1 BASINGSTOKE AND NORTH HAMPSHIRE HOSPITALS NHS FOUNDATION TRUST SUMMARY This policy provides guidance for providing safe maintenance procedures for assets and buildings owned by the Trust. 1

2 BASINGSTOKE and NORTH HAMPSHIRE HOSPITALS NHS FOUNDATION TRUST Planned Preventative Maintenance and Building Refurbishment Policy CONTENTS ~~~~~~~~~~ Section Page 1. EXECUTIVE SUMMARY 4 2. INTRODUCTION 4 3. AIMS OF POLICY 5 4. OBJECTIVES 6 5. SCHEDULES AND PRIORITIES 7 6. PROCESS 7 7. AIR HANDLING SYSTEMS 8 8. CONTRACTORS POLICY LINKAGE RESPONSIBILITIES REFERENCES CONTRIBUTERS POLICY REVIEW 11 2

3 BASINGSTOKE and NORTH HAMPSHIRE HOSPITALS NHS FOUNDATION TRUST Planned Preventative Maintenance and Building Refurbishment Procedures Implementation Plan Invitation for comment by key stakeholders. March Submission to Infection Control Committee. March Submission to Divisional Governance Boards. March Submission to Executive Committee March Implementation. TBC Summary of changes Revision 1.1 Amendment made by Andrew Bowler to include section on Air Handling systems 26/02/2010. Reviewed in accordance with: - The Health and Social Care Act 2008: Code of Practice for health and adult social care on the prevention and control of infections and related guidance as published 16 December

4 1. EXECUTIVE SUMMARY. All of the building and the equipment within the boundaries of the land owned by Basingstoke and North Hampshire NHS should be subject to Planned Preventative Maintenance programmes to ensure that the safety of patients, staff and visitors are maintained at all times. Refurbishment of any areas of the Estates should also take into account the need for future maintenance requirements and ensure that these issues have been identified as part of the project. The Planned Preventative Maintenance programmes should be based around the requirements identified within Health Technical Memorandums, Health and Safety guidance documents and to ensure compliance all statutory requirements. All Trust General Managers are responsible for the area they manage to ensure safety of staff, patients and visitors. They should be aware, by Estates, of what is and is not being regularly maintained in their department. They should make the business cases for servicing of high risk building services and equipment with support from the Estates Department. The Estates Department is responsible for central services in plant rooms. It is essential all Planned Preventative Maintenance is recorded and that records are available to be scrutinised if required. This process is all managed by EFM helpdesk and a dedicated Estates software package called Eclipse. All Planned Preventative Maintenance carried out under a service contract will be managed by the Supplies department, Supplies will receive service sheets and inform the relevant managers of any rectification works identified as part of their visits. Supplies department will also ensure that Planned Maintenance visits take place against the schedules issues on appointment. All equipment to be maintained by Estates will be logged as assets and set up within the Estates Information Management IT system with specific maintenance tasks set at the correct time intervals as identified either by legislation, guidance or manufacturers recommendations. All equipment to be maintained by Medical Equipment Department will be logged within the MED Planned Preventative Maintenance Program with specific maintenance tasks set at the correct time intervals as identified either by legislation, guidance or manufacturers recommendations. In the event of staff shortages, exceptional periods of excessive defects and or revenue shortfalls the Planned Preventative Maintenance program may not be fully completed. The % completed will be reported to Corporate Governance each month, resources will be applied on a risk based rational, with activities that relate to statutory compliance and patient safety being of paramount importance when assessing risk. 2. INTRODUCTION The Trust attaches the greatest importance to the Health, Safety and Welfare of its staff, patients, contractors and visitors, and considers it essential that management and staff should work together to achieve an environment compatible with an acceptable provision of services to patients and visitors to reduce risks to the lowest reasonably practicable. 4

5 The purpose of the Planned Preventative Maintenance Program and Building Refurbishment policy is to: Meet Health and Safety and Statutory requirements Protect the assets of the installation and building Continue to provide the specified service /working environment. Provide a safe environment for staff and patients Ensure adequate investment into the Trust Estate The Planned Preventative Maintenance program will reflect best practice, manufacturer s recommendations or Hospital Technical Memoranda (HTM s) which provide additional guidance, that if not followed could be used against the Trust in a legal case. Revisions to HTM s and Health and Safety Executive guidance issued after plant was installed, generally require more stringent checks which require more resources and modifications. Therefore there is a need to review the plan annually to take into account any changes. The Health and Safety at Work etc Act 1974 requires the Trust to provide a safe environment and planned Preventative Maintenance schedules would be used by HSE in an investigation in action against the Trust, and lack of regular maintenance and checks on any equipment or service could be held to be a contributory issue. Many legal claims against the Trust for accidents can require evidence of regular checks of plant and equipment. Where Planned Preventative Maintenance is carried out these records are required to be made available from the Estates IT system. All Trust General Managers are responsible for the area they manage to ensure safety of staff, patients and visitors. They should be aware, by Estates, of what is and is not being regularly maintained in their department. They should make the business cases for servicing of high risk building services and equipment with support from the Estates Department. The Estates Department is responsible for central services in plant rooms. The age of the building stock can make it very difficult to fully implement PPM programmes. For example there is a lot of plant and equipment throughout the Trust that is obsolete and spares are no longer available. Therefore it is essential that a risk based backlog maintenance capital program is linked to the (Draft) Estates Strategy and (Draft) Estates Development Control plan is in place to address such issues, via a replacement or refurbishment program. A system for risk based Planned Maintenance procedures will be followed and a reporting procedure adopted to provide information to Governance boards. 3. AIMS OF POLICY The aim of this procedure is:- 1. To raise awareness of the need for Planned Preventative Maintenance programs for all equipment purchased throughout the Trust 2. To ensure those procuring diagnostic, medical and other electronic equipment consider Planned Preventative Maintenance implications at an early stage and consult with the appropriate technical department(s). 5

