1 Public Disclosure Authorized Public Disclosure Authorized The World Bank Implementation Status & Results Cote d'ivoire RCI- Emergency Urban Infrastructure (FY08) (P110020) Operation Name: RCI- Emergency Urban Infrastructure (FY08) (P110020) Project Stage: Implementation Seq.No: 12 Status: ARCHIVED Archive : 04-Jan-2014 Country: Cote d'ivoire Approval FY: 2008 Product Line: IBRD/IDA Region: AFRICA Lending Instrument: Emergency Recovery Loan Implementing Agency(ies): Key s Board Approval 12-Jun-2008 Original Closing 15-Sep-2012 Planned Mid Term Review 07-Sep-2010 Last Archived ISR 05-Jul-2013 Effectiveness 09-Sep-2008 Revised Closing Actual Mid Term Review 22-Oct-2010 Project Development Objectives Project Development Objective (from Project Appraisal Document) The Project Development Objective (PDO) is to increase access to and improve the quality of urban infrastructure and services in the country#s two largest cities, Abidjan and Bouak#. The achievement of this objective would support GoCI#s efforts to demonstrate visible and tangible improvements in the lives of its citizens, a critical step for sustaining social and political stability and economic recovery in the country. Has the Project Development Objective been changed since Board Approval of the Project? Yes No Component(s) losure Authorized Public Disclosure Authorized Component Name Component Cost Urban Water Supply Sanitation (Sewerage) Solid Waste Management Urban Road Rehabilitation Municipal Contracts 7.00 Overall Ratings Previous Rating Current Rating Progress towards achievement of PDO Satisfactory Satisfactory Overall Implementation Progress (IP) Satisfactory Satisfactory Overall Risk Rating Implementation Status Overview The project implementation is satisfactory; most activities are finalized and most indicator targets are met. The project disbursement progress since the last mission in October 2013 Page 1 of 5
2 is also satisfactory, with a disbursement rate that went from 96.8% to 100% for the initial grant and from 84.74% to 94.18% for the additional financing grant. The project achievement has contributed to improving access and quality of urban services in the cities of Abidjan, Bouaké, Agboville Man and some secondary centers within the country (Mayo and Tinhou). The interim results of the project can be summarized as follows: Increase of drinking water production for more than 53,000 m3/day in Abidjan, Korogho and Bouaké, extension of the water distribution network and connecting suburban areas under-equipped and low-income households to the drinking water network. Due to the project, about: (i) 2.55 million additional people have access to improved drinking water service provision in the targeted cities; (ii) 0.48 million additional people have access to improved sanitation; (iii) 430,000 people have access to drivable roads in all seasons in selected cities; the risk of flooding is reduced in Abidjan with the construction of approximately 4.7 kilometers of drainage of rainwater and treatment of the Guru basin and; (iv) about 4.5 million people of the District of Abidjan have regular solid waste collection service. Overall project components are executed and completed except the sanitation component. The activities foreseen in the initial financing to eliminate various illegal dumping sites of solid waste in Abidjan in order to safeguard public health and environment were successfully completed. With regard to the additional financing, all activities are successfully completed except for the consolidation centers (Centres de groupage) which were planned to be the first step to receive garbage from pre-collectors. The mission noted the unsuccessful efforts made by the Ivorian Government to find appropriate sites that meet environmental, social and safety criteria for the development of consolidation centers. Four sites were initially identified of 25 targeted, but they were not equipped for the following reasons: (i) the one located in Port Bouet in the airport area and has been rejected because it may eventually formed a hazard to aviation with the presence of birds; (ii) the site of the Williams ville is dedicated by the Government for the construction of the bus station in Abidjan and; (iv) the population of Abobo Baule has not agreed to release the site identified in their neighborhood. Only the fourth site in Bingerville could meet the criteria but was abandoned in view because of the short time remaining before the end of the project. With the above difficulties, the mission and the Ivorian Government have decided to use the funding for the consolidation centers for more roads and water. The GoCI will continue to explore other possibilities to find other sites that could be equipped to and be financed from its own resources once the administrative problems are resolved. Locations Country First Administrative Division Location Planned Actual Cote d'ivoire Region des Lagunes Yopougon-Sante Cote d'ivoire Region des Lagunes Yopougon-Attie Cote d'ivoire Not Entered Williamsville Cote d'ivoire Region des Lagunes Treichville Cote d'ivoire Region du Bas-Sassandra San-Pedro Cote d'ivoire Region des Lagunes Port-Bouet Cote d'ivoire Region des Lagunes Koumassi Cote d'ivoire Region des Savanes Korhogo Cote d'ivoire Region du Sud-Bandama Divo Cote d'ivoire Region du Haut-Sassandra Daloa Cote d'ivoire Region des Lagunes Cocody Cote d'ivoire Region de la Vallee du Bandama Bouake Cote d'ivoire Region des Lagunes Adjame Page 2 of 5
