Port of Portland FY11-13 Disadvantaged Business Enterprise (DBE) Goal

Similar documents
HILLSBOROUGH COUNTY AVIATION AUTHORITY THREE YEAR OVERALL DISADVANTAGED BUSINESS ENTERPRISE GOAL Federal Fiscal Years 2017, 2018 and 2019

Memphis International Airport

Disparity Study Action Plan June 10, 2009 Recommendation: 10-1 Emerging Small Business (ESB) Program Action: Impact: Timeline:

City of Houston Office of Business Opportunity

NEW ORLEANS AVIATION BOARD (NOAB) DISADVANTAGED BUSINESS ENTERPRISE (DBE) PROGRAM Goal Setting Methodology and Calculations

Sandpoint Airport. FY Overall Goal Amendment to the Disadvantaged Business Enterprise (DBE) Program

ATTACHMENT 5. Section 26.45: Overall DBE Three-Year Goal Methodology

Port of Portland Small Business Program FFY16

Santa Clara Valley Transportation Authority Disadvantaged Business Enterprise (DBE) Program

Update on the 2007 Disparity Study February 2011

Port Small Business Development Program

TRANSIT JOINT POWERS AUTHORITY FOR MERCED COUNTY

AIRPORT CONCESSIONS DISADVANTAGED BUSINESS ENTERPRISE (ACDBE) PROGRAM

The Division expects to let the following FTA/ USDOT-assisted projects in FFYs :

Historically Underutilized Business (HUB) Strategic Plan

Historically Underutilized Business (HUB) Strategic Plan

City of Arlington, Texas LOCAL & MWBE POLICY

Solano County Transit (SolTrans) Overall Disadvantaged Business Enterprise (DBE) Goal FFY through FFY

Disadvantaged Business Enterprise Program and Triennial DBE Goal Setting Methodology and Rationale

Historically Underutilized Business (HUB) Strategic Plan

August 9, Re: DBE Program Triennial Goal Concurrence - Recipient ID #1674. Dear Mr. Smith:

APPENDIX A. Definitions of Terms

CONTRACTING AND PURCHASING

FEDERAL TRANSIT ADMINISTRATION DISADVANTAGED BUSINESS ENTERPRISE OVERALL GOAL APPROVE PROPOSED AMENDMENT TO DBE OVERALL GOAL

City of Arlington, Texas

Disadvantaged Business Enterprise (DBE) Program and Goals for LSCOG

BUSINESS DIVERSITY OUTREACH PROGRAM

SECTION II. Collection and Analysis of Metro Contract Data

NDOT Civil Rights DBE Program Small Business Element

Proposal to Increase M/W/ESB Utilization in PTE Contracting

DISADVANTAGED BUSINESS ENTERPRISE (DBE) PROGRAM

Memorandum CAPITAL OF SILICON VALLEY

PROCEDURE Metropolitan Council Underutilized Business (MCUB) Program

2017 Statewide On-Call Design Request for Proposal

AIRPORT CONCESSION DISADVANTAGED BUSINESS ENTERPRISE PLAN. CITY OF PORTLAND, MAINE, dba PORTLAND INTERNATIONAL JETPORT (PWM)

Sheltered Market Program Description Background

LOWELL REGIONAL TRANSIT AUTHORITY

ABC S of DBE & ACDBE Programs

Disadvantaged Business Enterprise (DBE) Utilization on City Projects. Division of Affirmative Action

The airport s non-rental car concession opportunities are detailed below.

Procedure Manual. Minority/Women Business Enterprise Program

Florida Department of Transportation 605 Suwannee Street Tallahassee, FL

AIRPORT CONCESSION DISADVANTAGED BUSINESS ENTERPRISE (ACDBE)

LOUIS ARMSTRONG NEW ORLEANS INTERNATIONAL AIRPORT AIRPORT CONCESSIONS DISADVANTAGED BUSINESS ENTERPRISES GOAL SETTING METHODOLOGY

Metropolitan Washington Airports Authority. Request for Qualifications Information. Architectural / Engineering Design Services.

C (Procedure) Small, Minority, Women and Veteran Owned Business Enterprise Program PURPOSE DEFINITIONS

Disadvantaged Business Enterprise Program Open House

OCTOBER 1, 2015 ADDENDUM NO. 1 FOR REQUEST FOR QUALIFICATIONS ( RFQ ) FOR DESIGN CONSULTING SERVICES (TARGET MARKET) SPECIFICATION NO.

