ASSESSMENT OF NUCLEAR OPERATIONS AT THE LAGUNA VERDE NUCLEAR POWER PLANT, MEXICO

Similar documents
Outage dates (duration): September 5, 1996 to May 27, 1999 (2.7 years) Reactor age when outage began: 8.8 years

I. Summary. Commercial operation commencement date April , February , June ,

Fluorine Gas Mist Pot Fails

Gasket Failure Causes Leak

IAEA SAFETY STANDARDS SERIES. GENERAL SAFETY REQUIREMENTS No. GSR Part 1 (Rev.1)

Wrong PSV Found Installed in Field

Defective Backhoe Breaks Line

Functions important to nuclear power plant safety, and training and qualification of personnel

Crane Bashes Pipes. Lessons Learned. Volume 03 Issue USW

EXTRAORDINARY PUBLISHED BY AUTHORITY. ISLAMABAD, THURSDAY, March 1, 2012

NATIONAL NUCLEAR REGULATOR

DIRECTIVES. COUNCIL DIRECTIVE 2009/71/EURATOM of 25 June 2009 establishing a Community framework for the nuclear safety of nuclear installations

NORTHWESTERN UNIVERSITY PROJECT NAME JOB # ISSUED: 03/29/2017

NEI [Revision 0] Guidelines for a Certified Fuel Handler Training and Retraining Program

1. LEGISLATIVE AND REGULATORY FRAMEWORK LEARNING OBJECTIVES FOR SECTION 1. Legislative and Regulatory Framework

Worker s Arm Pulled Into Belt and Pulley

LEGISLATIVE ACTS AND OTHER INSTRUMENTS COUNCIL DIRECTIVE establishing a Community framework for the nuclear safety of nuclear installations

As amended upto 31 1st December 2015

X STANDARD REVIEW PLAN

ES-301 Administrative Topics Outline Form ES-301-1

This document describes the University s processes for reporting and investigating health and safety Incidents and Near Misses.

Life Extension of Nuclear Power Plants

Regulations on the Safety of Nuclear Power Plants Operation (PAK/913)

Baler Gone Wild! Lessons Learned. Volume 03 Issue USW

EU Stress Tests and National Action Plans

1.01 To implement procedures to identify hazards at the University of Windsor.

Convention on Nuclear Safety 7 th Review Meeting 2017

The Code of Conduct on the Safety of Research Reactors

Pars Oil & Gas Company HEALTH, SAFETY AND ENVIRONMENT PROCEDURE. HSE Anomaly Reporting Procedure DOCUMENT ID - PR-74-POGC-002 REVISION 0.

HEALTH AND SAFETY POLICY

Subj: CHANGE OR EXCHANGE OF COMMAND OF NUCLEAR POWERED SHIPS. Encl: (1) Engineering Department Change of Command Inspection List

GENERAL HEALTH AND SAFETY POLICY

Licensing of Nuclear Installations

REGULATORY DOCUMENTS. The main classes of regulatory documents developed by the CNSC are:

Incident Reporting, Notification, and Review Procedure

Decommissioning Licensing Process of Nuclear Installations in Spain Cristina CORREA SÁINZ.

Topic 3 Contribute to safe work practices in the workplace 43

HEALTH AND SAFETY POLICY 2010

SEMEM3-05 Carrying out fault diagnosis on mechanical equipment

INTEGRATED REGULATORY REVIEW SERVICE (IRRS)

BASINGSTOKE AND NORTH HAMPSHIRE HOSPITALS NHS FOUNDATION TRUST

COMDTPUB P16721 NVIC August 25, 2014

UV21096 Health and safety in catering and hospitality

HERCA Guidance Implementation of RPE and RPO requirements of BSS Directive Nov Index

SEMEMI SQA Unit Code H2AK 04 Carrying out fault location on mechanical equipment

No. 22 in In accordance to articles 152 & 108 / second of Labor Law no. (71) of 1987 we decided to issue the following instructions:

Decommissioning Licensing Process of Nuclear Installations in Spain Cristina CORREA SÁINZ.

