Presentation Outline Introductions District Description IPR Program Demonstration Project Minimum Project Tasks Key Proposal Requirements Evaluation Criteria Schedule Questions
Potable Water Wastewater Recycled Water Santee Lakes 100% imported ~12,000 ac-ft/year 34% reduction due to conservation 5 MGD generated 2 MGD Ray Stoyer WRF Remaining to PLWWTP Owns ~ 3% Metro treatment capacity ~ 900 ac-ft/yr irrigation ~ 1,120 ac-ft/yr to Santee Lakes Only permitted inland live stream discharger 2 nd largest RV camp ground in SD County (including 10 cabins) ~750,000 visitors/year Year round special events
Padre Dam & IPR Adopted Strategic Goal to increase water, wastewater and energy independence Add drought resistant local water supply Continue to meet Title 22 obligations Minimize future financial obligations associated with Pt. Loma waiver Add capacity for IPR and GRRP
Santee GRRP Concept Minimum Retention Time or Response Time
IPR Program Timeline
PDMWD s IPR Program Goals 1. Produce minimum of 15% of Districts Potable Supply (2,000 to 3,000 AF/Y of local supply) 2. Price of water < $2,000 /AF 3. Full Scale GRRP operation ASAP while gaining regulatory acceptance & meeting regulatory requirements 4. Support District Strategic Goal 4 (Increase Water, Wastewater and Energy Independence 5. Limit Financial Obligations to District Ratepayers assuming District were to continue to connect to the METRO system
Padre Dam s IPR Demonstration Project
Demonstration Project Objectives Utilize FAT Technology 100,000 gpd MF/RO or UF/RO 10 gpm Advanced Oxidation Establish requirements for a fullscale IPR project Seek to eliminate blending requirements Minimize retention time in aquifer Establish parameters for full-scale implementation ASAP Support District s IPR Program & Strategic Goals Meet Prop 50 Grant requirements
Demonstration Project Contracts Envisioned to be accomplished under 2 separate contracts 1. Contract 1 Program Management (this RFP) 2. Contract 2 Design and Installation of the Demonstration Facility Consultant Selected for Contract 1 responsible to manage combined total of Contracts 1 and 2 to not exceed $2.5M
Minimum Project Tasks Coordinate project Review existing regulatory documents and develop a regulatory strategy Provide and Convene and Independent Advisory Panel Cost Estimating (Capital and O&M)
Minimum Project Tasks Develop a Testing and Monitoring Plan Include laboratory testing Verify Removal of Pathogens and COC s Provide recommendations for a Source Control Plan Assess Impact of WateReuse Study on Nitrification
Minimum Project Tasks Quality Assurance Project Plan (QAPP) Project Assurance Effectiveness Plan (PAEP) Engineering Report for Brine Management Final Project Report Public Outreach QA/QC
Key Proposal Requirements Conceptual Program Plan Meet Demonstration Project Objectives Satisfy minimum requirements Provide remaining concepts and ideas to develop and implement a highly successfully project Project Organization & Key Project Personnel Experience, Resumes, References Replacement of key team members will not be permitted w/o District approval QA/QC program Rate Schedule & fee proposal
Evaluation Criteria Scored on 100 point basis by committee Conceptual Program Plan (60 points) Project Manager Experience & Availability (10 points) Qualifications and specific experience of Key Team Members (10 points) Firm experience (10 points) Demonstrate best value to District (10 points) Interview Minimum 3 highest scoring firms
Selection Process District Board Not involved in RFP preparation Not included on scoring committee Updated on progress, as necessary Staff directed to direct any Board inquiries to Director of Engineering or GM Engineering Staff (During proposal period) Minimize interaction with consultants (perception issues) Obtain questions regarding RFP in writing: Level playing field Scoring committee typically made up of staff from varying District departments No Firm has this project in the bag
Upcoming Schedule Pre-proposal Meeting (Today) Selection/ Negotiation Interviews. (June 2013) (May 2013) Proposal Due (April 30, 2013) June 2016 Contract Award (July 2013)
RFP Inquiries Must be in writing (email is acceptable) Send to: asandvik@padre.org All inquiries to be received by April 8, 2013. Check website frequently for District responses.
Questions and Discussion