning & Transportation Commission Staff Report Report Type: Meeting Date: 1/29/2014 Summary Title: Review of the Business and Economics Element of the Comprehensive Plan

More information

METHODOLOGY - Scope of Work

METHODOLOGY - Scope of Work The scope of work for the Truckee West River Site Redevelopment Feasibility Study will be undertaken through a series of sequential steps or tasks and will comprise four major tasks as follows. TASK 1:

More information

Chapter 9: Economic Development

Chapter 9: Economic Development Chapter 9: Economic Development 9.0 Accomplishments Since 2007 As the economic driver for the State, New Castle County continues to review development regulations and offer additional incentives and enhancements

More information

Lessons Learned for a Transit Public-Private Partnership. Phillip A. Washington, General Manager Regional Transportation District

Lessons Learned for a Transit Public-Private Partnership. Phillip A. Washington, General Manager Regional Transportation District Lessons Learned for a Transit Public-Private Partnership Phillip A. Washington, General Manager Regional Transportation District Feb. 7, 2011 The RTD FasTracks Plan 122 miles of new light rail and commuter

More information

CITY OF LA CENTER PUBLIC WORKS

CITY OF LA CENTER PUBLIC WORKS CITY OF LA CENTER PUBLIC WORKS TRAFFIC CALMING PROGRAM APPROVED PER RESOLUTION 08-304 ON DECEMBER 10, 2008 TABLE OF CONTENTS PAGE Summary... 1 Procedures... 2 Project Eligibility... 2 Project Funding &

More information

Urban Partnership Communications Plan

Urban Partnership Communications Plan Urban Partnership Communications Plan CONTENTS URBAN PARTNERSHIP OVERVIEW 01 COMMUNICATIONS PLAN 02 TOLLING 04 TRANSIT 05 TECHNOLOGY 06 TRANSPORTATION DEMAND MANAGEMENT 07 APPENDICES A: SR 520 Bridge Tolling

More information

Financing Transit Projects with Traditional and Innovative Sources And Mechanisms

Financing Transit Projects with Traditional and Innovative Sources And Mechanisms Financing Transit Projects with Traditional and Innovative Sources And Mechanisms Exploring the Potential for Bus Rapid Transit and Transit- Oriented Development in the I- 287/Tappan Zee Bridge Corridor

More information

PINELLAS COUNTY DEO#12-1ESR

PINELLAS COUNTY DEO#12-1ESR Agenda Item #3.H.11 02/13/12 LOCAL GOVERNMENT COMPREHENSIVE PLAN PROPOSED AMENDMENT REPORT PINELLAS COUNTY DEO#12-1ESR 1 THIS PAGE INTENTIONALLY LEFT BLANK 2 PINELLAS COUNTY LPA 22-10-11 Expedited State

More information

$5.2 Billion Transportation Funding Deal Announced, includes $1.5 Billion for Local Streets and Roads

$5.2 Billion Transportation Funding Deal Announced, includes $1.5 Billion for Local Streets and Roads 1400 K Street, Suite 400 Sacramento, California 95814 Phone: (916) 658-8200 Fax: (916) 658-8240 www.cacities.org $5.2 Billion Transportation Funding Deal Announced, includes $1.5 Billion for Local Streets

More information

NORTHWEST SECTOR STUDY PHASE I REPORT. Approved 17 February 2015 (Resolution )

NORTHWEST SECTOR STUDY PHASE I REPORT. Approved 17 February 2015 (Resolution ) EMBRACE ENHANCE EXPAND NORTHWEST SECTOR STUDY PHASE I REPORT Approved 17 February 2015 (Resolution 2015-02-022) This plan has been prepared by Parsons Brinckerhoff and their subconsultants for the City

More information

FUNDING SOURCES. Appendix I. Funding Sources

FUNDING SOURCES. Appendix I. Funding Sources Appendix I. Funding Sources FUNDING SOURCES planning and related efforts can be funded through a variety of local, state, and federal sources. However, these revenues have many guidelines in terms of how

More information

APA/PAW 2013 Joint Awards Program Submittal

APA/PAW 2013 Joint Awards Program Submittal May 30, 2013 APA/PAW Awards Committee Washington APA Office 603 Stewart Street, Suite 610 Seattle, WA 98101 Dear APA/PAW Awards Committee: RE: APA/PAW 2013 Joint Awards Program Submittal Enclosed is a

