Quarterly Progress Report on Strategic Initiatives July to September 2013

Similar documents
Quarterly Progress Report on Corporate Strategic Initiatives

A. Executive Summary...3. B. Initiatives and Status at a Glance...4

CITY OF VICTORIA. Strategic Plan. (Amended February 2016 and January 2017)

Version 2.0 Revisions approved by Council on January 29, 2017

Strategic Plan

Age-friendly Communities

Municipal Interests in Liquor Licensing

Chester County Vision Partnership Grant Program January 2017

VALUE FOR SERVICE RESIDENTIAL PROPERTY TAX. Results for the Community

Town of the Blue Mountains Community Improvement Plan

Asset Management Planning Program Program & Application Guide

Regina Community Grants Program

Seawall Earthquake Safety + Disaster Prevention Program Community Meeting June 21, 2018

Local Economy Directions Paper

CITY OF LOS ANGELES INTER-DEPARTMENTAL CORRESPONDENCE

Friday, June 21, 13. Building better communities through the arts

Project Report: Achieving Value for Money Charles Jago Northern Sport Centre

City of Edina, Minnesota GrandView Phase I Redevelopment, 5146 Eden Avenue Request for Interest for Development Partner

Smithsonian Institution

OUR COMMUNITY VISION OUR CORPORATE MISSION. Together, we will build an innovative, caring and vibrant Kitchener.

Request for Proposals

Brownfield Redevelopment CIP Performance:

Status of Implementing Legislation Regarding the Eastern Band of Cherokee Indians

Project Proposal Project A7-2009

BLUE HILLS MASTER PLAN RFP OUTLINE

GEORGE MASSEY TUNNEL REPLACEMENT PROJECT

CITY OF NELSON SUSTAINABILITY CHECKLIST

City of Saint John Growth Committee - Open Session AGENDA

ir TA1T T1A7 L- cillor Item No Halifax Regional Council April 23, 2013 Mayor Savaae and Members of Halifax Regional Council TO: SUBMITTED BY:

REGIONAL TRANSIT FEASIBILITY PLAN

Application: City of Port Coquitlam

Quality Improvement Plan (QIP) Narrative for Health Care Organizations in Ontario

Attachment A: Q3 Operational Plan Progress Report. Legend: On Track Some Challenges Major Challenges Complete Inactive

Guidelines for Proposed Donations of Public Art and Monuments to the City of Toronto

Improving the Chemotherapy Appointment Experience at the BC Cancer Agency

Distinctly Boerne! Boerne Master Plan ( ) JOINT MEETING OVERVIEW & PRIORITIZATION

ONTARIO SENIORS SECRETARIAT SENIORS COMMUNITY GRANT PROGRAM GUIDELINES

Request for Proposals # P12-044A. Pre-Qualification - Purchase and. Development of Bloomfield Property

Sewer System Improvement Program

Chesapeake Conservation Corps Host Organization Application Instructions

REQUEST FOR PROPOSALS

Economic Development Element

1. INTRODUCTION & OVERVIEW

BUILDING MARKHAM S FUTURE TOGETHER. Summary of Public Engagement & Research

The CRD Arts Service Strategic Plan

City of Tacoma Community & Economic Development Department Business Plan: Prosperity on Purpose for the City of Destiny*

Understanding Opportunities Available Through International Financial Institutions

1.2 All Expressions of Interest should provide a digital copy of their complete proposal in MS Office Word 2003 (or newer) or pdf format.

JANUARY 2018 (21 work days) FEBRUARY 2018 (19 work days)

PUBLIC PROJECT 2011 APPLICATION FOR URBAN DESIGN REVIEW BOARD City of Des Moines, Iowa

PROGRAM GUIDELINES LOCAL GOVERNMENT MANAGEMENT INTERNSHIP

PLANNING DEPARTMENT ADMINISTRATION

Kitchener Public Art Five-Year Plan

STATISTICAL PRESS NOTICE MONTHLY CRITICAL CARE BEDS AND CANCELLED URGENT OPERATIONS DATA, ENGLAND March 2018

Strategic Plan update

Midwestern Sustainability: The Wright Fit. Shirley Liu Tasha Beghtol Francis Waisath Menno Schukking

Public Art Policy Markham Municipal Projects

Economic Development Element of the Arroyo Grande General Plan. Prepared by the City of Arroyo Grande Community Development Department

BOROUGH OF ROSELLE PUBLIC NOTICE ANNUAL NOTICE OF CALENDAR YEAR 2018 WORKSHOP SESSIONS, PRE-AGENDA MEETINGS AND REGULAR MEETINGS

Business Plan: Parks and Natural Areas Planning & Design

REGULAR MEETING OF CITY COUNCIL AGENDA

Camp SEA Lab. Strategic Plan July June Adopted 7/17/2013 by the Friends of Camp SEA Lab Board of Directors

Driving Quality Improvement in Managed Care. Toby Douglas, Director California Department of Health Care Services

Report Purpose To provide the Priorities Committee with an update on the Municipal Development Plan (MDP) update process and public engagement.

