Western Avalon Terminal Station T5 Tap Changer Replacement. Status Update Briefing August 15, 2014

Similar documents
Seawall Earthquake Safety + Disaster Prevention Program Community Meeting June 21, 2018

Navy ManTech Program. ManTech Update. Tom Hite CTC 15 October 2014

Marine Protection Rules Part 130B Oil Transfer Site Marine Oil Spill Contingency Plans

Standardising Acute and Specialised Care Theme 3 Governance and Approach to Hospital Based Services Strategy Overview 28 th July 2017

Exhibit R-2, RDT&E Budget Item Justification

Commandant Education Boards. Major Jerry A. Godfrey Combat Service Support Majors Monitor Manpower Management Officer Assignments

Smithsonian Institution

NHS Forth Valley. Annual Procurement Report 2017/18

NHS DORSET CLINICAL COMMISSIONING GROUP GOVERNING BODY MEETING ADULT AND CHILDREN CONTINUING HEALTHCARE ANNUAL REPORT

November NHS Rushcliffe CCG Assurance Framework

CHC-A Continuity Dashboard. All Sites Continuity - Asthma. 2nd Qtr-03. 2nd Qtr-04. 2nd Qtr-06. 4th Qtr-03. 4th Qtr-06. 3rd Qtr-04.

A. General provisions and other electrical systems are specified in other Sections of Division 26.

REQUEST FOR QUALIFICATIONS CONSULTING EXECUTIVE LANDSCAPE ARCHITECT HOPKINS LANE BIKE & PEDESTRIAN IMPROVEMENT UNIVERSITY OF CALIFORNIA, SAN DIEGO

UNCLASSIFIED. R-1 ITEM NOMENCLATURE PE BB: SOF Underwater Systems

The Case for Optimal Staffing: A Call to Action

Oct-15 As above CK/JG. Aug/Sep TU Reps

BOROUGH OF ROSELLE PUBLIC NOTICE ANNUAL NOTICE OF CALENDAR YEAR 2018 WORKSHOP SESSIONS, PRE-AGENDA MEETINGS AND REGULAR MEETINGS

Employment & Unemployment

Employment & Unemployment

UNCLASSIFIED R-1 ITEM NOMENCLATURE FY 2013 OCO

August 2018 Labor Market Review Reported by: Cassie Janes

Incident Reporting Training Guide

Abu Dhabi EHSMS Regulatory Framework (AD EHSMS RF)

Status of Implementing Legislation Regarding the Eastern Band of Cherokee Indians

Metro Mobility Agency Contract Award. Transportation Committee April 23, 2018

Employment & Unemployment

Corporate Services Employment Report: January Employment by Staff Group. Jan 2018 (Jan 2017 figure: 1,462) Overall 1,

Egypt National Railways Restructuring Project (ENRRP) Procurement Plan Updated on April 21, 2014

UNCLASSIFIED R-1 ITEM NOMENCLATURE

Transportation and warehousing

FY16 Spend - DoD as Funding Dept Services = 51% of Obligations

DATA Act Analytics. Unlocking Federal Spending Data through Analytics

VALUE ENGINEERING PROGRAM

INLAND RAIL - PARKES TO NARROMINE (P2N) INDUSTRY BRIEFING

Request for Qualifications. for. Electrical Substation Transformer Replacement. Stillwater Utilities Authority (SUA) City of Stillwater, Oklahoma

Operational Excellence: Lean

Jun 03 Jul 03 Aug 03 Sep 03 Oct 03 Nov 03 Dec 03 Jan 04 Feb 04 Mar 04 Apr 04 May 04

August 2018 Labor Market Review Reported by: Cassie Janes

UNCLASSIFIED. R-1 ITEM NOMENCLATURE PE F: Air Force Integrated Personnel and Pay System (AF-IPPS) FY 2012 OCO

7 IA 7 Hazardous Materials. (Accidental Release)

Procurement Plan Enhancing Quality of Financial Reporting (EQ-FINREP) Grant No:

SCIENCE ADVISORY COMMITTEE TERMS OF REFERENCE

Implementation Status & Results Congo, Democratic Republic of Emergency Demobilization and Reintegration Project (P078658)

ALBERTA TRANSPORTATION North Central Region Edson Area Instrumentation Monitoring Results

UNCLASSIFIED FY This program develops and demonstrates advanced technologies, including Electromagnetic (EM) Rail Gun for naval weapon systems.

