1 Wards affected: Middleton, Eaton Manor and Whitehouse ITEM 6 CABINET PROCUREMENT COMMITTEE 4 APRIL 2012 DESIGN, DEVELOPMENT AND CONSTRUCTION OF FOUR NEW PRIMARY SCHOOLS INVITATION TO TENDER Author: Helen Rowlay, Capital Development Manager. Tel: (01908) Executive Summary In order to meet the projected demand for pupil places arising from new housing development across Milton Keynes, four new primary schools are required by September A two year lead in period is required to enable the necessary consultation, tendering process, design development and construction to take place to achieve this date. The schemes will be procured as design and build contracts through Lot 1 of the Milton Keynes Council Construction Framework. This report is seeking approval to commence the tender process in accordance with the Council s Contract Procedure Rules and Financial Regulations. Tenders will be invited using the Council s E-Tendering system. 1 Recommendation 1.1 That tenders be invited for the procurement of the following new primary schools on a design and build basis through Lot 1 of the Milton Keynes Council Construction Framework. School Oakgrove Primary School Western Expansion Area Primary School 1 Eastern Expansion Area Primary School 2 Newton Leys Primary School Eventual Capacity 420 pupil places 630 pupil places 630 pupil places 420 pupil places 2. Issues 2.1 The Council s Constitution requires all procurement in excess of 100,000 to be approved by Cabinet Procurement Committee. This includes both the decision to formally award contracts and the decision to authorise officers to commence tender processes. 2.2 This report requests approval to obtain tenders for the provision of four new primary schools as outlined in paragraph 1.1. The funding required will be met by the respective project budgets within the Council's Capital Programme, CP ITEM 06 4 APRIL 2012 PAGE 1
2 approved by Cabinet on 28th February Formal Spend approval was agreed by the Capital Programme Review Panel on 6th February Consultation and Policy The procurement seeks to implement the Council's statutory duty in ensuring that there are sufficient school places (Education and Inspections Act 2006) The current pupil projections indicate that additional school places are required to meet the demand from projected new housing development in the above areas by September 2014 (based on the current projected rate of house build). The size of school required for each development has been determined by the number of houses to be built and resultant pupil projections. Admissions to these schools will be managed in order to allow the schools to grow in size in line with demand. Typically places are only opened in Years R to 4 and the admission number will be set low and then raised up to maximum capacity over a number of years to ensure that there are sufficient places at the school to offer to local residents as the community grows The need for four primary schools to open in one year results from a number of factors. Firstly, the primary schools already agreed to be opened in the Western Expansion Area and Newton Leys in 2010 were delayed due to the downturn in the housing market. The housing programme for these areas now demonstrates that there will be a need for the delayed schools to be opened in Secondly the Brooklands development continues at a pace and Cabinet has already determined that the first primary school in the area, Brooklands Farm Primary, will expand with effect from September Despite this expansion the projected housing programme demonstrates the need for further places for to serve Brooklands residents from Finally the section 106 agreement for the Oakgrove development has recently been signed and a primary school site secured conditional upon proving need in the local area. The current programme for Oakgrove demonstrates that this is likely to take place in time to open the school in September The Council will not commit to contract on the delivery of these new schools until it is certain that the designated sites are available and ready for development The schemes will be procured using a design and build contract through Lot 1 of the Milton Keynes Council Construction Framework. The Capital Development Team will work with advisers, Headteachers and governor representatives (where possible) to ensure designs are both fit for purpose and cost effective. 2.4 Specification The draft specification for each school will be developed in line with Department for Education recommended space standards (which are currently subject to revision). They will be compliant with all relevant Building Regulations and construction standards. CP ITEM 06 4 APRIL 2012 PAGE 2
