Community Update Brochure

Similar documents
Chapter 1 Introduction 1.0 Background

An Bord Pleanála STRATEGIC INFRASTRUCTURE DEVELOPMENT PLANNING AND DEVELOPMENT ACTS 2000 TO An Bord Pleanála Reference Number: 29S.

17. 2bn EUR. EIB Group support for key enabling technologies and technical deployment for an innovative Europe

Guidance Notes for Applying for a Licence to Generate Electricity

Manager s report on submissions received in respect of the Draft Navan Local Area Plan

Meaford Energy Centre Section 47 Planning Act 2008 Statement of Community Consultation

Chief Executive s Report on the Submissions Received on the Proposed Material Amendments to the Draft Louth County Development Plan

Seabank 3 Stakeholder and Community Consultation Strategy. Seabank 3. Stakeholder and Community Consultation Strategy. June 2013.

Adamstown Strategic Development Zone Planning Scheme Amendment No. 1. Approved by South Dublin County Council

DSO Non GPA Process. November 2010 Version 8

August All of the information listed above will be made available to the chosen consultant and should be used to inform the final study.

Generator Interconnection Facilities Study Report Franklin County, NC 50.0 MW Solar Farm Queue #384

Manager s Report on Submissions Received in respect of the Amendments to the Draft Navan Local Area Plan

SUSTAINABLE TRANSPORT - GREENWAYS

NOTICE OF PREPARATION OF AN ENVIRONMENTAL IMPACT REPORT AND SCOPING MEETING FOR THE DOWNTOWN SPECIFIC PLAN COMMENT PERIOD

Preparing a successful proposal

If any queries arise ESB Networks DAC can be contacted at or

Department of Agriculture, Environment and Rural Affairs (DAERA)

Meath County Council. Burial Ground Grant Scheme Application Form 2017

Cavan Local Community Development Committee. County Cavan LEADER Local Development Strategy 2016 EXTRACT. Section 4 LDS Action Plan

Rural Regeneration and Development Fund

Cavan County Development Board. Economic Plan

Invitation to Submit Expression of Interest and Proposal

icrag Environmental Geosciences Postgraduate Programme Supported by Geological Survey Ireland Call Document

MID Community Newsletter

Generator Interconnection Impact Study Report Bladen County, NC 75.0 MW Solar Farm Queue #377

SENIORS ALERT SCHEME Information Brochure September 2015

Generator Interconnection Impact Study Report Wayne County, NC 20.0 MW Solar Farm Queue #364

National Productivity Investment Fund for the Local Road Network Application Form

Comprehensive Plan 2009

Generator Interconnection System Impact Study Report Carteret County, NC MW Queue #297 Original Submittal Revision 1

COUNTY OF SANTA BARBARA

Global Partnership on Output-based Aid Grant Agreement

Home Energy Saving (HES) scheme - Homeowner Application Form Version 1.0

APPENDIX I AGENCY CONSULTATIONS

Local Rural Development Strategy for LAG South Antrim DEVELOPMENT STRATEGY FOR AXIS 3 NORTHERN IRELAND RURAL DEVELOPMENT PROGRAMME

INTERREG ATLANTIC AREA PROGRAMME CITIZENS SUMMARY

Public Notice U.S. ARMY CORPS OF ENGINEERS, GALVESTON DISTRICT AND TEXAS COMMISSION ON ENVIRONMENTAL QUALITY

Order of Business. D. Approval of the Statement of Proceedings/Minutes for the meeting of January 24, 2018.

XXXXX Kwalsa Phase II Project. Interconnection Facilities Study and Project Plan

Northline Solar Project

RG 102 Accreditation for the Inspection of Non-public High Voltage Electrical Systems

RESEARCH & INNOVATION (R&I) HEALTH & LIFE SCIENCES AND RENEWABLE ENERGY

AFRICA POWER VISION (APV) FEATURED PROJECT BRIEF (WEF Africa side event) 3 June Africa Power Vision (APV) Featured Project Brief

Addendum to ESAH Version 3 Supply Application

Fiji Electricity Authority. MR 323/2017 Feasibility Study of Pumped Storage Hydropower at Monasavu Request for Prices

Sandpiper Pipeline Route

Small Business Innovation Research (SBIR) Ireland

The State of Interconnection in NYS:

Home Energy Saving (HES) scheme - Homeowner Application Form Version 10.0

Home Energy Saving scheme. Application Guide Version 1.1

DUBLINE DEVELOPMENT FUND. Application Guidelines. Connecting places, peoples and pasts

MINISTRY OF ENERGY KENYA ELECTRICITY MODERNIZATION PROJECT-IDA CR Terms of Reference Power Engineering Consultant