CITY OF LANCASTER REVITALIZATION AND IMPROVEMENT ZONE AUTHORITY

UNCLASSIFIED. UNCLASSIFIED Air Force Page 1 of 7 R-1 Line #90

UNCLASSIFIED. Cost To Complete Total Program Element ED8: Paladin Integrated Management (PIM)

Cardinal Bank & George Mason University

Enlisted Professional Military Education FY 18 Academic Calendar. Table of Contents COLLEGE OF DISTANCE EDUCATION AND TRAINING (CDET):

School Board of Brevard County, Florida Half-Cent Sales Surtax Internal Audit Fiscal Year

Kentucky Sepsis Summit. August 2016

Implementing the Pilot Program for Debris Removal

UNCLASSIFIED R-1 ITEM NOMENCLATURE

BOARD OF DIRECTORS PAPER COVER SHEET. Meeting Date: 1 st December 2010

Sunnybrook: Improving prosthetic care for patients with lower limb amputation

Quality Management Report 2017 Q2

UNCLASSIFIED. R-1 Program Element (Number/Name) PE A / Integrated Personnel and Pay System-Army (IPPS-A) Prior Years FY 2013 FY 2014 FY 2015

New Hope Crushed Stone. Monthly Update Solebury Communications Group November 2017

Open Government Data For Bangladesh. Access to Information Programme Prime Minister s Office Dhaka, Bangladesh

A&E - Preparing a 2018 Capital Budget Request Including Predesign Guideline Updates. System Director, Capital Development

EOP/SUPPORT ANNEX F/APPENDIX 14 EOC FINANCE SECTION APPENDIX 14 EOC FINANCE SECTION

HUMAN FACTORS ENGINEERING - VALVES

BASINGSTOKE AND NORTH HAMPSHIRE HOSPITALS NHS FOUNDATION TRUST

KANATA HIGHLANDS URBAN EXPANSION STUDY TERMS OF REFERENCE

IA5. Hazardous Materials (Accidental Release)

Friday, June 21, 13. Building better communities through the arts

Central City Line Kick-off and Tour

UNCLASSIFIED. UNCLASSIFIED Navy Page 1 of 7 P-1 Line #18

OPNAVINST F N4 5 Jun 2012

UNCLASSIFIED//FOR OFFICIAL USE ONLY

ICS I-100 Introduction to Incident Command System Final Exam B.

PROMPR22 Carrying out fault diagnosis on mechanical equipment

Florida Department of Transportation 605 Suwannee Street Tallahassee, FL

MILPERSMAN OPNAV N130) Phone: DSN COM FAX

Influence of Patient Flow on Quality Care

Andrea Croft RGN Lead Advanced Nurse Practitioner Anticoagulation. Welsh Nurse Director Thrombosis UK

Public Disclosure Copy. Implementation Status & Results Report Global Partnership for Education Grant for Basic Education Project (P117662)

UNCLASSIFIED. R-1 Program Element (Number/Name) PE D8Z / Prompt Global Strike Capability Development. Prior Years FY 2013 FY 2014 FY 2015

Commanding General LAW 2200 Lester Street, Suite 120 Quantico, VA Fax:

Incident reporting, investigation and follow-up

Title. SF Health Network Telephone Communication Program. Subtitle. Antenor Arenas Director, Centralized Call Center

Oil Spill Recovery Institute. Graduate Research Fellowship. Program Description and Application Information

NATIONAL OCEANIC AND ATMOSPHERIC ADMINISTRATION NOAA ADMINISTRATIVE ORDER SERIES TABLE OF CONTENTS. as of December 8, 2008

Xcel Energy Colorado DSM Roundtable Discussion. February 13, :00pm to 4:00pm 1800 Larimer, Room 03G01

North Carolina Division of Medical Assistance

REQUEST FOR PROPOSALS (RFP) For Electrical Engineering Design Services City Hall Switchgear Replacement October 28, 2016

HQMC 11 Jun Show the PCN distribution in the "DISTRIBUTION:" section of the basic Order to read: "PCN "

