SUBJECT: ACTIONS RELATED TO THE MINETA SAN JOSE INTERNATIONAL AIRPORT - PERIMETER SECURITY TECHNOLOGY INFRASTRUCTURE
|
|
- Eustace Eaton
- 5 years ago
- Views:
Transcription
1 COUNCIL AGENDA: 08/02/16 ITEM: 6.4 CITY OF SAN JOSE CAPITAL OF SILICON VALLEY TO: HONORABLE MAYOR AND CITY COUNCIL Memorandum FROM: Barry Ng Kimberly J. Becker Jennifer A. Maguire SUBJECT: SEE BELOW DATE: Approvec LOSF- SUBJECT: ACTIONS RELATED TO THE MINETA SAN JOSE INTERNATIONAL AIRPORT - PERIMETER SECURITY TECHNOLOGY INFRASTRUCTURE REASON FOR ADDENDUM In order to meet the schedule commitments for the reimbursable Federal Aviation Administration grant deadline, staff requests Council approval at its August 2, 2016, meeting. RECOMMENDATION (a) Reject all bids opened on July 14, 2016 for Norman Y. Mineta San Jose International Airport - Perimeter Security Technology Infrastructure. (b) Adopt a resolution authorizing the Director of Public Works to: (1) Determine the lowest responsive and responsible bidder, decide any bid protests, and award the construction contract for the Norman Y. Mineta San Jose International Airport - Perimeter Security Technology Infrastructure Re-Bid project in an amount not to exceed $8,110,000, contingent on the award and execution of an Airport Improvement Program (AIP) grant from the Federal Aviation Administration (FAA) of a minimum amount of at least $6,000,000 and the appropriation of sufficient funds; (2) Establish a construction contingency of fifteen percent (15%) of the amount of the construction contract for the project if the Director awards a contract; and
2 Page 2 (3) Issue any change orders up to the amount of the contingency if the Director awards a construction contract for the project. (c) Adopt a resolution making findings that identify specific companies and product by brand or trade name in the bid specifications for this Project is necessary for the following specific elements of this project to match other products in use at the Airport: Security Access Controls and Security Camera Services. (d) Adopt the following Appropriations Ordinance and Funding Sources Resolution Amendments in the Airport Capital Improvement Fund: (1) Increase the Perimeter Security Technology Infrastructure appropriation to the Airport Department in the amount of $6,450,000; and (2) Increase the estimate for Earned Revenue from Federal Government to the Airport Department in the amount of $6,450,000. (e) Adopt the following Appropriations Ordinance Amendments in the Airport Renewal and Replacement Fund: (1) Establish the Perimeter Security Technology Infrastructure appropriation to the Airport Department in the amount of $1,549,000; and (2) Decrease the Unrestricted Ending Fund Balance by $1,549,000. OUTCOME The recommendation provides the most efficient means of awarding and executing a construction contract for the Project given the tight time constraints. The 15 percent contingency will provide funding for any unanticipated work necessary for the proper completion of the project. BACKGROUND Airport staff periodically assembles a priority list of capital improvement projects that meet eligibility requirements for the FAA's AIP grant funding. This priority list is submitted to the FAA for review and prioritization based on the 15 general requirements for project funding, as outlined in the FAA's Airport Improvement Program Handbook. To be eligible for funding, proposed projects must demonstrate the advancement of one of the following AIP objectives: airport safety, airport security, airport capacity, meeting FAA standards, preservation of airport infrastructure through reconstruction or rehabilitation, protection and enhancing the environment, minimization of aircraft noise impacts, and airport planning. The Perimeter Security Technology Infrastructure fits the necessary security criteria for FAA - AIP grant funding.
3 Page 3 The Airport has been very diligent in enhancing the safety and security within the Air Operations Area (AOA). Among the recent projects the Airport has undertaken is the new perimeter security fence project. The fence project implements a much improved fencing standard which makes it significantly more difficult to gain access to the AOA. The next step in this process is implementing a new Perimeter Security Technology Infrastructure project that will further address security enhancements around the perimeter of the Airport into the AOA. The award of the Project is contingent upon the execution of the grant from the FAA. Project Description The Airport participated in a study conducted by the National Safe Skies Alliance (Safe Skies), that researched and tested various technologies and their reliability at several sites to deter unauthorized access to the AOA. The analysis performed by Safe Skies indicated that installation of a security camera based detection system along the AOA fence would provide an alert and tracking system to notify the Airport's operations center of a potential unauthorized entry of several intrusion types, -including human and animals. The City has applied for a FAA AIP grant and the application has been looked favorably by the FAA. In addition to the base bid scope of work, there are six add alternate bid items as follows: Add Alternative 1: Add Alternative 2: Add Alternative 3: Add Alternative 4: Add Alternative 5: Add Alternative 6: Adds the installation of biometric access control at vehicle and pedestrian gates. Adds camera installations around the North at Ewert road area. Adds camera installations adjacent to the CNG vicinity. Adds camera installation adjacent to the belly freight area. Adds camera installations to the West side adjacent to tower areas. Adds camera installations adjacent to the Parking Lot 5/6 (south of Terminal B) vicinity. Pending the receipt of the FAA grant, construction is scheduled to begin in September 2016 and is projected to be completed by April 2017.
4 Page 4 ANALYSIS This memorandum is being submitted for the August 2, 2016, City Council meeting. Staff originally opened bids for this Project on July 14, Staff recommends that the City Council reject these bids due to a technical irregularity in the bidding process based on sole sourcing certain vendors in the project specifications without first receiving City Council approval to do so. The City intends to rebid the project and open bids on August 11, Staff is recommending that the City Council delegate authority to the Director of Public Works to determine the lowest responsive and responsible bidder, decide any bid protests, and award the construction contract for the Project. The Director's authority to award the construction contract would be contingent on the Airport executing an FAA AIP grant in the minimum amount of $6,000,000 and the appropriation of sufficient funds. The FAA has given notice that the Perimeter Security Technology Infrastructure project has favorable potential to receive federal funding (AIP grants) in the upcoming fiscal year, which is anticipated to be awarded in August but no later than September 30, The FAA awards AIP grants based on actual bid results, as well as the availability of grant funds, therefore the award of the contract will be contingent upon the award of the AIP grant from the FAA. The maximum project costs of $13,000,000 and the maximum contract award of $8,110,000 have been established based on available funds and on FAA's grant limitations placed on reimbursement for project expenditures. Project Funding Source: Description Amount FAA Grant $10,480,000 Airport Local Match Funds $2,520,000 Total Project Funding $13,000,000 Staff recommends a 15 percent contingency that is consistent with Council Capital Project Contingency Policy, Resolution No , for building renovation work. Additionally, staff recommends the delegation of authority to the Director of Public Works for the issuance of change orders up to the amount of the contingency, in order to keep the critical construction timeline.
