(Ist Phase 18 months )

Procurement Plan. Threshold US$ 1. ICB and LIB (Goods) Above US$ 1,500,000 All 2. NCB (Goods) and (Non-

Procurement Plan ENGAGING COMMUNITIES FOR BETTER SCHOOLS IN THE KYRGYZ REPUBLIC PROJECT US$2.73 MILLION EQUIVALENT

Procurement Plan ENGAGING COMMUNITIES FOR BETTER SCHOOLS IN THE KYRGYZ REPUBLIC PROJECT US$2.73 MILLION EQUIVALENT

Second Tamil Nadu Road Sector Project PROCUREMENT PLAN

Procurement Plan. Threshold US$ 1. ICB and LIB (Goods) Above US$ 1,500,000 All 2. NCB (Goods) and (Non-

Access to Sustainable Energy Project (ASEP) Procurement Plan

Loan Credit No. : IDA Bank s Approval Date of the Procurement Plan : May 24, Date of General Procurement Notice : May 24, 2017

Sample Procurement Plan

GESP Procurement Plan MARCH 2017

Sample Procurement Plan

2. Bank s approval Date of the procurement Plan: Revised version: June 5, Period covered by this procurement plan: 30 June June 2017

GOVERNMENT OF MAURITIUS MANUFACTURING AND SERVICES DEVELOPMENT AND COMPETITIVENESS PROJECT (MSDC) LOAN NO MU PROCUREMENT PLAN FOR THE PERIOD

Sample Procurement Plan

Procurement Plan. 5. Any Other Special Procurement Arrangements: [including advance procurement and retroactive financing, if applicable] N/A

Sample Procurement Plan

Procurement Plan. US$ 1. ICB and LIB (Goods) All contracts procured under ICB

RCIP-4 Comoros, Procurement Plan

Kerala State Transport Project II (P130339)

Sample Procurement Plan

Lao PDR: Trade Development Facility Project Procurement Plan (April 2012 March 2013)

Sample Procurement Plan

procurement Plan I. General

GOVERNMENT OF INDONESIA SCHOLARSHIP PROGRAM FOR STRENGTHENING REFORMING INSTITUTIONS (SPIRIT) PROCUREMENT PLAN

GOVERNMENT OF INDONESIA SCHOLARSHIP PROGRAM FOR STRENGTHENING REFORMING INSTITUTIONS (SPIRIT) PROCUREMENT PLAN

Sample Procurement Plan

procurement Plan I. General

procurement Plan I. General

Procurement Plan. I. General. 1. Project Information Country: Malawi Project Name: Lilongwe Water and Sanitation Project Project ID: P163794

PROCUREMENT PLAN. Energy Efficiency Measures and Solar Photovoltaic Plant Project Executing Agency:

PROCUREMENT PLAN (Textual Part)

Implementation Status & Results Indonesia Support for Poor and Disadvantaged Areas Project (P078070)

PROCUREMENT PLAN. Procurement of Goods and Works

PROCUREMENT PLAN. b) Project Name: Market-led Smallholder Development in the Zambezi Valley Project

Sample Procurement Plan

PROCUREMENT PLAN. Period covered by this Procurement Plan: September 2017, June Preamble

Implementation Status & Results Indonesia Support for Poor and Disadvantaged Areas Project (P078070)

SKILLS DEVELOPMENT PROJECT

Ayeyarwady Integrated River Basin Management Project (AIRBM) Procurement

Overview of Operational Procurement. Nancy Bikondo - Omosa Procurement Specialist Procurement Policy and Services Group June 2013

PROCUREMENT PLAN N/A. Date of First Procurement Plan: 31 May 2017 Date of this Procurement Plan: 3 September 2018, Version 2

ICDS Systems Strengthening & Nutrition Improvement Project (ISSNIP)

Sample Procurement Plan

Procurement Plan Enhancing Quality of Financial Reporting (EQ-FINREP) Grant No:

PROCUREMENT PLAN. Procurement of Goods and Works Method Threshold Comments. Consulting Services

RETF: P (TF097410), P132585, and P (TF014769) BETF: P (TF092194)

Commissariat à la Promotion des Investissements

Re: Indonesia: JSDF Grant for Sustaining Women s Leadership Project Grant No.TF095058

