Version 5 24 th August City Deal and Growth Deal Programme Board. Business Case Approval Form

Similar documents
National Productivity Investment Fund for the Local Road Network Application Form

Report. To the Chair and Members of CABINET

1 - PROJECT DETAILS 1.1 PROMOTER S INFORMATION. Title and full name of main contact: Position: Investment and Economic Initiatives Manager

BOROUGH OF POOLE COUNCIL. 15 December 2015

Sheffield City Region Mayoral Combined Authority. Additional evidence, such as letters of support, maps or plans should be included in an annex.

2014 to 2020 European Structural and Investment Funds Growth Programme. Call for Proposals European Social Fund. Priority Axis 2 : Skills for Growth

European Regional Development Funding Breakfast Briefing

Further capital spend proposals (following the Call for Projects ) Melanie Corcoran, Director of Delivery

Mark Dance, Cabinet Member for Economic Development. Growth, Economic Development and Communities Cabinet Committee 21 November 2017

Greater Cambridge Partnership Executive Board. Chris Tunstall Interim Transport Director. Western Orbital

Northern Cultural Regeneration Fund

Heritage Grants - Receiving a grant. Mentoring and monitoring; Permission to Start; and Grant payment

National Productivity Investment Fund for the Local Road Network Application Form

Community Energy: A Local Authority Perspective

This report will be open to the public on 11 July 2017.

Project Priority Assessment Tool

2015 FSB Wessex Regional Local Authority Small Business Friendly Awards Dorset

Developing a New Strategy for the Visitor Economy

HIGH SPEED 2 SUPPLY CHAIN PROGRA AMME (HS2 SCP)

English devolution deals

Black Country Land & Property Investment Fund

Land and Property Investment Fund (LPIF) Project Lifecyle APPENDIX 37

Funding New Homes with HCA Grant and Other Sources Risks and Regulations JOHN PATERSON

England s Economic Heartland

Central Bedfordshire Council. Determination of Proposal to Commission New Middle School Places in Leighton Buzzard

1.1 Introduction. 1.2 Strategic Context HES Corporate Plan

UKRI Strength in Places (SIPF) Programme Overview

BIRMINGHAM CITY COUNCIL STRATEGIC DIRECTOR OF DEVELOPMENT & CULTURE

Northern Community Rail Station Adoption Fund Application Process

Centurion Way Feasibility Study - South Downs National Park Authority Application for Coast to Capital LEP Feasibility Fund

OUTLINE BUSINESS CASE TEMPLATE LGF3 : Crewe High Speed-ready Heart Regeneration Programme

Cherwell Local Plan (Part1)

Targeted Basic Need Programme Questions and Answers

Priority Axis 1: Promoting Research and Innovation

Office for Students Challenge Competition Industrial strategy and skills support for local students and graduates

D2N2 LGF DEAL SHEET Revised, 25 th June 2014

ABERDEEN CITY REGION DEAL:

The Growth Fund Guidance

WOLVERHAMPTON CCG. Governing Body Meeting 9 th September 2014

Rural Strategy & Food Enterprise Zones. Jon Burgess, Greater Lincolnshire LEP

GM Devolution. Darren Banks Executive Director of Strategy

WMCA Board. Date 8 December Report title Midland Metro Wednesbury to Brierley Hill Extension - Submission of Transport and Works Act Order

Targeted Regeneration Investment. Guidance for local authorities and delivery partners

Business Plan Lancashire: The Place for Growth.

