Local Government Unit Private Infrastructure Project Development Facility (Loan 1729-PHI) in the Philippines

Size: px
Start display at page:

Download "Local Government Unit Private Infrastructure Project Development Facility (Loan 1729-PHI) in the Philippines"

Transcription

1 Project Completion Report PCR: PHI Local Government Unit Private Infrastructure Project Development Facility (Loan 1729-PHI) in the Philippines June 2005

2 CURRENCY EQUIVALENTS Currency Unit peso/s (P) At Appraisal At Project Completion 8 November September 2004 P1.00 = $ $ $1.00 = P P ABBREVIATIONS ADB Asian Development Bank BOO build-own-operate BOT build-operate-transfer CCPSP Coordinating Council for Private Sector Participation CRS credit rating system DILG Department of Interior and Local Government DMC developing member country DOF Department of Finance EA Executing Agency GFI government financial institution JBIC Japan Bank for International Cooperation LBP Land Bank of the Philippines LGFSD Local Government Financial Services Department LGU local government unit ODA official development assistance PCR project completion report PDF project development facility PPA Philippine Port Authority PSP private sector participation PUD Public Utilities Department TA technical assistance TASF Technical Assistance Special Fund TCR technical assistance completion report NOTES (i) (ii) The fiscal year (FY) of the Government and its agencies ends on 31 December. In this report, "$" refers to the US dollars.

3 ii CONTENTS Page BASIC DATA iii I. PROJECT DESCRIPTION 1 II. EVALUATION OF DESIGN AND IMPLEMENTATION 1 A. Relevance of Design and Formulation 1 B. Project Outputs 4 C. Project Cost 5 D. Disbursements 5 E. Project Schedule 6 F. Implementation Arrangements 8 G. Conditions and Covenants 8 H. Consultant Recruitment and Procurement 9 I. Performance of Consultants, Contractors, and Suppliers 9 J. Performance of the Borrower and Executing Agency 10 K. Performance of the Asian Development Bank 10 III. Evaluation of Performance 11 A. Relevance 11 B. Efficacy in Achievement of Purpose 11 C. Efficiency in Achievement of Outputs and Purpose 11 D. Preliminary Assessment of Sustainability 12 E. Environmental, Sociocultural, and Other Impacts 12 IV. OVERALL ASSESSMENT AND RECOMMENDATIONS 12 A. Overall Assessment 12 B. Lessons Learned 12 C. Recommendations 14 APPENDIXES 1. Project Framework Project Outputs Estimated and Actual Project Costs Chronology of Events Organization Chart during Project Implementation Status of Compliance with Loan Covenants 28

4 iii BASIC DATA A. Loan Identification 1. Country 2. Loan Number 3. Project Title 4. Borrower 5. Executing Agency 6. Amount of Loan 7. Amount of Grant 8. Project Completion Report Number B. Loan Data 1. Appraisal Date Started Date Completed 2. Loan Negotiations Date Started Date Completed 3. Date of Board Approval 4. Date of Loan Agreement 5. Date of Loan Effectiveness In Loan Agreement Actual Number of Extensions 6. Closing Date In Loan Agreement Actual Number of Extensions 7. Terms of Loan Interest Rate Maturity (number of years) Grace Period (number of years) 8. Terms of Relending Interest Rate Maturity (number of years) Grace Period (number of years) Second-Step Borrower Philippines 1729 Local Government Unit (LGU) Private Infrastructure Project Development Facility Land Bank of the Philippines Land Bank of the Philippines Y314,745,000 ($3 million equivalent) $600,000 PCR: PHI October December November November December March June June 2000 None 6 June September 2004 none Floating interest rate, based on the Asian Development Bank's market-based loan facility for Japanese yen 15 years 3 years Variable interest rate based on prevailing commercial rate maximum 5 years 1 year Local government units with commercially viable project

5 iv 9. Disbursements a. Dates Initial Disbursement 30 October 2002 Effective Date 5 June 2000 Final Disbursement 14 September 2004 Original Closing Date 6 June 2004 Time Interval 22.5 months Time Interval 48 months Category or Subloan Consulting Services b. Amount ($ million) Original Allocation Last Revised Allocation Amount Canceled Net Amount Available Amount Disbursed Undisbursed Balance Total Note: Y 314,745,000 ($3.0 million equivalent) at the time of loan appraisal. The difference between the $3.0 million and the total of $2.016 cancellation and $0.328 amount disbursed is due to exchange rate difference during the implementation. Category or Subloan Amount Value Date (Application No.) Disbursed Consulting Services: Application No. TA , October 2002 Application No. TA , April 2003 Application No. TA ,834 7 May 2004 Application No. TA , June 2004 Application No. TA ,552 2 September 2004 Application No. TA , September 2004 Total 328,307 C. Project Data 1. Project Cost ($ million) Cost Appraisal Estimate Actual FX LC Total FX LC Total A. Project Development Facility B. Capacity Building in LGU Financing Total FX = foreign exchange, LC = local currency, LGU = local government unit.

6 v 2. Financing Plan ($ million) Cost Appraisal Estimate Actual FX LC Total FX LC Total A. Project Development Facility 1. ADB LBP/LGU/BOT Subtotal B. Capacity Building in LGU Financing 1. ADB LBP Subtotal Total ADB = Asian Development Bank, BOT = build-operate-transfer, FX = foreign exchange, LBP = Land Bank of the Philippines, LC = local currency, LGU =local government unit. 3. Project Performance Report Ratings Implementation Period Development Objectives Ratings Implementation Progress From 1 Jan to 31 Dec 2000 Satisfactory Satisfactory From 1 Jan to 31 Aug 2001 Satisfactory Satisfactory From 1 Sep to 31 Oct 2001 Satisfactory Partly Satisfactory From 1 Nov to 31 Dec 2001 Satisfactory Satisfactory From 1 Jan to 28 Feb 2002 Satisfactory Satisfactory From 1 Mar to 31 Mar 2002 Partly Satisfactory Satisfactory From 1 Apr to 31 May 2002 Partly Satisfactory Partly Satisfactory From 1 Jun to 31 Dec 2002 Satisfactory Partly Satisfactory From 1 Jan to 31 Dec 2003 Satisfactory Partly Satisfactory From 1 Jan to 28 Feb 2004 Satisfactory Partly Satisfactory From 1 Mar to 31 Mar 2004 Satisfactory Satisfactory From 1 Apr to 14 Sep 2004 Partly Satisfactory Satisfactory D. Data on Asian Development Bank Missions Name of Mission Inclusive Dates No. of Persons Reconnaissance Mar Mission No. of Person- Days a Specialization of Members Investment officer Senior financial analyst Programs officer Financial analyst

7 vi Name of Mission Follow-Up Mission 1 Inclusive Dates 13 Oct 11 Dec 1998 No. of Persons 4 No. of Person- Days a Specialization of Members Private sector specialist Programs officer Economist Financial analyst Follow up Mission 2 24 May 30 Aug a Private sector specialist Counsel Financial analyst Loan Review Mission 1 Loan Review Mission 2 Loan Review Mission 3 Loan Review Mission Apr Governance specialist 13 May Senior financial management specialist Operations officer Economics officer Jun Governance specialist Operations officer 1 5 Sep Governance specialist Loan Review Mission 5 Project Completion Review b 21 Jul 9 Aug Nov 10 Dec Senior financial management specialist Operations officer 2 20 Senior financial management specialist Operations officer a b The actual number of days for the mission cannot be computed because the mission was carried out intermittently and the corresponding mission authorization requests, if any, can no longer be traced. The project completion report was prepared by Emma Yang, senior financial management specialist, and Hermie Bustamante, operations officer.

8 I. PROJECT DESCRIPTION 1. In December 1999, the Asian Development Bank (ADB) approved a technical assistance (TA) loan of $3.0 million equivalent and a TA grant of $0.60 million to the Land Bank of the Philippines (LBP). The Project comprised two components: (i) Part A Project Development Facility (PDF), and (ii) Part B Capacity Building in Local Government Unit (LGU) Financing. Under Part A, a revolving credit facility was to be established in LBP to finance consulting assistance to help LGUs solicit private sector participation in local infrastructure for project preparation. The consultants were to provide services comprised Phase 1 of project feasibility preparation and Phase 2 of bidding, evaluation, negotiations with, and contract awarding to private sector participants in revenue-generating infrastructure projects. As for Part B, LBP s inhouse capabilities were to be strengthened to finance LGU infrastructure projects with private sector involvement through (i) improvement of the credit rating system by incorporating governance criteria, (ii) training in private sector modalities, (iii) development of new credit products and enhancements to catalyze private finance, and (iv) preparation for a possible future ADB credit line. The project was classified to have economic growth as primary objective, and environmentally it is considered a Category C project. 2. The rationale for establishing the project development facility was based on the government plan to devolve responsibility for providing basic infrastructure services to the LGUs. With passage of Republic Act 7160, otherwise known as the Local Government Code of 1991, the primary responsibility for providing basic infrastructure services was devolved to LGUs. But traditional sources of LGU financing (e.g., official development assistance, internal revenue allotments, and local taxes) have been insufficient to meet their infrastructure needs. Thus the Government seeks to supplement these financing sources by helping credit-worthy LGUs with viable infrastructure projects to tap private sector financial sources. This could be through straight borrowing or any of the Government s private sector participation schemes, including build-operate-transfer (BOT) or build-own-operate (BOO). 3. The project s overall goal was to support decentralization process and regional economic development through increasing private sector funding of infrastructure projects at the LGU level. Specifically the TA aimed at promoting good governance and enhancing LGU capacity to prepare and bid infrastructure projects for private sector participation. The project comprised (i) project development facility (PDF), a revolving credit facility enhancing LGU capacity to prepare and tender suitable infrastructure projects for private sector participation, and (ii) capacity building assistance to enhance the capacity of government financial institutions (GFIs) to evaluate LGU project proposals for financing. Appendix 1 gives the project framework. II. EVALUATION OF DESIGN AND IMPLEMENTATION A. Relevance of Design and Formulation 4. The project design was relevant in terms of consistency with the country s development objectives and ADB s Philippine country program and strategy. To encourage regional development and decentralization, the Government passed the LGU Code of 1991, which empowered LGUs to finance and manage their infrastructure projects. This created a significant demand for financial resources that could not be sufficiently covered by traditionally available public sector sources. To supplement the traditional sources, the Government passed Republic Act 6957 (amended by Republic Act 7718), otherwise known as the BOT Law, which allows the private sector to finance, operate, and maintain infrastructure projects of creditworthy LGUs.