3 2.4.2 A 'Cost Effective Template for Design and Construction' will be used and a 'standardised' approach to design and construction will be utilised where possible The procurement seeks to deliver good quality, cost effective school buildings that will provide sufficient permanent school places to meet the demand created from new housing growth Recently agreed target costs per square metre will be applied In order to maximise efficiency (and thus cost savings) in the design and procurement process it is intended to procure a single 420 place school design and a single 630 place school design, which would each be constructed on two sites. 2.5 Evaluation Criteria & Panel The Most Economically Advantageous Tender (MEAT) evaluation of tenders will be as follows: a) Price will be 60% of the evaluation b) Quality will be 40% of the evaluation The quality evaluation criteria will also have appropriate sub criteria that reflect the importance of issues such as design quality, experience and programme/delivery Tenders submitted will be evaluated by a panel comprising of the appointed Project Manager, Cost Consultant, Lead Client Officer and Head of Capital and Infrastructure. Colleagues within Finance, Legal and Corporate Procurement will be engaged to support the tender process. 2.6 Contract Terms and Conditions Tenders will be sought for a contract period commencing in January 2013 and completing in September 2014, excluding the defects liability period. The tender period including an allowance for evaluation, Cabinet Procurement Committee decision and call in period is expected to take place between June 2012 and November The Terms and Conditions as agreed under the Milton Keynes Council Construction Framework will be used for each of these contracts The Council s Senior Client Officer for the procurement of each of these schemes is as follows. Oakgrove Primary School Sarah Layton Western Expansion Area Primary School 1 Joe McGovern Eastern Expansion Area Primary School 2 Kath Cook CP ITEM 06 4 APRIL 2012 PAGE 3
4 Newton Leys Primary School Glenn Oldfield The Programme will be overseen and led by Mark Dolling, Head of Capital and Infrastructure (Capital Projects Director) The appointed Project Managers and Cost Consultants for these schemes will be Hewitt Freeborn Associates (HFA). Following Procurement Committee approval of these schemes, HFA will be appointed under the Construction Related Professional Services Framework, which was approved by Cabinet on 3rd November Alternative Options 3.1 Not to agree to tender the schemes at this time. Due to the lead in times required to take forward the tender, design and construction of each building, the schools may not be available for September Do nothing. Milton Keynes Council has a statutory responsibility to ensure that there are sufficient school places for all children and young people. If no action is taken, initially pupils would need to be transported to schools elsewhere across the borough disrupting families and creating a revenue cost to the council. However, given the pressure within the existing system it is probable that there will not be capacity to meet demand without this proposed new school provision. 4 Implications 4.1 Policy The award of this contract contributes to the delivery of the following strategic aims: Living in MK Cleaner, greener, safer healthier MK 4.2 Resources and Risk There is currently an allocation of 6,000,000 for both Newton Leys Primary School and Oakgrove Primary School in the proposed capital programme, from which an estimated 297,000 on each will be spent on design development activity during Oakgrove Primary School will be funded through Section 106 contributions. - Newton Leys Primary School will be funded through 3,987,522 Section 106 contributions and 2,012,478 Basic Need There is currently an allocation of 7,617,000 for both the Western Expansion Primary School 1 and Eastern Expansion Primary School 2 in the proposed CP ITEM 06 4 APRIL 2012 PAGE 4
5 capital programme, from which an estimated 341,000 on each will be spent on design development during Eastern Expansion Primary School 2 will be funded through 1,760,000 tariff contributions and 5,857,000 Basic Need. - Western Expansion Primary School 1 will be funded through 1,340,000 tariff contributions and 6,277,000 Basic Need A detailed project Risk Register is compiled at the outset of every major project and maintained throughout the lifecycle of the scheme, from pre-start through to post-completion. All stakeholders contribute to this register to ensure that it is comprehensive (End User, Client Officer, Project Manager and Constructor). The Risk Register contains all risk and mitigating actions/strategies. It is formally reviewed and updated by a Project or Programme Board on a monthly basis. Y Capital N Revenue Y Accommodation N IT N Medium Term Plan Y Asset Management 4.3 Carbon and Energy Management 4.4 Legal Each project will support the Council s Carbon and Energy Management policy and will use sustainable sources/methods where possible. The appointed contractor will be required to be compliant with relevant environmental legislation The Council has a legal obligation under the Education and Inspections Act 2006 to provide sufficient, high quality school places This recommendation complies with Milton Keynes Council's Contract Procedure Rules, United Kingdom and European legislation. 4.5 Other Implications Y Equalities/Diversity N Sustainability Y Human Rights N E-Government N Stakeholders Y Crime and Disorder Y Carbon and Energy Policy Background Papers: Milton Keynes School Organisation Framework CP ITEM 06 4 APRIL 2012 PAGE 5
