Asbestos Management Plan Commercial Services and Development, University of Tasmania

Similar documents
ASBESTOS MANAGEMENT PLAN

SAMPLE. Asbestos. Nominated Supervisor DANGER CONTAINS ASBESTOS FIBRES AVOID CREATING DUST CANCER AND LUNG DISEASE HAZARD.

Asbestos Management Policy (Version 4)

POLICY ON THE CONTROL OF ASBESTOS AT WORK

Asbestos (Health and Safety) Policy

UNCONTROLLED IF PRINTED. Issued with the authority of the Chief Commissioner and General Manager of Scouts Australia NSW

ASBESTOS POLICY. Version: 3 Senior Managers Operational Group Date ratified: March 2016

ASBESTOS MANAGEMENT PLAN

Asbestos identification, risk assessment approaches, asbestos register and asbestos management plan

ASBESTOS MANAGEMENT PLAN

ASBESTOS MANAGEMENT POLICY

Asbestos Management Policy

ASBESTOS POLICY PROCEDURES & GUIDANCE

HS16 Asbestos Management

Developing your council s asbestos policy. A guide to using the 2015 Model Asbestos Policy for NSW Councils to develop an asbestos policy

REVISION 5 (Ref: ZHUX0015/JF/R1/Rev5)

NZQA registered unit standard version 1 Page 1 of 6. Conduct asbestos assessment associated with removal

ASBESTOS MANAGEMENT PLAN

APPLICATION FOR A LICENCE TO OPERATE AS AN ASBESTOS REMOVALIST

Policy on Managing Asbestos

Asbestos Management Plan for an Essex County Council premises

ASBESTOS MANAGEMENT PLAN

THE MANAGEMENT OF ASBESTOS POLICY, RESPONSIBILITIES AND PROCEDURES

An electronic copy of this document is available on the SC intranet and the Learning Gateway.

FORT RUCKER Environmental Document

HEALTH AND SAFETY ARRANGEMENTS

Asbestos Management Plan

ASBESTOS MANAGEMENT POLICY

Developing your council s asbestos policy. A guide to the Model Asbestos Policy for NSW councils

NASUWT. heal h safe. ASBESTOS: Advice for NASUWT Representatives. The Teachers Union. at work. the largest UK-wide teachers union

November 7, 2013 November 7, To establish an asbestos management program for County facilities and projects.

POLICY. Asbestos removal OHSMS REQUIREMENTS FOR CLASS A ASBESTOS REMOVAL

Asbestos Register. Sheffield City Council

ASBESTOS MANAGEMENT. Policy and Arrangements. Oxfordshire County Council December 2013

Permit to Work Procedure

ASBESTOS MANAGEMENT PLAN:

Asbestos Management Policy May 2015

Asbestos Awareness Annual Presentation

MANAGEMENT OF ASBESTOS

Asbestos - Duty to Manage & Learning From its Mismanagement

Incident Response and Investigation Procedure

Asbestos Management Procedure

Occupational Health and Safety Policy

UNIVERSITY OF ROEHAMPTON ASBESTOS POLICY

SAFETY, HEALTH AND WELLBEING POLICY

OCCUPATIONAL HEALTH AND SAFETY POLICY

Work Health and Safety Committee Terms of Reference

Health and and Safety Executive. Health and Safety. Executive Update. Phil Chester HM Inspector of Health and Safety

Health and Safety Policy

DIRECTIVE 2009/148/EC OF THE EUROPEAN PARLIAMENT AND OF THE COUNCIL

Asbestos Management Plan. 12 th Edition. September 2014

Asbestos Management Plan

NZQA registered unit standard version 1 Page 1 of 5

HEALTH & SAFETY POLICY CONTENTS

Responsibilities Work Health and Safety Minimum. October, 2013

Formaldehyde Exposure Control Policy

Operational date 01 April 2012 Review date April 2014 Version Number V0.3 Supersedes

Topic 3 Contribute to safe work practices in the workplace 43

ST. AUGUSTINE S CATHOLIC PRIMARY SCHOOL

Summers-Inman Group Health and Safety Policy SUMMERS-INMAN GROUP HEALTH AND SAFETY POLICY. Revision -

