Actual Project Name : Community Recovery In Earthquake Affected Areas Through Urban Poverty Project Country: Indonesia

Similar documents
IMPLEMENTATION COMPLETION AND RESULTS REPORT (TF-55626) ON A MULTI-DONOR TRUST FUND FOR ACEH AND NORTH SUMATRA GRANT

L/C/TF Number(s) Closing Date (Original) Total Project Cost (USD) TF Dec ,900,000.00

Actual Project Name : Renewable Energy Market Transformation L/C Number: US$M): Project Costs (US$M

NATIONAL COMMUNITY EMPOWERMENT PROGRAM IN URBAN AREAS FOR APPROVED ON NOVEMBER 20, 2012 REPUBLIC OF INDONESIA

BETF: P (TF and TF013728)

INTEGRATED SAFEGUARDS DATASHEET APPRAISAL STAGE

Public Disclosure Copy. Implementation Status & Results Report Global Partnership for Education Grant for Basic Education Project (P117662)

INTEGRATED SAFEGUARDS DATASHEET APPRAISAL STAGE

Implementation Status & Results Indonesia ID SPADA in Aceh and Nias (P097605)

Foundation for Advanced Studies on International Development (FASID)

P (TF and TF ) Rekompak. George Soraya

PROJECT INFORMATION DOCUMENT (PID) ADDITIONAL FINANCING Report No.: PIDA4973. Project Name

L/C/TF Number(s) Closing Date (Original) Total Project Cost (USD) IDA Aug ,000,000.00

ACEH ECONOMIC DEVELOPMENT FINANCING FACIILITY (EDFF) ANNEX 1: ANTI-CORRUPTION ACTION PLAN

L/C/TF Number(s) Closing Date (Original) Total Project Cost (USD) IDA-51370,IDA-H Jun ,000,000.00

INTEGRATED SAFEGUARDS DATA SHEET CONCEPT STAGE Report No.: AC3002. Date ISDS Prepared/Updated: 02/22/2009 I. BASIC INFORMATION. A. Basic Project Data

INTEGRATED SAFEGUARDS DATA SHEET CONCEPT STAGE

FOR OFFICIAL USE ONLY RESTRUCTURING PAPER ON A

Implementation Status & Results Indonesia Support for Poor and Disadvantaged Areas Project (P078070)

Public Disclosure Authorized. Public Disclosure Authorized. Public Disclosure Authorized. Public Disclosure Authorized

FOR OFFICIAL USE ONLY RESTRUCTURING PAPER ON A

GRANT AGREEMENT (ADB Strategic Climate Fund) (Greater Mekong Subregion Biodiversity Conservation Corridors Project Additional Financing)

Multi-Donor Trust Fund for Aceh and North Sumatra Grant Agreement

INNOVATIONS IN FINANCE INDONESIA

KECAMATAN DEVELOPMENT PROJECT *

THE WORLD BANK IBRD * IDA WORLD BANK GROUP

EMPOWERMENT IN URBAN AREAS

L/C/TF Number(s) Closing Date (Original) Total Project Cost (USD) IBRD Dec ,000, Original Commitment 13,400,

United Nations Peace Building Fund Grant Agreement

Analyzing the UN Tsunami Relief Fund Expenditure Tracking Database: Can the UN be more transparent? Vivek Ramkumar

Global Environment Facility Grant Agreement

Resettlement Planning Document

THE NATIONAL SOLIDARITY PROGRAM (NSP) AND ITS RELATION TO UN-HABITAT 1

Implementation Status & Results Indonesia Support for Poor and Disadvantaged Areas Project (P078070)

NOTICE OF RECEIPT OF REQUEST. Request for Inspection. Nigeria: Lagos Metropolitan Development and Governance Project (P071340)

Procedure: PR/IN/04 May 21,2012. Procedure: Accreditation of GEF Project Agencies

4.07. Infrastructure Stimulus Spending. Chapter 4 Section. Background. Follow-up to VFM Section 3.07, 2010 Annual Report. Ministry of Infrastructure

EU Grant Agreement DOC8UMEW. Public Disclosure Authorized GRANT NUMBER TF0A2379. Public Disclosure Authorized. (Access to Sustainable Energy Project)

North Lombok District, Indonesia

GUIDELINES FOR THE IMPLEMENTATION OF THE PUBLIC INVOLVEMENT POLICY

Case study: System of households water use subsidies in Chile.

