UTILIZING LEAN MANAGEMENT PRINCIPLES DURING A MEDITECH 6.1 IMPLEMENTATION

Similar documents
Hillside Medical Office

Northern California Go-live

Best Practices: Access Case Management

From Implementation to Optimization: Moving Beyond Operations

ACO Practice Transformation Program

Laguna Honda Lean Transformation. Laguna Honda Strategic Performance Management November 2017

Making Differences Matter Redesign Ambulatory Medication Reconciliation

1 Title Improving Wellness and Care Management with an Electronic Health Record System

Eligible Hours ( ) Achieving HIMSS Stage 7 and Gaining Physician Adoption of a Paperless Record CHC

Achieving Operational Excellence with an EHR a CIO s Perspective

eprescribing Information to Improve Medication Adherence

One Medicine: Incorporating Population Health Principles and Best Practices into Clinical Workflow

Health IT Council and Advisory Committee Meeting. June 18, 2012 One Ashburton Place, 21 st Floor Boston, MA

Date: April 6, 2018 SUBJECT: REQUEST FOR QUALIFICATIONS. RFQ # Business Analyst Services

Core Item: Hospital. Cover Page. Admissions and Readmissions. Executive Summary

Building a Lean Team. Using Lean Methodology to Develop a Collaborative Rounding Model. April 28 th, 2010

Roadmap to accountable care: The chicken or the egg technology investment or clinical process improvement?

MEANINGFUL USE FOCUSES INDUSTRY ON BABY STEPS

Midmark White Paper The Connected Point of Care Ecosystem: A Solid Foundation for Value-Based Care

Lean Six Sigma in Healthcare. 4 Simple BFO s s that Change Everything

Lab Quality Confab Process Improvement Institute. New Orleans, LA. John Waugh 11/3/2015

Eliminating Common PACU Delays

Hospital Readmissions Survival Guide

PBSI-EHR Off the Charts Meaningful Use in 2016 The Patient Engagement Stage

The Transition to Version 5010 and ICD-10

Transitioning OPAT (Outpatient Antibiotic Therapy) patients from the Acute Care Setting to the Ambulatory Setting

Improving Clinical Flow ECHO Collaborative Change Package

Integrated Leadership for Hospitals and Health Systems: Principles for Success

TRANSFORMING DHS: THE RESTRUCTURING OF AMBULATORY AND MANAGED CARE SERVICES WITHIN THE LOS ANGELES COUNTY DEPARTMENT OF HEALTH SERVICES

Optimizing InDxLogic

A strategy for building a value-based care program

Virtual Care Solutions Moving Care from the Hospital to the Home

Leverage Information and Technology, Now and in the Future

Using Lean Principles to Decrease Outpatient Registration Wait Times. It s a Journey not a Destination

2017/2018. KPN Health, Inc. Quality Payment Program Solutions Guide. KPN Health, Inc. A CMS Qualified Clinical Data Registry (QCDR) KPN Health, Inc.

Innovative Models for Team-Based Care: A Solution for Burnout Gaines Richardson, MD, Faculty Monroe Clinic / Mark Thompson, MD, SSM Heath, WI

Elmhurst Memorial Healthcare Successfully Attests to Stage 1 Meaningful Use

Clinical Program Cost Leadership Improvement

5D QAPI from an Operational Approach. Christine M. Osterberg RN BSN Senior Nursing Consultant Pathway Health Pathway Health 2013

REDESIGNING ALLIED HEALTH OUTPATIENTS - Lean Thinking Applications to Allied Health

Meaningful Use Participation Basics for the Small Provider

Adopting Accountable Care An Implementation Guide for Physician Practices

Interoperability is Happening Now

Joint Commission Laboratory Accreditation: Why It Is Right For Your Organization

How Data-Driven Safety Culture Changes Can Lower HAC Rates

Hospital Readmissions

LEAN Transformation Storyboard 2015 to present

Iowa Medicaid: Innovations & Initiatives

Quality Improvement Plan (QIP) Narrative for Health Care Organizations in Ontario

A Multi-Phased Approach to Using Clinical Data to Drive Evidence-Based EMR Redesign. Kulik, Carole Marie; Foad, Wendy; Brown, Gretchen

PFAC as Consultant to Hospital Initiatives

Partnerships- Cooperation with other care providers that is guided by open communication, trust, and shared decision-making.