Procurement of Prevention and Wellbeing Training
ACTION TAKEN UNDER DELEGATED POWERS BY OFFICER 01 March 2016 Title Report of Wards Status Procurement of Prevention and Wellbeing Training Commissioning Lead Health and Wellbeing All Public Enclosures
More informationCentral Bedfordshire Council. Determination of Proposal to Commission New Middle School Places in Leighton Buzzard
Central Bedfordshire Council EXECUTIVE 6 October 2015 Determination of Proposal to Commission New Middle School Places in Leighton Buzzard Report of: Cllr Mark Versallion, Executive Member for Education
More informationColindale Ward. Not applicable
Meeting Cabinet Resources Committee Date 16 December 2013 Subject Report of Summary Delivering a new Library and Centre for Independent Living as part of the Barnet and Southgate College development at
More informationBARNSLEY METROPOLITAN BOROUGH COUNCIL
BARNSLEY METROPOLITAN BOROUGH COUNCIL This matter is a Key Decision within the Council s definition and has been included in the relevant Forward Plan Report of the Executive Director (People) to Cabinet
More informationACTION TAKEN UNDER DELEGATED POWERS BY OFFICER 27 th March Contracts Award for Accommodation and Support Services (Lot 1 Support at Home)
ACTION TAKEN UNDER DELEGATED POWERS BY OFFICER 27 th March 2017 Title Contracts Award for Accommodation and Support Services (Lot 1 Support at Home) Report of Dawn Wakeling, Adults & Health Commissioning
More informationDirector of Finance and Corporate Services and the Director of Development and Housing Services
To: Procurement Sub-Committee On: 21 st January 2014 Report by: Joint Report by Director of Finance and Corporate Services and the Director of Development and Housing Services Heading: Contract Authorisation
More informationCHIEF OFFICER IN CONSULTATION WITH COMMITTEE CHAIRMAN DELEGATED POWERS REPORT
CHIEF OFFICER IN CONSULTATION WITH COMMITTEE CHAIRMAN DELEGATED POWERS REPORT Title Report of Wards Status Award of Film Liaison Services concession contract to FilmFixer Assistant Chief Executive, in
More informationTrust Health and Safety Policy
Trust Health and Safety Policy DATE ISSUED: September 2018 REVIEW DATE: September 2019 APPROVED BY: Board of Trustees OBJECTIVES The objectives of this document are: To set the general direction for health,
More informationMental Health Social Work: Community Support. Summary
Adults and Safeguarding Commitee 8 th June 2015 Title Mental Health Social Work: Community Support Report of Dawn Wakeling Adults and Health Commissioning Director Wards All Status Public Enclosures Appendix
More information2014 to 2020 European Structural and Investment Funds Growth Programme. Call for Proposals European Social Fund. Priority Axis 2 : Skills for Growth
2014 to 2020 European Structural and Investment Funds Growth Programme Call for Proposals European Social Fund Priority Axis 2: Skills for Growth Managing Authority ESI Fund Priority Axis: Investment Priority:
More informationBIRMINGHAM CITY COUNCIL
BIRMINGHAM CITY COUNCIL PUBLIC REPORT Report to: CABINET Report of: Strategic Director for People Date of Decision: 28 th June 2016 SUBJECT: STRATEGY AND PROCUREMENT PROCESS FOR THE PROVISION OF EARLY
More informationCollaborative Agreement for CCGs and NHS England
RCCG/GB/15/164 Collaborative Agreement for CCGs and NHS England East Midlands Collaborative Commissioning Oversight Group (EMCCOG) 1. Particulars 1.1. This Agreement records the particulars of the agreement
More informationBIRMINGHAM CITY COUNCIL PUBLIC REPORT
BIRMINGHAM CITY COUNCIL PUBLIC REPORT Report to: CABINET Report of: Strategic Director for Major Projects Date of Decision: 22 nd March 2016 SUBJECT: BIG DATA CORRIDOR: A NEW BUSINESS ECONOMY SUBMISSION
More informationHealth Safety BARNSLEY AN EMPLOYEE S GUIDE TO THE BARNSLEY MBC HEALTH & SAFETY POLICY. Metropolitan Borough Council
Health & Safety P O L I C Y AN EMPLOYEE S GUIDE TO THE BARNSLEY MBC HEALTH & SAFETY POLICY BARNSLEY Metropolitan Borough Council DUTIES AND RESPONSIBILITIES 1 ELECTED MEMBERS Elected Members have a responsibility
More informationMKCCG Estates Statement January 2015
MKCCG Estates Statement January 2015 This statement should be read in conjunction with the Milton Keynes CCG Primary Care Strategy and Care Closer to Home Strategy. Background Milton Keynes CCG (MKCCG)
More informationOverarching Section 75 Agreement Adults Integrated Health and Social Care Services. Subject. Cabinet Member
ACTION TAKEN BY CABINET MEMBER (EXECUTIVE FUNCTION) Subject Cabinet Member Overarching Section 75 Agreement Adults Integrated Health and Social Care Services Cabinet Member for Adults Cabinet Member for
More informationReport. To the Chair and Members of CABINET