6 3. To ensure that the Trust operates a fair and consistent process in assessing requests for the Planned Preventative Maintenance of equipment and services 4. To ensure that the building services infrastructure of Trust properties is not put at risk by the uncontrolled introduction of equipment and plant 5. To ensure that adequate revenue is provided to allow for changes in legislation and thus to allow modification to Planned Preventative Maintenance schedules. 6. To ensure plant and building maintenance schedules are recorded. 7. To ensure that adequate service contracts are in place for equipment where specialist training and test equipment are required. 8. To identify through Planned Preventive Maintenance tasks, areas that require refurbishment. 9. To ensure that Infection Control issues are included in both Regular maintenance tasks and building refurbishments. 10. To provide a strategic link to address backlog maintenance and implement building refurbishment via the Capital Investment Group, (Draft) Estates Development Control plan and the (Draft) Estates strategy 4. OBJECTIVES 1. To provide a safe and energy efficient environment for staff, patients and visitors 2. To ensure, as far as practicable, that Building Infection Control issues are addressed during Planned Preventative Maintenance tasks and building refurbishments 3. To ensure maximum life cycles of plant and equipment are achieved. 4. To predict, monitor and prevent equipment failures by replacement or refurbishment of equipment. 5. To monitor plant performance against design parameters 6. To compile a comprehensive maintenance record for plant and equipment. 7. To ensure all new plant and equipment is adequately funded for Planned Preventative Maintenance before purchasing. 8. To ensure Estates staff are provided with adequate training and documentation to ensure correct maintenance is carried out. 9. To ensure best value is delivered for maintaining the plant and equipment. 10. To ensure equipment and plant is made available to maintain at correct intervals. 11. To ensure condemned and obsolete equipment is removed from the Planned Preventative Maintenance program 6

7 12. To ensure the Planned Preventative Maintenance program is updated following area and equipment. 13. To ensure the Planned Preventative Maintenance program is regularly updated to reflect new legislation and guidance. 5. SCHEDULING AND PRIORITY 1. All planned maintenance tasks are to be annually risk assessed and given a priority scored against compliance to legislation, guidance and Health Technical Memorandums. 2. The Estates Infection Control Committee will review any processes or procedures relating to Planned Preventative Maintenance, Building repair or refurbishment. 3. All Planned Maintenance tasks will be reported against a traffic light scoring system to indicate high, medium and low risk. 4. All statutory Planned Maintenance tasks (identified as Red using the traffic light system) are to be completed within 1 month of issue. 5. The Trust will aim to complete A minimum of 75% of all planned maintenance tasks each year. 6. Performance against planned maintenance activity will be reported to Corporate Governance Boards monthly 6. PROCESS 1. All new equipment is to be subject to Pre Purchase Questionnaire, (Via Supplies), to ensure that maintenance; training and energy requirements can be funded by the purchaser prior to procurement. For major schemes this process will be managed by the Capital Investment Group. 2. Any additional revenue consequences due to future changes in legislation must be met by the Trust. 3. For any equipment requiring specific training, the training is to be carried out at the time of commissioning or prior to the equipment being taken into use. 4. Revenue costs for new equipment to be identified and funded by the purchaser prior to purchase. This will include any refresher training requirements identified at the time of purchase 5. All equipment to be maintained by Estates will be logged as assets and set up within the Estates Information Management IT system with specific maintenance tasks set at the correct time intervals as identified either by legislation, guidance or manufacturers recommendations. 6. All equipment to be maintained by Medical Equipment Department will be logged within the MED Planned Preventative Maintenance Program with 7

8 specific maintenance tasks set at the correct time intervals as identified either by legislation, guidance or manufacturers recommendations. 7. At the pre determined dates the Planned Preventative Maintenance sheet will be allocated to an appropriately trained tradesman, any logbooks will be completed and the time spent will be recorded in the Estates Information Management IT system. 8. All spare parts or consumables replaced will be recorded against the job specific docket number to ensure full maintenance records are maintained. 9. The user will notify the Maintenance Manager (Estates) or the Medical Equipment Manager if there is any change of use of the equipment or areas. 10. Any breakdowns or equipment performance issues will be reported by the user via Facilities Helpdesk (Extension 3523), or Medical Equipment Department (Extension 3520) depending on equipment type. Significant equipment failures should also be reported by the Health and Safety Incident reporting process. 11. Planned Preventative Maintenance Programs will be reviewed annually, against budgets, by the Senior Engineer for Estates or Medical Equipment Manger. Any changes will be discussed with the Managers of the specific areas and Infection Control prior to any changes being made. 12. In the event of staff shortages, exceptional periods of excessive defects and or revenue shortfalls the Planned Preventative Maintenance program may not be fully completed. The % completed will be reported to Corporate Governance each month, resources will be applied on a risk based rational, with activities that relate to statutory compliance and patient safety being of paramount importance when assessing risk. 13. Estates will manage a dedicated rapid response team (Environmental Team) to specifically deal with minor wall damage, replacement of curtain rails etc, which may present an Infection Control risk to Patients, staff and Visitors. 14. Estates staff are to ensure that areas are kept clean during and following any works within the buildings, this will involve liaison with other Facilities Management staff to provide additional cleaning etc as required. 7. Air Handling Systems 1. All ventilation systems should be inspected on an annual basis, with systems associated with critical systems inspected on a quarterly basis. 2. The performance of all critical ventilation systems (such as those servicing operating theatres) need to be verified on an annual basis. 3. Local exhaust ventilation systems (extract systems) should be inspected and tested at least every 14 months. 4. The inspection should confirm that the system meets the following minimum requirements: - a. Safe access is possible whilst carrying out routine maintenance activities 8

9 b. The risks associated with Legionella and other potentially hazardous organisms have been managed c. The system remains fit for the purpose it was originally intended d. The system performance is adequate to the functional requirement eg air flow and air quality checks etc. e. The fire containment has not been breached 5. The maintenance frequency of the plant will be assessed according to the function of the system, it s location and the consequence of failure. 6. Air handling unit drainage systems should be inspected to ensure that they are clean and operating correctly. 7. Care should be taken whilst changing the air filters to avoid inhaling the dust, properly disposing of the used filters and vacuuming the dust residue from the filter housing to avoid contamination of the system. 8. Filters used in an extract system for the containment of hazardous substances or organisms should incorporate design provision for their safe removal. 9. The intake section of a ventilation system should be vacuumed-out to remove visible particles, the frequency of the cleaning operation will depend on the use of the system. 10. If the HEPA filters are changed on a ventilation system then an entrainment test needs to be carried out before the system is put back into service. 11. Critical ventilation systems should meet the following operating constraints during the verification process:- a. Achieve not less than 75% of the original design air-change rate b. Achieve not less than 75% of the original design pressure regime c. Sounds levels should not exceed levels specified in HTM Part B d. If the area is an horizontal ultra clean operating theatre the discharge velocity should not be less than 0.4 m/s e. If a critical system should fail to meet the above mentioned parameters it should be taken out of service 12. Pharmacy aseptic suites should conform to the requirements of the European guide to manufacturing practice and the requirements of the Medicine Inspectorate if a licensed manufacturing unit. 13. Sterile services inspection and packing rooms should conform to the requirements of BS EN ISO Inspection and maintenance regimes should be carried out in accordance with HTM Records of inspection and maintenance should be kept for at least five years 16. Any major issues associated with the status, operation or maintenance of the ventilation system should be discussed at the Decontamination & Estates Sub Committee. 9

