The State of Interconnection in NYS:

Similar documents
National Grid System Reliability Procurement DemandLink Pilot Update

Rhode Island Renewable Distributed Generation Standard Contract Enrollment Application and Enrollment Process Rules

The Narragansett Electric Company d/b/a National Grid

July 1, 2006 Revision 2

Generator Interconnection System Impact Study Report Carteret County, NC MW Queue #297 Original Submittal Revision 1

The Narragansett Electric Company d/b/a National Grid

Southern California Edison Original Cal. PUC Sheet No E Rosemead, California (U 338-E) Cancelling Cal. PUC Sheet No.

2017 All Source Request for Proposals for Electric Power Supply and Load Management Resources. Pre-Bid Meeting

Renewable Portfolio Standard Planning and Development Process

Request for Proposal (RFP)

Generator Interconnection Facilities Study Report Franklin County, NC 50.0 MW Solar Farm Queue #384

Refer to section 2.C. for more information on the evaluation criteria.

ADVERTISEMENT OF PUBLIC NOTICE

Small and Large Generator Interconnection Procedures

2012 Request for Proposals Solar On-site Renewable Energy Credits (REC)

Illinois Power Agency Long-Term Renewable Resources Procurement Plan. What s Next?

Title 35-A: PUBLIC UTILITIES

PacifiCorp 2017S SOLAR Request for Proposals. Bidder s Conference Portland November 21, 2017

NY-Sun CHG&E SOLAR SUMMIT VI 6th Annual Conference for Solar Energy Professionals

Energy Efficiency Alberta Residential and Commercial Solar Program Guidebook

May 6, 2002 Revision 2

STATE OF NEW YORK PUBLIC SERVICE COMMISSION CASE 16-

ORANGE & ROCKLAND UTILITIES, INC. REQUEST FOR INFORMATION FOR ENTITIES WISHING TO SUBMIT DISTRIBUTED GENERATION PROPOSALS February 2003

Generator Interconnection Impact Study Report Bladen County, NC 75.0 MW Solar Farm Queue #377

Comprehensive Interconnection Process Improvements

MCE Feed-In Tariff for Distributed Renewable Generation

FEED-IN TARIFF POLICY APPLICATION AND IMPLEMENTATION GUIDELINES

FY2016 RENEWABLE ELECTRIC STORAGE INCENTIVE PROGRAM STRAW PROPOSAL MAY 07, 2015

Request for Proposal

Feed-in Tariff: Guidance for renewable installations (Version 5)

Standard Development Timeline

Energy. Request For Proposals for Renewable Power Supply Resources

Generator Interconnection Impact Study Report Wayne County, NC 20.0 MW Solar Farm Queue #364

Request for Proposal

4.10. Organ and Tissue Donation and Transplantation. Chapter 4 Section. Background. Follow-up to VFM Section 3.10, 2010 Annual Report

RESIDENTIAL AND SMALL COMMERCIAL STANDARD OFFER PROGRAM

COUNTY OF SANTA BARBARA

FEED-IN TARIFF LICENSEE TRANSFER

Federal and State Incentives for Wind Development

UCF SOLAR FARM-UCF 584 Solar Developer Project Fact Sheet

SOUTH CAROLINA ELECTRIC & GAS COMPANY REQUEST FOR PROPOSALS FOR SOLAR PHOTOVOLTAIC DISTRIBUTED ENERGY RESOURCES AT TWO DESIGNATED SITES

SREC Securitization Straw Proposal June 13, 2008

Statewide Codes & Standards Program 1

CENTRAL MUNICIPAL POWER AGENCY/SERVICES

Request for Proposals and Specifications for a Community Solar Project

Northline Solar Project

REVISOR RSI/BR RSI-ENERGY

e - Lab Accelerator! A Boot Camp for Electricity Innovation!

Non-Pipeline Solutions Pre-RFP Webinar. January 24, 2018

Energy Efficiency Alberta Residential and Commercial Solar Program Terms and Conditions

First Nations Energy Education Exchange Workshop

DRAFT PROPOSAL REQUIREMENTS

INDUSTRIAL ENERGY OPTIMIZATION PROGRAM

2017 Solar*Rewards Large Request for Proposals Solar On-site Renewable Energy Credits (REC)

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION. North American Electric Reliability ) Corporation ) Docket No.

