1 Public-Private Partnership in Infrastructure Development Case Studies from Asia and Europe This book, produced by the EAP³N Project with contributions from its members, all of whom are active academics and practitioners in the field of infrastructure PPP, is intended to be as an aid to greater mutual understanding in this area. It is structured into two parts and consists of one Introduction chapter and five case studies, each focusing on a specific project and each highlighting key issues and problem areas.
2 Imprint Scientific series of Chair Construction Economics Editor Bauhaus-Universität Weimar Faculty of Civil Engineering Chair Construction Economics Univ.-Prof. Dr.-Ing. Dipl.-Wirtsch.-Ing. Hans Wilhelm Alfen Marienstraße 7a Weimar, Germany Phone: +49 (0) Availability Publisher of Bauhaus-Universität Weimar Fax: +49 (0) Authors Hans Wilhelm Alfen, Satyanarayana N. Kalidindi, Stephen Ogunlana, ShouQing Wang, Martinus P. Abednego, Andrea Frank-Jungbecker, Yu-Chien Amber Jan, Yongjian Ke, YuWen Liu, L. Boeing Singh, GuoFu Zhao Print Docupoint Magdeburg GmbH Cover Christian Mohr ISBN This publication is also available as digital version under URL
3 Table of Contents 1 AN INTRODUCTION TO PPP CONCEPT What is PPP? Definition and Delimitation of PPP Advantages of PPP: Efficiency Gains Elements Determining the PPP Business Model Basic Model: Urban Development versus Public Service Provision Forms of Privatisation and Privatisation Development Path Kind of Partnership Mode of Sector Financing PPP Contract Models in International Practice Phases of a PPP Project Enabling Framework Legal Framework Regulatory Framework Administrative framework Contractual Framework Project Agreement Project Shareholders and their Perspectives PPP Project Stakeholders Perspective PPP Project Financing Funding Sources and Financial Instruments Financing Strategy Major Issues Financial Package and Risk Profile Risk Management Risk Identification Risk Assessment Risk Allocation Risk Mitigation CASE STUDY I - DIFFERENT RISK PERSPECTIVES IN THE 2ND STAGE CIPULARANG TOLLWAY PROJECT Infrastructure Development in Indonesia Tollroad Development in Indonesia... 43
4 2.3 The 2nd Stage Cipularang Tollway project Project Background Problems Encountered in Project Issues on Differences in Perspectives between the Government and Private Sector Project Success Government s Perspective on Project Success Private Sector s Perspective on Project Success Project Efficiency Government s Perspective on Project Efficiency Private Sector s Perspective on Project Efficiency Project Risks Conclusion CASE STUDY II - GOVERNANCE ISSUES IN THE YEN LENH BRIDGE BOT PROJECT Infrastructure Development in Vietnam BOT Projects in Vietnam Yen Lenh Bridge BOT Project Project Background BOT Project Risk Identification Land Acquisition Delay Delay in Approval from Government Agencies Risk of Transportation Network in Region Influencing the BOT Project Cost Overrun Unrealistic Forecast on Future Economic Development & Demand of the Society Increasing Inflation Rate Incorrect Analysis of Ownership Duration Interest Rate Fluctuation General Corruption and Untrustworthiness of Public Official Actual Traffic Revenues Lower than Estimated Risk Perceptions in the Project Governance Issues in Project Fairness Transparency Accountability Sustainability Effectiveness and Efficiency... 86
5 3.5 Conclusion CASE STUDY III - WARNOWQUERUNG ROSTOCK EXPERIENCES FROM THE FIRST GERMAN PPP ROAD PROJECT UNDER THE F-MODEL Project Background Project Objectives Project Scope and Site Legal Framework Federal Private Road Financing Act of 1994 (FStrPrivFinG) and F- Model Contractual and Financial Framework Stakeholders and Project Structure Sources of Finance Risk Allocation Traffic Forecast Current Developments Lessons Learned CASE STUDY IV - LAIBIN B POWER PROJECT THE FIRST STATE- APPROVED BOT PROJECT IN CHINA Project Background Project Description Project Partners Central Government Provincial Government Sponsor Project Company Lender Customer Supplier Contractor Operator Development Process Initial Planning Prequalification Tendering Tender Evaluation Evaluation Criteria Critical Success Factors
6 5.5 Legislation Driving the Project Basic Deal Structure Concession Agreement (CA) Power Purchase Agreement (PPA) Financial Analysis Government Initiatives Exclusive Concession Granted Power Purchase Guarantee Fuel Supply Guarantee Force Majeure Guarantee Foreign Exchange Guarantee Compensation under Government s Default and Political Risks Tax Incentives Guarantee of Lenders Right Land and Utilities and Other Support Measures Risk Management Tariff Adjustment Chinese Parties Reliability & Creditworthiness Dispatch Constraint Change in Law Exchange Rate & Convertibility Force Majeure Financial Closing Delay in Approval Expropriation Corruption Risk Allocation Summary CASE STUDY VI - THE NATIONAL STADIUM BOT PROJECT FOR BEIJING 2008 OLYMPIC GAMES Introduction Project Objectives State Level Project Level Development Process Project Partners The Public Partner
