Detroit Renewable Power Consent Judgment Schedule

Similar documents
MICHIGAN DEPARTMENT OF ENVIRONMENTAL QUALITY. June 2, 1997

PETITION FOR DISSOLUTION OF SUMMARY SUSPENSION. , hereinafter referred to as Respondent, by and

MICHIGAN DEPARTMENT OF ENVIRONMENTAL QUALITY

WarmWise Business Custom Rebates Program Manual

REQUEST FOR PROFESSIONAL QUALIFICATIONS

Northern Ireland Social Care Council. NISCC (Registration) Rules 2017

CNL-CNSC Administrative Protocol for the Renewal of the Whiteshell Laboratories Licence and the Proposed In Situ Decommissioning of the WR-1 Reactor

AIR CONDITIONING AND REFRIGERATION Administrative Rules of the Texas Department of Licensing and Regulation 16 Texas Administrative Code, Chapter 75

Managed Care Organization Hospital Access Program Hospital Participation Agreement

Practice Review Guide April 2015

Title 22: HEALTH AND WELFARE

Request for Proposals (RFP) Consulting and Design Services for Solar Photovoltaic Systems for Iowa City Facilities September 22, 2017

Practice Review Guide

ASSE International Seal Control Board Procedures

STANDARD REQUEST FOR QUOTATIONS (SRQ) (CONSULTANCY AND DESIGN)

IN THE CIRCUIT COURT OF MONTGOMERY COUNTY, ALABAMA

STATE OF NEW JERSEY DEPARTMENT OF LAW AND PUBLIC SAFETY OFFICE OF THE ATTORNEY GENERAL

POLICIES AND PROCEDURES MANUAL

1. The local Y shall remain in compliance with Article II, Section 2 of the National Council of YMCAs Constitution (Qualifications for Membership).

NOTICE OF RECEIPT OF REQUEST. Request for Inspection. Nigeria: Lagos Metropolitan Development and Governance Project (P071340)

QRO Operator Certification Renewal Application

WEATHERIZATION ENERGY AUDITOR SINGLE FAMILY. House as a System

PRELIMINARY PLANNING AND DURATION OF PUBLIC-PRIVATE COMPETITIONS (SEC. 937)

(9) Efforts to enact protections for kidney dialysis patients in California have been stymied in Sacramento by the dialysis corporations, which spent

To: Prefectural Governors From: Director General, Pharmaceutical and Food Affairs Bureau, Ministry of Health, Labour and Welfare

THE SURVEY PROCESS THE ALF/SCALF SURVEY PROCESS 1/14/2016. Assisted Living Facilities and. Specialty Care Assisted Living Facilities

MULTIFAMILY UPGRADE CUSTOMER HANDBOOK

HB 2800: Hospital Nurse Staffing Law (document prepared by Oregon Nurses Association, 10/06)

MICHIGAN DEPARTMENT OF ENVIRONMENTAL QUALITY. March 16, 1999

KDOT Procurement Guidelines for STP/CMAQ Funded Planning, Education, and Outreach Projects Effective 10/1/12

ALABAMA DEPARTMENT OF MENTAL HEALTH BEHAVIOR ANALYST LICENSING BOARD DIVISION OF DEVELOPMENTAL DISABILITIES ADMINISTRATIVE CODE

VERIFICATION OF READINESS TO START UP OR RESTART NUCLEAR FACILITIES

SUBCHAPTER 03M UNIFORM ADMINISTRATION OF STATE AWARDS OF FINANCIAL ASSISTANCE SECTION ORGANIZATION AND FUNCTION

City of Boise. Civil Rights Title VI Plan. October 2014

University of Maryland Baltimore. Radiation Safety Procedure

Northeast Power Coordinating Council, Inc. Regional Standards Process Manual (RSPM)

Startup Terrace 2018 Selection Award. Application Guide

1303A West Campus Drive

AIR CONDITIONING AND REFRIGERATION

Understanding the Grievances and Appeals Process for Medicaid Enrollees

EMERGENCY COMMUNICATIONS SYSTEM MAINTENANCE AGREEMENT BETWEEN THE MARIN EMERGENCY RADIO AUTHORITY (MERA) AND THE COUNTY OF MARIN (2005)

DOD MANUAL DOD ENVIRONMENTAL LABORATORY ACCREDITATION PROGRAM (ELAP)

Investigative Unit Operations Plan

BEFORE THE ENVIRONMENTAL QUALITY COUNCIL F I LED STATE OF WYOMING EQC DOCKET NO JUN ) ) ) ) ) )

Incentive Guidelines Knowledge Transfer

Comprehensive Counseling & Consulting, LLC

RULES OF PROCEDURE FOR CALIBRATION LABORATORY ACCREDITATION

POCKET GUIDE TO THE ACCREDITATION STANDARDS (ISO 15189:2014)

Base Year - July 01, 2016 June 30, 2017, with optional renewal at Board s sole. (520)

may request a second opinion from the MCCMH Executive Director.