5 My 26, 2016 Page 5 Sole Source Requirements for Certain Project Elements State law generally prohibits public entities from "sole sourcing" materials, products and services. However, an exception is when the awarding authority makes a finding, which is described in the request for bids, that "sole sourcing" is necessary to match other products in use on a particular public improvement. Staff is requesting that the City Council adopt a resolution finding that the following companies and products must be "sole sourced" on this Project to match other products in use at the Airport. Staff would include the finding in the re-bid documents. Security Access Controls: Additions to the Door Access Control system must be able to integrate with the current access control system and be able to communicate with the existing security control and monitoring system to preserve uninterrupted coverage and reporting for Airport security staff. Stanley Security is the current holder of the contract to provide maintenance of the access control system for the airport. The local representatives for Stanley have been performing work at the Airport for several years. Security Cameras: The Airport's security cameras are controlled by, and provide information through, one integrated system that operates campus-wide. Continuity with the existing camera system must be maintained to ensure uninterrupted coverage and operability for Airport security staff. G4S is the current holder of the contract to provide security camera services for the Airport. Disadvantaged Business Enterprise Participation This project is funded in part with a federal US Department of Transportation/FAA AIP grant, the federal Disadvantaged Business Enterprise (DBE) Program regulations found in 49 CFR Part 26 apply. The City's current DBE participation goal for its US Department of Transportationfunded Airport Improvement Program in Federal Fiscal Years is 14.5% annually. City staff did extensive outreach to encourage DBE participation. Outreach efforts included: Identification of potential/possible subcontracting opportunities - four work areas identified; Identification of 214-certified DBEs in those four subcontracting work areas; blast sent to 214-certified DBEs, ethnic chambers, San Jose Chamber, and other interested organizations including Minority Business Consortium - blast included project information, subcontracting opportunities (NAICS Codes and Caltrans Work
6 July 26,2016 Page 6 Codes) bid date and time, Pre-Bid meeting date, time and location and DBE certification requirements; Posting project on Airport's and FAA's Opportunities website: Mineta San Jose International Airport; Follow-up phone calls to 123-certified DBEs to remind them about the project and encourage attendance at June 24 Pre-Bid Meeting; Held a Pre-Bid meeting with 25 company attendees, which included a networking opportunity at conclusion of the meeting (for primes and subcontractors to meet); and Based on demand, held a second Pre-Bid Meeting to tour the project location. EVALUATION AND FOLLOW-UP Staff will submit an Information Memorandum to Council after bids are opened which will summarize DBE outreach and participation on the project. PUBLIC OUTREACH To solicit contractors, this project will be listed on BidSync for 10 days and advertised on one day in the San Jose Post Record to meet the Federal Economic Development Administration (EDA) Grant Criteria. The complete bid package and project information for all Department of Public Works construction projects are available on BidSync for interested contractors, contractor organizations and builders' exchanges. This memo will be posted on the City's website for the August 2, 2016 Council agenda. FISCAL/POLICY ALIGNMENT The San Jose Municipal Code requires that capital projects at the Airport be consistent with the adopted Airport Master Plan. The proposed improvement project would be a minor alteration of existing Airport facilities and is therefore consistent with the adopted Airport Master Plan. pursuant to San Jose Municipal Code Section (B)(4).. COORDINATION The project and memorandum have been coordinated with the City Attorney's Office.
7 Page 7 COST SUMMARY/IMPLICATIONS 1. ESTIMATED COST OF PROJECT Project Delivery $ 3,673,000 Construction (Engineer's Estimate) $ 8,110,000 Contingency $ TOTAL ESTIMATED PROJECT COSTS $ 13,000,000 Prior year expenditures REMAINING PROJECT COSTS $325,000 $ 12,675, COST ELEMENTS OF AGREEMENT/CONTRACT: 3. SOURCE OF FUNDING: Airport Capital Improvement Fund Airport Revenue Bond Improvement Fund Airport Renewal and Replacement Fund 4. FISCAL IMPACT: The project has been reviewed and was determined that it will have no significant adverse impact on the Airport operating budget. BUDGET REFERENCE The table below identifies the fund and appropriations to fund the project recommended as part of this memorandum. Fund # Appn # Appn. Name Current Appn. Amount 520 R110 Revenue from Federal Government Rec. Budget Action Total Proposed Capital Budget Page Last Budget Action (Date, Ord. No.) $20,125,000 $6,450,000 $26,575,000 V-615 6/21/16, Perimeter Security Technology Infrastructure 527 NEW Perimeter Security Technology Infrastructure $3,769,000 $6,450,000 $10,219,000 V-619 6/21/16, N/A $1,549,000 $1,549,000 V-619 N/A