Report Date: 20 th March 2018 To the Chair and Members of CABINET APPROVAL TO PROGRESS THE FUNDING AGREEMENT WITH SHEFFIELD CITY REGION AND ASSOCIATED BACK TO BACK AGREEMENT WITH NETWORK RAIL AND TO ACCEPT
More informationST. AUGUSTINE S CATHOLIC PRIMARY SCHOOL
ST. AUGUSTINE S CATHOLIC PRIMARY SCHOOL HEALTH & SAFETY POLICY SEPTEMBER 2017 THIS HEALTH & SAFETY POLICY WAS APPROVED AND ADOPTED BY THE FULL GOVERNING BODY ON: 1 CONTENTS STATEMENT OF INTENT 3 ORGANISATIONAL
More informationEngland s Economic Heartland Strategic Alliance Strategic Transport Forum. 12 th February Agenda Item 4: Governance Arrangements
England s Economic Heartland Strategic Alliance Strategic Transport Forum 12 th February 2016 Agenda Item 4: Governance Arrangements Recommendation: It is recommended that: a) The Terms of Reference are
More informationHealth and Safety Provision Statements of Intent. The Harpur Trust Health & Safety Policy
Health and Safety Provision Statements of Intent For further information and to see a copy of our complete Health and Safety Policy, please contact the School. The Harpur Trust Health & Safety Policy 1
More informationEnvironment Committee 11 January 2017
Environment Committee 11 January 2017 Title Playing Pitch Strategy 2017/2022 Report of Wards Status Urgent Key Enclosures Commissioning Director: Environment All Public No No Draft Playing Pitch Strategy
More informationSERVICE CONTRACT NOTICE
Public document to be completed by the Contracting Authority SERVICE CONTRACT NOTICE Technical Assistance to the programme: Renewable energy and energy efficiency programme in Jordan The Hashemite Kingdom
More informationCentral London Clinical Commissioning Group Governing Body Meeting 13 August 2014
Central London Clinical Commissioning Group Governing Body Meeting 13 August 2014 CONTRACT AWARD - CARE PROVIDER PROCUREMENT OF SPECIALIST HOUSING FOR OLDER PEOPLE IN WESTMINSTER (SHSOP) 1. Executive Summary
More information1 - PROJECT DETAILS 1.1 PROMOTER S INFORMATION. Title and full name of main contact: Position: Investment and Economic Initiatives Manager
Strategic Outline Business Case Please complete this to enable an initial assessment of your project. Once completed, please return by email to callsubmissions@sheffieldcityregion.org.uk by 5pm on 8 th
More informationCorporate Report Format. To the Mayor and Members of the Cabinet. Town Centre Wi-Fi Solution. Relevant Cabinet Wards Affected Key Decision
Corporate Report Format To the Mayor and Members of the Cabinet Town Centre Wi-Fi Solution Relevant Cabinet Wards Affected Key Decision Member(s) Cllr Tony Corden Town K1302 EXECUTIVE SUMMARY 1. This report
More informationReport to Cabinet. 19 April Day Services for Older People (Key Decision Ref. No. SMBC1621) Social Care
Agenda Item 4 Report to Cabinet 19 April 2017 Subject: Presenting Cabinet Member: Day Services for Older People (Key Decision Ref. No. SMBC1621) Social Care 1. Summary Statement 1.1 On 18 May 2016, Cabinet
More informationVAUGHAN PRIMARY SCHOOL HEALTH AND SAFETY POLICY
VAUGHAN PRIMARY SCHOOL HEALTH AND SAFETY POLICY Reviewed: Summer 2017 Next Review: Summer 2018 GENERAL The Governing Body notes the provisions of the Health and Safety at Work. etc Act 1974 (s.3(1)), which
More informationReservation of Powers to the Board & Delegation of Powers
Reservation of Powers to the Board & Delegation of Powers Status: Draft Next Review Date: March 2014 Page 1 of 102 Reservation of Powers to the Board & Delegation of Powers Issue Date: 5 April 2013 Document
More informationApplication for Funding
About this form This form enables you to make an application for funding under any of the three investment tiers for the Provincial Growth Fund: Regional Projects and Capability; Sector Investments; and
More information1.1 To provide the LEP Board with an update on the work of the Employment and Skills Panel (ESP).
Panel Chair: Stephanie Burras Author: Emma Longbottom Report to: LEP Board Date: 29 November 2017 Subject: Employment and Skills Panel 1 Purpose 1.1 To provide the LEP Board with an update on the work
More informationRequest for Supplementary Tender (mini-competition)
Request for Supplementary Tender (mini-competition) HEA - SYSTEM OF ROLLING REVIEWS Review of Procurement Practices in HEA-funded Higher Education Institutions Terms of Reference Background As part of
More informationKINETON GREEN PRIMARY SCHOOL HEALTH AND SAFETY POLICY
KINETON GREEN PRIMARY SCHOOL HEALTH AND SAFETY POLICY March 2015 Review Date March 2016 Section One Health and Safety Policy CONTENTS 1.1 Introduction 1.2 The School Health & Safety Policy Statement of
More informationKildare County Council
Kildare County Council PUBLIC SPENDING CODE Quality Assurance Report for 2016 To be submitted to the National Oversight and Audit Commission (NOAC) Certification This Annual Quality Assurance Report sets
More informationAdults and Safeguarding Committee 19 March Implementing the Care Act 2014: Carers; Prevention; Information, Advice and Advocacy.