REQUEST FOR PROPOSALS for the Development of Sidewalk Inventory for the DVRPC Region

REQUEST FOR QUALIFICATIONS CONSULTING SERVICES FOR WALLA WALLA REGIONAL AIRPORT (ALW) WALLA WALLA, WASHINGTON. October 2, 2018

San Antonio Regional Business Disparity Causation Analysis Study

Request for Proposal (RFP) The Klamath Tribes Youth Fitness Center Klamath Tribes Housing Department (KTHD) RFP # 09-KTHD17

Florida Department of Transportation (FDOT) Business Participation Plan FY 13/14

2018 New Orleans Disparity Study

ACI-NA SMALL AIRPORTS CONFERENCE FAA CIVIL RIGHTS - DBE REGULATORY UPDATE. Federal Aviation Administration

SUBCONTRACTING ON CDOT CONSTRUCTION PROJECTS Ramp Up Ridgway!

How to do Business with NAVAL FACILITIES ENGINEERING COMMAND for Architect Engineer Contracts

REQUEST FOR SEALED PROPOSAL. ADVERTISEMENT for STREET CONSTRUCTION SERVICES. RFP STREET WIDENING and TRAFFIC SIGNAL INSTALLATION

SUSQUEHANNA AREA REGIONAL AIRPORT AUTHORITY

PRE-SUBMITTAL CONFERENCE REQUEST FOR QUALIFICATIONS (RFQ)

Disadvantaged Business Enterprise (DBE) Program for Federally-Assisted Projects. Federal Fiscal Years

DBE/Small Business Workshop. June 12, 2015

UC Berkeley Supplier Diversity Basics. Module 1: Policy and Regulatory Requirements

Disadvantaged Business Enterprise Plan (DBE) For Projects Funded Through the Federal Transit Administration (FTA) FY to FY

PRE-SUBMITTAL CONFERENCE REQUEST FOR QUALIFICATIONS (RFQ)

ARE YOU READY FOR PRIMETIME II? & SBE/DBE CERTIFICATION BASICS

APPENDIX A SCOPE OF WORK

Hosted by the SLMBE Office

Mid-Coast Corridor Transit Project Construction Bench Open House November 9, 2016

REQUEST FOR QUALIFICATIONS FOR Energy Services Master Agreement

DISADVANTAGED BUSINESS ENTERPRISE RACE-NEUTRAL IMPLEMENTATION AGREEMENT FOR LOCAL AGENCIES

REQUEST FOR QUALIFICATIONS

KDOT Procurement Guidelines for STP/CMAQ Funded Planning, Education, and Outreach Projects Effective 10/1/12

CITY OF SAN ANTONIO AVIATION DEPARTMENT 49 CFR PARTS 26 & 23 DBE AND SBEDA PROGRAMS OVERVIEW

M/WBE PROGRAM OVERVIEW

CITY OF FRESNO AIRPORTS DEPARTMENT REQUEST FOR QUALIFICATIONS (RFQ) FOR CONSULTING SERVICES FRESNO YOSEMITE INTERNATIONAL AIRPORT

8, 2018 REQUEST FOR PROPOSALS (RFP): G

Request for Proposals

SOUTHERN FLORIDA MINORITY SUPPLIER DEVELOPMENT COUNCIL CONSTRUCTION INDUSTRY GROUP MEETING

UNION COUNTY MINORITY AND SMALL BUSINESS GUIDELINES AND OUTREACH PLAN

PRE-PROPOSAL CONFERENCE

City and County of Denver International Airport. Airport Concession Disadvantaged Business Enterprise Program. Table of Contents

Highway Construction Training and Disadvantaged Business Enterprise Program

FAA AIRPORT IMPROVEMENT PROGRAM GRANTS

APPENDIX A. DBE Information to be submitted with Proposal

The DBE Program is an outreach, education, and objectives program designed to increase the participation of DBEs in the CWSRF Program.

ONTARIO INTERNATIONAL AIRPORT

Addendum No.3 to ITB Wakulla County Fire and EMS Station Issued: November 1, 2017

HUB Participation: Historical Analysis

Small Business Subcontracting Plans & Reporting

SUBJECT: ACTIONS RELATED TO THE MINETA SAN JOSE INTERNATIONAL AIRPORT - PERIMETER SECURITY TECHNOLOGY INFRASTRUCTURE

Marin County Transit District Overall Disadvantaged Business Enterprise (DBE) Goal Federal Fiscal Years

APPENDIX B Consultant Title VI Evaluation Form

LANDSCAPE AND IRRIGATION MAINTENANCE SERVICES SYSTEMWIDE (EXCLUDING METRO ORANGE LINE)