Re: Indonesia: JSDF Grant for Sustaining Women s Leadership Project Grant No.TF095058

RESTRUCTURING PAPER ON A PROPOSED PROJECT RESTRUCTURING OF HAITI - URBAN COMMUNITY DRIVEN DEVELOPMENT PROJECT (PRODEPUR) ADDITIONAL FINANCING GRANT

Anti Poverty Interventions through Community-based Programs (PNPM) and Direct Cash Support (PKH)

Your response to this survey is strictly anonymous and will remain secure.

The hallmarks of the Global Community Engagement and Resilience Fund (GCERF) Core Funding Mechanism (CFM) are:

RESTRUCTURING PAPER ON A PROPOSED PROJECT RESTRUCTURING OF THE URBAN SECTOR DEVELOPMENT REFORM PROJECT (USDRP) LOAN 7760-IND

GFDRR Country Evaluation:

Letter No. CD-399/PAMSIMAS/X/2013 October 30, 2013

Supporting Nepal to Build Back Better

REPORT BY THE COMPTROLLER AND AUDITOR GENERAL HC 686 SESSION DECEMBER Department of Health. Progress in making NHS efficiency savings

Honduras: Social Investment Fund IV and V

IMPLEMENTATION COMPLETION AND RESULTS REPORT (IBRD-72830) ON A LOAN IN THE AMOUNT OF EURO 35.0 MILLION (US$ MILLION EQUIVALENT) TO THE

RESTRUCTURING PAPER ON A PROPOSED PROJECT RESTRUCTURING OF

Wildlife Conservation Society 12/24/08 to 12/31/13 (72 months)

Global Partnership on Output-based Aid Grant Agreement

Financing Agreement. (National Program for Community Empowerment in Rural Areas Project) between REPUBLIC OF INDONESIA. and

PROJECT INFORMATION DOCUMENT (PID) APPRAISAL STAGE

ANNEX V - HEALTH A. INTRODUCTION

Multi Donor Fund for Aceh and Nias Project Update July 2006

INDONESIA NATIONAL ROADS IMPROVEMENT PROJECT WESTERN INDONESIA PROJECT INFORMATION DOCUMENT CONCEPT STAGE Report No.:AB2075 Project Name

Completion Report. Project Number: Loan Number: 2449-INO(SF) October Indonesia: Rural Infrastructure Support to the PNPM Mandiri Project

Abbreviations and Acronyms 4

Indonesia Humanitarian Response Fund Guidelines

TF ID (PEACH Grant for Sub-National Public Financial Management Capacity Building Project)

Instructions for completing the CFC Application Form

Nepal: Small Towns Water Supply and Sanitation Sector Project

Direct NGO Access to CERF Discussion Paper 11 May 2017

Financing Agreement. (National Program for Community Empowerment in Urban Areas Project) between REPUBLIC OF INDONESIA. and

OFFICIAL DOCUMENTS I

NEW PROJECT INFORMATION DOCUMENT (PID) APPRAISAL STAGE Report No.: Report No.: LATIN AMERICA AND CARIBBEAN Country

Implementation Status & Results Brazil BR-Housing Sector TAL (P050761)

Sri Lanka: Tsunami-Affected Areas Rebuilding Project

Indonesia: Aceh Nias Rehabilitation and Reconstruction

PROJECT INFORMATION DOCUMENT (PID) CONCEPT STAGE. Adaptable Program Loan P F-Financial Intermediary Assessment 08-May Nov-2012

PROJECT INFORMATION DOCUMENT (PID) CONCEPT STAGE

AFRICAN DEVELOPMENT BANK

Global Partnership on Output-based Aid Grant Agreement

AFRICAN DEVELOPMEMENT BANK EGYPT

Grantee Operating Manual

Report of the joint evaluation of the Indonesian ECB consortium s responses to the West Java and West Sumatra earthquakes

Implementing Projects, Achieving Results

Indonesia - FCPF Readiness Preparation Grant FCPFR - Forest Carbon Partnership Facility

Support for Applied Research in Smart Specialisation Growth Areas. Chapter 1 General Provisions

Mississippi Development Authority. Katrina Supplemental CDBG Funds. For. Hancock County Long Term Recovery CDBG Disaster Recovery Program

Country Partnership Strategy between the World Bank and the government of Morocco. CPS proposed framework

Use of External Consultants

Integrated Safeguards Data Sheet Identification / Concept Stage (ISDS)