PROCUREMENT PLAN. Consulting Services

National Electrification Project (P152936) Detailed Procurement Plan

PROCUREMENT PLAN. Basic Data

Procurement Plan dated January 2, 2013

MOZAMBIQUE Technical and Vocational Education and Training Project

REVISED PROCUREMENT PLAN FOR POVERTY REDUCTION FUND PROJECT, PHASE II Fund: IDA Grant No. H685-LA Revised date: 23 July 2012

RETF: P (TF097410), P132585, and P (TF014769) BETF: P (TF092194)

Loan No INO: POOR FARMERS INCOME IMPROVEMENT THROUGH INNOVATION PROJECT. INCEPTION MISSION May 21 June 5, 2003 MEMORANDUM OF UNDERSTANDING

Thresholds for Procurement Methods and Bank s Prior Reviews:

PROCUREMENT PLAN (Textual Part)

PROCUREMENT PLAN. Procurement of Goods and Works Method Threshold Comments International Competitive Bidding (ICB) for Works $25,000,00

Netherlands Grant for the Water Resources and Irrigation Reform Implementation Program Grant Number TF

PROCUREMENT PLAN. Implementing Agency: N/A. Date of First Procurement Plan: 28 January 2008 Date of this Procurement Plan: 26 March 2014, Rev.

Part A [To be completed by the Executing Agency]

PROCUREMENT PLAN. A. Methods, Thresholds, Review and 18-Month Procurement Plan. 1. Procurement and Consulting Methods and Thresholds

Priority programmes and rural retention the example of TB. Karin Bergstrom Stop TB Department WHO, Geneva

.DOCUMENTS OFFICIAL. TF 0 1Lf63

FEDERAL REPUBLIC OF NIGERIA

Andhra Pradesh Rural Water Supply and Sanitation (APRWSS) Project

HEALTH FACILITIES SAFE FROM DISASTERS

1. Basic Data Project Name: Improved Sanitary and Phytosanitary (SPS) Handling in Greater Mekong Subregion (GMS) Trade Project

PROCUREMENT PLAN. Date of First Procurement Plan: 17 May 2012 Date of this Procurement Plan: 21 September 2012

FOR OFFICIAL USE ONLY RESTRUCTURING PAPER ON A

Goods and Equipment List Item Narosec BuginyaNARL ABI Bulindi KAZARDNASARIMbararaNAFORI Ngetta Nabuin NaCRRI

Multi-Donor Trust Fund for Aceh and North Sumatra Grant Agreement

PROCUREMENT PLAN. Consulting Services

PROCUREMENT PLAN. Basic Data Project Name: Transport Connections in the Northern Mountainous Provinces Project

Global Financing Facility Grant Agreement

2) Rivers State Works Goods Consultancy

GHA/WATTFP/G01/ , NCB Post Prior Plan 22 Feb Mar Jun 2010 Actual 30 Jun Aug 2010

Re: Philippines: Cities Alliance Multi-Donor Trust Fund: Development of the National Slum Upgrading Strategy Grant No. TF099881

World Bank Consultant Guidelines and Business Opportunities

Procurement Plan Attachment 2

Country Coordinating Mechanism The Global Fund to Fight AIDS, Tuberculosis, and Malaria Indonesia (CCM Indonesia)

Outgoing Subagreements: Subawards and Subcontracts

Development of New INA-CBG Reclassification

OFFICIALf DOCUMENTS. Re: REPUBLIC OF DJIBOUTI JSDF Grant for Enhancing Income Opportunities Project Grant No. TFOAO350

Afghanistan Reconstruction Trust Fund Grant Agreement

Global Partnership on Output-based Aid Grant Agreement

PROCUREMENT PLAN. Period covered by this Procurement Plan: March 22, 2017 December 12, Preamble

PROCUREMENT PLAN KETSANA EMERGENCY RECONSTRUCTION AND REHABILITATION PROJECT (ERRP) COVERING PROJECT PERIOD: THREE YEARS April-01,2011

Indonesia - FCPF Readiness Preparation Grant FCPFR - FOREST CARBON PARTNERSHIP FACILITY

Global Environment Facility Proposal for PDF Block B Grant

INDONESIA NATIONAL ROADS IMPROVEMENT PROJECT WESTERN INDONESIA PROJECT INFORMATION DOCUMENT CONCEPT STAGE Report No.:AB2075 Project Name

Letter No. CD-064/INIS/III/2014 March 26, 2014

Minutes of Meeting Subject

March 9, Honourable Winston Dookeran Minister of Finance Eric Williams Finance Building Independence Square Port of Spain Trinidad and Tobago

