1 Ohio Department of Transportation John R. Kasich, Governor Jerry Wray, Director The Process Errol Scholtz & Chris Brown ODOT District Three LPA Section September 22, 2016
2 Main Phases 1. Application and Scope 2. Preliminary Design 3. Detailed Design/ROW Acquisition 4. PS&E Package 5. Award 6. Construction 2
3 Main Phases 3
4 1. Application and Scope LPA Receives Notice of Project Funding Central Office or County Engineer s Association of Ohio (CEAO) Occasionally from other offices Notification provides details specific to project 4
5 1. Application and Scope LPA contacts the District for scoping meeting and field review Fill out forms Not necessary to have separate office meeting 5
6 1. Application and Scope Complete field review and draft scope of services form LPA invites their staff Consultant can be invited D03 invites staff 6
7 1. Application and Scope Complete Scope of Services Form Information must match award information & Ellis Local signs Scope ODOT P&E staff sign Submit enabling legislation 7
8 1. Application and Scope Complete LPA Participation Form Needs to be updated every three years Financial page required Update if there are changes in LPA 8
9 1. Application and Scope Prepare LPA Agreement District prepares after Scope is signed LPA signs, checks cost recovery method Agreement returned to District for Director s signature One original sent back to LPA 5 Cost recovery methods: 9
10 1. Application and Scope If Federal or State funds in design, LPA needs to: To follow Quality Based Selection (QBS) process Sign agreement and submit to District 3 District 3 requests Federal authorization for Preliminary Engineering 10
11 1. Application and Scope If Federal or State funds in design, LPA needs to: District 3 prepares and submit encumbrance request After money is encumbered, the District prepares 3 rd party agreement District 3 prepares Invoice & Payment System forms (IPS) Local prepares & submits invoices after paying local share 11
12 2. Design If LPA is going to use CEAO task order or OES task order: Provide scope to Levi Wingler District requests Federal authorization for PE District requests price proposal from consultant District prepares & submits encumbrance request 12
13 2. Design Project proceeds into design If significant changes in scope occur, contact the District If cost is significantly higher as design progresses, contact the District If project schedule is lagging, contact the District If ahead of schedule, thank you! 13
14 2. Design LPA submits Stage 2 (in most cases) 5 paper + electronic files Plans, estimate, utility coordination letters Project specific (Scope may have more or different submittal) 14
15 2. Design Plans approved Four-week review period May require resubmission May request disposition of comment at next submission Environmental has to be cleared before moving to Detailed Design (DD) 15
16 4. ROW Acquisition LPA submits Final ROW Plans If there is a Right of Way phase submit to Brad Corder Two sets of construction and ROW plans Two sets of descriptions + records supporting existing Once approved, will receive ok to begin acquisition 16
17 4. ROW Acquisition If federal money in Acquisition phase and/or DD District requests Federal authorization for sub-phase District prepares/submits encumbrance request LPA follows QBS or abbreviated QBS, receives price proposal District prepares 3 rd party agreement after receive District prepares IPS 17
18 4. PS&E Package Pre-PS&E Package submission Provide final estimate to the District for DBE goal All projects have to go to goalsetting committee Submit acquisition files to Brad Corder if project has ROW Assure environmental commitments are in place Provide NHS waiver if required Provide proprietary material waiver if required 18
19 4. PS&E Package Next step is PS&E package submission 4 hard copies + electronic file District will send Package checklist D3 completes ROW certification Environmental Consultation Form PS&E Submission form PS&E Checklist Biddable/Buildable IOC 19
20 4. PS&E Package District Submits PS&E Package to Central Office Local Programs Submitted electronically Central Office provides Federal authorization May take several weeks 20
21 4. PS&E Package Central Office sends Authorization to District District sends to local Authorizes local to bid and award project (but not begin construction) 21
22 22
23 5. Award LPA bids project Federal/State Requirements-advertise at least one time Open bids on 22 nd day after first advertisement Any addenda have to be reviewed by D03 LPA goes through review process to award project 23
24 5. Award LPA Submits award package Bid Tab Proof of Advertisement Attachment 2 for contractor for direct pay Enabling legislation Bid analysis checklist Construction start and complete dates 24
25 5. Award LPA Submits award package Single paper copy and electronic files D3 prepares IOC to accompany submission to CO If federal funding for construction engineering, submit info as well If LPA is doing CE, provide estimated cost for encumbrance Provide evidence of DBE goal approval 25