Global Partnership on Output-based Aid. Grant Agreement. GPOBA GRANT NUMBER TF I1rD

PROJECT PROPOSAL PAPER FOR GPSA GRANT US$ 500,000 PUBLISH WHAT YOU PAY INDONESIA - (PWYP) INDONESIA FOR A

PROJECT INFORMATION DOCUMENT (PID) CONCEPT STAGE Report No.: AB7052

Fiduciary Arrangements for Grant Recipients

WikiLeaks Document Release

Public Policy making, risk analysis, and disaster prevention for sustainable development

Mississippi Development Authority. Katrina Supplemental CDBG Funds. For. Hancock County Long Term Recovery CDBG Disaster Recovery Program

War-to-Peace Transition in Mozambique: The Provincial Reintegration Support Program

North Carolina Department of Public Safety Division of Emergency Management

Response to recommendations made in the Independent review into Liverpool Community Health NHS Trust

INTEGRATED SAFEGUARDS DATA SHEET APPRAISAL STAGE

INTEGRATED SAFEGUARDS DATA SHEET CONCEPT STAGE

Transcription:

Public Disclosure Authorized IEG ICR Review Independent Evaluation Group 1. Project Data: Date Posted : 04/18/2012 Report Number : ICRR13623 Public Disclosure Authorized Public Disclosure Authorized PROJ ID : P096647 Appraisal Actual Project Name : Community Recovery Project Costs (US$M US$M): 17.96 17.45 In Earthquake Affected Areas Through Urban Poverty Project Country: Indonesia Loan/Credit (US$M US$M): 17.96 17.45 Sector Board : UD Cofinancing (US$M US$M): Sector(s): Sub-national government administration (50%) General water sanitation and flood protection sector (50%) Theme(s): Access to urban services and housing (67% - P) Natural disaster management (33% - S) L/C Number: Partners involved : Board Approval Date : 08/24/2005 Closing Date : 12/31/2009 12/31/2009 Evaluator : Panel Reviewer : Group Manager : Group: Silke Heuser George T. K. Pitman IEG ICR Review 1 IEGPS1 2. Project Objectives and Components: Public Disclosure Authorized a. Objectives: According to the Project Appraisal Document (PAD, page 1), the project development objective (PDO) was: to provide support for reconstruction and rehabilitation to urban communities impacted by earthquakes and tsunami. According to the Community Recovery Project through the Urban Poverty Program Multi -Donor Trust Fund for Aceh and North Sumatra Grant Agreement, Trust Fund No. TF055626, the PDO was: to assist in the reconstruction and rehabilitation of urban communities devastated as a result of earthquakes and tsunamis in the Affected Areas." This ICR Review assesses the project against the PAD s objectives which are more monitorable. b.were the project objectives/key associated outcome targets revised during implementation? No