Business Accelerator Operator Request for Proposals. Release Date: March 14, 2017

1.1 Charitable Fundraising Strategy

LAND PARTNERSHIPS GRANT PROGRAM. PROGRAM GUIDELINES April 2018

Central City Line Kick-off and Tour

City of Nampa Strategic Plan. Adopted December 19, 2011

BC Rural Dividend Program Guide

Accreditation Support for Ohio Local Health Districts Request for Training or Technical Assistance - Round 1 The Ohio Department of Health

Compliance Division Staff Report

Downtown Revitalization. Strategic Action Plan

Canby Façade Improvement Program

City of Terrace Economic Development Strategy

Petaluma City Council Goals and Priorities for 2017 and 2018

Community Grant Guidelines

SAMPLE DOCUMENT. Implementation or operational plan

Oregon John A. Kitzhaber, M.D., Governor

INDUSTRY - SUSTAINABILITY - INNOVATION ECONOMIC DEVELOPMENT STRATEGY

National Exercise Program (NEP) Overview. August 2009

REQUEST FOR PROPOSAL CITY OF PORT ARANSAS GAS DEPARTMENT FOR NATURAL GAS SUPPLY. RFP # Gas

New York s Great Lakes Basin Small Grants Program 2014 Request for Proposals

BC Rural Dividend Program Guide

Presentation to Community Planning and Economic Development Standing Committee July 20th, 2017

T O W N O F M I D L A N D MIDLAND BAY LANDING A MIDLAND WATERFRONT DEVELOPMENT OPPORTUNITY

The hallmarks of the Global Community Engagement and Resilience Fund (GCERF) Core Funding Mechanism (CFM) are:

Request for Proposals ALICE Impact Funding

CITY OF WALDPORT GOALS. A) Complete MOU for former HS Open Space Project Pending receipt of final $11,000 from LCSD for feasibility study

Winnipeg Regional Health Authority. Community Development Healthy Aging

KANSAS CITY REGIONAL TIGER PROJECT PMOC PROGESS REPORT 2014 Fiscal Quarter 1 October 1 December 31, 2013

Port Botany Terminal Q. Environmental Management System. Community Feedback Quarterly Report. Reporting Period: 1 April to 30 June 2018

Multi Use Entertainment Venue Venue Development Agreement Discussion

MONTHLY JOB VACANCY STUDY 2016 YEAR IN REVIEW PARRY SOUND DISTRICT MONTHLY JOB VACANCY STUDY YEAR IN REVIEW - PARRY SOUND DISTRICT

Economic Development Concept Plan

On May 21, the TPB approved

Age-Friendly Newfoundland and Labrador: Community Grants Application Guidelines

CITY OF ABBOTSFORD PERMISSIVE PROPERTY TAX EXEMPTION. Policy No. C REVISIONS. Revision No. Date Approved Description

Port Botany Terminal Q. Environmental Management System. Community Feedback Quarterly Report. Reporting Period: 1 July to 30 September 2018

Heritage Action Plan Character Home Zoning Review. Public Consultation Update Presentation to City Council March 7, 2017

Transcription:

Quarterly Progress Report on Strategic Initiatives July to September 2013 July to September 2013 Quarterly Progress Report Page 1

Table of Contents A. Executive Summary... 4 B. Initiatives and at a Glance... 5 C. Initiative Summaries... 7 1. Implement Customer Service Action Plan... 7 2. Make Continuous Improvements to Governance... 9 3. Review Organizational Structure... 11 4. Pursue Naming Rights for Victoria Conference Centre... 12 5. Review Parking Services... 13 6. Introduce Open Initiatives... 14 7. Finalize Official Community Plan and Local Area Planning Implementation Strategy... 16 8. Manage 120 Gorge Road Affordable Housing Project... 17 9. Examine and Improve Public Transportation Options... 18 10. Introduce Housing Initiatives... 20 11. Renovate or Replace Fire Hall #1... 22 12. Implement Esquimalt Policing Decision... 24 13. Develop Options for Crystal Pool and Fitness Centre... 25 14. Implement Economic Development Strategy... 27 15. Develop a Feasibility Study and Business Case for Harbour Waterfront Revitalization... 29 16. Establish New Downtown Zones and Integrate Density Bonus System... 30 17. Replace Johnson Street Bridge... 31 18. Pilot and Evaluate Transportation Changes in Beacon Hill Park... 33 19. Develop Asset Management Framework and Implementation Plan... 35 20. Maximize Opportunities from Sewage Treatment Infrastructure Construction... 36 D. Other Accomplishments this Quarter... 37 July to September 2013 Quarterly Progress Report Page 2

