Generator Interconnection Impact Study Report Wayne County, NC 20.0 MW Solar Farm Queue #364

Similar documents
Generator Interconnection Facilities Study Report Franklin County, NC 50.0 MW Solar Farm Queue #384

Generator Interconnection Impact Study Report Bladen County, NC 75.0 MW Solar Farm Queue #377

Generator Interconnection System Impact Study Report Carteret County, NC MW Queue #297 Original Submittal Revision 1

ATTACHMENT B. 1. Intent to Bid/Bidder Contact Information Form. 2. Executive Summary. 3. Proposal Characteristics and Term Sheet

Standard Development Timeline

Bio Energy #1 Distribution Generator Interconnections Less than 35 kv

Small and Large Generator Interconnection Procedures

OC Approved 2/17/05 SB/DS Stability Limits for the addition of 3.26% Series Reactor

A. General provisions and other electrical systems are specified in other Sections of Division 26.

XXXXX Kwalsa Phase II Project. Interconnection Facilities Study and Project Plan

Addendum to ESAH Version 3 Supply Application

Future Development Plan:

j. Billing procedure k. Periodical Inspections Page 1

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION ) ) )

107 FERC 61,053 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION

The State of Interconnection in NYS:

NPCC Tasks Related to NERC Blackout Recommendations Timeline

Transmission Planning Attachment K Public Input Meeting

PART 1 - Rules and Regulations for the Renewable Energy Development Fund Programs

Standard NUC Nuclear Plant Interface Coordination

RG 102 Accreditation for the Inspection of Non-public High Voltage Electrical Systems

Comprehensive Interconnection Process Improvements

Washington Headquarters Services Military Construction, Defense-Wide FY 2010 Budget Estimates ($ in thousands)

Implementation Plan Set Two of Phase III & IV Reliability Standards

STATE OF NORTH CAROLINA UTILITIES COMMISSION RALEIGH DOCKET NO. E-2, SUB 1089 BEFORE THE NORTH CAROLINA UTILITIES COMMISSION

Southern California Edison Original Cal. PUC Sheet No E Rosemead, California (U 338-E) Cancelling Cal. PUC Sheet No.

TRANSMISSION TRANSMISSION SYSTEM OPERATIONS DIVISION

Standard FAC Facility Ratings. A. Introduction

Luis Fondacci. James Manning. Administrative. The November 14, 2016 OSC Meeting Minutes and Highlights were reviewed and approved with one edit.

MLR Institute of Technology

Automation, Protection, and Control General Engineering Services for JEA Generating Plants and Substations

ADVERTISEMENT OF PUBLIC NOTICE

TECHNICAL DAYS, APRIL 2017 ABB Plant Fingerprint Assessment Optimizing Operations. Fernando Tobar, Country Service Manager

To ensure system protection is coordinated among operating entities.

B. All of the documents in this RFP form the Basis-of-Design for this project.

The University of Texas at San Antonio

Community Update Brochure

WECC Standard VAR-STD-2a-1 Automatic Voltage Regulators

Energy. Request For Proposals for Renewable Power Supply Resources

Energy Efficiency Alberta Residential and Commercial Solar Program Guidebook

Energy Efficiency Alberta Residential and Commercial Solar Program Terms and Conditions

Western Service Center

Annual Performance Indicator (PI)

NPCC Tasks Related to NERC Blackout Recommendations Timeline

UNIFIED FACILITIES GUIDE SPECIFICATIONS

Training and Evaluation Outline Report

AUSTIN ENERGY REQUEST FOR PROPOSALS (RFP) FOR THE PURCHASE OF RENEWABLE CAPACITY & ENERGY FROM RENEWABLE ENERGY RESOURCES

APPENDIX 2: Electrical Design

If any queries arise ESB Networks DAC can be contacted at or

AMSP Guidebook. February 2017

NATIONAL NUCLEAR REGULATOR

This Letter. Re: PC Guide For Power System Protection Testing

DEPARTMENT OF FACILITIES MANAGEMENT MAINTENANCE AND SERVICES INVITATION TO TENDER

4.2.2 Transmission Owners Transmission Planners Transmission Service Providers Balancing Authorities.

Pilot Program Framework Proposal

Request for Proposals and Specifications for a Distributed Generation Solar Project entitled The Freeman Coliseum Solar Project

