Members of the Board of Directors. Wendy Knowles, Clerk of the Board. Update on the California High-Speed Rail Program Revised 2012 Business Plan

Similar documents
CALIFORNIA HIGH-SPEED RAIL DIANA GOMEZ

Special Meeting Agenda

The New Incrementalism: Building and Financing US High-Speed Rail

CONNECTING AND TRANSFORMING CALIFORNIA. Ben Tripousis, Northern California Regional Director SPUR Tuesday, October 25, 2016 San Jose, California

City of Palo Alto (ID # 6831) City Council Staff Report

Connecting and Transforming California

SUBJECT: REGIONAL RAlL PLANNING AND ENGINEERING BENCH AND REGIONAL RAlL UPDATE. INITIATE PROCESS TO ESTABLISH A REGIONAL RAlL BENCH

SAN IPSE CAPITAL OF SILICON VALLEY ?/2W/(T. Memorandum TO: HONORABLE MAYOR AND CITY COUNCIL. FROM: Kim Walesh Jim Ortbal

Regional Transportation Activities Report. VTA Funding Measure

To: From: Subject: Program continues to. Overview. the City of. Background. began the. As part of with both

Diridon Station Joint Policy Advisory Board MINUTES

Peninsula Corridor Joint Powers Board Legislative Program

A. Amend the FY LACMTA Budget to add $3,000,000 from Measure R 3% Commuter Rail funds for the Rancho Vista Grade Separation Project

May 17, To: From: Subject: Program continues to. Overview. Step Two. fixed-guideway. Program. for. Background

Metrolink Budget for FY /Additional Service on the Antelope Valley Line

ORANGE COUNTY TRANSPORTATION AUTHORITY. Agreement for Construction of the Placentia Avenue Railroad Grade Separation Project.

Memorandum Plans and Programs Committee June 21, 2016

San Francisco to San Jose (Caltrain) / HNTB

2018 State of County Transportation Jim Hartnett, General Manager/CEO

Re: Comments on the Draft Guidelines for the Low-Carbon Transit Operations Program

A High Speed Foundation: How to Build a Better California Around High Speed Rail

Long Range Transportation Plan

San Francisco Transportation Plan (SFTP) and Early Action Plan

Thursday, January 26, :00 PM 7:30 PM SamTrans Offices - Bacciocco Auditorium 2 nd Floor 1250 San Carlos Ave., San Carlos.

FISCAL YEAR ECONOMIC IMPACT ANALYSIS TECHNICAL SUPPORTING DOCUMENT

San Francisco Transportation Task Force 2045

MOBILITY PARTNERSHIP AGENDA

SAN MATEO COUNTY TRANSPORTATION AUTHORITY (TA) 1250 SAN CARLOS AVENUE, SAN CARLOS, CA MINUTES OF SEPTEMBER 1, 2016

UC MERCED. Sep-2017 Report. Economic Impact in the San Joaquin Valley and State (from the period of July 2000 through August 2017 cumulative)

PUBLIC-PRIVATE PARTNERSHIP PROGRAM, HIGH DESERT CORRIDOR

Authority Board March 26, 2013

~BEVE~Y AGENDA REPORT

THE CALIFORNIA STATE UNIVERSITY

San Mateo County Measure A Grade Separation Program

Economic Development Subsidy Report Pursuant to Government Code Section 53083

SUPERIOR COURT OF THE STATE OF CALIFORNIA COUNTY OF SACRAMENTO

2016 Measure B Program Areas

John Baker Regulatory Analyst California Public Utilities Commission. May 22, 2014

SECTION II. Collection and Analysis of Metro Contract Data

The Value of Metrolink in Relieving Peak-Hour Freeway Congestion

Public and Agency Involvement. 8.1 Scoping Meetings and Noticing. Chapter 8

REMOVE II Public Transportation Subsidy and Park-and-Ride Lot Component GUIDELINES, POLICIES, AND PROCEDURES GUIDELINES, POLICIES, AND PROCEDURES

Integrated Regional Conservation and Development. Avoid and Minimize Project Impacts

KEY CONTACTS NORTHERN CALIFORNIA. National Provider Contracting & Network Management: Department Phone No. Fax No. TTY (510) (510)

PUBLIC TRANSPORTATION & COMMUTER VANPOOL PASSENGER SUBSIDY COMPONENT REMOVE II PROGRAM GUIDELINES, POLICIES, AND PROCEDURES

Agenda. Tulare County Association of Governments Railroad Advisory Committee

Metro. Board Report. File #: , File Type:Informational Report

DRAFT. PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA Item 18 (Rev.1) Agenda ID ENERGY DIVISION RESOLUTION G-3522 November 10, 2016

CITY OF LOS ANGELES CALIFORNIA

KEY CONTACTS NORTHERN CALIFORNIA. National Provider Contracting & Network Management: Department Phone No. Fax No. TTY (510) (510)

REQUEST FOR INFORMATION

THE PENINSULA ECONOMY

Meeting Agenda Thursday, September 6, 2018 Time: 10:00 a.m.