7 6.4.2 The Private Partner China International Trust and Investment Corporation Beijing Urban Construction Group Corporation Golden State Holding Group Cooperation Project Management Advisors Project Structure Project Scope and Location Project Scope Location Government s Supports and Incentives Basic Deal Structure The BMG s Obligations The Project Company s Obligations The Project Company s Revenues The Competitive Stadiums Sources of Finance The Shareholders of the Project The Financial Arrangements of the Project Insights into Major Issues The Disputes in the Project Disputes among the Project Company s Partners Disputes between the Project Company and The BMG Dispute between the Project Company and the Design Consortium The Impacts of Canceling the Retractable Roof Pros of Canceling the Retractable Roof Cons of Canceling the Retractable Roof Risks in the Project Summary
PPP Highways Experiences: Chile and Mexico. John Hodges INF Vice Presidency Belgrade Workshop June 6, 2006
PPP Highways Experiences: Chile and Mexico John Hodges INF Vice Presidency Belgrade Workshop June 6, 2006 International PPP Experiences First Programs: France, Spain Pioneering Developing Countries: Argentina,
More informationExperience on Public Private Partnership in Punjab
Experience on Public Private Partnership in Punjab Experience Sharing Workshop for State Road Agencies Nov 1-2 2006, New Delhi Punjab Roads & Bridges Development Board Structure of Presentation Basic Information
More informationPPP Mechanisms for Sustainable Ci5es Hubert Jenny
The views expressed in this presentation are the views of the author/s and do not necessarily reflect the views or policies of the Asian Development Bank, or its Board of Governors, or the governments
More informationProfessional financing advice for meso-scale renewable energy projects in sub-saharan Africa.
Professional financing advice for meso-scale renewable energy projects in sub-saharan Africa. Salzburg 29 November 2017 What is the RECP Finance Catalyst? The Finance Catalyst team links renewable energy
More informationAttracting Private Sector Investment in Infrastructure Experiences from India
UNESCAP High-level Expert Group Meeting on Infrastructure Public-Private Partnerships for Sustainable Development Attracting Private Sector Investment in Infrastructure Experiences from India Cherian Thomas
More informationSHI Hua EDUCATION. Bachelor Degree of Law, Law School of Shanxi University
SHI Hua Professor of Law Doctoral Supervisor Tongji University School of Law 1239 Siping Road 200092 Shanghai, CHINA Email: tjshihua@yahoo.com.cn Tel: 021-65981765 Fax: 021-65982644 EDUCATION Doctor Degree,
More informationApproved Project Sponsor s Participating TO Application Process Clean-Up. Proposal and Tariff
Approved Project Sponsor s Participating TO Application Process Clean-Up Proposal and Tariff September 30, 2015 M&ID Page 1 Table of Contents 1 Executive Summary... 3 2 Stakeholder Process Next Steps...
More informationDraft PPP Regulations
Legal Update Infrastructure PPP/PFI Vietnam 3 September 2010 Draft PPP Regulations Vietnam has an urgent need to upgrade and develop its infrastructure. However, having attained middle income status, the
More informationFEED-IN TARIFF POLICY APPLICATION AND IMPLEMENTATION GUIDELINES
Ministry of Energy FEED-IN TARIFF POLICY APPLICATION AND IMPLEMENTATION GUIDELINES 1 December, 2012 TABLE OF CONTENTS 1 INTRODUCTION 3 2 OVERVIEW OF THE FiT PROCEDURE 3 3 EXPRESSION OF INTEREST APPLICATION
More informationFinancing Mechanisms and Reforms to Leverage Local Resources
Financing Mechanisms and Reforms to Leverage Local Resources Regional Workshop on Water Utilities Bangkok, July 2006 Meera Mehta, Water and Sanitation Program Africa Outline 1. Global trends and the nature
More informationFinal. Technical Assistance of Solar PV Project Pipeline in India
German Financial Cooperation with India Final INVITATION FOR EXPRESSION OF INTEREST Consulting Services for Technical Assistance of Solar PV Project Pipeline in India KfW on behalf, of Indian Renewable
More informationPakistan s Public Private Partnership (PPP) Program
Capacity Building and Training under Infrastructure Project Development Facility (IPDF) 23 rd September 2014 Pakistan s Public Private Partnership (PPP) Program Presentation Outline 1. Facilitation 2.