SHEFFIELD CITY REGION DEVOLUTION AGREEMENT

Doncaster Council Inward Investment Incentives. Pilot Scheme Policy Document

MEETING OF THE GOVERNING BODY IN PUBLIC 7 January 2014

2014 to 2020 European Structural and Investment Funds Growth Programme. Call for Proposals European Social Fund. Priority Axis 2 : Skills for Growth

PROJECT CALL GUIDANCE - Expression of Interest (Stage 1)

Application for Funding

Manchester Health and Care Commissioning Board. A partnership between Manchester. City Council and NHS Manchester Clinical Commissioning Group

TYRE STEWARDSHIP AUSTRALIA. Tyre Stewardship Research Fund Guidelines. Round 2. Project Stream

Local Energy Challenge Fund

CARDIFF CAPITAL REGION JOINT CABINET JOINT CABINET MEETING 15 JANUARY 2018 METRO CENTRAL PROJECT REPORT OF COUNCILLOR HUW THOMAS AGENDA ITEM: 8

Yorkshire and Humber Integrated Urgent Care: Service Development and Procurement

Corsham Mansion House

Appendix 1: Public Health Business Plan: Priority One - Effective public health commissioning

Introduction to GRIP Governance for Railway Investment Projects

EUA Finance for the Regions: The economic benefits of retrofitting Victoria s building stock through Environmental Upgrade Agreements.

Application Form Green Infrastructure Fund

ERDF WORKSHOP. ERDF 20/12/2016

Enterprise Solution Centre Programme Frequently Asked Questions

Transport NI York Street Interchange APPENDIX A PROJECT BRIEF

Guideline for Applicants to the Building Resilience to Climate Change Grants Program August 2014

Appendix 2 Watford Borough Council Economic Development Action Plan

ANEURIN BEVAN HEALTH BOARD CLINICAL FUTURES STRATEGY AND SPECIALIST CRITICAL CARE CENTRE: BRIEFING

Methods: National Clinical Policies

England s Economic Heartland Strategic Alliance Strategic Transport Forum. 12 th February Agenda Item 4: Governance Arrangements

Project Lifecycle Full Business Case

Greater Norwich Growth Board Meeting Minutes

Draft South East Creative Economy Network Towards a SELEP Creative Open Workspace Master Plan. Executive Summary

Greater Norwich Development Partnership Greater Norwich Employment Growth Study Summary of Recommendations

Workforce Development Fund

Renal Unit - Full Business Case. Full Business Case Executive Summary. Renal Unit

Research Funding: Expanding Excellence in England (E3) Fund

SUCCESS - RGF funded support for the creative sector in coastal SELEP areas

Newham Clinical Commissioning Group Board Meeting

THE TECHNOLOGY DEVELOPER ACCELERATOR PROGRAMME. Helping to turn low carbon technology into products developed in the UK

The Integrated Support and Assurance Process (ISAP): guidance on assuring novel and complex contracts

The ideal Local Authority. Green Deal and ECO

Outcome Based Commissioning in Richmond. March 2015

RESPONSE TO RECOMMENDATIONS FROM THE HEALTH & SOCIAL CARE COMMITTEE: INQUIRY INTO ACCESS TO MEDICAL TECHNOLOGIES IN WALES

GREATER BIRMINGHAM AND SOLIHULL GROWTH DEAL

1 Fund Summary The Havant Economy The Fund Capital Investment Fund Types of Funding Grants...

BIRMINGHAM CITY COUNCIL PUBLIC REPORT

Local Pinch Point Fund Application Form

AGENDA 4 th June pm at Exhibition Room, Innovation Centre, York Science Park, University of York.

JOB DESCRIPTION. WMAHSN Patient Safety Programme Manager

June Page 1 of 7

STOCKPORT S PORTAS PILOT

Report of the ESTATES COMMITTEE. 19 January 2010

Regional assistance programs

COMMISSIONING SUPPORT PROGRAMME. Standard operating procedure

ERDF : Low Carbon Travel and Transport (LCTT) Programme

84% 70% 139m. 20m. 300m. 600m 6, ,000 jobs 13,750. Impact of SFT s work. When complete, TIF projects will support

Consultation on fee rates and fee scales

Trust Board Meeting : Wednesday 11 March 2015 TB

Award of the new Adults Homecare Service, Extra Care and Children s Care Support Services Contract