10 17. When areas are being refurbished the use of negative pressure will be considered as a means of dust control for infection control management. This will be part of the Infection control team leads remit to advise of any practical methods that can be employed. Any other ventilation systems will also need to be assessed to ensure that any positive pressure effects are taken into account when works are being undertaken, this may involve the plant being isolated for the duration of the works. 8. CONTRACTORS 1. All contractors will be inducted in Trust procedures in accordance with the Management of contractor s policy. 2. All contractors will provide risk assessments and method statements in advance for all planned maintenance tasks to be carried out. 3. The contractor will be allocated a link Infection Control lead for the works as described in the management of Contractors policy. 4. The Trust must ensure that contractors employed to carry out planned maintenance and emergency support must be suitably qualified. 5. Contractors must be fully trained in the systems installed 6. Service contracts will be reviewed by Supplies prior to renewal and advice sought from the appropriate persons within the Trust to ensure full compliance with legislation is attained through the contract. 7. Supplies will ensure that all scheduled service visits occur as per contract and tat records are maintained for all works carried out. 8. Appropriate test equipment must be supplied by the contractor, as required, and be fully tested and calibrated 9. Copies of valid calibration certificates to be provided with any reports as required. 10. Contractors must have access to an adequate supply of spares to ensure that plant and equipment can be maintained correctly. 11. Service record sheets must always be provided following each service or breakdown visit. 9. POLICY LINKAGE This Policy is to be linked with the 1. Trust Procurement Policy. 2. Management of contractors policy 3. Hygiene Code 4. (Draft) Estates Strategy document 5. (Draft) Estates Development Plan Policy 10

11 6. Governance and Risk Management policy 7. Infection Control Manual 8. Business Continuity Plans 9. Incident, near miss hazard reporting policy 10. RESPONSIBILITIES a. The Trust will provide adequate funding to provide a full Planned Preventative Maintenance Program. b. The Trust will provide adequate capital investment to ensure refurbishment or replacement of plant or buildings as identified by condition monitoring. c. EFM helpdesk to log all contractors entering and leaving site. d. Supplies to ensure that companies providing service contracts are aware of the document and its requirements. e. Estates / Supplies to ensure that all Contractors complete relevant plant log books f. Designated Infection Control lead to ensure all infection control procedures are adhered to. 11. REFERENCES Health and Safety at work Act 1974 Standards for Better Health (DH 2006) NHSLA CONTRIBUTERS Paul Bond Andrew Bowler Chris Vowell Andrew Long Gary Turner David Gurd Tsambika Jeffries Tammie Purdue Hazel Gray Nigel Parker Corporate Governance Board MACH Governance Board Emergency Governance Board Elective Governance Board Infection Control Committee Head of EFM Maintenance Manager Building Supervisor Estates Electrical Supervisor Estates Mechanical Supervisor Estates Health and Safety Advisor Risk Manager Head of Supplies and Purchasing Infection Control Nurse Medical Equipment Manager 13. DOCUMENT REVIEW The Head of EFM and Maintenance Manager will conduct an annual review of the Procedure and its application. 11

The Newcastle upon Tyne Hospitals NHS Foundation Trust. Ventilation Policy

The Newcastle upon Tyne Hospitals NHS Foundation Trust. Ventilation Policy The Newcastle upon Tyne Hospitals NHS Foundation Trust Ventilation Policy Version.: 1.0 Effective From: 15 January 2016 Expiry Date: 15 January 2019 Date Ratified: 22 December 2015 Ratified By: Estates

More information

SUP 08 Operational procedures for Medical Gas Pipeline Systems (MGPS) Unified procedures for use within NHS Scotland

SUP 08 Operational procedures for Medical Gas Pipeline Systems (MGPS) Unified procedures for use within NHS Scotland SUP 08 Operational procedures for Medical Gas Pipeline Systems (MGPS) Unified procedures for use within NHS Scotland May 2015 Contents Page Acknowledgements... 4 Introduction... 5 1. Aim and scope... 6

More information

Facilities and Estates. Safety and Suitability of Premises Policy. Document Control Summary. Contents. New. Status:

Facilities and Estates. Safety and Suitability of Premises Policy. Document Control Summary. Contents. New. Status: Facilities and Estates Safety and Suitability of Premises Policy Document Control Summary Status: New Version: v1.0 Date: 29/1/2016 Author/Title: Owner/Title: Simon Davidson Assistant Director of Facilities

More information

HEALTH AND SAFETY POLICY

HEALTH AND SAFETY POLICY NHS GREATER GLASGOW AND CLYDE HEALTH AND SAFETY POLICY November 2015 Lead Manager: K. Fleming Head of Health and Safety Responsible Director A. MacPherson Director of Human Resources and Organisational

More information

specialising in maths and computing Health, Safety and Environmental Policy Date March 2012 Review Date March 2014 Governor Committee Health & Safety

specialising in maths and computing Health, Safety and Environmental Policy Date March 2012 Review Date March 2014 Governor Committee Health & Safety specialising in maths and computing Health, Safety and Environmental Policy Date March 2012 Review Date March 2014 Governor Committee Health & Safety HEALTH, SAFETY AND ENVIRONMENTAL POLICY HEALTH AND

More information

HEALTH AND SAFETY POLICY

HEALTH AND SAFETY POLICY HEALTH AND SAFETY POLICY Policy Statement, Specific Health and Safety Policies/ Safe Working Procedures Version 2 Page 1 of 11 General Health and Safety Policy Statement 1. Objectives 2. Responsibilities

More information

ESTATES VENTILATION POLICY

ESTATES VENTILATION POLICY ESTATES VENTILATION POLICY Policy Number: 382 Supercedes: Standards For Healthcare Services No/s Version No: Date Of Review: 1.0 March 2014 Reviewer Name: Completed Action: Approved by: Date Approved:

More information

Health and Safety Policy

Health and Safety Policy Health and Safety Policy Health & Safety Policy for Winton Primary School 1. Policy Statement The aim of the governing body and the headteacher is to provide a safe and healthy working and learning environment

More information

Prison Service Order Health and Safety Policy Statement

Prison Service Order Health and Safety Policy Statement Prison Service Order Health and Safety Policy Statement ORDER NUMBER 3801 Date of Initial Issue 20/04/2007 (replaces the previous version issued 23/03/05) Issue No. 273 PSI Amendments should be read in

More information

Health and Safety Policy

Health and Safety Policy Health and Safety Policy Policy reviewed by: Philippa Mills : September 2017 Next review date : September 2018 School refers to Cambridge International School; parents refers to parents, guardians and

More information

LSE HEALTH AND SAFETY POLICY

LSE HEALTH AND SAFETY POLICY LSE HEALTH AND SAFETY POLICY 1. Purpose 1.1. This document sets out the School s approach to fulfilling the requirements of legislation on health and safety. 2. Context 2.1. Health and Safety at Work etc.

