CWE Flow-based Market Coupling Project

Similar documents
CWE Flow-based Market Coupling Project. at EMART Energy 2012

CWE Flow-Based Market Coupling: on the Eve of Implementation. Pieter Schavemaker and Philippe Noury

CWE FB MC project. PENTA SG1, April 8 th 2013, Brussels

CWE FB MC project. PLEF SG1, March 30 th 2012, Brussels

Flow-Based Market Coupling First lessons

CWE Enhanced FB. Report presentation. March 22 nd, 2011

Casc Publication Handbook

POSITION PAPER BY ALL CWE NRAs on THE CWE TSOs PROPOSAL for A FB IDCC METHODOLOGY

Position Paper of CWE NRAs on Flow- Based Market Coupling

Status WG European Market Design. Users Group 20 March 2014

Context paper CWE Intraday

CWE Flow-Based Market Coupling Forum. 23 rd of June 2014 in Düsseldorf

Methodology for capacity calculation for ID timeframe

BritNed: Enabling Market Integration

Documentation of the CWE FB MC solution as basis for the formal approval-request (Brussels, 9 th May 2014)

CWE MC Go-Live Forum. Düsseldorf June 8th

Implementation of day-ahead (DA) market coupling in the North-Western Europe (NWE) region summary memo

Current and future challenges of TSOs in the European Market design. Dr. Oliver John 27 September 2016

Nordic FB Stakeholder Forum

Social Welfare Report / 2014*

Leading coordination For enhanced reliability of supply.

Balancing pilot projects update. April 2016

Cooperation between the Nordic and the Baltic power systems in Electricity Balancing

NWE Day-Ahead Market Coupling Project. 2 nd Progress Report

Nordic TSO Perspective on the future of the Nordic Electricity Market

Publishing date: 04/02/2014 Document title: We appreciate your feedback. Share this document

Developing an Incremental Proposal for EU gas transmission. Draft Project Plan

Joint European Stakeholder Group. Tuesday 21 November 2017 Meeting 25 London

Pilot Program Framework Proposal

Publishing date: 29/05/2015. We appreciate your feedback. Share this document

Joint European Stakeholder Group. Monday 12 February 2018 Meeting 29 WebEx

2017 All Source Request for Proposals for Electric Power Supply and Load Management Resources. Pre-Bid Meeting

DER Pilot Program. Brian Yung Market Design Specialist Business Issues Committee. August 9, 2017, 10 Krey Blvd, Rensselaer, NY 12144

STDF MEDIUM-TERM STRATEGY ( )

UPDATE ON THE MOROCCAN SOLAR PLAN

I-SEM Cutover Run Sheet

Explanatory document for the Nordic synchronous area proposal for coordination actions aiming to reduce FRCE as defined in Article 152(14) and

SMART ENERGY DISTRIBUTION SYSTEMS

Darstellung der TEN-E Verordnung und der Connecting Europe Facility

Global vision, Unified solutions

Rhode Island Renewable Distributed Generation Standard Contract Enrollment Application and Enrollment Process Rules

Andrew Kirby Director, Healthcare Solutions Microsoft Services

Distributed Multi-Nodal ATFM Operational Trial

Page. II. TECHNICAL ASSISTANCE PROJECT DESCRIPTIONS.. 3 A. Introduction... B. Technical Assistance Areas.. 1. Rate Design Consumer Programs...

ENTSO-E Practical implementation document for inclusion of trasmission and storage projects in the 10-year network development (TYNDP)2018

Good practices on Single Window Regional Integration Experience of ASEAN countries

WEDNESDAY APRIL 27 TH 2011 OUTREACH & PILOT RECRUITMENT

Technical and Vocational Education and Training (TVET) System in Lagos State

User Group Meeting. December 2, 2011

Renewable Energy Feed-in-Tariff Stakeholder Workshop Objectives

Day-Ahead Market and Forward Reliability Commitment Timing to Meet FERC Order on Compliance for Gas Electric Scheduling Requirements