8 Subject: San Jos6 Airport Perimeter Security Technology Infrastructure Page Ending Fund Balance - Unrestricted Perimeter Security Technology Infrastructure $11,681,812 ($1,549,000) $10,132,812 V-619 6/21/16, $907,000 N/A $907,000 V-619 6/21/16, CEOA Resolution Nos and 71451, PP /s/ BARRY NG Director of Public Works /s/ KIMBERLY J. BECKER Director of Aviation //^y k i JENNIFER A. MAGUIRE Senior Deputy City Manager/ Budget Director I hereby certify that there will be available for appropriation in the Airport Capital Improvement Fund in , monies in excess of those heretofore appropriated therefrom, said excess being at least $6,450,000. /, /a / --.Ac*, JENNIFER A. MAGUIRE Senior Deputy City Manager/ Budget Director For questions please contact Michael O'Connell, Deputy Director, Public Works Department, at
Memorandum CAPITAL OF SILICON VALLEY
COUNCIL AGENDA: 10/06/15 ITEM: I CITY OF, SANlOSE Memorandum CAPITAL OF SILICON VALLEY TO: HONORABLE MAYOR AND CITY COUNCIL FROM: Kimberly J. Becker Barry Ng SUBJECT: SEE BELOW DATE: Approved D " e f/23
More informationSUBJECT: SEE BELOW DATE: May 26, 2016
COUNCIL AGENDA: 06-07-16 ITEM: A. CI CITY OF C: 3- SAN JOSE CAPITAL OF SILICON VALLEY TO: HONORABLE MAYOR AND CITY COUNCIL Memorandum FROM: Barry Ng SUBJECT: SEE BELOW DATE: Approved IL2_PS^ Date 5 ^ lip
More informationSAN JOSE CAPITAL OF SILICON VALLEY
CITY OF "3 SAN JOSE CAPITAL OF SILICON VALLEY COUNCIL AGENDA: 11/29/16 ITEM: Memorandum TO: HONORABLE MAYOR AND CITY COUNCIL FROM: Barry Ng Jim Ortbal SUBJECT: 7652 - ST. JOHN STREET MULTI MODAL IMPROVEMENTS
More informationMemorandum CAPITAL OF SILICON VALLEY
COUNCIL AGENDA: 01/26/16 ITEM: 3.6 CITY OF, SAN JOSE Memorandum CAPITAL OF SILICON VALLEY TO: HONORABLE MAYOR AND CITY COUNCIL FROM: Julia Cooper SUBJECT: SEE BELOW DATE: Approved Tjii 7 - - l
More informationSAN IPSE CAPITAL OF SILICON VALLEY
CITY OF *3 SAN IPSE CAPITAL OF SILICON VALLEY TO: HONORABLE MAYOR AND CITY COUNCIL COUNCIL AGENDA: 6-21-16 ITEM: -7 «o Memorandum FROM: Angel Rios, Jr. SUBJECT: PARKS, RECREATION AND NEIGHBORHOOD SERVICES
More information(b) A Grant Agreement with The Health Trust in the amount of $1,800,000 for Fiscal Year
COUNCIL AGENDA: 08/08/17 ITEM: 4.7 CITY OF C7 72 San Jose CAPITAL OF SILICON VALLEY TO: HONORABLE MAYOR AND CITY COUNCIL Memorandum FROM: Jacky Morales-Ferrand Jennifer A. Maguire SUBJECT: AWARD OF CONTRACTS
More informationCITY OF FRESNO AIRPORTS DEPARTMENT REQUEST FOR QUALIFICATIONS (RFQ) FOR CONSULTING SERVICES FRESNO YOSEMITE INTERNATIONAL AIRPORT
CITY OF FRESNO AIRPORTS DEPARTMENT REQUEST FOR QUALIFICATIONS (RFQ) FOR CONSULTING SERVICES FRESNO YOSEMITE INTERNATIONAL AIRPORT Residential Sound Insulation Program A. PROGRAM NARRATIVE The City of Fresno
More informationDecember, 2017 Request for Proposals for Airport Business and Financial Consultant At Savannah/Hilton Head International Airport
December, 2017 Request for Proposals for Airport Business and Financial Consultant At Savannah/Hilton Head International Airport Dear Proposer: The Savannah Airport Commission is requesting proposals for
More informationACI-NA SMALL AIRPORTS CONFERENCE FAA CIVIL RIGHTS - DBE REGULATORY UPDATE. Federal Aviation Administration
ACI-NA SMALL AIRPORTS CONFERENCE FAA CIVIL RIGHTS - DBE REGULATORY UPDATE Presented to: 2011 Small Airports Conference By: Wilbur Barham Director, National Airports Civil Rights Policy and Compliance Date:
More informationPIEDMONT TRIAD AIRPORT AUTHORITY
PIEDMONT TRIAD AIRPORT AUTHORITY REQUEST FOR QUALIFICATIONS (RFQ) for FAR PART 150 NOISE COMPATIBILITY STUDY for PIEDMONT TRIAD INTERNATIONAL AIRPORT The Piedmont Triad Airport Authority (PTAA) will receive
More informationMEMORANDUM. July 7, 2016
MEMORANDUM July 7, 2016 TO: FROM: MEMBERS, PORT COMMISSION Hon. Willie Adams, President Hon. Kimberly Brandon, Vice President Hon. Leslie Katz Hon. Eleni Kounalakis Hon. Doreen Woo Ho Elaine Forbes Interim
More informationSECTION 9: FORMAL PROCEDURES
SECTION 9: FORMAL PROCEDURES 9.0 General 9.0.1 Items or services which are anticipated to be over formal level will normally be acquired through formal written quotations or proposals. The splitting of
More informationBelow are five basic procurement methods common to most CDBG projects:
PROCUREMENT PROCESS I. INTRODUCTION Recipients of Community Development Block Grant (CDBG) funds will procure a variety of items, materials and services throughout the duration of their projects. Section
More informationSOLANO COMMUNITY COLLEGE DISTRICT GOVERNING BOARD AGENDA ITEM REVISIONS TO MEASURE Q SMALL, LOCAL, AND DIVERSE BUSINESS PROGRAM PILOT PROGRAM
AGENDA ITEM MEETING DATE June 6, 2018 SOLANO COMMUNITY COLLEGE DISTRICT GOVERNING BOARD AGENDA ITEM TO: SUBJECT: Members of the Governing Board REVISIONS TO MEASURE Q SMALL, LOCAL, AND DIVERSE BUSINESS
More informationSTATE AID TO AIRPORTS PROGRAM NC DEPARTMENT OF TRANSPORTATION DIVISION OF AVIATION
APRIL 2018 STATE AID TO AIRPORTS PROGRAM State Authorization: N.C.G.S. 63 NC DEPARTMENT OF TRANSPORTATION DIVISION OF AVIATION Agency Contact Person Program and Financial Betsy Beam, Grants Administrator
More informationSTANDARD PROCEDURE Number: S410.10
Page: 1 of 8 PURPOSE: To establish procedures for the competitive procurement of goods and services utilizing an Invitation to Bid (ITB) or Invitation to Quote (ITQ) solicitation process or small purchase
More informationSolano County Transit (SolTrans) Overall Disadvantaged Business Enterprise (DBE) Goal FFY through FFY
Solano County Transit (SolTrans) Overall Disadvantaged Business Enterprise (DBE) Goal FFY 2016 17 through FFY 2018 19 Summary In accordance with the requirements of 49 C.F.R. Part 26 (Participation by
More informationSandpoint Airport. FY Overall Goal Amendment to the Disadvantaged Business Enterprise (DBE) Program
Sandpoint Airport FY 2018-2020 Overall Goal Amendment to the Disadvantaged Business Enterprise () Program Table of Contents OVERALL GOALS ( 26.45)... 2 AMOUNT OF GOAL FY 2018-2020 IMPROVEMENTS... 2 METHOD...