Radiation Protection Program Updates

INSTRUMENTATION TECHNICIAN I/II/III

Overview of the Regulatory Framework for the Safety of Nuclear Power Plants in Romania

EMERGENCY PREPAREDNESS AND RESPONSE TECHNICAL SERVICES CATALOGUE

Effective discharge from hospital: the role of communication of home circumstances February 2017

February 8, 2017 SUBJECT: GRAND GULF NUCLEAR STATION - NRC INTEGRATED INSPECTION REPORT /

WHS-56 Incident Reporting and Investigation

GAO NUCLEAR REGULATION. Progress Made in Emergency Preparedness at Indian Point 2, but Additional Improvements Needed

SAN JOAQUIN VALLEY UNIFIED AIR POLLUTION CONTROL DISTRICT COMPLIANCE DEPARTMENT COM 2035

EQUIPMENT MANAGEMENT MEDICAL EQUIPMENT: EC , EC UTILITY SYSTEMS: EC , EC

Emergency Preparedness Near Nuclear Power Plants

Certification of Persons Working at Nuclear Power Plants

B. All of the documents in this RFP form the Basis-of-Design for this project.

Operational Experience Log Book

Global Security Evolution

MISSION REPORT ON THE INTEGRATED NUCLEAR INFRASTRUCTURE REVIEW (INIR)

POSITON DESCRIPTION TUG ENGINEER

THE IAEA FUKUSHIMA REPORT AND THE IMPLICATIONS FOR NUCLEAR SAFETY AND EMERGENCY PREPAREDNESS

EPSC s activities are directed towards four principal objectives:

NRC INSPECTION MANUAL STSB

SOMETHING IS ROTTEN IN THE STATE OF THE NHS

National Patient Safety Agency Root Cause Analysis (RCA) Investigation

Level 5 Diploma in Occupational Health and Safety Practice ( )

Regulatory framework and safety requirements for new (gen III) reactors

KENTUCKY HOSPITAL ASSOCIATION OVERHEAD EMERGENCY CODES FREQUENTLY ASKED QUESTIONS

Health and Safety Policy

PROMPR22 Carrying out fault diagnosis on mechanical equipment

TEMPLE UNIVERSITY ENVIRONMENTAL HEALTH AND RADIATION SAFETY

SUP 08 Operational procedures for Medical Gas Pipeline Systems (MGPS) Unified procedures for use within NHS Scotland

Operating Facilities Programme. Assessment of the Periodic Review of Safety for the A** Facility at Aldermaston

The Mineral Products Association

North York General Hospital Policy Manual

Incident Information

Health and Safety Policy

Fundamental Principles

Accident/Incident Investigation Plan

Vietnam Agency for Radiation and Nuclear Safety (VARANS), 113 Tran Duy Hung, Hanoi, Vietnam Corresponding author: Luu Nam Hai

ONR GUIDE LC22: MODIFICATION OR EXPERIMENT ON EXISTING PLANT. Nuclear Safety Technical Inspection Guide. NS-INSP-GD-022 Revision 3 TABLE OF CONTENTS

The IAEA OSART Review. Attachment 1 Tokyo Electric Power Company

IAEA Safety Standards for Regulatory Bodies Overview and Recent Development

SHOULD I APPLY FOR AN ARC DECRA? GUIDELINES

Dominic Cox Royal Free Hospital London Joan Pearson Leeds General Infirmary

TAHOE CITY PUBLIC UTILITY DISTRICT Job Description

NUCLEAR SAFETY PROGRAM

Submission for the Midwifery Practice Scheme - Second Consultation Paper Including a response to the following papers:

SHOULD I APPLY FOR AN ARC FUTURE FELLOWSHIP? GUIDELINES

EMPLOYMENT SERVICES INJURY & ILLNESS PREVENTION PROGRAM THINK SAFETY FIRST CPPFOUNDATION.COM

A. General provisions and other electrical systems are specified in other Sections of Division 26.

Physical Protection of Nuclear Installations After 11 September 2001

R&D Tax Credits. Energy and natural resources sector

Redirection of DPRK Nuclear Talent to the LWR Project. Authors: John B. Mulligan, HanKwon Choi. 1