During the 4 Years: December, December, 1994 * TOTAL INDUSTRY JOBS LOST (30,800) -1.9%

EPSRC-KETEP Call for Collaborative Research between the UK and Korea in Smart Grids

PacifiCorp 2017S SOLAR Request for Proposals. Bidder s Conference Portland November 21, 2017

1st Workshop Federal Grid Code

winning in US commercial staffing

Recommendations for Digital Strategy II

Child Welfare Services New System Project

Organization: Frederick Memorial Hospital. Solution Title: We Found the Missing Piece to Our CLABSI Puzzle

Project Update. BAAF October 14, 2016

Plan of Action for the Information Society in Latin America and the Caribbean elac 2007

ACER s functions and responsibilities in the European Union

CLINICAL AUDIT JOB VACANCIES REPORT (edition 5) PUBLISHED JULY 2015

TECHNICAL DAYS, APRIL 2017 ABB Plant Fingerprint Assessment Optimizing Operations. Fernando Tobar, Country Service Manager

TRANSMISSION TRANSMISSION SYSTEM OPERATIONS DIVISION

SMALL AND MIDSIZE BUSINESSES IN ASIA-PACIFIC

HEALTH WORKFORCE SUPPLY AND REQUIREMENTS PROJECTION MODELS. World Health Organization Div. of Health Systems 1211 Geneva 27, Switzerland

Building a Smarter Healthcare System The IE s Role. Kristin H. Goin Service Consultant Children s Healthcare of Atlanta

Jun 03 Jul 03 Aug 03 Sep 03 Oct 03 Nov 03 Dec 03 Jan 04 Feb 04 Mar 04 Apr 04 May 04

Long Range Development Plan Advisory Groups Sustainability

The Nurse Labor and Education Markets in the English-Speaking CARICOM: Issues and Options for Reform

Implementation of HB 2941, Section 3 Community Solar Program Design August 11, Reminder Please add your name to the sign in sheet.

Joint European Standing Group Meeting 32

Income Eligible Procurement. February

A McKesson Perspective: ICD-10-CM/PCS

capital markets day 2017 london. human forward.

LESSONS LEARNED IN LENGTH OF STAY (LOS)

Nordic Open Access. Background and Developments. 10th Fiesole Collection Development Retreat March 28-29, 2008

Avoiding the Cap Trap What Every Hospice Needs to Know. Matthew Gordon, CPA Principal Consultant / Founder Cap Doctor Associates, Inc.

R&D Tax Credits. Energy and natural resources sector

Term of Contract 15-year term, from 1 October 2018 to 31 December 2033

From Implementation to Optimization: Moving Beyond Operations

FREEWAT modeling platform: software architecture and state of development Iacopo Borsi TEA SISTEMI SpA

Request for Proposal (RFP)

Fourth Quarter 2006 Results 5 Jun (Listing Date) to 30 Sep 06 Analyst and Media Briefing. 16 October 2006

REGIONAL I. BACKGROUND

Accreditation Support for Ohio Local Health Districts Request for Training or Technical Assistance - Round 1 The Ohio Department of Health

Group Professionals Concept. Robbin Brugman MD Group Professionals Concept

From Big Data to Big Knowledge Optimizing Medication Management

The Narragansett Electric Company d/b/a National Grid

Why Nordic Health and Welfare Innovation?

European Association of Public Banks

The Key Principles And Characteristics Of An Effective Hospital Medicine Group

8/30/ American Public Works Association (APWA) International Congress and Exposition. August 30, 2015

The development dimension of e-commerce and the digital economy

Small and Large Generator Interconnection Procedures

Experiential Education

Request for Proposal

THE IAEA FUKUSHIMA REPORT AND THE IMPLICATIONS FOR NUCLEAR SAFETY AND EMERGENCY PREPAREDNESS

Performance-Based Regulation: The Power of Outcomes

Transcription:

CWE Flow-based Market Coupling Project 1

Agenda ATC CWE MC Operations CWE FB MC Project FB implementation status FB theoretical basics Market communication during the external parallel run 2