Federal Public Transportation Program: In Brief

J. Andrew Hansz. Ph.D., CFA, MAI Gazarian Real Estate Center Craig School of Business California State University, Fresno

Peninsula Corridor Joint Powers Board (JPB) Board of Directors Meeting 1250 San Carlos Avenue, San Carlos CA Minutes March 1, 2012

CSUF & Telecommuting. An analysis of the potential application of telecommuting practices at CSUF

Community Advisory Panel Meeting #

AGENDA. March 4, 2014 Tuesday. 4. Public Comment Public testimony by each individual speaker shall be limited to three minutes

Blue Shield/Care1st and Centene/Health Net Undertakings IHA Stakeholder Meeting

Shaping Investments for San Francisco s Transportation Future The 2017 San Francisco Transportation Plan (SFTP) Update

Amtrak in the New Era

NOTICE OF AVAILABILITY TIERED DRAFT ENVIRONMENTAL IMPACT REPORT FOR THE SAN FRANCISCO STATE UNIVERSITY CREATIVE ARTS & HOLLOWAY MIXED-USE PROJECT

Background Materials

SAN FRANCISCO MUNICIPAL TRANSPORTATION AGENCY

Harnessing High-Speed Rail. How California and its cities can use rail to reshape their growth

LIGHT RAIL: IS ORANGE COUNTY ON THE RIGHT TRACK?

State Project No. XXXXXX City Project No. c401807

RESOLUTION ADOPTINGPRINCIPLES AND APPROVING A LIST OF CANDIDATE PROJECTS AND FUNDING REQUESTS FOR REGIONAL MEASURE 3

$5.2 Billion Transportation Funding Deal Announced, includes $1.5 Billion for Local Streets and Roads

VTA s BART Silicon Valley Extension BART Phase II Project Update

VTA s Capital Projects Program & BART Phase II Procurement Opportunities. VTA s Procurement Fair and Workshop. November 1, 2016

VTA s BART Silicon Valley Phase II Extension Project

Berkeley Progressive Alliance Candidate Questionnaire June 2018 Primary. Deadline for submitting completed questionnaires: Friday January 19, 2018

In developing the program, as directed by the Board (Attachment A), staff used the following framework:

Paths Forward: The San Gabriel Valley Greenway Network

SAN FRANCISCO AIRPORT COMMISSION MINUTES

APPENDIX B BUS RAPID TRANSIT

What s Inside... January 2013

Staff Report. TO: Honorable Mayor and City Council DATE: June 16, 2015

THE CALIFORNIA STATE UNIVERSITY

Survey of Nurse Employers in California

San Francisco Municipal Transportation Agency Legislative Priorities

Met r 0 Met"'fKK'ibn Transportation Authority

BUDGETING WITH AN EYE ON

HACU MEMBER INSTITUTIONS BY SENATE DISTRICT

Defining the Terms: POLST, Advance Directives, and California s Infrastructure

Transit and Rail Efforts Impacting Northern Virginia

CONSERVATION STRATEGY GROUP

Blanket Travel Request Travel Expense Claim (blanket mileage) Policy and Procedures (travel prior to 12/1/14)

Peninsula Corridor Joint Powers Board (JPB) Board of Directors Meeting 1250 San Carlos Avenue, San Carlos CA MINUTES OF NOVEMBER 2, 2017

REQUEST FOR PROPOSALS

SAN JOSE CAPITAL OF SILICON VALLEY

Florida s Future: Funding Growth Through Public Private Partnerships. Ed Turanchik. March 10, 2014

% Pass. % Pass. # Taken. Allan Hancock College 40 80% 35 80% % % %

One Bay Area Grant (OBAG): Local Program Development - Criteria ACTION ITEM

Research Funding in Texas

SOUTHERN NEVADA HEALTH DISTRICT. Classification Plan Recommendations

Open House Round 2. State Rail Plan. A Collaborative Vision for Transportation

Higher Education includes the University of California (UC), the California State