c. Components (or Key Conditions in the case of DPLs, as appropriate): A: Community Development. (Appraisal: US$4.11 million; Actual: US$4.17 million). This component consisted of the provision of technical advisory services to carry out community development activities. B: Urban Community Grants. (Appraisal: US$11.73 million; Actual: US$11.13 million). This component would provide block grants (of IDR 300 million) to urban communities to finance activities, such as (a) specific high-priority infrastructure investments, (b) competitive proposals from community groups, and (c) social safety net programs for the benefit of the poorest and most vulnerable groups or individuals. C: Strengthening the Role and Capacity of Local Government. (Appraisal: US$1.00 million; Actual: US$1.02 million). This component would provide technical assistance to strengthen the role and capacity of local governments to work together with community organizations to address disaster relief, recovery, community infrastructure rehabilitation and reconstruction, based on community values. D: Implementation Management Support. (Appraisal: US$1.12 million; Actual: US$1.13 million). The project would be managed by a Project Management Unit (PMU) assisted by an administrative unit (PIMPRO), with a designated representative located in Aceh, who reports regularly to Badan Rekonstruksi dan Rehabilitasi (BRR), a temporary government unit tasked with the coordination of the reconstruction and rehabilitation of Aceh and Nias ) on Project progress for coordination purposes. d. Comments on Project Cost, Financing, Borrower Contribution, and Dates: Project costs : There were changes in the share of urban communities /beneficiaries under component B. The project distributed urban community grants to 273 instead of 402 urban communities. The grant amount per community was increased from Indonesian Rupiah, IDR 300 million, to between IDR 300 and 500 million (not exceeding US$2,000 equivalent). This change was undertaken because shortly after appraisal, a rapid survey of the project area revealed that approximately 465,700 people were in need of improved infrastructure instead of 697,600 people. Financing : This project was financed by the Multi-Donor Trust Fund for Aceh and North Sumatra. A large number of multilateral and bilateral donors had made significant financial commitments in support of the planned reconstruction and rehabilitation efforts, including contributions of over US$ 700 million. The Multi-Donor Fund for Aceh and Nias provided a US$17.96 million grant to Government of Indonesia (GoI) to finance the full cost of the project. 78% of funds were disbursed before half of the project implementation period had elapsed. A total of $0.51 million was cancelled in August 2010. Borrower Contribution : No contribution was either planned or made. Dates: This project was approved in FY 2005, nine months after the tsunami hit on December 26, 2004. It was closed on schedule after an implementation period of four years. 3. Relevance of Objectives & Design: (i) Relevance of project objectives : High. PDOs were critical and highly relevant, and corresponded to the government s own plans and priorities. The project benefited from being part of an overall Multi-Donor Fund for Aceh and Nias-financed program for reconstruction in Aceh, and particularly from being an extension of existing urban poverty projects that were either already in implementation or soon to begin implementation. Project objectives were also relevant to the FY 2009-12 country partnership strategy report that lists environmental sustainability and disaster mitigation as one of five core engagement areas for Indonesia and the Bank. Objectives were also fully consistent with the Bank s 2003-06 Country Assistance Strategy (CAS) for Indonesia, which the Bank updated in 2005 by introducing a new CAS pillar, called Disaster Risk Management. As part of the updated strategy, the Bank committed itself, inter alia, to sustained heavy engagement in Aceh and Nias throughout 2005-06 and beyond. (ii ii) Relevance of project design : Substantial. The background analysis was strong in large part because the government of Indonesia had already prepared a Master Plan for the Rehabilitation and Reconstruction of Aceh and Nias that was intended to guide and coordinate all recovery programs. As a result, project design was relevant to stated objectives in that the components and implementation arrangements were well designed, realistic, and not overly complex. Components were adapted from proven approaches from other projects already under implementation, with specific modifications for the post-disaster environment in Aceh. The Multi-Donor Fund for Aceh and Nias, which provided the project financing, was an effective way of marshalling and coordinating the funds flowing in from many sources to help ensure that they were used in an effective and coherent manner. The results framework in the ICR data sheet included indicators for intermediate and final outcomes necessary for the reconstruction and rehabilitation of urban communities impacted by earthquake and tsunami. The PAD (page 23) included only output indicators. Assessments and mitigation measures were generally on target, and while some were more successfully mitigated than others, there were no unanticipated risks or missed opportunities for mitigation that seriously limited achievement of project outcomes. Annex 3, page 26 of the PAD lists a number of exogenous factors that