DEPARTMENT OF THE NAVY HEADQUARTERS UNITED STATES MARINE CORPS WASHINGTON, DC MCO MPL:cms 25 Apr 1986

UNIVERSITY OF PITTSBURGH SCHOOL OF NURSING ACADEMIC POLICIES AND PROCEDURES FOR THE UNDERGRADUATE AND GRADUATE PROGRAMS

Guidelines on Occupational Safety and Health Management Systems Ministry of Labour Notification No. 53, April 30, 1999

NOTE BY THE DIRECTOR GENERAL PROGRESS IN THE ELIMINATION OF THE SYRIAN CHEMICAL WEAPONS PROGRAMME

GOVERNMENT OF THE RUSSIAN FEDERATION. DECREE of December 27, 2012 N On the Rules STATE REGISTRATION OF MEDICAL PRODUCTS

CHIEF NATIONAL GUARD BUREAU INSTRUCTION

Terms of Reference and Call for Submissions. 26 March 2018

COMMISSION IMPLEMENTING REGULATION (EU)

Template Language for Memorandum of Understanding between Duals Demonstration Health Plans and County Behavioral Health Department(s)

Early Education and Care Voucher Services Agreement Summer Camps 2018

PANAMA MARITIME AUTHORITY MERCHANT MARINE CIRCULAR MMC-365

Ladysmith School District. Indoor Environmental Quality Management Plan

Directive for the Austrian JI/CDM Programme

Page 1 of 5 ADMINISTRATIVE POLICY AND PROCEDURE

NC General Statutes - Chapter 90A Article 2 1

APPLICATION MANUAL MINISTRY OF REGIONAL DEVELOPMENT AND PUBLIC WORKS. PHARE National Programme 2004 III part

MEMORANDUM OF UNDERSTANDING LEGAL AID ONTARIO ("LAO") and. COMMUNITY LEGAL CLINIC (the "Clinic")

GUIDELINES FOR BUSINESS IMPROVEMENT GRANT PROGRAM BY THE COLUMBUS COMMUNITY & INDUSTRIAL DEVELOPMENT CORPORATION

Review of Invoice Processing Controls - Wackenhut s Security Services Contract

ACCREDITATION PROCESS FOR TESTING/ CALIBRATION/ MEDICAL LABORATORIES

CITY OF MOBILE REQUEST FOR PROPOSAL TRANSIT MANAGEMENT SERVICES

Case 1:18-cv Document 1 Filed 03/12/18 Page 1 of 12 IN THE UNITED STATES DISTRICT COURT FOR THE DISTRICT OF COLUMBIA

CHAPTER 37 - BOARD OF NURSING HOME ADMINISTRATORS SUBCHAPTER 37B - DEPARTMENTAL RULES SECTION GENERAL PROVISIONS

Department of Defense DIRECTIVE

8. Provider Rights and Responsibilities

DEPARTMENT OF THE NAVY OFFICE OF THE SECRETARY 1000 NAVY PENTAGON WASHINGTON, DC

Request for Qualifications Architectural Analysis Programming and Planning for the Clear Creek County Courts Wing Remodel Project Georgetown, Colorado

Office of Business and Financial Services Procurement and Contracts Division Section SUBJECT: PROCUREMENT OF CONSTRUCTION SERVICES

PRIVACY MANAGEMENT FRAMEWORK

CHIEF EXECUTIVE OFFICER ATHI WATER SERVICES BOARD P.O BOX NAIROBI

Notification and Federal Employee Antidiscrimination and Retaliation Act (NoFEAR) Fiscal Year 2016 Report

APPLICATION FOR LEGAL SERVICES CONTACT INFORMATION

Okla. Admin. Code 340: : Purpose. Okla. Admin. Code 340: : Definitions [REVOKED] Okla. Admin.