More information

Florida Job Growth Grant Fund Public Infrastructure Grant Proposal

Florida Job Growth Grant Fund Public Infrastructure Grant Proposal Florida Job Growth Grant Fund Public Infrastructure Grant Proposal Proposal Instructions: The Florida Job Growth Grant Fund Proposal (this document) must be completed by the governmental entity applying

More information

PROGRAM GUIDE. ELIGIBLE APPLICANTS To be eligible to apply to the program:

PROGRAM GUIDE. ELIGIBLE APPLICANTS To be eligible to apply to the program: PROGRAM GUIDE PROGRAM PURPOSE AND GOAL The City of Williams Lake is pleased to provide the business façade improvement program with funding from Northern Development Initiative Trust. The purpose of the

More information

In developing the program, as directed by the Board (Attachment A), staff used the following framework:

In developing the program, as directed by the Board (Attachment A), staff used the following framework: _... ~ Los Angeles County ~ T~"'-"- Metro One Gateway Plaza Los Angeles, CA 90012-2952 213.922.200C metro. net 15 REVISED PLANNING AND PROGRAMMING COMMITTEE SEPTEMBER 18, 2013 SUBJECT: ACTION: OPEN STREETS

More information

POLY HIGH REDEVELOPMENT PROJECT AREA FIVE-YEAR IMPLEMENTATION PLAN

POLY HIGH REDEVELOPMENT PROJECT AREA FIVE-YEAR IMPLEMENTATION PLAN POLY HIGH REDEVELOPMENT PROJECT AREA FIVE-YEAR IMPLEMENTATION PLAN Fiscal Year 2010 Fiscal Year 2014 (October 1, 2009 - September 30, 2014) CITY OF LONG BEACH REDEVELOPMENT AGENCY 333 West Ocean Boulevard,

More information

2018 POLICY FRAMEWORK FOR PSRC S FEDERAL FUNDS

2018 POLICY FRAMEWORK FOR PSRC S FEDERAL FUNDS 2018 POLICY FRAMEWORK FOR PSRC S FEDERAL FUNDS TABLE OF CONTENTS Section 1: Background... 3 A. Policy Framework... 3 B. Development of the 2019-2022 Regional Transportation Improvement Program (TIP)..

More information

REQUEST FOR APPLICATIONS. Technical Advisory Panels for Two DRCOG Communities. Urban Land Institute Colorado District Council (ULI Colorado)

REQUEST FOR APPLICATIONS. Technical Advisory Panels for Two DRCOG Communities. Urban Land Institute Colorado District Council (ULI Colorado) REQUEST FOR APPLICATIONS Technical Advisory Panels for Two DRCOG Communities Urban Land Institute Colorado District Council (ULI Colorado) Date of Issuance: February 1, 2018 Due date for applications:

More information

Dane County Comprehensive Plan Economic Development Goals & Objectives HED Work Group July 7, 2006

Dane County Comprehensive Plan Economic Development Goals & Objectives HED Work Group July 7, 2006 Dane County Comprehensive Plan Economic Development Goals & Objectives HED Work Group July 7, 2006 Section I. Goal 1: Dane County will help to build and promote a robust, sustainable economy that enhances

More information

District of 100 Mile House. Business Façade Improvement Program Guidelines

District of 100 Mile House. Business Façade Improvement Program Guidelines District of 100 Mile House Business Façade Improvement Program Guidelines - 2014 Business Façade Improvement Program Guide 2014 District of 100 Mile House Façade Improvement Program Guidelines Program

More information

Community Advisory Panel Meeting #

Community Advisory Panel Meeting # Community Advisory Panel Meeting # 3 10.10.18.. Agenda Welcome and Introductions Community Conversations Review mailing in anticipation of next two community meetings Work Plan / Schedule Alternatives

More information

Comprehensive Planning Grant. Comprehensive Plan Checklist

Comprehensive Planning Grant. Comprehensive Plan Checklist Comprehensive Planning Grant Comprehensive Plan Checklist This form was updated April 2010 Comprehensive Planning Grant Program Department of Administration Division of Intergovernmental Relations 101