Adults and Safeguarding Committee 19 March 2015 Title Report of Wards Implementing the Care Act 2014: Carers; Prevention; Information, Advice and Advocacy Dawn Wakeling (Adult and Health Commissioning
More informationNHS ENGLAND INVITATION TO TENDER STAGE TWO ITT NHS GENOMIC MEDICINE CENTRE SELECTION - WAVE 1
NHS ENGLAND INVITATION TO TENDER STAGE TWO ITT NHS GENOMIC MEDICINE CENTRE SELECTION - WAVE 1 2 NHS England - Invitation to Tender Stage Two ITT: NHS Genomic Medicine Centre Selection - Wave 1 Version
More informationNHS WOLVERHAMPTON CLINICAL COMMISSIONING GROUP CONSTITUTION
NHS WOLVERHAMPTON CLINICAL COMMISSIONING GROUP CONSTITUTION Version: [78] NHS England Effective Date: 1 December 2015 April 2017 CONTENTS Part Description Page Foreword 1 1 Introduction and Commencement
More informationCabinet Member for Education, Children and Families
Meeting Cabinet Resources Committee Date 24 September 2013 Subject Provision of therapies to Children with Special Educational Needs and placements to children in care Report of Summary Cabinet Member
More information1. Governance Services receive draft report Name of GSO Jeremy Williams. Date. Name. Date
DELEGATED POWERS REPORT NO. SUBJECT: Early Intervention and Prevention Services Family Nurse Partnership All of the following actions MUST be completed at each stage of the process and the signed and dated
More informationHEALTH AND SAFETY POLICY
Date written November 2016 Date of renewal When required Date approved November 2016 Approved by FGB HEALTH AND SAFETY POLICY Statement of Intent The headteacher and governing body of Sholing Infant School
More informationspecialising in maths and computing Health, Safety and Environmental Policy Date March 2012 Review Date March 2014 Governor Committee Health & Safety
specialising in maths and computing Health, Safety and Environmental Policy Date March 2012 Review Date March 2014 Governor Committee Health & Safety HEALTH, SAFETY AND ENVIRONMENTAL POLICY HEALTH AND
More informationFor anyone interested the plans are available to view in reception.
Commencement of Building Works In the last newsletter we informed everyone that the practice is being expanded. We are now pleased to announce that the builders will be on site from Monday 15 th January.
More information2014 to 2020 European Structural and Investment Funds Growth Programme. Call for Proposals European Social Fund. Priority Axis 2 : Skills for Growth
2014 to 2020 European Structural and Investment Funds Growth Programme Call for Proposals European Social Fund Priority Axis 2: Skills for Growth Managing Authority ESI Fund Priority Axis: Investment Priority
More informationFreedom of Information Policy
Freedom of Information Policy Prepared By Deputy Chief Executive Approved By Operational Policy Policy Review Date October 2018 1 Contents 1. Purpose... 3 2. Scope... 3 3. Classes of information... 4 4.
More informationSTANDARD GRANT APPLICATION FORM 1 REFERENCE NUMBER OF THE CALL FOR PROPOSALS: 2 TREN/SUB
STANDARD GRANT APPLICATION FORM 1 PROGRAMME CONCERNED: 2 ACTIONS IN THE FIELD OF URBAN MOBILITY REFERENCE NUMBER OF THE CALL FOR PROPOSALS: 2 TREN/SUB 02-2008 [Before filling in this form, please read
More informationDate 14/10/09. Date 15/10/09. Date 29/10/09. Date 29/10/09. Name of TU rep. Colin Petrie issues only) Date 23/09/09. Date 21/10/09.
DELEGATED POWERS REPORT NO. 917 SUBJECT: New Post in Safeguarding and Social Care Participation Worker Children in Care Control sheet All of the following actions MUST be completed at each stage of the
More informationGENERAL STATEMENT OF SAFETY POLICY
THE SOUTHERN EDUCATION & LIBRARY BOARD GENERAL STATEMENT OF SAFETY POLICY POLICY OBJECTIVE: The objective of this Policy is to ensure, so far as is reasonably practicable, that no person is placed in a
More informationWestern Australian Industry Participation Strategy (WAIPS)
Western Australian Industry Participation Strategy (WAIPS) Table of Contents Message from the Premier... 2 1. Overview... 3 2. Coverage... 3 3. Key Components of the WAIPS... 4 3.1 Procurement Related
More informationStatement of responsibilities for grants certification Wales Audit Office
Statement of responsibilities for grants certification Wales Audit Office Date issued: December 2016 Document reference: 707A2016 This document has been prepared as part of work performed in accordance
More informationSUSTAINABLE TRAVEL GRANT SCHEME GUIDANCE NOTES. For. Matched Funded Grants Maximum 2,000
SUSTAINABLE TRAVEL GRANT SCHEME GUIDANCE NOTES For Matched Funded Grants Maximum 2,000 2017-2018 Strathclyde Partnership for Transport (SPT) has created a Sustainable Travel Grant Scheme (STGS) which councils,
More informationGUIDANCE ON MANAGING CHURCH BUILDING PROJECTS
GUIDANCE ON MANAGING CHURCH BUILDING PROJECTS Introduction Responsibility for Church buildings rests with each Parochial Church Council (PCC) under the Constitution. PCCs will therefore be involved from