ATC CWE MC - Operations (R.ROUSSEAU) 3

ATC CWE MC - Operations New common CWE website CWE Project launched a new common website where actual flow data and prices as well as ATC data are available on a daily basis: You can visit this website at the following address: https://www.europeanpricecoupling.eu/ 4

ATC CWE MC - Operations Long Clock Change (LCC) The functioning of Long Clock Change within the different systems has been changed: 2011 Due to different market rules and some technical constraints, ATC values for hours 3a and 3b had to be set to zero on hub borders (FR-DE, FR-BE, DE-NL) For EPEX SPOT, participants had to submit the same order for the hours 3a and 3b For APX and Belpex, participants had to submit orders for 25 hours instead of 24 2012 Today both exchanges have the same market rules regarding LCC As a consequence, 25 hours ATC will be published and all participants will submit 25 hours order books Please note that for Nordic countries (included in ITVC coupling) the rule does not change this year and only 24 hours bidding will be possible (hour 3A and 3B are doubled automatically). EMCC was updated to accommodate both rules Satisfying tests to simulate the dealing with 25 hours were organized: LCC day and the day after were tested Tests run smoothly 5

CWE FB MC - Project (P. FONCK) 6

CWE FB MC - Project Context CWE-Region roadmap and objectives: Harmonization and improvement of long-term explicit auction rules Implementation of a day-ahead Flow Based market coupling Implementation of harmonized continuous cross-border intraday trade Maximization of the amount and the utilization of cross-border capacities Increase of market Transparency Guarantee regarding Security of Supply (SoS) 2007 2010 FB parallel run 2013 Signature of the Memorandum of Understanding by the Pentalateral Energy Forum Launch of CWE ATC MC Launch of CWE FB MC Objective: analysis, design and implementation of a flow-based market coupling between 5 countries of the CWE region Objective: first step towards an integrated day-ahead market while studying a FBMC in parallel Objective: simulating the impact of FB MC Objective: algorithm taking into account a more sophisticated grid modeling in order to optimize commercial flows on the electrical interconnections of meshed networks as in the CWE region Objective: A CWE FB MC providing more trading opportunities for the market and maximizing the CWE Day-Ahead market 7

CWE FB MC - Project Project Planning Dependencies: Stabilization of FB computation before end of 2012 Duration of external parallel run (one full year vs. 10 months including seasonality) Duration of simulations and testing with NWE Regulatory approval 2012 2013 Predictability of LT auctions: As FB MC Go Live is foreseen for the end of 2013, the impact of this market design change on LT capacity auctions is minimized for 2013 July Aug Sept Oct Nov Dec Jan Feb March April May June July Aug Sept Oct Nov Dec Parallel run Internal parallel run External parallel run (weekly publication) External parallel run (daily publication) Delivery to NRAs NRA approval Stakeholders acceptance Approval package Delivery of PC documents to NRAs Public Consultation Survey Final approval package* CWE FB MC Go live window Market Parties implication through FB_UG meetings Support Utility tool and Q&A Forum * Including answers to public consultation s outputs Market Forum Market Forum Market Forum 8

FB implementation status (P. NOURY) 9

FB implementation status Methodology stabilization All TSOs have been steadily working on a detailed action plan in order to stabilize the FB methodology in terms of: Generation Shift Keys Flow Reliability Margins Generation Shift Keys (GSK) Flow Reliability Margins (FRM) Critical Branches (CB) (GSK) (FRM) selection Remedial Actions (RA) Experimentation of new methodologies in order to overcome the main limitations of the current approach Finalization of operational FRM values thanks to the learning of the internal parallel run currently performed by TSOs Implementation of objective selection process in order to foster the usage of an adequate Critical Branches set Implementation of coordinated usage of RA under Flow based in order to optimize the capacity domain All TSOs are confident that the provided work on these actions will be reflected in the parallel run results The FB principles will be described in detail in the CWE consultation package and will be submitted to Regulatory approval in the course of 2013 10