HEALTH AND SAFETY POLICY

Volunteer Work Health and Safety Minimum Standard. December 2014

THE LAURELS SCHOOL Risk Assessment Policy

Health and Safety Policy and Procedures

Academy Health and Safety Policy 2017/2018

COMPLIANCE WITH THIS PUBLICATION IS MANDATORY

RISK ASSESSMENT POLICY Independent School Standards Regulations 2014, Part 3 16(a) December 2015

Health and Safety Policy and Procedures

Review Date: Scope: All CHL Employees and Contractors Originated: 5/15/2017 References: OSHA Revisions:

Health and Safety Policy and Managerial Responsibilities

Asbestos & Hazardous Materials. Contaminated Land. Environmental Management & Monitoring. Occupational Hygiene WH&S

Duties of a Principal

ASBESTOS MANAGEMENT POLICY Responsible Officer Director of Property and New Business

Health and Safety at Work (General Risk and Workplace Management) Regulations 2016 (LI 2016/13)

CONDUCTING WORKPLACE INSPECTIONS CS-OHS-20

Our Company Working for a Healthier Future. Asbestos Services Uniquely Experienced

Safety Department. Issue Date: 29 Sep. 14 Approval Date: 29 Sep. 14. Occupational Hygiene

HEALTH AND SAFETY POLICY STATEMENT AND ARRANGMENTS MANUAL

Northern Arizona University Asbestos O&M Program Second Revision: Implemented Feb 23, 2017

Australian Canoeing Limited Workplace Health & Safety Policy

Incident and Hazard Reporting, Investigation and Corrective Actions Procedure

HEALTH AND SAFETY POLICY AND PROCEDURES

HEALTH AND SAFETY POLICY

Safe Storage of Hazardous Chemicals Policy

HEALTH AND SAFETY POLICY STUDLEY HIGH SCHOOL

Health & Safety Policy

Peninsula Dental Social Enterprise (PDSE)

Incident Reporting and Investigation Guideline

HEALTH & SAFETY POLICY

HEALTH AND SAFETY POLICY 2010

DEPARTMENT OF LABOUR. Government Notice. R: February 2002 OCCUPATIONAL HEALTH AND SAFETY ACT, 1993 (ACT NO. 85 OF 1993)

Health and Safety Policy Part 1 Policy and organisation

Personal Protective Equipment Procedure

ST MICHAEL S CHURCH SCHOOL HEALTH AND SAFETY POLICY

CSOHS Procurement Policy For St Ambrose Catholic Primary School, Pottsville

ASBESTOS ABATEMENT AND DEMOLITION/RENOVATION NOTIFICATION FORM

VAUGHAN PRIMARY SCHOOL HEALTH AND SAFETY POLICY

9. GOVERNANCE. Policy 9.13 WORK HEALTH SAFETY POLICY

HEALTH & SAFETY POLICY. 1. Policy Schedule. Date of last review: October Date of next review: September 2018.

Occupational Health and Safety Act, 1993 Asbestos Regulations, 2001

Transcription:

Asbestos Management Plan Commercial Services and Development, University of Tasmania Prepared by: Alan Mason Risk and Compliance Officer Infrastructure Planning and Compliance Unit Commercial Services & Development Version 1.3, 2016 Version control - Last Saved on 25/02/2016

Contents Introduction and governance... 1 What is ACM?... 1 Where does ACM occur?... 2 Management strategy... 2 Financial strategy... 3 Roles and responsibilities... 3 Reporting... 5 Management plan review... 5 Asbestos management procedures... 5 Asbestos register... 5 Action plan schedule (CSD staff sample included)... 6 Version Details By Date 1.0 Original Draft Alan Mason 13 Feb 2014 1.1 Framework added, reformatted sections, Barry Russell 24 Feb 2014 general content added 1.2 Typos updated Barry Russell 17 Jul 2014 1.3 Proofread FB 25 Feb 2016 University of Tasmania Asbestos Management Plan Page 2