More informationWhat are the steps? Incentives for energy efficient buildings
Buildings energy efficiency sessions done in partnership with: Energy Efficiency Training Week What are the steps? Incentives for energy efficient buildings Buildings Session 7 Energy Efficiency Training
More informationGlobal Infrastructure Hub Update
Global Infrastructure Hub Update IWG Update Introduction Dear IWG members, Welcome to the first edition in a series of updates that the GI Hub will provide in advance of each G20 Infrastructure Working
More informationInvestment Opportunities in Thailand. Mrs. Hirunya Suchinai Secretary General Thailand Board of Investment
Investment Opportunities in Thailand Mrs. Hirunya Suchinai Secretary General Thailand Board of Investment 12 September 2017 Thailand Consistently Ranks High in International Surveys Thailand was ranked
More informationImplementation Process : Solicited Project
Implementation Process : Solicited Project Selection of PPI Project Request for Proposals(RFP) Private Sector Submission of Project Proposals Evaluation/Selection of Preferred Bidder Preferred Bidder Negotiation
More informationAPPENDIX D CHECKLIST FOR PROPOSALS
APPENDIX D CHECKLIST FOR PROPOSALS Is proposal content complete, clear, and concise? Proposals should include a comprehensive scope of work, and have enough detail to permit the responsible public entity
More informationCity of Munich and UnternehmerTUM plan the city of the future: New innovation and start-up center in the creative quarter
Press release 03.02.2016 City of Munich and UnternehmerTUM plan the city of the future: New innovation and start-up center in the creative quarter The City of Munich and UnternehmerTUM GmbH, the company
More informationTransmission Unbundling
Transmission Unbundling Dr. Marie-Therese Richter, LL.M. Energy lawyer, 1 Outline Legal basis and purpose of unbundling Status quo in the Contracting Parties Unbundling options - Overview Practical issues
More information2015 East Asia and Pacific (EAP) PPI 1 Update
2015 East Asia and Pacific (EAP) PPI 1 Update Total investment 2 in infrastructure 3 with private participation in emerging economies in East Asia and the Pacific fell by 16 percent from US$15.9 billion
More informationInvitation for Expression of Interest. Programme Renewable Energy for Productive Use (PUREP), Phase I
German Financial Cooperation with Bangladesh Consulting Services for the Energy Sector Bangladesh Invitation for Expression of Interest For the Programme Renewable Energy for Productive Use (PUREP), Phase
More informationDraft RATIONALE AND MODALITIES FOR THE AWARD OF COMMUNICATION INFRASTRUCRE LICENCE (COMMUNICATION TOWER)
Draft RATIONALE AND MODALITIES FOR THE AWARD OF COMMUNICATION INFRASTRUCRE LICENCE (COMMUNICATION TOWER) 1.0 Preamble In furtherance of the National Telecommunications Policy 2005 (NTP 05), the Electronic
More informationShould Electricity Sectors in Developing Countries be Unbundled?
How to Improve the Performance of Infrastructure Service Providers Should Electricity Sectors in Developing Countries be Unbundled? John Besant-Jones June 27, 2007 Distinction between Integration and Unbundling
More informationBuilding Infrastructure through PPPs with the AfDB
Building Infrastructure through PPPs with the AfDB 1 Ẉho are we? AfDB: Africa s Premier Development Financial Institution AAA by all rating agencies African Development Bank (ADB) African Development Fund
More informationCall for UAB grant applications for the capture and retention of research talent at the Universitat Autònoma de Barcelona
Call for UAB grant applications for the capture and retention of research talent at the Universitat Autònoma de Barcelona Agreement of the Research Committee made on 20 June 2018 Preamble The Universitat
More informationACI AIRPORT SERVICE QUALITY (ASQ) SURVEY SERVICES
DRAFTED BY ACI WORLD SECRETARIAT Table of Contents Table of Contents... 2 Executive Summary... 3 1. Introduction... 4 1.1. Overview... 4 1.2. Background... 5 1.3. Objective... 5 1.4. Non-binding Nature...