More information

+! % / 0/ 1 2, 2 2, 3 1 ",, 4 +! % # ! 2, $

+! % / 0/ 1 2, 2 2, 3 1 ,, 4 +! % # ! 2, $ Lakeland Vision is an independent, non-profit organization. It was formed in 1998 with the goal of creating and implementing a comprehensive, action-oriented vision for the future of the greater Lakeland

More information

APPENDIX METROFUTURE OVERVIEW OVERVIEW

APPENDIX METROFUTURE OVERVIEW OVERVIEW APPENDIX B METROFUTURE OVERVIEW OVERVIEW Land use decisions and many economic development decisions in Massachusetts are controlled directly by local municipalities through zoning. This planning is guided

More information

Business Façade Improvement Program Available

Business Façade Improvement Program Available MEDIA RELEASE City of Williams Lake For Immediate Release March 1, 2017 Tel: 250-392-2311 Fax: 250-392-4408 450 Mart Street Williams Lake, BC V2G 1N3 Business Façade Improvement Program Available Northern

More information

Tacony Community Development Corporation Façade Improvement Program Guidelines and Application Form

Tacony Community Development Corporation Façade Improvement Program Guidelines and Application Form Tacony Community Development Corporation Façade Improvement Program Guidelines and Application Form I. Introduction & Objectives The Tacony Community Development Corporation (TCDC) Façade Improvement Program

More information

Future Trends & Themes Summary. Presented to Executive Steering Committee: April 12, 2017

Future Trends & Themes Summary. Presented to Executive Steering Committee: April 12, 2017 Future Trends & Themes Summary Presented to Executive Steering Committee: April 12, 2017 Vision Workshop Regional/Local Themes The region and the Prince William area share the following key themes: Future

More information

SUMMARY OF THE GROW AMERICA ACT As Submitted to Congress on April 29, 2014

SUMMARY OF THE GROW AMERICA ACT As Submitted to Congress on April 29, 2014 SUMMARY OF THE ACT As Submitted to Congress on April 29, 2014 The U.S. Department of Transportation (USDOT) submitted the Generating Renewal, Opportunity, and Work with Accelerated Mobility, Efficiency,

More information

US 50/SOUTH SHORE COMMUNITY REVITALIZATION PROJECT

US 50/SOUTH SHORE COMMUNITY REVITALIZATION PROJECT US 50/SOUTH SHORE COMMUNITY REVITALIZATION PROJECT ABOUT THE PROJECT Frequently Asked Questions What is the US 50/South Shore Community Revitalization Project? A transportation project along U.S. Highway

More information

Appendix 5 Freight Funding Programs

Appendix 5 Freight Funding Programs 5. Chapter Heading Appendix 5 Freight Programs Table of Contents 4.1 Surface Transportation Block Grant (STBG);... 5-1 4.2 Transportation Investment Generating Economic Recovery Discretionary Grant Program

More information

Client: Boulder County Transportation Project: SH 119 Bus Rapid Transit & Bikeway Facility Design

Client: Boulder County Transportation Project: SH 119 Bus Rapid Transit & Bikeway Facility Design Client: Boulder County Transportation Project: SH 119 Bus Rapid Transit & Bikeway Facility Design I. Applicant (Client) Information Organization Name and Address Boulder County Transportation, 2525 13th

More information

Greater Reno-Sparks-Tahoe Economic Development Three-Year Strategic Plan

Greater Reno-Sparks-Tahoe Economic Development Three-Year Strategic Plan Greater Reno-Sparks-Tahoe Economic Development Three-Year Strategic Plan 4.26.12 TABLE OF CONTENTS INTRODUCTION...3 COMMUNITY ASSESSMENT...5 TARGET SECTORS...7 STRATEGIES & METRICS...9 Entrepreneurial

More information

Coolidge - Florence Regional Transportation Plan

Coolidge - Florence Regional Transportation Plan Coolidge - Florence Regional Transportation Plan A Partnership Among the City of Coolidge, Town of Florence, and ADOT FINAL REPORT Kimley-Horn Kimley Kimley-Horn and and Associates, Associates, Inc. Inc.