FOR PROFESSIONAL DESIGN SERVICES

How to Obtain an Architect-Engineer Contract with NAVFAC

Contract Compliance Program

Department of Homeland Security. Office of Small and Disadvantaged Business Utilization (OSDBU) Homeland Security

Membrane Pre-Selection Request For Proposal

Informational Workshop How to do Business with the City of Irvine March 31, 2011

Transcription:

Port of FY11-13 Disadvantaged Business Enterprise (DBE) Goal During Federal Fiscal Years FY11, FY12, FY13, October 1, 2010 September 30, 2013, the Port of plans to solicit bids/proposals for the following projects pending agreement of Port stakeholders: Project Location Fiscal Year(s) Project Name Estimate Brief Description 2011 South Runway Rehab 2011-2013 Preconditioned Air PDX Gates 2012 Taxiway C East Rehabilitation 2013 RW 3/21 S Safety Area Grading 2013 TW E North & Exits Rehab 2013 TW E South & Exits $66,700,000 Rehabilitate Runway 10R/28L. Scope includes surface and structural pavement rehabilitation where necessary. $7,000,000 Install preconditioned air units at the remaining 35 loading bridges at PDX that currently do not have units including electrical system upgrades as required to meet additional electrical demand. $14,900,000 Rehabilitate taxiway C east of runway 3/21. Scope includes surface and structural pavement rehabilitation where necessary. $1,550,000 Re-grade and construct drainage improvements at the south end of runway 3/21. $9,300,000 Rehabilitate taxiway E and exits north of Runway 10R/28L. Scope includes surface and structural pavement rehabilitation where necessary. $11,600,000 Rehabilitate Taxiway E and exits south of Runway 10R/28L. 2013 TW E Centerline $1,900,000 Install centerline

Troutdale Lighting 2011 HIO Construct RW 12L/30R 2011 HIO RW 12-30 Threshold Rehab 2012 HIO Relocate Taxiway C 2012-2013 HIO RW 2-20 Relocation and Extend TW B 2013 TTD Reconstruct Rwy 7-25 lighting on Taxiway E between RWY 10L/28R and Taxiway E6. $6,455,000 Construct a new 3200' B-1 runway parallel to the main runway for use by light GA aircraft. $1,600,000 Mill and inlay an 80' x 2000' portion of Runway 30 touchdown zone. $4,512,600 This project will replace older taxiways with a new taxiway. $15,391,000 Extend runway 2-20 to a total length of 4200 feet, extend taxiways B & C 400 feet to connect new runway approximately 20 end. $9,100,000 Reconstruct existing 150; X 5400' runway; narrow to 100' wide, relocated/reconstruct edging lighting, construct required drainage improvements. To establish the Port of overall Disadvantaged Business Enterprise (DBE) goal for FY11-13, the Port uses the methodology found on the Office of Small and Disadvantaged Business Utilization (OSDBU) website (http://osdbuweb.dot.gov): Tips for Goal Setting in Disadvantaged Business Enterprise Programs. Step One Initially we identified the availability of DBE and non-dbe firms who are ready, willing and able to compete for AIP funded contracts that will be let by the Port of in FY11-13. The Port has determined our market area to be those firms that are in our BizTrak system data base. This data base is populated with businesses that have submitted bids/proposals on Port projects in the past and also includes businesses that have submitted bids/proposals as sub-contractors/sub-consultants to primary

bidders/proposers. The BizTrak system is linked with the Oregon State certification website therefore firms in our data base are updated weekly in regards to their certification status. The construction and architecture and engineering industry businesses in our market area are primarily located in Oregon and Washington states. The disparity study completed for the Port of in February 2009 identified the relevant market area for the construction, architecture and engineering business categories to be the state of Oregon, the MSA, and King County Washington. In reviewing the suppliers in the Port potential supplier list for the nine NAICS codes, 80% of the suppliers are located in Oregon and Washington states. We have identified the following work categories by NAICS that will be included in the four Port of pending projects planned for FY11-13: NAICS Description and Percent of Work DBE All 237310 Heavy Construction* 53 404 238210 Electrical Contractor 15 306 541370 Surveying 15 161 238910 Site Preparation Contractors 49 405 561990 All Other Support Services (traffic control) 22 87 561730 Landscape Service (seeding, erosion control) 21 143 238220 Plumbing, Heating, Air Conditioning 5 173 237110 Water and Sewer Line 10 265 484110 Trucking 20 85 541330 Engineering Services 41 915 *includes pavement milling, pavements/concrete, pavement/asphalt, drainage, excavation & embankment, trucking, and pavement painting. The Biz Trak system has a DBE Goal setting function that is programmed in accordance with the Office of Small and Disadvantage Business Utilization (OSDBU) website (http://osdbuweb.dot.gov): Tips for Goal Setting in Disadvantaged Business Enterprise Programs. This goal setting function is utilized along with a search of the state of Oregon Office of Minority, Women, and Emerging Small Business data base to develop a step one base figure. To determine the percent of DBE s ready, willing and able to compete for contracting opportunities at the Port of, the total number of DBE firms is divided by the total number of DBE plus non-dbe firms identified. Step One Base Figure = 251 DBE / 2944 DBE + Non-DBE = 10.49%