Introduction and governance The University of Tasmania is committed to maintaining the health and safety of staff, students, contractors and visitors. The University aims to eliminate exposure to asbestos where reasonably practicable via the identification and removal of asbestos from the workplace. Where elimination is not possible, exposure is to be minimised so far as is reasonably practicable. Figure 1: University of Tasmania Asbestos Management Governance Framework Requirements for the management of asbestos in the workplace are outlined in Chapter 8 of the Tasmanian Work Health and Safety Regulations of 2012. In particular: S425 outlines requirements for an Asbestos register. S429 outlines requirements for an Asbestos management plan. Further guidance on asbestos in the workplace is also provided in the following Workplace Standards Tasmania Codes of Practice: How to Manage and Control Asbestos in the Workplace How to Safely Remove Asbestos. What is ACM? Asbestos-containing material (ACM) means any material or thing that, as part of its design, contains asbestos. Types of asbestos include: Friable asbestos: any material in a powder form or that can be crumpled, pulverised or reduced to powder by hand pressure University of Tasmania Asbestos Management Plan Page 1

Non-friable asbestos: any material containing asbestos that is not friable asbestos, including material containing asbestos fibres reinforced with a bonding compound Respirable asbestos: any asbestos fibre that: o o is less than 3 microns wide is more than 5 microns long o has a length to width ratio of more than 3:1. Where does ACM occur? ACM can be found in various forms in University buildings constructed before 2003 and in some specialist equipment present in laboratories and workshops. Friable asbestos may be present in, amongst other locations: plant rooms as lagged piping or insulation ceiling, wall cavity and underfloor spaces as lagged piping or insulation. Non-friable asbestos may be present in, amongst other locations: floor and wall tiles wall panelling ceiling and soffit panels doors. ACM may be identified at the University via the following means: information contained on the Asbestos Register hazard inspections in situ markings or warning signs general observations construction, demolition or refurbishment activity. Management strategy Once identified, ACM will be assessed in accordance with the hierarchy of control set out in the University s WHS Risk Management Guidelines. The inherent risk of human exposure may be controlled via a range of means: removal enclosure encapsulation or sealing leaving in situ and marking or labelling. The control measure decided upon for any given ACM item and the date any actions completed will be made known to staff and contractors via the University s Asbestos Register. ACM items found to exhibit a risk of potential human exposure will be removed or treated according to the following timeframes: High Risk: removed or enclosed/ encapsulated and marked within 3 months University of Tasmania Asbestos Management Plan Page 2

Medium Risk: enclosed, encapsulated and marked within 3 to 6 months Low Risk: enclosed, encapsulated and marked within 6 to 12 months. Items that exhibit low risk having been enclosed or encapsulated shall be periodically reinspected, usually at 3 yearly intervals. Evidence of reinspection shall be recorded on the Asbestos Register. Financial strategy Inspection and testing of ACM in the University s base building infrastructure workplace is funded via the CSD WHS Works Program. Removal, encasement, encapsulation and marking of ACM in the University s base building infrastructure is funded via the CSD backlog maintenance program or by individual building redevelopment project budgets. ACM found in teaching or research equipment of faculty or organisational units must be financially managed by the faculty or organisational unit. Physical management of ACM in these situations is the responsibility of CSD. Roles and responsibilities Officers are responsible for ensuring: This procedure is implemented effectively within their area of responsibility; including the identification of asbestos by a competent person, and ensuring relevant workers and other persons are appropriately trained. Organisational unit specific guidelines are developed where necessary, and that they are consistent with the information contained in this procedure. All workers are made aware of the location of any asbestos they may disturb or come into contact with, and that they have access to any relevant asbestos monitoring results. The presence and location of asbestos at the University is clearly indicated. An asbestos management plan is developed and maintained. An asbestos register is maintained, reviewed and readily available to workers and other persons at the University. Permit to work (PTW) issue officers (project managers/supervisors) are responsible for: authorising and coordinating asbestos work, including distribution of information within the work area and verifying the implementation of controls ensuring that a project risk assessment is completed prior to any work involving asbestos, and recorded in the asbestos register in the event of demolition work involving asbestos, ensuring that the contractor notifies the Director of Workplace Standards Tasmania of the presence of asbestos ensuring that the Director of Workplace Standards Tasmania is notified in writing of asbestos removal work where required ensuring that all University staff and union representatives are informed as necessary of asbestos-related works in accordance with the legislated ACM management guidelines University of Tasmania Asbestos Management Plan Page 3