IGO GROUP SAFETY STANDARD 15 - ENERGY CONTROL AND ISOLATION INDEPENDENCE GROUP NL

NRC Public Meeting October 27, 2014

FEDERAL CONTRACTING. Mary L. Peetz Small Business Professional Luke AFB. 11 May Fly, Fight, & Win 101. Cave Tonitrum

UNCLASSIFIED. R-1 ITEM NOMENCLATURE PE F: Air Traffic Control/Approach/Landing System (ATCALS) FY 2012 OCO

GOVERNMENT OF THE DISTRICT OF COLUMBIA Office of Contracting and Procurement REQUEST FOR TASK ORDER PROPOSAL

NORTHWESTERN UNIVERSITY PROJECT NAME JOB # ISSUED: 03/29/2017

SUPPLY CHAIN MANAGEMENT AND PROJECT MANAGEMENT

WARM HOMES FUND ROADSHOW. November/ December 2017

Leveraging your own health plan to build a Specialty Pharmacy

UNCLASSIFIED R-1 ITEM NOMENCLATURE

Welcome SUPT Students

FFSC NAS JAX Workshops

Transcription:

Western Avalon Terminal Station T5 Tap Changer Replacement Status Update Briefing August 15, 2014

Contents Project Dashboard Progress & Schedule Summary Contracting Plan Risk Analysis Project Photos (Incremental to Information Provided July 30) 2

Project Dashboard 3

Progress & Schedule Summary 1. T5 Transformer Modifications contract (supply and install) in place with CG Power (Transformer OEM) 2. Reinhauser Tap Changer parts manufacture in progress. Assembly starting next week for completion Sep 5. 3. Tap Changer Delivery Air Freight through Halifax, Truck to WAV 5 to 7 days Planned Sep 13 (1 week delay) 4

Progress & Schedule Summary 5. Site work is approximately four weeks; ready for commissioning by end September/early Oct with a planned in service date of October 13 th (1 week delay) 6. Risk Review undertaken August 7 th. Action list spreadsheet developed. 7. Overall Schedule tracking 1 week later due to actual delivery times; Ready for Service date Oct 13 (See attached schedule) 5

Level 2 Schedule Summary 6

Level 2 Schedule S Curve (Preliminary Project Accounting in Process of Set-Up) $1,400.00 Western Avalon Transformer Project 2014 Costs ($,000's) $1,200.00 $1,000.00 $800.00 $600.00 Actual Planned $400.00 $200.00 $0.00 1/1 1/31 3/2 4/1 5/1 5/31 6/30 7/30 8/29 9/28 10/28 Note: Forecast Final Expenditures (FFE) tracking with compliance with original budget. Actual Costs Aug 1 reflects contractual commitments for major equipment and install contracts to Aug 15.) 7

Contracting Plan 1 T5 Transformer Modification (Supply & Install, Tap Changer) 2 T5 Tap Changer T5 Transformer modifications materials and install, tap chnager materials and install, supply to PAD T5 Tap Changer Supply to CG Power (Sub Contract) CG Power Rheinhauser 6/23/2014 On Site Sep 5 6/23/2014 deliver to site Sep 13 13 Oct 13/10/2014 Rep on site for install Ongoing Ongoing 8

Risk Analysis Third Party Facilitated Risk Workshop and Risk Register Spreadsheet produced for WAV Aug 7. Major risks similar to, but less than those for SSD. Actions identify to risks where practical. 9

Risk Analysis Example of Issues T5 Tap Changer Delivery Timing, Damage Expedite (air freight) and monitor; T5 Tap Changer Installation/Failure T5 Transformer modifications CG Power detailed plan cutting and cleaning P&C Re Connections Oversight OEM recommendations, modifications and commissioning 10

Project Photos None Available at this time Tap Changer parts in manufacture, Assembly starts next week.