More informationPUBLIC PRIVATE PARTENERSHIP (PPP) OF WATER SUPPLY SYSTEM IN PONDOK GEDE AND JATI ASIH, BEKASI CITY
PUBLIC PRIVATE PARTENERSHIP (PPP) OF WATER SUPPLY SYSTEM IN PONDOK GEDE AND JATI ASIH, BEKASI CITY Project Overview Background Need Adequate Infrastructure (incl. Water Supply Service Coverage (2014) :
More informationDFG. Guidelines. Infrastructure for Electronic Publications and Digital Scholarly Communication. DFG form /15 page 1 of 12
form 12.11 09/15 page 1 of 12 Guidelines Infrastructure for Electronic Publications and Digital Scholarly Communication form 12.11 09/15 page 2 of 12 I Programme Information 1 Objective As part of its
More information2017 CEF Transport Blending Call. FREQUENTLY ASKED QUESTIONS Blending features Last update 12 July 2017 (new questions in blue)
2017 CEF Transport Blending Call FREQUENTLY ASKED QUESTIONS Blending features Last update 12 July 2017 (new questions in blue) 1. What is an Affordability analysis? In the context of a PPP, affordability
More informationImplementing Subsidy Reforms: lessons from international experience Maria Vagliasindi, Program Leader, GCC, World Bank SUBSIDY REFORM 11 1
Implementing Subsidy Reforms: lessons from international experience Maria Vagliasindi, Program Leader, GCC, World Bank SUBSIDY REFORM 11 1 Energy subsidy cost are extremely high Energy subsidies in selected
More informationOn-grid Renewable Energy Planning
On-grid Renewable Energy Planning Promotion of an Auction Scheme for Renewable Energy Project (PROLER) Adam Ayache Project officer Agência Francesa de Desenvolvimento French Development Agency PROLER in
More information北京长风信息技术产业联盟. Opportunities of Smart City in China. Beijing Changfeng Information Technology Industry Alliance. Presented by Teng Wang March 2018
北京长风信息技术产业联盟 Beijing Changfeng Information Technology Industry Alliance Opportunities of Smart City in China Presented by Teng Wang March 2018 Introduction of Changfeng Alliance Beijing Changfeng Alliance
More informationand Commission on the amended Energy Efficiency Directive and Renewable Energies Directives. Page 1
Information on financing of projects under the framework of the European Climate Initiative of the German Federal Ministry for the Environment, Nature Conservation, Building and Nuclear Safety (BMUB) Last
More informationGlobal Location Trends: Asia-Pacific Facts & Figures
IBM Global Business Services November 2012 Global Location Trends: Asia-Pacific Facts & Figures Table of Contents (1/4) Chapter 1: Leading sectors and activities for foreign investment 1.1 Top investing
More informationSOLAR PV TRADE MISSION INDONESIA
A 5-day turnkey solution to explore the opportunities for your solar business in Indonesia DIAMOND SPONSOR STRATEGIC PARTNER KEY CHARACTERISTICS Get all the information you need to develop your solar business
More informationBOLD IDEAS AND FRESH THINKING IN ASIA S LEGAL INDUSTRY. TIME OF RECKONING Singapore s legal market at the crossroads
TIME OF RECKONING Singapore s legal market at the crossroads GROWING ARSENAL Litigators have an array of tech tools to choose from GETTING ON TRACK A closer look at the ASEAN s railway plans BOLD IDEAS
More informationInternational Cooperation in Horizon 2020 Transport R&I area
No guarantee for accuracy or completeness of the information Your network of Transport National Contact Points International Cooperation in Horizon 2020 Transport R&I area Co-funded by the Horizon 2020
More informationMaritime Opportunities: Turkey 2014
Maritime Opportunities: Turkey 2014 James V. Koch Board of Visitors Professor of Economics Old Dominion University Sponsored by the Virginia Economic Development Partnership s (VEDP) Going Global Defense
More informationInnovative Infrastructure Financing (Click on section to go to article) 6.1 Private Toll Roads 6.2 Public-Private Partnerships 6.
Innovative Infrastructure Financing (Click on section to go to article) 6.1 Private Toll Roads 6.2 Public-Private Partnerships 6.3 Marketization STRATEGY: INNOVATIVE INFRASTRUCTURE FINANCING NO. 6.1.1
More informationTHE CPA AUSTRALIA ASIA-PACIFIC SMALL BUSINESS SURVEY 2016
THE CPA AUSTRALIA ASIA-PACIFIC SMALL BUSINESS SURVEY GENERAL REPORT FOR AUSTRALIA, CHINA, HONG KONG, INDONESIA, MALAYSIA, NEW ZEALAND, SINGAPORE AND VIETNAM Legal notice CPA Australia Ltd ( CPA Australia
More informationTHE CITY OF SEATTLE CITY LIGHT DEPARTMENT 2012 REQUEST FOR PROPOSALS. Long-Term Renewable Resources And/or Renewable Energy Certificates
THE CITY OF SEATTLE CITY LIGHT DEPARTMENT 2012 REQUEST FOR PROPOSALS Long-Term Renewable Resources And/or Renewable Energy Certificates Issued September 12, 2012 1 - Introduction The City of Seattle, City