could influence project outcome as well as appropriate mitigating measures. 4. Achievement of Objectives (Efficacy): The project was successful in achieving its overall objective, to provide support for reconstruction and rehabilitation to urban communities impacted by the earthquake and tsunami. Substantial. The Project allocated grants for the reconstruction and rehabilitation of community infrastructure to the 273 urban communities determined to be most in need of such support. At the same time, it made sure that all 402 urban communities received facilitator support to help them access other sources of finance for activities identified in their Community Rehabilitation and Reconstruction Plans. As a result, virtually all residents of the 273 urban communities, who were severely impoverished by the impact of the tsunami, received benefits and improved services from the Project. As of December 31, 2009, the largest share of Project-financed block grants for community infrastructure was allocated to roads and bridges, drainage, and water. Over 38,843 households (about 48% of the population in the 273 urban communities selected to receive block grants ) received social assistance grants. This was 64% of the target ( that at least 75% of disaster victim households in the targeted urban communities receive benefits and improved services from the Project ) if only block grants are considered. Improved services to the 402 communities may have increased the number of beneficiaries but these numbers are not known. About IDR 74.5 billion ( just over US$10 million equivalent), or 91% of the total amount available for block grants, was used for community infrastructure. As shown in the following table, over 70% of these infrastructure grants were used to finance investments in roads and drainage. Clean water, public toilets and village halls accounted for most of the remainder. The other 9% of the block grant funds (IDR 7.8 billion) were disbursed as direct social service assistance to specific individuals or households. This largely consisted of small cash grants, averaging about US$22, to the poorest kelurahan residents to pay for training (such as sewing or typing courses), minor home improvement or repair, health care and medical expenses, or other urgent needs. Community Infrastructure Sub -projects and Grant Financing Type of infrastructure Total output Grant financing (IDR % of grant financing billions) Access roads 231.4 km 29.2 39.2 Drainage 176.3 km 23.6 31.7 Clean water 4,915 units 5.7 7.7 Public toilets 405 units 5.2 6.9 Village halls 120 units 4.5 6.1 Bridges 1,382 meters 3.1 4.1 Sluices 92 units 0.8 1.1 Health posts 29 units 0.8 1.1 Electricity generators 877 units 0.6 0.8 School buildings 159 units 0.6 0.8 rehabilitated Waste disposal units 806 units 0.3 0.4 TOTAL 74.5 100.0 Source: ICR, Annex 8 The Project supported the establishment of a model which was successfully implemented elsewhere in Indonesia for participatory planning and financing in 273 urban communities across the province where communities participated in a democratic, participatory process of planning and decision -making regarding the allocation of public development funds. The vast majority of the Community Trustee Committees established by the Project were deemed representative, effective and participatory, based on their composition, voting rates, women s participation, complaint handling, and their success in identifying infrastructure priorities, creating community reconstruction plans, and carrying out the needed investments. This was 90% of the target ( that at least 70% of Community Trustee Committees that have been formed are representative, effective, and operate in a participatory manner.) The Project was highly successful in assisting communities in all 402 participating urban communities to prepare the Community Rehabilitation and Reconstruction Plans required to mobilize additional funding from other community-driven development or CDD-type programs, such as the Urban Poverty Project 3, and the National Community Empowerment Program), as well as from the Community-Based Settlement Rehabilitation and Reconstruction Project and a UN-Habitat housing project. This was 100% of the target ( that at least 50% of Community Trustee Committees are able to channel other donor reconstruction funds to their communities.)

5. Efficiency (not applicable to DPLs): Efficiency is rated as substantial. Given the low cost of the subprojects financed by the Project and the substantial economic benefits of infrastructure investments in a location where infrastructure was largely absent in the aftermath of the tsunami, it was not deemed useful in the PAD to estimate indicators such as NPVs or EIRRs or FIRRs. Efficiency was therefore gauged by unit rate norms, which are highly favorable for community -executed infrastructure projects. For example, a 2005 study by the National Planning Board(A Post Construction Economic Impact Analysis Study for CDD Programs) found that the average construction cost of CDD projects was 40 percent lower than those done by contractors of local governments. The cost savings were mainly attributed to the high level of voluntary labor contributed by residents in community -driven development projects. A more recent study, which was undertaken in 2009 at the request of the Ministry of Public Works, arrived at similar conclusions. The study, which covered six cities throughout Indonesia, found that community groups are normally able to construct small-scale infrastructure at a far lower cost than government contractors, the main reasons being: (i) lower labor costs, (ii) substantially lower prices of construction materials, and (iii) an exemption from VAT. Based on an analysis of 4,270 infrastructure activities, the study found that the cost of community-driven infrastructure development was, on average, about 47 percent lower than similar government-financed infrastructure. There was substantial variation in cost savings across sub -sectors, however. For example, the cost of community paving -block roads and drainage was over 40 percent lower than government contractors, whereas community -constructed concrete pathways were about 20 percent less expensive. a. If available, enter the Economic Rate of Return (ERR ERR)/Financial Rate of Return (FRR FRR) at appraisal and the re-estimated estimated value at evaluation : Rate Available? Point Value Coverage/Scope* Appraisal % % ICR estimate % % * Refers to percent of total project cost for which ERR/FRR was calculated. 6. Outcome: Outcome is rated satisfactory based on high relevance of objectives and substantial design, the substantial efficacy, and substantial efficiency. The PDOs and design remained relevant throughout the implementation period. The Project was not only central in efforts to support reconstruction and rehabilitation for disaster -affected communities, but was also designed to enable a smooth transition from special post -disaster assistance to the government s ongoing nationwide CDD program, using the same community planning approach and mechanisms. a. Outcome Rating : Satisfactory 7. Rationale for Risk to Development Outcome Rating: The central reconstruction objective of the project remained highly relevant, and despite some shortcomings in operations and maintenance arrangements, the project outcomes contributed to the higher level impact of restoring community well-being, security, and economic activity in the wake of the disaster, even if better long -term infrastructure maintenance is still needed. Furthermore, though emergency post-tsunami reconstruction needs have eased, in the process of achieving these shorter term objectives the Project also helped establish effective, participatory and representative community committees that can mobilize funds through the preparation of Community Rehabilitation and Reconstruction Plans, and linked these mechanisms to more permanent programs and to ongoing, non-emergency community development plans and goals. Both central and local governments have indicated a strong and long-term commitment to the financing of such plans thus utilizing capacity built by the project A notable cross-cutting risk discussed in the PAD was that operating in the province of Aceh generally was seen as involving some inherent risks because it was a post -disaster environment in a province that had been plagued by civil unrest for decades. However, since the Project was designed to work closely and directly with communities and was located in urban areas where the incidence of civil conflict was lower, these risks were not considered substantial. With the signing of the peace agreement in mid -2005, these risks are negligible today. a. Risk to Development Outcome Rating : Moderate 8. Assessment of Bank Performance:

Quality-at at-entry Entry: The quality of the project at entry was high and contributed to its successful outcomes. The Bank's performance in the identification, preparation, and appraisal of the Project was satisfactory. A mid-term review of the entire Multi-Donor Fund for Aceh and Nias portfolio, which was conducted by an independent consultant in 2008 at the request of the donors to the Fund also had given a satisfactory rating. The main reasons for this rating were the Project s robust M&E system, not-excessive number of outcome indicators, a very good complaints handling system, and the fact that it was based on the design of Urban Poverty Project 2. Quality of Supervision : The Bank mobilized a multi-disciplinary supervision team with expertise in project management, financial management, procurement, monitoring, and safeguards. The Jakarta-based Urban Poverty Project task team was moved to Aceh at short notice, and assisted the Government during the initial stage of Project implementation. Several team members were based in Aceh for two years to assist with resolving various coordination issues. This arrangement allowed for more frequent site visits and more sustained follow -up than for other Urban Poverty Projects, and was undertaken at a relatively low cost, which was shared with other reconstruction projects. According to the ICR (page 13), in spite of intensive supervision, the Project continued to be plagued by less than satisfactory financial management issues, especially in the early part of the implementation period. Pages 13-14 of the ICR also note "Supervision was intensive, especially because of very limited capabilities of communities and local government institutions in the first two years following the tsunami and earthquake. This enabled the Bank to identify and proactively address key issues adversely affecting achievement of the PDOs at an early stage, notably problems with delays in budget approval, facilitator recruitment, ineffective socialization campaigns, and limited compliance with financial management procedures. Because of these supervision efforts, performance in these areas improved over time... a. Ensuring Quality -at at-entry Entry:Satisfactory b. Quality of Supervision :Satisfactory c. Overall Bank Performance :Satisfactory 9. Assessment of Borrower Performance: Government Performance : GoI strongly supported the Project from the start, and the Ministry of Finance cooperated swiftly to reallocate $2.5 million from other Bank-financed projects to jump-start implementation (these funds were later reimbursed from the first disbursements to the Project ). Supported by the implementing agency, the Project was prepared within 3.5 months (the concept was developed in May 2005, and the grant was approved in August 2005), one of the shortest preparation times for any GoI project of this type. The Government also took steps that helped to end decades of civil unrest in the Province, which greatly facilitated the implementation of the Project. Implementing Agency Performance : From the outset, the implementing agency supported a bottom -up, community-driven approach to disaster management. It strongly supported the establishment of a comprehensive M&E system to maintain a high level of transparency of the outcomes of the Project. It also took steps to modify implementation arrangements where needed, and responded to complaints or suspicions about the misuse of funds with great vigor. There were, however, several avoidable problems that stronger management might have been able to correct, such as poor compliance with financial management procedures, and limited sustainability of part of the capacity building investments financed by the Project. According to the ICR, pages 6-7, "Improper financial management. Financial management (FM) of block grants was less than satisfactory throughout the Project implementation period, as communities were often unable to comply with FM guidelines, especially those related to the safekeeping of cash and the dissemination of financial reports. These problems were most pressing in the early part of Project implementation, when it was difficult to find qualified facilitators willing to work in a conflict area. During the second half of the Project implementation period, the FM rating improved from moderately unsatisfactory to moderately satisfactory, but shortcomings in a broad range of accountability and transparency issues continued to exist. However, these FM shortcomings did not lead to any known misuse of funds or unresolved complaints about use of funds." In addition, as the Project progressed, the implementing agency gradually shifted its attention to the development of other projects. a. Government Performance :Satisfactory b. Implementing Agency Performance :Moderately Satisfactory c. Overall Borrower Performance :Moderately Satisfactory