More informationSTATE AID TO AIRPORTS PROGRAM NC DEPARTMENT OF TRANSPORTATION DIVISION OF AVIATION
APRIL 2014 STATE AID TO AIRPORTS PROGRAM State Authorization: N.C.G.S. 63 NC DEPARTMENT OF TRANSPORTATION DIVISION OF AVIATION Agency Contact Person Program and Financial Nancy C. Seigler, Grants Administrator
More informationSENATE, No. 123 STATE OF NEW JERSEY. 217th LEGISLATURE PRE-FILED FOR INTRODUCTION IN THE 2016 SESSION
SENATE, No. STATE OF NEW JERSEY th LEGISLATURE PRE-FILED FOR INTRODUCTION IN THE 0 SESSION Sponsored by: Senator JOSEPH PENNACCHIO District (Essex, Morris and Passaic) Senator RONALD L. RICE District (Essex)
More informationREQUEST FOR PROPOSALS PROFESSIONAL SERVICES FOR THE MARCH LANE/EAST BAY MUD BICYCLE AND PEDESTRIAN PATH CONNECTIVITY IMPROVEMENTS.
REQUEST FOR PROPOSALS PROFESSIONAL SERVICES FOR THE MARCH LANE/EAST BAY MUD BICYCLE AND PEDESTRIAN PATH CONNECTIVITY IMPROVEMENTS Federal Project No. CML-5008(179) City Project No. PW1722 Issued by: City
More information1. Declare Leed Electric, Inc. (Leed), first low bidder, to be non-responsive, as discussed in this report.
Joint Report No. 3 CD No. 6 REQUEST TO AWARD A CONTRACT FOR THE DONALD C. TILLMAN WATER RECLAMATION PLANT (DCTWRP) CHLORINE CONTACT TANK GATE ACTUATORS (CIP 6210) (REBID) - WORK ORDER NO. SZD11277 RECOMMENDATIONS
More informationUNION COUNTY MINORITY AND SMALL BUSINESS GUIDELINES AND OUTREACH PLAN
UNION COUNTY MINORITY AND SMALL BUSINESS GUIDELINES AND OUTREACH PLAN TABLE OF CONTENTS Definitions. 1 Responsibilities 3 Dispute Procedures... 7 Minority Business Construction Contract Provisions. 8 Minimum
More informationREQUEST FOR PROPOSAL FOR POLICE OPERATIONS STUDY. Police Department CITY OF LA PALMA
REQUEST FOR PROPOSAL FOR POLICE OPERATIONS STUDY Police Department CITY OF LA PALMA Released on November 27, 2013 Police Operations Study REQUEST FOR PROPOSAL ( RFP ) 1. BACKGROUND The City of La Palma
More informationSTENOGRAPHER REQUEST FOR QUALIFICATIONS (RFQ)
STENOGRAPHER REQUEST FOR QUALIFICATIONS (RFQ) Los Angeles County Children and Families First Proposition 10 Commission (aka First 5 LA) RELEASE DATE: FEBRUARY 11, 2014 TABLE OF CONTENTS I. TIMELINE FOR
More informationTERREBONNE PARISH REQUEST FOR QUALIFICATIONS FOR ENGINEERING SERVICES. Generator Sizing and Installation
TERREBONNE PARISH REQUEST FOR QUALIFICATIONS FOR ENGINEERING SERVICES Generator Sizing and Installation Proposal Due Date: June 26, 2017 Proposal Due Time: 2:00 P.M. Released May 23, 2017 Table of Contents
More informationNEW ORLEANS AVIATION BOARD (NOAB) DISADVANTAGED BUSINESS ENTERPRISE (DBE) PROGRAM Goal Setting Methodology and Calculations
NEW ORLEANS AVIATION BOARD (NOAB) DISADVANTAGED BUSINESS ENTERPRISE (DBE) PROGRAM Goal Setting Methodology and Calculations Goal Overview Federal Fiscal Year 2011 (October 1, 2010 to September 30, 2011)
More informationHILLSBOROUGH COUNTY AVIATION AUTHORITY THREE YEAR OVERALL DISADVANTAGED BUSINESS ENTERPRISE GOAL Federal Fiscal Years 2017, 2018 and 2019
I. Introduction HILLSBOROUGH COUNTY AVIATION AUTHORITY THREE YEAR OVERALL DISADVANTAGED BUSINESS ENTERPRISE GOAL Federal Fiscal Years 2017, 2018 and 2019 The United States Congress has determined that
More informationCONTRACTING AND PURCHASING
CONTRACTING AND PURCHASING 2017 Educational Series CONTRACTING AND PURCHASING INTRODUCTION GOODS AND SERVICES Texas Department of Transportation (TxDOT) contracting activities are established and controlled
More informationBest-Value Procurement Manual. MnDOT Office of Construction and Innovative Contracting (OCIC)
Best-Value Procurement Manual MnDOT Office of Construction and Innovative Contracting (OCIC) March, 2013 Table of Contents July 29, 2010 1 Preface... 1 1.1 Purpose of Manual... 1 1.2 What is Best Value
More informationSUBJECT: AMENDED AND RESTATED AGREEMENT WITH CREATV SAN JOSE FOR PUBLIC AND EDUCATIONAL ACCESS CHANNEL MANAGEMENT
CITY OF SAN JOSE CAPITAL OF SILICON VALLEY TO: HONORABLE MAYOR AND CITY COUNCIL COUNCIL AGENDA: 9/1/15 ITEM: Memorandum FROM: David Vossbrink SUBJECT: SEE BELOW DATE: Approved Date SUBJECT: AMENDED AND
More informationB Request for Proposal for. Qualified Firms. Financial Advisory Services. Grossmont-Cuyamaca Community College District
B17.045 Request for Proposal for Qualified Firms For Financial Advisory Services For the Grossmont-Cuyamaca Community College District Proposal Due Date August 18, 2017 4pm Return Proposals to: Grossmont-Cuyamaca
More informationCOUNTY OF LOS ANGELES
COUNTY OF LOS ANGELES DEPARTMENT OF PUBLIC WORKS JAMES A. NOYES, Director 900 SOUTH FREMONT AVENUE ALHAMBRA, CALIFORNIA 91803-1331 Telephone: (626) 458-5100 ADDRESS ALL CORRESPONDENCE TO: P.O. BOX 1460
More informationSTATE FUNDS AND FISCAL COMPLIANCE POLICIES
STATE FUNDS AND FISCAL COMPLIANCE POLICIES 100.040. USE OF STATE FUNDS The governing body of the A.W. Brown-Fellowship Leadership Academy adopts the following policy which shall be effective on the date