26 5. Award Construction Engineering Follow QBS process in selecting consultant Consultant for CE cannot be same consultant who designed project Can be submitted before award package is submitted Can also be awarded after the award package has been submitted 26
27 5. Award District notifies LPA of encumbrances Contractor cannot begin construction until money is encumbered Same with consultant District prepares LPA local let template District prepares IPS forms if Federal funds in CE 27
28 6. Construction Construction begins If project construction cost is going to exceed encumbered amount, notify Beth Wilson asap (Also Chris and Errol) Same for CE Ellis is revised and modification is sent to CO After money is encumbered, can invoice Can move money from CO to CE and vice versa, as long as Federal cap is not exceeded 28
29 6. Construction All other activities handled by construction department Invoices for CO and CE Change orders Construction monitoring Project closeout 29
30 Begin process all over with new project! 30
31 The Process Questions? 31
Plan Quality and Review
Ohio Department of Transportation John R. Kasich, Governor Jerry Wray, Director Plan Quality and Review Scott C. Boyer, P.E. LPA Coordinator District 7 Planning & Engineering October 4, 2016 Project Initiation
More informationOhio Department of Transportation. Transportation Funding for LPAs
Ohio Department of Transportation Transportation Funding for LPAs Christopher L. Brown, P.E., District Three LPA Errol R. Scholtz, E.I., District Three LPA John R. Kasich, Governor Jerry Wray, Director
More informationFederal-Aid LPA Design Process Overview. MoDOT St. Louis District Local Programs
Federal-Aid LPA Design Process Overview MoDOT St. Louis District Local Programs November 2017 Local Program Contacts St. Louis District Note: North St. Louis County = Along and north of Page Avenue Programming,
More informationProcedures for Local Public Agency Project Administration (Revised 5/2014)
Procedures for Local Public Agency Project Administration (Revised 5/2014) OVERVIEW A Local Public Agency (LPA) is defined as a county, municipal corporation, state or local authority, board, commission,
More informationOIG AUDIT A GRANTEE S PERSPECTIVE
OIG AUDIT A GRANTEE S PERSPECTIVE FLOOD SUMMER OF 2011 CDBG-DR ALLOCATION $67 MILLION 2012 CDBG-DR ALLOCATION $35 MILLION 2013 NOT AN ENTITLEMENT CITY BUT TREATED AS ONE THE LETTER OIG AUDIT NOTIFICATION
More informationJOINT PROCESS REVIEW OF THE VIRGINIA DEPARTMENT OF TRANSPORTATION S LOCAL GOVERNMENT ADMINISTERED FEDERAL-AID PROGRAM
JOINT PROCESS REVIEW OF THE VIRGINIA DEPARTMENT OF TRANSPORTATION S LOCAL GOVERNMENT ADMINISTERED FEDERAL-AID PROGRAM By Federal Highway Administration Virginia Division And Virginia Department of Transportation
More informationFederal Funding & Project Administration 101. Presented By: Kyle Johnson, P.E. (Bolton & Menk) Dan Erickson, P.E. (Metro District State Aid Engineer)
Federal Funding & Project Administration 101 Presented By: Kyle Johnson, P.E. (Bolton & Menk) Dan Erickson, P.E. (Metro District State Aid Engineer) Overview of Content Presentation Content This is a general
More informationAppendix B Review Matrix Text & Table Footnotes
Review Submissions The PDP includes a series of review submissions designed to ensure that all projects are developed in accordance with ODOT policies. The PDP Products Review Matrix found in this Appendix
More informationCHAPTER 19 FINANCIAL MANAGEMENT AND REIMBURSEMENT PROCESSING
CHAPTER 19 FINANCIAL MANAGEMENT AND REIMBURSEMENT PROCESSING Table of Contents 19.1 Introduction 19.2 Applicability 19.3 Processing of Invoices 19.4 Local Percentage 19.4.1 In-Kind Match 19.4.2 In-Kind
More informationUpdated December 2017
3 Updated December 2017 CHAPTER 19 FINANCIAL MANAGEMENT AND REIMBURSEMENT PROCESSING Table of Contents 19.1 Introduction 19.2 Applicability 19.3 Processing of Invoices 19.4 Local Percentage 19.4.1 In-Kind
More informationCity of Somersworth, New Hampshire OFFICE OF THE FINANCE DIRECTOR
SCOTT A. SMITH Finance Director sasmith@somersworth.com One Government Way Somersworth, New Hampshire 03878 Phone: (603) 692-9504 Fax: (603) 692-9570 www.somersworth.com City of Somersworth, New Hampshire
More informationREQUEST FOR QUALIFICATIONS (RFQ) FOR DESIGN ENGINEERING SERVICES FOR TOWN CENTER STORMWATER IMPROVEMENTS
REQUEST FOR QUALIFICATIONS (RFQ) FOR DESIGN ENGINEERING SERVICES FOR TOWN CENTER STORMWATER IMPROVEMENTS The Village of Richton Park has set forth to accomplish flood control projects in the Village s
More informationNevada Volunteers AmeriCorps Program Closeout Checklist and Certification
Nevada Volunteers AmeriCorps Program Closeout Checklist and Certification Instructions: The following closeout documents are due to Nevada Volunteers no later than 90 days following the expiration of the
More informationAddendum No.3 to ITB Wakulla County Fire and EMS Station Issued: November 1, 2017
Addendum No.3 to ITB 2017-33 Wakulla County Fire and EMS Station Issued: November 1, 2017 MANDATORY PRE-BID CONFERENCE RFI 1. ITB Section 2.0 Schedule of Events Bids are due November 20, 2017 @ 2:00 P.M.