10. M&E Design, Implementation, & Utilization: a) M&E design. At the beginning of implementation, the Bank established a comprehensive management information system, to help monitor and evaluate the Project. It is extremely comprehensive (providing, for example, the number of beneficiaries for each activity financed by the Project, with timely information provided on a monthly basis) and readily accessible by the public. In spite of these obvious advantages, the system could have been further improved by explicitly linking it to monitoring and evaluation of the Project s performance indicators, some of which were either recorded by other systems (e.g. % Project urban community implement sub-projects in line with Community Rehabilitation and Reconstruction Plans and % Project urban community households utilize reconstructed/rehabilitated community infrastructure ) or had to be inferred from intermediate indicators (e.g. % Disaster victim households in the targeted urban community received benefits and improved services of the project and Poorest household disaster victims receive social service assistance grants ). b) M&E implementation. The M&E system was set up early in the Project, except for the system for the women s empowerment program that was developed during implementation to more narrowly target part of the grant component and thereby enhance women s participation in community development activities. Data generated by the system are publicly available on the National Community Empowerment Program website (http://www.p2kp.org) in the form of downloadable MS-Excel files, which are updated on a monthly basis. However, it is not easy to understand the contents of the downloadable files (partly because the definitions of some data labels are missing ). c) M&E utilization. The data collected was useful in ensuring that the Community Trustee Committee for Reconstruction and Rehabilitation were representative and that the Community Rehabilitation and Reconstruction Plans were of good quality and realistic. Since the data confirmed that women s participation targets were being met in percentage terms, it influenced the Bank and the Ministry of Public Works' efforts to improve the voice of women through qualitative approaches and by introducing new subproject selection strategies rather than merely increasing participation rates. The data also showed that although about 48 percent of households in the eligible urban communities received social service assistance grants, it was not realistic or relevant to identify, much less target, the poorest 10 percent of the population for this household grant assistance, and ultimately it was not as high a priority for the communities as anticipated. It also provided data with which to adjust the block grant amounts for some villages based on both need and effectiveness of utilization. a. M&E Quality Rating : Substantial 11. Other Issues (Safeguards, Fiduciary, Unintended Positive and Negative Impacts): Safeguards : This was a category B project. According to the ICR, safeguard assessments and arrangements were robust. Appropriate oversight arrangements were put in place, most investments were expected to be small in scale and limited to reconstruction of existing infrastructure, and a negative list of subprojects not eligible for financing was created, along with standard operating procedures and guidelines to help minimize or address any localized impacts. The block grants were implemented by community groups in self -help community group, and each of them managed a subproject which typically did not exceed US$ 2,000 equivalent. Given the small size the subprojects financed by the Project, it was a priori expected that any adverse social and environmental impacts of such subprojects would be small or negligible. This expectation was confirmed by the Project s many supervision missions. Indeed, the Project generated substantial social and environmental benefits by providing key infrastructure in locations where most basic infrastructure was devastated by the natural disasters. Investments in drainage, water supply and sanit ation generated direct environmental benefits. The project did not encounter any cultural property or indigenous people related issues during project implementation. According to the PAD (page 19) "Subprojects are not expected to require involuntary resettlement or acquisition of significant amounts of land. In the event they do, however, a Land Acquisition and Resettlement Policy Framework has been developed in accordance with OP 4.12 to ensure application of the appropriate safeguard policies." The ICR does not mention land acquisition (see section 15). Fiduciary Compliance : The Project encountered problems with financial management throughout implementation, primarily because communities were often unable to comply with financial management guidelines, especially those related to safekeeping (community treasurers were not supposed to keep cash balances of more than IDR 1 million for more than 48 hours from receipt) and the dissemination of financial reports (which should be displayed in at least five strategic locations within an urban community ). These problems were exacerbated by difficulties in finding qualified facilitators willing to work in a conflict area. The complexity of the arrangements was not considered inappropriate nor a primary factor in the financial management shortcomings. It also should be emphasized that the fiduciary problems were related to difficulties in making communities comply with proper financial management procedures. In case of poor financial management performance by a certain urban community, block grants to that community were suspended until acceptable performance was reached. "In 2006, 2007, 2008, and 2009, the Project received an unqualified opinion from BPKP, the state auditor " (ICR page 9). Furthermore, the "FM shortcomings did not lead to any known misuse of funds or unresolved complaints about use of funds" (ICR page 6-7).