About this Report The purpose of this report is to update Council on the status of those initiatives that have been identified as priorities for the organization to the end of 2015. The content of the report will change from quarter to quarter as new initiatives are started and others completed. This report is not meant to be a complete description of the work performed by City staff during the quarter. Staff are also engaged in delivering core services and participating in other significant initiatives. The City of Victoria Strategic Plan for 2013 to 2015 groups strategies and key initiatives under four strategic areas: focuses on Council decision making and the organization s performance. Our Community concentrates on issues of livability and social well-being. focuses on what is needed to encourage economic growth and vitality. Our Environment targets our ability to protect and sustain the environment and reduce our ecological impact. As shown in the figure above, these strategic areas are not mutually exclusive. Although initiatives are grouped in this report under the most relevant of these four strategic areas, many support achievement of goals in multiple areas. This report has three sections: Initiatives and at a Glance is a snapshot of the current status of initiatives. The status reflects whether any changes in objectives, scope, resources or timelines have occurred since Council was last updated on the project. Initiative Summaries comprise the bulk of the report. These are summaries of each initiative, highlighting its contribution to the Strategic Plan for 2013 to 2015, the objectives of the project, and project phases and timeline. An explanation of each project s status can also be found in this section. Other Accomplishments this Quarter recognizes notable accomplishments from the quarter that may not be associated with an initiative featured in the report, but demonstrate significant progress in reaching the goals and strategies outlined in the Strategic Plan. Our Service Principles emphasize our commitment to accountability. We are: Open and Accountable: We listen, continually measure our performance and communicate the results. This document is one means for staff to demonstrate our commitment to accountability, sustainability, and willingness to take responsibility for our actions. As noted in the Strategic Plan for 2013 to 2015, this shared commitment is at the centre of the relationship between Council, staff and the community and enables us to work together to make the vision outlined in that Plan a reality. July to September 2013 Quarterly Progress Report Page 3

A. Executive Summary This document is an update from the City Manager to Council on the progress of strategic initiatives for the period from July 1 to September 30, 2013. Several initiatives were completed over the past quarter. The review of the City s organizational structure was completed and changes implemented. Webcasting was launched in September 2013, with live streaming available to the public for the October 3, 2013 Planning and Land Use and Governance and Priorities Committee meetings. Also in September, Council approved the Official Community Plan Implementation Strategy, which will serve as the basis for initiating and coordinating various actions required to achieve the Official Community Plan. The majority of remaining initiatives have a green status, with no changes to project plans since Council was last updated on their status. A number of initiatives experienced significant milestones this quarter: progress has been made on governance discussions, which are now scheduled for completion this month the pursuit of naming rights for the Victoria Conference Centre moved from in planning status, with a naming rights broker engaged and a feasibility study anticipated in January 2014 the pilot period for transportation changes in Beacon Hill Park concluded in September, with an evaluation of the results planned for vember, and the preliminary concept for public realm improvements along Dallas Road was presented to Council in July. Staff will begin public consultation on this preliminary concept in October. Six initiatives have experienced timeline shifts and have been assigned a yellow status. These are: Manage 120 Gorge Road Affordable Housing Project partners continue their review of legal contracts and the date for transfer of the property remains unknown Examine and Improve Public Transportation Options development of the Cycling Task Force Project Charter took longer than anticipated and now will be presented to Council in vember Introduce Housing Initiatives timelines for the first two project phases have been extended Renovate or Replace Fire Hall #1 options will now be presented to Council in Quarter 4 of this year Establish New Downtown Zones and Integrate Density Bonus System the first phase of this project, which is the development of new zones for the Central Business District, will now be completed in June, rather than March, 2014, and Develop Asset Management Framework and Implementation Plan the Implementation Plan will now be presented to Council in January 2014. The Other Accomplishments section of this report highlights a wide range of activities. This past quarter marked the end of the busy summer festival season, with events ranging from Canada Day festivities to Culture Days in the Square. July to September 2013 Quarterly Progress Report Page 4

B. Initiatives and at a Glance 1. Initiative Implement Customer Service Action Plan City Hall Renovations Public Service Counter Business Licensing Land Development Permits and Inspections Estimated Completion Date October 2013 June 2014 January 2016 December 2014 Ongoing 2. Make Continuous Improvements to Governance TBD 3. Review Organizational Structure August 2013 4. Pursue Naming Rights for Victoria Conference Centre April 2014 5. Review Parking Services January 2014 6. Introduce Open Initiatives Webcasting September 2013 Our Community 7. 8. 9. Finalize Official Community Plan and Local Area Planning Implementation Strategy Manage 120 Gorge Road Affordable Housing Project Examine and Improve Public Transportation Options Transit Cycling September 2013 TBD TBD TBD 10. Introduce Housing Initiatives October 2015 11. Renovate or Replace Fire Hall #1 TBD 12. Implement Esquimalt Policing Decision December 2013 Develop Options for Crystal Pool and Fitness 13. Centre June 2014 14. Implement Economic Development Strategy ED contract ends June 2015 15. Develop a Feasibility Study and Business Case for Harbour Waterfront Revitalization Establish New Downtown Zones and Integrate 16. Density Bonus System Our Environment Project Charter Quarter 4 of 2013 Central Business District zones June 2014 17. Replace Johnson Street Bridge Q1 2016 18. 19. 20. Pilot and Evaluate Transportation Changes in Beacon Hill Park Develop Asset Management Framework and Implementation Plan Maximize Opportunities from Sewage Treatment Infrastructure Construction Evaluation vember 2013 Implementation Plan January 2014 Software Acquisition June 2014 Concept approval May 2014 Implementation TBD July to September 2013 Quarterly Progress Report Page 5