Transport NI York Street Interchange APPENDIX A PROJECT BRIEF

Rural Business Investment Scheme

5. This statement is being made in accordance with section 47 of the Act.

A FUNDING CALL FOR TOURISM ACCOMMODATION AND ANCILLARY SERVICES

Wyoming Public Service Commission (WPSC) Biennium Strategic Plan

Published 30/11/2017. Rural Business Investment Scheme

Ocean Energy Prototype Research and Development Programme. Application Guide. Date: 18/2/2015

Guidelines on completing and submitting Banking Licence Applications

RG 103 Accreditation for the Inspection of Electrical Equipment in Quarries

REQUEST FOR QUALIFICATIONS EXECUTIVE ELECTRICAL ENGINEER I-5 ELECTRICAL SWITCH STATION UNIVERSITY OF CALIFORNIA, SAN DIEGO. CPM Project No.

PPN NETWORK NEWS. Your FREE fortnightly round-up of all that is important in the Co Monaghan community sector, delivered to your Inbox

PUBLIC SCHOOL FACILITIES ELEMENT:

NEWS RELEASE MICHIGAN ADVANCE CONSTRUCTION STARTS FOR GORDIE HOWE INTERNATIONAL BRIDGE PROJECT

NPF Submissions Forward Planning Section Department of Housing, Planning, Community and Local Government Custom House Dublin D01 W6X0

Term of Contract 15-year term, from 1 October 2018 to 31 December 2033

a) Manitoba Hydro received seven ATK or land use and occupancy proposals from First Nations and the MMF.

RESERVOIR LEGISLATION IN NORTHERN IRELAND

Mr. Sang-wan, Byun, Vice President of the EXIM Bank of Korea, Members of the Press, Distinguished Guests, Ladies and Gentlemen:

UNIVERSITY OF CALIFORNIA, SANTA CRUZ

COMMISSION DIRECTIVE 2011/18/EU

UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION

xxxxxx xxxxxx VOLUME 5: FOLDER 1 Consultation Report Chapter 1. Introduction

Request for Proposals and Specifications for a Community Solar Project

Enduring Connection Policy Stage 1 (ECP-1)

Project Co-ordinator (Northern Ireland)

CHAPTER House Bill No. 5013

Rural Business Investment Scheme

ENVIRONMENTAL IMPACT REPORT

Manager s Report Draft Meath County Development Plan TABLE OF CONTENTS

PROJECT - Have Your Say. Message from Sandy Rupprecht, CEO of NuGen MOORSIDE PROJECT

Blending European Union aid to catalyse investments

Meeting Minutes. Gate 3 Liaison Group Meeting #16. CER Office, 20 th July, Attendance by Liaison Group Members or Approved Substitute

City of Bellingham Request for Proposals for Consultant Services Fairhaven Highlands Environmental Impact Statement RFP#26B-2007

Work with us as evaluator or reviewer!

Site Safety Plus. Site Management Safety Training Scheme Refresher (SMSTS-R) Course appendix H

Rural Business Investment Scheme

Strategic Policy Environment Levy

Contents. The Rural Development (LEADER) Programme Co. Kildare s Local Development Strategy Who can apply?...

BUILDING POSITIVE RELATIONS - PEACE ACTION PLAN

Request for Qualifications Professional Engineering Services

CITY OF SACRAMENTO COMMUNITY DEVELOPMENT CALIFORNIA 300 Richards Blvd. DEPARTMENT

INVENERGY LLC Meeting Summary Report Northline Solar Project

Appendix F Public Meeting Summaries. F1: May 2013 Public Meeting Summary F2: September 2013 Public Meeting Summary

Achievement Awards. Virginia Association of Counties APPLICATION FORM

Small Firms Association. Submission on the National Planning Framework Ireland 2040 Our Plan

Transposition of Aviation Directive. Aviation in EU ETS Workshop 30 June 2009

EUROPARC Conference 2015

Transcription:

North-South 400kV Interconnection Development Community Update Brochure June 2015 Part Funded by the EU-TEN-E Initiative Application for Planning Approval to An Bord Pleanála