More informationBASINGSTOKE AND NORTH HAMPSHIRE HOSPITALS NHS FOUNDATION TRUST
BASINGSTOKE AND NORTH HAMPSHIRE HOSPITALS NHS FOUNDATION TRUST SUMMARY This policy provides guidance for providing safe maintenance procedures for assets and buildings owned by the Trust. 1 BASINGSTOKE
More informationHeritage Grants - Receiving a grant. Mentoring and monitoring; Permission to Start; and Grant payment
Heritage Grants - Receiving a grant Mentoring and monitoring; Permission to Start; and September 2017 1 Introduction... 2 Filling in forms... 2 Before Starting... 2 Reporting on progress... 3 Mentoring
More informationSecuring excellence in IT Services. Operating Model for Community Pharmacies, Appliance Contractors, Dental Practices and Community Optometry
Securing excellence in IT Services Operating Model for Community Pharmacies, Appliance Contractors, Dental Practices and Community Optometry December 2012 Table of Contents 01 Glossary of terms 02 Introduction
More informationHealth & Safety Policy - SCHOOL RESPONSIBILITIES
Health & Safety Policy - SCHOOL RESPONSIBILITIES Headteacher and Governors Head Teachers are responsible for the day-to-day Health and Safety management of schools and all staff directly employed by the
More informationSPECIALIST PROVISION: PROCUREMENT AND DIRECTORY
SPECIFICATION SPECIALIST PROVISION: PROCUREMENT AND DIRECTORY Matt Hempstock Project Manager West of England Works matt.hempstock@weston.ac.uk 1 1. EXECUTIVE SUMMARY 1.1. The West of England Works Project
More informationBARNSLEY METROPOLITAN BOROUGH COUNCIL
BARNSLEY METROPOLITAN BOROUGH COUNCIL This matter is not a Key Decision within the Council s definition and has not been included in the relevant Forward Plan Joint Report of the Director Finance, Assets
More informationGENERAL HEALTH AND SAFETY POLICY
GENERAL HEALTH AND SAFETY POLICY 2017-18 GENERAL STATEMENT OF INTENT Moreton Hall is committed to ensuring the health and well being of its students, staff and visitors, so far as is reasonably practicable.
More informationHealth and Safety Policy for Worcesters School
London Borough of Enfield Health and Safety Policy Worcesters Primary School 01.03.16 Name Signature Date Revised by: Checked and Reviewed by: Approved by: Lesley Crossman Karen Jaeggi Chair of Governors
More informationPOLICY ON THE CONTROL OF ASBESTOS AT WORK
POLICY ON THE CONTROL OF ASBESTOS AT WORK Review date: 27/10/2018 Reviewer: Compliance Officer Circulation for comment: Technical Services Manager Works Supervisor Building Supervisor Data Coordinator
More informationChairman of Environment Committee. Summary
Environment Committee 14 March 2018 Title Report of Wards Status Urgent Key Copthall Sports Hub and Mill Hill Open Spaces Draft Masterplan Chairman of Environment Committee All Public No No Enclosures
More informationStifford Clays Primary School
Stifford Clays Primary School Health and Safety Policy 1 Contents Item Paragraph Numbers Statement of Commitment 3-4 Health and Safety Action Plan 5 Responsibilities 6 High Vigilance towards All Children
More informationSample CHO Primary Care Division Quality and Safety Committee. Terms of Reference
DRAFT TITLE: Sample CHO Primary Care Division Quality and Safety Committee Terms of Reference AUTHOR: [insert details] APPROVED BY: [insert details] REFERENCE NO: [insert details] REVISION NO: [insert
More informationMemorandum of agreement. The following memorandum of agreement must be used as required by direction 3(b). Memorandum of Agreement
Appendix A Memorandum of agreement The following memorandum of agreement must be used as required by direction 3(b). Memorandum of Agreement Section 256 transfer Reference number: NHSG 001 Title of Scheme:
More informationSPONSORSHIP AND JOINT WORKING WITH THE PHARMACEUTICAL INDUSTRY
SPONSORSHIP AND JOINT WORKING WITH THE PHARMACEUTICAL INDUSTRY 1 SUMMARY This document sets out Haringey Clinical Commissioning Group policy and advice to employees on sponsorship and joint working with
More informationOperational date 01 April 2012 Review date April 2014 Version Number V0.3 Supersedes
Page 1 of 12 Title Health and Safety Policy Summary Purpose A Policy outlining an undertaking by the BSO to comply with the Health and Safety at Work (NI) Order 1978. It includes a policy statement, definitions
More informationThe South African Council for the Project and Construction. Management Professions (SACPCMP)
THE SOUTH AFRICAN COUNCIL FOR THE PROJECT AND CONSRUCTION MANAGEMENT PROFESSIONS The South African Council for the Project and Construction Management Professions (SACPCMP) Registration Rules for Construction
More informationHealth and Safety Roles, Responsibilities and Organisation