More information

Electrical Services Policy

Electrical Services Policy Engineering, Maintenance & Infrastructure Electrical Services Policy EM&I C002 Version 1.0 15 th May 2015 Section Contents Page Page 1.0 Introduction... 4 2.0 Purpose... 4 3.0 Scope... 4 4.0 Management

More information

St Anne's Community Services Staff Manual

St Anne's Community Services Staff Manual 4.01 St Anne's Health and Safety Policy Title of Policy: 4.01 St. Anne s Health and Safety Policy Issue date: July 2016 Version number: V5.0 Ratified by: H&S Committee 27 th July 2016 Expiry date: July

More information

ASBESTOS POLICY. Version: 3 Senior Managers Operational Group Date ratified: March 2016

ASBESTOS POLICY. Version: 3 Senior Managers Operational Group Date ratified: March 2016 ASBESTOS POLICY Version: 3 Ratified by: Senior Managers Operational Group Date ratified: March 2016 Title of originator/author: Estates Manager Title of responsible committee/group: Regulation Governance

More information

Health and Safety Policy and Managerial Responsibilities

Health and Safety Policy and Managerial Responsibilities Health and Safety Policy and Managerial Responsibilities 1.0 Purpose This document outlines the policies, procedures and practices governing the manner in which the Royal Conservatoire of Scotland manages

More information

HEALTH AND SAFETY PRIORITY ACTION PLAN 2012/13

HEALTH AND SAFETY PRIORITY ACTION PLAN 2012/13 AGENDA ITEM 4.2 HEALTH AND SAFETY PRIORITY ACTION PLAN /13 Executive Lead: Deputy Chief Executive Author: Head of Health and Safety Contact Details for further information: Charles Dalton 02920 743751

More information

HEALTH and SAFETY POLICY

HEALTH and SAFETY POLICY HEALTH and SAFETY POLICY Version 5 March 2016 (review & minor amendments October 14 & March 2016) Approved by the Executive/SLT on: May 2012 Staff Consultative Group advised on: June 2012 Board of Governors

More information

PERSONAL PROTECTIVE EQUIPMENT (PPE) GUIDELINES

PERSONAL PROTECTIVE EQUIPMENT (PPE) GUIDELINES PERSONAL PROTECTIVE EQUIPMENT (PPE) GUIDELINES PURPOSE These guidelines support the Health and Safety Policy and provides assistance on the selection and use of PPE at the University. DEFINITIONS Hazard

More information

DistanceLearningCentre.com Ltd. Health and Safety Policy. Health and Safety at Work etc Act 1974

DistanceLearningCentre.com Ltd. Health and Safety Policy. Health and Safety at Work etc Act 1974 DistanceLearningCentre.com Ltd Health and Safety Policy Health and Safety at Work etc Act 1974 This is the Health and Safety Policy Statement of the DistanceLearningCentre.com Ltd. The Centre regards Health

More information

HEALTH & SAFETY RESPONSIBILITIES AND ARRANGEMENTS

HEALTH & SAFETY RESPONSIBILITIES AND ARRANGEMENTS HEALTH & SAFETY RESPONSIBILITIES AND ARRANGEMENTS Latest Revision July 2016 Reviewer: H&S Dept Next Revision July 2017 Compliance HASAW (1974) Associated Policies All H&S section policies Contents 1. Introduction

More information

GENERAL HEALTH AND SAFETY POLICY

GENERAL HEALTH AND SAFETY POLICY GENERAL HEALTH AND SAFETY POLICY 2017-18 GENERAL STATEMENT OF INTENT Moreton Hall is committed to ensuring the health and well being of its students, staff and visitors, so far as is reasonably practicable.

More information

Health and Safety Policy

Health and Safety Policy Health and Safety Policy Version: 9.0 Approval Status: Approved Document Owner: Geoff Slade Classification: External Review Date: 13/07/2018 Reviewed: 05/07/2016 Table of Contents 1. Statement of Intent...

More information

Date ratified November Review Date November This Policy supersedes the following document which must now be destroyed:

Date ratified November Review Date November This Policy supersedes the following document which must now be destroyed: Document Title Reference Number Lead Officer Author(s) (name and designation) Ratified by Cleaning Policy NTW(O)71 James Duncan Deputy Chief Executive / Executive Director of Finance Steve Blackburn Deputy

More information

Inspecting Informing Improving. Hygiene code inspection report: West Hertfordshire Hospitals NHS Trust

Inspecting Informing Improving. Hygiene code inspection report: West Hertfordshire Hospitals NHS Trust Inspecting Informing Improving Hygiene code inspection report: West Hertfordshire Hospitals NHS Trust December 2008 Outcome of inspection for: Hospital(s) visited: West Hertfordshire Hospitals NHS Trust

More information

P N R Associates Ltd

P N R Associates Ltd HEALTH AND SAFETY POLICY P N R Associates Ltd 19 Reading Road Pangbourne Berkshire RG8 7LR Tel: 0118 984 4646 Fax: 0118 984 4862 Email: info@pnr-associates.com PREPARED BY 16a Market Square, Sandy, Bedfordshire

More information

HEALTH & SAFETY POLICY. 1. Policy Schedule. Date of last review: October Date of next review: September 2018.