3 Country First Administrative Division Location Planned Actual Cote d'ivoire Region des Lagunes Adjame Cote d'ivoire Region des Lagunes Abobo Cote d'ivoire Region des Lagunes Abidjan Cote d'ivoire Region des Lagunes Marcory Results Project Development Objective Indicators Indicator Name Core Unit of Measure Baseline Current End Target Number of people in urban areas provided with Number Value access to Improved Sanitation under the 15-Aug-2008 project Number of people in urban areas provided with Number Value access to Improved Water Sources under the 15-Aug-2008 project Number of people in urban areas provided with Number Value access to regular solid waste collection under 15-Aug-2008 the project No data available 25 collection centers are cancelled due to unavailability of sites Number of people in urban areas provided with Number Value access to all-season roads within a 500 meter 15-Aug-2008 range under the project No data available Direct project beneficiaries Number Value Female beneficiaries Percentage Sub Type Supplemental Value Intermediate Results Indicators Page 3 of 5
4 Indicator Name Core Unit of Measure Baseline Current End Target Component II: Urban Sanitation (Sewerage) Text Value 1,066, ,766, May-2008 Number of additional people connected to the interceptor Previous data should be 1,220,102 instead of 153,890 Number of rehabilited pumping stations Text Value May-2008 Reduced waste water flow being discharged into the lagoon Component III: Solid Waste Management Percentage of waste collected and dumped to the disposal site compared to total waste produced Text Value ,000 m3/day or 10,500 BDO/day 29-May-2008 Previous data should be 1,400 instead of 4,500 Text Value 50% (706,000 tones) 86% 80% (1,129,600 tons) 29-May-2008 Component V: Municipal Contracts Number of municipal audits and municipal contracts prepared Text Value May-2008 Improved community water points constructed or rehabilitated under the project New piped household water connections that are resulting from the project intervention Number Value Aug water points + 38 schools 132 water points + 38 schools newly connected connected Number Value Aug-2008 Roads rehabilitated, Non-rural Kilometers Value Aug-2008 More roads are rehabilitated using remaining funds from component 3. Data on Financial Performance (as of 29-Oct-2013) Financial Agreement(s) Key s Page 4 of 5
5 Project Ln/Cr/Tf Status Approval Signing Effectiveness Original Closing Revised Closing P IDA-H3970 Effective 12-Jun Jul Sep Sep-2012 P IDA-H5910 Effective 17-Jun Jul Oct Sep-2013 Disbursements (in Millions) Project Ln/Cr/Tf Status Currency Original Revised Cancelled Disbursed Undisbursed % Disbursed P IDA-H3970 Effective XDR P IDA-H5910 Effective XDR Disbursement Graph Key Decisions Regarding Implementation None. Restructuring History There has been no restructuring to date. Related Projects P Emergency Urban Infrastructure Project (Additional Financing) Page 5 of 5
Implementation Status & Results Nigeria Lagos Urban Transport Project 2 (P112956)
Public Disclosure Authorized Public Disclosure Authorized The World Bank Implementation Status & Results Nigeria Lagos Urban Transport Project 2 (P112956) Operation Name: Lagos Urban Transport Project
More informationImplementation Status & Results Dominican Republic DO APL1 Water and Sanitation in Tourist Areas (P054221)
Public Disclosure Authorized Public Disclosure Authorized The World Bank Implementation Status & Results Dominican Republic DO APL1 Water and Sanitation in Tourist Areas (P054221) Operation Name: DO APL1
More informationImplementation Status & Results Dominican Republic DO APL1 Water and Sanitation in Tourist Areas (P054221)
Public Disclosure Authorized Public Disclosure Authorized The World Bank Implementation Status & Results Dominican Republic DO APL1 Water and Sanitation in Tourist Areas (P054221) Operation Name: DO APL1
More informationImplementation Status & Results Kazakhstan Agricultural Competitiveness Project (P049721)
Public Disclosure Authorized Public Disclosure Authorized The World Bank Implementation Status & Results Kazakhstan Agricultural Competitiveness Project (P49721) Operation Name: Agricultural Competitiveness
More informationImplementation Status & Results Congo, Democratic Republic of Emergency Demobilization and Reintegration Project (P078658)
Public Disclosure Authorized Public Disclosure Authorized The World Bank Implementation Status & Results Congo, Democratic Republic of Emergency Demobilization and Reintegration Project (P078658) Operation
More informationImplementation Status & Results OECS Countries Telecommunications & ICT Development Project (P088448)
Public Disclosure Authorized Public Disclosure Authorized losure Authorized Public Disclosure Authorized The World Bank Implementation Status & Results OECS Countries Telecommunications & ICT Development
More informationProject Name. PROJECT INFORMATION DOCUMENT (PID) APPRAISAL STAGE Report No.: AB3736 RCI- Emergency Urban Infrastructure (FY08) AFRICA Sector.
Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Project Name PROJECT INFORMATION DOCUMENT (PID) APPRAISAL STAGE Report No.: AB3736 RCI-
More informationImplementation Status & Results Jordan Jordan - Cultural Heritage, Tourism & Urban Development (P081823)
Public Disclosure Authorized Public Disclosure Authorized The World Bank Implementation Status & Results Jordan Jordan - Cultural Heritage, Tourism & Urban Development (P081823) Operation Name: Jordan
More informationImplementation Status & Results Guinea Development of Inclusive Education in Guinea (P129210)
Public Disclosure Authorized Public Disclosure Authorized The World Bank Implementation Status & Results Guinea Development of Inclusive Education in Guinea (P129210) Operation Name: Development of Inclusive
More informationImplementation Status & Results West Bank and Gaza Gaza II Emergency Water Project (P065920)
Public Disclosure Authorized Public Disclosure Authorized The World Bank Implementation Status & Results West Bank and Gaza Gaza II Emergency Water Project (P065920) Operation Name: Gaza II Emergency Water
More informationImplementation Status & Results Guinea National Rural Infrastructure Project (P065127)
Public Disclosure Authorized Public Disclosure Authorized The World Bank Implementation Status & Results Guinea National Rural Infrastructure Project (P065127) Operation Name: National Rural Infrastructure
More informationImplementation Status & Results Morocco MA-Rural Roads II (P094007)
losure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized The World Bank Implementation Status & Results Morocco MA-Rural Roads II (P094007) Operation Name:
More informationImplementation Status & Results Brazil BR-Housing Sector TAL (P050761)
Public Disclosure Authorized Public Disclosure Authorized The World Bank Implementation Status & Results Brazil BR-Housing Sector TAL (P050761) Operation Name: BR-Housing Sector TAL (P050761) Project Stage:
More informationImplementation Status & Results Morocco Morocco Urban WS&S Access Pilots (P102527)
Public Disclosure Authorized Public Disclosure Authorized The World Bank Implementation Status & Results Morocco Morocco Urban WS&S Access Pilots (P102527) Operation Name: Morocco Urban WS&S Access Pilots
More informationImplementation Status & Results Central African Republic Multisectoral HIV/AIDS Project (P073525)
losure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized The World Bank Implementation Status & Results Central African Republic Multisectoral HIV/AIDS Project
More informationImplementation Status & Results Sri Lanka Sri Lanka - Second Health Sector Development Project (P118806)
Public Disclosure Authorized Public Disclosure Authorized The World Bank Implementation Status & Results Sri Lanka Sri Lanka - Second Health Sector Development Project (P118806) Operation Name: Sri Lanka
More informationImplementation Status & Results Benin ebenin Project (P113370)
Public Disclosure Authorized Public Disclosure Authorized The World Bank Implementation Status & Results Benin ebenin Project (P113370) Operation Name: ebenin Project (P113370) Project Stage: Implementation
More informationImplementation Status & Results Rwanda Second Emergency Demobilization and Reintegration Project (P112712)
Public Disclosure Authorized Public Disclosure Authorized The World Bank Implementation Status & Results Rwanda Second Emergency Demobilization and Reintegration Project (P112712) Operation Name: Second
More informationImplementation Status & Results Indonesia Support for Poor and Disadvantaged Areas Project (P078070)
Public Disclosure Authorized Public Disclosure Authorized The World Bank Implementation Status & Results Indonesia Support for Poor and Disadvantaged Areas Project (P078070) Operation Name: Support for
More informationImplementation Status & Results Kyrgyz Republic Small Towns Infrastructure & Capacity Building Project (P083377)
Public Disclosure Authorized Public Disclosure Authorized The World Bank Implementation Status & Results Kyrgyz Republic Small Towns Infrastructure & Capacity Building Project (P83377) Operation Name:
More informationImplementation Status & Results Swaziland Swaziland Health, HIV/AIDS and TB Project (P110156)
Public Disclosure Authorized Public Disclosure Authorized The World Bank Implementation Status & Results Swaziland Swaziland Health, HIV/AIDS and TB Project (P110156) Operation Name: Swaziland Health,
More informationImplementation Status & Results Dominican Republic Water and Sanitation in Tourist Areas (P054221)
