The History of the Atlantic Islands Centre Project

Similar documents
Guidance Notes. Guidance Notes 1

Climate Challenge Fund Content and images for websites, newsletters and social media

1.1 Introduction. 1.2 Strategic Context HES Corporate Plan

Information Pack - Freelance (self-employed) roles Bannockburn House Trust - 30 January V4

United Kingdom-Sheffield: Urban planning and landscape architectural services 2016/S Contract notice. Services

Match Funding your Heritage Lottery Fund Heritage Grant With a National Churches Trust Repair Grant

Project Development Grants Guidance Notes

NATIONAL MUSEUMS LIVERPOOL. Board of Trustees. 17 September 2015, 10.00am. (World Museum)

Project cost: Eligible cost: Grant award: 8000

Match Funding your Heritage Lottery Fund Our Heritage Grant With a National Churches Trust Repair or Community Grant

GUIDE FOR APPLICANTS INTERREG VA

Heritage Lottery Fund 16 April 2013

AND SCOTTISH NATURAL HERITAGE.

Grants for Archaeology Projects Guidance for potential applicants to the archaeology programme

Partnership Grants Programme Guidance Notes for Applicants in Northern Ireland

FUNDING NATURAL HERITAGE PROJECTS IN SCOTLAND LIFE+ NATURE AND BIODIVERISTY

Poppyscotland Audience Development Brief The Moving Poppy.

ISLE OF ULVA Community Right To Buy

SCOTTISH ENTERPRISE REGIONAL AND SME INVESTMENT AID SCHEME

Heritage Grants - Receiving a grant. Mentoring and monitoring; Permission to Start; and Grant payment

Poppyscotland Development Phase Advisor Brief The Moving Poppy.

MC/18/37 Notice of Motion 2017/202: Applications for grants from the National Lottery

Main Street Historic Building Facade Improvement Scheme Operating Guidelines

SPORT FACILITIES FUND GUIDANCE PAGE 1

Landscape Conservation Action Plan

Request for Quotation. Brand Development

Environment, Climate Change and Land Reform Committee. Draft Budget Written submission from Scottish Natural Heritage

RESOLUTION NUMBER 2877

HERITAGE LOTTERY FUND GRANTS FOR PLACES OF WORSHIP APPOINTING PROFESSIONALS

Low Carbon Skills Fund Rules and Guidance

84% 70% 139m. 20m. 300m. 600m 6, ,000 jobs 13,750. Impact of SFT s work. When complete, TIF projects will support

Revitalising Redesdale Community Heritage Fund Guidance Notes for Grant Applicants

Heritage Revealed : Accessing Dartington s Historic Landscape Brief for the Project Delivery Coordinator THE DARTINGTON HALL TRUST

INVITATION TO TENDER

Strategic Investment Board Chief Executive s Report January 2013

Business Frontage Improvement Grant Scheme. Application Form

Heritage Grants. Application guidance. March Grants over 100,000

SALADO INDEPENDENT SCHOOL DISTRICT

Company Profile Phillips & Jordan, Inc. Key Markets

LAND PARTNERSHIPS GRANT PROGRAM. PROGRAM GUIDELINES April 2018

The Lodge FAQs updated February 2018

All Souls, Bolton. Short description of the project

The Ryder Cup 2014 Gleneagles. Scottish Procurement & Commercial Directorate

Funding for church building projects can we help you? Catherine Townsend

GUIDANCE ON MANAGING CHURCH BUILDING PROJECTS

Celebrating excellence in Structural Engineering. Entry Guidelines

Unlocking Vindolanda s Wooden Underworld

Request for Proposal (RFP) The Klamath Tribes Youth Fitness Center Klamath Tribes Housing Department (KTHD) RFP # 09-KTHD17

SECTION 8 JANUARy 2015

Scottish Borders Council Town Centre Regeneration Action Plan

Army Medical Services The Museum of Military Medicine. Plans for future relocation