HEALTH & SAFETY POLICY. 1. Policy Schedule. Date of last review: October Date of next review: September 2018. HEALTH & SAFETY POLICY 1. Policy Schedule Date of last review: October 2017 Date of next review: September 2018 Policy Statement The Governors and the Chief Executive Officer / Group Principal of South

More information

RG 102 Accreditation for the Inspection of Non-public High Voltage Electrical Systems

RG 102 Accreditation for the Inspection of Non-public High Voltage Electrical Systems This publication contains policy, recommendations and guidance applicable to UKAS accredited inspection bodies RG 102 Accreditation for the Inspection of Non-public High Voltage Electrical Systems Contents

More information

Estates Quality Manual

Estates Quality Manual DOCUMENT CONTROL Author/Contact Document Reference Estates Quality Tel: 01946 523787 Email: steve.dougan@ncuh.nhs.uk Facilities Manger Tel: 01228 814507 Email: carol.johnston@ncuh.nhs.uk EFM_QMS_EFQM Version

More information

Announced Care Inspection Report 9 October N Wright Dental Practice Ltd

Announced Care Inspection Report 9 October N Wright Dental Practice Ltd Announced Care Inspection Report 9 October 2017 N Wright Dental Practice Ltd Type of Service: Independent Hospital (IH) Dental Treatment Address: 115 Holywood Road, Belfast, BT4 3BE Tel No: 028 9047 1471

More information

Occupational Health & Safety Policy

Occupational Health & Safety Policy Occupational Health & Safety Policy N.B. Staff should be discouraged from printing this document. This is to avoid the risk of out of date printed versions of the document. The Intranet should be referred

More information

Academy Health and Safety Policy 2017/2018

Academy Health and Safety Policy 2017/2018 Academy Health and Safety Policy 2017/2018 Academy Name: Summerhill Academy Implementation Date: September 2017 Version: 1 History of Policy Changes Date Page Change Reason for Change September 2015 October

More information

IGO GROUP SAFETY STANDARD 15 - ENERGY CONTROL AND ISOLATION INDEPENDENCE GROUP NL

IGO GROUP SAFETY STANDARD 15 - ENERGY CONTROL AND ISOLATION INDEPENDENCE GROUP NL IGO GROUP SAFETY STANDARD 15 - ENERGY CONTROL AND ISOLATION INDEPENDENCE GROUP NL CONTENTS 1. INTENT... 3 2. APPLICATION... 3 3. GENERAL REQUIREMENTS... 3 4. DETAILED GUIDANCE ON ISOLATION... 4 5. TRAINING

More information

Health & Safety Policy

Health & Safety Policy Health & Safety Policy Title Health & Safety Policy Author Head of Health & Safety Approved by Management Board Issue date 1 st May 2015 Review date March 2018 (or sooner if necessary) Links to other procedures

More information

HEALTH AND SAFETY POLICY 2010

HEALTH AND SAFETY POLICY 2010 April 2008 CONTENTS Page No ii 1 GENERAL STATEMENT OF POLICY 2 2 DELIVERING HEALTH AND SAFETY 3 2.1 Management 3 2.2 Policy and Procedures 3 2.3 Training 4 2.4 Communication and Involvement 4 2.5 The Working

More information

Control of Substances Hazardous to Health (COSHH) Procedure

Control of Substances Hazardous to Health (COSHH) Procedure Control of Substances Hazardous to Health (COSHH) Procedure Objective The purpose of this procedure is: To ensure that the necessary use of substances hazardous to health is safe and controlled. To ensure

More information

ST. AUGUSTINE S CATHOLIC PRIMARY SCHOOL

ST. AUGUSTINE S CATHOLIC PRIMARY SCHOOL ST. AUGUSTINE S CATHOLIC PRIMARY SCHOOL HEALTH & SAFETY POLICY SEPTEMBER 2017 THIS HEALTH & SAFETY POLICY WAS APPROVED AND ADOPTED BY THE FULL GOVERNING BODY ON: 1 CONTENTS STATEMENT OF INTENT 3 ORGANISATIONAL

More information

RISK ASSESSMENT POLICY

RISK ASSESSMENT POLICY RISK ASSESSMENT POLICY Sensible risk management is about practical steps to managing real risks, not bureaucratic back covering. Address the real risks, not only to pupils, but also to the health and well-being

More information

Ringwood Waldorf School

Ringwood Waldorf School Ringwood Waldorf School HEALTH AND SAFETY POLICY INTRODUCTION The Sheiling Trust carries legal responsibility for all the Activities on the estate and this includes the Ringwood Waldorf School. Health

More information

RG 103 Accreditation for the Inspection of Electrical Equipment in Quarries

RG 103 Accreditation for the Inspection of Electrical Equipment in Quarries This publication contains policy, recommendations and guidance applicable to UKAS accredited inspection bodies RG 103 Accreditation for the Inspection of Electrical Equipment in Quarries Contents Section

More information

Health and Safety Policy

Health and Safety Policy Health and Safety Policy Date Agreed: Review Date: September 2017 Approved by Governors Central CE Academy Revision Record Revision No. Date Issued Prepared By Approved 1 9 January 2017 SFa New policy

More information

ASBESTOS MANAGEMENT POLICY

ASBESTOS MANAGEMENT POLICY ASBESTOS MANAGEMENT POLICY Version 5.0 File ref ASBESTOS MANAGEMENT POLICY Date approved June 2016 Date to be reviewed June 2019 To by reviewed by ASBESTOS STEERING GROUP Asbestos Management Policy June

More information

Abu Dhabi Occupational Safety and Health System Framework (OSHAD-SF) Code of Practice

Abu Dhabi Occupational Safety and Health System Framework (OSHAD-SF) Code of Practice Abu Dhabi Occupational Safety and Health System Framework (OSHAD-SF) Code of Practice CoP 2.0 Personal Protective Equipment Version 3.1 June 2018 Table of Contents 1. Introduction... 3 2. Training and

More information

HEALTH & SAFETY POLICY CONTENTS

HEALTH & SAFETY POLICY CONTENTS Health & Safety Policy Statement of Intent Health and Safety responsibilities Health and Safety rules Warning signs Working conditions Fire precautions Accidents and Incidents Health Hygiene Protective

More information

PRE-REGISTRATION BUILDING AND ENGINEERING DOCUMENTATION CHECK LIST. - for - NEW BUILD NURSING HOMES

PRE-REGISTRATION BUILDING AND ENGINEERING DOCUMENTATION CHECK LIST. - for - NEW BUILD NURSING HOMES REGULATION AND QUALITY IMPROVEMENT AUTHORITY 9 th Floor Riverside Tower 5 Lanyon Place Belfast BT1 3BT Tel: (028) 9051 7500 Fax: (028) 9051 7501 PRE-REGISTRATION BUILDING AND ENGINEERING DOCUMENTATION

More information

Version: 2. Date adopted: 17 May publication: Review date: September Expiry date: March 2019