More informationSTATE AID TO AIRPORTS PROGRAM NC DEPARTMENT OF TRANSPORTATION DIVISION OF AVIATION
APRIL 2018 STATE AID TO AIRPORTS PROGRAM State Authorization: N.C.G.S. 63 NC DEPARTMENT OF TRANSPORTATION DIVISION OF AVIATION Agency Contact Person Program and Financial Betsy Beam, Grants Administrator
More informationEnhancement Program Project Delivery Breakout Session #4C Track: Funding Programs
Enhancement Program Project Delivery Breakout Session #4C Track: Funding Programs Pam Liston TE Program Manager, VDOT Local Assistance Division October 25, 2012 Federal Reimbursement Program Transportation
More informationOahuMPO Transportation Alternatives Program
OahuMPO Transportation Alternatives Program Guide for Sponsors and Applicants Approved by the OahuMPO Policy Committee May 19, 2015 This guide focuses upon the Transportation Alternatives Program (TAP)
More informationThe Lifecycle of a Sponsored Project
The Lifecycle of a Sponsored Project Active Period Spending, Invoicing, Reporting, Monitoring Award Processing And Account Setup Final Reporting Proposal Closeout Funding Funding Sources Where is the Money?
More informationIowa DOT Update 2016 APWA Fall Conference JOHN E. DOSTART, P.E.
Iowa DOT Update 2016 APWA Fall Conference JOHN E. DOSTART, P.E. Hilton Garden Inn September 29, 2016 Member of the Day Personal Updates M.J. Charlie Purcell Promoted to Project Delivery Bureau Director
More informationLPA PARTICIPATION REQUIREMENTS
LPA Participation Requirements LPA PARTICIPATION REQUIREMENTS The Federal Highway Administration (FHWA) permits the Ohio Department of Transportation (ODOT) to delegate project activities on Federal-aid
More informationTransportation Advisory Board Regional Program Year Policy
Transportation Advisory Board Regional Program Year Policy - The Regional Program Year Policy is intended to manage the development and timely delivery of transportation projects awarded federal funds
More informationAppendix 3 to AO/1-7094/12/NL/CO Page 1
Page 1 NOTE THE BIDDERS ATTENTION IS DRAWN TO THE FACT THAT THE GENERAL TENDER CONDITION PUBLISHED ON EMITS ARE NOT APPLICABLE TO THE PRESENT INVITATION TO TENDER. THE ONLY APPLICABLE TENDER CONDITIONS
More informationGrants Management Workshop. Proposal and Award Management Support
Grants Management Workshop Proposal and Award Management Support Agenda Sponsored Project Administration UVM and RSENR Support Systems Provide an overview of the grant life cycle For each stage of the
More informationRESOLUTION NUMBER 2877
RESOLUTION NUMBER 2877 A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF PERRIS, STATE OF CALIFORNIA SETTING FORTH POLICIES INTENDED TO OBTAIN CONSISTENCY AND UNIFORMITY IN THE ADMINISTRATION OF THE FEDERALLY
More informationAmerican Recovery and Reinvestment Act (ARRA) Title 23 Refresher. FHWA Federal-Aid Program for Local Public Agencies
American Recovery and Reinvestment Act (ARRA) Title 23 Refresher FHWA Federal-Aid Program for Local Public Agencies 1 ARRA Implementation for Local Public Agencies Provide an overview of the fundamental
More informationADDRESS 30 South Meridian Street, Suite 1000, Indianapolis, IN PHONE TOLL FREE WEB
BEP Notice 18-98 To: BEP Recipient (All Divisions) From: Asset Preservation Department Date: Janurary 2, 2018 Re: New BEP Waiver Form & Site Evaluation Matrix (SEM) Effective immediately, all Recipients
More informationTxDOT Statewide 2017 TA Set-Aside Questions & Answers
TxDOT Statewide 2017 TA Set-Aside Questions & Answers Below are some common questions received in TxDOT s 2017 TA Set-Aside Call for Projects. The Code of Federal Regulations (CFR) and Texas Administration
More informationAPPLICATION FOR TECHNICAL ASSISTANCE PROGRAM CONTACT INFORMATION. Progress Energy Carolinas INCENTIVE PROGRAM
APPLICATION FOR TECHNICAL ASSISTANCE PROGRAM CONTACT INFORMATION Progress Energy Carolinas INCENTIVE PROGRAM Visit our website http://progress energy.com/carolinasbusiness or Call our program hotline 866.326.6059
More informationThe Recovery Act: Dealing with Closeout