Request for Proposals for Technical and Financial Feasibility Assessment of Community Microgrid Projects in Massachusetts

Energy Savings Bid Program 2007 Policy Manual

Renewable Energy Feed-in-Tariff Stakeholder Workshop Objectives

THE CITY OF SEATTLE CITY LIGHT DEPARTMENT 2012 REQUEST FOR PROPOSALS. Long-Term Renewable Resources And/or Renewable Energy Certificates

EVALUATION AND STATUS REPORT

107 FERC 61,053 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION

microfit FAQ Version 4.1

LADWP Feed-in Tariff (FiT) Program Workshop. LABC & Council District 14 Councilmember Jose Huizar November 12, 2014

Request for Proposals ( RFP ) Under the SREC-Based Financing ( SREC-II ) Program

Trade Ally WPS Bonus Bid Program

Pilot Project Initiative

ENERGY PERFORMANCE CONTRACTING

RFP No. FY2017-ACES-02: Advancing Commonwealth Energy Storage Program Consultant

To ensure system protection is coordinated among operating entities.

Page. II. TECHNICAL ASSISTANCE PROJECT DESCRIPTIONS.. 3 A. Introduction... B. Technical Assistance Areas.. 1. Rate Design Consumer Programs...

New Solar Homes Partnership. Web Tool Application Guide

Multifamily Affordable Solar Housing. Semi Annual Progress Report. July 30, 2012

Indigenous Supportive Housing Program (ISHP)

NHS ISLE OF WIGHT CLINICAL COMMISSIONING GROUP CLINICAL FUNDING AUTHORISATION POLICY

City of Batavia Downtown Improvement Grant

Interconnection: Meeting the Solar Rush. Leslie Moynihan, Snohomish PUD Jake Wade, Puget Sound Energy Katie Zook, Seattle City Light

Regional Greenhouse Gas Initiative, Inc. Request for Proposals #18-01 RGGI Auction Services Contractor. June 18, 2018

New York State COMMUNITY DEVELOPMENT BLOCK GRANT PROGRAM. Microenterprise Assistance PROGRAM GUIDELINES

APPENDIX D CHECKLIST FOR PROPOSALS

DRAFT. PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA Item 18 (Rev.1) Agenda ID ENERGY DIVISION RESOLUTION G-3522 November 10, 2016

CUSTOM INCENTIVE GUIDE

2018 RENEWABLE ENERGY GROWTH PROGRAM

CONSUMERS ENERGY COMPANY REQUEST FOR PROPOSALS SOLAR GENERATION PROJECTS. Bids Due: July 28, :00 noon EPT (Jackson, MI) Issued.

PART 1 - Rules and Regulations for the Renewable Energy Development Fund Programs

What You Should Know About the Siting of Major Electric Generating Facilities

Indigenous Supportive Housing Program (ISHP)

a clean energy leader without specific measures to ensure that low-income households participate and benefit.

Scaling Solar: An Update. Mr. Dana R. Younger Chief Renewable Energy Specialist Global Infrastructure & Natural Resources Department March 5, 2018

STATE OF NORTH CAROLINA UTILITIES COMMISSION RALEIGH DOCKET NO. E-2, SUB 1089 BEFORE THE NORTH CAROLINA UTILITIES COMMISSION

California s Distributed Solar Energy Program. Working to Transform the Market for Solar PV and Thermal

AUSTIN ENERGY REQUEST FOR PROPOSALS (RFP) FOR THE PURCHASE OF RENEWABLE CAPACITY & ENERGY FROM RENEWABLE ENERGY RESOURCES

NY-Sun Operating Plan. New York State Energy Research and Development Authority Albany, NY

Submitted Pursuant to: Minnesota Statutes section 216C.43, subd. 12 Prepared by: Department of Commerce Division of Energy Resources

Solar Photovoltaic. Standard Offer Program (SVPSOP) 2018 Program Manual. Rev # Final

FREQUENTLY ASKED QUESTIONS

Program Plan For the Energy Efficiency and Renewable Energy Technology Account Under New York s Clean Air Interstate Rules (CAIR)

APPLICATION PROCEDURE TO OPERATE A COMMERCIAL CANNABIS BUSINESS IN CULVER CITY

PROGRAM OPPORTUNITY NOTICE EFFICIENCY MAINE TRUST CUSTOM INCENTIVE PROGRAM FOR DISTRIBUTED GENERATION PROJECTS PON EM

California Self-Generation Incentive Program Evaluation

EFFICIENCY MAINE TRUST REQUEST FOR PROPOSALS FOR LOAD MANAGEMENT INNOVATION PILOTS RFP EM Date Issued: April 12, 2018

Transcription:

The State of Interconnection in NYS: Understanding the Current Situation, Navigating the New Interconnection Requirements in NY, and What s Next Melissa Kemp, NYSEIA Policy Co-Chair

About NYSEIA NYSEIA is the only statewide membership and trade association dedicated solely to advancing solar energy use in New York state. Led by a growing staff and diverse Board of Directors, NYSEIA strives to achieve responsible and sustainable solar energy adoption throughout the state, while creating jobs that benefit communities and urgently reducing the environmental impacts from fossil fuels.

Importance of Interconnection and SIR Interconnection is an essential component of renewable electricity project feasibility from a project development timeline, certainty, and economic viability perspective The Standard Interconnection Requirements (SIR) are New York s state-wide regulations intended to create uniform interconnection rules and processes for connecting distributed generation (DG) systems that use state jurisdictional rates to New York s electric distribution grid. The SIR provides application procedures, requirements, review and screening processes, timelines, cost guidelines etc.

Current State of Interconnection in NY Interconnection has become an even more critical topic in New York over the last two years, as larger scale projects and a greater volume of projects have been proposed, and New York s clean energy goals have become more defined and now mandated through the new Clean Energy Standard. The status of the interconnection of projects through the SIR in New York is published once per month by the Joint Utilities in PSC Matter 13-00205. These filings include completed MW and proposed MW in the queue by utility, as well as information on the projects in the queue themselves including date application received, project developer, project size, project technology, circuit #, and information on project process stages and costs

Current State of Interconnection in NY New York has installed 483 MW of non-wind DG (mostly solar) through the JUs and SIR as of 8/31/16, and roughly another 250 MW minimum through LIPA/PSEG to total around 733 MW total The recent construction rate in New York has been about 150 MW in 2015 and just over 80 MW this year so far

Current State of Interconnection in NY The current queue is larger than NY has experienced in the past. As of August 31, 2016, the NY interconnection queue stands at a total of 3,906 MW of proposed non-wind projects - three times the size it was at the beginning of 2016 and 11 times the size it was in early 2015 But there is wide consensus from stakeholders and market participants that it does not accurately reflect the number of feasible projects, as there have been many information-seeking, speculative, and/or immature applications

Current State of Interconnection in NY MW of Solar Capacity 4500 4000 3500 3000 2500 2000 1500 1000 500 0 1/31/15 Total Queue Size (MW) 1/31/16 7/31/16 Total Installed to Date (MW)

Recent Challenges and Interconnection Issues No way to get information on circuits upfront without submitting an interconnection application and getting in the queue Different technical standards being used by utilities across the state to evaluate project feasibility and decide on necessary upgrades Effectively no binding timelines for developer decisions and payments Lack of project maturity requirements to enter and continue through queue Lack of tools help projects better manage delays due to local moratoriums and high cost upgrades Significant variation in upgrade costs across utility territories and lack of transparency about those costs Delays in the reports and studies in the process In part driven by waves of application in response to regulatory changes

Recent Challenges and Interconnection Issues Lack of some key types of data in the published interconnection queue and need for further standardization of how much and in what format the queue is shared Lack of standardization of data provided across all utilities in the SIR process reports, such as the Preliminary Technical Reports and CESIR studies Lack of policy for the process of updating these reports, and also what constitutes material modification of applications No requirements for construction scheduling or completion

New SIR Update After months of work between DPS, the JUs, and the DG industry, a significant update to the SIR was announced by the PSC on March 17, 2016 and went into effect formally on April 29, 2016. It can be accessed on the New York DPS DG website, and the full order is available in the PSC Docket Case #15-E-0557. It is a significant step towards addressing several of the above issues (as shown in orange below) The update included the addition of a pre-application report option, standardized initial technical screens and supplemental review, binding developer/project milestone timelines, and a lower payment to execute an interconnection contract

Update to the SIR: Process 50 kw 5MW A. Step 2: Pre-application Report Request (Appendix D) Request by applicant for 13 key pieces of information on the distribution circuit interested in connecting to. No customer name or site control required, and does not place you in the interconnection queue. Fee is $750, Utility has 10 business days to complete, and Applicant has 15 business days to use fee credit; Receipt of fees continue to trigger start of timelines. Many utilities are now offering online or digital payment options. This information can be used to determine likelihood of passing preliminary screens, supplemental screens, and potential for high-cost upgrades. We are going to begin to review how to use this information most effectively later on in the presentation.

Update to the SIR: Process 50 kw 5MW (Cont) B. Step 3: Application Submission If the pre-application report information indicates that the circuit is viable or you already know a circuit, submitting a formal interconnection application is the next step. Application requirements are similar to the past and still requires Customer Name for non-cdg projects, but are now listed in a formal checklist (Appendix F). Fee is $0 if received completed pre-application report recently (within past 15 business days) or $750 if not; Utility has 15 business days to complete the preliminary review; Incomplete applications will be removed from the interconnection queue after 30 business days

Update to the SIR: Process 50 kw 5MW (Cont) C. Step 4: Utility Performs Screening Analysis Utility review now includes a set of six preliminary standard state-wide technical screens (Appendix G). After receipt of preliminary report, Applicant has 30 business days to decide and notify utility on next steps or removed from the interconnection queue. Next step options are:

Update to the SIR: Process 50 kw 5MW (Cont) If passed preliminary screens, should go straight to executed contract with no CESIR or further study and no upgrade requirements If failed one or more screens, applicant can request: Preliminary Analysis Results Meeting Optional meeting with utility intended to offer quick possible resolution if failed a preliminary technical screen with obvious straightforward solution (i.e. revision of system size slightly downward, replacement of one piece of equipment due to rating, etc)

Update to the SIR: Process 50 kw 5MW (Cont) Supplemental Review 2 nd set of three technical screens that applicant can request to be applied to project (Appendix G). Intended for projects that minimally fail one or more preliminary technical screens but that may not be an issue if slightly more study done. Most likely to apply to projects under 1 MW. There is a $2,500 fee and 20 business day turnaround. Full CESIR Study If neither of the two options seems likely to provide a solution, a full study is required. Withdraw the Application

Update to the SIR: Process 50 kw 5MW (Cont) D. Step 5 and 6: CESIR Study If Required - Requirements remain similar to previous SIR. Utility has 60 business days to complete and up to 80 business days if over 2 MW. Detailed description of reasoning for any system upgrades required along with utility cost estimates broken down by specific equipment requirements, labor, etc. Contingencies associated with the cost estimates shall not exceed +/- 25%. E. Step 7: Deposit, and Execution of Contract - After CESIR completion, applicant has 60 business days to pay 25% of upgrade costs to execute interconnection contract, which sets your place in the queue and locks in the project s property tax status. The remaining 75% of costs are then due in an additional 120 days and then utility upgrades can start.

Update to the SIR: Rationale for Technical Screens The overriding goal is to maintain the safe and reliable operation of the distribution grid while enabling larger amounts of distributed generation to be interconnected more efficiently and more cost effectively The concept of a screening analysis is to identify a common set of conservative conditions which, if met, make it very unlikely for the generation to be able to cause any unacceptable impacts on the functioning of the distribution grid The current method of screening has been traced to the early 2000 s with California s Rule 21 A collection of 13 screens (six of which were adopted in the new SIR) are currently in use in California, Hawaii, Massachusetts and a number of other States as well as by the Federal Energy Regulatory Commission s Small Generator Interconnection Procedures