More informationUpcoming Energy & Infrastructure Projects in India and South East Asia
Upcoming Energy & Infrastructure Projects in India and South East Asia (Country Wise Track of Forthcoming Oil & Gas Projects, Thermal Power Plant Projects, Power Transmission Projects, Wind Power Projects,
More informationI 2 Program Frequently Asked Questions
I 2 Program Frequently Asked Questions What is the Genome BC Industry Innovation (I 2 ) Program? The I 2 Program offers repayable growth capital to businesses (with less than 500 employees), commercializing
More informationUniversal Access to Information & Communication Technology in the Asia Pacific Region
Universal Access to Information & Communication Technology in the Asia Pacific Region The Asia and Pacific Regional Preparatory Meeting for the World Telecommunication Development Conference Bali, Indonesia,
More information9. Positioning Ports for Grant Funding and Government Loan Programs
9. Positioning Ports for Grant Funding and Government Loan Programs 9.1. Grant Funding Overview Grant funding continues to be a key factor for ports in meeting capital investment requirements. Grants can
More informationRequest for proposal for providing services to the Oberlin Group for the launch of a new Open Access publishing venture for the liberal arts
Request for proposal for providing services to the Oberlin Group for the launch of a new Open Access publishing venture for the liberal arts 4 th November 2014 RFP Responses Close: 1 st December 2014 Responses
More informationAPPENDIX B BUSINESS POLICIES
APPENDIX B BUSINESS POLICIES 2018-2019 TABLE OF CONTENTS DEFAULT POLICY... 1-1 ACCOUNTING AND REPORTING REQUIREMENTS... 2-1 PRODUCER S FEES & CORPORATE OVERHEAD (PFCO) POLICY... 3-1 COMPLETION PROTECTION
More informationCall for UAB grant applications for the capture and retention of research talent at the Universitat Autònoma de Barcelona
Call for UAB grant applications for the capture and retention of research talent at the Universitat Autònoma de Barcelona Agreement of the Research Committee made on 28 June 2017 Preamble The Universitat
More informationProcurement Process of PPP Projects in Korea
Procurement Process of PPP Projects in Korea December, 2007 Public and Private Infrastructure Investment Management Center (PIMAC) Korea Development Institute 1. PPP Project Types in Korea 2. Procurement
More informationU.S.-Funded Assistance Programs in China
Order Code RS22663 Updated January 28, 2008 U.S.-Funded Assistance Programs in China Summary Thomas Lum Specialist in Asian Affairs Foreign Affairs, Defense, and Trade Division United States foreign assistance
More informationisawt (International Summer: America and the World Today) Summer 2018
isawt (International Summer: America and the World Today) Summer 2018 Program Description Program Dates Arrival: Friday, August 3, 2018 Airport: Chicago O Hare International Airport (ORD) Departure: Thursday,
More informationPROJECT SELECTION Educational Series
PROJECT SELECTION 2017 Educational Series PROJECT SELECTION THE PROJECT SELECTION PROCESS Understanding how the state s roads, bridges and other transportation infrastructure are selected for funding helps
More informationTRANSPORTATION RESEARCH BOARD. 85th ANNUAL MEETING
TRANSPORTATION RESEARCH BOARD 85th ANNUAL MEETING Panel on Public Private Initiatives: New Concepts in Transportation Project Delivery Recent Trends and Innovations January 23, 2006 Washington, DC GEOFFREY
More informationFossil Fuel Subsidy Reform
2015/FMP/WKSP1/016 Session: 5 Fossil Fuel Subsidy Reform Submitted by: United States Workshop on Fiscal Management Through Transparency and Reforms Bagac, Philippines 9-10 June 2015 Fossil Fuel Subsidy
More informationMiami-Dade County Expressway Authority. Policy For Receipt, Solicitation And Evaluation Of Public. Private Partnership Proposals
Miami-Dade County Expressway Authority Policy For Receipt, Solicitation And Evaluation Of Public Private Partnership Proposals SECTION 1. Background Miami-Dade County Expressway Authority ( MDX ) finds
More informationDOCUMENTS GPOBA GRANT NUMBER TF Global Partnership on Output-based Aid. Grant Agreement
GPOBA GRANT NUMBER TF092629 DOCUMENTS Global Partnership on Output-based Aid Grant Agreement (Extending Telecommunications in Rural Indonesia Project) between REPUBLIC OF INDONESIA and INTERNATIONAL BANK
More informationReflections on Pre-commercial / Innovation Procurement
Reflections on Pre-commercial / Innovation Procurement Roman P Willweber, LL.M. 2 March 2017 Routes to innovation Innovation Rethink our means of public procurement Provide grants and funding Picture:
More informationASSESSING CONSTRUCTION THE ROLE OF INTERNAL AUDIT CONSULTANT ROBERT S. BRIGHT PRESIDENT TALSON SOLUTIONS LLC