STATUS KEY In planning phase changes to project plan since last reporting date Minor changes to project plan since last reporting date, no significant change in overall objectives/scope, schedule or resources required Major change in objectives/scope, schedule or resources since last reporting date Completed July to September 2013 Quarterly Progress Report Page 6

C. Initiative Summaries 1. Implement Customer Service Action Plan Our Community Examine key permit and licensing functions to ensure that customer service and internal efficiency are maximized Our Environment Improve customer service Increase access to City information and services Engineering and Public Works, Legislative and Regulatory Services, Sustainable Planning and Community Development, Communications and Civic Engagement (overall Action Plan lead) City Hall renovations require: ongoing construction management contract with Durwest and contracts with various subcontractors services of Graphic Office Interiors Ltd. to supply and install furniture systems ongoing professional services from Chow, Low, Hammond Architects and various subcontractors Have the objectives or scope of the project changed? Reconstruction of the Public Service Counter has been added as a project phase Have the resources required to complete the project changed? Has the timeline for the project changed? Yes Renovate City Hall 2011 October 2013 Reconstruct Public Service Counter September 2013 June 2014 Implement enhanced Land Development business processes 2012 December 2014 Improve Business Licensing process and update bylaw September 2012 January 2016 Implement enhanced Permits and Inspections business processes 2011 Ongoing July to September 2013 Quarterly Progress Report Page 7

Timeline October 2013 City Hall renovated December 2014 Land Development business processes enhanced January 2016 Business Licence Bylaw updated Jan-13 Jan-14 Jan-15 Jan-16 May 2013 Business Licensing process improved and function moved to Development Centre June 2014 Public Service Counter reconstructed Ongoing Permits and Inspections business processes enhanced July to September 2013 Quarterly Progress Report Page 8

2. Make Continuous Improvements to Governance Our Community Enhance information sharing among Council, staff and the public to promote citizen and staff engagement and facilitate informed decision-making Our Environment Improve role definition for elected officials and staff Improve organizational efficiency and effectiveness Improve public understanding of governance model Legislative and Regulatory Services Have the objectives or scope of the project changed? Have the resources required to complete the project changed? Has the timeline for the project changed? Estimated completion dates for initial phases are now known Yes third party services commissioned or expected Develop and deliver orientation program for the new Council to enhance Council decision-making processes Review Council governance model and propose recommendations for improvement to the new Council April 2011 January 2012 April 2011 October 2013 Implement new governance model October 2013 vember 2013 Develop and recommend up to date bylaws that set out administrative authorities Further phases will be determined after all recommendations considered by Council January 2011 January 2014 TBD TBD July to September 2013 Quarterly Progress Report Page 9

Timeline January 2012 Orientation program delivered vember 2013 New governance model implemented Apr-11 Jul-11 Oct-11 Jan-12 Apr-12 Jul-12 Oct-12 Jan-13 Apr-13 Jul-13 Oct-13 Jan-14 TBD Further phases October 2013 Recommendations considered January 2014 Bylaws developed July to September 2013 Quarterly Progress Report Page 10

Our Community 3. Review Organizational Structure Our Environment Identify and implement changes to City service delivery that will result in cost savings or other benefits Align the organization to the City's Official Community Plan and Strategic Plan in order to meet the overarching goals, strategies and key initiatives identified by Council Optimize the efficiency and effectiveness of the organization Identify opportunities to realize synergies in the delivery of municipal services Human Resources Completed third party services commissioned or expected Complete organizational review September 2012 June 2013 Implement organizational changes June 2013 August 2013 Timeline June 2013 Review completed August 2013 Review implemented Oct-12 v-12 Dec-12 Jan-13 Feb-13 Mar-13 Apr-13 May-13 Jun-13 Jul-13 Aug-13 July to September 2013 Quarterly Progress Report Page 11

4. Pursue Naming Rights for Victoria Conference Centre Our Community Pursue alternative sources of revenue to complement traditional tax revenue Our Environment Realize revenue commensurate with the naming rights opportunity Victoria Conference Centre Have the objectives or scope of the project changed? Have the resources required to complete the project changed? Has the timeline for the project changed? Description of services Third party service provider Date of commission Value Reports produced Phase 1 Research/Strategic Feasibility Report and Phase 2 Market Development, Presentations and Conclusion Spectrum Marketing Corporation September 1, 2013 $88,000 plus 12.5% conclusion fee Prepare feasibility study with opportunities for Council consideration September 2013 January 2014 Conclude naming rights agreement January 2014 April 2014 Timeline January 2014 Feasibility Study prepared April 2014 Naming rights agreement concluded Oct-13 Jan-14 Apr-14 July to September 2013 Quarterly Progress Report Page 12