9 2 5. Private sector participation in LGU infrastructure has been constrained by the lack of LGU (i) capacity to prepare and tender projects for private sector participation; (ii) creditworthiness, mainly because of poor public sector governance structures and limited financing sources; and (iii) accessibility to long-term funds, because of shortcomings in the country s capital market. Thus, the Government has worked toward a financing framework to optimize and supplement the financing available to LGUs for infrastructure projects by tapping private sector sources. 6. The PDF, established under Part A, supported the Government s financing framework. It was the initial component of a larger national PDF initiative to provide project preparatory assistance to all government implementing agencies, at both national and local levels. The Government had planned to expand the PDF and get financial support from other donors. 7. The project design was in line with ADB s Philippine country strategy and program, which aimed to (i) broaden LGU institutional and financial capabilities to undertake development programs and projects, and encourage private sector participation; (ii) support human resource development and investment in basic needs; (iii) help improve the efficiency and performance of LGU infrastructure delivery; and (iv) improve self reliance and lessen LGU financial dependence on the Government. 8. The Project was not properly implemented as envisaged during conceptualization. Few LGUs identified during project preparation and implementation were properly assessed of their understanding of the PDF and BOT schemes. Most LGUs were keen to finance feasibility studies for their respective projects through grants, not loans. Thus, only 2 of the 30 identified LGUs (17 during project processing and 13 during implementation) took advantage of the PDF. Unfortunately, the first subproject was partially implemented, then subsequently canceled, because of institutional differences among participating LGUs. But implementation of the second subproject is underway, and completion is expected in the first half of But because of the decision to close the loan account in 2004, financing for this subproject was limited to Phase 1. Phase 2 is now financed by the LGU from a separate LBP loan. During implementation, six main weaknesses in project design and formulation were identified: (i) (ii) Limited facility coverage. Demand for credit to finance infrastructure was high, and LGUs were increasingly willing to borrow and assume responsibility for repayment of the loans. But most LGUs were not enthusiastic about the facility offered under the Project because (a) the PDF supported only the preparation of feasibility studies and bidding processes, but not the ensuing projects; and (b) the facility was limited only to revenue-generating projects that were deemed suitable for private sector participation. If the PDF were broadened to allow LGUs to obtain loans and undertake the infrastructure projects themselves, the take-up would probably have been far higher. But the BOT Center maintained that extending the facility would detract from the unique purpose of the BOT Law to promote private sector participation (PSP). This conceptual conflict between the target beneficiary and BOT Center was not anticipated when the Project began. Non-familiarity with the build-operate-transfer modality. LGUs were still unfamiliar with the BOT concept promoted through the PDF, and were reluctant to enter into such contracts, given the poor track record and high-profile failures at the national level. To overcome this resistance, the Project had intended as a matter of strategy to use the first one or two sub-loans as demonstration cases to

10 3 encourage further LGU participation. Thus, the Project would have fulfilled two purposes: to provide financing for the preparatory works, and to support policy reform to encourage partnerships of the public and private sectors. But because of delay in project implementation and the closing of the loan account in September 2004, without extension, the implementation of one of the two approved purposes was not fully completed in time to serve as a demonstration case. (iii) (iv) (v) (vi) Insufficient marketing efforts. The agencies involved in the Project LBP and the Coordinating Council for Private Sector Participation (CCPSP), which was later renamed the BOT Center by Executive Order 144 have promoted PDF through different approaches. The BOT Center tended to be more proactive in producing marketing materials and conducting orientation seminars for local government officials. But it was constrained by its limited staff and offices that were only in Manila. In contrast, LBP had a far broader reach through its regional lending centers, which were the first ports-of-call for local governments seeking financial assistance. Although the LBP headquarters had trained its staff at regional lending centers, the level of interest and understanding at the regional level remained too low to enable effective marketing of the PDF to LGUs. Availability of other and cheaper financing assistance. LGUs were reluctant to borrow for feasibility study, but wanted only to finance largely from grants or their own resources. The PDF even faced competition from other ADB projects (e.g., the Mindanao Basic Urban Services Sector), which provided grants for the feasibility study. PDF was offered at the prevailing commercial rates the fixed rate at 11% while LGUs could tap cheaper sources. LGUs generally failed to appreciate the distinction between fixed and variable rates, and simply opted for the cheaper funds. The LGUs also argued that since ADB provided the funds, the funds should be lent at concessional rates. Although LBP had expressed willingness to lower the PDF rate to make it competitive, it was only willing to give a variable, not a fixed, rate. Unacceptable processes for consultant selection. The consultants were selected by LBP in accordance with the ADB Guidelines, and the team of consultants included international experts. A fundamental reason to provide international consultancy assistance to the Borrower was to protect LGUs from unsolicited private bids, low-quality feasibility studies, and nonqualified contractors. But LGUs still questioned the consultant s selection processes, and the relatively high costs of international consultants just for feasibility studies. Discussions with potential recipients indicated that LGUs would have liked more participation in selection, and would have preferred cheaper local consultants with comparable qualifications. High market risk. The loan required the LGUs to assume full cost of the feasibility study in case there was no successful bidder for the projects. Once the project was successfully awarded, the LGU could pass the cost of the feasibility study to the winning bidder. Few LGUs would take on an expensive feasibility study in which successful bidding process was not guaranteed.

11 4 9. Capacity building for the LBP under Part B was considered essential for project implementation. The PDF program was new to both LBP and the LGUs. Thus, it was necessary that LBP familiarize with the PDF concept so it could more effectively market PDF to the LGUs. B. Project Outputs 1. Part A. Project Development Facility 10. At loan approval in December 1999, 17 potential projects were in the pipeline; another 13 subprojects had been identified during implementation. The loan was anticipated to finance as many as 10 subprojects. But only two subprojects have been approved: the Davao del Norte Integrated Water Resource Development Project, and the Modernization of Olongapo City s Public Utilities Department (PUD). The PDF funded only Phase 1 of both subprojects; their status is discussed in the following paragraphs. Appendix 2 compares project outputs at appraisal and completion, including a list of subprojects that did not materialize. (i) (ii) Davao del Norte Integrated Water Resource Development Subproject. The consultant s feasibility study was submitted to key officials of the six LGUs and the Davao provincial government for review and deliberation. But some stakeholders did not accept the feasibility study and recommendations. Concerned officials from two of the six water districts (Tagum and Panabo) rejected the institutional recommendation to discontinue the existing six water districts and combine them in a single provincial water district. Because of this, Davao del Norte and the six participating LGUs jointly agreed to pre-terminate their agreement with the consultants for implementation of Phase 2 of the subproject. Due to the termination of the feasibility study, the four water districts that accepted the consultant s recommendation had turned to local water utilities administrations for financing support and received loans from their local water utilities administrations to rehabilitate their water distribution facilities. Modenization of Olongapo City s PUD Subproject. Olongapo City accepted the consultant s report, including the recommendation for the employees separation program for those employees affected by the PUD modernization, and those who want to voluntarily leave their government positions. To make the program effective, a premium over the legal separation pay will be offered to departing employees, based on their number of government service years. Departing employees will also be paid the monetary value for their leave credits. The separation program will become effective when the distribution system is turned over to the winning bidder. The city government will absorb employees that the private operator does not employ. In consultation with LBP, the consultants services under Phase 2 of the project will no longer be financed under the ADB loan. Instead, those services will be financed by the LBPapproved loan to Olongapo. Implementation of Phase 2 will be completed in the first half of Part B. Capacity Building in Financing of Local Government Units 11. Capacity building was supported by TA 3349-PHI: Capacity Building in Local Government Unit Financing. The consultant s final report was rated satisfactory, and the overall

12 5 rating of the TA was also successful since TCR focused on the delivery of outputs. 1 It summarized the work undertaken and the main finding, and proposed an innovative way to catalyze LGU financing through a multifaceted, market-oriented approach. Recommendations for improving LGU loan processing and administration were accepted, and LBP appreciated the regional training provided. LBP considered the credit rating system developed under the TA an excellent tool. A seminar on LGU financing and credit rating was well-attended by both the public and private banking community, and was a key mechanism for promoting the TA findings. Capacity building and training were accomplished through three 2-day regional seminars. However by reviewing the TA outcomes at the time of completion of the loan, there are concerns on the sustainability of the impacts of the TA. C. Project Cost 12. At appraisal, the project cost was estimated at $4.515 million, but the actual project cost was only $1.078 million (Table 1). Table 1: Project Cost Appraisal Actual Estimate Cost Source FX LC Total FX LC Total Part A: Project Development Facility Part B: LBP Capacity Building Total FX = foreign exchange, LBP = Land Bank of the Philippines, LC = local currency. Source: Report and Recommendation of the President to the Board of Directors on a Proposed Technical Assistance Loan and Grant to the Philippines and the Land Bank of the Philippines for the LGU Private Infrastructure Project Development Facility. 13. Of the total estimated project costs of $4.515 million for Parts A and B, ADB was to provide $3.0 million equivalent as a TA loan for Part A and $0.6 million as a TA grant for Part B. LBP was to provide $0.335 million; the BOT Center, $0.250; million; and LGUs, $0.330 million. 14. Under Part A, the actual loan utilization was significantly lower than the appraisal cost estimate. The significant disparity in cost is attributed to the lesser number of approved subprojects. Only two out of the ten expected subprojects materialized, and ADB financing for both subprojects was limited to phase 1 only. On the other hand, the activities of Part B were implemented according to its schedule. The actual costs are within the estimated costs projected during appraisal. A comparison of detailed cost estimates at appraisal and actual expenditures are shown in Appendix 3. D. Disbursements 15. The arrangement for disbursement of loan proceeds is appropriate. Consultants are paid directly, based on approved billings. Such disbursements are booked to the relevant LGUs as subloan disbursement under LBP s PDF credit facility. No extension of loan closing date was made in view of ADB s decision to close the loan account on or before the Project s original loan 1 TCR was circulated to the Board on 25 July Document No. IN