Project Background The North-South 400kV Interconnection Development is part of a strategic cross-border electricity transmission infrastructure scheme undertaken jointly by EirGrid and System Operator Northern Ireland (SONI) the proposed interconnector. The application for planning approval by EirGrid to An Bord Pleanála relates to that portion of the overall proposed interconnector within Ireland (which runs through counties Monaghan, Cavan and Meath) from the existing ESB 400kV substation at Woodland, County Meath to the border at Lemgare, County Monaghan. The application by SONI for that portion of the proposed interconnector in Northern Ireland (from the border to a planned substation on the Northern Ireland transmission network, in Turleenan, County Tyrone), is currently with the DOE Planning Service in Northern Ireland. Project Drivers The project will provide a second high-capacity interconnector between the two transmission systems on the island of Ireland, delivering benefits to householders, communities, businesses and the economy. Improve Competition Improve competition the proposed interconnector will improve the efficiency of the all-island single electricity market. Secure supply of electricity enhance the security of the electricity supply throughout the island of Ireland which is essential for economic growth, the creation of jobs and improving the standard of living and quality of life for all. Secure Electricity Supply North-South 400kV Interconnection Development Renewable Energy Integration Help Ireland meet its 40% renewable electricity target allow more renewable energy to be connected to the electricity network, reducing our production of greenhouse gases and our reliance on imported fossil fuels.

EirGrid is Submitting its Application for Approval to An Bord Pleanála EirGrid is in the process of submitting an application for approval to An Bord Pleanála for the North-South 400kV Interconnection Development. A ten week period of statutory public consultation will commence one week after the date of submission. This brochure provides a summary of the planning process and the documents that EirGrid is submitting to An Bord Pleanála. An Bord Pleanála is the competent authority responsible for assessing and determining applications for strategic infrastructure developments. If you wish to make a submission in relation to the application for approval you can do so in writing to An Bord Pleanála directly. An Bord Pleanála has the discretion to conduct an oral hearing during which members of the public may also make submissions and observations with regard to the project. The development comprises: A new single-circuit 400kV overhead transmission line in counties Monaghan, Cavan and Meath Modifications to three existing 110kV overhead lines A new 400kV circuit along the unused northern side of the Oldstreet to Woodland 400kV line Associated works within and immediately adjacent to the existing Woodland substation in Meath An associated temporary materials construction storage yard in County Monaghan Associated permanent and temporary construction and excavation works In March 2015 EirGrid published a proposed line route for the project that forms the basis of the planning application to be submitted to An Bord Pleanála. The line design has taken into account requests from stakeholders, mostly landowners, for localised changes to the line design. These were evaluated in accordance with the criteria set out in the Preferred Project Solution Report, published in July 2013, and many were accommodated. The proposed line route is described in a series of maps contained in Volume 3B Figures of the EIS. These detailed maps show the location of all towers (intermediate, angle and transposition) in addition to many of the constraints that the proposed line seeks to avoid. Mitigation Measures The proposed mitigation measures are extensive. The EIS and NIS should be reviewed for a full understanding of the measures proposed in relation to the development. By way of example, these include a Construction Environmental Management Plan; Traffic Management Plan; appointment of a wayleave agent; appointment of an ecological clerk of works; temporary silt screens; controlling work practices; supervision of construction works; and appointment of a project archaeologist. Public Display The application documentation, including the Environmental Impact Statement (EIS) and Natura Impact Statement (NIS), will be placed on public display during the ten week period of public consultation as follows: On-line: The application documentation (including the EIS and NIS) may be viewed/downloaded at www.eirgridnorthsouthinterconnector.ie Hard copies may be viewed at the offices of: An Bord Pleanála, 64 Marlborough Street, Dublin 1 Meath County Council, County Hall, Navan, County Meath Cavan County Council, Cavan Courthouse, Farnham Street, Cavan, County Cavan Monaghan County Council, County Offices, The Glen, Monaghan, County Monaghan EirGrid Project Information Centres: Navan Information Centre, 10a Kennedy House, Kennedy Road, Navan, County Meath every Tuesday and Friday between 12 noon and 7pm. Carrickmacross Information Centre, Carrickmacross Workhouse, Shercock Road, Carrickmacross, County Monaghan every Monday and Thursday between 12 noon and 7pm. Cootehill Information Centre, Cootehill Enterprise & Technology Centre, Cootehill, County Cavan every Wednesday between 12 noon and 7pm. In addition, the Navan, Carrickmacross and Cootehill Information centres will be open every day between 12 noon and 7pm for the following two weeks: Tuesday 16th to Monday 22nd June 2015 between 12 noon and 7pm. Monday 17th to Friday 21st August 2015 between 12 noon and 7pm. Submissions/Observations Submissions and/or observations in relation to the application for the proposed development may be made in writing only to An Bord Pleanála, from Tuesday 16th June to Monday 24th August 2015, and shall be accompanied by the statutory fee of 50. Post: An Bord Pleanála, 64 Marlborough Street, Dublin 1.