More informationAugust 9, Re: DBE Program Triennial Goal Concurrence - Recipient ID #1674. Dear Mr. Smith:
U.S. Department of Transportation Federal Transit Administration REGION IX Arizona, California, Hawaii, Nevada, Guam American Samoa, Northern Mariana Islands 201 Mission Street Suite 1650 San Francisco,
More informationWelcome to the City of Chicago. Department of Procurement Services
Welcome to the Rahm Emanuel, Mayor Jamie Rhee, Chief Procurement Officer Doing Business with the Mission Statement Laws Governing the Procurement Process Types of Procurement Certification Contract Monitoring
More informationSCHOOL BOARD ACTION REPORT
SCHOOL BOARD ACTION REPORT DATE: October 25, 2017 FROM: Executive Committee of the School Board For Introduction: November 15, 2017 For Action: November 15, 2017 1. TITLE Approval of a contract for an
More informationINVITATION TO BID (ITB) RESIDENTIAL NOISE MITIGATION PROGRAM(P676A) ITB NO. H27-RNMP
PRE-BID CONFERENCE INVITATION TO BID (ITB) RESIDENTIAL NOISE MITIGATION PROGRAM(P676A) ITB NO. H27-RNMP-2017-003 Al Oracion Sr. Procurement Specialist Houston Airport System Thursday, August 25, 2016 10:00
More informationRESOLUTION NUMBER 2877
RESOLUTION NUMBER 2877 A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF PERRIS, STATE OF CALIFORNIA SETTING FORTH POLICIES INTENDED TO OBTAIN CONSISTENCY AND UNIFORMITY IN THE ADMINISTRATION OF THE FEDERALLY
More informationNDOT Civil Rights DBE Program Small Business Element
NDOT Civil Rights DBE Program Small Business Element The DBE program improvements regulations that became effective on February 28, 2011, require federal funds recipients such as NDOT must include an SBE
More informationInformational Workshop How to do Business with the City of Irvine March 31, 2011
Informational Workshop How to do Business with the City of Irvine March 31, 2011 Presented by Brian D. Brown, CPSM Buyer City of Irvine About the City of Irvine The City of Irvine has an annual budget
More informationFort Bend Independent School District. Small Business Enterprise Program Procedures
Fort Bend Independent School District Small Business Enterprise Program Procedures Spring 2015 TABLE OF CONTENTS I. Summary Of Fort Bend Independent School District s Small Business Enterprise Program
More informationOffice of Business and Financial Services Procurement and Contracts Division Section SUBJECT: PROCUREMENT OF CONSTRUCTION SERVICES
2510.8 SUBJECT: PROCUREMENT OF CONSTRUCTION SERVICES :1 OBJECTIVE: To establish a uniform policy and procedure for the acquisition of construction services for the City of Orlando (City), including, but
More informationREQUEST FOR QUALIFICATIONS (RFQ) AIRPORT ARCHITECTURAL AND ENGINEERING SERVICES AGREEMENT MINOT INTERNATIONAL AIRPORT
REQUEST FOR QUALIFICATIONS (RFQ) AIRPORT ARCHITECTURAL AND ENGINEERING SERVICES AGREEMENT MINOT INTERNATIONAL AIRPORT 2016-2021 GENERAL The intent and purpose of this Request for Qualifications (RFQ) is
More informationPort Small Business Development Program
Port Small Business Development Program April 11, 2013 Angela Watkins Small Business Development Program Manager 1 Purpose The purpose of the Port small business development program is to enhance the opportunity
More informationMassachusetts Bay Transportation Authority. POLICIES & PROCEDURES Design Build Procurement Procedures April 2016
Massachusetts Bay Transportation Authority POLICIES & PROCEDURES Design Build Procurement Procedures April 2016 Design Build Procurement Procedures April 2016 Massachusetts Bay Transportation Authority
More information'Los Angeles World Airports REPORT TO THE B0 A RD OF AIRPORT COMMISSIONERS. s( 1
ElY IMY _,_7- - - Approved b. 0.21 'Los Angeles World Airports REPORT TO THE B0 A RD OF AIRPORT COMMISSIONERS ; 4 Dom Ne? Deputy Executive Director Meeting Date: 5/19/2014 hp,.6 -,.. El Completed Reviewed
More informationDisadvantaged Business Enterprise Program and Triennial DBE Goal Setting Methodology and Rationale
Disadvantaged Business Enterprise Program and Triennial DBE Goal Setting Methodology and Rationale Kenn Hardin Senior Manager Civil Rights Division RTD Small Business Office August 14, 2013 Agenda Introductions
More informationCITY OF SAN ANTONIO AVIATION DEPARTMENT 49 CFR PARTS 26 & 23 DBE AND SBEDA PROGRAMS OVERVIEW
CITY OF SAN ANTONIO AVIATION DEPARTMENT 49 CFR PARTS 26 & 23 DBE AND SBEDA PROGRAMS OVERVIEW January 11, 2017 BACKGROUND San Antonio Airport System San Antonio Airport System is composed of the San Antonio
More informationCITY OF MOBILE REQUEST FOR PROPOSAL TRANSIT MANAGEMENT SERVICES
CITY OF MOBILE REQUEST FOR PROPOSAL TRANSIT MANAGEMENT SERVICES CLOSING DAY AND TIME: Sealed proposals will be received no later than: 2:00 P.M. CST January 8, 2018 MARK PACKAGE: TRANSIT MANAGEMENT PROPOSAL