The Recovery Act: Dealing with Closeout Kary Burin, Community Action Partnership Association of Idaho 1 Six Idaho agencies perform weatherization ti for low and moderate income families. CAP CCOA El-Ada
More informationLOCAL COORDINATED PLANNING GRANTS MAY 24, 2017
LOCAL COORDINATED PLANNING GRANTS MAY 24, 2017 LOCAL COORDINATED PLANNING GRANTS Danielle Gray, Statewide Mobility Coordinator Danielle.Gray@dot.ohio.gov 614-466-2309 2 Local Coordinated Planning Grants
More informationOhio Transportation Excellence in Diversity and Inclusion Awards
Ohio Transportation Excellence in Diversity and Inclusion Awards 2018 Nomination Nomination Deadline: January 31, 2018 Sponsored by: Awards Overview and Nomination Requirements 1. Program Name The program
More informationREQUEST FOR PROPOSALS
REQUEST FOR PROPOSALS FOR TO PREPARE PROFESSIONAL DESIGN SERVICES PLANS, SPECIFICATIONS, AND ESTIMATE (PS&E) FOR THE RAISED MEDIAN ALONG DR. MARTIN LUTHER KING JR. BOULEVARD CITY PROJECT NO. PW1716/ FEDERAL
More informationREQUEST FOR PROPOSALS
REQUEST FOR PROPOSALS FOR PROFESSIONAL DESIGN SERVICES RAISED MEDIAN ALONG DR. MARTIN LUTHER KING JR. BOULEVARD CITY PROJECT NO. PW1716 FEDERAL PROJECT NO. HSIPL-5008(167) CITY OF STOCKTON PUBLIC WORKS
More informationNon-Federal Cost Share Match Program Grant Implementation Checklist
Non-Federal Cost Share Match Program Grant Implementation Checklist Non-Federal Cost Share Match Program Grant Implementation Checklist Table of Contents 1.0 Introduction... 2.0 Grant Implementation Process
More informationOHIO TURNPIKE AND INFRASTRUCTURE COMMISSION
OHIO TURNPIKE AND INFRASTRUCTURE COMMISSION REQUEST FOR PROPOSALS ( RFP ) PROFESSIONAL ENGINEERING AND CONSTRUCTION ADMINISTRATION AND INSPECTION SERVICES REF: REHABILITATION OF VARIOUS BRIDGES AT MILEPOSTS
More informationAirport Project Development: From Beginning to End
Airport Project Development: From Beginning to End AVIATION DIVISION April 16, 2015 Embassy Suites San Marcos Introductions Amy Slaughter, CTPM Grants Harry Lorton, PE Engineering Ed Mayle, PM - Engineering
More informationO H I O P U B L I C W O R K S C O M M I S S I O N P R O J E C T G R A N T A G R E E M E N T
O H I O P U B L I C W O R K S C O M M I S S I O N P R O J E C T G R A N T A G R E E M E N T S T A T E C A P I T A L I M P R O V E M E N T P R O G R A M Pursuant to Ohio Revised Code 164.05 and Ohio Administrative
More informationQUALIFICATIONS BASED SELECTION (QBS)
QUALIFICATIONS BASED SELECTION (QBS) Transportation Professional Services Procurement Process LaSalle County Highway Department 1400 N.27 th Road Ottawa, IL 61350 Phone: (815) 434-0743 Fax: (815) 434-0747
More informationContact person: Ernestine Mbroh (405)
OKLAHOMA DEPARTMENT OF TRANSPORTATION Project Management Division 200 N.E. 21 st Street Oklahoma City, OK 73105-3204 Division Phone: (405) 522-7601 Division FAX: (405) 522-7612 DATE: June 29, 2010 TO:
More informationGREEN STORMWATER INFRASTRUCTURE DESIGN PROCESS WORKFLOW PACKET
GREEN STORMWATER INFRASTRUCTURE DESIGN PROCESS WORKFLOW PACKET Last Updated: May 15, 2015 1 GSI Process Workflow Introduction This packet provides summary workflows, detailed workflows, and expanded process
More informationTIER 1 CUT OFF GUIDELINES (7/30/12)
TIER 1 CUT OFF GUIDELINES (7/30/12) The attached schedule of steps in the process for advertisement of a project is an update of the schedules distributed previously. As before, this schedule applies to
More informationDEPARTMENT OF TRANSPORTATION POLICY FOR INDUSTRIAL PARK, AGRI-BUSINESS ACCESS, AND COMMUNITY ACCESS GRANT PROGRAMS
DOT-168 Revised 12/22/06 DEPARTMENT OF TRANSPORTATION POLICY FOR INDUSTRIAL PARK, AGRI-BUSINESS ACCESS, AND COMMUNITY ACCESS GRANT PROGRAMS SOUTH DAKOTA DEPARTMENT OF TRANSPORTATION 700 EAST BROADWAY PIERRE,
More informationDOING BUSINESS WITH THE. Orange County Board of County Commissioners. Orange County Procurement Division
DOING BUSINESS WITH THE Orange County Board of County Commissioners Orange County Procurement Division TABLE OF CONTENTS Preface... 1 How Can I Receive Copies Of Solicitations?... 2 Bidder s List... 2
More informationOffice of Business and Financial Services Procurement and Contracts Division Section SUBJECT: PROCUREMENT OF CONSTRUCTION SERVICES