1. Project Information: Land Administration and Management Project. The IBRD Loan number is 4851 ALB. The SIDA Grant number is TF090309

CARIBBEAN DEVELOPMENT BANK GUIDELINES FOR THE SELECTION AND ENGAGEMENT OF CONSULTANTS BY RECIPIENTS OF CDB FINANCING

NATIONAL COMMUNITY EMPOWERMENT PROGRAM IN URBAN AREAS FOR APPROVED ON NOVEMBER 20, 2012 REPUBLIC OF INDONESIA

Transcription:

Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized NATIONAL SLUM UPGRADING PROGRAM (NSUP) I. General Information 1. Project information: LOAN IBRD Ln.8636; AIIB LN 004-IDN Plan Version : 3 Date: March 15, 2018 a. Country: Indonesia b. Recipient: Republic of Indonesia c. Project Name: National Slum Upgrading Program (NSUP) d. Project Implementing Agency (PIA): (i) Directorate General of Human Settlements, Ministry Public Works and Housing (MPWH) 2. Bank s No Objection Date of the Plan: a. Original : May 30, 2016 b. Version 2 : July, 17, 2016 c. Version 3 : March, 15, 2018 d. Version : 3. Date of General Notice: 4. Period covered by this procurement plan: Effectiveness Loan Closing (estimated Dec 2020) II. Types of Contract, Bank s Review Requirements and Applied Methods Public Disclosure Authorized A. Works, Goods and Non-Consulting Services 1. Prior Review Threshold: Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for : Ref. Method 1. International Competitive Bidding (Works) 2. National Competitive Bidding (Works) Method $25 million $200k - $25 million Bank s Review Requirement Each contract shall be subject to Bank s prior Each contract $15 million equivalent shall prior All other

3. Shopping for Works < $200k No prior review (only post review). 4. International Competitive Bidding $2 million Each contract $4 (Goods) million equivalent shall prior All other 5. National Competitive Bidding $100k - $2 Each contract $4 (Goods) million million equivalent shall prior All other 6. Shopping for Goods <100k No prior review (only 7. International Competitive Bidding (Non-Consultant Service) 8. National Competitive Bidding (Non-Consultant Service) 9. Shopping for Non-Consulting Service post review). $10 million Each contract shall be subject to Bank s prior $100k - $10 million Each contract $4 million equivalent shall prior All other <$100,000 No prior review (only post review). 10. Direct Contracting N/A Justification shall be provided when submit procurement plan. 1. Pre-qualification: Not applicable. 2. Proposed Procedures for CDD Components (as per paragraph. 3.17 of the Guidelines: As specified in the Project Operations Manual (POM) 3. Reference to (if any) Project Operational/ Manual: Project Operations Manual of NSUP 4. Any Other Special Arrangements: -NA- 5. Summary of the Packages planned during the first 18 months after project effectiveness (including those that are subject to retroactive financing and advanced procurement) 1 2 3 4 5 6 7 Ref. Description Packages Domestic Review Comments Cost (US$ million) Preference (yes/no) by Bank (Prior / Post) 1. Summary of 0.44 2 No Post

the NCB (Works) 2. Summary of the NCB (Nonconsulting Services) 3. Summary of the NCB (Nonconsulting Services) 34.67 7 No Prior 20.22 10 No Post B. Selection of Consultants 1. Prior Review Threshold: Selection decisions subject to prior review by Bank as stated in Appendix 1 to the Guidelines for Selection and Employment of Consultants: Ref. Selection Method 1. Competitive Method (Firms) QCBS, QBS, LCS, FBS 2. Competitive Methods (Firms) QCS 3. Individual Consultant 4. Single Source (Firms and Individual) Selection Method Threshold Bank s Prior Review Requirement $300,000 Each contract $2,000,000 equivalent shall be subject to Bank s prior All other <$300,000 Each contract $2,000,000 equivalent shall be subject to Bank s prior All other Competitive Selection by comparing at least three CVs N/A None, except for procurement specialist and specific position as indicated in this procurement plan. Justification shall be provided when submit procurement plan. 2. Short list comprising entirely of national consultants: Short list of consultants for services (firms), estimated to cost less than $ 400,000 equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. 3. Any Other Special Selection Arrangements: N/A 4. Summary of Consultancy Assignments with Selection Methods and Time Schedule during the first 18 months after project effectiveness (including those that are subject to retroactive financing and advanced procurement)