PROCEDURE Health & Safety Roles and Responsibilities. Number: J 0101 Date Published: 13 June 2017

Top Ten Health Technology Hazards

Transcription:

ASSESSMENT OF NUCLEAR OPERATIONS AT THE LAGUNA VERDE NUCLEAR POWER PLANT, MEXICO CLIENT: GREENPEACE INTERNATIONAL REPORT REF NO 15 MAY 2007 First Issued 3 April 2000 Large & Associates, London The Gatehouse 1-2 Repository Road Ha Ha Rd Woolwich London SE18 4BQ 44[0]181 316 4236 317 2860 fax 44[0]181 317 2859

NUCLEAR SAFETY AT LAGUNA VERDE WANO FIELD REPORTS AND PEER REVIEW The duplex BWR reactors at Laguna Verde, Veracruz 1 WANO Peer Review. 2 have been subject to a The review mechanism involved a team of inspectors visiting the power plant and compiling a series of field and observation reports. 3 What has been made available is a compilation of the confidential WANO inspectors reports which are unlikely to be included in the final version of the peer review but, that said, these reports provide an invaluable insight into operations at Laguna Verde NPP. This assessment comprised two parts: PART I SUMMARY OF ASSESSMENT INSTITUTIONAL FAILURE The WANO field reports identify a number of managerial and organisational areas that are weak and/or neglected at Laguna Verde, so much so that this NPP, its organisation structures and corporate management might be considered to be at the 4 edge of inst itutional failure. Institutional failure is that where related causative factors and events combine and act in such a way as to bring the system overall down. The elements of institutional failure are not so straightforward to be categorised in a classical fashion, such as mechanical breakdown, etc., being very much deeper in that each relates to or is a type of human error or human behaviour active in the corporate body. This type of failure is not unique to nuclear plants and facilities. However, because these are acknowledged highly hazardous, the defence-in-depth approach (involving duplication, diversity and redundancy of equipment) means that an electro-mechanical failure should not provoke collapse of the plant safety regime. 1 2 3 4 Laguna Verde GE Boiling Water Reactors (BWR%) located about 200km south-east of Mexico City of 628 and 654Wme capacity, commissioned in July 1990 and April 1995, World Association of Nuclear Operators (WANO) Peer Review completed to draft stage by January 2000. The ~200 page WANO report passed to Large & Associates by Greenpeace International is marked DRAFT WANO PEER REVIEW FIELD NOTES PRIVATE UNEDITED WORKING COPY AND DATED November 1999 and it contains 63 separate field reports not all of which are reviewed here. Weaver K R A Conceptual Study of the Role of the Institution in Safety, Proc Int Symp Quality in Nuclear Power Plant Operation, Toronto 1989 Page 2 of 10

This means that accidents at nuclear facilities must involve some recognisable element of institutional failure. THE CAUSATIVE ELEMENTS OF INSTITUTIONAL FAILURE The underlying causative factors of institutional failure can be extracted from three past nuclear accidents each of which should not have developed to such severity if the causative affect had been electro-mechanical alone. At Three Mile Island, for example, inadequate resources, both human and material, together with long-term lack of maintenance, lack off operator training, and deficiencies in Metropolitan Edison s own quality assurance plan, 5 all contributed to the accident. At Windscale, in 1957, there were resource deficiencies including an almost complete lack of documentation relating to the critical Wigner energy annealing operation that triggered the core fire. 6 Windscale and TMI accidents both include a failure to allocate adequate or appropriate resources. The accident at Chernobyl examples another institutional failure causative element. During the hours of build up to the accident at Chernobyl, the operatives became determined to complete a planned test even though as each hour of delay past, imposed by the regional grid controller, the reactor was rendered more unstable. 7 In this situation a production imperative dominated the safety rationale, it injected a sense of urgency to get the job done come what may. There are two other distinct causative elements that relate to failure to understand the limitations of the safety regime and if, indeed, the safety regime is deteriorating to an unsafe situation. A year before the TMI accident the similar Davis-Besse NPP experienced a loss-offeedwater transient and although this was recognised to provide opportunity for inappropriate operator actions, the warning signal was not heeded. At TMI the same transient triggered a whole cascade of failures following the automatic isolation of the condensate treatment plant. Warning signals given by past events are very important because proper detection and understanding of these provides for future signals to be correctly interpreted and acted upon. This type of omission is failure to acknowledge or recognise an unsatisfactory or deteriorating safety 5 6 7 Kemeny J G Report to the President s Commission on the Accident at Three Mile Island, US Gov Printing Office, Washington 1979 Penney W Report on the Accident at Windscale No 1 Pile on 10 th October 1957, Report to the Chair of the United Kingdom Atomic Energy Authority, October 19557 The so-called xenon trap USSR State Committee on the Accident at Chernobyl Nuclear Power Plant and its Consequences, IAEA Post Accident Meeting August 1986 Page 3 of 10