Public Disclosure Authorized Public Disclosure Authorized The World Bank Implementation Status & Results Dominican Republic Water and Sanitation in Tourist Areas (P054221) Operation Name: Water and Sanitation
More informationImplementation Status & Results Tanzania Sustainable Management of Mineral Resources (P096302)
Public Disclosure Authorized Public Disclosure Authorized The World Bank Implementation Status & Results Tanzania Sustainable Management of Mineral Resources (P096302) Operation Name: Sustainable Management
More informationImplementation Status & Results Morocco MA-Rural Roads II (P094007)
Public Disclosure Authorized Public Disclosure Authorized The World Bank Implementation Status & Results Morocco MA-Rural Roads II (P094007) Operation Name: MA-Rural Roads II (P094007) Project Stage: Implementation
More informationImplementation Status & Results Indonesia Support for Poor and Disadvantaged Areas Project (P078070)
Public Disclosure Authorized Public Disclosure Authorized The World Bank Implementation Status & Results Indonesia Support for Poor and Disadvantaged Areas Project (P078070) Operation Name: Support for
More informationImplementation Status & Results Congo, Democratic Republic of Forest and Nature Conservation Project (P100620)
Public Disclosure Authorized Public Disclosure Authorized The World Bank Implementation Status & Results Congo, Democratic Republic of Forest and Nature Conservation Project (P100620) Operation Name: Forest
More informationImplementation Status & Results Indonesia Health Professional Education Quality Project (P113341)
Public Disclosure Authorized Public Disclosure Authorized The World Bank Implementation Status & Results Indonesia Health Professional Education Quality Project (P113341) Operation Name: Health Professional
More informationOBA Urban Sanitation Facility for the Greater Accra Metropolitan Area (GAMA) (P145139)
Public Disclosure Authorized AFRICA Ghana Water Global Practice Recipient Executed Activities Investment Project Financing FY 2014 Seq No: 3 ARCHIVED on 10-May-2017 ISR25522 Implementing Agencies: Public
More informationPublic Disclosure Copy. Implementation Status & Results Report CO APL1 La Guajira Water & Sanitation Infrast and Service Mngmt Proj (P096965)
LATIN AMERICA AND CARIBBEAN Colombia Water Global Practice IBRD/IDA Adaptable Program Loan FY 2007 Seq No: 15 ARCHIVED on 04-Dec-2014 ISR17292 Implementing Agencies: Key Dates Key Project Dates Board Approval
More informationImplementation Status & Results Congo, Democratic Republic of Forest and Nature Conservation Project (P100620)
Public Disclosure Authorized Public Disclosure Authorized The World Bank Implementation Status & Results Congo, Democratic Republic of Forest and Nature Conservation Project (P100620) Operation Name: Forest
More informationImplementation Status & Results Guatemala GUATEMALA Maternal and Infant Health and Nutrition (P077756)
Public Disclosure Authorized Public Disclosure Authorized The World Bank Implementation Status & Results Guatemala GUATEMALA Maternal and Infant Health and Nutrition (P077756) Operation Name: GUATEMALA
More informationImplementation Status & Results Indonesia ID SPADA in Aceh and Nias (P097605)
Public Disclosure Authorized Public Disclosure Authorized The World Bank Implementation Status & Results Indonesia ID SPADA in Aceh and Nias (P9765) Operation Name: ID SPADA in Aceh and Nias (P9765) Project
More informationThe World Bank Research and Innovation in Science and Technology Project (P121842)
Public Disclosure Authorized EAST ASIA AND PACIFIC Indonesia Education Global Practice IBRD/IDA Specific Investment Loan FY 2013 Seq No: 8 ARCHIVED on 22-Jun-2017 ISR27107 Implementing Agencies: Ministry
More informationThe World Bank Sustainable Rural Sanitation Services Program for Results (P154112)
Public Disclosure Authorized MIDDLE EAST AND NORTH AFRICA Egypt, Arab Republic of Water Global Practice IBRD/IDA Program-for-Results FY 2016 Seq No: 1 ARCHIVED on 05-Nov-2015 ISR21200 Implementing Agencies:
More informationThe World Bank Africa Higher Education Centers of Excellence Project (P126974)
AFRICA Africa Education Global Practice IBRD/IDA Specific Investment Loan FY 2014 Seq No: 3 ARCHIVED on 25-Jun-2015 ISR19488 Implementing Agencies: National University Commision, Ministry of Higher Education,
More informationThe World Bank The Gambia - Growth & Competitiveness (P114240)
Public Disclosure Authorized AFRICA Gambia, The Financial and Private Sector Development Global Practice IBRD/IDA Specific Investment Loan FY 2011 Seq No: 8 ARCHIVED on 23-Dec-2014 ISR17317 Implementing
More informationThe World Bank Burkina Faso - Bagre Growth Pole Project (P119662)