13 6 closing date of 6 June 2004, due to slow project implementation and the anticipation that there would be no additional subprojects to be approved or implemented under the Project. LBP was advised, and concurred with ADB s decision. LBP was given a 3-month grace period to complete the payment for the consultant s remaining claims for the Olongapo City subproject. The TA loan account was closed on 14 September 2004, with a total disbursement of $0.328 million and cancelation of an unutilized loan amount of $2.518 million. E. Project Schedule 16. The Loan Agreement stipulated that both TA components were expected to commence in the first quarter of The TA loan for Part A was expected to be committed over 3 years with disbursement continuing as long as 12 months. Thereafter LBP s PDF would continue operating, financed by reflows of funds. Part B would be implemented over 18 months. Appendix 4 chronologically lists major project milestones. 17. The loan was anticipated to finance as many as 10 subprojects over 4.5 years, ending in June But the Project has experienced significant delays in implementation due to difficulties encountered by LBP and the BOT Center in getting the LGUs confirmation to avail of the TA loan facility. The latter in turn is due to the LGUs (i) lack of appreciation of the BOT/PSP policies; (ii) reluctance to access loans for pre-investment studies, especially with the availability of grants for such studies from other financing facilities; and (iii) reluctance to pursue infrastructure projects whose implementation usually goes beyond the 3-year terms of local executives. 18. Thus, the feasibility study for the first subloan to Davao del Norte was approved only in June 2002, and was completed in January Phase 2 of the consultancy assistance related to the preparation of tender documents. Evaluation and awarding were subsequently canceled because the LGUs involved in the subproject failed to agree on the amalgamation of the water districts under them. The second subloan agreement was signed by LBP and Olongapo City on 27 January 2004 for the rehabilitation and upgrading of the city s system of electrical power distribution. The feasibility study was completed and accepted by the City of Olongapo. The bidding process began in December 2004 and is expected to be completed during the first half of Under Part B, the target was to have at least five LGUs subprojects appraised for possible financing by LBP, and recommendations for terms and conditions for a possible ADB credit line to LBP to finance implementation of such subprojects. The key objectives of the credit line were to (i) pioneer project financing approaches for LGU infrastructure, (ii) provide private sector developers and project proponents with long-term peso-denominated debt, (iii) serve as a catalyst for mobilizing commercial debt and equity, (iv) help develop more mature capital markets through several successful project financing operations, and (v) create a credible bridge to future use of municipal bonds and similar instruments for LGU infrastructure development. 20. Compared with the targeted five subprojects for possible ADB credit lines to LBP for financing, no subprojects were actually financed by LBP to a private developer under this program. The reasons behind it can be attributed to the following two main constraints:

14 7 1. Organizational constraints. These were: a. Actual implementation was constrained by the fact that some LGUs lacked the capacity to identify and submit subprojects. Such LGUs require effort and time to develop subproject proposals. b. The TA component was a misnomer. Some LGUs initially expressed interest in Private Infrastructure Project Development Facility, thinking that it was a direct financial grant rather than a loan. c. The onlending interest rate to LGUs on the PDF was higher than the internal LBP interest rate to LGUs to finance their projects. d. The LGUs perceived that official development assistance (ODA) loans entail long and tedious processing procedures and requirements. Some LGUs stated that the targeted completion time of a project would never be accomplished if financing were from ODA loans. e. Project implementation normally goes beyond the 3-year term of the local executives. Thus, previous marketing efforts were useless if newly elected executives did not support the Project. Re-marketing to create awareness of the PDF was necessary. f. LGUs were not keen on accepting international consultants imposed on them. LGUs wanted a free hand in choosing consultants because they bear the burden of paying the loans. g. Prudent private investors would not just bid on an LGU project, putting full trust on a feasibility study done by a third party unknown to them. h. The consultant for the capacity building component recommended adoption of a revised computerized credit rating system (CRS) for LGUs. But CRS was found limiting because the proposed system classifies LGUs in only two categories: good and bad. In the present LBP system, LGUs are classified as prime, high-grade, medium-grade, and poor. Furthermore, the LBPs raw data on LGUs were not in a form that can be readily used by the system. Hence, there was a need for conversion. The data needed relies heavily on a number of updated inputs to be provided by the LBP field units, the LGUs, Department of Finance (DOF), Commission on Audit, Department of National Defense, and the National Economic and Development Authority. Without updated data from those agencies, the system will be ineffective. With consistency of the present CRS to existing LBP credit policies, LBP found no urgency to adopt the recommended revised CRS. However, with limitations, the present LBP CRSs for LGUs have been sufficient to address ADB s current requirements. i. The credit line proposal was considered innovative but LBP could not immediately implement it because: (i) there was no champion in DOF to implement it, due to changes in the Government; (ii) it was too early to implement the proposal because no project had yet been prepared under the PDF; (iii) economic conditions were not conducive to its implementation; (iv) the proposal was, in some ways, too innovative; and (v) LGUs had a negative perception of BOT projects. 2. Implementation constraints. These were: a. The onlending interest rate to LGUs on the PDF was higher than the internal LBP interest rate to LGUs to finance their projects. b. Most LGUs sought only infrastructure financing. Local executives sometimes had difficulty justifying million-peso loans to their constituents

15 8 just to finance the feasibility studies, especially with no assurance that private investors would participate in the BOT. c. Project implementation normally goes beyond the 3-year terms of local executives. Thus, previous marketing efforts were useless if newly elected executives did not support the Project. Re-marketing to create awareness of the PDF was necessary. d. LGUs were not keen on accepting international consultants selected by LBP and imposed on them. LGUs wanted a free hand in choosing consultants because they bear the burden of paying the loans. e. Prudent private investors would not just bid on an LGU project, putting full trust on a feasibility study done by a third party unknown to them. f. LBP considered the enhanced CRS an excellent tool, but did not adopt it, mainly because it was inconsistent with ADB s new priorities, caused by reorganization and corresponding changes in management. LBP found it unnecessary to follow the consultant s recommendation, considering that its portfolio with LGUs had done well and its lending centers personnel were immersed with the LGUs. LBP felt that no enhanced CRS could perform better than the frequent and physical interactions of ADB and the LGU executives and staff. g. The credit line proposal was considered innovative but LBP could not immediately implement it because: (i) there was no champion in DOF to implement it, due to changes in the Government; (ii) it was too early to implement the proposal because no project had yet been prepared under the PDF; (iii) economic conditions were not conducive to its implementation; (iv) the proposal was, in some ways, too innovative; and (v) LGUs had a negative perception of BOT projects. F. Implementation Arrangements 21. The project implementation arrangements remained essentially as envisaged during appraisal. For Part A, LBP, under its Local Government Financial Services Department (LGFSD), established a PDF desk to be responsible for PDF relending operations, including coordination with LGUs through LBPs regional centers and close coordination with the BOT Center. But LBP reorganization, which resulted in transfer of original project officers and personnel, greatly hampered PDF implementation. LGFSD was dissolved and its personnel handling the PDF were transferred to other LBP branches or units. The LGUs loan-related files were transferred to the area lending centers. The BOT Center, under its LGU and Project Preparation Division, provided technical support for LBPs PDF operations. LGUs established a project unit and assigned counterpart staff and facilities for project implementation. Appendix 6 gives the organization chart for project implementation. 22. The consulting firm engaged under Part B, provided 28.6 person-months of consultancy assistance, comprising 15.6 person-months for foreign and 13.0 person-months for domestic consultants. The contract period was appropriate for the consultants to carry out their terms of reference, which were designed to provide support for the accompanying TA loan. G. Conditions and Covenants 23. The Executing Agency s (EA) compliance with the loan covenants was partly satisfactory. LBP could not effectively market the PDF because (i) LBP officers originally involved in the Project were transferred to other branches or units; and (ii) concerned officers in

16 9 some LBP branches were not aware of the PDF to be offered to LGUs. LBP also failed to submit the quarterly progress report within the time specified in the Loan Agreement. Appendix 7 gives detailed compliance of the EAs with the loan covenants. H. Consultant Recruitment and Procurement 24. Under Part A, an estimated 55 person-months of international and 220 person-months of domestic consulting services would be required over the 3-year implementation period. An international consulting firm would undertake the first year s PDF activities, and consultants might be engaged for the duration of project implementation. 25. In February 2001, LBP engaged an international consulting firm to help the LGU undertake the feasibility study of the identified subproject and all phases of tendering, negotiation, and awarding of contracts. The consultancy agreement covers about 18 personmonths of international and 70 person-months of domestic consulting services. The consultants were recruited in accordance with ADB s Guidelines on the Use of Consultants. 26. The total contract period for the consultants for the Davao del Norte project was 7 months. But the contract period was reduced to about 3 months because the stakeholders terminated the consultants services because they could not agree with the consultants recommendation to close their respective water districts and create a new provincial water district. For the Olongapo project, the consultants utilized a total of 3 calendar months for Phase 1, as envisaged in the contract agreement between LBP and the LGUs. 27. Under Part B, an international consulting firm was engaged to provide 15 person-months of services to LBP, to be supported by 15 person-months of domestic consulting services in the areas of LGU finance, banking, law, and information technology. The total actual inputs of the consultants were consistent with the appraisal estimate except for the domestic consultants, where the actual inputs were short by 2 person-months. The consultants procured computers and accessories with ADB s approval. The consultants turned over the equipment to LBP on completion of project implementation. I. Performance of Consultants, Contractors, and Suppliers 28. The services provided by the consulting firm engaged under Part A of the project cannot easily be measured because of the event that took place during implementation of the two subprojects. In Davao del Norte, the consultants could complete only the feasibility study, but not the second phase of the project, which involved bidding and contract award. Nonimplementation of the second phase is attributed to the refusal of two of the six LGUs to accept the consultants recommendation to consolidate the six municipal water districts into one provincial district. Because of this, the consultancy contract for Phase 2 was terminated prematurely. 29. For the second subproject, in Olongapo, the city accepted the consultants feasibility report, including its recommendations. But because implementation of Phase 2 of the project has slipped to 2005, subproject financing was limited only to Phase The contract for Part B LBP Capacity Building in LGU Financing was not well negotiated. The negotiations took more than a week because local representatives had no real authority to negotiate and the team leader was not involved. Thus at inception, many problems affected project implementation. The consultant team leadership and performance were not well