FB implementation status Operational deployment In implementing a complete new methodology, CWE Project had to recognize the complexity of the process at different levels: Operational Level IT Level Faced with local TSO organization, CWE Project is challenged to coordinate the activities between all TSOs Knowledge transfer and management relations within the operators, control centers, experts need to be assured despite alternating shifts Sophisticated IT developments need to be designed and implemented and their availability is subject to a lot of negotiations and testing All TSOs have been permanently improving their operational and decision making process and are confident that a stabilized and coordinated process will be implemented for the parallel run 11

FB implementation status Experimentation results Current experimentation results show a gap between theoretical studies, detailed in the Feasibility Report, and practical results in terms of welfare gain, convergence rate, etc This gap, which shows that the potential of FB is not yet reached at an operational level, is linked to the notions introduced in the 2 previous slides: In terms of methodology: TSOs are finalizing the adjustment of the model to operational reality In terms of operational implementation: Transfer of expertise to operators and ad hoc tools development are also being finalized TSOs are putting all their effort in the stabilization of an efficient and effective process so as to reach the potential of FB when the parallel run is launched and to provide the most relevant results to Market Parties during the external parallel run 12

FB theoretical basics (P. NOURY) 13

FB theoretical basics Main concepts of CWE FB FB plain and intuitive FB experimental results FB in CWE and ATCs outside the CWE region 14

Main concepts of CWE FB Congestion management in the broadest sense Determination of available transmission capacity Capacity allocation Congestion forecast If needed: congestion relief Bids / reservations Generation schedules Timeline 15

Main concepts of CWE FB Approximation of the security of supply domain Example with 3 countries Country B Country A Monitored lines Outage scenario Margin left (MW) Influence of exchange on lines (PTDF) A B A C B C No outage 150 10% Outage1 Line 1 120 Outage 1 20% +100 MW line 1 Country C Line 2 Line 3-100 MW 16

Main concepts of CWE FB The security of supply domain Exchange(A>C) 400 Monitored Lines Line 1 Line 2 Line 3 Outage scenario Margin left (MW) Influence of exchange on lines (PTDF) A B A C B C No outage 150 1% 10% 3% Outage 1 120 5% 20% 1% Outage 2 100 6% 25% 1% No outage 150-2% 0 5% Outage 3 100-12% 0 10% No outage Outage 4! Numbers are for illustration only 300 200 100-100 - 200-300 0 Exchange(A>B) 400-300 - 200-100 0 100 200 300 400-400 Constraints Security of supply domain 17

Main concepts of CWE FB ATC & FB constraints theory Security domain is obtained by taking into account all the relevant physical constraints of the grid Exchange(A>C) 400 300 200 Given the security domain, NTC/ATC constraints and the corresponding NTC/ATC domain are a choice made by the TSO 100-100 0 Exchange(A>B) - 400-300 - 200-100 0 100 200 300 400-200 - 300 The FB domain is the security domain itself - 400 constraints polyhedron NTC/ATC security domain Flow-based 19

Main concepts of CWE FB ATC and FB domain Determination of available transmission capacity step 1 step 2 output Exchange(A>C) 400 300 200 100 Security of Supply domain Capacity split Between borders ATC 0-400 - 300-200 - 100 0 100 200 300 400-100 Exchange(A>B) FB - 200-300 - 400 20

Main concepts of CWE FB ATC vs FB constraints theory FB offers more trading opportunities with the same level of security of supply Exchange(A>C) 400 300 200 In FB capacity split is not a choice of the TSO, but is market driven (at the time of allocation) 100-100 0 Exchange(A>B) - 400-300 - 200-100 0 100 200 300 400-200 - 300-400 constraints polyhedron NTC/ATC security domain Flow-based 21