WAV Transformer # Activity Name Remaining Start Finish Comments Duration 1 WAV Transformer 58d 16-Jun-14 A 31-Oct-14 Incremental Layout Updated: 12-Aug-14 June 2014 July 2014 August 2014 September 2014 October 2014 November 2014 December 2014 01 08 15 22 29 06 13 20 27 03 10 17 24 31 07 14 21 28 05 12 19 26 02 09 16 23 30 07 14 21 28 2 Project Milestones 26d 09-Sep-14 15-Oct-14 3 Start of Construction 0d 09-Sep-14 4 Tap Changer on Site 0d 13-Sep-14 5 Commissioning Complete 0d 15-Oct-14 6 PM Tasks 0d 30-Jun-14 A 07-Aug-14 A 7 Develop Project Scope Statement 0d 30-Jun-14 A 25-Jul-14 A Start of Construction Tap Changer on Site Commissioning Complete 8 Prepare Safety Assessment & Safety Plan 0d 14-Jul-14 A 25-Jul-14 A Contractor 9 Finalize PSS & approve 0d 25-Jul-14 A 01-Aug-14 A 10 Risk Workshop 0d 30-Jul-14 A 07-Aug-14 A 11 Engineering 57d 16-Jun-14 A 31-Oct-14 12 PCC 57d 16-Jun-14 A 31-Oct-14 13 PCC Engineering 57d 16-Jun-14 A 31-Oct-14 14 Perform P&C Prep - Isolation plan 15d 12-Aug-14 02-Sep-14 TRO 15 Electrical 57d 16-Jun-14 A 31-Oct-14 16 Engineering - Electrical 57d 16-Jun-14 A 31-Oct-14 17 Procurement - Material 23d 23-Jun-14 A 13-Sep-14 18 T5 Transformer Tap Changer 23d 23-Jun-14 A 13-Sep-14 19 Order Tap Changer 0d 23-Jun-14 A 25-Jun-14 A 20 Fabrication Period 17d 25-Jun-14 A 04-Sep-14 21 Ship to site 9d 05-Sep-14 13-Sep-14 22 Procurement - Installation Contract 0d 25-Jun-14 A 02-Jul-14 A 23 Prepare & Issue Contract 0d 25-Jun-14 A 02-Jul-14 A 24 Construction - T5 Transformer Tap Ch 31d 09-Sep-14 16-Oct-14 Perform P&C Prep - Isolation plan Fabrication Period Ship to site PCC Engineering Engineering - Electrical 25 LOTO 31d 09-Sep-14 16-Oct-14 26 Isolate Work Zone 2d 09-Sep-14* 11-Sep-14 27 Permit Holder 31d 09-Sep-14 16-Oct-14 28 De-Isolate Work Zone 1d 15-Oct-14 16-Oct-14 29 Contractor's Schedule 23d 11-Sep-14 08-Oct-14 30 Mobilization to site 2d 11-Sep-14 13-Sep-14 31 Equipment Set-up & Misc 2d 12-Sep-14 15-Sep-14 32 Safety/Job Hazard Assessment 3d 12-Sep-14 16-Sep-14 33 Transformer Maintenance Activities 14d 15-Sep-14* 01-Oct-14 34 Pressurize Transformer 2d 30-Sep-14 02-Oct-14 35 Perform Dew Point Test 1d 01-Oct-14 02-Oct-14 36 Pull Vacuum 2d 01-Oct-14 03-Oct-14 37 Vacuum Oil Fill 2d 02-Oct-14 04-Oct-14 38 Transformer Testing 2d 03-Oct-14 06-Oct-14 39 Clean Up Site 2d 04-Oct-14 07-Oct-14 40 Demobilization 2d 06-Oct-14 08-Oct-14 41 Electrical Construction 1d 06-Oct-14 07-Oct-14 42 Comms 1d 06-Oct-14 07-Oct-14 43 Make RTU changes & do Telecontrol pts check with 1d 06-Oct-14 07-Oct-14 ECC 44 Elect/P&C/Comms. Commissioning 7d 06-Oct-14 15-Oct-14 45 Transformer T5 Tap Changer 7d 06-Oct-14 15-Oct-14 46 Commission T5 Transf. Prot. & All Other Applicable 7d 06-Oct-14 15-Oct-14 P&C Connections Isolate Work Zone De-Isolate Work Zone Mobilization to site Equipment Set-up & Misc Safety/Job Hazard Assessment Transformer Maintenance Activities Pressurize Transformer Perform Dew Point Test Pull Vacuum Vacuum Oil Fill Transformer Testing Clean Up Site Demobilization Make RTU changes & do Telecontrol pts check with ECC Commission T5 Transf. Prot. & All Other Applicable P&C Connections Actual Work Remaining Work Critical Remaining Work Milestone Summary Page 1 of 1