Full Business Case. County Hospital Outpatients (Executive Summary) May Contents

Page 1 EXTRAORDINARY COUNCIL MEETING 4 April 2016

Transcription:

Version 5 24 th August 2016 City Deal and Growth Deal Programme Board Business Case Approval Form 1. Project title and proposing organisation(s) Former ROF Featherstone Strategic Employment Site Access Improvements Promoted by Staffordshire County Council. 2. Decision date 31 st October 2016. 3. Decision summary: Recommendation etc. On the assumption that the ROF Featherstone project receives funding through Growth Deal 3, that the City Deal and Growth Deal Programme Board recommends: Spending of circa 700,000 for project development in Financial Year 2016/17 to mitigate against slippage of spending from the Growth Deal 1 and Growth Deal 2 programmes Funding will be switched from the Stafford Western Access Growth Deal 1 allocation Further project funding up to the total of 2 million requested through the Growth Deal 3 bid 4. Is the decision exempt from being publically reported by the LEP (if so please specify the reasons why) No 5. Options appraisal The ROF Featherstone Site is a strategically important employment site, at a key gateway location to the West Midlands conurbation and with excellent links to the local and national highway network. Access constraints and expensive abnormal off site infrastructure costs have acted as a barrier to investment to date, however these are now being overcome through the appetite of local partners to promote economic growth at this location. Gap funding is required to make the development a viable proposition when considering the market value of the development site balanced against the costs of remediation, access and infrastructure and professional fees. As part of a viability and delivery options study commissioned by South Staffordshire Council in connection with the ROF Featherstone employment site, a Page 1 of 10

number of potential access options and site development options, taking account of local access constraints have been assessed, including: Do nothing Option 1 Two options which provide a link between Brookhouse Lane to Cannock Road with two possible alignments: A) Access from Brookhouse Lane to Cannock Road, south of Featherstone; or B) Access from Brookhouse Lane to M54 J1 eastbound off slip, south of Featherstone. Option 2 Access from New Road to Brookhouse Lane; Option 3 Upgrade of existing rail underpass on Brinsford Road/Cat and Kittens Lane; Option 4 New connection from Cat and Kittens Lane to Stafford Road; and Option 5 New connection from Brookhouse Lane to Stafford Road. A further scheme option has more recently been explored, involving the improvement of Cat and Kittens Lane to a point south of the M54 with the construction of a new carriageway to the roundabout junction of the A460, Bognop Road and Moseley Road. A detailed transport modelling and options appraisal exercise is now being undertaken, and the results of this will inform the development of the preferred option. 5.1. Strategic case The ROF Featherstone site is the single largest undeveloped employment land site in the South Staffordshire Local Plan. A viability and delivery options study commissioned as part of the Local Plan review in 2014 identified that the site was unlikely to come forward commercially without a modest extension to the existing employment allocation (this extension has been proposed through a site allocations document), and would not be economic unless gap funding to offset abnormal off site infrastructure costs was secured. The project will directly contribute to the following SSLEP priorities: 1) Connected County delivery of the ROF Featherstone Strategic Employment site would help address market demand for high quality employment sites around the M54 in South Staffordshire, contributing to a portfolio of high quality investment ready sites in the area alongside i54 and Bericote Four Ashes. The SEP priority for competitive connectivity prioritises the bringing forward of strategic employment sites underpinned by strong supporting transport and supporting infrastructure to drive business growth. The strategic location of the site close to junction 1 and 2 of the M54 and the proposed M54/M6/M6 Link road provides an ideal opportunity for a sustainable transport solution. 2) Sector Growth Unlocking the site will create the conditions for, and promote enterprise led expansion in large and small businesses across our priority sectors. The M6 / M54 corridor has built a recent reputation as an area of high growth and strong market interest in high value manufacturing and engineering and its connected supply chains. In particular, the area is becoming increasingly attractive Page 2 of 10