Public Disclosure Authorized AFRICA Burkina Faso Trade & Competitiveness Global Practice IBRD/IDA Specific Investment Loan FY 2011 Seq No: 12 ARCHIVED on 11-Jun-2017 ISR28154 Implementing Agencies: BagrePole,
More informationImplementation Status & Results Brazil Ceara Regional Economic Development: Cidades do Ceara (P099369)
Public Disclosure Authorized Public Disclosure Authorized The World Bank Implementation Status & Results Brazil Ceara Regional Economic Development: Cidades do Ceara (P99369) Operation Name: Ceara Regional
More informationThe World Bank Integrated Growth Poles and Corridor Project 2 (P113971)
Public Disclosure Authorized AFRICA Madagascar Trade & Competitiveness Global Practice IBRD/IDA Investment Project Financing FY 2015 Seq No: 6 ARCHIVED on 27-Dec-2017 ISR30958 Implementing Agencies: Ministry
More informationPublic Disclosure Copy
Public Disclosure Authorized EAST ASIA AND PACIFIC Indonesia Social, Urban, Rural and Resilience Global Practice Global Practice IBRD/IDA Investment Project Financing FY 2013 Seq No: 11 ARCHIVED on 03-May-2018
More informationImplementation Status & Results Montenegro Healthcare System Improvement Project (Montenegro) (P082223)
Public Disclosure Authorized Public Disclosure Authorized The World Bank Implementation Status & Results Montenegro Healthcare System Improvement Project (Montenegro) (P082223) Operation Name: Healthcare
More informationPublic Disclosure Copy
Public Disclosure Authorized AFRICA Burundi Health, Nutrition & Population Global Practice IBRD/IDA Investment Project Financing FY 2017 Seq No: 2 ARCHIVED on 20-Dec-2017 ISR29199 Implementing Agencies:
More informationPublic Disclosure Copy. Implementation Status & Results Report Global Partnership for Education Grant for Basic Education Project (P117662)
Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized AFRICA Liberia Education Global Practice Recipient Executed Activities Specific Investment
More informationPublic Disclosure Copy. Implementation Status & Results Report Senegal: Extractive Industries Transparency Initiative Implementation (P131626)
Public Disclosure Authorized AFRICA Senegal Energy and Mining Global Practice Recipient Executed Activities Technical Assistance Loan FY 2014 Seq No: 1 ARCHIVED on 18-Jun-2015 ISR19209 Implementing Agencies:
More informationPublic Disclosure Copy
LATIN AMERICA AND CARIBBEAN Brazil Recipient Executed Activities Investment Project Financing FY 2016 Seq No: 1 ARCHIVED on 17-May-2017 ISR27363 Implementing Agencies: Key Dates Key Project Dates Bank
More informationThe World Bank Swaziland Health, HIV/AIDS and TB Project (P110156)
Public Disclosure Authorized AFRICA Swaziland Health, Nutrition & Population Global Practice IBRD/IDA Specific Investment Loan FY 2011 Seq No: 10 ARCHIVED on 27-Jun-2016 ISR24063 Implementing Agencies:
More informationINDONESIA: IMPROVING TEACHER PERFORMANCE AND ACCOUNTABILITY (KIAT GURU)
Public Disclosure Authorized INDONESIA: IMPROVING TEACHER PERFORMANCE AND ACCOUNTABILITY (KIAT GURU) (P159191) EAST ASIA AND PACIFIC Indonesia Social, Urban, Rural and Resilience Global Practice Global
More informationThe World Bank JM Youth Employment in Digital and Animation Industries (P148013)
Public Disclosure Authorized LATIN AMERICA AND CARIBBEAN Jamaica Social Development Global Practice IBRD/IDA Investment Project Financing FY 2015 Seq No: 2 ARCHIVED on 29-Jun-2015 ISR19585 Implementing
More informationPublic Disclosure Copy
Public Disclosure Authorized MIDDLE EAST AND NORTH AFRICA Morocco Transport & ICT Global Practice IBRD/IDA Program-for-Results FY 2016 Seq No: 3 ARCHIVED on 15-Jun-2017 ISR28180 Implementing Agencies:
More informationThe World Bank Kenya GPE Primary Education Development Project (P146797)
Public Disclosure Authorized AFRICA Kenya Education Global Practice Recipient Executed Activities Investment Project Financing FY 2015 Seq No: 6 ARCHIVED on 01-Nov-2017 ISR29517 Implementing Agencies:
More informationPublic Disclosure Copy
Public Disclosure Authorized AFRICA Ethiopia Finance & Markets Global Practice IBRD/IDA Investment Project Financing FY 2016 Seq No: 3 ARCHIVED on 25-May-2017 ISR27984 Implementing Agencies: National Bank
More informationThe World Bank St. Petersburg Economic Development Project (P069063)
Public Disclosure Authorized EUROPE AND CENTRAL ASIA Russian Federation Urban Development Global Practice IBRD/IDA Financial Intermediary Loan FY 2003 Seq No: 23 ARCHIVED on 08-Dec-2014 ISR17382 Implementing
More informationPublic Disclosure Copy. Implementation Status & Results Report Second Private Sector Competitiveness and Economic Diversification Prj (P144933)