2510.8 SUBJECT: PROCUREMENT OF CONSTRUCTION SERVICES :1 OBJECTIVE: To establish a uniform policy and procedure for the acquisition of construction services for the City of Orlando (City), including, but
More informationNOTICE OF REQUEST FOR PROPOSALS
NOTICE OF REQUEST FOR PROPOSALS Competitive sealed proposals for professional services will be received by the Contracting Agency, Guadalupe County, New Mexico, for RFP No. 2014-005. The Contracting Agency
More informationSTATE AID TO AIRPORTS PROGRAM NC DEPARTMENT OF TRANSPORTATION DIVISION OF AVIATION
APRIL 2014 STATE AID TO AIRPORTS PROGRAM State Authorization: N.C.G.S. 63 NC DEPARTMENT OF TRANSPORTATION DIVISION OF AVIATION Agency Contact Person Program and Financial Nancy C. Seigler, Grants Administrator
More informationProject Manager's Procedure Manual
Project Manager's Procedure Manual Facilities Planning & Construction Department Florida Agriculture and Mechanical University July 2012 Signature Page for Professional Service Guide Approval Director,
More informationftp://ftp.dot.state.oh.us/pub/districts/d06/download/january%202018%20programmatic/del /
12-18-17 Posting Date Information for January 2018 Programmatic Group District 6, DEL-36-14.85, PID No. 107214 District Six has posted the draft scope of services and associated supporting documents to
More informationPre-Award Audit/DBE/Title VI Breakout Session #2
Pre-Award Audit/DBE/Title VI Breakout Session #2 Wednesday, September 19, 2018 Tammy Mancinelli Moderator Assistant Division Administrator, Civil Rights Division, VDOT AGENDA TITLE VI JEOPARDY Tammy Mancinelli,
More informationSTATE OF MINNESOTA CAPITAL GRANTS MANUAL. A step-by-step guide that describes what grantees need to do to receive state capital grant payments
STATE OF MINNESOTA CAPITAL GRANTS MANUAL A step-by-step guide that describes what grantees need to do to receive state capital grant payments Revised March 2010 The State of Minnesota Capital Grants Manual
More informationCity of Batavia Downtown Improvement Grant
City of Batavia Downtown Improvement Grant INTRODUCTION The Downtown Improvement Grant Program is designed to enhance the overall economic viability and appearance of downtown Batavia by assisting in the
More informationTameika Edwards presenting Regulations Title Page Slide #2
Tameika Edwards presenting Regulations Title Page Slide #2 We re going to begin with the regulations. Governing Regulations Slide #3 Article 15 A and 5 NYCRR Parts 142-144 were signed into law to promote
More informationWelcome and Introductions
Fiscal Matters: An Overview of Annual Head Start and Early Head Start Grant Requirements U.S. Department of Health and Human Services, Welcome and Introductions Staff Grantee Representatives 1 Goals for
More informationCompleted project applications must be received no later than December 31, 2010 at 4:00 PM.
Ohio Department of Transportation Small and Disadvantaged Businesses Diesel Emissions Reduction Grant (DERG) Program For Diesel Powered Equipment Replacement, Repower, Retrofit, and Anti-Idle Projects
More informationSmall Business Enterprise Program Participation Plan
EXHIBIT H Small Business Enterprise Program Participation Plan Version 5.11.2015 www.transportation.ohio.gov ODOT is an Equal Opportunity Employer and Provider of Services TABLE OF CONTENTS I. PURPOSE...
More informationGuidance for Locally Administered Projects. Funded Through the NJDOT/MPO Program Funds Exchange. August 27, Revised September 15, 2014
1 Guidance for Locally Administered Projects Funded Through the NJDOT/MPO Program Funds Exchange August 27, 2013 Revised September 15, 2014 This document establishes guidelines for administering the program
More informationBig Sky Regional Peer Exchange on Federal-aid Highway Program Financial Management
Big Sky Regional Peer Exchange on Federal-aid Highway Program Financial Management Date: May 9-10, 2018 Location: Salt Lake City, UT (UDOT Learning Center) Overview This customized exchange will provide
More informationSAN ANTONIO WATER SYSTEM NACO PUMP STATION IMPROVEMENTS PROJECT SAWS PROJECT NO SOLICITATION NO. B DD ADDENDUM NO.