Step Two: The next step is to determine if an adjustment to the system generated Step One Base Figure is warranted. To make this determination a system generated list of DBE firms for the identified NAICS is reviewed and any DBE firms whose certifications are no longer current are deleted from the list of ready, willing and able DBE s. The list of all firms ready willing and able to compete for Port business opportunities is also reviewed to filter out businesses that are not relevant to the calculation because they are duplicates, they do not perform the type of work the Port is contracting out, they are no longer in business, or they are so far outside the Port geographical market are that they are not likely to submit a bid on a Port job. NAICS Description and Percent of Work DBE All 237310 Heavy Construction* 20 273 238210 Electrical Contractor 6 137 541370 Surveying 8 78 238910 Site Preparation Contractors 19 201 561990 All Other Support Services (traffic control) 6 8 561730 Landscape Service (seeding, erosion control) 3 103 238220 Plumbing, Heating, Air Conditioning 5 101 237110 Water and Sewer Line 6 241 484110 Trucking 16 47 541330 Engineering Services 29 281 Adjusted Step One Base Figure = 118 DBE / 1470 DBE + Non-DBE = 8.03% The Step One Base Figure can also be adjusted for recent past performance. The means utilized for achieving DBE participation changed at the Port of from fiscal year 05 and prior from a combination of race neutral and race conscious means to 100% race neutral in fiscal years 06, 07, 08 and 09. The Port returned to DBE project goals in FY10. As of September 1, 2010, DBE commitments on Port federally funded projects for FY10 is 5.2%; the overall DBE goal was 5%. The median past performance is determined by looking at the past performance for the five previous fiscal years. Past performance for those five years was: FY06 7.8% FY07 2.8% FY08 -.8% FY09 3.4% FY10 5.2% The median past performance is determined by placing the five numbers in number order from low to high and then selected number in the middle if there is an odd number of numbers;.8% 2.8% 3.4% 5.2% 7.8% 3.4% is the median past performance.

The Adjusted Step One Base Figure DBE goal is adjusted again by averaging the Adjusted Step One Base Figure with the median past performance on Port projects. Step Two Base Figure =((8.03+3.4)/2) = 5.715 % The FY11-13 Port DBE goal will not be adjusted for past performance because the Port did not establish DBE project goals in fiscal years 06, 07, 08, 09. Not establishing DBE project goals led to lower DBE participation. Making the adjustment for past participation would lower the goal below determined availability. The Port resumed DBE project goals in FY10. DBE goals of 6.5% and 5.1% were established on two airfield projects respectfully and the commitment to meet or exceed the goal was made by both awarded prime contractors. Overall DBE accomplishment for FY10 for the Port was 5.2%. Because DBE participation is trending upward with the resumption of DBE project goals, the Port will not adjust the FY11 13 overall Port DBE goal for past performance. The DBE goal for the Port of for FY011-13 not adjusted for past performance is 8.03%. The Port completed a disparity study in February 2009. MGT of America was the disparity study consultant. The study time period was July 1, 2002 June 30, 2007. The study findings and recommendations related to the Port DBE program were: Findings: 1. M/W/DBE Prime Utilization During the study period, 18 M/W/DBEs won prime construction contracts for $34.8 million on Port projects (13.22% of the total). 8 M/W/DBEs won prime architecture and engineering contracts for $1.2 million on Port projects (9.64% of the total). 2. M/W/DBE Prime Availability was 13.36% for construction prime contractors and 27.44% for architecture and engineering prime contractors. 3. Underutilization existed for African American, Hispanic American, Asian American, and Native American prime construction contractors and for Hispanic American, Asian American, Native American and Nonminority Women architecture and engineering prime contractors. 4. Over the current study period 73 M/W/DBE construction subcontractors won $14.1 million in construction subcontracts on Port projects (15.85% of the total construction subcontracts). 6 M/W/DBEs won 12 A&E subcontracts for $39,425 on Port projects (14.98%). 5. Underutilization existed during the study period for African American, Hispanic American, Asian American, and Native American construction subcontractors. Underutilization existed during the study period for African American, Asian American, Native American, and Nonminority Women architecture and engineering subcontractors. 6. The Port stopped placing DBE goals on construction contracts in 2006. Minority DBE construction subcontractor utilization stopped entirely at that point. The implementation of the ESB program in 2007 did not halt this pattern. There was,