CIP Cyber Security Incident Reporting and Response Planning

UCF SOLAR FARM-UCF 584 Solar Developer Project Fact Sheet

Request for Proposals and Specifications for a Community Solar Project

July 1, 2006 Revision 2

TRIP OF YALLOURN POWER STATION NO KV BUSBAR ON 6 DECEMBER 2015

WarmWise Business Custom Rebates Program Manual

PacifiCorp 2017S SOLAR Request for Proposals. Bidder s Conference Portland November 21, 2017

The Narragansett Electric Company d/b/a National Grid

Request for Qualifications. for. Electrical Substation Transformer Replacement. Stillwater Utilities Authority (SUA) City of Stillwater, Oklahoma

METHODOLOGY - Scope of Work

Powered by Safety. Powell Training Catalog

WIND AND SOLAR SPP SOLICITATION 2015 REQUEST FOR QUALIFICATION (RFQ) COMMERCIAL OPERATION OF WIND AND SOLAR SMALL POWER PROJECTS OCTOBER 2015 FOR

2017 All Source Request for Proposals for Electric Power Supply and Load Management Resources. Pre-Bid Meeting

Invitation to Submit Expression of Interest and Proposal

Greater Cambridge Partnership Executive Board. Chris Tunstall Interim Transport Director. Western Orbital

Refer to section 2.C. for more information on the evaluation criteria.

Buck & Boost Transformer Installation Instructions

PROJECT PREPARATORY TECHNICAL ASSISTANCE

Solar Electricity For Community Buildings Pilot Program. Workbook

Department of Defense DIRECTIVE

Electric Reliability Organization Event Analysis Process Phase 2 Field Test Draft May 2,

American Recovery and Reinvestment Act (ARRA) Professional Engineering and Related Technical Services

ELECTRONICS TECHNICIAN I ELECTRONICS TECHNICIAN II

The Narragansett Electric Company d/b/a National Grid

Page. II. TECHNICAL ASSISTANCE PROJECT DESCRIPTIONS.. 3 A. Introduction... B. Technical Assistance Areas.. 1. Rate Design Consumer Programs...

May 6, 2002 Revision 2

Transport NI York Street Interchange APPENDIX A PROJECT BRIEF

DSO Non GPA Process. November 2010 Version 8

30 November CLP launches electricity infrastructure development programme to help energise Kowloon East and Kai Tak development area

SunZia Southwest Transmission Project. September. Project Update for the Board of Socorro County Commissioners February 28, 2017.

PER-005 System Personnel Training

PAVING THE WAY FOR GRID MODERNIZATION. Presenter December 2016

EPSRC-KETEP Call for Collaborative Research between the UK and Korea in Smart Grids

CITY OF COFFEYVILLE, KANSAS REQUEST FOR PROPOSALS FOR ELECTRICAL ENGINEERING, SUBSTATION MAINTENANCE, TESTING & SUPPORT SERVICES

GE Energy Connections

TOWN OF NEW TECUMSETH PROTOCOL FIT APPLICATIONS FOR RENEWABLE ENERGY

MRA4 Modbus HighPROTEC. Data point list. Manual DOK-TD-MRA4MDE

FUNDAMENTALS OF ELECTRICITY TRANSMISSION COURSE

P A N E L B O A R D S C H E D U L E

HT1611C Timer with Dialer Interface

Embassy of the United States of America Ottawa, August 29, 1988 No. 364

GESP Procurement Plan MARCH 2017

TOLEDO METROPOLITAN AREA COUNCIL OF GOVERNMENTS

Solar Photovoltaic. Standard Offer Program (SVPSOP) 2018 Program Manual. Rev # Final

Transcription:

Generator Interconnection Impact Study Report Wayne County, NC 20.0 Solar Farm Queue #364

Table of Contents 1 PURPOSE... 3 2 ASSUMPTIONS... 3 3 RESULTS... 4 3.1 Power-flow Analysis Results... 4 3.2 Stability Analysis Results... 4 3.3 Power Factor Requirements... 4 3.4 Short Circuit Analysis Results... 5 3.5 Harmonics Assessment... 5 3.6 Interconnection of Customer s Generation... 6 3.7 Estimate of Interconnection Cost... 6 4 SUMMARY... 7 APPENDIX I : FIGURES... 8-2 -