More informationTOPIC: CONTRACTS STATE OF MISSISSIPPI DEPARTMENT OF EDUCATION SECTION 17.0 PAGE 1 OF 38 EFFECTIVE DATE: MAY 1, 2017 REVISION #4: MARCH 1, 2017
SECTION 17.0 PAGE 1 OF 38 CONTRACT PROCUREMENT POLICY The Mississippi Department of Education (Department) Contract Procurement Policy set forth herein applies to the procurement, management, and control
More informationDOING BUSINESS WITH THE. Orange County Board of County Commissioners. Orange County Procurement Division
DOING BUSINESS WITH THE Orange County Board of County Commissioners Orange County Procurement Division TABLE OF CONTENTS Preface... 1 How Can I Receive Copies Of Solicitations?... 2 Bidder s List... 2
More informationSOUTHERN UTE INDIAN TRIBE REQUEST FOR PROPOSALS (RFP) FOR ENVIRONMENTAL CONSULTING SERVICES FOR
SOUTHERN UTE INDIAN TRIBE REQUEST FOR PROPOSALS (RFP) FOR ENVIRONMENTAL CONSULTING SERVICES FOR Asbestos Remediation of the Old Cafeteria Building Date of RFP Release March 21, 2012 April 25, 2012 - Proposals
More informationBAKER CENTER A. PROPOSAL PACKAGE
BAKER CENTER A. PROPOSAL PACKAGE FOR THE REPURPOSING, SHORT-TERM LEASE, PARTNERSHIP OR OTHER OPEN-ENDED OPTIONS OF REAL PROPERTY AND IMPROVEMENTS LOCATED AT 3908 AVENUE B, AUSTIN, TRAVIS COUNTY, TEXAS
More informationLEXINGTON-FAYETTE URBAN COUNTY AIRPORT BOARD REQUEST FOR PROPOSALS. to provide INVESTMENT MANAGEMENT SERVICES. for BLUE GRASS AIRPORT
LEXINGTON-FAYETTE URBAN COUNTY AIRPORT BOARD REQUEST FOR PROPOSALS to provide INVESTMENT MANAGEMENT SERVICES for BLUE GRASS AIRPORT DATED: March 5, 2017 TABLE OF CONTENTS 1. NOTICE AND REQUEST FOR PROPOSALS...
More informationAdvancing Accountability
Advancing Accountability BEST PRACTICES IN CONTRACT AND GRANT MANAGEMENT FLORIDA DEPARTMENT OF FINANCIAL SERVICES 1 Intro & Housekeeping Introduction of instructors Housekeeping Class history Class material
More informationSOP Procurement Standard Operating Procedures Grow Southwest Indiana Region 11 RWB Approval Date: 08/26/2011
SOP 11-09 Procurement Standard Operating Procedures Grow Southwest Indiana Region 11 RWB Approval Date: 08/26/2011 Purpose To set forth guidance for the conduct of procurement activities by the Grow Southwest
More informationKDOT Procurement Guidelines for STP/CMAQ Funded Planning, Education, and Outreach Projects Effective 10/1/12
KDOT Procurement Guidelines for STP/CMAQ Funded Planning, Education, and Outreach Projects Effective 10/1/12 Purpose These guidelines are intended to guide the procurement of goods and consultant services
More informationTexas Department of Transportation Page 1 of 19 Public Transportation. (a) Purpose. Title 49 U.S.C. 5329, authorizes the
Texas Department of Transportation Page of 0 SUBCHAPTER D. PROGRAM ADMINISTRATION.. Public Transit Safety Program. (a) Purpose. Title U.S.C., authorizes the Secretary of the U.S. DOT to create and implement
More informationFOR PROFESSIONAL DESIGN SERVICES
SEDA-Council of Governments REQUEST FOR PROPOSALS FOR PROFESSIONAL DESIGN SERVICES TOWN OF BLOOMSBURG COLUMBIA COUNTY, PENNSYLVANIA COMMUNITY DEVELOPMENT BLOCK GRANT ACTIVITIES AND CDBG-DISASTER RECOVERY
More informationGOODWILL YOUTHBUILD GED/High School Education Instruction
REQUEST FOR PROPOSALS FOR GOODWILL YOUTHBUILD GED/High School Education Instruction Issued By: Goodwill of the Olympics and Rainier Region YouthBuild Program 714 S 27 th St Tacoma, WA 98372 November 13,
More informationRFP Number: R P1 Addendum No. 1 Page 1 of 1
ATTENTION ALL POTENTIAL BIDDERS: PURCHASING DIVISION BOARD OF COUNTY COMMISSIONERS BROWARD COUNTY, FLORIDA RFP Name: Cooperative Marketing Program Services Non-sheltered Market ADDENDUM NO. 1 DATE OF ADDENDUM:
More informationSAN JOSE CAPITAL OF SILICON VALLEY
PSFSS AGENDA: 9/17/2015 ITEM: (d) 6 CITY OF SAN JOSE CAPITAL OF SILICON VALLEY TO: PUBLIC SAFETY, FINANCE, AND STRATEGIC SUPPORT COMMITTEE Memorandum FROM: Curtis P. Jacobson SUBJECT: FIRE DEPARTMENT EMERGENCY
More informationREQUEST FOR QUALIFICATIONS FOR A PROFESSIONAL ARCHITECTURAL FIRM TO PROVIDE ARCHITECTURAL SERVICES FOR THE BZN YELLOWSTONE INTERNATIONAL AIRPORT
REQUEST FOR QUALIFICATIONS FOR A PROFESSIONAL ARCHITECTURAL FIRM TO PROVIDE ARCHITECTURAL SERVICES FOR THE BZN YELLOWSTONE INTERNATIONAL AIRPORT TERMINAL EXPANSION PROJECT FEBRUARY 2018 MORRISON-MAIERLE,
More informationKAREN E. RUSHING. Audit of the Vendor Selection Process
KAREN E. RUSHING Clerk of the Circuit Court and County Comptroller Audit of the Vendor Selection Process Audit Services Karen E. Rushing Clerk of the Circuit Court and County Comptroller Jeanette L. Phillips,
More informationTable of Contents. C. Promote Institutional Awareness, Understanding and Coordination
1 Table of Contents 1. Overview 2. The District s Mission 3. The Program Goals 4. Small, Local and Other Business Identification 5. Strategic Initiatives A. Provide Community Outreach and Education B.