More information

PUBLIC PARTICIPATION PLAN

PUBLIC PARTICIPATION PLAN Prepared for: Metropolitan Transportation Planning Organization for the Gainesville Urbanized Area 2040 Long Range Transportation Plan PUBLIC PARTICIPATION PLAN Prepared by: Atkins Global & Quest Corporation

More information

2018 Regional Solicitation for Transportation Projects

2018 Regional Solicitation for Transportation Projects 2018 Regional Solicitation for Transportation Projects Regional Solicitation Workshop April 17 2018 Regional Solicitation Purpose To distribute federal Surface Transportation Block Grant Program (STBGP)

More information

City of Stockton. Legislation Text APPROVE NEW STOREFRONT BEAUTIFICATION MICRO GRANT PROGRAM FOR EXTERIOR IMPROVEMENTS TO LOCAL COMMERCIAL BUSINESSES

City of Stockton. Legislation Text APPROVE NEW STOREFRONT BEAUTIFICATION MICRO GRANT PROGRAM FOR EXTERIOR IMPROVEMENTS TO LOCAL COMMERCIAL BUSINESSES City of Stockton Legislation Text File #: 18-4835, Version: 1 APPROVE NEW STOREFRONT BEAUTIFICATION MICRO GRANT PROGRAM FOR EXTERIOR IMPROVEMENTS TO LOCAL COMMERCIAL BUSINESSES RECOMMENDATION It is recommended

More information

League Task Force on the Next Generation of Economic Development Tools Background Report: Community Development Corporations April 12, 2012

League Task Force on the Next Generation of Economic Development Tools Background Report: Community Development Corporations April 12, 2012 League Task Force on the Next Generation of Economic Development Tools Background Report: Community Development Corporations April 12, 2012 For the past few months, the League Task Force on the Next Generation

More information

SUNIGA/LEMAY MULTI-MODAL AND FREIGHT CONNECTIVITY PROJECT

SUNIGA/LEMAY MULTI-MODAL AND FREIGHT CONNECTIVITY PROJECT June 4, 2015 Existing Condition Improved Condition Table of Contents APPLICATION LETTER...i EXECUTIVE SUMMARY...1 A. PROJECT DESCRIPTION...4 B. PROJECT LOCATION...6 C. PROJECT PARTIES...9 D. GRANT FUNDS

More information

Request for Proposals: CDBG Housing Rehabilitation Loan Program

Request for Proposals: CDBG Housing Rehabilitation Loan Program Request for Proposals: CDBG Housing Rehabilitation Loan Program To Provide Administrative Services for Community Development Block Grant Revolving Loan Funds Community Development Authority of the City

More information

DISTRICT OF KITIMAT. Business Façade Improvement Program 2017

DISTRICT OF KITIMAT. Business Façade Improvement Program 2017 DISTRICT OF KITIMAT Business Façade Improvement Program 2017 Program Purpose and Goals The District of Kitimat, in collaboration with the Kitimat Chamber of Commerce, aims to enhance economic development

More information

NORTH CENTRAL TEXAS COUNCIL OF GOVERNMENTS METROPOLITAN PLANNING ORGANIZATION REQUEST FOR PROPOSALS

NORTH CENTRAL TEXAS COUNCIL OF GOVERNMENTS METROPOLITAN PLANNING ORGANIZATION REQUEST FOR PROPOSALS NORTH CENTRAL TEXAS COUNCIL OF GOVERNMENTS METROPOLITAN PLANNING ORGANIZATION REQUEST FOR PROPOSALS CITY OF CEDAR HILL CITY CENTER TRANSIT-ORIENTED DEVELOPMENT PLAN August 19, 2011 REQUEST FOR PROPOSALS

More information

Diridon Station Joint Policy Advisory Board MINUTES

Diridon Station Joint Policy Advisory Board MINUTES CALL TO ORDER Diridon Station Joint Policy Advisory Board Friday, December 17, 2010 MINUTES The Regular Meeting of the Diridon Station Joint Policy Advisory Board ( Committee ) was called to order at 3:06

More information

City of Edina, Minnesota GrandView Phase I Redevelopment, 5146 Eden Avenue Request for Interest for Development Partner

City of Edina, Minnesota GrandView Phase I Redevelopment, 5146 Eden Avenue Request for Interest for Development Partner City of Edina, Minnesota GrandView Phase I Redevelopment, 5146 Eden Avenue Request for Interest for Development Partner The City of Edina has a rich history of innovative developments that have become

More information

CASE STUDY: OVERVIEW OF A UNIVERSITY PROGRAM

CASE STUDY: OVERVIEW OF A UNIVERSITY PROGRAM CASE STUDY: OVERVIEW OF A UNIVERSITY PROGRAM Example of Option #1: Pre-Tax Benefits Plus Secondary Measures (secondary measures not required with Option #1) San Jose State University (SJSU) is a public

More information

REQUEST FOR PROPOSALS

REQUEST FOR PROPOSALS REQUEST FOR PROPOSALS Downtown Triangle Redevelopment 1 st Street North, East Jackson Street, and Market Street City of Wisconsin Rapids 444 West Grand Avenue, Wisconsin Rapids, WI 54495 February 2017

More information

Brownfield Redevelopment The Developer s Perspective

Brownfield Redevelopment The Developer s Perspective Brownfield Redevelopment The Developer s Perspective About CommunitySmith Principles and Priorities CommunitySmith exists to create successful community revitalization projects by facilitating open and

More information

Appendix 5: Port Annual Economic Development Plan

Appendix 5: Port Annual Economic Development Plan Appendix 5: Port Annual Economic Development Plan Appendix 5 Page A5-1 Annual Economic Development Plan PORT OF WALLA WALLA ECONOMIC DEVELOPMENT PLAN FOR WALLA WALLA COUNTY YEAR 2012 Port of Walla Walla

More information

BROWARD COUNTY TRANSIT MAJOR SERVICE CHANGE TO 595 EXPRESS SUNRISE - FORT LAUDERDALE. A Title VI Service Equity Analysis

BROWARD COUNTY TRANSIT MAJOR SERVICE CHANGE TO 595 EXPRESS SUNRISE - FORT LAUDERDALE. A Title VI Service Equity Analysis BROWARD COUNTY TRANSIT MAJOR SERVICE CHANGE TO 595 EXPRESS SUNRISE - FORT LAUDERDALE A Title VI Service Equity Analysis Prepared September 2015 Submitted for compliance with Title VI of the Civil Rights

More information

PUBLIC PARTICIPATION PLAN

PUBLIC PARTICIPATION PLAN 0 PUBLIC PARTICIPATION PLAN GENERAL The City of Tyler currently serves as the fiscal agent for the Tyler Area Metropolitan Planning Organization (MPO), which represents the Tyler Metropolitan Study Area.

More information

Partial Action Plan for New York Business Recovery and Economic Revitalization

Partial Action Plan for New York Business Recovery and Economic Revitalization LOWER MANHATTAN DEVELOPMENT CORPORATION in partnership with EMPIRE STATE DEVELOPMENT and NEW YORK CITY ECONOMIC DEVELOPMENT CORPORATION Partial Action Plan for New York Business Recovery and Economic Revitalization

More information

SAN JOSE CAPITAL OF SILICON VALLEY

SAN JOSE CAPITAL OF SILICON VALLEY CITY OF "3 SAN JOSE CAPITAL OF SILICON VALLEY COUNCIL AGENDA: 11/29/16 ITEM: Memorandum TO: HONORABLE MAYOR AND CITY COUNCIL FROM: Barry Ng Jim Ortbal SUBJECT: 7652 - ST. JOHN STREET MULTI MODAL IMPROVEMENTS

More information

Economic Development Strategic Plan Executive Summary Delta County, CO. Prepared By:

Economic Development Strategic Plan Executive Summary Delta County, CO. Prepared By: Economic Development Strategic Plan Executive Summary Delta County, CO Prepared By: 1 Introduction In 2015, Region 10, a 501(c)(3) Economic Development District that services six counties in western Colorado,

More information

THE STATION AT POTOMAC YARD. Public, Private, and Non-Profit Collaboration BY HELEN S. MCILVAINE

THE STATION AT POTOMAC YARD. Public, Private, and Non-Profit Collaboration BY HELEN S. MCILVAINE THE STATION AT POTOMAC YARD Public, Private, and Non-Profit Collaboration BY HELEN S. MCILVAINE The Station at Potomac Yard is a creative and cooperative approach to meeting multiple community needs in

More information