to the automotive, aerospace and high technology sectors. The corridor is also superbly located to attract logistics and distribution developments. 5.2. Economic case The fully developed site is estimated to create up to 2800 jobs which are likely to be equally split between B2 (general industrial) and B8 (distribution and warehousing) uses. This has been calculated as follows: B2 uses = 1935 jobs (69,677 sq m of floor space at employment density of 36 sq m per FTE job) B8 uses = 870 jobs (69,677 sq m of floor space at employment density of 80 sq m per FTE job) These employment densities are calculated as per the Homes and Communities Agency Employment Density guidance which is available from the following link: https://www.gov.uk/government/publications/employment-densities-guide The estimated GVA benefits from the site will be quantified following greater certainty around the end users on site, however given the anticipated split of development outlined above the total GVA generated by employment on site once fully developed out could be in the order of - 104,095,695 B2 uses: 1935 jobs x 38861 (GVA per employee in manufacturing) = 75,196,035 B8 uses: 870 jobs x 33218 (GVA per employee in logistics) = 28,899,660 5.3. Commercial case The County Council has a full professional team to deliver major capital projects, including significant strength and depth in town planning, surveying, civil engineering and all the building professional disciplines. The Council also has strategic partnerships with Amey to deliver civil engineering projects and with Kier to deliver building projects. This ensures early contractor involvement in all projects and significantly reduces procurement and contract delays. This team is supported by an experienced team of project managers, lawyers, finance and procurement specialists. The County Council has significant skills and experience in managing the finances of large capital projects. The Council has a clear understanding of the costs and timescales involved in bringing forward capital projects and in selling employment land. Within the County Council s team, we have experienced civil engineering quantity surveyors and development surveyors. Our legal and financial teams also have considerable experience in supporting our capital programme. The preferred option for procurement of a works contractor will be through the partnership with Amey through the Infrastructure + framework contract, with a reserve option to use the Midlands Highways Alliance framework contract. Page 3 of 10

5.4. Financial case Total Project Cost Total cost of the project? Up to 12.5 million Funding Requirements and Leverage / Match Funding total funding requirement being requested Costs have been developed based on a preliminary scheme survey which have informed preliminary designs based on the options identified at 5 Options Appraisal above. These costs have been assessed by a quantity surveyor and factored for inflation based on a 2018 works start date. An optimism bias factor of 25% has been applied alongside a project contingency allowance of 10%. Relevant professional fees and preliminaries have been accounted for within these cost assumptions. 2.0 million The funding request is as set out in the initial Growth Deal 3 funding bid expression of interest. Match funding to be provided 3.75m (private sector) This contribution will be secured from the private sector development partner through the Site Implementation Agreement. 6.75m (other public sector) The proposal for other public sector contributions will be sourced from a loan secured against the future business rates received from the scheme. 5.5. Management case The Senior Responsible Owner is Steve Burrows, Commissioner for Business and Enterprise at Staffordshire County Council. The project will be managed in accordance with PRINCE 2 principles and reported on a regular basis through Staffordshire County Council s Economic Growth Programme and Senior Leadership Team mechanisms. The risk management strategy to be employed for the project will be aligned to the PRINCE2 TM project management methodology and Staffordshire County Council s Corporate Risk Management Policy. The project forms part of Staffordshire County Council s Economic Growth Programme which considers and allocates relevant resources to drive economic growth in the county. As part of the infrastructure + partnership arrangement with Amey, Staffordshire County Council has unrivalled access to engineering project management and delivery resources. Risks will be constantly reviewed throughout the life of the project and revised as necessary. The Project Manager will maintain the high level Risk Register and be responsible for ensuring that programme and project risks are identified, assessed and controlled throughout the lifetime of the project. Page 4 of 10