1 ASSESSING CONSTRUCTION AUDIT RISK: THE ROLE OF INTERNAL AUDIT AND THE EXTERNAL CONSULTANT ROBERT S. BRIGHT PRESIDENT TALSON SOLUTIONS LLC AHIA 31 st Annual Conference August 26-29, 2012 Philadelphia
More informationDevolution Trust Fund Zambia
Devolution Trust Fund Zambia Implementation of Pro-poor policy for WSS in Zambia UN Independent Expert s Consultation on Good Practices with State Actors: 19-20 Jan 2011 Geneva Sam Gonga Manager DTF/ZAMBIA
More informationCase Study 24X7 WATER SUPPLY IN 3 CITIES OF KARNATAKA. Water Supply
Case Study 24X7 WATER SUPPLY IN 3 CITIES OF KARNATAKA Water Supply 1 CASE OVERVIEW Country: India Centre/State/ULB: 29 select wards in three pilot cities of Gulbarga, Belgaum and Hubli-Dharwad, Karnataka
More informationCITY OF LANCASTER REVITALIZATION AND IMPROVEMENT ZONE AUTHORITY
CITY OF LANCASTER REVITALIZATION AND IMPROVEMENT ZONE AUTHORITY Guidelines for Obtaining Financing for Projects in the City of Lancaster s City Revitalization and Improvement Zone Purposes of These Guidelines
More informationAppendix A: World Bank Group Response to Market and Government Failures
Appendix A: World Bank Group Response to Market and Government Failures When market failures exist, markets are not likely to provide innovation and entrepreneurship at an optimal level because the social
More informationREAs/REFs in Rural Electrification A Review of three EU Rural Electrification Reports
REAs/REFs in Rural Electrification A Review of three EU Rural Electrification Reports African Electrification Initiative Practitioner Workshop Dakar, 14-16 November 2011 Ralph Karhammar rkarhammar@gmail.com
More informationINNOTOUR RESEARCH IN GERMANY
INNOTOUR RESEARCH IN GERMANY Dr. Eckart Bierdümpel, International Business Development, Fraunhofer HQ 31.5.2017, Birlinghoven The Fraunhofer-Gesellschaft at a Glance The Fraunhofer-Gesellschaft undertakes
More informationPRIVATE CONCESSIONS FOR SMALL TOWN WATER SUPPLY. Early Experiences from Paraguay. May, 2001
PRIVATE CONCESSIONS FOR SMALL TOWN WATER SUPPLY Alexander E. Bakalian Franz R. Drees May, 2001 Population : 5.5 million (2000) Area : 407,000 km 2 (40% in Eastern Region where 98% of the population lives)
More informationThailand as a Gateway to ASEAN
Thailand as a Gateway to ASEAN Dr. Ratchanee Wattanawisitporn Consul (Investment) / Director Thailand Board of Investment September 12, 2017, Graz 1 Thailand at a Glance 2 Thailand s Economic Overview
More informationVietnam BOT power projects: MOIT imposes tougher statutory remedies for delays
Legal Update April 2017 Vietnam BOT power projects: MOIT imposes tougher statutory remedies for delays The Ministry of Industry and Trade (MOIT) recently issued Circular No. 43/2016/TT-BCT (Circular 43)
More informationInnovative Public Procurement of Intelligent Transport Solutions City of Copenhagen
Innovative Public Procurement of Intelligent Transport Solutions City of Copenhagen About this Best Practice Case In recent years the City of Copenhagen set up numerous initiatives to achieve their goal
More informationRequest for Proposals:
Request for Proposals: TRANSACTION ADVISORY & OTHER PROFESSIONAL SERVICES TO BE RENDERED ON STUDENT ACCOMMODATION AND OTHER EDUCATIONAL INFRASTRUCTURE PROJECTS AT DIFFERENT CAMPUSES OF THE DURBAN UNIVERSITY
More informationAdvancing Innovation in ECA September 17-20, Yerevan, Armenia Innovation and Absorption in ECA - The Role of Government
Advancing Innovation in ECA September 17-20, Yerevan, Armenia Innovation and Absorption in ECA - The Role of Government September 17, 2007 Mr. Itzhak Goldberg Advisor, Policy and Strategy World Bank The
More informationPROMOTING REGIONAL ELECTRICITY TRADE IN CENTRAL ASIA. Paul Vallely Program Leader Central Asia Regional Office 6 September 2017
PROMOTING REGIONAL ELECTRICITY TRADE IN CENTRAL ASIA Paul Vallely Program Leader Central Asia Regional Office 6 September 2017 Organization of Presentation A. Regional Power Trade Section 1 Benefits of
More informationSuccessful Physician-Hospital Integration A Case Study. Nick Fabrizio, PhD, FACMPE, FACHE Principal MGMA Health Care Consulting Group
Successful Physician-Hospital Integration A Case Study Nick Fabrizio, PhD, FACMPE, FACHE Principal MGMA Health Care Consulting Group February 7, 2013 Speaker bio Nick Fabrizio, PhD, FACMPE, FACHE is a
More informationAsia-Link Symposium Programme, Bangkok 2006, 10 th November
Asia-Link Symposium Programme, Bangkok 2006, 10 th November Asia-Link Symposium European Higher Education Fair 2006 EHEF EU 250 Asia-Link Erasmus Mundus Scholarship 7 2007-2013 Framework Program for Research
More informationWelcome to. Shijiazhuang TieDao. University!