Our Community 5. Review Parking Services Our Environment Identify and implement changes to City service delivery that will result in cost savings or other benefits To improve the customer experience parking downtown To reduce operational costs To increase turnover on-street making it easier to find parking Engineering and Public Works Have the objectives or scope of the project changed? Have the resources required to complete the project changed? Has the timeline for the project changed? Presentation of recommendations to Council delayed until vember, but overall timeline remains unchanged Yes third party services commissioned or expected Obtain Council approval of Project Charter April 2013 Conduct technical review and consult with stakeholders April 2013 September 2013 Prepare final report and present to Council for approval September 2013 vember 2013 Develop Implementation Plan and communication strategies and start to implement recommendations vember 2013 January 2014 Timeline April 2013 Project Charter approved September 2013 Consultation and technical review completed January 2014 Implementation started Apr-13 May-13 Jun-13 Jul-13 Aug-13 Sep-13 Oct-13 v-13 Dec-13 Jan-14 vember 2013 (previously October 2013) Final report approved July to September 2013 Quarterly Progress Report Page 13

6. Introduce Open Initiatives Our Community Enhance information sharing among Council, staff and the public to promote citizen and staff engagement and facilitate informed decision-making Our Environment Increase public and staff access to Council proceedings and other City information Legislative and Regulatory Services Have the objectives or scope of the project changed? Have the resources required to complete the project changed? Has the timeline for the project changed? Description of services Digital agenda hosting services Webcasting hosting services Webcasting hardware/ software supply and installation Webcasting promotional video Third party service provider Date of commission Value icompass Ltd. January 2013 $23,000 N/A Granicus Inc. May 2013 $11,000 N/A Granicus Inc. May 2013 $61,500 N/A Media One September 2013 $1,035 N/A Reports produced Prepare Feasibility Assessment March 2012 October 2012 Introduce online open data catalogue Feb 2013 Enhancements will be ongoing Launch public webmap June 2013 Purchase and install webcasting equipment and implement webcasting Introduce other open government initiatives January 2013 September 2013 TBD based upon Council direction TBD based upon Council direction July to September 2013 Quarterly Progress Report Page 14

Timeline October 2012 Feasibility Assessment completed February 2013 Online Open Data Catalogue launched June 2013 Webmap launched September 2013 Webcasting implemented Apr-12 Jul-12 Oct-12 Jan-13 Apr-13 Jul-13 Oct-13 Ongoing Open Data Catalogue enhanced Introduction of other open government initiatives TBD based upon Council direction July to September 2013 Quarterly Progress Report Page 15

7. Finalize Official Community Plan and Local Area Planning Implementation Strategy Our Community Various depending upon initiatives identified in Implementation Strategy Our Environment Develop a clear plan of action to undertake implementation of the new Official Community Plan and local area planning program that is supported by Council and the community Sustainable Planning and Community Development Completed third party services commissioned or expected Obtain approval of Implementation Strategy Q4 2012 September 2013 Initiate Implementation Actions as outlined in the Strategy Ongoing Ongoing Timeline September 2013 Implementation Strategy approved Oct-12 Jan-13 Apr-13 Jul-13 Oct-13 Implementation Actions initiated as outlined in the Strategy - Ongoing July to September 2013 Quarterly Progress Report Page 16

8. Manage 120 Gorge Road Affordable Housing Project Our Community Partner with regional stakeholders to address transportation and other community issues Our Environment Protect and create affordable small family housing and supported housing Engineering and Public Works Have the objectives or scope of the project changed? Have the resources required to complete the project changed? Has the timeline for the project changed? Date for title transfer continues to be TBD third party services commissioned or expected Develop business case and acquire property August 2009 June 2010 Negotiate and transfer title to Victoria Native Friendship Centre September 2009 TBD Pursue and confirm funding sources January 2010 December 2012 Manage renovations vember 2012 June 2013 Timeline December 2012 Funding sources confirmed June 2013 Renovations completed Jul-10 Oct-10 Jan-11 Apr-11 Jul-11 Oct-11 Jan-12 Apr-12 Jul-12 Oct-12 Jan-13 Apr-13 Jul-13 June 2010 Property acquired TBD - Title Transferred July to September 2013 Quarterly Progress Report Page 17