Transcription:

BOARD COMMITTEE TRANSMITTAL May 14, 2012 To: From: Subject: Members of the Board of Directors Wendy Knowles, Clerk of the Board Update on the California High-Speed Rail Program Revised 2012 Business Plan Transit Committee Meeting of May 10, 2012 Present: Absent: Directors Dalton, Galloway, Glaab, Herzog, Nguyen, Pulido, and Winterbottom Director Bankhead Committee Vote No action was taken on this receive and file item. Staff Recommendation Receive and file as an information item. Orange County Transportation Authority 550 South Main Street / P.O. Box 14184 / Orange / California 92863-1584 / (714) 560-OCTA (6282)

ORANGE COUNTY TRANSPORTATION AUTHORITY Update on the California High-Speed Rail Program Revised 2012 Business Plan Staff Report

May 10, 2012 To: From: Transit Committeee Will Kempton, Chief Executive Officer Subject: Update on the California 2012 Business Plan High-Speed Rail Program Revised Overview The California High-Speed Rail Authority released its Revised 2012 Business Plan on April 2, 2012, updating the previous version released in November 2011. The Revised 2012 Business Plan includes updates to ridership and revenue projections, project cost, funding, schedule, and implementation strategies. This report provides an overview of the key changes made in the Revised 2012 Business Plan. Recommendations Receive and file as an information item. Background The California High-Speed Rail Authority (CHSRA) was required by state law to submit business plans to the legislature in 2008 and 2009. Chapter 618, Statutes of 2009 (Senate Bill 783, Ashburn), requires CHSRA to submit a business plan to the Legislature by January 1, 2012, and every two years thereafter. The CHSRA released its Draft 2012 Business Plan (Draft Plan) on November 1, 2011, to solicit comments and input. The Draft Plan included details on several key project components, including ridership and revenue projections, project cost, funding, schedule, and implementation strategies. More than 250 comments were submitted to CHSRA on the Draft Plan, including a comment letter by the Orange County Transportation Authority (OCTA) in December 2011. Over the past several months, CHSRA stafff has worked to address the comments and concerns raised by project stakeholders, including the California High-Speed Rail Peer Review Group, the Legislative Analyst s Office, and the Bureau of State Audits. The public feedback received on the Draft Plan, along with further analysis by CHSRA, resulted in a number Orange County Transportation Authority 550 South Main Street / P.O. Box 14184 / Orange / California 92863-1584 / (714) 560-OCTA (6282)

Update on the California High-Speed Rail Program Revised 2012 Business Plan Page 2 of significant changes which are presented in the California High-Speed Rail Program Revised 2012 Business Plan (Revised Plan), released on April 2, 2012, and adopted by the CHSRA Board of Directors (Board) on April 19, 2012. The Revised Plan addresses several of the comments raised in the December 2011 OCTA comment letter. A summary of OCTA s comments and how each is addressed in the Revised Plan is included in Attachment A. Discussion The Revised Plan includes a number of significant changes from the November 2011 version. There are four key changes that should be highlighted: 1. A lower overall cost for the blended system approach 2. Specific investment in the bookends of the system 3. Identification of an Initial Operating Segment (IOS) to be the Southern California section (Merced to Los Angeles) 4. Provides for incremental improvements to the Northern California section (Merced to San Jose/San Francisco) and the San Fernando Valley to Orange County sections while the IOS is being constructed Capital Cost for Blended System Capital costs to construct the high-speed rail (HSR) system under the blended approach dropped from an estimated $78.2 billion to $68.4 billion due to better utilization of existing rail systems, a faster project delivery approach, and a modified engineering and segment utilization approach. The full Phase 1 as included in the Draft Plan had included an estimated cost for implementing the system of $98 billion. The blended approach allows existing passenger rail service providers such as Amtrak, Metrolink, and Caltrain to provide much needed connectivity to the backbone of the HSR system by sharing facilities and tracks. This will allow for existing services to bridge the gaps in the HSR system from Central Valley to the urban areas in the north and south in advance of the full project build-out. Investment in the Bookends The Revised Plan also adopts an early investment strategy that would include up to $3.5 billion in improvements to the bookends of the system in the Bay Area and Southern California. These investments could provide immediate benefits to the existing passenger rail services operating in Southern California by reducing travel times and improving safety while paving the way for future HSR service. Improvements could include upgrades to stations, track and signal improvements, and a limited number of key grade separations.