Update to the SIR: Preliminary Screening Analysis Screen A: Is the PCC on a Networked Secondary System? Screen B: Is Certified Equipment Used? Screen C: Is the Electric Power System (EPS) Rating Exceeded? Screen D: Is the Line Configuration Compatible with the Interconnection Type? Screen E: Simplified Penetration Test (15% of the annual peak load) Screen F: Simplified Voltage Fluctuation Test (Voltage fluctuation < 5% of the prevailing voltage level and voltage flicker not included here) For a full discussion of these screens, and their purpose and rationale please see NYSEIA s webinar, Understanding the new Interconnection Rules for Developers from May 3, 2016 on our website

Update to the SIR: Supplemental Review If a system fails the preliminary review and a results meeting cannot identify readily agreeable options to enable interconnection, supplemental review can be chosen for systems that the developer believes are likely to be interconnectable with additional scrutiny but without requiring a full system impact study The cost is $2,500 and the timeline for completion is 20 business days If a system is unlikely to pass the three supplemental review screens the developer can opt at any time to move to a CESIR

Update to the SIR: Supplemental Review (cont) Screen G: Supplemental Penetration Test (is the aggregate Generating Facility capacity on the Line Section less than 100% of the minimum load and definition of minimum load important) Screen H: Power Quality and Voltage Tests (allows for a more detailed assessment of the potential voltage impacts caused by the proposed generation) Screen I: Safety and Reliability Tests For a full discussion of these screens, and their purpose and rationale please see NYSEIA s webinar, Understanding the new Interconnection Rules for Developers from May 3, 2016 on our website

Recent Challenges and Interconnection Issues No way to get information on circuits upfront without submitting an interconnection application and getting in the queue Different technical standards being used by utilities across the state to evaluate project feasibility and decide on necessary upgrades Effectively no binding timelines for developer decisions and payments Lack of project maturity requirements to enter and continue through queue Lack of tools help projects better manage delays due to local moratoriums and high cost upgrades Significant variation in upgrade costs across utility territories and lack of transparency about those costs Delays in the reports and studies in the process In part driven by waves of application in response to regulatory changes

Recent Challenges and Interconnection Issues Lack of some key types of data in the published interconnection queue and need for further standardization of how much and in what format the queue is shared Lack of standardization of data provided across all utilities in the SIR process reports, such as the Preliminary Technical Reports and CESIR studies Lack of policy for the process of updating these reports, and also what constitutes material modification of applications No requirements for construction scheduling or completion

What s Next Interconnection Queue Management While the SIR update was significant step forward, it did not address the large volume of projects that had entered the queue before it took effect, and it did not completely address all of the important areas of queue management going forward Critical to projects moving to construction and maximizing the utility of the new screening process Proposal out of 3 month collaboration in the Interconnection Policy Working Group to be filed this Friday Includes such items as: Requiring Property Owner Consent and Site Control Applying Binding Timelines for Developer Decisions and Payments to Interconnection Applications Submitted Prior to April 2016 Allowing Extensions for Committed Projects with Local Permitting Moratoriums Implementing a Limited Mandatory Cost Sharing Mechanism

What s Next Interconnection Technical Working Group (ITWG) Goal of creating best practice technical standards that work towards reduction of barriers, which will simplify the process and costs Issues include: Substation Level Reverse Power Flow Anti-islanding and DTT Requirements Monitoring and Control Requirements Voltage Flicker and Regulation Begun drafting of state-wide common technical standards matrix

Recent Challenges and Interconnection Issues No way to get information on circuits upfront without submitting an interconnection application and getting in the queue Different technical standards being used by utilities across the state to evaluate project feasibility and decide on necessary upgrades Effectively no binding timelines for developer decisions and payments Lack of project maturity requirements to enter and continue through queue Lack of tools help projects better manage delays due to local moratoriums and high cost upgrades Significant variation in upgrade costs across utility territories and lack of transparency about those costs Delays in the reports and studies in the process In part driven by waves of application in response to regulatory changes

Recent Challenges and Interconnection Issues Lack of some key types of data in the published interconnection queue and need for further standardization of how much and in what format the queue is shared Lack of standardization of data provided across all utilities in the SIR process reports, such as the Preliminary Technical Reports and CESIR studies Lack of policy for the process of updating these reports, and also what constitutes material modification of applications No requirements for construction scheduling or completion

Questions? Melissa Kemp, melissa.kemp@3reenergyconsulting.com