Addendum No. 1 Naco Pump Station Improvements Project SAWS Project No. 12-6003 Solicitation No. B-14-005-DD SAN ANTONIO WATER SYSTEM NACO PUMP STATION IMPROVEMENTS PROJECT SAWS PROJECT NO. 12-6003 SOLICITATION
More informationOhio Home Care Waiver Provider Application Process
Ohio Home Care Waiver Provider Application Process Provider Enrollment Website medicaid.ohio.gov Hover over the Providers Tab Hover over Enrollment and Support Click Provider Enrollment On the next page,
More informationSafety Projects and the Local Agency Program (LAP)
Safety Projects and the Local Agency Program (LAP) Wednesday, January 8, 2014 Lawrence Taylor Consultant D7 Safety/LAP Project Manager Workshop Series Wed. Oct. 30 Wed. Nov. 6 Wed. Nov. 13 Wed. Nov. 20
More informationKANSAS CITY REGIONAL TIGER PROJECT PMOC PROGESS REPORT 2014 Fiscal Quarter 1 October 1 December 31, 2013
KANSAS CITY REGIONAL TIGER PROJECT PMOC PROGESS REPORT 2014 Fiscal Quarter 1 October 1 December 31, 2013 January 16, 2014 PROJECT TYPE: Multimodal (bicycle, pedestrian, roadway, transit) LOCATION: Kansas
More informationLOCAL STORMWATER BMP IMPLEMENTATION PROGRAM PROJECT APPLICATION INSTRUCTIONS
COMMONWEALTH OF PENNSYLVANIA DEPARTMENT OF ENVIRONMENTAL PROTECTION BUREAU OF CLEAN WATER LOCAL STORMWATER BMP IMPLEMENTATION PROGRAM PROJECT APPLICATION INSTRUCTIONS The Department of Environmental Protection
More informationREQUEST FOR PROPOSAL FOR BACKUP EMERGENCY GENERATORS DESIGN TOWN OF YUCCA VALLEY
REQUEST FOR PROPOSAL FOR BACKUP EMERGENCY GENERATORS DESIGN TOWN OF YUCCA VALLEY RELEASED ON MARCH 21, 2017 PROPOSAL DUE DATE: APRIL 27, 2017 @ 3:00 PM March 21, 2017 NOTICE INVITING SEALED PROPOSALS,
More informationCounty of Hawai i Department of Research and Development Innovation Grants for Fiscal Year Frequently Asked Questions
County of Hawai i Department of Research and Development Innovation Grants for Fiscal Year 2018-2019 Frequently Asked Questions 1. What is the Department of Research and Development Innovation Grants Program?
More informationREQUEST FOR PROPOSALS (RFP) For Electrical Engineering Design Services City Hall Switchgear Replacement October 28, 2016
MAYOR GARY O. PHILLIPS VICE MAYOR KATE COLIN COUNCILMEMBER MARIBETH BUSHEY COUNCILMEMBER JOHN GAMBLIN COUNCILMEMBER ANDREW CUYUGAN MCCULLOUGH PUBLIC WORKS DEPARTMENT: (415)485-3355 FAX: (415)485-3334 Bill
More informationU R B A N INIT I A T I V E S (UI) Commitment and Disbursement Procedures for Local Program Administrators Updated March 2013
U R B A N INIT I A T I V E S (UI) Commitment and Disbursement Procedures for Local Program Administrators Updated The procedures set forth in this document should be followed by organizations administering
More informationCity of Provo, Utah Parks and Recreation Department. Request for Proposal (RFP) Architectural Services for a New Community Recreation Center
City of Provo, Utah Parks and Recreation Department Request for Proposal (RFP) Architectural Services for a New Community Recreation Center RFP No. 14065 I. GENERAL OVERVIEW AND DESCRIPTION OF PROJECT
More informationRequest for Proposals for Angeltrax Mobile Video Surveillance Systems
Request for Proposals for Angeltrax Mobile Video Surveillance Systems The Tahoe Transportation District (TTD) is seeking proposals from qualified vendors for the sale and installation of Angeltrax Mobile
More informationCITY OF BELL REQUEST FOR PROPOSALS FOR ARCHITECTURAL SERVICES FOR TREDER PARK RESTROOM AND STORAGE FACILITY
CITY OF BELL 6330 PINE AVENUE BELL, CA 90201 PH: (323) 588-6211 fx: (323) 771-9473 I. INTRODUCTION CITY OF BELL REQUEST FOR PROPOSALS FOR ARCHITECTURAL SERVICES FOR TREDER PARK RESTROOM AND STORAGE FACILITY
More informationREQUEST FOR PROPOSALS
REQUEST FOR PROPOSALS Government of Newfoundland and Labrador REQUEST FOR PROPOSALS Agency of Record for Marketing Strategy and Implementation Plan and Creative Development Services February 18, 2015 1.0
More informationPRE-PROPOSAL MEETING TUESDAY, JULY 17, 2018
The University of Texas Medical Branch RFP 18-053 CRYO EM RENOVATION PRE-PROPOSAL MEETING TUESDAY, JULY 17, 2018 Working Together to Work Wonders 1 PRE-PROPOSAL MEETING AND TOUR 10:00 am Pre-Submittal
More informationHighway Safety Improvement Program Procedures Manual
Highway Safety Improvement Program Procedures Manual February 2017 Division of Planning Office of Systems Planning and Program Management Contents Section Page Preface... iii HSIP Program Procedure...