COUNTY COUNCIL OF PRINCE GEORGE'S COUNTY, MARYLAND SITTING AS THE DISTRICT COUNCIL 2016 Legislative Session

Facade Improvement Incentive Operating Guidelines

Centurion Way Feasibility Study - South Downs National Park Authority Application for Coast to Capital LEP Feasibility Fund

Ingrid Green Scotland Europa

Policy for Special Rate/Charge Schemes in Retail/Commercial Precincts or Centres April 2014

Marshes Mitigation Banking Pilot. CM Services Informational Session 10:00 AM 12:00 PM July 10, 2015

This request for qualifications seeks the following type of service providers:

Update on SNH activity on the SBS Challenge and Route Map to 2020 discussion

Village and Community Hall Grants

Thank you for your letter sent yesterday on behalf of the Health and Sport Committee.

ERDF : Low Carbon Travel and Transport (LCTT) Programme

Argyll & Bute Health & Social Care Partnership. Health and Wellbeing Fund GUIDANCE PACK

OVERVIEW OF LANDFILL COMMUNITY FUND (LCF)

GUIDE FOR APPLICANTS

Grant Application Form

Heritage Delivery Plan Consultation Feedback Review: February 2018

Government s role in supporting arts, culture and heritage facilities throughout New Zealand

CALL FOR ENTRIES. Follow us for award updates and design SPONSORED BY:

distinction as to race, religion, age or disability, and in compliance with relevant legislation.

International Architectural Design Competition

Fundraising for Church Buildings Projects. DAC Roadshows 2017

Report of the ESTATES COMMITTEE. 19 January 2010

Planning: a Short Guide

PORTAS REVIEW PILOTS APPLICATION FORM

Great Place Scheme. Grants between 100,000 and 500,000 Guidance for applicants in Wales

Forward Plan

Synopsis of Revised Changes to DCA s Rules for Developments of Regional Impact

Accreditation Scheme for museums and galleries in the United Kingdom: Application form

INFORMATION ON SETTING UP A FOOD PRODUCTION BUSINESS IN WESTMEATH

Delivering Affordable Sustainable Housing COMMUNITY LAND TRUST FUND

DMTF Standards Incubation Process

ERDF : Low Carbon Travel and Transport (LCTT) Programme

Tourism Funding What s available to support your destinations

223 W Wisconsin Ave. P.O. Box 131 Tomahawk, WI Operating Plan For the Tomahawk Downtown Business Improvement District 2019

THE CORPORATION OF THE MUNICIPALITY OF KINCARDINE

28TH PLADUR BUILDING SOLUTIONS COMPETITION

MAIN GRANT PROGRAMME GUIDELINES Revised: Guidelines March 2017

ECU s Equality Charters Guide to processes. January 2018

CLLD/LEADER and Cooperation. Dr Maura Farrell NUIG/NRN

RURAL & ISLANDS HOUSING FUNDS

Town of Agawam Community Preservation Committee Application for Funding

European Structural and Investment Funds. Aberdeenshire Council

8, 2018 REQUEST FOR PROPOSALS (RFP): G

Local Economy Directions Paper

Marina Strategy: Section A Request for Proposal. 1. Request for Proposal. 2. Communication. 3. Key Contacts

Incentive Guidelines. ERDF Research and Development Grant Scheme

SOUTH CITY GOOD NEIGHBOR GRANT

Conrad Grebel University College. Kitchen and Dining Room Expansion and Renovation Architectural Feasibility Study

ACI AIRPORT SERVICE QUALITY (ASQ) SURVEY SERVICES

Transcription:

The History of the Atlantic Islands Centre Project 2003 Autumn/Winter Two community consultation meetings formed a proposal for an integrated project: A home for the Luing History Group, with museum, archive, display areas, family history research area, café, offices. A welcome to visitors, with heritage interpretation panels around the island, walks and signage. Improvements to the environment involving old quarry restoration and access, picnic area, beach improvement, sea erosion protection. 2004 Spring Initial project design; bid for Heritage Lottery Fund grant within Nadair programme. 2004 October HLF grant was awarded to cover the whole project at 40% funding. 2004-2005 Spring Isle of Luing Community Trust formed, inaugural General Meeting in May 2005. 2005 June 2006 February Land and mineral rights valuations obtained. Negotiations for the land purchases. The Senior Planning Officer raised problems over sites at risk from coastal erosion, and advised use of the Engine House site. Applications made to Scottish Land Fund (SLF) and Highlands and Islands Enterprise (HIE) for land purchase grants. They required some re-valuations which resulted in one of the potential land parcels not being proceeded with. 2006 April SLF/HIE grants were awarded for land purchase from two separate landowners. One was a remnant estate of the former quarry owner around Cullipool conservation village, the other was the old quarry Engine House, with adjacent land. 2006 June Difficulties in obtaining matching funding for the building project caused much delay and Nadair recommended separating the heritage interpretation and environmental improvements from the building project with the HLF grant being split. This was approved by HLF with matching funding awarded by Whelk Leader + and Scottish Natural Heritage (SNH). 2006 July Approval of business plan after lengthy discussions with Nadair adviser. 2006 August The plans to build a Centre on the Engine House site were put to a large community meeting and endorsed overwhelmingly, with only one vote against being registered. This decision is binding on the Trust and directors as the land purchase funding was provided on this condition by means of a legal Deed of Restriction. The appointment of an architect was also approved. 2006 October December Land boundary problems delayed progress considerably but the Trust solicitor obtained time extensions and disputes over titles were eventually resolved.

2007 January The solicitor required 94 title deeds for land previously sold to residents of Cullipool and others. Wednesday 31 January: approval for the funding for land purchase granted. 2007 February Time to use the Nadair/HLF grant ran out, and the offer was withdrawn. The directors were advised to start again with a new HLF bid. 2007 April December Efforts concentrated on the heritage interpretation and environmental improvement project. The 14 finished panels were designed and delivered at the end of the year and slate plinths prepared for their installation throughout Luing in 2008. 2007 November First draft plans from architect for the building on the Engine House site presented for community comments at a public meeting. 2008 February- May We learned that there would be no further Nadair funding programmes. 2008 July Nadair mothballed ; at their closure event, it was learned that HLF view was that Argyll had had its share of HLF funding, so a purely heritage-focused project would not receive funding. The directors revised and broadened the project to enable application to non-heritage funders such as Big Lottery, so the idea of an Atlantic Islands Centre (AIC) was developed. 2008 August Consultations with the Luing History Group, and a detailed document about the Centre was produced as a result. Article published in the Luing Newsletter of Winter 2008. 2008 October 2009 February The development phase of the project was designed and costed, leading to a grant application to the Big Lottery Fund Investing in Ideas scheme (grant received in February), and to Argyll & The Islands LEADER (European Funding). 2009 February The detailed work of defining the revised AIC project was described at a community consultation meeting. The main points raised concerned the roof, waste water disposal and car parking, but no objections were raised to the concept itself, so the directors proceeded to take the project forward. 2009 March April LEADER funding approved in March, and HIE considered the revised Centre project for one of its account managed projects. 2009 May Trust AGM: a summary of the revised project and its development phase included in the Annual Report, and approved without comment by members present. 2009 April November Development phase taken forward visits to other island projects, clearance of the ground for the ground engineer, further architect s plans, and further consultation with the Luing History Group, including meetings with Argyll & Bute Council s museums adviser to develop a consensus on the design and use of the Centre. HIE provided consultancy for the Business Plan. 2009 December Architect s plans were presented at a consultation meeting at which many issues were raised including an offer of a new site at Fladda.