9. Examine and Improve Public Transportation Options Our Community Partner with regional stakeholders to address transportation and other community issues Our Environment Examine and improve public transportation options Engineering and Public Works Have the objectives or scope of the project changed? Have the resources required to complete the project changed? Has the timeline for the project changed? Yes Preparation of Cycling Task Force Project Charter took longer than anticipated third party services commissioned or expected Transit Work with BC Transit to develop report on Douglas Street interim measures for BC Transit Commission 2012 April 2013 Obtain Council direction on report recommendations April 2013 May 2013 Work with BC Transit to develop Implementation Plan June 2013 December 2013 Construct Douglas Street corridor improvements from Herald Street to Hillside Avenue January 2014 TBD based upon final design Future phases TBD TBD Cycling Establish Cycling Task Force May 2013 Prepare Project Charter for Council approval June 2013 vember 2013 Further phases will depend on Project Charter TBD TBD July to September 2013 Quarterly Progress Report Page 18

Timeline Transit April 2013 Report for BC Transit Commission developed May 2013 Council direction obtained December 2013 Implementation Plan developed Oct-12 Jan-13 Apr-13 Jul-13 Oct-13 Jan-14 Apr-14 Douglas Street corridor improvements constructed from Herald to Hillside - TBD based upon final design Future phases - TBD Cycling May 2013 Cycling Task Force established vember 2013 (previously August 2013) Project Charter approved Oct-12 Jan-13 Apr-13 Jul-13 Oct-13 Jan-14 Apr-14 Further phases TBD depending on Project Charter July to September 2013 Quarterly Progress Report Page 19

Our Community 10. Introduce Housing Initiatives Our Environment Ensure that land use policies and practices facilitate development of a diversity of housing choices to support future population needs Develop policies and initiatives to better address OCP policies related to housing diversity and affordability Partner with CRD, government and stakeholders to address barriers to development, identify policy solutions and pilot housing innovations Sustainable Planning and Community Development Have the objectives or scope of the project changed? Have the resources required to complete the project changed? Has the timeline for the project changed? Timelines for initial project phases have been extended due to limited availability of required staff resources Yes Services of a consultant may be required in Quarter 4 of 2013 Conduct policy and practice review vember 2012 December 2013 Develop rental housing policies vember 2012 June 2014 Establish targets and create monitoring tools December 2012 December 2014 Pilot housing innovations December 2012 October 2015 July to September 2013 Quarterly Progress Report Page 20

Timeline vember 2012 Action Plan approved June 2014 (previously vember 2013) Rental housing policies developed October 2015 Housing innovations piloted Jan-13 Jan-14 Jan-15 December 2013 (previously vember 2013) Policies and practices reviewed December 2014 Targets established and monitoring tools created July to September 2013 Quarterly Progress Report Page 21

Our Community 11. Renovate or Replace Fire Hall #1 Enhance public safety and enable the coordination and delivery of policing and fire services Our Environment Provide a Fire Hall that meets department needs and is seismically resilient Engineering and Public Works Have the objectives or scope of the project changed? Have the resources required to complete the project changed? Has the timeline for the project changed? Presentation of options to Council rescheduled to follow Asset Management presentation to Governance and Priorities Committee on October 3, 2013 Yes Description of services Third party service provider Date of commission Value Reports produced Architectural services Johnston Davidson Architecture and Planning Inc. $10,000 Evaluate options Q1 2013 Q2 2013 Obtain Council approval of recommended option Q2 2013 Q4 2013 Design and construction TBD TBD July to September 2013 Quarterly Progress Report Page 22

Timeline Apr-13 Q2 2013 - Jul-13 Scope and Interval budget Description confirmed Design and Construction - TBD Oct-12 Jan-13 Apr-13 Jul-13 Oct-13 Oct-13 Q4-2013 Dec-13 Interval Description (previously Q3 2013) Council approval obtained July to September 2013 Quarterly Progress Report Page 23

12. Implement Esquimalt Policing Decision Our Community Enhance public safety and enable the coordination and delivery of policing and fire services Our Environment Develop operating agreement for policing in Esquimalt and Victoria City Manager s Office Have the objectives or scope of the project changed? Have the resources required to complete the project changed? Has the timeline for the project changed? Third party services may be commissioned if arbitration is required Finalize policing contract June 2012 December 2013 Timeline December 2013 Contract finalized Jul-12 Oct-12 Jan-13 Apr-13 Jul-13 Oct-13 Jan-14 July to September 2013 Quarterly Progress Report Page 24

13. Develop Options for Crystal Pool and Fitness Centre Our Community Our Environment Engage with the public on the future of recreation facilities and programs in the city Engage the public to create a common understanding of the current condition of the facility Assess the public s understanding of options and willingness to fund a pool and/or recreation facility Determine the type of facility and the operational model that the public is most interested in supporting Determine if partners are willing to be involved in future facility construction and/or operation Parks, Recreation and Culture Have the objectives or scope of the project changed? Have the resources required to complete the project changed? Has the timeline for the project changed? Timelines for several phases have been extended due to competing demands for the required staff resources. Overall timeline remains unchanged. Yes Contract negotiations underway for comparative data collection services. Third party services will also be required for architectural programming options and costing. Obtain approval of Project Charter June 2013 Obtain approval of Engagement Strategy vember 2013 Gather information July 2013 February 2014 Conduct gap analysis January 2014 March 2014 Develop options and present recommendations to Council March 2014 June 2014 July to September 2013 Quarterly Progress Report Page 25

Timeline June 2013 Project Charter approved February 2014 (previously vember 2013) Information gathered June 2014 Recommendations presented to Council Jul-13 Oct-13 Jan-14 Apr-14 Jul-14 vember 2013 (previously September 2013) Engagement Strategy approved March 2014 (previously December 2013) Gap analysis conducted July to September 2013 Quarterly Progress Report Page 26

14. Implement Economic Development Strategy Our Community Our Environment All strategies under Create a sustainable economy Grow business in the city Increase sustainable prosperity in Victoria City Manager s Office Have the objectives or scope of the project changed? Have the resources required to complete the project changed? Has the timeline for the project changed? Description of services Implement City s Economic Development Strategy Third party service provider Date of commission Value of services Sage Baker June 2013 $360,000 N/A Reports produced Form Economic Development Advisory Group March 2012 December 2012 Establish a City economic development function vember 2012 March 2013 Develop Implementation Action Plan June 2012 September 2013 Various initiatives in support of the three identified core areas of focus (Support for the ship building industry in a working harbour; Support for an environment for entrepreneurship downtown; Working with First Nations and other relevant parties for the revitalization of Rock Bay) July 2013 June 2015 July to September 2013 Quarterly Progress Report Page 27

Timeline December 2012 Economic Development Cabinet formed September 2013 Implementation Action Plan developed June 2015 Economic development contract ends Apr-12 Jul-12 Oct-12 Jan-13 Apr-13 Jul-13 Oct-13 Jan-14 Apr-14 Jul-14 Oct-14 Jan-15 Apr-15 Jul-15 March 2013 Economic development function established July to September 2013 Quarterly Progress Report Page 28

15. Develop a Feasibility Study and Business Case for Harbour Waterfront Revitalization Our Community Our Environment Engage in local area planning projects that will facilitate economic development Implement policy direction set out in the Official Community Plan, Economic Development Strategy and Downtown Core Area Plan Sustainable Planning and Community Development In planning phase. Project Charter will be coming to Council for approval in Quarter 4 of 2013. Need for third party services will be identified in the Project Charter Timeline July to September 2013 Quarterly Progress Report Page 29

16. Establish New Downtown Zones and Integrate Density Bonus System Our Community Our Environment Engage in local area planning projects that will facilitate economic development Increase certainty for development industry and community Sustainable Planning and Community Development Have the objectives or scope of the project changed? Have the resources required to complete the project changed? Has the timeline for the project changed? Timelines for the first phase of the project have been extended because anticipated staff resources have been unavailable Yes Likely will be third party services required, although the exact nature of these services depends upon future internal capacity and is unknown at this time Develop and test proposed zones for Central Business District, consult stakeholders and develop recommendations for Council. Prepare Zoning Regulation Bylaw amendments based upon Council direction. July 2012 June 2014 Prepare bylaw amendments for remainder of Bonus Density Area TBD TBD Prepare bylaw amendments for outside Bonus Density Areas, where needed TBD TBD Timeline June 2014 (previously March 2014) Bylaw amendments for Central Business District prepared Oct-12 Jan-13 Apr-13 Jul-13 Oct-13 Jan-14 Apr-14 Jul-14 Oct-14 TBD Bylaw amendments for remainder of Density Bonus Area prepared TBD Bylaw amendments for outside Density Bonus Areas prepared, where needed July to September 2013 Quarterly Progress Report Page 30

Our Community 17. Replace Johnson Street Bridge Our Environment Develop and implement asset management policies and plans that will facilitate prioritization and decisionmaking regarding capital assets Replace the existing bridge with a more reliable, safer and more sustainable bridge with improved cyclist and pedestrian amenities Johnson Street Bridge Project Have the objectives or scope of the project changed? Have the resources required to complete the project changed? Has the timeline for the project changed? Description of services Three Annual Audits of PST Payments Third party service provider Date of commission Value of services MNP Ltd. October 2013 $15,570 Reports produced Complete final design of bridge and public realm Q1 2011 Q4 2012 Award general contract Q1 2012 Q4 2012 Construct new bridge and underground and road works Q2 2013 Q3 2015 Remove old bridge Q3 2015 Q4 2015 July to September 2013 Quarterly Progress Report Page 31

Timeline Oct-12 Q4 2012 Final design completed and general contract awarded Q3 Jul-15 2015 New bridge opened to traffic Jan-12 Jan-13 Jan-14 Jan-15 Jan-16 February 2011 Project Charter approved Q4 Oct-15 2015 Old bridge removed July to September 2013 Quarterly Progress Report Page 32