17 10 managed. There was no obvious support from a head office for review of work or support of general implementation. The consultants performance is rated as satisfactory, overall, but there was a problem. The affiliated consultant of the lead firm was rated marginal due to lapses in coordinating with the BOT Center and late submission of revisions for the final report, which significantly delayed submission of the final report. Overall, the consultant s inputs were appropriate in terms of design, quality, and quantity. J. Performance of the Borrower and Executing Agency 31. LBP s performance was considered partly satisfactory. In line with the Loan Agreement, LBP was responsible for marketing the facility, with BOT assistance. But LBP s marketing effort was insufficient, particularly at the regional level. In fact, LBP had little incentive to market the facility independently of other products that it offers. LBP mainly relied on the list of LGUs and possible projects that the BOT Center provided. 32. Both the LBP LGFSD and the BOT Center should have been provided sufficient and qualified staff and adequate resources to support the LBP PDF credit facility during TA implementation. But frequent staffing changes during implementation negated the knowledge and experience gained by those earlier assigned to the Project. 33. Before loan approval, the BOT Center assured LBP and ADB that a number of worthy projects were in the pipeline. But most projects initially identified were canceled because the sponsoring LGUs had either lost interest or could secure grant assistance from other funding agencies. The 2001 election further hampered project marketing and implementation. Thus, only two subprojects were approved before the TA loan was closed. K. Performance of the Asian Development Bank 34. ADB s overall performance is rated as partly satisfactory. ADB should have addressed deficiencies in project design and formulation immediately when they became apparent, but did not. ADB should have changed the project scope when none of the initial and subsequent subprojects materialized in 2001, and no disbursements from the loan accounts were made. 35. During early project implementation, ADB met with representatives of LBP and the consultants to discuss issues and report requirements. Five review missions were subsequently conducted. In , ADB called tripartite monthly meetings of ADB, LBP, and the BOT Center to share information, monitor progress, and deal with current issues. The possibility of loan cancelation was discussed in country portfolio review meetings in November 2002 and April Both LBP and the BOT Center reiterated the Project s importance, and requested more time to improve project performance, which ADB approved. ADB also approved LBP's request to extend the consultants services but only until May 2004, rather than August 2004, as originally planned. Approval for contract extension was based on ADB's decision to close the loan account on or before 6 June 2004, after completing payment for consultants services for phase 1 of the Olongapo City subproject. Constant reminders to LBP were made relative to submission of quarterly progress reports.

18 11 III. EVALUATION OF PERFORMANCE A. Relevance 36. The overall Project is rated partly relevant. The Project s objectives and scope, as formulated at appraisal, were consistent with the Government s framework for LGU financing and ADB s sector strategy for public governance and urban development. But the Project suffered from a lack of EA ownership, and a lack of LGU interest. Deficiencies in project design and formulation contributed to the limited achievement of project targets. Thus, Part A is rated as partly relevant. As to the relevance of Part B, its design assumed successful implementation of Part A. As the implementation of Part A was limited to the financing of only two subprojects, in retrospect, Part B could not be most relevant. B. Efficacy in Achievement of Purpose 37. The Project aimed to support regional development and decentralization by facilitating private sector financing of infrastructure projects at the LGU level. Specific objectives were to promote good governance and enhance LGU capacity to prepare and bid infrastructure projects for private sector participation. To achieve the objectives, the Project was to (i) establish a project preparatory financing mechanism for LGU-level infrastructure projects, (ii) enhance GFI s LGU financing capacity, and (iii) build capacity in LGU credit/governance rating. 38. The first target was achieved to a limited extent. Although a project development facility was established and consultants were engaged, LBP approved only two LGU infrastructure subprojects. 39. Most of the Part B objectives, for capacity building, were achieved. But the Project failed to productively apply what had been learned to market the product because LBP had its own funds to offer to potential borrowers, in competition with those that the Facility offered. Thus, Part B, and the overall project is less efficacious. C. Efficiency in Achievement of Outputs and Purpose 40. The Project was inefficient in achieving its targeted outputs, which were to (i) complete feasibility studies and tender of at least 10 LGU-level infrastructure projects; (ii) train at least 10 LGUs and involve them in preparing and managing private sector projects; (iii) development of LBP s and other GFI capacity to appraise and finance projects, including expertise in credit ratings; (iv) computerize and enhance LBP s LGU financial information and credit rating systems; (v) incorporate governance rating criteria in LBP s credit rating system; and (vi) define the proposed credit line to finance implementation of the LGU private sector project, and appraise five projects. The target outputs for (i) and (ii) were marginally met, but LBP did not properly address or implement the others, as the TA consultant recommended. 41. Although LBP had undergone capacity building under Part B, that knowledge seemed to have been used to evaluate LGU projects for financing with its own funds not to market the Project. No LGUs visited at project closing were aware of the PDF. Interviews revealed that no one from LBP approached and promoted the Facility to them. Furthermore, LBPs believed that, even if they had been aware of PDF, they still would not have used it because grant funds were available to finance the feasibility study. Nor were the LGUs convinced of the privatization concept. Most still perceived that local government not the private sector should undertake public infrastructure projects.

19 12 D. Preliminary Assessment of Sustainability 42. Based on the small number of LGUs that used the loan facility, and the limited interest of other LGUs, the sustainability of the PDF, in its current form, seems unlikely. Furthermore, lending competition was not only from the other donor agencies but also from LBP, which was entrusted with project implementation. E. Environmental, Sociocultural, and Other Impacts 43. The Project, which only provides funding for the preliminary costs of conducting feasibility studies, has had no direct environmental, sociocultural, or other impacts. The two subprojects entailed no land acquisition or resettlement, or environmental issues, since ADB funded only Phase 1 of the feasibility study. 44. The two LGUs assured that the feasibility studies financed under the Project complied with ADB s environmental and social guidelines, including the policy on involuntary resettlement. IV. OVERALL ASSESSMENT AND RECOMMENDATIONS A. Overall Assessment 45. Neither Part A nor Part B of the Project was properly implemented. In Part A, the Project did not take off effectively because the LGUs were unwilling to borrow for feasibility studies. Competition arose from other donor agencies, and from LBP itself, in several ways. First, a number of donor agencies offered grants to finance feasibility studies. Second, LBP offered financing for feasibility studies as part of its loan processing activities. In contrast, the fund that the Project offered was a loan. Furthermore, the loan charged interest equivalent to prevailing commercial rates, which was higher than the interest that LBP charged to its customers for loans from its own funds. 46. Part B was not successful. Although the grant was fully utilized to provide LBP staff some degree of familiarity with the processing and evaluation of LGU projects with private sector participation, LBP s subsequent marketing of the Project was not effective. ADB s closing review of the prospective projects showed that few LGUs had been aware of the PDF. Furthermore, in lieu of promoting the use of ADB funds, LBP used its own funds to finance viable projects. Although it was implemented satisfactorily, output of Part B was not sustained and it was not relevant to the development outcomes at the LGU level. 47. Part A is rated unsuccessful, while Part B is partly successful. Overall, the Project is rated unsuccessful. B. Lessons Learned 48. The Project had valid objectives, but several essential factors were overlooked during its conceptualization stage. Project implementation yielded the following major lessons learned that should impact on design and implementation of similar loans in the future: (i) Demand analysis of local government units. A thorough demand analysis of LGUs should have been conducted to ascertain target LGUs willingness to participate in the Project. To strengthen commitment, participatory approach

20 13 during the design of such projects is absolutely necessary. The financial capacity of the identified LGUs to enter into loan agreements of several million pesos for preparation of feasibility studies and tender documents, which might or might not transform into actual LGU infrastructure, should have been examined first. (ii) (iii) (iv) (v) (vi) Simpler implementation arrangements. Coordination between the LBP and the BOT Center during project implementation left much to be desired. Although the BOT Center was quite proactive in producing marketing materials and conducting orientation seminars for local government officials, its activities had limited impact as its staff and offices are located only in Manila. In contrast, although LBP has a far broader reach through its regional lending centers, which had been provided training, the level of interest and understanding at the LBP regional level remained low. The LBP regional representatives could have enhanced their capacities to market the product to LGUs by attending the training conducted by the BOT Center. Loan coverage and terms. The facility had limited focus in terms of activity and project eligibility. First, the facility offered loans only to finance feasibility studies and tender documents; it gave no funding for the ensuing project. Second, financing was restricted only for private sector projects and LGUs were not fully keen nor familiar or comfortable with bidding projects out. The interest of LGUs would probably have been higher if the facility had allowed financing for LGUs to develop local government infrastructure. There were also problems with the terms of lending in terms of higher interest rate and the lack of understanding of the advantages of fixed-rate borrowing. Mitigating political influence. The project design should have reflected a basic understanding of the dynamics of political cycles. Local leadership changed every 3 years, and the project selection process lay in the hands of the incumbent or newly elected local executives. More often than not, newly elected officials shelved projects that the former local executives initiated, especially if the officials belonged to different parties. Mitigating measures to alleviate the effects of political changes could have been included in the project design. For example, the project design could have minimized the risk of political interference by following the established division of work among government agencies, which designates the Department of Interior and local governments to assist in LGU infrastructure development. Furthermore, measures to alleviate negative effects of political changes could have been built into the design by adjusting the project schedule to mayoral terms. Financial channels for LGUs. Local LBP branches were usually the first agencies that the LGUs approached when seeking funds for development projects. LBP loans include the cost of a feasibility study, so LGUs prefer to use GFIs. Thus, LBP s role as a financial conduit should be carefully reviewed to minimize conflicts of interest. Earlier project termination. ADB could have insisted that the Project close in late 2002, when implementation progress was low and few potential subprojects had materialized.