situation. Lack of appreciation of the technical limitations of the safety regime stems from failure at senior institutional levels to define the links within the safety regime. This can result in over demand on the performance of particular technical systems and/or the resources provide to it. This is illustrated at TMI where Kemeny reported a widespread lack of expertise throughout the organisation and, similarly, at Chernobyl where senior management levels at the plant and in MinAtom expressed absolute confidence in the benign safety nature to the RBMK reactor system. APPLYING INSTITUTIONAL FAILURE TO LAGUNA VERDE With hindsight, these causative elements can be salvaged in the aftermath of a nuclear accident by picking through the evidence and history of events that led to the institutional failure. However, the challenge here is whether the elements of institutional failure can be identified before a physical breakdown of the plant occurs. That is, is the situation at Laguna Verde, as reported by the WANO inspectors, indicative of developing institutional failure or is the plant s management simply in a morass? If Laguna Verde s management is befuddled then this, as inefficient and confused as it seems to be, may be a relatively stable position, although the overall risk of serious accident might be higher. If Laguna Verde can be categorised as being somewhere along the path to institutional failure, then the situation might be unstable with the plant being doomed to a serious accident at some time in the future. So it is useful to assess the WANO field reports in terms of the causative elements of institutional failure identified earlier:- i) Failure to Allocate Appropriate o r Adequate Resources At Laguna Verde, Resources applies to equipment, procedural documentation and personnel. In equipment, there are many failures in the provision and correct identification of spare parts and maintenance is not properly resourced: For example, one single valve caused a reactor scram in 1994 and, although the problem with the valve was identified then, nothing was done until 1999 when a virtually identical scram was again caused by the same malfunctioning valve. Technical and procedural support to the operatives is at a poor level if not, in some Page 4 of 10

critical areas, completely absent: The lack of rigid procedures seems to have seeded a novel mindset at the plant, inasmuch that in troubleshooting a demineraliser problem with the reactor at full power, the technicians not only adopted their own ad hoc procedures without a written plan but believed, totally against the administrative protocol of the plant, that a written plan was not required. There were also major deficiencies in staffing: The simulator supervisors were so understaffed that they had little time to set up the simulator correctly to the extent that it operated in an unstable mode, thereby denying the staff effective and realistic training. ii) Failure To Acknowledge an Unsatisfactory or Deteriorating Safety Environment This relates to detecting and understanding warning signals and, particularly, in amassing and reviewing past warning signals. At Laguna Verde, the WANO inspectors expressed particular concern over the investigation of incidents in that root cause recommendations are sometimes ignored because of the available budget, Repeat events may have occurred because corrective actions were not implemented, Near miss events are not recorded, the causes of the 1999 scram were never fully investigated, and that although in place, the Independent Quality Assurance group had issued 120 recommendations but, to date, no feedback from other station staff had been received. In addition, the high incidence of defective instrumentation, temporary wiring installations, storage of combustibles in high risk areas, absence of disciplined preventative maintenance, etc., although readily identified by operatives on the ground neither they nor, as it seems, their supervisors were prepared to remedy these shortfalls. Individually, these defective and malfunctioning pieces of equipment might be considered niggling but, viewed collectively, such could represent a serious intrusion into the plant s safety capability. The point here is that it seems that no individual at Laguna Verde seems to have been charged with and grasped the deterioration of the plant s overall safety environment. iii) Failure to Recognise the Limitations o f the Safety Envelope Quite astonishingly, the WANO inspectors state that, on one hand, the senior supervisors considered that Safety culture is not a station recognised issue whereas, on the other, the Managers believed there to be a lack of safety culture at all levels, noting that although they felt responsible for safety culture they stated Page 5 of 10