According to the ICR, page 18 "The Project established an elaborate complaints handling system. As of January, 31 2009, 285 complaints were registered, of which only 17 (6 percent) were related to the alleged misuse of funds. The funds involved totaled only IDR 263.4 million, or 0.31 percent of total kelurahan grants financed by the Project. Thirteen of the 17 cases, involving 97 percent of these funds, were resolved, leaving less than 0.01 percent of the grants under allegations of misuse." The project team subsequently clarified that 0.01 percent of the grants under allegations of misuse amounted to about $8,000 and that Some of the cases where the community unable to resolve were referred to the police, including the 0.01 %. Unintended Positive and Negative Impacts : The Project had three unintended outcomes that benefited other programs: The Project s design was used to prepare two projects that provided emergency reconstruction assistance in rebuilding community infrastructure destroyed by earthquakes in and around Yogyakarta and Padang. The women s empowerment program, which was developed by the Project in 2007 and successfully implemented in 2008, will become an integral part of the National Community Empowerment Program. The provincial government of Aceh is now financing implementation of the village Community Rehabilitation and Reconstruction Plans from its own financial resources after the Project s urban community grants were disbursed in full instead of relying on central government or donor support. 12. Ratings: ICR IEG Review Outcome: Satisfactory Satisfactory Risk to Development Moderate Moderate Outcome: Reason for Disagreement /Comments Bank Performance : Satisfactory Borrower Performance : Satisfactory Quality of ICR : Satisfactory Moderately Satisfactory Satisfactory There were several avoidable problems that stronger management in the Implementing Agency might have been able to correct, such as poor compliance with financial management procedures, and limited sustainability of part of the capacity building investments financed by the Project. See Sections 9b and 11. NOTES: - When insufficient information is provided by the Bank for IEG to arrive at a clear rating, IEG will downgrade the relevant ratings as warranted beginning July 1, 2006. - The "Reason for Disagreement/Comments" column could cross-reference other sections of the ICR Review, as appropriate. 13. Lessons: Lessons from the ICR that reflect IEG's experience with natural disasters reconstruction were the following : CDD-type projects can be effective and can be set up at short notice to mitigate the impacts of natural disasters. This was demonstrated by using the design of the Project to prepare two other disaster relief projects on short notice (to rebuild community infrastructure destroyed by earthquakes that hit Yogyakarta in 2006 and Padang in 2009, respectively). Moreover, the Project did not only support much -needed investments, but also contributed to the psychological recovery of the victims by involving them in the decision-making processes. Flexibility in design and implementation arrangements are essential for disaster recovery projects. Because of a high level of uncertainty during preparation, the Project design should allow the Bank and the Grantee to adapt to changing circumstances during implementation when more information becomes available. Efficient use of funds for disaster relief programs requires coordination with long -term development plans. Such coordination is needed to ensure appropriate levels of rehabilitation for infrastructure that will be reconstructed on a large scale at later stage, whilst at the same time considering the benefits of short -term

rehabilitation to get communities back on their feet and develop productive activities. 14. Assessment Recommended? Yes No Why? To verify the ratings and document lessons learned. An assessment could inform the upcoming disaster evaluation scheduled for FY 2013. It could also draw out lessons on how to tailor CDD -type projects to natural disaster emergencies. An assessment would examine what worked well and aspects that were challenging, so that future project design could be shaped drawing from this experience to benefit future post disaster reconstruction. At present, there is little documentation of what specific aspects of CDD projects work or do not work well in a post-disaster context and why. Since this project was fundamental to the success of the Indonesia - Community-based Settlement Reconstruction and Rehabilitation Project for Nad and Nias (P096248), it would be an even richer learning experience to conduct an assessment of both projects together. The Bank's role in ensuring fiduciary probity and sound financial management should also be examined. 15. Comments on Quality of ICR: The ICR was succinct and of good quality. The discussion of the project experience was thorough and a good effort has been made to draw out important lessons from the various problems encountered. The discussion of the challenges encountered putting together the CDD -type post-disaster interventions will be useful to those planning subsequent post-disaster efforts. The project team was interviewed and clarifications are incorporated in this review. A shortcoming in the ICR was that it did not report on the land acquisition issue mentioned in the PAD. a.quality of ICR Rating : Satisfactory