Nepal: Small Towns Water Supply and Sanitation Sector Project

Nepal: Small Towns Water Supply and Sanitation Sector Project Validation Report Reference Number: PVR 193 Project Number: 31402 Loan Number: 1755(SF) November 2012 Nepal: Small Towns Water Supply and Sanitation Sector Project Independent Evaluation Department ABBREVIATIONS

More information

PROJECT PREPARATORY TECHNICAL ASSISTANCE

PROJECT PREPARATORY TECHNICAL ASSISTANCE Appendix 3 11 A. Justification PROJECT PREPARATORY TECHNICAL ASSISTANCE 1. The government has identified the priority areas to be covered under the ensuing project. A PPTA is necessary to provide sound

More information

India: Agribusiness Infrastructure Development Investment Program (Tranche 2)

India: Agribusiness Infrastructure Development Investment Program (Tranche 2) Completion Report Project Number: 37091-033 Loan Number: 2837 August 2017 India: Agribusiness Infrastructure Development Investment Program (Tranche 2) This document is being disclosed to the public in

More information

Papua New Guinea: Implementation of the Electricity Industry Policy

Papua New Guinea: Implementation of the Electricity Industry Policy Technical Assistance Report Project Number: 46012 December 2012 Papua New Guinea: Implementation of the Electricity Industry Policy The views expressed herein are those of the consultant and do not necessarily

More information

Completion Report. Pakistan: Balochistan Devolved Social Services Program

Completion Report. Pakistan: Balochistan Devolved Social Services Program Completion Report Project Number: 37218 Loan Numbers: 2202, 2203, and 2204 Grant Number: 0028 December 2011 Pakistan: Balochistan Devolved Social Services Program CURRENCY EQUIVALENTS Currency Unit Pakistan

More information

PROJECT PREPARATORY TECHNICAL ASSISTANCE

PROJECT PREPARATORY TECHNICAL ASSISTANCE A. Justification PROJECT PREPARATORY TECHNICAL ASSISTANCE 1. A project preparatory technical assistance (PPTA) is required to support the Ministry of New and Renewable Energy (MNRE) and Solar Energy Corporation

More information

Public Disclosure Copy. Implementation Status & Results Report Global Partnership for Education Grant for Basic Education Project (P117662)

Public Disclosure Copy. Implementation Status & Results Report Global Partnership for Education Grant for Basic Education Project (P117662) Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized AFRICA Liberia Education Global Practice Recipient Executed Activities Specific Investment

More information

People s Republic of China: Strengthening the Role of E-Commerce in Poverty Reduction in Southwestern Mountainous Areas in Chongqing

People s Republic of China: Strengthening the Role of E-Commerce in Poverty Reduction in Southwestern Mountainous Areas in Chongqing Technical Assistance Report Project Number: 51022-001 Knowledge and Support Technical Assistance (KSTA) December 2017 People s Republic of China: Strengthening the Role of E-Commerce in Poverty Reduction

More information

FRAMEWORK FINANCING AGREEMENT. (National Highway Development Sector Investment Program Project 1) between ISLAMIC REPUBLIC OF PAKISTAN.

FRAMEWORK FINANCING AGREEMENT. (National Highway Development Sector Investment Program Project 1) between ISLAMIC REPUBLIC OF PAKISTAN. FRAMEWORK FINANCING AGREEMENT (National Highway Development Sector Investment Program Project 1) between ISLAMIC REPUBLIC OF PAKISTAN and ASIAN DEVELOPMENT BANK DATED 29 October 2005 FRAMEWORK FINANCING

More information

India: Madhya Pradesh State Roads Sector Project II

India: Madhya Pradesh State Roads Sector Project II Completion Report Project Number: 37328-013 Loan Number: 2330 September 2015 India: Madhya Pradesh State Roads Sector Project II This document is being disclosed to the public in accordance with ADB s

More information

Uzbekistan: Woman and Child Health Development Project

Uzbekistan: Woman and Child Health Development Project Validation Report Reference Number: PVR-331 Project Number: 36509 Loan Number: 2090 September 2014 Uzbekistan: Woman and Child Health Development Project Independent Evaluation Department ABBREVIATIONS

More information

Completion Report. Project Number: Loan Number: 2230-PAK October Pakistan: Rural Enterprise Modernization Project

Completion Report. Project Number: Loan Number: 2230-PAK October Pakistan: Rural Enterprise Modernization Project Completion Report Project Number: 38447 Loan Number: 2230-PAK October 2010 Pakistan: Rural Enterprise Modernization Project CURRENCY EQUIVALENTS Currency Unit Pakistan rupee/s (PRe/PRs) At Appraisal At

More information

Rajasthan Urban Sector Development Program

Rajasthan Urban Sector Development Program India: Rajasthan Urban Sector Development Program Project Name Rajasthan Urban Sector Development Program Project Number 42267-026 Country Project Status Project Type / Modality of Assistance Source of

More information

Kyrgyz Republic: Investment Climate Improvement Program

Kyrgyz Republic: Investment Climate Improvement Program Validation Report Reference Number: PVR-423 Project Numbers: 41544-022, 41544-082, 41544-084 Grant Numbers: 0120, 0319, and 0393 October 2015 Kyrgyz Republic: Investment Climate Improvement Program Independent

More information

OPERATIONS MANUAL BANK POLICIES (BP) These policies were prepared for use by ADB staff and are not necessarily a complete treatment of the subject.

OPERATIONS MANUAL BANK POLICIES (BP) These policies were prepared for use by ADB staff and are not necessarily a complete treatment of the subject. OM Section E2/BP Page 1 of 3 OPERATIONS MANUAL BANK POLICIES (BP) These policies were prepared for use by ADB staff and are not necessarily a complete treatment of the subject. A. Introduction JAPAN FUND

More information

GLOBAL INFRASTRUCTURE FACILITY OPERATING GUIDELINES

GLOBAL INFRASTRUCTURE FACILITY OPERATING GUIDELINES GLOBAL INFRASTRUCTURE FACILITY OPERATING GUIDELINES As Adopted by the GIF Governing Council on 20 April, 2015 And Revised on 16 June, 2016 A. INTRODUCTION 1. The Global Infrastructure Facility ( GIF )

More information

Global Financing Facility Grant Agreement

Global Financing Facility Grant Agreement Public Disclosure Authorized OFFICIAL DOCUMENTS GFF GRANT NUMBER TF0A2561 Public Disclosure Authorized Global Financing Facility Grant Agreement (Transforming Health Systems for Universal Care Project)

More information

DOCUMENTS GPOBA GRANT NUMBER TF Global Partnership on Output-based Aid. Grant Agreement

DOCUMENTS GPOBA GRANT NUMBER TF Global Partnership on Output-based Aid. Grant Agreement GPOBA GRANT NUMBER TF092629 DOCUMENTS Global Partnership on Output-based Aid Grant Agreement (Extending Telecommunications in Rural Indonesia Project) between REPUBLIC OF INDONESIA and INTERNATIONAL BANK

More information

Viet Nam: Second Small and Medium-Sized Enterprises Development Program

Viet Nam: Second Small and Medium-Sized Enterprises Development Program Validation Report December 2017 Viet Nam: Second Small and Medium-Sized Enterprises Development Program Reference Number: PVR-544 Program Numbers: 41360-013 and 41360-014 Loan Numbers: 2680 and 3050 ABBREVIATIONS

More information

Completion Report. Project Number: Loan Number: 2449-INO(SF) October Indonesia: Rural Infrastructure Support to the PNPM Mandiri Project

Completion Report. Project Number: Loan Number: 2449-INO(SF) October Indonesia: Rural Infrastructure Support to the PNPM Mandiri Project Completion Report Project Number: 40247 Loan Number: 2449-INO(SF) October 2012 Indonesia: Rural Infrastructure Support to the PNPM Mandiri Project CURRENCY EQUIVALENTS Currency Unit rupiah (Rp) At Appraisal

More information

Supplementary Appendix D 1

Supplementary Appendix D 1 Supplementary Appendix D 1 ENVIRONMENTAL ASSESSMENT OF FINANCIAL INTERMEDIATION LOANS AND EQUITY INVESTMENTS A. Description of the Development Bank of the Philippines (DBP) 1. DBP was established in 1947

More information

Policy Rules for the ORIO Grant Facility

Policy Rules for the ORIO Grant Facility Policy Rules for the ORIO Grant Facility Policy Rules grant facility ORIO 2012 1. What is ORIO?... 3 2. Definitions... 3 3. The role of infrastructure... 4 4. Implementation... 5 5. Target group... 5 6.