ensuring that workers engaged to carry out removal work or maintenance work on asbestos are trained in the identification and safe handling of, and appropriate controls for, asbestos, and appropriate training records are kept ensuring that ACM clearance certificates are in place prior to reoccupying the treatment space. Manager/Supervisors are responsible for ensuring: The exposure of a person at the University to airborne asbestos fibres is eliminated, or if this is not reasonably practicable, minimised. The exposure standard for asbestos is not exceeded. Appropriate records relating to asbestos-related activities are kept, including any health surveillance records for at least 40 years. Workers engaged to carry out removal work or maintenance work on asbestos, are trained in the identification and safe handling of, and appropriate controls for, asbestos, and appropriate training records are kept. Workers do not use, or they do not direct or allow a worker to use equipment on asbestos that causes the release of airborne asbestos fibres, other than nominated equipment which may only be used in controlled circumstances. Appropriate action and notification is undertaken in the event of airborne asbestos fibres being released. The Infrastructure Planning and Compliance Unit within Commercial Services & Development is responsible for ensuring: All reasonable steps are taken to identify asbestos at the University. Risk assessments are undertaken and records kept on the potential exposure to airborne asbestos fibres of any worker working in areas containing asbestos. Measures are implemented to minimise the potential for workers to be exposed to airborne asbestos fibres. Workers are made aware of all known asbestos on site that they could be exposed to, and the location of the asbestos register. All known asbestos has been clearly labelled. The implementation and effectiveness of this procedure is monitored. All workers and other persons are responsible for ensuring: Any work involving the possibility of exposure to airborne asbestos fibre is carried out in accordance with this procedure and any information, training or instruction they have received. They notify the relevant organisational unit officer of any identified asbestos or suspected asbestos containing products not included on the relevant asbestos register. They wear personal protective equipment as required. They consider whether work that they are about to do will disturb asbestos, with reference to the relevant asbestos register. University of Tasmania Asbestos Management Plan Page 4

Reporting Day to day Maintenance, construction and refurbishment works discovering ACM shall report all instances to the CSD works supervisor or project manager upon discovery. All discovered ACM will be added to the UTAS Asbestos Register and notification shall be passed to central WHS and Workplace Standards Tasmania or other state regulators as appropriate in accordance with the legislated management guidelines. Updates to the register will be reported to all CSD maintenance and works supervisors and controllers. Monthly ACM activity shall be reported to the CSD Associate Directors Meeting as part of the WHS issues communication requirements. Proposed current high-risk ACM activity shall be reported to the CSD Associate Directors Meeting A summary of ACM financial liability shall be reported to the CSD Associate Directors Meeting Quarterly A summary of ACM activity shall be reported to the UTAS WHS Committee as part of the WHS issues communication requirements. Proposed current high risk ACM activity shall be reported to the UTAS WHS Committee with project timeless A summary of ACM financial liability shall be reported to the UTAS WHS Committee. Management plan review This Asbestos Management Plan and associated Asbestos Register shall be reviewed every 12 months and updated accordingly. Asbestos management procedures Management of Asbestos at University of Tasmania premises shall be in accordance with the University s Asbestos Procedure and relevant Worksafe Tasmania Codes of Practice. The University s procedures can be found at the CSD WHS website at www.utas.edu.au/commercialservices-development/work-health-and-safety Asbestos register The UTAS asbestos register (see Figure 2 on the next page) can be viewed online by all staff and works contractors. The register can be found at: https://sisfm.admin.utas.edu.au/unitasreports/haz_asbestos/hazreportexternal.aspx#. Reports are provided to an individual building level. This register contains records of all known ACM items at UTAS as well as records of all other items that have tested negative for asbestos occurrence. University of Tasmania Asbestos Management Plan Page 5

Figure 2: Screen shot from the University s Asbestos Register (staff view) Elements recorded are: building, building level and room location asbestos-containing item description ACM status (positive, negative, other) ACM type if tested, sample number ACM condition and inherent risk factor likelihood of human exposure reinspection frequency, time based on risk factor actions taken or recommended actions name of inspection agency reinspection completion date. Action plan schedule (CSD staff sample included) Newly identified ACM items and items requiring removal, enclosure, encapsulation and marking shall have works scheduled via action plan timeframes identified in the University s Asbestos Register. Re-inspect programs and individual ACM activity tasks are scheduled via the Work Request System work order notification system. Below is a web-based quick access view of the register for CSD works supervisors and project managers. University of Tasmania Asbestos Management Plan Page 6

Figure 3: Screen shot from the University s Asbestos Register (public view) The Archibus register contains substantially more detailed information if required. University of Tasmania Asbestos Management Plan Page 1