OUTLINE Welcome to Ladies and Gentlemen: I would like to take this chance to express our warm welcome to our respective friends! Shijiazhuang TieDao Welcome to China! University! Welcome to our President
More informationGENERAL CONDITIONS FOR PLANNING GRANTS WITHIN THE DEMO ENVIRONMENT PROGRAMME
GENERAL CONDITIONS FOR PLANNING GRANTS WITHIN THE DEMO ENVIRONMENT PROGRAMME 2015-2019 1. General 1.1 Scope These conditions set forth the terms for projects that have been awarded a Grant for Planning
More informationCree Nation Government Department of Capital Works & Services. Architectural services Whapmagoostui Community Pool & Youth Center
Cree Nation Government Department of Capital Works & Services Architectural services Whapmagoostui Community Pool & Youth Center Request for Professional Services Terms of Reference August 2017, version
More information1 CONTRACTING ENTITY 1.1 Official name: Athens International Airport S.A. 1.2 Postal address: Administration Building (17)/ Procurement Department
1 CONTRACTING ENTITY 1.1 Official name: Athens International Airport S.A. 1.2 Postal address: Administration Building (17)/ Procurement Department 190 19 Spata Greece 1.3 Contact point: Telephone: +30
More informationCape Town, 10 May 2017 Solutions and Innovations in Procurement
Cape Town, 10 May 2017 Solutions and Innovations in Procurement The Vision: Procurement in Investment Project Financing supports clients to achieve value for money with integrity in delivering sustainable
More informationCall for proposals (CFP) Ref No. TLIU 001/RIS01/2018
Call for proposals (CFP) REGIONAL INNOVATION SUPPORT (RIS) PROGRAMME Ref No. TLIU 001/RIS01/2018 Date of Issue Monday, 22 January 2018 Closing Date Wednesday, 28 February 2018 Place rnchabeleng@csir.co.za
More informationBidding Announcement for General Contracting of Shanghai Lin gang Jiaoda Zhibang Distributed PV Power Generation Project
Bidding Announcement for General Contracting of Shanghai Lin gang Jiaoda Zhibang Distributed PV Power Generation Project (IFB No.: S.Z. 2017-1762) Release time: April 13, 2018 Project location: Shanghai
More informationTERMS and CONDITIONS of BUSINESS Executive Search and Recruitment Terms
1.1 These Terms and Conditions of business ( these Terms ) are between NextGen Global Executive Search, hereafter known as the Recruiting Firm, whose registered office is at 1717 North Naper Blvd., Suite
More informationUse of External Consultants
Summary Introduction The Department of Transportation and Works (the Department) is responsible for the administration, supervision, control, regulation, management and direction of all matters relating
More informationCONTRACTING AND PURCHASING
CONTRACTING AND PURCHASING 2017 Educational Series CONTRACTING AND PURCHASING INTRODUCTION GOODS AND SERVICES Texas Department of Transportation (TxDOT) contracting activities are established and controlled
More informationFinancing Innovations in RES and EE in Germany. ener2i Training Workshop, Minsk, Belarus, Julian Schoenbeck, EnergyAgency.