More informationBloomfield College Grants Financial Management Policy
Bloomfield College Grants Financial Management Policy April 2014 This document provides for policies and procedures for the fiscal grant management process for Bloomfield College. Grants include awards
More informationBureau of Waste Management
Standard Operating Procedures for Processing Municipal and Residual Waste Major Permit Modifications, not Including Increases in Capacity Applications for Landfills, Resource Recovery Facilities, Transfer
More informationSprinkler Cost Assistance Program Application
City of Mesa Sprinkler Cost Assistance Program Application In Fiscal Year 2010/2011, Mesa s City Council adopted a set of strategic initiatives aimed at guiding the efforts of City Staff. The Economic
More informationGrants Financial Procedures (Post-Award) v. 2.0
Grants Financial Procedures (Post-Award) v. 2.0 1 Grants Financial Procedures (Post Award) Version Number: 2.0 Procedures Identifier: Superseded Procedure(s): BU-PR0001 N/A Date Approved: 9/1/2013 Effective
More informationMembrane Pre-Selection Request For Proposal
Membrane Pre-Selection Request For Proposal City of San Luis Obispo Water Resource Recovery Facility Project Mandatory Pre-proposal Conference - July 7, 2017 Water Resource Recovery Facility Project Community
More informationSpecial Approval per TAC Part A - LG Qualifications Statement (Local Government Agency management of project development process elements)
Special Approval per TAC 15.52 Part A - LG Qualifications Statement (Local Government Agency management of project development process elements) Project CSJ: Local government (LG) agencies may manage elements
More informationREQUEST FOR QUALIFICATIONS FOR PROFESSIONAL SERVICES
Boone County, Kentucky INVITATION FOR BID #060817 REQUEST FOR QUALIFICATIONS FOR PROFESSIONAL SERVICES ACCEPTANCE DATE: Prior to 2:00 p.m., June 8, 2017 Local time ACCEPTANCE PLACE Boone County Fiscal
More informationBidders Conference. One-Stop Career Center Operator March 18, An Equal Opportunity Employer/Program
Bidders Conference One-Stop Career Center Operator March 18, 2015 An Equal Opportunity Employer/Program Welcome Introduction Please ensure that you have signed the sign-in sheet All materials on WC website:
More informationThe American Recovery and Reinvestment Act of Enacted February 17, 2009
The American Recovery and Reinvestment Act of 2009 http://www.dot.gov/recovery/ Enacted February 17, 2009 A Rose by any other name The American Recovery and Reinvestment Act of 2009 Was commonly referred
More informationBALTIMORE CITY PUBLIC SCHOOLS MINORITY AND WOMEN BUSINESS ENTERPRISE PROGRAM AND PROCEDURES MANUAL FOR STATE FUNDED PROJECTS
BALTIMORE CITY PUBLIC SCHOOLS MINORITY AND WOMEN BUSINESS ENTERPRISE PROGRAM AND PROCEDURES MANUAL FOR STATE FUNDED PROJECTS January 2014 MINORITY BUSINESS ENTERPRISE PROCEDURES FOR STATE FUNDED PUBLIC
More informationSetting Up an Award and Creating a Grant
The award is the mechanism that specifies the terms and conditions based on the sponsor agreement. There are four steps to setting up an award: 1. Create Award 2. Create Grant 3. Create Billing Schedule
More informationCounty Transportation Infrastructure Fund Grant Program Frequently Asked Questions
County Transportation Infrastructure Fund Grant Program Frequently Asked Questions Updated Feb. 10, 2015 FREQUENTLY ASKED QUESTIONS County Transportation Infrastructure Fund Grant Program A. Deadlines
More informationTucson Modern Streetcar
Tucson Modern Streetcar Framework for Project Management Oversight Mayor & Council Presentation April 20, 2010 Project Goals An element of region s seamless transit system Create permanent & short term
More informationBOCC POLICY: SECTION NUMBER COUNTY COASTAL CANAL GRANT PROGRAM EFFECTIVE DATE: February 15, 2017 SUPERSEDES:
BOARD OF COUNTY COMMISSIONERS HILLSBOROUGH COUNTY TAMPA, FLORIDA 33601 BOCC POLICY: SECTION NUMBER 01.31.01.00 SUBJECT: COUNTY COASTAL CANAL GRANT PROGRAM EFFECTIVE DATE: February 15, 2017 SUPERSEDES:
More informationWorkshop Synopses. Classes include:
Workshop Synopses Advanced Track This group of classes is designed for experienced primary and back-up agency designated procurement officers only. Offered on the first day of conference, this track is
More informationFOR REINVESTMENT ACT. NILAH DEVANEY NWRO, AWARDING OFFICIAL
1 PL 93-638 AWARD PROCESS FOR AMERICAN RECOVERY AND REINVESTMENT ACT (ARRA) NILAH DEVANEY NWRO, AWARDING OFFICIAL 503-872-2867 E-Mail: nilah.devaney@bia.gov 2 ARRA OVERVIEW ON DEADLINES FEBRUARY 17, 2010,
More informationTERREBONNE PARISH REQUEST FOR QUALIFICATIONS FOR ENGINEERING SERVICES. Generator Sizing and Installation
TERREBONNE PARISH REQUEST FOR QUALIFICATIONS FOR ENGINEERING SERVICES Generator Sizing and Installation Proposal Due Date: June 26, 2017 Proposal Due Time: 2:00 P.M. Released May 23, 2017 Table of Contents
More informationObjectives for Financial Control over Grant Programs
Objectives for Financial Control over Grant Programs I. Cash management of grant funds is monitored for appropriate timing of receipts and disbursements of grant funds. (Cash Management) II. Procedures
More informationStandard Procedure No (SP) Effective: April 11, 2001 Responsible Office: Division of
Approved: //s// Walid E. Gemayel Walid E. Gemayel, Deputy Director Construction Management Standard Procedure No. 510-003(SP) Effective: April 11, 2001 Responsible Office: Division of Construction Management
More informationFunding Opportunities
2012-2013 Funding Opportunities Florida Farmworker Jobs and Education Program Grant Due April 16, 2012 http://www.fldoe.org/workforce/dwdgrants/ Division of Career and Adult Education 1 Funding Conference
More informationFederal Highway Administration (FHWA)
CHAPTER ONE 1-1.0 CHAPTER ONE OVERVIEW It is critically important that all communications include the Local Public Agency s designated Employee in Responsible Charge (ERC). It is also critical that the
More informationREQUEST FOR PROPOSALS PROFESSIONAL SERVICES FOR RAISED MEDIAN AT EL DORADO STREET. Issued by:
REQUEST FOR PROPOSALS PROFESSIONAL SERVICES FOR RAISED MEDIAN AT EL DORADO STREET (BETWEEN ESSEX STREET AND THE CALAVERAS RIVER BRIDGE) Federal Project No. HRRRL-5008(163) Issued by: City of Stockton Public
More informationCUYAHOGA COUNTY DEPARTMENT OF PUBLIC WORKS POLICY ON CONSULTANT SELECTION. October 2011
CUYAHOGA COUNTY DEPARTMENT OF PUBLIC WORKS POLICY ON CONSULTANT SELECTION October 2011 CONTENTS SECTION PAGE INTRODUCTION...1 OBJECTIVE...1 A. Determination of Need to Use Consultant Services...2 B. Consultant
More information2011 Application. Infrastructure Investment Payments. Background
Background In the aftermath of Hurricanes Katrina and Rita, the State of Louisiana Department of Health and Hospitals (DHH) was awarded a $100 million Primary Care Access and Stabilization Grant (PCASG)
More informationRequest for Qualifications No. RFQ Professional Services Consultants. for. High School Professional Development. for. Seattle Public Schools
Seattle Public Schools Contracting Services 2445 Third Avenue South Seattle, WA 98134 Telephone: (206) 252-0566 Fax: (206) 743-3018 contractingservices@seattleschools.org Request for Qualifications No.
More informationInformational Workshop How to do Business with the City of Irvine March 31, 2011
Informational Workshop How to do Business with the City of Irvine March 31, 2011 Presented by Brian D. Brown, CPSM Buyer City of Irvine About the City of Irvine The City of Irvine has an annual budget
More informationREQUEST FOR PROPOSALS PROFESSIONAL SERVICES FOR THE BRIDGE REHABILITATION PROJECT. Issued by:
REQUEST FOR PROPOSALS PROFESSIONAL SERVICES FOR THE BRIDGE REHABILITATION PROJECT FEDERAL PROJECT NO. BPMP-5008 (157) CITY PROJECT NO. PW1603 Issued by: City of Stockton Public Works Department 22 E. Weber
More informationRequest for Proposals for Construction Manager at Risk Watertown Community Center
Request for Proposals for Construction Manager at Risk Watertown Community Center October 29, 2014 City of Watertown, South Dakota Publish: Wednesday, October 29, 2014 Section 1 Advertisement for Proposals
More information