Guide to the Planning Application Documents The application documentation is presented in five volumes, all of which are available for review at the specified locations as detailed on the previous page. In addition, the application documentation is available in the Irish language at each of these locations. VOLUME 1 Statutory Particulars and Drawings Volume 1A Statutory Particulars Notices, Forms, etc. Volume 1B Planning Drawings (showing proposed development) VOLUME 2 Reports Volume 2A Volume 2B Volume 2A Volume 2B Planning Report Public and Landowner Consultation Report Appendices associated with the Planning Report Appendices associated with the Consultation Report VOLUME 3 Multi-Volume EIS VOLUME 3A & 3B Volume 3A Volume 3B Non-Technical Summary Common Chapters (CMSA & MSA) Volume 3A Non-Technical Summary provides a non-technical summary of Volumes 3B, 3C and 3D. Volume 3B Common Chapters is a document which deals with strategic issues arising in respect of the proposed development, including Consideration of Alternatives, Cumulative Impacts and Impact Interactions and Transboundary Impacts 03 Scoping the EIS 04 Transmission & Technology Alternatives 05 Route Alternatives 06 Description of Development Transmission Circuit and Substation Works 07 Construction 08 Electric Magnetic Fields (EMF) 09 Transboundary 10 Cumulative and Impact Interactions 11 Summary of Mitigation Measures Volume 3B Appendices associated with Volume 3B. 01 Introduction 02 Strategic Need Volume 3B Figures including the 1:5,000 mapping for the proposed development at A1 scale.

VOLUME 3 Multi-Volume EIS VOLUME 3C & 3D Volume 3C Volume 3D Cavan Monaghan Study Area (CMSA) Meath Study Area (MSA) Volume 3C of the EIS considers the Cavan Monaghan Study Area. This volume provides an appraisal of the proposed development from the area of two crossing points of the jurisdictional border with Northern Ireland at Lemgare, County Monaghan to the townland of Clonturkan, County Cavan. Volume 3D of the EIS considers the Meath Study Area. This volume provides an appraisal of the proposed development, from the townland of Clonturkan, County Cavan to the existing Woodland 400kV Substation in County Meath. Volume 3C and Volume 3D each contain the following individual chapters specific to the particular study area being focused on in each volume: 01 Introduction 02 Human Beings Population and Economic 03 Human Beings Land Use 04 Human Beings Tourism and Amenity 05 Human Beings EMF 06 Flora and Fauna 07 Soils, Geology and Hydrogeology 08 Water 09 Air Noise 10 Air Quality and Climate 11 Landscape 12 Material Assets General 13 Material Assets Traffic 14 Cultural Heritage Volume 3C Volume 3C Volume 3D Volume 3D Appendices associated with Volume 3C Figures associated with Volume 3C Appendices associated with Volume 3D Figures associated with Volume 3D VOLUME 4 Joint Environmental Report This report is a summary of the overall proposed interconnector from Turleenan, County Tyrone to Woodland, County Meath, jointly prepared by EirGrid and SONI, and focussing primarily on environmental issues, including transboundary impacts and cumulative effects. The SONI Consolidated Environmental Statement (ES) and Consolidated ES Addendum is included as an appendix to this report. VOLUME 5 Natura Impact Statement (NIS) This is a document prepared pursuant to the requirements of the Habitats Directives to inform the appropriate assessment (AA) to be carried out by An Bord Pleanála as to the likely impacts of the proposed development on a European site or sites.

About EirGrid EirGrid, a state-owned company, is the national operator of the electricity transmission grid. The national transmission grid is an interconnected network of high-voltage power lines and cables, comparable to the motorways, dual carriageways and main roads of the national road network. It is operated at three voltage levels; 400kV, 220kV and 110kV and is approximately 6,400km in overall length within Ireland. It is the backbone of Ireland s electricity system and is vital to ensuring that all industrial, commercial and residential customers from both rural and urban areas have a safe, secure, reliable, economic and efficient electricity supply. Contact Details For further information about where the application or maps are on display or to purchase documents please contact the project team as follows: Phone: Lo-call 1890 25 26 90 (9am to 5pm Monday to Friday) Email: northsouth@eirgrid.com Website: http://www.eirgridprojects.com/projects/ northsouth400kvinterconnectiondevelopment Please note, submissions and/or observations in relation to the application for planning approval should NOT be sent to EirGrid but should be made directly to An Bord Pleanála, 64 Malborough Street, Dublin 1 by 5.30p.m. on Monday 24th August 2015. Printed copies of the full application, or parts thereof, can be obtained at a price not exceeding the reasonable cost of making a copy upon request. Copies are available in both the English and Irish languages. www.eirgridprojects.com