At present, the potential for unexpected additional costs is assessed to be low, however as with any proposal of this nature, market risks associated with the attractiveness and viability of the site, and economic risks such as inflation and the wider performance of the economy at a macro level will be mitigated against on a proportionate and appropriate basis. Where appropriate, risks will be costed in order that a comprehensive record of potential project costs is maintained and managed. Risks will be reviewed at contract award stage through a risk workshop and a shared risk register produced to allocate ownership and determine the value of the residual risks to be included within the Target Cost. 5.6. Resource and VFM analysis Cost/Benefit Analysis Taking the overall estimated costs of the project and anticipated Gross Value Added benefits into account, the project Benefit to Cost Ratio is: 104.1 million (total GVA benefit) / 12.5 million (project cost) = BCR of 8.3 In addition, the project is expected to generate 52 of Gross Value Added Benefits for every 1 of Growth Deal funding. Scheme Funding A funding request of 2million was included in the Growth Deal 3 bid submission. The ROF Featherstone site has been identified as one of the priority projects within the submission. The project team has a well developed relationship with the private sector owners and developers of the site St. Francis Group, and initial Heads of Terms for the Site Implementation Agreement between parties, including expectations of funding have been agreed. The Site Implementation Agreement identifies a private sector contribution of 3.75m. The remaining project costs are funded through a public sector contribution of 6.75m which will be borrowed against the anticipated receipts through business rates associated with the development. Cost assumptions Cost over runs are not expected to be significant as a fully costed programme will be prepared by a Quantity Surveyor in the determination of a final target cost for the project. At this point of the project an optimism bias factor of 25% has been added to the initial project costs alongside a project contingency rate of 10%. Page 5 of 10

Financial risks will also be managed through the use of an NEC Option C contract which incentivises the robust identification of costs and a Pain and Gain mechanism to deal with potential variations to the target cost. All land required for the project is either within the ownership or an option of ownership of the developer and will be dedicated at zero cost or is within the public highway Infrastructure The project will deliver the following outputs: Newly constructed and upgraded highway and associated junctions to provide access to development site (the total length of road will be subject to the confirmation of the preferred option route) Diversion of existing utilities and services (the provision of new utilities to the site will be at the expense of the site developer) As a direct result of the infrastructure project: The remediation of approximately 36 hectares of net developable land by the site developer Employment outputs As set out in section 5.2 above, the fully developed site is estimated to create up to 2800 jobs which are likely to be equally split between B2 (general industrial) and B8 (distribution and warehousing) uses. This has been calculated as follows: B2 uses = 1935 jobs (69,677 sq m of floor space at employment density of 36 sq m per FTE job) B8 uses = 870 jobs (69,677 sq m of floor space at employment density of 80 sq m per FTE job) 6. Consultation process Staffordshire County Council s Cabinet gave its approval to undertake the design and project management of the infrastructure for the scheme at its meeting on the 18 th May 2016. The preferred option for the final scheme will be informed by a detailed consultation exercise which is scheduled to commence during November 2016. The principle of development at the ROF Featherstone employment site has been extensively tested through the South Staffordshire Local Plan review which is expected to be adopted in early 2018. Following selection of the preferred option a further consultation exercise will be undertaken as part of the planning application for the project. 7. Location of proposal Page 6 of 10