Strategy Guide Specialty Care Practice Assessment

3. Does the institution have a dedicated hospital-wide committee geared towards the improvement of laboratory test stewardship? a. Yes b.

Comparison of ACP Policy and IOM Report Graduate Medical Education That Meets the Nation's Health Needs

CASE STUDY NORMAN REGIONAL HEALTH SYSTEM BOOSTING PATIENT SAFETY WITH ACCESS SOLUTIONS

HIT Innovations to Build an Empowering and Learning Culture March 2, 2016

Final Meaningful Use Stage 3 Requirements Released August 2018

Improving Care Coordination to Manage an ACO Population. Greater Baltimore Medical Center

From Big Data to Big Knowledge Optimizing Medication Management

Nonprofit partnership. A grass roots organization where Board of Directors have vested interest in its success.

Clinical Integration and P4P: Using Pay for Performance to Build Clinical Integration within a Physician-Hospital IPA

Optum Anesthesia. Completely integrated anesthesia information management system

Implementation Issues of the Physician Practice. for ICD-10-CM

Using Data for Proactive Patient Population Management

Using Facets of Midas+ Hospital Case Management to Support Transitions of Care. Barbara Craig, Midas+ SaaS Advisor

Minnesota s Plan for the Prevention, Treatment and Recovery of Addiction

Transitions of Care. Objectives 1/6/2016. Roman Digilio, PharmD PGY1 Resident West Kendall Baptist Hospital. The author has nothing to disclose.

Recent Veterans of Major EMR Launches Share Insights on Keys to a Robust Go-Live Command Center

ED Care Triage: Linkage to Primary Care

MACRA Frequently Asked Questions

Practical Applications on Efficiency

Overview. Overview 01:55 PM 09/06/2017

Our Patient Portal Experience

Launching an Enterprise Data Warehouse to Rapidly Reduce Waste in Asthma Care

How to Participate Today 4/28/2015. HealthFusion.com 2015 HealthFusion, Inc. 1. Meaningful Use Stage 3: What the Future Holds

2. What is the main similarity between quality assurance and quality improvement?

Improving the Delivery of Troponin Results to the Emergency Department using Lean Methodology

UPDATE ON MEANINGFUL USE. HITECH Stimulus Act of 2009: CSC Point of View

Unifying Real-Time Mobile Rounds with Follow Up Care Calls to Improve Patient Experience and Outcomes

Meaningful Use Stage 2

MLK MACC Organizational Structure (Deliverable #3)

SWAN Alerts and Best Practices for Improved Care Coordination

Toward the Electronic Patient Record:

Roll Out of the HIT Meaningful Use Standards and Certification Criteria

Overview of the Changes to the Meaningful Use Program Called for in the Proposed Inpatient Prospective Payment System Rule April 27, 2018

Spring User Conference May Sandestin, FL Detailed Agenda

EHR Implementation Best Practices. EHR White Paper

Quality Improvement Plan (QIP): 2015/16 Progress Report

January 4, Dear Sir/Madam:

REQUIREMENTS GUIDE: How to Qualify for EHR Stimulus Funds under ARRA

HOW 5S ORGANIZING BOOSTS MONEY, TIME, AND PATIENT OUTCOMES

2015 MEANINGFUL USE STAGE 2 FOR ELIGIBLE PROVIDERS USING CERTIFIED EMR TECHNOLOGY

The American Recovery and Reinvestment Act: Incentivizing Investments in Healthcare

Identify obstacles, and understand the aspects of the revenue cycle that you should be focusing on at your organization

Seamless Clinical Data Integration

Cutting Avoidable Readmissions Starts in the Emergency Department

EMPI Patient Matching Solution Product Use Cases: Epic Electronic Health Record Integration

Jumpstarting population health management

Bethesda Hospital PGY1 Residency Program Learning Experiences

Transcription:

UTILIZING LEAN MANAGEMENT PRINCIPLES DURING A MEDITECH 6.1 IMPLEMENTATION

II UTILIZING LEAN MANAGEMENT PRINCIPLES DURING A MEDITECH 6.1 IMPLEMENTATION EXECUTIVE SUMMARY Healthcare may be the only industry to increase automation while decreasing efficiency. Much of this is due to the nature of how information technology came to be in the industry, particularly in the acute hospital setting. What began as patient management systems and billing systems then grew to support ancillary efforts before finally reaching patient care through nursing and physician applications. Thus, the key users and most vital members of the healthcare team were utilizing systems that were never designed around their workflows. More recent versions of health IT systems are not simply rewrites of the old systems, but complete redesigns from the ground up with the system user and workflow at the heart of the new design. For example, a MEDITECH 6.1 implementation begins with the READY implementation model which devotes 4-6 months to designing the application to incorporate increased standardization and best practices. Lean management has been used successfully for years to improve workflows and drive out waste from inefficient processes, and is now being applied to the MEDITECH 6.1 implementation. The Lean principle of doing less with more is fitting for an industry that is being challenged to remove cost and decrease waste, while increasing quality and reducing errors. THE SETUP In mid-2015, Signature Healthcare in Brockton, Mass. made the decision to replace its 20+ year-old IT system with MEDITECH 6.1 in order to provide a better foundation for future growth and move to a greater at-risk position in a competitive healthcare market. The organization s driving need was to move from numerous disparate systems, including MEDITECH Magic, to a single integrated electronic health record (EHR). Although the 6.1 implementation required a significant financial investment, Signature was committed to a hospital-wide change and made the project the focus of its Lean initiatives and the key to organizational transformation.

III GUIDING PRINCIPLES Lean is not just how we did this project; it s how we do everything. It s part of our culture and who we are. -Jim Papadakos, CFO of Signature and project executive for the MEDITECH 6.1 implementation During the implementation, the organization aimed to focus on three overriding Lean principles that it applies every day: 1. Continuous improvement: Never settling for the status quo 2. Eliminate waste: Recognizing that eliminating waste and cost from the system is necessary for survival 3. Respect for people: Maintaining a respectful and considerate attitude toward others and their ideas, even when there is disagreement

IV PRE-IMPLEMENTATION ACTIVITIES Approximately six months prior to the start of the 6.1 implementation, Signature leadership and Santa Rosa Consulting worked to create a governance structure to oversee the implementation project. During this pre-implementation phase, 18 Kaizen (or continuous improvement) teams were established to identify the most troublesome and least efficient workflows in the hospital, and value stream maps were created for the identified process areas to get the organization ready for change. At this point, implementation project team members, including some of the Santa Rosa Consulting staff, also received additional Lean training. The Core Team The Kaizen teams, also called core teams under the traditional MEDITECH implementation methodology, were made up of staff from across the organization (nursing, lab, registration, etc.). The teams included: 1. Team leaders with advanced Lean training to ensure the team was properly using Lean management principles 2. A Santa Rosa consultant who served as the subject matter expert on the software s capabilities, as well as MEDITECH and industry-defined best practices 3. A team leader from the operational area most impacted by this project 4. Staff most familiar with the details of the operation who would lead the build of the new system During the pre-implementation phase, the teams began by Going to the Gemba, a foundational Lean principle. Members from across the organization focused on thoroughly understanding the current workflow and process. This included walking the floors of the hospital, sitting in the billing and claims process departments, and standing with patient access staff so team members could see first-hand how each department used the system. By observing hospital staff engaged in their daily work, the team was able to design future state workflows that were more accurate and easier for hospital staff to understand and utilize following the new MEDITECH system implementation. In all healthcare organizations workarounds are created organically over time and become ingrained in hospital staff to the point where they are no longer identified as issues. Utilizing value stream mapping during current state workflow analysis helped the team pull these workarounds so that they could be part of the problem-solving process to be completed as a precursor to designing future state workflows.

IMPLEMENTATION TIMELINE V PHASE 01 Value Stream Mapping Kaizen Event Future State Workflows PHASE 02 Software Build System Testing PHASE 03 Go Live PHASE 04 Stabilization & Optimization 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 18+ TIMELINE (MONTHS) MONTHS 1-6 DESIGN PHASE Prior to the introduction of the READY implementation methodology, MEDITECH implementations began with training on the software and build process. The READY approach identifies the need for a 4-6-month period to review workflows and define a desired future state, keeping in mind the capabilities of the MEDITECH software and defined best practices. Led by the Santa Rosa Consulting team and MEDITECH implementation specialists, Signature started with the areas identified in the pre-implementation phase and began creating future state value stream maps. Lean principles, tools, and methods were then applied to goal creation and documentation during the design phase. Once all current state assessments were completed, the team executed a modified Kaizen event. This event allowed key department decision makers and the MEDITECH project team members to come together to review the findings of the current state analysis and collaborate on the best design for the future state of the organization s workflows. The decision makers prioritized the pain points for their departments, which provided guidance for the project team as they moved forward in the implementation. The project team also shared its system expertise with the department decision makers to help develop new future state workflows where necessary. This collaboration fostered cooperation between the project team and the decision makers while setting the team up for success during the implementation/build phase.