Public Disclosure Authorized AFRICA Lesotho Finance, Competitiveness and Innovation Global Practice IBRD/IDA Investment Project Financing FY 2014 Seq No: 10 ARCHIVED on 08-May-2018 ISR30476 Implementing
More informationThe World Bank Skills Strengthening for Industrial Value Enhancement Operation (P156867)
Public Disclosure Authorized SOUTH ASIA India Education Global Practice IBRD/IDA Program-for-Results FY 2017 Seq No: 1 ARCHIVED on 27-Jun-2017 ISR28685 Implementing Agencies: Ministry of Skill Development
More informationThe World Bank Swaziland Health, HIV/AIDS and TB Project (P110156)
Public Disclosure Authorized AFRICA Swaziland Health, Nutrition & Population Global Practice IBRD/IDA Specific Investment Loan FY 2011 Seq No: 12 ARCHIVED on 29-Jun-2017 ISR28124 Implementing Agencies:
More informationThe World Bank Second Karnataka State Highway Improvement (P107649)
Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized SOUTH ASIA India Transport & ICT Global Practice IBRD/IDA Specific Investment Loan FY
More informationThe World Bank Kenya GPE Primary Education Development Project (P146797)
Public Disclosure Authorized AFRICA Kenya Education Global Practice Recipient Executed Activities Investment Project Financing FY 2015 Seq No: 4 ARCHIVED on 15-Feb-2017 ISR26822 Implementing Agencies:
More informationThe World Bank JM Youth Employment in Digital and Animation Industries (P148013)
Public Disclosure Authorized LATIN AMERICA AND CARIBBEAN Jamaica Social, Urban, Rural and Resilience Global Practice Global Practice IBRD/IDA Investment Project Financing FY 2015 Seq No: 5 ARCHIVED on
More informationThe World Bank Health Professional Education Quality Project (P113341)
Public Disclosure Authorized EAST ASIA AND PACIFIC Indonesia Health, Nutrition and Population Global Practice IBRD/IDA Specific Investment Loan FY 2010 Seq No: 9 ARCHIVED on 24-Dec-2014 ISR17306 Implementing
More informationPublic Disclosure Copy. Implementation Status & Results Report Philippines: Extractive Industries Transparency Initiative Implementation (P128290)
Public Disclosure Authorized EAST ASIA AND PACIFIC Philippines Energy & Extractives Global Practice Recipient Executed Activities Technical Assistance Loan FY 2014 Seq No: 1 ARCHIVED on 07-Jul-2015 ISR19833
More informationThe World Bank Social Accountability Knowledge, Skills, Action and Networking (P147835)
Public Disclosure Authorized AFRICA Mozambique Governance Global Practice Recipient Executed Activities Investment Project Financing FY 2014 Seq No: 2 ARCHIVED on 12-Jan-2018 ISR29464 Implementing Agencies:
More informationThe World Bank Romania Secondary Education Project (P148585)
Public Disclosure Authorized Public Disclosure Authorized The World Bank RESTRUCTURING PAPER ON A PROPOSED PROJECT RESTRUCTURING OF ROMANIA SECONDARY EDUCATION PROJECT APPROVED ON MARCH 16, 2015 TO ROMANIA
More informationImplementation Status & Results Report MENA- Desert Ecosystems and Livelihoods Knowledge Sharing and Coordination Project (P130343)
Public Disclosure Authorized MIDDLE EAST AND NORTH AFRICA Middle East and North Africa Environment & Natural Resources Global Practice Global Environment Project Technical Assistance Loan FY 2013 Seq No:
More informationNATIONAL COMMUNITY EMPOWERMENT PROGRAM IN URBAN AREAS FOR APPROVED ON NOVEMBER 20, 2012 REPUBLIC OF INDONESIA
The World Bank DOCUMENT OF THE WORLD BANK REPORT NO.: RES25530 RESTRUCTURING PAPER ON A PROPOSED PROJECT RESTRUCTURING OF NATIONAL COMMUNITY EMPOWERMENT PROGRAM IN URBAN AREAS FOR 2012-2015 APPROVED ON
More informationFOR OFFICIAL USE ONLY RESTRUCTURING PAPER ON A
Public Disclosure Authorized Document of The World Bank FOR OFFICIAL USE ONLY Report No: RES22379 Public Disclosure Authorized Public Disclosure Authorized RESTRUCTURING PAPER ON A PROPOSED PROJECT RESTRUCTURING
More informationKey Dates. Project Development Objectives. Components. Overall Ratings. Implementation Status and Key Decisions
The World Bank EUROPE AND CENTRAL ASIA Kyrgyz Republic Procurement Global Practice Institutional Development Fund FY 2014 Seq No: 2 ARCHIVED on 08-Jun-2015 ISR19571 Implementing Agencies: Public Procurement
More informationPublic Disclosure Copy
Public Disclosure Authorized AFRICA Ethiopia Finance & Markets Global Practice IBRD/IDA Investment Project Financing FY 2016 Seq No: 4 ARCHIVED on 06-Dec-2017 ISR30229 Implementing Agencies: National Bank
More informationThe World Bank Serbia Research, Innovation and Technology Transfer Project (P145231)