Please see plan enclosed at appendix 1 8. Risk analysis Risk that South Staffordshire Council s Site Allocations Document is not adopted this risk is determined to be of high impact, but lower probability due to the general conformity with policy of the Core Strategy which allows for modest extensions to the existing freestanding sites. Mitigation continual engagement with South Staffordshire Council and membership of project team to ensure consistency of approach Proximity of potential options for proposed road to the Moseley Old Hall National Trust property this risk is determined to be of high impact and medium probability. The proximity of the scheme to the Moseley Old Hall heritage asset will require careful stakeholder engagement and will be sensitively designed to the local topography to ensure that its setting is not harmed. Mitigation careful stakeholder engagement with National Trust and other key stakeholders through concerted communications campaign to mitigate risk. Road will need to gain planning permission this risk is determined to be of high impact and medium probability. The preferred approach will be for the planning application to be determined by Staffordshire County Council through a regulation 3 planning application, and in this respect there is a low level of risk that the scheme will not be approved. There may be some risks associated with public opposition to the project, and in relation to possible cross boundary impacts with Wolverhampton City Council. - Mitigation SCC led regulation 3 planning application will minimise risks associated with gaining planning permission for road infrastructure Risk that ROF owners conclude that the project, even with an extension to the site, does not financially stack up this risk is determined to be of high impact and medium probability, this risk is being mitigated through working in close partnership with the developer St. Francis Group which is keenly pursuing the development of the site. Mitigation St. Francis Group team is actively involved in project team, and investment will be subject to the terms and conditions of Site Implementation Agreement. Initial market testing suggests that the site is attractive to market, and will be successfully brought forward. The cost of the new road exceeds the commercial viability and development value available to cross subsidise the road The costs of the project will be assessed by a Quantity Surveyor and include allowances for Optimism Bias and contingency. The private sector contributions identified have been agreed in principle with the developer. Mitigation strict cost controls attached to project management through a quantified costed risk assessment of the project, and the overall economic case for the project as set out above 9. Legal analysis The relevant legal arrangements will be confirmed in a Site Implementation Agreement between the developer St. Francis Group and Staffordshire County Council as the delivery body. The outcome of the options appraisal exercise and selection of a preferred option will inform the land take required for the project. At present all land required for the initial preferred option is either within the ownership of, or under option to the developer St. Francis Group. Page 7 of 10

10. Delivery The site is not within the defined Green Belt and is highlighted as one of four Freestanding Employment Sites in the adopted Core Strategy. South Staffordshire District Council have recently held a Site Allocations Preferred Options consultation which proposes an extension of up to 50% to the area of the existing 24ha site. The existing 24ha site (which includes 10ha of planting) has previously gained permission for B1/B2 use. However, the applicant did not implement the permission as it was felt that the lack of B8 use, alongside the poor local road network directly surrounding the site, meant that the planning permission was not considered financially viable to implement. The viability of the site has informed the current proposals to extend the area of the site by 50% as set out above. The County Council has a full professional team to deliver major capital projects, including significant strength and depth in town planning, surveying, civil engineering and all the building professional disciplines. The Council also has strategic partnerships with Amey to deliver civil engineering projects and with Kier to deliver building projects. This ensures early contractor involvement in all projects and significantly reduces procurement and contract delays. This team is supported by an experienced team of project managers, lawyers, finance and procurement specialists. The County Council has significant skills and experience in managing the finances of large capital projects. The Council has a clear understanding of the costs and timescales involved in bringing forward capital projects and in selling employment land. Within the County Council s team, we have experienced civil engineering quantity surveyors and development surveyors. Our legal and financial teams also have considerable experience in supporting our capital programme. The preferred option for procurement of a works contractor will be through the partnership with Amey through the Infrastructure + framework contract, with a reserve option to use the Midlands Highways Alliance framework contract. 11. Timetable The detailed programme and timetable will be confirmed following the conclusion of the options appraisal and consultation exercises. At present the indicative timetable is as follows: Completion of initial scheme design April 2017 Ecological survey works early 2017 Planning application submission summer 2017 Planning application determination Autumn 2017 Refinement of target costs and finalise business case Autumn/Winter 2017 Award Contract Winter 2017/18 Commence construction February 2018 Page 8 of 10

Complete construction March 2019 Benefits realisation (in the form of employment on site are expected to commence on site from March 2019 it is the developers intention to undertake site assembly works concurrently with the delivery of the infrastructure scheme) 12. Author Jonathan Vining Economic Growth Programme Manager Staffordshire County Council Tel 01785 277353 E mail jonathan.vining@staffordshire.gov.uk 13. Decision details For official use only details of date considered by City Deal and Growth Deal Programme Board and any additional information for decision record Page 9 of 10

APPENDIX 1 FORMER ROF FEATHERSTONE SITE LOCATION PLAN Page 10 of 10