More information

COPY REGULATION OF THE MINISTER OF FINANCE OF THE REPUBLIC OF INDONESIA NUMBER 223/PMK.011/2012

COPY REGULATION OF THE MINISTER OF FINANCE OF THE REPUBLIC OF INDONESIA NUMBER 223/PMK.011/2012 COPY REGULATION OF THE MINISTER OF FINANCE OF THE REPUBLIC OF INDONESIA NUMBER 223/PMK.011/2012 CONCERNING SUPPORT FOR FEASIBILITY IN PARTIAL CONSTRUCTION EXPENSES IN COOPERATION PROJECTS BETWEEN THE GOVERNMENT

More information

World Bank Iraq Trust Fund Grant Agreement

World Bank Iraq Trust Fund Grant Agreement Public Disclosure Authorized Conformed Copy GRANT NUMBER TF054052 Public Disclosure Authorized World Bank Iraq Trust Fund Grant Agreement Public Disclosure Authorized (Emergency Disabilities Project) between

More information

Initial Proposal Approval Process, Including the Criteria for Programme and Project Funding (Progress Report)

Initial Proposal Approval Process, Including the Criteria for Programme and Project Funding (Progress Report) Initial Proposal Approval Process, Including the Criteria for Programme and Project Funding (Progress Report) GCF/B.06/08 11 February 2014 Meeting of the Board 19 21 February 2014 Bali, Indonesia Agenda

More information

REQUEST FOR PROPOSAL CITY OF PORT ARANSAS GAS DEPARTMENT FOR NATURAL GAS SUPPLY. RFP # Gas

REQUEST FOR PROPOSAL CITY OF PORT ARANSAS GAS DEPARTMENT FOR NATURAL GAS SUPPLY. RFP # Gas REQUEST FOR PROPOSAL BY CITY OF PORT ARANSAS GAS DEPARTMENT FOR NATURAL GAS SUPPLY RFP # Gas-20170501 Issue Date May 1, 2017 Questions Due Thursday, May 25, 2017 by 3pm Due Date & Time for Proposals Friday,

More information

MINISTRY OF HEALTH AND LONG-TERM CARE. Summary of Transfer Payments for the Operation of Public Hospitals. Type of Funding

MINISTRY OF HEALTH AND LONG-TERM CARE. Summary of Transfer Payments for the Operation of Public Hospitals. Type of Funding MINISTRY OF HEALTH AND LONG-TERM CARE 3.09 Institutional Health Program Transfer Payments to Public Hospitals The Public Hospitals Act provides the legislative authority to regulate and fund the operations

More information

Use of External Consultants

Use of External Consultants Summary Introduction The Department of Transportation and Works (the Department) is responsible for the administration, supervision, control, regulation, management and direction of all matters relating

More information

OBA Urban Sanitation Facility for the Greater Accra Metropolitan Area (GAMA) (P145139)

OBA Urban Sanitation Facility for the Greater Accra Metropolitan Area (GAMA) (P145139) Public Disclosure Authorized AFRICA Ghana Water Global Practice Recipient Executed Activities Investment Project Financing FY 2014 Seq No: 3 ARCHIVED on 10-May-2017 ISR25522 Implementing Agencies: Public

More information

EU Grant Agreement DOC8UMEW. Public Disclosure Authorized GRANT NUMBER TF0A2379. Public Disclosure Authorized. (Access to Sustainable Energy Project)

EU Grant Agreement DOC8UMEW. Public Disclosure Authorized GRANT NUMBER TF0A2379. Public Disclosure Authorized. (Access to Sustainable Energy Project) Public Disclosure Authorized DOC8UMEW GRANT NUMBER TF0A2379 Public Disclosure Authorized Public Disclosure Authorized EU Grant Agreement (Access to Sustainable Energy Project) between INTERNATIONAL BANK

More information

FEDERAL REPUBLIC OF NIGERIA

FEDERAL REPUBLIC OF NIGERIA Supplemental Letter No. 1 (Lagos Urban Transport Project) Section 9.02 of the General Conditions Financial and Economic Data In connection with the above Credit to the Republic of Nigeria for the Lagos

More information

Public Disclosure Copy. Implementation Status & Results Report Second Private Sector Competitiveness and Economic Diversification Prj (P144933)

Public Disclosure Copy. Implementation Status & Results Report Second Private Sector Competitiveness and Economic Diversification Prj (P144933) Public Disclosure Authorized AFRICA Lesotho Finance, Competitiveness and Innovation Global Practice IBRD/IDA Investment Project Financing FY 2014 Seq No: 10 ARCHIVED on 08-May-2018 ISR30476 Implementing

More information

Project Administration Instructions

Project Administration Instructions Project Administration Instructions PAI 1.01 Page 1 of 5 INITIAL PROJECT ADMINISTRATION ACTIVITIES A. Introduction 1. The Project Administration Instructions (PAIs) outline ADB s policies and procedures

More information

PROJECT PREPARATORY TECHNICAL ASSISTANCE

PROJECT PREPARATORY TECHNICAL ASSISTANCE 12 Appendix 5 A. Justification PROJECT PREPARATORY TECHNICAL ASSISTANCE 1. The project preparatory technical assistance (PPTA) is needed for preparing the investment program and conducting technical, economic,

More information

INDONESIA NATIONAL ROADS IMPROVEMENT PROJECT WESTERN INDONESIA PROJECT INFORMATION DOCUMENT CONCEPT STAGE Report No.:AB2075 Project Name

INDONESIA NATIONAL ROADS IMPROVEMENT PROJECT WESTERN INDONESIA PROJECT INFORMATION DOCUMENT CONCEPT STAGE Report No.:AB2075 Project Name INDONESIA NATIONAL ROADS IMPROVEMENT PROJECT WESTERN INDONESIA PROJECT INFORMATION DOCUMENT CONCEPT STAGE Report No.:AB2075 Project Name ID-National Roads Improvement Project Western Indonesia Region EAST

More information

Philippines: Health Sector Development Program

Philippines: Health Sector Development Program Completion Report Project Number: 33278 Loan Number: 2136/2137 August 2014 Philippines: Health Sector Development Program This document is being disclosed to the public in accordance with ADB's Public

More information

AUDIT UNDP BOSNIA AND HERZEGOVINA GRANTS FROM THE GLOBAL FUND TO FIGHT AIDS, TUBERCULOSIS AND MALARIA. Report No Issue Date: 15 January 2014

AUDIT UNDP BOSNIA AND HERZEGOVINA GRANTS FROM THE GLOBAL FUND TO FIGHT AIDS, TUBERCULOSIS AND MALARIA. Report No Issue Date: 15 January 2014 UNITED NATIONS DEVELOPMENT PROGRAMME AUDIT OF UNDP BOSNIA AND HERZEGOVINA GRANTS FROM THE GLOBAL FUND TO FIGHT AIDS, TUBERCULOSIS AND MALARIA Report No. 1130 Issue Date: 15 January 2014 Table of Contents

More information

Clarifications III. Published on 8 February A) Eligible countries. B) Eligible sectors and technologies

Clarifications III. Published on 8 February A) Eligible countries. B) Eligible sectors and technologies 5 th Call of the NAMA Facility Clarifications III Published on 8 February 2018 Contents A) Eligible countries...1 B) Eligible sectors and technologies...1 C) Eligible applicants...2 D) Eligible support

More information

Sri Lanka: Small and Medium-Sized Enterprises Line of Credit Project Additional Financing

Sri Lanka: Small and Medium-Sized Enterprises Line of Credit Project Additional Financing Small and Medium-Sized Enterprises Line of Credit Project-Additional Financing (RRP SRI 49273-003) Project Administration Manual Project Number: 49273-003 Loan Number: 3370 Technical Assistance Number:

More information

Strategic Fundraising Plan. for the. Gunnison Ranchland Conservation Legacy. July prepared by Susan Lohr

Strategic Fundraising Plan. for the. Gunnison Ranchland Conservation Legacy. July prepared by Susan Lohr Strategic Fundraising Plan for the Gunnison Ranchland Conservation Legacy July 1999 -prepared by Susan Lohr Lohr Associates, P.O. Box 1757, Crested Butte, CO 81224 Phone/fax (970)349-7416, email: slohr@crestedbutte.net

More information

Pacific Urban Development Investment Planning and Capacity Development Facility

Pacific Urban Development Investment Planning and Capacity Development Facility Technical Assistance Report Project Number: 51175-001 Transaction Technical Assistance Facility (F-TRTA) July 2017 Pacific Urban Development Investment Planning and Capacity Development Facility This document

More information

PROCUREMENT PLAN. Date of First Procurement Plan: 17 May 2012 Date of this Procurement Plan: 21 September 2012

PROCUREMENT PLAN. Date of First Procurement Plan: 17 May 2012 Date of this Procurement Plan: 21 September 2012 PROCUREMENT PLAN APPENDIX 4 Basic Data Project Name: Ho Chi Minh City Urban Mass Rapid Transit Line 2 Investment Program tranche 2 Country: Viet Nam Executing Agency: HCMC Peoples Committee (HCMC PC).

More information

Microfinance for Rural Piped Water Services in Kenya

Microfinance for Rural Piped Water Services in Kenya Policy Note No.1 Microfinance for Rural Piped Water Services in Kenya Using an Output-based Aid Approach for Leveraging and Increasing Sustainability by Meera Mehta and Kameel Virjee The water sector in

More information

CARIBBEAN DEVELOPMENT BANK PROCEDURES FOR THE SELECTION AND ENGAGEMENT OF CONSULTANTS BY RECIPIENTS OF CDB FINANCING

CARIBBEAN DEVELOPMENT BANK PROCEDURES FOR THE SELECTION AND ENGAGEMENT OF CONSULTANTS BY RECIPIENTS OF CDB FINANCING CARIBBEAN DEVELOPMENT BANK PROCEDURES FOR THE SELECTION AND ENGAGEMENT OF CONSULTANTS BY RECIPIENTS OF CDB FINANCING P.O. Box 408, Wildey, St. Michael BB11000 Barbados, West Indies Telex: WB 2287 Tel:

More information

Scaling-Up Energy Efficiency: The Case for a Super-ESCO

Scaling-Up Energy Efficiency: The Case for a Super-ESCO Scaling-Up Energy Efficiency: The Case for a Super-ESCO Dilip R. Limaye New Delhi January 2010 Need for ESCOs in Developing Countries A range of DSM and EE programs are being initiated, developed and promoted

More information

PROCUREMENT PLAN. Basic Data Project Name: Transport Connections in the Northern Mountainous Provinces Project

PROCUREMENT PLAN. Basic Data Project Name: Transport Connections in the Northern Mountainous Provinces Project PROCUREMET PLA Basic Data Project ame: Transport Connections in the orthern Mountainous Provinces Project Country: Socialist Republic of Viet am Executing Agency: 6 Provinces Loan Amount: $80,000,000 Loan

More information

Request for Proposals

Request for Proposals Request for Proposals Disparity Study PROPOSALS WILL BE RECEIVED UNTIL 12:00 Noon, Friday, July 27 th, 2018 in Purchasing Department, City Hall Building 101 North Main Street, Suite 324 Winston-Salem,

More information

FROM GRANTS TO GROUNDBREAKING:

FROM GRANTS TO GROUNDBREAKING: ISSUE BRIEF #10 FROM GRANTS TO GROUNDBREAKING: Unlocking Impact Investments An ImpactAssets issue brief exploring critical concepts in impact investing Jointly authored by Amy Chung of Living Cities with