Version: 2. Date adopted: 17 May publication: Review date: September Expiry date: March 2019 Pest Control Policy This policy outlines the arrangements of management of pests on and within Trust properties Key words: Pest, Control Version: 2 Adopted by: Quality Assurance Committee Date adopted:

More information

CONTROLLED DOCUMENT. All Managers. All Employees. Page 1 of 30. Health and Safety Policy Issued: 26/01/2017

CONTROLLED DOCUMENT. All Managers. All Employees. Page 1 of 30. Health and Safety Policy Issued: 26/01/2017 CONTROLLED DOCUMENT CATEGORY: CLASSIFICATION: PURPOSE Controlled Document Number: Health and Safety Policy Policy Health and Safety Policy covering scope and responsibilities for health and safety in UHB

More information

HEALTH AND SAFETY POLICY STUDLEY HIGH SCHOOL

HEALTH AND SAFETY POLICY STUDLEY HIGH SCHOOL HEALTH AND SAFETY POLICY STUDLEY HIGH SCHOOL Review Period: Annually Autumn Term Review By: Leadership Group & P&R SP14 Health and Safety Policy Draft Oct 18 1 Reviewed & Approved by Governors, Date: Oct

More information

ROYAL COLLEGE OF ART HEALTH AND SAFETY POLICY

ROYAL COLLEGE OF ART HEALTH AND SAFETY POLICY ROYAL COLLEGE OF ART HEALTH AND SAFETY POLICY Mike Alexander Safety, Health and Environmental Officer 25 September 2012 1 1. HEALTH AND SAFETY POLICY STATEMENT In accordance with its duty under the Health

More information

Health & Safety Policy

Health & Safety Policy The Dales School Health and Safety Guidance Appendix 1 Health & Safety Policy Title Health & Safety Policy Author Head of Health & Safety Approved by Management Board Issue date 4 th October 2017 Review

More information

North East Ambulance Service NHS Trust Infection Prevention and Control Annual Work Plan April 2009 March 2010 October review (2)

North East Ambulance Service NHS Trust Infection Prevention and Control Annual Work Plan April 2009 March 2010 October review (2) North East Ambulance Service NHS Trust Infection Prevention and Control Annual Work Plan April 2009 March 2010 October review (2) No. Objective Actions Lead Date of 1 Leadership throughout Accountability

More information

Summers-Inman Group Health and Safety Policy SUMMERS-INMAN GROUP HEALTH AND SAFETY POLICY. Revision -

Summers-Inman Group Health and Safety Policy SUMMERS-INMAN GROUP HEALTH AND SAFETY POLICY. Revision - SUMMERS-INMAN GROUP HEALTH AND SAFETY POLICY 4 th November 2015 1 Table of Contents 1. Revision History... 5 2. Health and Safety Policy Statement... 7 3. Organisation... 9 Managing Director... 9 Group

More information

Health & Safety Policy

Health & Safety Policy Health & Safety Policy DATE ISSUED: 1 April 2014 DATE TO BE REVIEWED: 1 April 2014 Health & Safety Policy Page 1 of 11 CONTENTS POLICY OVERVIEW 1 Introduction 2 Purpose 3 Who This Policy Applies To 4 Key

More information

Health and Safety Updated September

Health and Safety Updated September Health and Safety Updated September 2011 1 STATEMENT OF INTENT 1. GENERAL The Employing Body recognises its overall responsibility for the health, safety and welfare of all employees, pupils and others

More information

Writtle College Health and Safety Policy

Writtle College Health and Safety Policy Writtle College Health and Safety Policy 2015-2016 Document Ownership: Role Title: Chair of the Board Department Approved by Senior Management Team 11 August 2015 Approved by Personnel & Remuneration Committee

More information

University of North Dakota Facilities Department Respiratory Protection Program. Table of Contents. 1.0 Introduction Purpose...

University of North Dakota Facilities Department Respiratory Protection Program. Table of Contents. 1.0 Introduction Purpose... University of North Dakota Facilities Department Respiratory Protection Program Table of Contents Section Page 1.0 Introduction...1 2.0 Purpose...1 3.0 Scope...1 4.0 Responsibilities...1 5.0 Respirator

More information

Compounded Sterile Preparations Pharmacy Content Outline May 2018

Compounded Sterile Preparations Pharmacy Content Outline May 2018 Compounded Sterile Preparations Pharmacy Content Outline May 2018 The following domains, tasks, and knowledge statements were identified and validated through a role delineation study. The proportion of

More information

Operational date 01 April 2012 Review date April 2014 Version Number V0.3 Supersedes

Operational date 01 April 2012 Review date April 2014 Version Number V0.3 Supersedes Page 1 of 12 Title Health and Safety Policy Summary Purpose A Policy outlining an undertaking by the BSO to comply with the Health and Safety at Work (NI) Order 1978. It includes a policy statement, definitions

More information

HEALTH AND SAFETY POLICY

HEALTH AND SAFETY POLICY HEALTH AND SAFETY POLICY Table of Contents Health and Safety Policy Statement... 3 Organisation (Roles & Responsibilities)... 4 Duties and Responsibilities of Parish Councillors... 4 Duties and Responsibilities

More information

Management Standard: Control of Legionella

Management Standard: Control of Legionella OHSS: H&S Management Standard 103 Control of Legionella Management Standard: Control of Legionella 1. Legal Framework This policy is produced to ensure compliance with; 1.1. the Health and Safety at Work

More information

Asbestos Management Policy (Version 4)

Asbestos Management Policy (Version 4) Asbestos Management Policy (Version 4) Contents Page Introduction 3 College Policy Statement for Asbestos Management 3 Objectives (of this Policy and Procedure) 3 Application of Policy 4 Licensed Asbestos

More information

Slips Trips and Falls Policy (Staff and Others)

Slips Trips and Falls Policy (Staff and Others) Title Reference Slips Trips and Falls Policy (Staff and Others) HS/POL/076 Description of document The purpose of this policy is to ensure all Norfolk Community Health & Care NHS Trust staff are aware

More information

Ark Academy. Health and Safety Policy Statement, Organisation and Arrangements June 2014

Ark Academy. Health and Safety Policy Statement, Organisation and Arrangements June 2014 Ark Academy Health and Safety Policy Statement, Organisation and Arrangements June 2014 This Health and Safety Policy incorporates: The Statement of Intent (Part 1) the declared commitment by the Ark Academy

More information

GENERAL STATEMENT OF SAFETY POLICY

GENERAL STATEMENT OF SAFETY POLICY THE SOUTHERN EDUCATION & LIBRARY BOARD GENERAL STATEMENT OF SAFETY POLICY POLICY OBJECTIVE: The objective of this Policy is to ensure, so far as is reasonably practicable, that no person is placed in a

More information

This policy applies to all staff and contractors working for the Agency and all persons working within its demised premises.