Update on the California High-Speed Rail Program Revised 2012 Business Plan Page 3 As stated in the Revised Plan, the funding for these investments is anticipated to come from existing Proposition 1A or other sources to be identified. IOS and Incremental Improvements The CHSRA states in the Revised Plan that the preferred implementation strategy is to build the system s 300-mile IOS between Merced and the San Fernando Valley, rather than between Bakersfield and the Bay Area. This approach also supports the goal of closing the gap in the state s existing passenger rail system between the San Fernando Valley and Bakersfield. Finally, the Revised Plan provides for incremental improvements to the Northern California section of the system between Merced and San Jose/ San Francisco. These incremental improvements may include electrification of the Caltrain line and other infrastructure improvements that will improve speed and safety. Delivery Approach Defined In identifying the IOS, the Revised Plan further lays out the phased delivery approach for the construction of the statewide HSR system. Under the Revised Plan, each phase builds on the previous segment while attempting to leverage existing services to provide additional connectivity. The phased approach is outlined below: The phased approach begins with the construction of the 300-mile IOS between Merced and the San Fernando Valley. The IOS includes an initial construction section from Fresno to Bakersfield, the only segment of the system that is currently fully funded. This is essentially 130 miles of track and structures that will offer no new service, but according to the Revised Plan, will provide benefit to existing Amtrak San Joaquin service. Cumulative cost: $31.3 billion (in year of expenditure). The Bay to Basin segment will extend the IOS to 410 miles in length, linking San Jose and Merced to the San Fernando Valley, providing the first HSR connection between the Bay Area and Southern California. Cumulative cost: $51.2 billion (in year of expenditure). The Phase 1 Blended system would reach 520 miles in length, providing a one-seat ride between San Francisco and Los Angeles utilizing blended operations over existing systems in Northern and Southern California. Cumulative cost: $68.4 billion (in year of expenditure).

Update on the California High-Speed Rail Program Revised 2012 Business Plan Page 4 The planned completion date of the IOS is 2021, with Bay to Basin following in 2026, and the Phase 1 blended system in 2028 which is an earlier implementation than identified in the Draft Plan. With the adoption of the Revised Plan, the CHSRA Board made a specific motion to include language in the resolution that calls out the inclusion of the Los Angeles to Anaheim segment, including electrification. Currently, CHSRA staff is working on the development of that section in coordination with the Southern California stakeholders. Staff will continue to monitor the development of the Los Angeles to Anaheim section and will report to the Board as the section planning is further developed and refined. Summary On April 2, 2012, the CHSRA has released the Revised Plan, which includes a number of significant changes in project cost, schedule, and delivery approach based on additional analysis and stakeholder input on the November 2012 Draft Plan. Attachment A. Summary of Orange County Transportation Authority Comments and Concerns on the California High-Speed Rail Authority Business Plan Prepared by: Approved by: Jennifer Bergener Director, Rail Programs and Facilities Engineering (714) 560-5462 Jim Beil, P.E. Executive Director, Capital Programs (714) 560-5646

ORANGE COUNTY TRANSPORTATION AUTHORITY Update on the California High-Speed Rail Program Revised 2012 Business Plan Attachment A

ATTACHMENT A Summary of Orange County Transportation Authority Comments and Concerns on the California High-Speed Rail Authority Business Plan Prior Comment/Concern Summary of Comment/Concern Revised Plan Response Phased Delivery Approach Project Schedule Cost Increase Funding/Financial Plan Compliance with Proposition 1A Cost Comparisons Began with construction in the Central Valley and ignored investment in the system bookends Project schedule was increased 13 years, adding cost and timely use risks Significant increase; limited contingency identified for worst case scenarios Funding plan largely speculative and includes no firm/long-term commitment Does the business plan comply with Proposition 1A? Included incongruent comparisons to roadway/airport infrastructure projects Initial Operating Segment (IOS) is identified to be south (Merced to Los Angeles); includes specific investment in bookends to support blended approach Inclusion of the blended approach allows for faster delivery, recognizing benefits sooner; blended system by 2028 Reduced cost for Phase 1 blended of $68.4 billion ($78.2 in prior draft) Calls for significant private sector investment following the IOS; cap and trade identified as a backstop Not addressed No longer included