More information

Global Partnership on Output-based Aid Grant Agreement

Global Partnership on Output-based Aid Grant Agreement Public Disclosure Authorized CONFORMED COPY GPOBA GRANT NUMBER TF096551-BD Public Disclosure Authorized Global Partnership on Output-based Aid Grant Agreement (Rural Electrification and Renewable Energy

More information

Fiduciary Arrangements for Grant Recipients

Fiduciary Arrangements for Grant Recipients Table of Contents 1. Introduction 2. Overview 3. Roles and Responsibilities 4. Selection of Principal Recipients and Minimum Requirements 5. Assessment of Principal Recipients 6. The Grant Agreement: Intended

More information

Global Partnership on Output-based Aid Grant Agreement

Global Partnership on Output-based Aid Grant Agreement Public Disclosure Authorized GPOBA GRANT NUMBER TF010757 Public Disclosure Authorized Public Disclosure Authorized Global Partnership on Output-based Aid Grant Agreement (Philippines Public Health Project)

More information

PROJECT INFORMATION DOCUMENT (PID) CONCEPT STAGE Report No.: AB7052

PROJECT INFORMATION DOCUMENT (PID) CONCEPT STAGE Report No.: AB7052 Project Name Region Country Sector(s) Lending Instrument Project ID Borrower(s) Implementing Agency Environmental Category Date PID Prepared Estimated Date of Appraisal Completion Estimated Date of Board

More information

FOR OFFICIAL USE ONLY RESTRUCTURING PAPER ON A

FOR OFFICIAL USE ONLY RESTRUCTURING PAPER ON A Public Disclosure Authorized Document of The World Bank FOR OFFICIAL USE ONLY Report No: RES22380 Public Disclosure Authorized Public Disclosure Authorized RESTRUCTURING PAPER ON A PROPOSED PROJECT RESTRUCTURING

More information

THE GLOBAL FUND to Fight AIDS, Tuberculosis and Malaria

THE GLOBAL FUND to Fight AIDS, Tuberculosis and Malaria THE GLOBAL FUND to Fight AIDS, Tuberculosis and Malaria Guidelines for Performance-Based Funding Table of Contents 1. Introduction 2. Overview 3. The Grant Agreement: Intended Program Results and Budget

More information

STATE OF MINNESOTA CAPITAL GRANTS MANUAL. A step-by-step guide that describes what grantees need to do to receive state capital grant payments

STATE OF MINNESOTA CAPITAL GRANTS MANUAL. A step-by-step guide that describes what grantees need to do to receive state capital grant payments STATE OF MINNESOTA CAPITAL GRANTS MANUAL A step-by-step guide that describes what grantees need to do to receive state capital grant payments Revised March 2010 The State of Minnesota Capital Grants Manual

More information

Regional: Supporting the Cities Development Initiative for Asia

Regional: Supporting the Cities Development Initiative for Asia Technical Assistance Report Project Number: 47285 Regional Capacity Development Technical Assistance (R-CDTA) November 2013 Regional: Supporting the Cities Development Initiative for Asia (Cofinanced by

More information

Procedure: PR/IN/04 May 21,2012. Procedure: Accreditation of GEF Project Agencies

Procedure: PR/IN/04 May 21,2012. Procedure: Accreditation of GEF Project Agencies Procedure: PR/IN/04 May 21,2012 Procedure: Accreditation of GEF Project Agencies 1 Summary: This paper sets forth the key procedures for the accreditation of GEF Project Agencies. Background: The present

More information

The World Bank Vietnam Climate Innovation Center (VCIC) RETF (P155260)

The World Bank Vietnam Climate Innovation Center (VCIC) RETF (P155260) Public Disclosure Authorized Public Disclosure Authorized The World Bank RESTRUCTURING PAPER ON A PROPOSED PROJECT RESTRUCTURING OF VIETNAM CLIMATE INNOVATION CENTER (VCIC) RETF APPROVED ON OCTOBER 30,

More information

Grant Assistance for Grassroots Human Security Projects. Embassy of Japan to the Independent State of Samoa

Grant Assistance for Grassroots Human Security Projects. Embassy of Japan to the Independent State of Samoa Grant Assistance for Grassroots Human Security Projects Guidelines GUIDELINES: GRANT ASSISTANCE FOR GRASSROOTS HUMAN SECURITY PROJECTS (GGP) Embassy of Japan to the Independent State of Samoa The Japanese

More information

KECAMATAN DEVELOPMENT PROJECT *

KECAMATAN DEVELOPMENT PROJECT * Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized I. Abstract KECAMATAN DEVELOPMENT PROJECT * The World Bank aided Kecamatan Development

More information

GRANT AGREEMENT (ADB Strategic Climate Fund) (Greater Mekong Subregion Biodiversity Conservation Corridors Project Additional Financing)

GRANT AGREEMENT (ADB Strategic Climate Fund) (Greater Mekong Subregion Biodiversity Conservation Corridors Project Additional Financing) GRANT NUMBER 0426-CAM (SCF) GRANT AGREEMENT (ADB Strategic Climate Fund) (Greater Mekong Subregion Biodiversity Conservation Corridors Project Additional Financing) (Cambodia Component) between KINGDOM

More information

Financing Agreement. (Zanzibar Basic Education Improvement Project) between THE UNITED REPUBLIC OF TANZANIA. and

Financing Agreement. (Zanzibar Basic Education Improvement Project) between THE UNITED REPUBLIC OF TANZANIA. and Public Disclosure Authorized CONFORMED COPY CREDIT NUMBER 4293-TA Public Disclosure Authorized Financing Agreement (Zanzibar Basic Education Improvement Project) between Public Disclosure Authorized THE

More information

Case study: System of households water use subsidies in Chile.

Case study: System of households water use subsidies in Chile. Case study: System of households water use subsidies in Chile. 1. Description In Chile the privatization of public water companies during the 70 s and 80 s resulted in increased tariffs. As a consequence,

More information

Technical Assistance to the Republic of Philippines for the Support for Health Sector Reform

Technical Assistance to the Republic of Philippines for the Support for Health Sector Reform Technical Assistance TAR: PHI 39066 Technical Assistance to the Republic of Philippines for the Support for Health Sector Reform September 2005 CURRENCY EQUIVALENTS (as of 5 August 2005) Currency Unit

More information

FOR OFFICIAL USE ONLY RESTRUCTURING PAPER ON A

FOR OFFICIAL USE ONLY RESTRUCTURING PAPER ON A Public Disclosure Authorized Document of The World Bank FOR OFFICIAL USE ONLY Report No: RES22379 Public Disclosure Authorized Public Disclosure Authorized RESTRUCTURING PAPER ON A PROPOSED PROJECT RESTRUCTURING

More information

ETHIOPIA : GENALE-DAWA RIVER BASIN INTEGRATED RESOURCES DEVELOPMENT MASTER PLAN STUDY* PROJECT COMPLETION REPORT*

ETHIOPIA : GENALE-DAWA RIVER BASIN INTEGRATED RESOURCES DEVELOPMENT MASTER PLAN STUDY* PROJECT COMPLETION REPORT* ETHIOPIA : GENALE-DAWA RIVER BASIN INTEGRATED RESOURCES DEVELOPMENT MASTER PLAN STUDY* PROJECT COMPLETION REPORT* *Questions on this document should be referred to: Mr. A.A. ABOU SABAA Director OSAN Ext.

More information

SECTION 3 POLICY & PROGRAM

SECTION 3 POLICY & PROGRAM SECTION 3 POLICY & PROGRAM 8120 Kinsman Road, Cleveland, Ohio 44104 Phone: 216-348-5000 Jeffery K. Patterson Chief Executive Officer TABLE OF CONTENTS Section Page # Section 3 POLICY Statement of Policy

More information

GOVERNMENT OF MAURITIUS MANUFACTURING AND SERVICES DEVELOPMENT AND COMPETITIVENESS PROJECT (MSDC) LOAN NO MU PROCUREMENT PLAN FOR THE PERIOD

GOVERNMENT OF MAURITIUS MANUFACTURING AND SERVICES DEVELOPMENT AND COMPETITIVENESS PROJECT (MSDC) LOAN NO MU PROCUREMENT PLAN FOR THE PERIOD Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized GOVERNMENT OF MAURITIUS MINISTRY OF BUSINESS, ENTERPRISES AND COOPERATIVES MANUFACTURING

More information

Economic and Social Council

Economic and Social Council UNITED NATIONS E Economic and Social Council Distr. GENERAL ECE/ENERGY/WP.4/2009/8 24 March 2009 Original: ENGLISH ECONOMIC COMMISSION FOR EUROPE COMMITTEE ON SUSTAINABLE ENERGY Steering Committee of the

More information

Cook Islands

Cook Islands \ Country Operations Business Plan October 2016 Cook Islands 2017 2019 This document is being disclosed to the public in accordance with ADB s Public Communications Policy 2011. CURRENCY EQUIVALENTS (as

More information

Republic of Indonesia: Water Supply and Sanitation Sector Development Project

Republic of Indonesia: Water Supply and Sanitation Sector Development Project Technical Assistance Report Project Number: 43304-022 Capacity Development Technical Assistance (CDTA) November 2011 Republic of Indonesia: Water Supply and Sanitation Sector Development Project (Financed

More information

KENYA ROADS BOARD FOR FINANCIAL YEARS 2018/19 TO 2020/21. TENDER No. KRB/922/2018/2019 JULY 2018

KENYA ROADS BOARD FOR FINANCIAL YEARS 2018/19 TO 2020/21. TENDER No. KRB/922/2018/2019 JULY 2018 KENYA ROADS BOARD RE-ADVERTISEMENT FOR EXPRESSION OF INTEREST (EOI) FOR PROVISION OF TECHNICAL, FINANCIAL AND PERFORMANCE AUDIT CONSULTANCY SERVICES FOR KENYA ROADS BOARD FOR FINANCIAL YEARS 2018/19 TO

More information

III. The provider of support is the Technology Agency of the Czech Republic (hereafter just TA CR ) seated in Prague 6, Evropska 2589/33b.