FB plain and intuitive Intuitiveness As a result of the optimization process within the allocation system, the outcome of market-coupling can on some occasions be qualified as counter-intuitive which may lead to situations with some bilateral exchanges against the spread where an area with the cheapest (most expensive) price is importing (exporting). These results were partly based on some normative assumptions to be further assessed during the parallel run This non-intuitive feature has a physical explanation: the counter-intuive exchange releaves a constraint somewhere in the grid, hence allowing other exchanges bringing more welfare The market coupling system can cope with such situation through the applying of the intuitive-patch. Counterintuitive exchanges can then be forbidden, however this is at the cost of welfare since it is equivalent to adding additional constraints in the system Today, the 2 options are open : plain FB or intuitive FB. This topic will be specifically addressed during the public consultation, and this will be supported by detailed documentation. Moreover, the external parallel run will provide simulations under the 2 models 22

FB experimental results FB domain CWE reported in Oct 2011 on their experimental findings with FBMC, based on 9 weeks of data ( CWE Enhanced Flow-Based MC feasibility report ) FB offers more trading opportunities with the same level of SoS as the current coordinated ATC 23

FB experimental results FB market impact FB market coupling results in higher welfare and better price convergence compared to the current ATC MC ones 24

FB in CWE and ATCs outside the CWE region Hybrid Coupling (1/2) For Hybrid coupling two variants exist: 1. Standard: realized ATC transactions are not taken into account in the margin of the CBs TSOs need to reserve margins (worst-case) on their CBs for the possible usage by the ATC area FB area Price coupling ATC ATC area Just like today No competition for the use of the scarce capacity in the allocation mechanism due to the ex-ante split Not optimal: scarce capacity not always fully used Total margin on the CB Margin reserved for the ATC Margin left for the FB 25

FB in CWE and ATCs outside the CWE region Hybrid Coupling (2/2) 2. Advanced: realized ATC transactions are taken into account in the margin of the CBs TSOs do not need to reserve margins on their CBs use of margin is market driven Price coupling Competition for the use of the scarce capacity in the allocation mechanism FB area ATC ATC area Optimal use of scarce capacity Maximum social welfare Interconnection is subject to FB price properties (typically: counter-intuitive exchanges on CWE Non CWE borders, price spread on both ends of the line while its capacity is not fully used) CWE FB Market coupling will go live with a standard hybrid coupling while keeping open the possibility to evolve towards an advanced hybrid coupling in a later stage Total margin on the CB Margin available for the FB and ATC trades 26

Market communication during the external parallel run (J. HOEKSEMA) 27

Market communication during the external parallel run MP support CWE Project proposes different forums to ensure a clear and transparent communication between all Market Parties and the Project during the external parallel run: 2012 2013 July Aug Sept Oct Nov Dec Jan Feb March April May June July Aug Sept Oct Nov Dec Parallel run Internal parallel run External parallel run (weekly publication) External parallel run (daily publication) Delivery to NRAs NRA approval Stakeholders acceptance Support Continuous meetings will ensure steady exchanges between the Market and the Project Delivery of PC documents to NRAs Market Parties implication through FB_UG meetings Market Forum Approval package A Kickoff Market Forum before the start of the external parallel run end of 2012 to explain the functioning of the parallel run and the functionalities of the utility tool Public Consultation Market Forum Survey Final approval package* Opportunity for MPs to address all questions closely related to FB methodology which will be taken into account in the NRAs approval document Q&A Utility Forum tool CWE FB MC Go live window Platform Available where in XLS format explanations, and accessible FBUG s outcomes, on CASC s expert Market website will help presentations MPs to do their and simulations pedagogical material are available Forum during the external parallel run A second Market Forum during the public consultation process where MPs questions will be answered 28

Market communication during the external parallel run Focus on Utility tool (1/2) The following interface allows simulations for trading volumes of CWE MC Markets for each hour: Maximum exchange from DE to BE assuming no other exchanges (Non simultaneous values!) Maximum DE export (other areas are importing to ensure the balance) 29

Market communication during the external parallel run Focus on Utility tool (2/2) Market graphs and a CWE map facilitate the understanding of impacts of trade volumes for hub to hub exchanges: Maximum bilateral exchanges CWE max net positions and bilateral exchanges Data shown for hour: 13 For a live demonstration of the utility tool simulation facilities: 30