DISCHARGE MEDICATION RECONCILIATION VI PROVIDER Discharge orders entered Provider chooses convert Provider chooses whether to continue medications Start a new medication? YES New medication chosen from active list or new Rx NO PRIMARY NURSE Home meds confirmed & updated Home medications are up-to-date Reviews medication list with patient along with discharge information New medication education is reviewed with patient as part of the discharge instructions PATIENT Patient recieves information printed on medications if it is appropriate MONTHS 7-16 IMPLEMENTATION PHASE Following the design phase, Signature began the implementation phase for MEDITECH 6.1, which included both the software build and system testing. Software Build During this phase, core teams began to build out the software according to the future state value stream maps. Because all workflows and processes may not have been reviewed, teams quickly met to ensure that all of these were in unison. As the MEDITECH product is an integrated product, it was essential that the teams not only focused on their areas, but worked with other teams and across traditional department boundaries.

VII Balanced Scorecard Throughout the project, but especially during the implementation phase, the balanced scorecard was used continuously to track and measure progress and success. Each team created issue-specific scorecards, as well as an overriding scorecard that was updated weekly. See below a scorecard example. SOURCE METRIC STATUS ACTUAL VS. TARGET WEEK 1 WEEK 2 WEEK 3 WEEK 4 Finance Work Flows Complete Actual Target Actual 12 14 16 18 Green 18 18 20 20 Finance Future State Complete Actual Target Actual 7 7 9 12 Green 5 6 8 10 Actual Staff Build Training Actual Target Actual 26 26 26 26 Green 26 26 26 26 Finance Third Party Apps Reviewed Actual Target Actual 4 7 8 13 Green 7 9 11 13 Finance Interfaces Documented Actual Target Actual 5 6 7 8 Green 5 6 7 8 Finance Reports Identified Actual Target Actual 25 25 30 32 Green 20 25 30 35 Finance Conversions Actual Target Actual 4 4 4 4 Green 4 4 4 4 The balanced scorecard was a visual reminder to address problems and opportunities that had been identified and keep teams on track. With milestones and completion measures defined for each team each week, project leadership could quickly identify problem areas and teams that might not be on track. This constant reminder was key to keeping the teams on time and on budget. System Testing The testing phase of a READY implementation had three separate components within it, and they each needed to be executed with a focus on success metrics. These success metrics had to be defined before the formal start of the testing phase and needed to support the Key Performance Indicators (KPIs) identified by the organization prior to the start of the READY implementation. The team focused testing on the Kaizen principle, and then used the Plan-Do-Check-Act (PDCA) cycle to address issues encountered during testing.

VIII THREE PHASES OF SYSTEM TESTING 1. UNIT TESTING: This is the initial phase of testing in a READY implementation, and must occur at least once during the implementation process. The MEDITECH unit testing was focused on each individual application, and the newly-built content and functionality was thoroughly tested to eliminate as many issues as possible before advancing to the next phase of testing. Because issues tend to be straightforward in this phase, the team was able to record them in issue logs and address them with a PDCA cycle in which they tested the resolutions to ensure they met the needs of the organization. This helped set up the project team and MEDITECH system for the next round of testing. 2. INTEGRATED TESTING: The second part of the READY implementation s testing phase is integrated testing, and it s the first opportunity to test the new system build and workflows between applications. During this time, information flows through all parts of the system, and issues are typically more complex than those identified during the unit testing phase. The MEDITECH team used the PDCA cycle during issue resolution, and involved relevant team members to ensure the issues were truly resolved and that unnecessary workarounds were not incorporated into the workflows for the new system. At this point during a Lean implementation, depending on the extent of the issues and required changes, an organization may want to schedule another Kaizen event to review the planned future state and discuss any substantial modifications that need to be made as a result of testing. This will allow the team to work in a structured, collaborative fashion, and to ensure that resolutions to issues are not crafted in a vacuum. 3. PARALLEL TESTING: By the time parallel testing was executed, the majority of issues had been identified and addressed, but there was still the possibility for additional issues. In the event that complex issues occur, the PDCA cycle should be employed again to ensure the issue resolutions truly support the goals of the system implementation.