III. The provider of support is the Technology Agency of the Czech Republic (hereafter just TA CR ) seated in Prague 6, Evropska 2589/33b. III. Programme of the Technology Agency of the Czech Republic to support the development of long-term collaboration of the public and private sectors on research, development and innovations 1. Programme

More information

DIME-GAFSP First Quarterly Progress Report

DIME-GAFSP First Quarterly Progress Report DIME-GAFSP First Quarterly Progress Report Feburary 24, 2012 The World Bank s Development Impact Evaluation Initiative (DIME) has been contracted to lead in-depth impact evaluations on a subset of GAFSP

More information

Terms of Reference AUDIT OF SOLAR HOME SYSTEMS PROJECT. The assignment is to engage an auditor for the following.

Terms of Reference AUDIT OF SOLAR HOME SYSTEMS PROJECT. The assignment is to engage an auditor for the following. Note: Bank solar home systems projects receiving grant funds from the Global Environment Facility (GEF) are normally required to have their records and accounts audited by an independent entity each fiscal

More information

Country Operations Business Plan. Samoa October 2016

Country Operations Business Plan. Samoa October 2016 Country Operations Business Plan October 2016 Samoa 2017 2019 This document is being disclosed to the public in accordance with ADB's Public Communications Policy 2011. CURRENCY EQUIVALENTS (As of 26

More information

Office of the Inspector General Department of Defense

Office of the Inspector General Department of Defense o0t DISTRIBUTION STATEMENT A Approved for Public Release Distribution Unlimited FOREIGN COMPARATIVE TESTING PROGRAM Report No. 98-133 May 13, 1998 Office of the Inspector General Department of Defense

More information

European Association of Public Banks

European Association of Public Banks DG Competition stateaidgreffe@ec.europa.eu HT 618 Register-ID : 8754829960-32 24 February 2012 EAPB comments on the Consultation Paper on the Research, Development and Innovation State aid Framework Dear

More information

Trust Fund Grant Agreement

Trust Fund Grant Agreement Public Disclosure Authorized CONFORMED COPY GRANT NUMBER TF057872-GZ Public Disclosure Authorized Trust Fund Grant Agreement (Palestinian NGO-III Project) Public Disclosure Authorized between INTERNATIONAL

More information

Appendix VI: Developing and Writing Grant Proposals

Appendix VI: Developing and Writing Grant Proposals Appendix VI: Developing and Writing Grant Proposals PART ONE: DEVELOPING A GRANT PROPOSAL Preparation A successful grant proposal is one that is well-prepared, thoughtfully planned, and concisely packaged.

More information

United Nations Peace Building Fund Grant Agreement

United Nations Peace Building Fund Grant Agreement Public Disclosure Authorized OFFICIAL DOCUMENTS Public Disclosure Authorized GRANT NUMBER TF018255 United Nations Peace Building Fund Grant Agreement (Additional Financing for the Productive Social Safety

More information

Proposed Grant Assistance Kyrgyz Republic: Improving Livelihoods of Rural Women through Development of Handicrafts Industry

Proposed Grant Assistance Kyrgyz Republic: Improving Livelihoods of Rural Women through Development of Handicrafts Industry Grant Assistance Report Project Number: 40539 November 2006 Proposed Grant Assistance Kyrgyz Republic: Improving Livelihoods of Rural Women through Development of Handicrafts Industry (Financed by the

More information

STANDARD TERMS AND CONDITIONS ON NORWAY GRANTS FROM INNOVATION NORWAY

STANDARD TERMS AND CONDITIONS ON NORWAY GRANTS FROM INNOVATION NORWAY STANDARD TERMS AND CONDITIONS ON NORWAY GRANTS FROM INNOVATION NORWAY 1 Scope of the Project Contract The Grant to the Project Promoter is offered on the terms and conditions laid down in the Grant Offer

More information

Republic of Tajikistan Dushanbe-Uzbekistan Border Road Improvement Project

Republic of Tajikistan Dushanbe-Uzbekistan Border Road Improvement Project PD 0002-TJK June 6, 2016 PROJECT DOCUMENT Republic of Tajikistan Dushanbe-Uzbekistan Border Road Improvement Project This document has a restricted distribution and may be used by recipients only in performance

More information

Navy Officials Did Not Consistently Comply With Requirements for Assessing Contractor Performance

Navy Officials Did Not Consistently Comply With Requirements for Assessing Contractor Performance Inspector General U.S. Department of Defense Report No. DODIG-2015-114 MAY 1, 2015 Navy Officials Did Not Consistently Comply With Requirements for Assessing Contractor Performance INTEGRITY EFFICIENCY

More information

Public Disclosure Copy

Public Disclosure Copy Public Disclosure Authorized AFRICA Ethiopia Finance & Markets Global Practice IBRD/IDA Investment Project Financing FY 2016 Seq No: 4 ARCHIVED on 06-Dec-2017 ISR30229 Implementing Agencies: National Bank

More information

Global Partnership on Output-based Aid Grant Agreement

Global Partnership on Output-based Aid Grant Agreement Global Partnership on Output-based Aid GRANT NUMBERS TF057614 AND TF057615 Global Partnership on Output-based Aid Grant Agreement (Kenya - Microfinance for Community-Managed Water Projects) between K-REP

More information

Creating a Patient-Centered Payment System to Support Higher-Quality, More Affordable Health Care. Harold D. Miller

Creating a Patient-Centered Payment System to Support Higher-Quality, More Affordable Health Care. Harold D. Miller Creating a Patient-Centered Payment System to Support Higher-Quality, More Affordable Health Care Harold D. Miller First Edition October 2017 CONTENTS EXECUTIVE SUMMARY... i I. THE QUEST TO PAY FOR VALUE

More information

IAF Guidance on the Application of ISO/IEC Guide 61:1996

IAF Guidance on the Application of ISO/IEC Guide 61:1996 IAF Guidance Document IAF Guidance on the Application of ISO/IEC Guide 61:1996 General Requirements for Assessment and Accreditation of Certification/Registration Bodies Issue 3, Version 3 (IAF GD 1:2003)

More information

Program Management Plan

Program Management Plan Program Management Plan Section 5310 ENHANCED MOBILITY OF SENIORS AND INDIVIDUALS WITH DISABILITIES PROGRAM Table of Contents GOALS AND OBJECTIVES... 3 ROLES AND RESPONSIBILITIES OF VIA... 3 ALAMO AREA

More information

PPIAF Assistance in Nepal

PPIAF Assistance in Nepal Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized PPIAF Assistance in Nepal June 2012 The Federal Democratic Republic of Nepal (Nepal)

More information

I 2 Program Frequently Asked Questions

I 2 Program Frequently Asked Questions I 2 Program Frequently Asked Questions What is the Genome BC Industry Innovation (I 2 ) Program? The I 2 Program offers repayable growth capital to businesses (with less than 500 employees), commercializing

More information

WIPO REGIONAL SEMINAR ON SUPPORT SERVICES FOR INVENTORS, VALUATION AND COMMERCIALIZATION OF INVENTIONS AND RESEARCH RESULTS

WIPO REGIONAL SEMINAR ON SUPPORT SERVICES FOR INVENTORS, VALUATION AND COMMERCIALIZATION OF INVENTIONS AND RESEARCH RESULTS WIPO/INV/MNL/98/8 ORIGINAL: English DATE: November 1998 E TECHNOLOGY APPLICATION AND PROMOTION INSTITUTE WORLD INTELLECTUAL PROPERTY ORGANIZATION WIPO REGIONAL SEMINAR ON SUPPORT SERVICES FOR INVENTORS,

More information

ADB Business Opportunities Seminar

ADB Business Opportunities Seminar ADB Business Opportunities Seminar 4 November 2016 Vienna, Austria Presented by Walter Poick Director, Procurement Division 2 (East Asia, Southeast Asia and Pacific Operations) Operations Services and

More information

Trust Fund Grant Agreement

Trust Fund Grant Agreement Public Disclosure Authorized CONFORMED COPY GRANT NUMBER TF094521 GZ Public Disclosure Authorized Trust Fund Grant Agreement (Additional Financing for the Palestinian NGO-III Project) Public Disclosure

More information

Report to Congress. June Deputy Under Secretary of Defense (Installations and Environment)

Report to Congress. June Deputy Under Secretary of Defense (Installations and Environment) Report to Congress Demonstration Program to Accelerate Design Efforts for Military Construction Projects Carried Out Using Design-Build Selection Procedures June 2008 Deputy Under Secretary of Defense

More information

CRS Report for Congress

CRS Report for Congress Order Code RS22162 June 9, 2005 CRS Report for Congress Received through the CRS Web Summary The World Bank: The International Development Association s 14 th Replenishment (2006-2008) Martin A. Weiss

More information

Afghanistan Reconstruction Trust Fund Grant Agreement

Afghanistan Reconstruction Trust Fund Grant Agreement Public Disclosure Authorized OFFICIAL DOCUMENTS ARTF GRANT NUMBER TFOAO730 Public Disclosure Authorized Public Disclosure Authorized Afghanistan Reconstruction Trust Fund Grant Agreement (Higher Education

More information

P4: PACIFIC REGIONAL ICT REGULATORY DEVELOPMENT PROJECT APPROVED ON JULY 30, 2014 UNIVERSITY OF THE SOUTH PACIFIC

P4: PACIFIC REGIONAL ICT REGULATORY DEVELOPMENT PROJECT APPROVED ON JULY 30, 2014 UNIVERSITY OF THE SOUTH PACIFIC Public Disclosure Authorized The World Bank DOCUMENT OF THE WORLD BANK REPORT NO.: RES29928 Public Disclosure Authorized Public Disclosure Authorized RESTRUCTURING PAPER ON A PROPOSED PROJECT RESTRUCTURING

More information

Pakistan: Punjab Community Water Supply and Sanitation Sector Project

Pakistan: Punjab Community Water Supply and Sanitation Sector Project Validation Report Reference Number: PCV: PAK 2009-48 Project Number: 35314 Loan Number: 1950-PAK(SF) December 2009 Pakistan: Punjab Community Water Supply and Sanitation Sector Project Independent Evaluation

More information