This policy applies to all staff and contractors working for the Agency and all persons working within its demised premises. 6 September 2012 EMA/65832/2011 Executive Director POLICY/0004 Status: Public Effective date: 06-Sep-12 Review date: 06-Sep-13 Supersedes: POLICY/0004 (18-APR-11) 1. Introduction and purpose It is the

More information

The Provision and Use of Work Equipment (PUWER) Policy

The Provision and Use of Work Equipment (PUWER) Policy The Provision and Use of Work Equipment (PUWER) Policy DOCUMENT CONTROL Version: 4 Ratified by: Estates Sub-Committee Date Ratified: 12 December 2016 Name of originator / author: Health and Safety Lead

More information

We are the regulator: Our job is to check whether hospitals, care homes and care services are meeting essential standards.

We are the regulator: Our job is to check whether hospitals, care homes and care services are meeting essential standards. Inspection Report We are the regulator: Our job is to check whether hospitals, care homes and care services are meeting essential standards. St Austell Dental Centre 28 East Hill, St Austell, PL25 4TR

More information

HEALTH AND SAFETY POLICY

HEALTH AND SAFETY POLICY Striving for Excellence Opportunity and Success for All HEALTH AND SAFETY POLICY Contents Policy Statement page number Organisation Roles and responsibilities Academy Trust 4 Principal 4 Senior Leadership

More information

OCCUPATIONAL HEALTH AND SAFETY POLICY: ARRANGEMENTS

OCCUPATIONAL HEALTH AND SAFETY POLICY: ARRANGEMENTS The Glasgow School of Art OCCUPATIONAL HEALTH AND SAFETY POLICY: ARRANGEMENTS February 2017 Policy Control Title Occupational Health And Safety Policy: Arrangements Date Approved February 2017 Approving

More information

BOXING SCOTLAND LIMITED (BSL) HEALTH & SAFETY POLICY

BOXING SCOTLAND LIMITED (BSL) HEALTH & SAFETY POLICY BOXING SCOTLAND LIMITED (BSL) HEALTH & SAFETY POLICY STATEMENT OF INTENT The BSL Board of Directors and senior management strive to achieve the highest standards of health, safety and welfare consistent

More information

Health and Safety Policy

Health and Safety Policy Health and Safety Policy Policy Nr 301 Page 1 of 11 General Statement of Health and Safety As Trustees of Lewes Old School we fully recognise our collective responsibility for providing, so far as is reasonably

More information

Health and Safety Policy

Health and Safety Policy Health and Safety Policy 2015 Statement of Health and Safety Policy The University recognises its obligations to properly control the risks to the health of its staff, students and visitors. Strong strategic

More information

HEALTH AND SAFETY POLICY

HEALTH AND SAFETY POLICY Date written November 2016 Date of renewal When required Date approved November 2016 Approved by FGB HEALTH AND SAFETY POLICY Statement of Intent The headteacher and governing body of Sholing Infant School

More information

Decontamination of Medical and Laboratory Equipment Prior to Maintenance or Transportation

Decontamination of Medical and Laboratory Equipment Prior to Maintenance or Transportation Decontamination of Medical and Laboratory Equipment Prior to Maintenance or Transportation Version 4.0 Date to be reviewed January 2020 To be reviewed by Medical Engineering Manager Policy Title: Decontamination

More information

ST BEDE S CATHOLIC ACADEMY FIRST AID POLICY

ST BEDE S CATHOLIC ACADEMY FIRST AID POLICY ST BEDE S CATHOLIC ACADEMY FIRST AID POLICY Document Management: Date Policy Approved: October 2009 Date reviewed: September 2018 Next Review Date: September 2021 Version: 2.0 Approving Body: Local Management

More information

Leadership and management of health and safety at the University of Warwick

Leadership and management of health and safety at the University of Warwick Leadership and management of health and safety at the University of Warwick Document Control Version Number Date issued Author Update information v1 07 11 16 7 Nov 2016 John Phillips Initial Issue v1.1

More information

Linen Services Policy

Linen Services Policy Policy No: IC10 Version: 6.0 Name of Policy: Linen Services Policy Effective From: 18/08/2015 Date Ratified 15/07/2015 Ratified Infection Prevention and Control Committee Review Date 01/07/2017 Sponsor

More information

Whitehouse Primary School. Health & Safety Policy

Whitehouse Primary School. Health & Safety Policy Whitehouse Primary School Health & Safety Policy To be accepted if agreed Sept. 2016 Review Date Sept. 2018 Overview Whitehouse Primary School s Health and Safety Policy is to provide and maintain safe

More information

Guidance for the assessment of centres for persons with disabilities

Guidance for the assessment of centres for persons with disabilities Guidance for the assessment of centres for persons with disabilities September 2017 Page 1 of 145 About the Health Information and Quality Authority The Health Information and Quality Authority (HIQA)

More information

College Health and Safety Committee/Board of Governors

College Health and Safety Committee/Board of Governors Title: 2017: Health and Safety Policy Originator: College Health and Safety Manager Date: 1 st April 2017 College Health and Safety Committee/Board of Governors General Statement of Intent 1. Introduction

More information

Occupational Health, Safety and Welfare Policy

Occupational Health, Safety and Welfare Policy Occupational Health, Safety and Welfare Policy June 2018 The document is the responsibility of: The Safety Office (prepared in conjunction with the university s health and safety Committee) This document

More information

Medical and First Aid

Medical and First Aid Medical and First Aid Date Review Date First Aid Nominated Persons Nominated Governor 25.10.17 Annual Joan Goatley - Lead Dawn Robinson Anna Hassan Julie Gilmartin Chair of Governors We believe this policy

More information

FIVEHEAD PARISH COUNCIL HEALTH & SAFETY POLICY

FIVEHEAD PARISH COUNCIL HEALTH & SAFETY POLICY FIVEHEAD PARISH COUNCIL HEALTH & SAFETY POLICY Adopted 9 Nov 2016 Minute 2605 Amended Min 2738 Review date (annual) Annual meeting of the Parish Council (May) GENERAL STATEMENT OF POLICY Fivehead Parish