1 PURPOSE The purpose of this Impact study is to assess the impacts of the generator interconnection requests on the reliability of the (DEP) transmission system with respect to power flow, power factor, stability, and short circuit. Estimates of the cost and time required to interconnect the generation as well as to resolve the impacts as determined in this analysis are also included. The DEP internal system analysis consists of an evaluation of the internal DEP transmission system utilizing documented transmission planning criteria. The requests are described in Table 1 below. DEP Generator Interconnection Queue No. Table 1: Interconnection Requests Requested In-Service Date County Q364 20.0 12/31/2016 Wayne County, NC Interconnection Facility Lee Substation-Mt. Olive 115kV Line, Mt. Olive Tap 2 ASSUMPTIONS The following Impact Study results are from the DEP internal power-flow and dynamic models that reflect specific conditions of the DEP system at points in time consistent with the generator interconnection requests being evaluated. The cases include the most recent information for load, generation, transmission, interchange, and other pertinent data necessary for analysis. Future years may include transmission, generation, and interchange modifications that are not budgeted and for which no firm commitments have been made. Further, DEP retains the right to make modifications to modeling cases as needed if additional information is available or if specific scenarios necessitate changes. For the systems surrounding DEP, data is based on the ERAG MG model. The suitability of the model for use by others is the sole responsibility of the user. Prior queued generator interconnection requests were considered in this analysis. The results of this analysis are based on Interconnection Customer s queue requests including generation equipment data provided. If the facility technical data or interconnection points to the transmission system change, the results of this analysis may need to be reevaluated. This study was based on the following assumptions: CUSTOMER would construct, own and operate the electrical infrastructure that would connect their generation to DEP s facilities, including any step up transformers and lines from the generators, but excluding the circuit breaker in the new DEP breaker station where applicable. - 3 -

3 RESULTS 3.1 Power-flow Analysis Results Facilities that may require upgrade within the first three to five years following the in-service date are identified. Based on projected load growth on the DEP transmission system, facilities of concern are those with post-contingency loadings of 95% or greater of their thermal rating and low voltage of 92% and below, for the requested in-service year or the in-service year of a higher queued request. The identification of these facilities is crucial due to the construction lead times necessary for certain system upgrades. This process will ensure that appropriate focus is given to these problem areas to investigate whether construction of upgrade projects is achievable to accommodate the requested interconnection service. All queue requests, as well as nearby existing and prior-queued generation, were modeled and assumed to be operating at full output. Contingency analysis study results show that interconnection of these generation facilities result in no potential thermal or voltage issues on the DEP system. 3.2 Stability Analysis Results A stability analysis was performed to determine the impact of the proposed generation additions on the DEP transmission system and other nearby generation. All queue requests, as well as nearby existing and prior-queued generation, were modeled and assumed to be operating at full output. The proposed solar farm was modeled considering the specific layout and number of inverters (11 TMEIC PVL-L-1833GRM inverters, 22 MVA). The model included a single lumped equivalent generator (to represent the inverters) with inverter transformer (6%Z at 2000 kva x 11) and collector impedance. The interconnection to the DEP transmission system was via a single substation transformer (9%Z at 13/17.33/21.66//24.67 MVA), based on data provided by the Customer. A representative set of faults was simulated to determine if there would be any adverse impact to the transmission system as a result of the proposed generation. The ability of the solar farm to ride through the voltage depressions resulting from the faults was also verified, based on the model parameters provided by the Customer. The stability evaluation did not identify any stability related problems. All generators stayed on-line and stable for all simulated faults. If the Customer data changes from that provided, these results will need to be reevaluated. 3.3 Power Factor Requirements DEP s Large Generator Interconnection Procedure (LGIP) requires the proposed generation to be capable of delivering the requested to the Point of Interconnection (POI) at a 0.95 lagging power factor. For analysis of the power factor requirement, the Customer-supplied data regarding inverter capabilities, collector field configuration, impedances and line charging, and transformer impedances were used. The results of the analysis indicate that the proposed solar plant design, without capacitors, DOES NOT meet the 0.95 lagging power factor - 4 -