2010 January February The directors considered at length the issues raised at the December meeting and tried to progress the Fladda site option, but despite requests no written offer was received. In addition the Trust was informed that no funding would be available to develop this option and it could not be completed within the extended grant deadlines. 2010 March Modified plans prepared with reduced length and height of the new wing of the Centre, and a dedicated space for the Luing History Group. Resolution to proceed with these to planning application and subsequent build was put to all Members of the Trust. Out of 77 Members, 63 voted to proceed with the planning application and subsequent build, 3 voted against and 3 registered abstentions; results were declared at a Members meeting. 2010 July Planning application submitted. 2010 October Presentation of project to the Lorn Area Committee of Argyll & Bute Council. 2011 January Public planning application hearing by Argyll and Bute Council Planning Committee in Cullipool Hall, with presentations by supporters and opponents of the project. Application approved unanimously by the Planning Committee. 2011 March June Early funding applications unsuccessful. 2011 October Meeting in Dunoon with representatives of potential funders convened by MSP Michael Russell. 2011 November Meeting at Scottish Parliament with Lottery funders. The Trust accepted as an Associate Member of Museums Galleries Scotland. An amended version of plans for the Centre developed to reduce project costs. 2012 February -March Big Lottery Funding application granted Stage 1 approval, and target of fast track to Stage 2, submitted March, with the help of financial consultant provided by BL. 2012 April ERDF application submitted under Priority 3 as part of Argyll and Bute Council s Community Planning Partnership package. 2012 May BL grant of 754,000 awarded; HLF application unsuccessful. 2012 August CCF application approved for grant of 72,000. Centre Planning Group formed volunteers from the community to plan and organise events for the Centre 2012 September ERDF application re-submitted under Priority 2 following advice. 2012 October ERDF application approved for 361,000. 2012 November Funding for the construction project in place; open information evening held in Cullipool Hall to explain what happens next. Over 40 attended. 2012 December HIE to match-fund the Project Development Manager with BL - now full-time for 19 months. Advertisements placed.

2013 January Building warrant application submitted. PQQ notice to potential contractors.. 2013 February Interviews held for post of PDM Andrew Pinkerton appointed. 2013 March Andrew Pinkerton takes up PDM post. 2013 April Scoring of PQQ returns. 2013 May Tender documents issued to selected contractors, bids returned by end of May. Building warrant issued. 2013 June Contractor selected, selection process approved by funders, all legals completed. 2013 July Contract award letter issued to MacLeod Construction. Site handed to the control of the contractor for the period of construction. 2013 August MacLeod Construction commence work on site 2013 September Major rock fall into quarry while foundation excavations were progressing. Work stopped on safety grounds while problem assessed and solution proposed. Quarry face examined by a geotechnical 2013 October Geotechnical survey and project engineer produce a solution involving rows of minipiles to stabilise the ground and prevent further movement. 2013 November Architect amends plans to bring the engine house away from the quarry edge. 2013 December Non-material amendment to plans approved by Council Planning Department. 2014 January Construction work re-commences foundations laid. 2014 February Foundation slab completed. 2014 March Steelwork completed 2014 April Leach Colour Ltd appointed to create and produce interpretative material for the Centre fit-out. On-going work continues until early 2015. 2014 June Structures reach roof level. Change of slate specification applied for to enable guarantee for roof. 2014 July Slate cladding completed on Engine House. 2014 August Windows and doors installed. Underfloor heating pipework installed 2014 October Slate specification change approved by full Planning Committee. 2014 November Interviews for the post of Centre Development Manager (CDM) 2014 December Trading Company revised structure agreed

2015 January Gales delay progress on slating the roof. Trading Company starts up. 2015 February Laura McIntyre takes up CDM post for 3 years. Slating work on roof of building completes. 2015 March Water-source heat pump system commissioned. Leach Colour install interpretative material inside the Centre. 2015 May Contractors complete the building and site construction work, with handover of keys. Internal fit-out of kitchen café, retail area, exhibition areas and Local History Gallery. Gradual opening of Centre with members of Trust and History Group, followed by first public use. June 2015 Formal opening. Isle of Luing Community Trust directors