STRATFORD MIDDLE SCHOOL RENOVATION AND ADDITION ARLINGTON PUBLIC SCHOOLS PFRC JANUARY 24, 2017
PROJECT UPDATE AND SCHEDULE 1
PROJECT SCHEDULE USE PERMIT 2016 2017 2018 2019 2/2017 CERT. OF APPROP. 2/2017 DESIGN DEV. CONST. DOCS. BUILDING PERMIT CONSTRUCTION SCHOOL OPEN Fall 2017 Stratford Middle School - 3
PROJECT MILESTONES Concept Design approved November 2015 Schematic Design approved June 2016 Use Permit submitted: September 8, 2016 EA submitted: September 8, 2016 Water Quality Impact Assessment submitted: September 15, 2016 Certificate of Appropriateness submitted: September 22, 2016 Presenting to Commissions: (Fall/Winter 2016/2017) Resubmission of Use Permit / COA: December 21, 2016 County Board (projected): March 2017 Building Permit (projected): Fall 2017 Stratford Middle School - 4
STAKEHOLDER INVOLVEMENT 23 BLPC meetings 13 PFRC meetings 7 HALRB/DRC meetings/work sessions 2 Gallery Walks / Open Houses Additional meetings with: Community leaders Department of Parks and Recreation VDOT Arlington County School Board Members Stratford Middle School - 5
USE PERMIT UPDATE 2
USE PERMIT MILESTONES Use Permit: September 8, 2016 / December 21, 2016 Environmental Assessment: September 8, 2016 Water Quality Impact Assessment: September 15, 2016 Certificate of Appropriateness: September 22, 2016 / December 21, 2016 Commission Presentations: E2C2 - September 26, 2016 Urban Forestry - October 27, 2016 HALRB - December 21, 2016 Parks and Recreation - TBD Transportation - TBD Planning - TBD County Board - March 18, 2017 Stratford Middle School - 7
USE PERMIT COMMENT AND RESPONSE Stormwater approach Vacation Lane sidewalks Coordination with DPR Historic/COA Real Estate Stratford Middle School - 8
STORMWATER MANAGEMENT PLAN WWW.QUINNEVANS.COM STRATFORD MIDDLE SCHOOL RENOVATION & ADDITION 4100 Vacation Ln, Arlington, VA 22207 QEA # 31406600 WATER QUALITY DRAINAGE AREA MAP USE PERMIT 09/08/2016 REVISIONS NO. DESCRIPTION A REVISION DATE 12/21/2016 C-610 ARLINGTON, VIRGINIA DEPARTMENT OF ENVIRONMENTAL SERVICES STRATFORD MIDDLE SCHOOL 4100 VACATION LANE, ARLINGTON, VA 22007 SCALE: AS NOTED 1 4 7 8 9 10 DESIGNED: K.RYAN CHECKED: S.PANDISH 11 Stratford Middle School - 9
VACATION LANE SIDEWALK EXISTING SIDEWALK PROPOSED SIDEWALK EXISTING PROPOSED Stratford Middle School - 10
NEW ADDITION Stratford Middle School - 11
HISTORIC COMMITTEE UPDATE 3
HISTORIC COMMITTEE Committee kickoff was on January 11, 2017 Determine how to best recognize history of site while respecting the building/site design process and timeline Three stages: Exploration and Discovery Analysis and Evaluation Expression and Design Interpretive Planner to be chosen shortly Present concept to School Board in late spring/early summer 2017 Stratford Middle School - 13
SITE PLAN Stratford Middle School - 14