that this was a new project and they had just started getting familia r with it. Also, the WANO reports frequently touch upon the lack of expertise and training of the operatives, managers and supervisors at Laguna Verde. For example, in the key safety reactor engineering area, upon interviewing a reactor engineer, the supervisor and manager on the reactor event relating to on the fuel core load lines, the field reports concludes This is an example indicating a lack of fundamental reactor engineering knowledge. The field reports also conclude that there is no formal training for reactor engineers, that there is too much reliance upon on-the-job training and, importantly, no individual is presently being trained up to replace Reactor Engineering Supervisor at his retirement in 1 year hence. iv) Production Imperative The sense of the production imperative is not discussed in the WANO field reports although there is an overriding impression that at Laguna Verde there exists an incentive to get-the-job done come what may. This is illustrated by the lack of written procedures, the clearly reactive approach to maintenance, 8 group meetings at which open discussion is frowned upon and, what seems to be, the ineffectiveness of the root cause analysis, particular at its presentation and lack of implementation at the senior CROS level 9 because root cause recommendations are somet imes ignored because of available budget. LAGUNA VERDE AT THE CROSSROADS OF INSTITUTIONAL FAILURE? Obviously, organisational structure plays an important role in institutional failure: If the structure is too complex it is difficult to establish well defined rules and procedures that apply across a large number of organisational layers, but if overly simplified there may not be sufficient opportunity for checks and cross checks to be applied. The organisational structure at Laguna Verde seems relatively straightforward but hierarchal, if not autocratic, in how it manages important safety issues. For example, the opportunity of senior supervisors to reject the root cause recommendations on budgetary grounds and that the independent quality 8 9 And also ad hoc, particularly as reported for the electrical switching plant. Staff interviewed stated that root cause analysis personnel do not get any respect with making representations to CROS. They stated that CROS would often tell them that if they did not get to the root cause and [then] change the root cause. They do not argue with CROS because it is not good to buck the system. Page 6 of 10

assurance group had received no feedback on any of the 120 recommendations, both suggest that the corporate management of the plant cannot or will not segregate safety from production and budgetary influences. Moreover, there is the absurd difference of opinion between the line managers and the senior supervisors as to whether the safety culture is in place and adequate across the plant. If this dichotomy stands then, together with the sense that the flow of information is only down from and not up to senior management, it suggests that the corporate management at Laguna Verde does not recognise that safety is not solely the responsibility of those at the man-machine interface. Given this, the WANO field reports suggest that Laguna Verde is not simply in a morass but well on the road to institutional failure. 10 10 The text of the WANO letter to the plant operator of 7 January, 2000 is disturbing inasmuch that it states Issues such as those identified at Laguna Verde have existed at other nuclear stations in the past and still exist at other operating stations in North America today and As discussed with you... several plants in the United States and Canada are presently operating with a similar level of performance. These plants are currently operating with the full agreement of their governments, utilities, and WANO. In addition, a number of plants with the same level of performance have been operated in the past. Page 7 of 10