Public Disclosure Authorized EUROPE AND CENTRAL ASIA Serbia Trade & Competitiveness Global Practice Recipient Executed Activities Technical Assistance Loan FY 2015 Seq No: 1 ARCHIVED on 30-Oct-2015 ISR20707
More informationRESTRUCTURING PAPER ON A PROPOSED PROJECT RESTRUCTURING OF
Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Document of The World Bank RESTRUCTURING PAPER ON A PROPOSED PROJECT RESTRUCTURING OF
More informationP4: PACIFIC REGIONAL ICT REGULATORY DEVELOPMENT PROJECT APPROVED ON JULY 30, 2014 UNIVERSITY OF THE SOUTH PACIFIC
Public Disclosure Authorized The World Bank DOCUMENT OF THE WORLD BANK REPORT NO.: RES29928 Public Disclosure Authorized Public Disclosure Authorized RESTRUCTURING PAPER ON A PROPOSED PROJECT RESTRUCTURING
More informationFOR OFFICIAL USE ONLY RESTRUCTURING PAPER ON A
Public Disclosure Authorized Document of The World Bank FOR OFFICIAL USE ONLY Report No: RES22380 Public Disclosure Authorized Public Disclosure Authorized RESTRUCTURING PAPER ON A PROPOSED PROJECT RESTRUCTURING
More informationSTRENGTHENING MICRO-ENTREPRENEURSHIP FOR DISADVANTAGED YOUTH APPROVED ON JUNE 27, 2013 MINISTRY OF ECONOMY AND FINANCE (TGR)
The World Bank DOCUMENT OF THE WORLD BANK REPORT NO.: RES26443 RESTRUCTURING PAPER ON A PROPOSED PROJECT RESTRUCTURING OF STRENGTHENING MICRO-ENTREPRENEURSHIP FOR DISADVANTAGED YOUTH APPROVED ON JUNE 27,
More informationPublic Disclosure Copy
Public Disclosure Authorized EAST ASIA AND PACIFIC China Health, Nutrition & Population Global Practice IBRD/IDA Program-for-Results FY 2017 Seq No: 2 ARCHIVED on 25-Feb-2018 ISR31105 Implementing Agencies:
More informationPROJECT INFORMATION DOCUMENT (PID) APPRAISAL STAGE Report No.: PIDA109589
Public Disclosure Authorized PROJECT INFORMATION DOCUMENT (PID) APPRAISAL STAGE Report No: PIDA109589 Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Project Name
More informationPublic Disclosure Copy
SOUTH ASIA Pakistan Agriculture and Rural Development Global Practice Recipient Executed Activities Specific Investment Loan FY 2013 Seq No: 4 ARCHIVED on 26-Nov-2014 ISR17007 Implementing Agencies: KP
More informationThe World Bank MDTF-Economic Revitalization of KP and FATA (P124268)
Public Disclosure Authorized SOUTH ASIA Pakistan Trade & Competitiveness Global Practice Recipient Executed Activities Emergency Recovery Loan FY 2012 Seq No: 11 ARCHIVED on 06-Dec-2016 ISR25587 Implementing
More informationThe World Bank Vietnam Climate Innovation Center (VCIC) RETF (P155260)
Public Disclosure Authorized Public Disclosure Authorized The World Bank RESTRUCTURING PAPER ON A PROPOSED PROJECT RESTRUCTURING OF VIETNAM CLIMATE INNOVATION CENTER (VCIC) RETF APPROVED ON OCTOBER 30,
More informationPublic Disclosure Copy
Public Disclosure Authorized AFRICA Nigeria Public Sector Governance Global Practice Recipient Executed Activities Specific Investment Loan FY 20 Seq No: 4 ARCHIVED on 3-Feb-205 ISR7805 Implementing Agencies:
More informationIn accordance with Section 610(b)(2) of the Millennium Challenge Act of
This document is scheduled to be published in the Federal Register on 11/20/2017 and available online at https://federalregister.gov/d/2017-25198, and on FDsys.gov MILLENNIUM CHALLENGE CORPORATION [MCC
More informationBE PART OF THE NEW ECONOMIC MOMENTUM INTERNATIONAL FORUM FOR INVESTMENTS IN CÔTE D IVOIRE JANUARY ABIDJAN
BE PART OF THE NEW ECONOMIC MOMENTUM IN CÔTE D IVOIRE INTERNATIONAL FORUM FOR INVESTMENTS IN CÔTE D IVOIRE 29-31 JANUARY 2014 - ABIDJAN THE ACCELERATION OF ECONOMIC DEVELOPMENT IS OUR PRIORITY Alassane
More informationThe Toyota Foundation 2018 International Grant Program Application Form
The Toyota Foundation 2018 International Grant Program Application Form Notes: Please be sure to read the Program Guidelines before filling out this form. DO NOT alter the size of the text boxes. Altered
More informationDocument of 'f I CO Y The World Bank FOR OFFICIAL USE ONLY
Document of 'f I CO Y The World Bank Public Disclosure Authorized FOR OFFICIAL USE ONLY Report No. 3236a-IVC Public Disclosure Authorized IVORY COAST SECOND URBAN PROJECT STAFF APPRAISAI REPORT July 7,
More informationEmergency Plan of Action Final Report
Emergency Plan of Action Final Report Cote d Ivoire: (Civil Unrest Elections Preparedness) DREF Operation Operation n MDRCI009 Date of issue: 29 February, 2016 Date of disaster: 24-30 October 2015 (Dates
More informationSTATUS OF PROJECTS IN EXECUTION FY10 SOPE EUROPE AND CENTRAL ASIA REGION. Armenia. Public Disclosure Authorized. Public Disclosure Authorized
Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized STATUS OF PROJECTS IN EXECUTION FY10 SOPE Armenia Operations Policy and Country Services