More informationPart 1: Employment Restrictions After Leaving DoD: Personal Lifetime Ban
POST-GOVERNMENT SERVICE EMPLOYMENT RESTRICTIONS (RULES AFFECTING YOUR NEW JOB AFTER DoD) For Military Personnel E-1 through O-6 and Civilian Personnel who are not members of the Senior Executive Service
More informationRequest for Proposals RFP VIRTUAL SERVICES
Request for Proposals RFP 18-01 VIRTUAL SERVICES Contract Period October 1, 2018 ~ June 30, 2020 RFP Release Date: Friday, July 6, 2018 Program Proposal Due Date: August 8, 2018 3pm Hand or postal delivery
More informationSUBJECT: FIREWORKS ORDINANCE DATE: April 1,2016
CITY OF 2 SANjOSE CAPITAL OF SILICON VALLEY TO: HONORABLE MAYOR AND CITY COUNCIL COUNCIL AGENDA: 4/12/16 ITEM: 8.1 Memorandum FROM: Curtis P. Jacobson SUBJECT: FIREWORKS ORDINANCE DATE: Approved " _ /
More informationProcurement Processes Policy
Procurement Processes Policy Responsible Division: Purchasing & Materials Management Effective Date: January 1, 2017 Responsible Official: Chief Purchasing Official Last Revision Date: NA Table of Contents
More informationGUILFORD COUNTY PARTNERSHIP FOR CHILDREN REQUEST FOR PROPOSALS
GUILFORD COUNTY PARTNERSHIP FOR CHILDREN REQUEST FOR PROPOSALS TITLE: Catering Services, Human Resources Services, Information Technology Services, Outreach Services, Printing Services, Program Evaluation
More informationAdministrative Regulation SANGER UNIFIED SCHOOL DISTRICT. Business and Noninstructional Operations FEDERAL GRANT FUNDS
Administrative Regulation SANGER UNIFIED SCHOOL DISTRICT AR 3230(a) Business and Noninstructional Operations FEDERAL GRANT FUNDS Allowable Costs Prior to obligating or spending any federal grant funds,
More informationDORMITORY AUTHORITY OF THE STATE OF NEW YORK (DASNY) on behalf of the. HIGHER EDUCATION CAPITAL MATCHING (HECap) GRANT PROGRAM BOARD
DORMITORY AUTHORITY OF THE STATE OF NEW YORK (DASNY) on behalf of the HIGHER EDUCATION CAPITAL MATCHING (HECap) GRANT PROGRAM BOARD REQUEST FOR GRANT APPLICATIONS November 21, 2017 KEY DATES Eligible Project
More informationSECTION I - BACKGROUND
SOLICITATION TYPE: Notice of Funding Availability () DESCRIPTION: Safety Net Capital Improvement Program, ISSUE DATE: May 5, 2016 PROPOSAL DUE DATE: July 14, 2016 SUBMIT PROPOSAL TO: Sandra Murillo, Chief
More informationAutomated Airport Parking Project
Automated Airport Parking Project RFP 2017-03 I. INTRODUCTION This solicitation is being offered by Texarkana Airport Authority. The Airport is a public entity owned by the Cities of Texarkana, AR and
More informationSUBCONTRACTING ON CDOT CONSTRUCTION PROJECTS Ramp Up Ridgway!
SUBCONTRACTING ON CDOT CONSTRUCTION PROJECTS Ramp Up Ridgway! Connect2DOT Colorado Small Business Development Center Network (SBDC) program funded by CDOT Free training, consulting, and resources for small
More informationABC S of DBE & ACDBE Programs
ABC S of DBE & ACDBE Programs Project Take Off: Community Partnerships and Economic Growth Conference Presented to: By: Broward County Aviation Department Anthony W. Brown, FAA Date: Presentation Overview
More informationADDENDUM NUMBER 02 TO THE BID DOCUMENTS. BID NUMBER: SJCC Parking Garage LED Lighting Retrofit EVERGREEN VALLEY COLLEGE
SAN JOSE EVERGREEN COMMUNITY COLLEGE DISTRICT ADDENDUM NUMBER 02 TO THE BID DOCUMENTS To all general contract bidders of record on the Bid Proposal: BID NUMBER:0215-17 SJCC Parking Garage LED Lighting
More informationSOLICITATION FOR PARTICIPATION IN A REQUEST FOR PROPOSALS FOR CHIEF EXECUTIVE OFFICER (CEO) SEARCH SERVICES JACKSONVILLE, FL SOLICITATION NUMBER 94414
SOLICITATION FOR PARTICIPATION IN A REQUEST FOR PROPOSALS FOR CHIEF EXECUTIVE OFFICER (CEO) SEARCH SERVICES JACKSONVILLE, FL SOLICITATION NUMBER 94414 PROPOSALS ARE DUE ON APRIL 27, 2018 BY 12:00 PM EST
More informationThe DBE Program is an outreach, education, and objectives program designed to increase the participation of DBEs in the CWSRF Program.