PART II ASSESSMENT OF THE WANO REPORTS IN DETAIL Breaking down the WANO field reports into the relatively broad categories of maintenance, setting down of work and quality control procedures, spare parts management, training, health and safety and forward planning:- TABLE 1 SUMMARY OF LAGUNA VERDE WEAKNESSES HEADING LEGEND: A MAINTENANCE FAILURES B LACK OF PROCEDURES C SPARES SHORTAGES D LACK OF TRAINING AND HUMAN ERRORS/OMISSIONS E FAILURES IN HEALTH AND SAFETY HOUSEKEEPING F ABSENCE OF FORWARD PLANNING WANA Review Group No Examples A B C D E F EQUIPMENT PERFORMANCE AND MATERIAL CONDITION & EMERGENCY STANDBY AND NUCLEAR EQUIPMENT MALFUNCTIONS AND SHORTFALLS 1 During the past two years (1998-99) there occurred 3 failures of the emergency diesel generator cover; 5 incidence of serious equipment problems in the reactivity management systems; 7 problems with equipment resulting in loss of generation, extended outage and reactor shutdowns; and 2 incidences where radioactivity cross a barrier containment. As a result of either poor or omission of regular and preventa tive maintenance, all of the emergency generator failures stemmed for failure to adequately maintain the plant, particularly the electrical switchgear; there was one incident of a reactor recirculation pump failure to include the speed permissive relays in the preventative maintenance programme; and air entrainment into the primary circuit because a valve had not been refitted with a gasket. ELECTRICAL SWITCHING EQUIPMENT Operator error and/ or inadequate training resulted in, when endeavouring to identify a fault in the demineralizer system with the reactor at full power, the operatives went about the troubleshooting without a written plan, which was required by the plant administrative protocol, although the operating personnel did not believe that a plan was required. 2 As well as the somewhat ramshackle condition of the electrical switching area and a number of shortfalls relating to health and fire safety, there are no emergency act ion s procedur es in place and the operator of the control room had received no training in the switching control room procedures. EQUIPMENT PERFORMANCE TESTING PREVENTATIVE MAINTENANCE PROGRAM AND REPORTS, MAINTENANCE PACKAGE 3 No test procedure available for the room coolers 4 29 30 34 35 39 There is no documented technical basis for the Preventative Management Program, no cross connection of failures on similar systems, unauthorised work undertaken by operatives, and workers do not always follow written work instructions, sometimes incomplete written instructions REACTOR BUILDING CONDITION 5 Leakages in both RHR A and B rooms of Unit 1 are radioactively contaminated, one hot spot is marked at 6mSv/hr dating from December 1998, the sources of contamination have not been identified and there other examples, such a only 1 light working out of 5 in the valve room, all of which suggests that maintenance and housekeeping is neither routine or effective. HEATER DRAIN SYSTEM 6 Lack of forwar d planning and spares shortages is where a heater drain system valve which initiated a reactor scram in 1994 but was not replaced then nor had been replaced/repaired through two successive refuelling outages and, in fact, this same valve initiated a reactor scram in 1999 that was virtually identical to the 1994 scram. REACTOR REFUELLING 7 A number of examples show that the training and monitoring technique and procedures adopted by operatives, technicians and supervisors are insufficient to prevent the spread of contamination. s Page 8 of 10