18. Pilot and Evaluate Transportation Changes in Beacon Hill Park Our Community Our Environment Develop and implement plans for sustainable management of the City s natural resources, including parks, urban forest, native ecosystems and species at risk Enhance bicycle and pedestrian use of Beacon Hill Park Reduce car traffic in Beacon Hill Park Improve park pathway system Parks, Recreation and Culture Have the objectives or scope of the project changed? Have the resources required to complete the project changed? Has the timeline for the project changed? Yes Evaluation will now be presented in vember third party services commissioned or expected Pilot transportation changes July 2012 September 2013 Evaluate results of pilot project and develop recommendations for Council approval Implement recommendations August 2012 vember 2013 TBD depending upon recommendations July to September 2013 Quarterly Progress Report Page 33

Timeline vember 2013 (previously October) Evaluation completed and recommendations developed Implementation TBD depending upon recommendations Oct-12 Jan-13 Apr-13 Jul-13 Oct-13 Jan-14 September 2013 Pilot concluded July to September 2013 Quarterly Progress Report Page 34

19. Develop Asset Management Framework and Implementation Plan Our Community Develop and implement asset management policies and plans that will facilitate prioritization and decisionmaking regarding capital assets Our Environment Provide the City of Victoria with an Asset Management Strategy that will be a guide for the implementation of integrated asset management practices across the entire organization Promote informed decision-making and effective stewardship of all publicly owned municipal assets s Engineering and Public Works, Finance Have the objectives or scope of the project changed? Have the resources required to complete the project changed? Has the timeline for the project changed? Implementation Plan now scheduled for completion in January 2014 Yes Will require ongoing software maintenance services once software acquired Develop Strategic Framework for Asset Management July 2010 October 2012 Develop Asset Management Implementation Plan February 2013 January 2014 Acquire asset management software June 2013 June 2014 Implement Plan and policies ongoing Timeline October 2012 Strategic Framework developed January 2014 (previously September 2013) Implementation Plan developed Jul-10 Oct-10 Jan-11 Apr-11 Jul-11 Oct-11 Jan-12 Apr-12 Jul-12 Oct-12 Jan-13 Apr-13 Jul-13 Oct-13 Jan-14 Apr-14 Ongoing - Implement Plan and policies June 2014 Software acquired July to September 2013 Quarterly Progress Report Page 35

20. Maximize Opportunities from Sewage Treatment Infrastructure Construction Our Community Our Environment Develop and implement asset management policies and plans that will facilitate prioritization and decisionmaking regarding capital assets Maximize opportunity to align other capital works with the CRD sewage construction work Enhance public realm along Dallas Road Engineering and Public Works Have the objectives or scope of the project changed? Have the resources required to complete the project changed? Has the timeline for the project changed? third party services commissioned or expected Develop preliminary concept 2011 2011 Present preliminary concept for Council endorsement 2012 July 2013 Consult with the public on preliminary concept and secure Council approval Implement plan October 2013 May 2014 TBD based upon CRD construction timing Timeline 2011 Preliminary concept developed Jan-11 - v-11 July 2013 Preliminary concept presented for Council endorsement May 2014 Consultation completed and Council approval secured Apr-11 Jul-11 Oct-11 Jan-12 Apr-12 Jul-12 Oct-12 Jan-13 Apr-13 Jul-13 Oct-13 Jan-14 Apr-14 Jul-14 Implement plan TBD based upon CRD construction timing July to September 2013 Quarterly Progress Report Page 36

D. Other Accomplishments this Quarter In partnership with the District of Saanich and the Cities of Colwood and Langford, hosted a workshop with building inspectors, designers, builders and engineers to discuss recent changes to the BC Building Code relating to seismic design of houses Completed the 2013 Citizen and Business Surveys. Information gained from both surveys assists the City in its service delivery, planning and budgetary processes. Hosted an Open House to solicit public feedback on proposed Zoning Regulation Bylaw Improvements related to changes to site topography Hosted TEDxVictoria's simulcast of TEDCity2.0, a day-long event for urban innovators Our Community Celebrated Canada's 146th birthday with family-friendly activities, multicultural programming, live music performances, and spectacular fireworks Unveiled a plaque outside of Victoria City Hall to recognize the important role the Tiger Company Fire Hall played in providing fire protection to Victoria's downtown from 1880-1899 In partnership with the Greater Victoria Cycling Coalition, organized the Tour de Disaster Rally, designed to demonstrate the important role cyclists can play in disaster response Hosted a blood donor clinic at City Hall, in cooperation with Canadian Blood Services Presented Culture Days in the Square, part of a national celebration of Canada s diverse arts and cultural community, in partnership with La Sociétè francophone de Victoria and the Victoria African and Caribbean Cultural Society Welcomed four Vic-Star Scholarship recipients and other students from our Friendship City of Changsha, China who are pursuing studies in Canada Our Environment Partnered with the Victoria West Community Association Food Security Collective and the Fernwood Neighbourhood Resource Group to plant community orchards in Banfield Park in Victoria West and William Stevenson Park in Fernwood Received more than $180,000 in funding through the Province of British Columbia s Brownfield Renewal Program towards environmental investigation and testing at two City-owned downtown properties July to September 2013 Quarterly Progress Report Page 37