Financing Innovations in RES and EE in Germany ener2i Training Workshop, Minsk, Belarus, 15.10.2014 Julian Schoenbeck, EnergyAgency.NRW Content 1. Background: NRW, EnergyAgency.NRW and German Energy Transition
More informationProf. Dr.-Ing. Werner Enderle Head of System Evolution European GNSS Supervisory Authority
Prof. Dr.-Ing. Werner Enderle Head of System Evolution European GNSS Supervisory Authority Galileo in FP7 International Information Day for the 1st Call & Brokerage Event Darmstadt, Germany 19-20 November
More informationTHE VERIZON TELEPHONE COMPANIES TARIFF F.C.C. NO. 1 2nd Revised Page 22-1 Cancels 1st Revised Page 22-1 ACCESS SERVICE
2nd Revised Page 22-1 Cancels 1st Revised Page 22-1 22. Advanced Communications Networks 22.1 TCP/IP Data Aggregation Service (A) Service Description (USOC - XMO++) TCP/IP Data Aggregation Service is available
More informationOVERVIEW OF THE CFP PROCESS Co-Financing Grants for Commercial Renewable Energy Projects in Indonesia. Jakarta, 3 rd February 2015
OVERVIEW OF THE CFP PROCESS Co-Financing Grants for Commercial Renewable Energy Projects in Indonesia Jakarta, 3 rd February 2015 Disclaimer This presentation is to facilitate the Q&A by providing an overview
More informationTHE STATION AT POTOMAC YARD. Public, Private, and Non-Profit Collaboration BY HELEN S. MCILVAINE
THE STATION AT POTOMAC YARD Public, Private, and Non-Profit Collaboration BY HELEN S. MCILVAINE The Station at Potomac Yard is a creative and cooperative approach to meeting multiple community needs in
More informationELIGIBLE PROJECTS MUST MEET THE FOLLOWING CRITERIA:
GUIDELINES 2017-2018 THE CANADA-GERMANY DIGITAL MEDIA INCENTIVE The Canada-Germany Digital Media Incentive (the Incentive ) is a collaboration between the Canada Media Fund ( CMF or Party) and Medienboard
More informationScaling Solar: An Update. Mr. Dana R. Younger Chief Renewable Energy Specialist Global Infrastructure & Natural Resources Department March 5, 2018
Scaling Solar: An Update Mr. Dana R. Younger Chief Renewable Energy Specialist Global Infrastructure & Natural Resources Department March 5, 2018 What is Scaling Solar? Scaling Solar is a one stop shop
More informationLEGAL ADVISER FOR. Adarsh ITIs LEGAL ADVISER
Planning Commission ADDENDUM NO. 2 TO THE REQUEST FOR PROPOSAL (RFP) FOR SELECTION OF LEGAL ADVISER FOR Adarsh ITIs LEGAL ADVISER 13.09.2012 RFP for Legal Consultant: Model Concession Agreement for ITIs
More informationDAVID EATON. Small Business Commissioner Small Business Development Corporation
DAVID EATON Small Business Commissioner Small Business Development Corporation Overview Background is small business important to our economy? Overseas experience Role of the Small Business Development
More informationExperience and Perspectives
5 th MENAinc Workshop Regional Collaboration for Enterpreneurship Development October 21-24, 2007 / Bahrain Asia Incubator Network: Experience and Perspectives By Mr Annuar Mohd Saffar Vice President,
More informationAPPENDIX B. Case Studies GLOBAL INFRASTRUCTURE HUB TURNER & TOWNSEND
APPENDIX B Case Studies 1 APPENDIX B: CASE STUDIES Case Studies Contents Brabo I Light Rail 3 Hydropower Plant 8 Piracicaba 440/138kV Substation 13 500kV Tucuruí-Jurupari Transmission Line 17 Qiaoxi District
More informationLuc Gregoire Chief Financial Officer. Internet & Technology Services Conference. February,
Luc Gregoire Chief Financial Officer Cantor Fitzgerald 4 th Annual Internet & Technology Services Conference February, 23 2017 Cantor Fitzgerald 4 th Annual Internet & Technology Services Conference February
More informationHow Does Germany Fit Into an International MSP Roll-Out?
16 MAY 2013 13:30 AMETHYST ROOM Thought Leadership Session: How Does Germany Fit Into an International MSP Roll-Out? Moderator: Diana Gabriel, VP, Strategy & Solutions, Staffing Industry Analysts Panellists:
More informationPage. II. TECHNICAL ASSISTANCE PROJECT DESCRIPTIONS.. 3 A. Introduction... B. Technical Assistance Areas.. 1. Rate Design Consumer Programs...
TABLE OF CONTENTS I. INTRODUCTION............... Page 1 II. TECHNICAL ASSISTANCE PROJECT DESCRIPTIONS.. 3 A. Introduction.... 4 B. Technical Assistance Areas.. 5 1. Rate Design.... 5 2. Consumer Programs...
More informationKENYA INFRASTRUCTURE AND PPP PROJECT SOUTH EASTERN KENYA UNIVERSITY HOSTELS PPP PROJECT
KENYA INFRASTRUCTURE AND PPP PROJECT SOUTH EASTERN KENYA UNIVERSITY HOSTELS PPP PROJECT DEVELOPMENT, OPERATION AND MAINTENANCE Tender Number: [SEKU/PPP/HP-01/2017-2018] ADDENDUM TO REQUEST FOR QUALIFICATION
More informationRequest for Proposal. Mobile Application for Customer Interface. October 6 th, 2017 Procurement Contact Holly Hussey
Request for Proposal Mobile Application for Customer Interface October 6 th, 2017 Procurement Contact Holly Hussey supplyandservices@sjenergy.com SAINT JOHN ENERGY OVERVIEW Saint John Energy is an electrical
More informationUIC Regional Assembly for Middle-East
Regional Assembly for Middle-East Amman, Jordan 7-87 8 May 2008 Amman - Zarqa Light Rail system (LRS) By Eng. Zahi Bani Said Director of Monitoring and Licenses Directorate Public Transport Regulatory
More information