More informationRajasthan Urban Sector Development Program
India: Rajasthan Urban Sector Development Program Project Name Rajasthan Urban Sector Development Program Project Number 42267-026 Country Project Status Project Type / Modality of Assistance Source of
More informationINTEGRATED SAFEGUARDS DATA SHEET APPRAISAL STAGE
. Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Date ISDSPrepared/Updated: Date ISDS Approved/Disclosed I. BASIC INFORMATION 1. Basic
More informationBETF: P (TF and TF013728)
PNPM Urban in Aceh Quarterly Progress Report: January to March 2016 Summary Information Status Activity Number Task Team Leader(s) Executing Agency(ies) Active RETF: P131296 (TF012192) BETF: P131511 (TF012423
More informationEconomic Forum on Investment and Trade in Côte d'ivoire 15 September, 2017 London, United Kingdom
NATIONAL STEERING COMMITTEE FOR PUBLIC-PRIVATE PARTNERSHIPS (CNP-PPP) Economic Forum on Investment and Trade in Côte d'ivoire 15 September, 2017 London, United Kingdom Noumory SIDIBE Chairperson CNP-PPP
More informationGLOBAL INFRASTRUCTURE FACILITY OPERATING GUIDELINES
GLOBAL INFRASTRUCTURE FACILITY OPERATING GUIDELINES As Adopted by the GIF Governing Council on 20 April, 2015 And Revised on 16 June, 2016 A. INTRODUCTION 1. The Global Infrastructure Facility ( GIF )
More informationNevada s Metro Areas Show Improvement Since Height of Recession
For Immediate Release March 14, 2017 Nevada s Metro Areas Show Improvement Since Height of Recession CARSON CITY, NV In Las Vegas, the jobless rate stands at 5.1 percent for January, while Reno/Sparks
More informationTypes of Eligible Projects
U.S. Department of Agriculture Rural Development, Rural Utilities Service Water and Environmental Programs UNC School of Government Environmental Finance Center 2018 Water & Wastewater Finance Workshop
More informationForest Investment Program. Second Joint Mission Terms of Reference for Investment Plan Preparation March 1-5, 2016
REPUBLIQUE DE COTE D IVOIRE MINISTERE DE L ENVIRONNEMENT, DE LA SALUBRITE URBAINE ET DU DEVELOPPEMENT DURABLE Forest Investment Program Second Joint Mission Terms of Reference for Investment Plan Preparation
More informationRESTRUCTURING PAPER ON A PROPOSED PROJECT RESTRUCTURING MADAGASCAR SCALING RENEWABLE ENERGY PROGRAM (SREP) INVESTMENT PLAN (IP)
Public Disclosure Authorized The World Bank REPORT NO.: RES31786 RESTRUCTURING PAPER Public Disclosure Authorized ON A PROPOSED PROJECT RESTRUCTURING OF MADAGASCAR SCALING RENEWABLE ENERGY PROGRAM (SREP)
More informationPROJECT INFORMATION DOCUMENT (PID) ADDITIONAL FINANCING Report No.: PIDA4973. Project Name
Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized PROJECT INFORMATION DOCUMENT (PID) ADDITIONAL FINANCING Report No.: PIDA4973 Project
More informationRESTRUCTURING PAPER ON A PROPOSED PROJECT RESTRUCTURING OF HAITI - URBAN COMMUNITY DRIVEN DEVELOPMENT PROJECT (PRODEPUR) ADDITIONAL FINANCING GRANT
Public Disclosure Authorized Document of The World Bank Report No: 64887-HT Public Disclosure Authorized RESTRUCTURING PAPER ON A PROPOSED PROJECT RESTRUCTURING OF HAITI - URBAN COMMUNITY DRIVEN DEVELOPMENT
More informationBY ORDER OF THE AIR FORCE POLICY DIRECTIVE SECRETARY OF THE AIR FORCE 20 JULY 1994
BY ORDER OF THE AIR FORCE POLICY DIRECTIVE 32-70 SECRETARY OF THE AIR FORCE 20 JULY 1994 Civil Engineering ENVIRONMENTAL QUALITY 1.1. Achieving and maintaining environmental quality is an essential part
More informationGlobal Partnership on Output-based Aid Grant Agreement
Global Partnership on Output-based Aid GRANT NUMBERS TF057614 AND TF057615 Global Partnership on Output-based Aid Grant Agreement (Kenya - Microfinance for Community-Managed Water Projects) between K-REP
More informationRESTRUCTURING PAPER ON A PROPOSED PROJECT RESTRUCTURING OF THE HEALTH SECTOR REFORM PROJECT - PHASE II (APL2) LOAN NO RO January 28, 2005
Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Document of The World Bank RESTRUCTURING PAPER ON A PROPOSED PROJECT RESTRUCTURING OF
More informationCommunity Development Block Grant Program Year Application Instruction Booklet
Community Development Block Grant Program Year 2016-2017 Application Instruction Booklet Horry County Community Development Block Grant Office 1515 Fourth Avenue Conway, SC 29526 www.horrycounty.org 843-915-7033
More informationCase study: System of households water use subsidies in Chile.
Case study: System of households water use subsidies in Chile. 1. Description In Chile the privatization of public water companies during the 70 s and 80 s resulted in increased tariffs. As a consequence,
More information