however evidence of the use of M/WBEs that were not certified DBEs on projects without goals. Recommendations: 1. There is evidence supporting the reestablishment of race- and gender conscious DBE goals in construction and architecture and engineering subcontracting. This evidence is based on disparities in subcontracting, and the collapse in use of DBEs in the absence of goals on federal contracts, considerable statistical and anecdotal evidence of barriers in the private sector markets associated with race and gender after controlling for capacity variables. At the same time there was some evidence of the use of non-certified M/WBEs in the absence of goals. The strongest case for the restoration of DBE goals can be made for minority DBEs. Port DBE goals should be linked to certified DBE availability. Port DBE goals should not be a rigid quota placed on every project. The limited use of DBE goals means that the Port should continue to let out some opportunities without specific DBE goals and closely monitor DBE utilization on these projects. The objective should be to steadily increase the number of DBE dollars achieved without using race and gender conscious DBE goals. The following actions were taken in fiscal year 2010 based on the study recommendations: 1. The Port expanded the definition of small business to include all small businesses certified by the states of Oregon and Washington as minority-owned, disadvantaged-owned, women-owned, or emerging small business. 2. New Port guidelines for Work as Required contracts were adopted to better manage the associated task order process and the equitable use of awarded contractors. 3. An updated review of bonding and insurance requirements, including benchmarking with local agency peers, was conducted to verify that the Port was not setting bonding and insurance requirements that are not consistent with local peer agencies. No changes were made based on review and benchmarking. 4. DBE goals were resumed on FAA AIP projects. 2 FAA AIP projects were solicited with DBE goals and DBE goals were committed to by the awarded contractors. In addition to the return to DBE project goals, the Port will also continue to utilize race and gender neutral means to achieve DBE participation in Port of projects. Race and gender neutral means to achieve DBE goals include: Encouraging prime contractors to solicit bids from DBE sub contractors. Advertising projects in media that is focused toward minority and women owned businesses. Promoting Port projects at community outreach events including encouraging DBE contractors to consider bidding or proposing on Port projects.

Ongoing technical assistance and small business development facilitated through the Port of Mentor Protégé Program. Conducting open pre-bid meetings for all interested contractors. Providing contractors with a list of DBE certified businesses whose work scope matches work scope needed for specific projects. Evaluating and considering using various solicitation methods, including the RFP process where points can be awarded for small business inclusion, rather than the low bid process for award federally funded contracts. To solicit consultation regarding our FY11-13 overall DBE goal, the goal is posted on the Port of website, www.portofportland.com, Business Opportunities. Interested parties are invited to comment and are provided an email address for submitting comments regarding DBE availability, effects of discrimination on DBE opportunities, and the Port s efforts to solicit DBE participation. The goal will be adjusted if comments are received that warrant adjustment. The Port of adjusted overall DBE goal for fiscal year 2011-2013 is 8.03% DBE participation. Step Three The Port of has consistently implemented race/gender neutral means to achieve increased DBE participation including: To improve the accessibility of Port projects, we developed the online supplier registration and solicitation system. 4785 suppliers are currently registered, 245 or 5.1% are DBE firms. During fiscal year 10, 41 Port business opportunities were solicited using the online supplier solicitation system. The Port plans to upgrade the supplier registration and solicitation system in fiscal year 11 to improve accessibility of Port business opportunities. Through the Port of Mentor Protégé Program, we strive to help build the capacity and business know-how of the protégé firms. 56% of the current protégé firms are DBE and 31% of the graduated protégés are DBE. The Port actively participates in numerous local outreach events targeted to small businesses including certified DBE firms. The Port establishes Small Business goals on construction projects that do not receive federal funding, with an estimated value over $500,000. The Port includes participation of small businesses in Port Request for Proposals received for a variety of solicitation opportunities. Small business participation is valued at 10% of the possible evaluation points awarded. Small business is defined as any small business certified by Oregon or Washington states, including the race and gender neutral Emerging Small Business certification. During FY10, 7% of the subcontractors on Port projects were ESB sub-contractors. In conclusion, the overall DBE participation goal being submitted for the three fiscal years FY11, FY12, and FY13 by the Port of is 8% and will be accomplished using 7.5% race conscious means and.5% race neutral means.