More information

Consulted With Individual/Body Date Medical Devices Group August 2014

Consulted With Individual/Body Date Medical Devices Group August 2014 Medical Equipment Policy - Safe Use Of Medical Equipment Developed in response to: Contributes to Care Quality Commission Regulation Policy Registration No. 04066 Status: Public MHRA Guidance Regulation

More information

Health & Safety Policy & Procedures

Health & Safety Policy & Procedures Health & Safety Policy & Procedures [CS 1.0] Table of Contents Table of Contents... 2 1. Policy Statement... 4 2. Health and Safety Procedures Overview... 6 Part A Our Health and Safety Procedures... 7

More information

general criteria New Zealand Code of Radiology Management Practice for accreditation

general criteria New Zealand Code of Radiology Management Practice for accreditation general criteria for accreditation New Zealand Code of Radiology Management Practice Radiology Services Particular requirements for quality and competence Developed from NZS/ISO 15189: 2007 general criteria

More information

Statement of Principles

Statement of Principles Health and Safety Policy V2.1 Date Name Notes Drafted 22 nd Sep 2009 D.Robinson Drafted new version based on DCC model policy. Adopted 23 rd Nov 2009 PPC Reviewed 18 th Jun 2013 PPC Drafted new version

More information

ASBESTOS MANAGEMENT PLAN

ASBESTOS MANAGEMENT PLAN ASBESTOS MANAGEMENT PLAN REVISED JULY 2008 REVIEW DATE JULY 2009 Page 1 of 16 Contents 1.0 Introduction 3 2.0 Process 3 3.0 Programme for Compliance 3 4.0 Recording ACM s and Managing Risk 4 5.0 Responsibilities

More information

RQIA Provider Guidance Independent Clinic Private Doctor Service

RQIA Provider Guidance Independent Clinic Private Doctor Service RQIA Provider Guidance 2016-17 Independent Clinic Private Doctor Service www.r qia.org.uk A s s u r a n c e, C h a l l e n g e a n d I m p r o v e m e n t i n H e a l t h a n d S o c i a l C a r e What

More information

rksidehouseschoolparksidehou ouseschoolparksidehouseschool

rksidehouseschoolparksidehou ouseschoolparksidehouseschool Parksidehouseschoolparksideh ousesch oolparksidehouseschool Parkside House School parksid ehouseschoolpa rksideh First Aid Policy September ousesch oolparksidehou seschool July 2015 parksid ehouseschoolparksideh

More information

Jo Mitchell, Head of Assurance & Compliance (EFM) Policy to be followed by (target staff) Distribution Method

Jo Mitchell, Head of Assurance & Compliance (EFM) Policy to be followed by (target staff) Distribution Method Slips, Trips and Falls policy (Non-patient) Type: Policy Register No: 17020 Status: Public Developed in response to: Trust requirements Best Practice Contributes to CQC Outcome number: 15 Consulted With

More information

Health and Safety Policy and Procedures

Health and Safety Policy and Procedures DRD Builders Health and Safety Policy and Procedures VALID TO: 7 June 2016 Prepared on Wednesday, 5 August 2015-11:09am Page 1 of 33 Table of Contents 1. Policy Statement 3 2. Health and Safety Procedures

More information

Health, Safety and Wellbeing Policy

Health, Safety and Wellbeing Policy Health, Safety and Wellbeing Policy Page 1 of 18 Woodlands School - Health, Safety and Wellbeing Policy Section 1. Statement of Intent by Chair of Governors 2. Responsibilities - All Employees 3. Responsibilities

More information

ASBESTOS MANAGEMENT POLICY

ASBESTOS MANAGEMENT POLICY AGENDA ITEM 2.4 ASBESTOS MANAGEMENT POLICY Executive Lead: Director of Capital Planning, Estates and Operational Services Author: Estates Health & Safety and Asbestos Manager Contact Details for further

More information

HEALTH AND SAFETY MANAGEMENT AT UWE

HEALTH AND SAFETY MANAGEMENT AT UWE HEALTH AND SAFETY MANAGEMENT AT UWE Introduction This document sets out the University s strategic approach to health and safety management. It contains the Statement of Intent that outlines the University

More information

FIRST AID POLICY. Headteacher: Mrs S Allison. Approved by the Governing Board on:

FIRST AID POLICY. Headteacher: Mrs S Allison. Approved by the Governing Board on: FIRST AID POLICY Lawn Primary School, Norbury Close, Allestree, Derby DE22 2QR e-mail: admin@lawn.derby.sch.uk website: www.lawn.derby.sch.uk Tel./Fax: Derby (01332) 550178 Headteacher: Mrs S Allison Author:

More information

NHS Lewisham CCG Health & Safety Policy

NHS Lewisham CCG Health & Safety Policy NHS Lewisham CCG Health & Safety Policy Document Information Category: Summary: Corporate The purpose of this policy is to outline the Health and Safety strategy in accordance with statutory requirements

More information

CITY OF BIRMINGHAM EDUCATION DEPARTMENT BASKERVILLE SCHOOL HEALTH AND SAFETY POLICY

CITY OF BIRMINGHAM EDUCATION DEPARTMENT BASKERVILLE SCHOOL HEALTH AND SAFETY POLICY CITY OF BIRMINGHAM EDUCATION DEPARTMENT BASKERVILLE SCHOOL HEALTH AND SAFETY POLICY Date reviewed: April 2017 Next review: April 2018 BASKERVILLE SCHOOL, FELLOWS LANE, HARBORNE, BIRMINGHAM, B17 9TS TELEPHONE

More information

More Room 4U Ltd. H&S Arrangements & Procedures (English Version)

More Room 4U Ltd. H&S Arrangements & Procedures (English Version) More Room 4U Ltd H&S Arrangements & Procedures (English Version) Page 1 of 10 Document Control Date Author (print & sign name) Filename Version Final Approval By (print & sign name) 11.03.13 Janet Enright

More information

Cleaning of the Environment: Standard Operating Procedure

Cleaning of the Environment: Standard Operating Procedure Facilities and Estates Cleaning of the Environment: Standard Operating Procedure Document Control Summary Status: New Version: v1.0 Date: September 2015 Author/Title: Author/Title: Author/Title: Owner/Title:

More information

STRATHEARN SCHOOL. Draft HEALTH & SAFETY POLICY

STRATHEARN SCHOOL. Draft HEALTH & SAFETY POLICY STRATHEARN SCHOOL Draft HEALTH & SAFETY POLICY January 2016 CONTENTS Page Management Chain 3 Statement of General Policy 4-5 Organisation Responsibilities: 6 All Staff 6 Safety Representative 6-7 Heads

More information