requirement at the POI for the requested delivery level. If no capacitors are included in the plant design, Table 2 below summarizes the approved at the POI, along with the MVAR capability at the POI required to meet the 0.95 lagging power factor requirement at the POI. If capacitors are included in the design, Table 3 below summarizes the approved at the POI, along with the MVAR capability at the POI and the capacitor size required to meet the 0.95 lagging power factor requirement at the POI. The Customer must notify Duke Energy which option they choose before the Facility Study can be performed. Table 2: Approved and MVAR Capability Required at the POI to Meet Power Factor Requirements Reduce Option DEP Generator Interconnection Queue No. Requested Approved MVAR Capability Required 364 20.0 18.4 6.0 Table 3: Approved and MVAR Capability Required at the POI to Meet Power Factor Requirements Add Capacitor Option DEP Generator Interconnection Queue No. Requested Approved MVAR Capability Required Capacitor MVAR Required 364 20.0 20.0 6.6 1.3 3.4 Short Circuit Analysis Results A short circuit analysis was performed to assess the impact of the proposed generation addition on transmission system equipment capabilities. The analysis indicates that no short circuit equipment capabilities will be exceeded as result from the proposed generation additions and associated transmission upgrades. The results of the short circuit study are based on Customer provided generation equipment data and location. Also, the prudent use of engineering assumptions and typical values for some data were used. If the units technical data or interconnection points to the transmission system changes, the results of this analysis may need to be reevaluated. 3.5 Harmonics Assessment There is potential interaction of harmonic current injections from the Customer s proposed generation and certain capacitor banks on the DEP system. Testing may be necessary after the actual in-service date of this generation and the Customer will be responsible for mitigation of any detrimental impacts to the system. - 5 -

3.6 Interconnection of Customer s Generation The point of interconnection for Queue #364 is a new 115 kv breaker station connected to the Mt. Olive Tap of the Lee Substation-Mt. Olive 115kV Line near structure 11. The breaker station one-line is provided as Figure 1. The customer should verify that the MVA ratings of their connecting lines are sufficient to accommodate delivering the total MVA output to the point of interconnection at the required 0.95 power factor. 3.7 Estimate of Interconnection Cost Q364 The estimate includes the assumption that DEP will acquire and use a portion of the property that the Customer will secure for the addition of the facility. Tap Line Description: Estimated Cost: $650,000 New Breaker Station Description: Estimated Cost: $1,650,000 DEP will tap the Mt. Olive Tap of the Lee Substation-Mt. Olive 115kV Line and Construct a short tap line to New Breaker Station adjacent to DEP ROW. Manual switches will be installed on each side of the Tap. Construct new 1-115 kv breaker station at generation new connection point. Assumes a control building with cable trench, line trap, CCVTs, surge arrestors, power pot, 115 kv breaker with air break switches, metering PTs and CTs. Install Transfer Trip Scheme at New Breaker Station and Transmission Substations Description: It will be necessary to separate this generation facility from the DEP system for faults on the Lee Substation-Mt. Olive 115kV Line. Install protection system and transfer trip for coordination between the above listed transmission line and proposed generation facility. Estimated Cost: $200,000 Taxes Description: NC utility tax of 7% Estimated Cost: $175,000 Total Interconnection Cost Estimate: $2,675,000-6 -

Wayne Cowtty, NC - 20.0 M\\l, Queue #364 4 SUMMARY This Generator Interconnection Impact Study assesses the impact of interconnecting a new generation facility with a requested summer/winter rating of 20.0. Based on the data provided by the requester, the approved I\iIW injection is 18.4 I\iIW without a capacitor or 20.0 I'vIW with an 1.3 Mvar capacitor bank. Power flow, stability, and short circuit analyses found no issues. Interconnection upgrades to the DEP Transmission System arc necessary to accommodate Q364. The requested in-service date cannot be met. DEP will require at least 12 months after a firm written agreement to proceed is obtained from the customer. The additional cost for telecommunications and metering can be estimated as a monthly charge of S3,000/month per interconnection. Power-flow Stability Short Circuit T nterconnection Total Estimate so so so $2.675.000 $2,675,000 Study Completed by: ----'4.g.,L..IC..J.... ~< --... ~t:...l.1~,,.. ~ t-'l<l""=-'- ------ Bill Q~m~ke Energy Progress Reviewed by: Mark Byrd, PE, Duke Efiergy Progress

APPENDIX I : FIGURES - 8 -

-Figure 1- - 9 -