Health and Safety Roles, Responsibilities and Organisation Document Control Information Published Document Name: safety-organisation-gn.pdf Date issued: November 2015 Version: 3.0 Previous Review Dates:
More informationGUIDE FOR APPLICANTS INTERREG VA
GUIDE FOR APPLICANTS INTERREG VA Cross-border Programme for Territorial Co-operation 2014-2020, Northern Ireland, Border Region of Ireland and Western Scotland & PEACE IV EU Programme for Peace and Reconciliation
More informationSample Privacy Impact Assessment Report Project: Outsourcing clinical audit to an external company in St. Anywhere s hospital
Sample Privacy Impact Assessment Report Project: Outsourcing clinical audit to an external company in St. Anywhere s hospital October 2010 2 Please Note: The purpose of this document is to demonstrate
More informationPrivate Practice & Fee Paying Work For Medical Staff
Private Practice & Fee Paying Work For Medical Staff Policy: HR69 Policy Descriptor This document sets out standards for Medical Staff employed by the Trust about their conduct in relation to private practice
More informationProcurement of Social Care Services from Independent Providers
This is an official Northern Trust policy and should not be edited in any way Procurement of Social Care Services from Independent Providers Reference Number: NHSCT/12/484 Target audience: All staff in
More informationWorkforce Development Fund
Workforce Development Fund 2018 19 Partnership application form guidance January 2018 (v1.0) Contents Introduction... 2 The application process and timetable... 2 Qualifications and learning programmes
More informationPolicy Rules for the ORIO Grant Facility
Policy Rules for the ORIO Grant Facility Policy Rules grant facility ORIO 2012 1. What is ORIO?... 3 2. Definitions... 3 3. The role of infrastructure... 4 4. Implementation... 5 5. Target group... 5 6.
More informationImproving outdoor PE and sport facilities. Primary Spaces Roles and Responsibilities Tender and Installation Process
Improving outdoor PE and sport facilities Primary Spaces Roles and Responsibilities Tender and Installation Process Welcome to Primary Spaces 2. 18m We re investing 18 million of National Lottery funding
More informationSENIORS ALERT SCHEME Information Brochure September 2015
SENIORS ALERT SCHEME Information Brochure September 2015 INTRODUCTION The purpose of this brochure is to provide a background for organisations to the Seniors Alerts Scheme (SAS) and outline how the scheme
More informationEntrepreneurs Programme - Supply Chain Facilitation
Entrepreneurs Programme - Supply Chain Facilitation Version: 2 February 2016 Contents 1 Purpose of this guide... 4 2 Programme overview... 4 2.1 Business Management overview... 4 2.2 Supply Chain Facilitation
More informationGledhow Primary School Health and Safety Policy. The following statement sets out the health and safety objectives for the School.
Gledhow Primary School Health and Safety Policy Section 1: The Policy Statement The following statement sets out the health and safety objectives for the School. Will take all reasonable steps to provide
More informationLEGAL PROFESSION ACT (CHAPTER 161) LEGAL PROFESSION (CONTINUING PROFESSIONAL DEVELOPMENT) RULES 2012
LEGAL PROFESSION ACT (CHAPTER 161) LEGAL PROFESSION (CONTINUING PROFESSIONAL DEVELOPMENT) RULES 2012 GUIDELINES ON THE CONTINUING PROFESSIONAL DEVELOPMENT SCHEME 2017 (with effect from 1 January 2017)
More information2018 No. (W. ) WELSH LANGUAGE. The Welsh Language Standards (No. 7) Regulations 2018 D R A F T W E L S H S T A T U T O R Y I N S T R U M E N T S
Draft Regulations laid before the National Assembly for Wales under section 150(2) of the Welsh Language (Wales) Measure 2011, for approval by resolution of the National Assembly for Wales. D R A F T W
More informationCODE OF CONDUCT WHERE GP PRACTICES OR CONSORTIA ARE POTENTIAL PROVIDERS OF CCG COMMISISONED SERVICES
CODE OF CONDUCT WHERE GP PRACTICES OR CONSORTIA ARE POTENTIAL 1. Introduction PROVIDERS OF CCG COMMISISONED SERVICES 1.1. Managing potential conflicts of interest appropriately is needed to protect the
More informationTargeted Regeneration Investment. Guidance for local authorities and delivery partners
Targeted Regeneration Investment Guidance for local authorities and delivery partners 20 October 2017 0 Contents Page Executive Summary 2 Introduction 3 Prosperity for All 5 Programme aims and objectives
More informationQUALITY COMMITTEE. Terms of Reference
QUALITY COMMITTEE Terms of Reference CONSTITUTION 1. The Board of Directors approved the establishment of the Quality Committee (known as the Committee in these terms of reference) for the purpose of:
More informationHealth and Safety Policy
Health and Safety Policy Health & Safety Policy for Winton Primary School 1. Policy Statement The aim of the governing body and the headteacher is to provide a safe and healthy working and learning environment