SAFETY CULTURE 8 Shortfalls identified in lack of effective supervision specialist and first level managers OPERATOR EXPERIENCE 9 Lack of coordination between databases, no discussion of operating experience at the morning meetings, no self-evaluation programmes in place, no priority established for operating experience. CORRECTIVE ACTION 10 Near miss events not recorded ROOT CAUSE 11 Root cause analysis failing to correctly identify the cause problems, operatives untrained with analysis equipment, long delays if root cause outcome FEBRUARY 1999 SCRAM 12 All contributory causes of scram not evaluated GROUP INTERVIEWS SUPERVISORS, MANAGERS AND TRAINING INTERVIEWS 13 14 15 16 Supervisors do not believe safety culture to be a station issue but Managers believe there to be a lack of safety culture at all levels. No human performance assessment system established. Station training programmes not implemented in a timely manner and inadequate procedural guidance. SELF EVALUATION 17 There is no focused self-evaluation programme CHEMISTRY DATA REVIEW CONTROL AND FEEDWATER SAMPLING, PURIFICATION CONDUCT OF ENGINEERING REACTOR ENGINEERING ENGINEERING RECORDS SYSTEMS ENGINEER INTERVIEW SPARE PARTS CONTROLS REACTOR BUILDING VENTILATION MAIN STEAM RELIEF VALVE TEST 18 19 20 21 Excessive frequency of chloride spiking related to poor maintenance and abnormal chemistry data and events not highlighted, may equipment leaks of oil and hydraulic fluids, combustible materials present in chemical stores, lack of protective clothing, and failures of equipment and unsatisfactory temporary modifications 22 Root cause analysis unsatisfactory for Engineering 23 24 Absence of procedures shows lack of fundamental reactor engineering practical knowledge, no formal training for reactor engineers and strong reliance upon on-the-job training, no individual being trained up to replace Reactor Engineering Supervisor upon his retirement in 1 year hence, and radiological health and safety issues present. Engineering drawing record and revisions incomplete 25 No formal training for the diesel generators, possible problems wit h the emergency air starting procedures 27 Incorrect identification of spare parts. 28 Spare parts shortages and problems of identification, health and safety issues 32 Health and safety concerns HOUSEKEEPING 33 Requires improvement FASTENERS 36 Some fasteners on equipment missing and screw threads insufficiently engaged CRANES 37 Overhead cranes in the steam relief valve test area had never been tested and no preventative management had been performed o n the refuelling machine brakes WIRE SPLICING 38 Incorrect techniques result in health and safety hazard OFF GAS SYSTEM 39 Pre-Job briefings did not include for discussion of health and safety matters PLANNING 40 Work Packages delivered at last minute, no tool list within package PRIORITISATION OF 41 Generally, everything is over-prioritised MAINTENANCE WORK INDEPENDENT SAFETY ANALYSIS GROUP FIR E PROTECTION RESPONSE SIMULATOR CREW PERFORMANCE AND EVALUATION NUCLEAR OPERATIONS WORKS ACTIVITIES ORGANISATION AND ADMINISTRATION 42 No program quality review undertaken, issued 120 recommendations but, to date, no feedback for other station staff 44 Fire protection personnel slow in response 45 57 Lack of simulator capability, broken instrument panels and shortage of information and crew response in error because reactivity management standards are incomplete, simulator has defects and identical scenarios of Units 1 and 2 produce different reactions. Staff shortages on training and unrealistic and/or unstable preset conditions preset by the simulator supervisors reduce the effectiveness of the training and evaluation of operators. 46 Longstanding equipment problems cause a scram, some safety reviews on feedwater heater controls 47 Personality conflicts between managers and higher authority, the reactivity management indicator is inaccurate and the target is too liberal at one reactivity event per month, human performance indicator is also inaccurate, no method of reviewing maintenance backlogs available Page 9 of 10

MAIN CONTROL ROOM CONDITION OPERATOR ROUNDS HUMAN REVIEW ACTIVITIES RADIATION EXPOSURE 52 CONTROLS 53 CONTAMINATION 54 CONTROL 55 INDUSTRIAL SAFETY 56 CONDENSATE 58 FILTER REPLACEMENT DOSIMETRY TRAINING 59 60 62 48 Ancillary equipment not seismically fastened, several leaking safety relief valves left leaking over 7 month period, inadequate neutron monitoring for conditions below hot shut down, and the number of lit and defeated alarms is far too high and many alarm deficiencies are not identified with problem tags root cause of June 1999 scram not fully investigated 49 Longstanding equipment problems not addressed, operators adopted unwritten procedures, 50 51 2 areas of high radiation previously unidentified, high level items in pool not identified, filter float problem in pools, and some radiological controls insufficient to prevent unplanned exposures, many personal contamination incidents were not recorded, and many work practices could contribute to the spread of contamination, workers received additional radiation exposure because they were inexperienced System engineer training not systematically developed and not consistent with the job, engineering experience is not transmitted across to the training department, emergency preparedness in engineering is incomplete, no worker qualification list exists, all manufacturing and vender manuals are in English, no overhaul plan for the diesel air compressor, operator experience not systematically included in the training programme Page 10 of 10