HISTORIC PATH 302 STONE BOULDER WITH MARKER FOR INTERPRETATION OF HISTORIC PATHWAY. SEE CHARACTER IMAGE 1/SHEET L2-0H. TW 303.50 TW 306.50 300 SEAT WALL WITH INTERPRETIVE SIGN INTEGRATED. SEE CHARACTER IMAGE 3/SHEET L2.0H. TW 302.50 291.60 TW 306.50 298 (26) PROPOSED BIKE RACKS 97.70 TW 300.50 292 296 292 294.00 TW 304.50 95.20 95.10 TW 294.25 TW 294.25 294 TW 303.50 95.20 TW 299.50 294 296 TW 296.00 296 TW 291.17 OLD DOMINION ROAD CONCRETE RETAINING WALLS. SEE DETAIL 1/L4-1H. TW 300.50 306 304 97.70 298 300 TS 291.75 290 288 286 284 282 BS 280.75 BIOFILTER TW 289.85 T TS 285 280 ADA PATH CHANGED TO FLAGSTONE AT POINTS WHERE IT CROSSES THE HISTORIC PATH. SEE CHARACTER IMAGE 2/SHEET L2.0H. TW 306.50 TW 302.50 TW 302.50 302 SEE DETAIL 2/L4-1H. LOW WALL WITH INTEGRATED SEATING, TYP. SEE CHARACTER IMAGE 2/SHEET L2.0H. 304 TW 306.50 302 300 298 296 294 292 290 288 286 284 282 306 FIELD STONE MARKERS RECALL ORIGINAL PATH STUDENTS TOOK ON INTEGRATION DAY TO ENTER THE SCHOOL. SEE CHARACTER IMAGE 2/SHEET L2-0H. 310 308 STONE BOULDER WITH MARKER FOR INTERPRETATION OF HISTORIC PATHWAY. SEE CHARACTER IMAGE 1/SHEET L2-0H. 312 312 310 Peirce Mill, QEA Stratford Middle School - 15
HISTORIC PATH A 302 STONE BOULDER WITH MARKER FOR INTERPRETATION OF HISTORIC PATHWAY. SEE CHARACTER IMAGE 1/SHEET L2-0H. TW 303.50 TW 306.50 300 SEAT WALL WITH INTERPRETIVE SIGN INTEGRATED. SEE CHARACTER IMAGE 3/SHEET L2.0H. TW 302.50 291.60 A TW 306.50 298 (26) PROPOSED BIKE RACKS 97.70 TW 300.50 292 296 292 294.00 TW 304.50 95.20 95.10 TW 294.25 TW 294.25 294 OLD DOMINION ROAD CONCRETE RETAINING WALLS. SEE DETAIL 1/L4-1H. TW 303.50 TW 300.50 306 95.20 304 TW 299.50 97.70 294 296 298 C 300 TW 296.00 296 TS 291.75 BS 280.75 TW 291.17 290 288 286 284 282 BIOFILTER TW 289.85 T TS 285 B ADA PATH CHANGED TO FLAGSTONE AT POINTS WHERE IT CROSSES THE HISTORIC PATH. SEE CHARACTER IMAGE 2/SHEET L2.0H. B TW 306.50 TW 302.50 C TW 302.50 302 SEE DETAIL 2/L4-1H. 280 LOW WALL WITH INTEGRATED SEATING, TYP. SEE CHARACTER IMAGE 2/SHEET L2.0H. B 306 304 TW 306.50 302 300 298 296 294 292 290 288 286 284 282 FIELD STONE MARKERS RECALL ORIGINAL PATH STUDENTS TOOK ON INTEGRATION DAY TO ENTER THE SCHOOL. SEE CHARACTER IMAGE 2/SHEET L2-0H. STONE BOULDER WITH MARKER FOR INTERPRETATION OF HISTORIC PATHWAY. SEE CHARACTER IMAGE 1/SHEET L2-0H. A 310 312 308 C 312 310 Stratford Middle School - 16
BUILDING SECTION OPPORTUNITY FOR COMMEMORATION AT HEART OF SCHOOL FEATURE WALL Stratford Middle School - 17
CONSTRUCTION PHASING 4
CONSTRUCTION PHASING Possible Scope for Early Construction Work: Expanded Vacation Lane parking lot Construction entrance at Old Dominion Drive Considerations Minimize impact to Stratford Program Field access during 2018 spring season Construction access and routes Separating school and construction zones Stratford Middle School - 19
CONSTRUCTION SCHEDULE Construction Schedule Milestones GMP Fall 2017 Early Work Phase - January 2018 Construction Start - June 2018 Completion - August 2019 Stratford Middle School - 20