IX MONTH 17 GO-LIVE The implementation teams had begun to use balance scorecard pillars to track KPIs and their supporting metrics over the course of the project, but this activity intensified post-go-live. This allowed the teams to track and monitor appropriate process and outcome metrics so they could quickly identify potential problems, such as missing charges. At any go-live, the number of issues coming into the command center can be overwhelming. Strong communication and calm leadership helped the organization quickly identify and classify software, workflow, and training issues. Problem Solving Sheets were used to address issues that crossed multiple hospital departments. This facilitated open communication between departments and provided a written record for tracking issue origins, which facilitated closed-loop communication. MONTHS 18 AND BEYOND STABILIZATION AND OPTIMIZATION In very few cases, the defined workflows and processes did not work as hoped. Kaizen teams were quickly formed, value stream maps were created, and software modifications were made utilizing the Lean principle of PDCA. The organization made changes in small increments, being careful not to make radical change so that new workflows and processes had enough time to be understood and accepted. RESULTS Due to the Lean implementation, Signature successfully went live on MEDITECH 6.1 in April 2016, and the organization is now evaluating and planning a Lean implementation of the MEDITECH ambulatory system for its employed physician practice offices. This will result in a fully integrated record across the organization and further enhance Signature s population health position. 1. Quality improvements around most Centers for Medicare and Medicaid Services (CMS) quality measures and Meaningful Use statistics 2. An increased number of engaged medical staff due to the improved user interface, including a 98 percent adoption rate for orders and documentation 3. A launch pad for creating future operational improvements and efficiencies 4. Elimination of multiple niche vendors, including moving the emergency department (ED) and surgery systems to a single EHR for the acute setting. The result was better workflows, fewer Interfaces, vastly improved medication management, better medication tracking and integration with drug dispensing system, improved ordering process, improved patient flow from the ED to inpatient and from inpatient to surgey, a simplified nursing process and elimination of duplicate work.

X AUTHORS Mike Reel Santa Rosa Consulting MEDITECH Practice Leader Nicole Desjarlais Paulick Santa Rosa Consulting Project Manager Signature Healthcare Implementation Team Member Gerald Greeley Signature Healthcare Chief Information Officer About Signature Healthcare Signature Healthcare is a multi-specialty, not for profit hospital and physician group comprised of Brockton Hospital and Signature Medical Group, which is made up of more than 150 physicians practicing in 18 ambulatory locations. Signature Medical Group acts as a patient s medical home, working with them to coordinate all their healthcare needs, as well as provide access to evidence based patient care and education and self management support. We are one of the only not-for-profit community based healthcare delivery systems in Southeastern MA providing the full range of high quality primary care, specialty care, hospital care and related ancillary services on a coordinated basis delivered at a low cost. We are an affiliate of Beth Israel Deaconess Medical Center, Harvard Medical Faculty Physicians at BIDMC and the Floating Hospital for Children at Tufts Medical Center. Signature Healthcare is continuously recognized for the quality care patients experience when visiting with our doctors and nurses. Some of our most recent awards include being named a Top Performer on Key Quality Measures by The Joint Commission, receiving a national hospital safety score A rating as well as a Top Teaching Hospital by The Leapfrog Group, being noted as a Top Hospital by US News & World Report, as well as winning a Women s Choice Award for America s Best Breast Centers. Visit: MySignatureCare.org About Santa Rosa Consulting Santa Rosa Consulting provides management advisory services and technical consulting expertise across the full range of IT vendor products and systems, and empowering better healthcare by designing, creating, staffing and sustaining IT solutions that help make healing happen. Founded in 2008, Santa Rosa Consulting is managed by industry veterans with an average of 20 years of healthcare information technology experience. Santa Rosa is recognized for delivering world-class services and solutions and is a regular recipient of Modern Healthcare s Best Places to Work in Healthcare award. Visit: santarosaconsulting.com