More informationThe Royal Wolverhampton NHS Trust
The Royal Wolverhampton NHS Trust Trust Board Report Meeting Date: 25th July 2016 Title: Executive Summary: Action Requested: Author: Contact Details: Resource Implications: Equality and Diversity Assessment
More informationCity of Lincoln Council. Lincolnshire County Council North Kesteven District Council
Agenda Item 8 THE HEALTH SCRUTINY COMMITTEE FOR LINCOLNSHIRE Boston Borough Council East Lindsey District Council City of Lincoln Council Lincolnshire County Council North Kesteven District Council South
More informationAny Qualified Provider: your questions answered
Any Qualified Provider: your questions answered September 8, 2011 These answers cover a range of questions about the detail of Any Qualified Provider on integrated care, competition and procurement, liability
More informationDEPARTMENT OF FACILITIES MANAGEMENT MAINTENANCE AND SERVICES INVITATION TO TENDER
DEPARTMENT OF FACILITIES MANAGEMENT MAINTENANCE AND SERVICES INVITATION TO TENDER UNIVERSITY OF PRETORIA ELECTRICITY INFRASTRUCTURE SURVEY Tender No : FM/SUR/2014/104 Closing Date : 14 March 2014 Time
More informationTowards Quality Care for Patients. National Core Standards for Health Establishments in South Africa Abridged version
Towards Quality Care for Patients National Core Standards for Health Establishments in South Africa Abridged version National Department of Health 2011 National Core Standards for Health Establishments
More informationHealth & Safety Policy
Health & Safety Policy Title Health & Safety Policy Author Head of Health & Safety Approved by Management Board Issue date 1 st May 2015 Review date March 2018 (or sooner if necessary) Links to other procedures
More informationTransatlantic Strategy Forum
EUROPEAN COMMISSION DIRECTORATE-GENERAL FOR EXTERNAL RELATIONS Transatlantic Strategy Forum CALL FOR PROPOSALS N o RELEX/C1/2009/TSF Application Deadline: 14 April 2009 An amount of EUR 50,000 was earmarked
More informationScottish Environment Protection Agency Procurement Annual Report
Scottish Environment Protection Agency Procurement Annual Report 2017-2018 Page 1 of 9 1. Introduction This Annual Report provides an account of SEPA s procurement activity for 2017/18. 2. Background and
More informationEducational Visit - checklist To be read with DCC Outdoor Education, Visits and Off-Site Activities Health & Safety Policy - Devon County Council
Educational Visit - checklist To be read with DCC Outdoor Education, Visits and Off-Site Activities Health & Safety Policy - Devon County Council Adopted by Governors Sue Haywood Date 31.01.13 Review Date
More informationSTOCKPORT S PORTAS PILOT
STOCKPORT S PORTAS PILOT --- PROJECT APPLICATION PACK FOR GRANT FUNDING STOCKPORT PORTAS PILOT PROJECT DELIVERY GROUP Supported by Stockport Council Background In April 2013, members of Stockport s Town
More informationChildren Looked After Policy and Framework
Children Looked After Policy and Framework 1 SUMMARY This policy/framework demonstrates how the NHS Islington Clinical Commissioning Group (Islington CCG) meets its corporate accountability for Children
More informationHOUSING INFRASTRUCTURE FUND
Agenda Item No. 10 EXECUTIVE - 14 SEPTEMBER 2017 Executive Summary HOUSING INFRASTRUCTURE FUND In July 2017 the DCLG launched the Housing Infrastructure Fund. This is a government capital grant programme
More informationFramework Agreement for Care Homes in Central Bedfordshire
Meeting: Executive Date: 5 November 2013 Subject: Framework Agreement for Care Homes in Central Bedfordshire Report of: Summary: Cllr Carole Hegley, Executive Member for Social Care, Health and Housing
More informationSafeguarding Risk Assessment: Welfare, Health and Safety Policy. September 2017
Safeguarding Risk Assessment: Welfare, Health and Safety Policy September 2017 Relevant Staff Headteacher: Jessica Harris DSL: Helen Woodham H&S Lead: Julie McMillan (Business Manager), Tony Read (Caretaker)
More informationHealth and Safety Policy
Health and Safety Policy 2015 Statement of Health and Safety Policy The University recognises its obligations to properly control the risks to the health of its staff, students and visitors. Strong strategic
More informationSustainable Growth Agreement
Sustainable Growth Agreement 2050 Climate Group and Scottish Environment Protection Agency 6 July 2017 Sustainable Growth Agreement 6 July 2017 Between: Scottish Environment Protection Agency ( SEPA )
More informationHealthier Wigan Partnership Board. Richard Mundon Director of Strategy and Planning. Approve x Adopt Receive for information. On the BAF.
Trust Board Agenda Item 6. Date: 31.05.17 Title of Report Purpose of the report and the key issues for consideration/decision Prepared by: me & Title Presented by: Action Required (please X) Strategic/Corporate
More information