1 2 3 4 5 6 7 Ref. Type of Packages/ Comments Assignments Positions Description of Assignments 1. Summary of number of contracts that will be let under QCBS 2. Summary of number of individual consultant contracts that will be let under competitive selection (Time-Based /Lump-Sum) Cost (US$ million) Review by Bank (Prior / Post) 4.653 4 Post TMC 4-6, Evaluation Consultant (Time-Based) 4.414 1 Prior NMC- Region 2 (Time-Based 0.286 11 Post Under /Lump-Sum) Bappenas

Page 1 PROCUREMENT PLAN Indonesia : Indonesia National Slum Upgrading Project General Information Country: Indonesia Banks Approval Date of the Original Plan: 2018-03-20 Revised Plan Date(s): (comma delineated, leave blank if none) 2018-03-20 Project ID: P154782 GPN Date: Project Name: Indonesia National Slum Upgrading Project Loan / Credit No: Executing Agency(ies): Directorate of Settlement Development, Directorate General of Human Settlements, MPW WORKS Prequalification (Y/N) Amount Status Bid Evaluation Report Draft Pre-qualification Prequalification Draft Bidding Document Specific Bidding Documents as Proposal Submission / and Recommendation Signed Contract Contract Completion Documents Evaluation Report / Justification Notice / Invitation Issued Opening / Minutes for Award GOODS Prequalification (Y/N) Amount Status Bid Evaluation Report Draft Pre-qualification Prequalification Draft Bidding Document Specific Bidding Documents as Proposal Submission / and Recommendation Signed Contract Contract Completion Documents Evaluation Report / Justification Notice / Invitation Issued Opening / Minutes for Award NON CONSULTING SERVICES Prequalification (Y/N) Amount Status Bid Evaluation Report Draft Pre-qualification Prequalification Draft Bidding Document Specific Bidding Documents as Proposal Submission / and Recommendation Signed Contract Contract Completion Documents Evaluation Report / Justification Notice / Invitation Issued Opening / Minutes for Award NSUP-OSP-1 / Oversight 1 (Jawa Tengah-1) 5,010,468.00 0.00 Pending NSUP-OSP-2 / Oversight 2 (DIY & Jawa Tengah-2) 5,132,774.00 0.00 Pending NSUP-OSP-3 / Oversight 3 (Jawa Timur-1) 4,160,018.00 0.00 Pending NSUP-OSP-4 / Oversight 4 (Jawa Timur-2) 3,922,368.00 0.00 Pending NSUP-OSP-5 / Oversight 5 (Nusa Tenggara Barat, Bali, Nusa Tenggara Timur) 5,560,615.00 0.00 Pending NSUP-OSP-6 / Oversight 6 (Kalimantan Selatan & Kalimantan Tengah) 3,809,716.00 0.00 Pending NSUP-OSP-7 / Oversight 7 (Kalimantan Timur) 2,174,187.00 0.00 Pending NSUP-OSP-8 / Oversight 8 (Sulawesi Utara, Gorontalo & Maluku Utara) 4,629,585.00 0.00 Pending NSUP-OSP-9 / Oversight 9 (Sulawesi Selatan, Sulawesi Barat, Sulawesi Tengah) 5,364,061.00 0.00 Pending NSUP-OSP-10 / Oversight 10 (Sulawesi Tenggara) 1,809,185.00 0.00 Pending

Page 2 NSUP-OSP-11 / Oversight 11 (Maluku, Papua, Papua Barat) 4,810,410.00 0.00 Pending NSUP-ADV-12 / Non Consultant Service For Advisory Team 3,264,450.00 0.00 Pending 2017-09-05 2017-09-10 2017-10-22 2017-11-21 2017-12-26 2018-06-24 CONSULTING FIRMS Contract Type Amount Status Combined Evaluation Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Technical Terms of Reference Report and Draft Signed Contract Contract Completion Notice Request for Proposals as Issued Proposals / Minutes Proposal Negotiated Contract NSUP-CS-1 / NATIONAL MANAGEMENT CONSULTANT (NMC) REGION - 2 Services Investment Support Prior Quality And Cost- Based Selection Open - International 4,413,577.00 0.00 Pending 2017-03-10 2017-03-31 2017-08-22 2017-09-29 2017-10-19 2017-12-01 2018-01-15 2021-07-15 INDIVIDUAL CONSULTANTS Contract Type Amount Status Invitation to Draft Negotiated Terms of Reference Identified/Selected Signed Contract Contract Completion Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual