CASE STUDY Making Resettlement Work through Partnerships

Similar documents
( 30%) Special committee report, 1968, % MMDA %(1985), 40.2%(1988), 39.9%(1991), 35.5% (1994), 31.8% (1997), 33.

ADB Official Cofinancing with UNITED KINGDOM. Working together for development in Asia and the Pacific

DISASTER PREPARENESS INITIATIVES AND UPDATES ON YOLANDA REHABILITATION

MANDALUYONG CITY, PHILIPPINES. Case Study (Public Buildings) Project Summary:

Information for Participants Send accreditation/registration requests by

OPERATIONS MANUAL BANK POLICIES (BP) These policies were prepared for use by ADB staff and are not necessarily a complete treatment of the subject.

Disaster Risk Management at ADB with Lessons from Yolanda. Tatsuya Kanai Senior Advisor Office of Cofinancing Operations ADB

PROJECT INFORMATION DOCUMENT (PID) CONCEPT STAGE. Adaptable Program Loan P F-Financial Intermediary Assessment 08-May Nov-2012

GRANT AGREEMENT (ADB Strategic Climate Fund) (Greater Mekong Subregion Biodiversity Conservation Corridors Project Additional Financing)

Regional: Supporting the Cities Development Initiative for Asia

Disaster Preparedness and Response

PROJECT INFORMATION DOCUMENT (PID) CONCEPT STAGE Report No.: AB7052

KECAMATAN DEVELOPMENT PROJECT *

PROJECT INFORMATION DOCUMENT (PID) APPRAISAL STAGE

STEFFIE JOI CALUBAYAN-FRIAS

Global Agriculture and Food Security Program NICHOLA DYER, PROGRAM MANAGER

Canada and the Role of the Private Sector in Development in the Philippines. Presentation to: Canadian Chamber of Commerce October 2014

ANNOUNCEMENT Conference on Community-based Disaster Preparedness in Asia

The LORD hears the cry of the poor; he delivers them from all their troubles. Psalm 34:17

R E Q U E S T F O R P R O P O S A L S

CBMS-AKFI Development Grant Program

2012/SMEMM/010 Agenda Item: 2.4. SMEWG Chair Report. Purpose: Information Submitted by: SMEWG Chair

DECISION SCIENCES INSTITUTE Information Management During Disaster Response in Visayas Region of the Philippines: Typhoon Haiyan Experience

Supporting Nepal to Build Back Better

SEMINAR SERIES SPONSORSHIP

PPCR OPERATIONS AND RESULTS REPORT (SUMMARY)

Public Disclosure Authorized. Public Disclosure Authorized. Public Disclosure Authorized. Public Disclosure Authorized

The Next 15 Million: Entrepreneurship Training At Scale New Data On The Global Outreach Of ILO s Entrepreneurship Training

PHILIPPINES Typhoon Yolanda Ongoing Recovery

Republic of Indonesia: Water Supply and Sanitation Sector Development Project

ADB S COOPERATION WITH CIVIL SOCIETY ORGANIZATIONS 2017

Assessing Energy Needs, Market Opportunities, and Distribution Strategies. Eric Verploegen D-Lab s Off-Grid Energy Group February 22 nd 2016

DIGITAL STRATEGIES FOR DEVELOPMENT SUMMIT 2015

Addressing the sanitation crisis through a market-based approach

Entrepreneurship Education Policy and Implementation. in Philippines

UNESCO-Japan Prize on Education for Sustainable Development (ESD)

Expert Meeting on. Investment, Innovation and Entrepreneurship for Productive Capacity Building and Sustainable Development.

Wrigley Company Foundation 2011 Summary

Seminar SerieS SponSorShip

Key development issues and rationale for Bank involvement

ADB AND CIVIL SOCIETY PARTNERSHIP

Regional Learning Event on Cash Coordination 19 June 2015 Bangkok, Thailand

Global Partnership for Enhanced Social Accountability (GPESA) December 19, 2011 World Bank

People s Republic of China: Strengthening the Role of E-Commerce in Poverty Reduction in Southwestern Mountainous Areas in Chongqing

Wrigley Company Foundation 2012 Summary

ICT Statistics in the Philippines: A Situationer

Explanatory note 2017 Call for Nominations

Pfizer Foundation Global Health Innovation Grants Program: How flexible funding can drive social enterprise and improved health outcomes

Resettlement Planning Document

Rajasthan Urban Sector Development Program

Catholic Charities of Southeast Texas, Inc. Parish Social Ministry. Catholic Campaign for Human Development Local Grant Funding Criteria

The FedEx Award for Innovations in Disaster Preparedness Submission Form

: Ulaanbaatar Urban Services and Ger Areas Development Investment Program Project 1

Get it Done: Rebuild Michigan GRETCHEN WHITMER S PLAN FOR SAFE ROADS, CLEAN WATER, AND A BETTER ECONOMY

Indicators on Community Access to ICT: Critical Policy and Planning Tools in the Implementation of the Philippine Community E-Center Program

CHAPTER 2 TECHNOLOGY BUSINESS INCUBATORS GLOBAL SCENARIO

ECHO Partners' Conference 2009 Workshop B: "NGOs and the Cluster Roll-out, Strengths and Suggestions for the Future"

FRAMEWORK FINANCING AGREEMENT. (National Highway Development Sector Investment Program Project 1) between ISLAMIC REPUBLIC OF PAKISTAN.

with the Corporación Andina de Fomento (CAF) for Republic of Chile 16 March 2017 Entity Support & Strategic Frameworks

ASIA PACIFIC INFORMATION SUPERHIGHWAY (AP-IS)

Mainstreaming Low Carbon Path in the Transport Sector in the National and Local Levels

BPP Escamequita a Barrio Planta Project Initiative

Guidelines: Embassy of Japan in the Philippines

BUSINESS SUPPORT. DRC MENA livelihoods learning programme DECEMBER 2017

Kiva Labs Impact Study

Guidelines for Completing the Grant Application Form

Regional Brief: ICP for Asia and the Pacific

GOVERNANCE, STAKEHOLDER INVOLVEMENT, COORDINATION

Michigan Municipal League Hatch Detroit

UPC. An Overview. The Urban Projects Concept. Financial support for improved access to water and sanitation

ILO Manila Staff Union Action Programme in Response to Typhoon Yolanda,

IOM PHILIPPINES EMERGENCY RESPONSE DELIVERING RELIEF AND RECOVERY TO COMMUNITIES IN EMERGENCIES AND POST-CRISIS

The PEOPLE Service Concept and objectives. From the concept to the feasibility study. Analysis of Single Window Service models throughout the world

Edmonton s Joint Use Agreements. Annual Report

Volunteer Application

Investing in the Philippinesʼ Tourism Development. Atty.. GUILLER B. ASIDO Tourism Infrastructure and Enterprise Zone Authority

People s Republic of China: Strategy for Inclusive and Green Development of Small Cities, Towns, and Villages in Jiangxi Province

July 13, RE: Comments on Whole Child Model Documents. Dear CCS Redesign Team:

MAPPING OF SEs IN FOOD SECURITY SECTOR. Bikundo Onyari Nairobi, Kenya. 18 th October 2016

18th Microcredit Summit

Call for Proposals from Fundraising Consultants:

Speech by United Nations Development Programme

Safe Drinking Water and Sanitation for School Children Zimbabwe Final Report to the Isle of Man Overseas Aid Committee July 2011-April 2012

Sri Lanka: Tsunami-Affected Areas Rebuilding Project

PROSPEROUS INCLUSIVE RESILIENT SUSTAINABLE ASIA AND THE PACIFIC

Vietnam Innovation Day 2011

3. Where have we come from and what have we done so far?

Integra. International Corporate Capabilities th Street NW, Suite 555W, Washington, DC, Tel (202)

7. Ownership and Management of Incubators

Lao People s Democratic Republic: Strengthening Urban Water Supply Regulation

TECHNOLOGY SOLUTION FOR THE MARGINALIZED

Promote and strengthen international collaboration to reduce road traffic injuries. Preamble

1. Building partnerships

Community Driven Development: Findings and Applied Learning

Case study: System of households water use subsidies in Chile.

Ministerial declaration of the high-level segment submitted by the President of the Council

Proposed Grant Assistance Republic of the Union of Myanmar: Pro-Poor Community Infrastructure and Basic Services

ADB Expatriate Spouse Career Services

AUDIT OF THE UNDP AMKENI WAKENYA PROGRAMME KENYA. Report No Issue Date: 10 January 2014

Evaluation Study. ADB s Japan Funds: Japan Fund for Poverty Reduction. Operations Evaluation Department

Transcription:

CASE STUDY Making Resettlement Work through Partnerships Aerial view of Southville 7. Photo credit: ABS-CBN Lingkod Kapamilya Foundation. The Southville 7 community in the Philippines shows how different sectors of society worked successfully together to turn a basic housing project into a livable community for 5,000 resettled families. Overview Southville 7 is regarded as a model resettlement site in the Philippines. Its success is mainly because of multisector and multistakeholder efforts led by the National Housing Authority (NHA) and ABS-CBN Lingkod Kapamilya Foundation, Inc. (ALKFI). Building the resettlement community in partnership with multiple agencies with a range of mandates and operating styles was not easy. The partners of Southville 7 overcame challenges through close collaboration and by focusing on a common vision for the community. This case study shares the impact and lessons from the experiences in Southville 7, along with a framework that outlines the steps other organizations can take to make resettlement work. It is based on a detailed report, Southville 7: Making Resettlement Work, by the Asian Development Bank (ADB), which provided a $1.5 million grant in 2012 to support multisector partnerships. Project snapshot

Dates 2000: NHA completes Southville 7 Housing Project. 2006: Southville 7 becomes a resettlement site. 2009: NHA and ALKFI formally agree to share management of Southville 7. 2009-2011: About 3,000 families in Metro Manila, who were displaced by Typhoon Ondoy (Ketsana), arrive. 2010: Habitat for Humanity begins building houses. 2011: Local government of Calauan issues a moratorium on relocation to Southville 7, citing a lack of resources. 2012: ADB s Japan Fund for Poverty Reduction provides a $1.5 million grant. 2013: First homeowners associations register with Housing and Land Use Regulatory Board. 2013: Businesses start setting up shop, creating jobs for 300 residents. 2016: Partners formally reaffirm commitment and support for Southville 7 until 2020. Cost ADB's Japan Fund for Poverty Reduction (Grant): US$ 1,500,000 Government (In-kind): US$ 2,540,334 Government (Cash): US$ 250,000 Private sector contribution (In-kind): US$ 1,338,180 Community contribution (In-kind): US$ 380,230 Total: US$ 6,008,744 Institutions and Stakeholders Financing Asian Development Bank (Grant) Executing agency National Housing Authority Implementing agency ABS-CBN Lingkod Kapamilya Foundation Others Homeowners associations Municipal Government of Calauan Ayala Foundation, Consuelo Foundation, Habitat for Humanity Philippines, Life Project 4 Youth, Salesians of Don Bosco (NGO partners)

Challenges Families relocate to Southville 7 in Calauan, Laguna. Photo credit: ABS-CBN Lingkod Kapamilya Foundation, Inc. For a long time, Southville 7 in Calauan, a second-class municipality in Laguna province, was one of NHA's more challenging resettlement areas. Nestled between Laguna de Bay and Mount Kalisungan about 75 kilometers south of Metro Manila, Southville 7 is home to about 5,000 families. The housing project was built in 2000, but its relatively isolated location and a lack of services and local jobs meant that only a few took up residence. In 2006, it became a relocation site for families displaced from informal settlements and later for those who lost their homes to Typhoon Ondoy (also known as Ketsana) in 2009. This was a time before housing projects and resettlement sites were designed to include local services and social infrastructure, so conditions were not conducive to rebuilding lives after displacement. The local government of Calauan also has limited resources for the growing community. It issued a moratorium on relocation to Southville 7 in 2011. In 2009, NHA asked ALKFI to co-manage Southville 7. The housing agency took charge of estate management, while ALKFI facilitated the delivery of services not covered by the local government's limited resources. ALKFI also invited private sector and nongovernmental organizations (NGOs) to provide more housing, basic services such as water and electricity, and livelihood. ALKFI also approached the ADB, which approved a $1.5 million grant in 2012 to support multisector partnerships and address the growing challenges in Southville 7. Funded by ADB's Japan Fund for Poverty Reduction, the Promoting Partnerships and Innovation in Poor and Underserved Communities project piloted public-private partnerships to provide basic services, such as safe drinking water, and supported community development, innovation, and entrepreneurship through the Community Assistance Fund (CAF) and Community Innovation Fund (CIF).

Working with many partners involved complex arrangements. The Southville 7 project faced several challenges. Livelihood prospects for residents were limited. There were many livelihood initiatives at the site, but there were just too many people out of work. Activities funded by CIF and CAF did create some jobs, as did a few companies who outsourced some of their operations to Southville 7. Skills training also helped develop entrepreneurs. Partners saw cooperation as too time consuming. Each organization had its own way of working, and usually operated independently. The model of collaborative governance challenged every partner as it took more time and seemed unnecessary. Partners faced the pressure of their own project timelines and bureaucratic processes. For example, ALKFI proposed adding recreation spaces, a public market, health clinic, and livelihood center to Southville 7's development plan. NHA however had to go through the complex process of requesting land use reclassification for such changes, and reporting it to the Commission on Audit. Responsibilities were not clear, slowing progress. Roles and duties of partners were not clearly defined when the project began. There was overlapping of efforts and gaps in implementation. For example, NHA is the lead agency in Southville 7; however, it was not always clear if decisions were to be made at the national or at the local level. NHA cited the lack of coordination as the reason behind the relocation moratorium in 2011, which forced displaced residents from Metro Manila to look for other sites. NGOs worried about what would happen to the vacant housing units they had built and their commitment to donors. Poor coordination and communication affected service delivery. No coordinating agency emerged among the partners. NHA had little experience in working with the private sector, especially in a resettlement project. The same applied to ALKFI, for whom handling such projects was a first. As a result, service delivery was less efficient. Several NGOs conducted their own household surveys, leading to consultation fatigue among residents and inconsistent data. There was competition for community members to join projects and initiatives. Community leaders received multiple and conflicting requests from partners. Some services were not availed because of lack of referrals between agencies. Solutions The grant project piloted a model for strengthening multisector partnerships to support sustainable

development of poor and underserved communities that can be replicated in the Philippines and other countries in Asia and the Pacific. It developed a partnership framework, which is at the core of Southville 7 s success and sustainability. Framework: 12 Steps that Made the Southville 7 Experience a Success STEP 1: Prepare a Conceptual Plan Initiate consultations to identify the problem and propose solutions. Conduct background research. Clearly define the project context. In the Philippines, the relocation site must be climate changeready. STEP 2: Conduct Stakeholder Analysis STEP 3: Set Goals and Objectives Select a proponent and clarify expectations together. Identify stakeholder strengths and expertise. STEP 4: Identify Project Components Hold participatorydynamics consultative with stakeholders to set project goals, keeping in mind Map stakeholder andmeetings relationships. how these would help target beneficiaries. Assess needs to determine the infrastructure and basic utilities required. Consult potential partners to determine services that can be delivered. Prepare a stakeholder analysis to build trust among stakeholders. Objectives should be SMART: specific, measurable, achievable, relevant, and time-bound. A big project with a big scope, like Southville 7, includes infrastructure and livelihood development, microcredit, and capacity building. STEP 5: Develop an Action Plan Map activities on a weekly, monthly, or annual basis with a clear start and end date. Consult with donors and partners to ensure commitments are delivered on time. Identify all linked activities, i.e., those that must be done before the next activity can be started. STEP 6: Engage Target Beneficiaries Involve beneficiaries in project planning. Share information and discuss issues related to the relocation. Ensure coordination between sending and receiving local government units.

A database of relocated families and key data help keep information accessible. STEP 7: Prepare Site for Resettlement Make an inventory of available housing units and their condition. Check water, sanitation, and electricity connections. Do site inspections before physical relocation starts and ask the receiving local government unit to assist as needed. STEP 8: Design a Financial Plan Identify project cost requirements, including management costs. Calculate maintenance expenses. Take into account all cash and in-kind contributions. Include support for regular coordination among stakeholders, as well as bigger informationsharing events like community assemblies and conferences. STEP 9: Coordinate Set up an oversight entity to coordinate regularly with staekholders and agencies and to monitor and discuss issues. Hold regular meetings to get feedback of community members. Make membership inclusive and participatory so that all stakeholders, including community organizations, are given a voice. STEP 10: Ensure Good Communications Design a communications plan, including a feedback mechanism for community members. Establish ways to meet stakeholders face to face regularly. Communications channels keep the partnership transparent, dynamic, and collaborative. Communications also play a key role in promoting project ownership. STEP 11: Monitor and Evaluate

Set baselines, targets, and indicators to measure project success. Conduct surveys to track progress. Report as agreed with partners and assess partnerships regularly. Satisfaction surveys are one way to track program effectiveness. Consider regular reports of key indicators and milestones and tracking worksheets. STEP 12: Ensure Knowledge Transfer Decide how to share challenges, successes, lessons, and innovations from the project to all stakeholders. Seek advice from others with experience. Be attuned to the project s lessons and assess the factors contributing to its success or failure. Examine the good practices. Initiatives that the Southville 7 partners started include: forming a public-private partnership for water, involving homeowners associations; promoting entrepreneurship through livelihood assistance and training; organizing and strengthening homeowners associations; and developing a sustainability plan for Southville 7. Southville 7: Making Resettlement Work discusses the challenges, impacts, and lessons learned from these initiatives in detail. The project helped market vendor Lea Nabor, a Typhoon Ondoy (Ketsana) survivor, and other entrepreneurs in Southville 7 to grow their business by providing livelihood assistance and training. Photo credit: ABS-CBN Lingkod Kapamilya Foundation, Inc.

Numbers and facts 107 hectares Land area, divided into 3 sites Location Municipality of Calauan, Laguna. Southville 7 Sites 1 and 2 are located in Barangay Dayap, and Site 3, in Barangay Sto. Tomas About 5,000 Number of families 10 Number of homeowners associations Results Majority of residents in Southville 7 now have access to clean water through communal water stations that were set up by a public-private partnership between the homeowners associations and Laguna Water District. Video courtesy of ABS-CBN Lingkod Kapamilya Foundation. Employment opportunities increased. Residents applied the skills gained from training activities as employees and as entrepreneurs. Some opted to go to Metro Manila for higher-paying jobs but others were hired in enterprises that set up shop in Southville 7. Delivery of basic services improved. Four years after the project began, 92% of households now enjoy access to either piped water or communal water stations, while 43% have electricity. Facilities in Southville 7 include playgrounds,

daycare, a health clinic, and livelihood center. Voter registration in Calauan and community participation increased. The May 2016 national elections showed registered voters from Southville 7 increased, indicating successful integration into the resettlement site. The 10 homeowners associations in Southville 7 represent their communities in budget and planning sessions of the local government, and women play an active role as heads of homeowners associations, committee members, and entrepreneurs. Lessons Southville 7 has become a model resettlement site, influencing other resettlement efforts, such as in Tacloban City, after super Typhoon Yolanda (Haiyan) in 2013. Groups, including public officials from Myanmar, have visited the site to learn about its resettlement and housing practices. Private sector partners of all sizes bring value. ALKFI invited both small and big companies to invest in Southville 7 and NGO partners, including the Salesians of Don Bosco, Consuelo Foundation, and the Ayala Foundation, also started livelihood development projects. A common vision sets a clear direction for better collaboration. The shared vision of improving lives at Southville 7 united the partners. All NGOs working in Southville 7 are now committed to supporting the community through 2020, having signed a memorandum of agreement at a workshop in March 2016.

The Southville 7 partners agreed to continue supporting the project at the Multisector Partnership Framework Workshop in March 2016. It was attended by NHA, Municipal Government of Calauan, Barangay Dayap, Barangay Santo Tomas, homeowners' associations, and NGOs in the resettlement site: ABS-CBN Lingkod Kapamilya Foundation, Ayala Foundation, Consuelo Foundation, Don Bosco Calauan, Life Project 4 Youth, and Habitat for Humanity. Photo credit: ABS-CBN Lingkod Kapamilya Foundation. All agencies must be involved from the onset and enter the partnership as equals. The municipal and barangay governments were involved from the earliest stages, but better coordination among NHA, ALKFI, and the sending and receiving local governments would have prevented many problems. Consultation and participation take time, but experience suggests they add value. Facilitation by an outsider keeps the focus on community priorities. A third-party facilitator, perceived by all partners as neutral, proved critical to the success of the multistakeholder discussions. The facilitator ensured that inputs of community representatives were placed front and center a process that proved encouraging and empowering. Resources Asian Development Bank (ADB). 2012. Grant Assistance Report - Republic of the Philippines: Promoting Partnerships and Innovation in Poor and Underserved Communities. Manila. ADB. 2016. Southville 7: Making Resettlement Work. Mandaluyong. ADB. Philippines: Promoting Partnerships and Innovation in Poor and Underserved Communities. ABS-CBN Lingkod Kapamilya Foundation. ALKFI, Southville 7 Stakeholders Forge Partnership on Empowered Communities. To visit Southville 7, please contact: Engr. MARIA BELINDA V. SEVALLA

Division Manager A, Southville 7 Housing Project National Housing Authority Mobile: +63 998 9687943, +63 922 8747595 Email: belindasevalla@yahoo.com Engr. Raymund Abad Division Manager A, Laguna National Housing Authority Mobile: +63 998 9687944 Email: ray_abad@yahoo.com For inquiries on how to become a Southville 7 partner, please contact: Leah S. Bautista Operations Manager of Bayanijuan ABS-CBN Lingkod Kapamilya Foundation, Inc. Tel +63 2 4152272, extension 3714 Mobile: +63 937 3753059 Email: LSBautista@abs-cbnfoundation.com Elaine Thomas Social Development Specialist (Civil Society and Participation), Southeast Asia Department, Asian Development Bank Elaine Thomas designs and implements education and health projects in ADB s operations in Southeast Asia. Prior to joining ADB, she was country director for GOAL in Kenya. With over 20 years of development experience, she has also worked in the field in Azerbaijan, Cambodia, The Gambia, Somalia, and South Sudan. Last updated: December 2016