California State Water Resources Control Board Division of Financial Assistance (Division) 1001 I Street Sacramento, California 95814 (916) 341-5700 FAX (916) 341-5707 Mailing Address: P. O. Box 944212
More informationipt BOARD OF AIRPORT COMMISSIONERS REPORT TO THE
2/11/2016 2/29 3/2/2016: Y MV Approved by: Reviewed by: ipt.04 Los Angeles World Airports REPORT TO THE BOARD OF AIRPORT COMMISSIONERS CS r 5 CA/ `- /I 6 C,, - Samson Mengistu, Chief/Operating Officer
More informationREQUEST FOR PROPOSALS. General Contractor/ Construction Manager (GC/CM) Services
REQUEST FOR PROPOSALS General Contractor/ Construction Manager (GC/CM) Services Spokane International Airport (SIA) Security Upgrades Project #15-43-1866 SPOKANE INTERNATIONAL AIRPORT (SIA) 9000 W. Airport
More informationPAL-MAR WATER CONTROL DISTRICT Security-Maintenance Services RFP Proposal Packet
PAL-MAR WATER CONTROL DISTRICT Security-Maintenance Services RFP Proposal Packet A) Deadline for Submittal Proposal Due Date: On or before 4:00 p.m. on Tuesday, December 6, 2011. Interested applicants
More informationPARTNERSHIP AGREEMENT Between The U.S. Small Business Administration And The U.S. Department of Defense
PARTNERSHIP AGREEMENT Between The U.S. Small Business Administration And The U.S. Department of Defense Sections 7U) and 8(a) of the Small Business Act (the Act) (15 U.S.C. 636 (j) and 637(a)) authorize
More informationFlorida International University Project Fact Sheet Construction Manager Continuing Services Contact
PROJECT LOCATION: Modesto A. Maidique Campus (MMC), Biscayne Bay Campus (BBC), Engineering Center (EC) and other properties in South Florida managed by FIU. PROJECT DESCRIPTION: The Construction Manager
More information- 79th Session (2017) Assembly Bill No. 436 Assemblymen Monroe-Moreno, Neal, Spiegel, Bustamante Adams, Carrillo; and Frierson
Assembly Bill No. 436 Assemblymen Monroe-Moreno, Neal, Spiegel, Bustamante Adams, Carrillo; and Frierson CHAPTER... AN ACT relating to business; requiring the Office of Economic Development and the Regional
More informationMICHAEL N. FEUER CITY ATTORNEY REPORT RE:
MICHAEL N. FEUER CITY ATTORNEY REPORT RE: R13-0351 REPORTNO.~~ ~ DEC 0 9 2013 DRAFT ORDINANCE FOR THE HAIWEE POWER PLANT PENSTOCK REPLACEMENT PROJECT REQUESTING THE LOS ANGELES CITY COUNCIL TO ESTABLISH
More informationREQUEST FOR PROPOSALS
REQUEST FOR PROPOSALS FOR TO PREPARE PROFESSIONAL DESIGN SERVICES PLANS, SPECIFICATIONS, AND ESTIMATE (PS&E) FOR THE RAISED MEDIAN ALONG DR. MARTIN LUTHER KING JR. BOULEVARD CITY PROJECT NO. PW1716/ FEDERAL
More informationREQUEST FOR PROPOSALS (RFP) TRIENNIAL PERFORMANCE AUDIT FOR THE MADERA COUNTY TRANSPORTATION COMMISSION
REQUEST FOR PROPOSALS (RFP) TRIENNIAL PERFORMANCE AUDIT FOR THE MADERA COUNTY TRANSPORTATION COMMISSION Prepared By: Madera County Transportation Commission 2001 Howard Road, Suite 201 Madera, California
More informationHIGHWAY PLANNING AND CONSTRUCTION RAILROAD STATION IMPROVEMENT PROGRAM. N. C. Department of Transportation Rail Division
APRIL 2011 20. 205 HIGHWAY PLANNING AND CONSTRUCTION RAILROAD STATION IMPROVEMENT PROGRAM State Project/Program: SAFE, ACCOUNTABLE, FLEXIBLE, EFFICIENT TRANSPORTATION EQUITY ACT: A LEGACY FOR USERS (SAFETEA-LU)
More informationCity of Fernley GRANTS MANAGEMENT POLICIES AND PROCEDURES
1 of 12 I. PURPOSE The purpose of this policy is to set forth an overall framework for guiding the City s use and management of grant resources. II ` GENERAL POLICY Grant revenues are an important part
More informationHistorically Underutilized Business (HUB) Strategic Plan
The University of Texas MD Anderson Cancer Center Historically Underutilized Business (HUB) Strategic Plan Fiscal Years 2015 2016 Prepared November 2015 FINAL.doc page 1 of 9 FINAL.doc page 2 of 9 EXTERNAL
More informationSection 3. Contractor Handbook. The City of Middletown. for
Section 3 Contractor Handbook for The City of Middletown Updated: June 9, 2011 Section 3 Contractor Steps 1.) You are notified of a Bid opportunity subject to Section 3 2.) Attend walk-through (if required)
More informationContract Compliance Program
Contract Compliance Program Including Equal Employment Opportunity Program Disadvantaged Business Enterprise Program Targeted Small Business Program Updated June 2017 The Des Moines City Council adopted
More informationPROPOSAL. (Pages LBPP-1 through LBPP-7)
PROPOSAL (Pages LBPP-1 through LBPP-7) CITY OF LOS ANGELES REQUEST FOR PROPOSALS- LOCAL BUSINESS PREFERENCE PROGRAM (LBPP) City of Los Angeles Ordinance No. 181910, Article 21, Sections 10.47, et esq.
More informationREQUEST FOR PROPOSAL FOR DESIGN-BUILD SERVICES
REQUEST FOR PROPOSAL FOR DESIGN-BUILD SERVICES Agricultural Sciences Complex West Texas A&M University Canyon, Texas Project No. 18-3119 DEADLINE FOR SUBMITTAL: 2pm, Thursday, February 11, 2016 OFFICE
More informationREQUEST FOR GRANT APPLICATIONS FOR WALK, RIDE, AND ROLL TO SCHOOL MINI-GRANT PROGRAM
REQUEST FOR GRANT APPLICATIONS FOR WALK, RIDE, AND ROLL TO SCHOOL MINI-GRANT PROGRAM APPLICATION DEADLINE: April 21, 2017, at 5 p.m. Submit an application electronically between March 13, 2017, and April
More informationAll proposals must be received by August 30, 2016 at 2:00 PM EST
July 25, 2016 REQUEST FOR PROPOSAL Northwood School District SAU #44 Strategic Planning for the Northwood School District You are cordially invited to submit a proposal for Strategic Planning for the Northwood
More informationREQUEST FOR PROPOSALS PROFESSIONAL SERVICES FOR INSTALLATION & UPGRADE OF BICYCLE FACILITIES (CLASS II & CLASS III) Issued by:
REQUEST FOR PROPOSALS PROFESSIONAL SERVICES FOR INSTALLATION & UPGRADE OF BICYCLE FACILITIES (CLASS II & CLASS III) City Project No. PW1517 Federal Project No. CML-5008(150) Issued by: City of Stockton
More information