SECTION 4. Construction Site Runoff Control Program

7700 East First Place Denver, CO ph (303) fax (303)

CERTIFICATES OF FITNESS

Center for Clinical Standards and Quality /Survey & Certification

Adult Protective Services Referrals Operations Manual. Developed by the Department of Elder Affairs And The Department of Children and Families

Revised Michigan PTI Application Review Process

Alaska Department of Education and Early Development (DEED) and The Council for the Accreditation of Educator Preparation (CAEP) Partnership Agreement

FIRST 5 LA GRAPHIC DESIGN VENDOR REQUEST FOR QUALIFICATIONS (RFQ)

MILPERSMAN (901) NAVPERSCOM CUSTOMER SERVICE CENTER. (a) NAVSO P-6034, Joint Federal Travel Regulations (JFTR)

STATE OF NORTH CAROLINA UTILITIES COMMISSION RALEIGH DOCKET NO. E-2, SUB 1089 ) ) ) ) ) )

Department of Defense DIRECTIVE. Inspector General of the Department of Defense (IG DoD)

THIS AGREEMENT made effective this day of, 20. BETWEEN: NOVA SCOTIA HEALTH AUTHORITY ("NSHA") AND X. (Hereinafter referred to as the Agency )

Early Education and Care Voucher Services Agreement Summer Camps 2017

Training Regulation: Trainee Agreement

SUPPORTED LIVING PROVISION OF IN-HOME SUBSIDIES FOR PERSONS IN SUPPORTED LIVING ARRANGEMENTS

Northeast Power Coordinating Council, Inc. Regional Standard Processes Manual (RSPM)

PROVIDENCE HOSPITAL. Washington, D.C. SAMPLE RESIDENT CONTRACT FOR FAMILY MEDICINE

Transcription:

Michigan Department Of Environmental Quality - Air Quality Division Detroit Renewable Power Consent Judgment Schedule Revised 8/3/2018 The Consent Judgment (CJ) was entered in court on October 20, 2014. In the CJ, Detroit Renewable Power (Company) is required to meet the following time line: RDF Control Program and Installation Schedule 1. On or before 10/20/14, the Company shall in a signed writing notify the AQD Detroit District Supervisor that a contract for engineering services to design a system for controlling odors from the RDF Storage Building and RDF Conveyor Gallery (hereinafter referred to as the "RDF Control System") has been awarded. The RDF Control System shall include fans, air dampers, plenums, ductwork, and associated equipment that will collect exhaust air from the RDF Storage Building and RDF Conveyor Gallery and convey the air directly to the stoker boiler forced draft fan combustion air intakes. (CJ paragraph 3.1) Milestone: On 10/22/2014, the company notified the Detroit District Supervisor that they awarded a contract for engineering services to design the RDF control System on 10/15/14. RDF Odor Neutralization System and MSW Odor Control Plan 2. On or before 10/20/14, the Company shall have retained a qualified third party to evaluate the odor neutralizer spray system in the RDF Storage Building and shall have completed appropriate improvements or upgrades. & (CJ paragraph 3.10) 3. No later than 11/19/14, (within 30 days after the Effective Date), the Company shall notify the AQD Detroit District Supervisor in writing that the improvements and/or upgrades have been completed. (CJ paragraph 3.11) Milestone: On 10/29/2014, the company notified the Detroit District Supervisor that they retained Delray Mechanical Corporation to evaluate the odor neutralizer spray system in the improvements to the odor neutralizer system in the RDF Storage Building; & Delray Mechanical Corporation completed improvements to the odor neutralizer spray system on 7/15/14. 4. No later than 11/19/14, (within 30 days after the Effective Date), the company shall develop an odor control plan, which include the following (CJ paragraph 3.11, 3.12, 3.13, 3.14, 3.15, & 3.16): a. To properly operate the waterless odor neutralizer system in the RDF processing area from April 15 through October 15 of each year during the term of this Consent Judgment b. To properly operate the wet odor neutralizing system for the MSW processing area from April 15 through October 15 of each year during the term of this Consent Judgment c. To clean the solid waste receiving tipping floor, pit area, and processing equipment on a daily basis, or more often if required, such that odor from these sources is minimized, in compliance with the ROP No. MI-ROP-M4148-2011; D. Flexible Group Conditions FGMSWPROC-Lines 1

d. To take any and all actions necessary to control odorous emissions from the Facility to comply with Rule 901 in the event of a mechanical failure lasting more than 24 hours that prevents the processing of the MSW into RDF or utilization of the RDF as fuel for the boilers. Milestone: On 11/6/2014, the company met with AQD staff & presented the Odor Management Plan which included the above items. Odor Management Plan 5. No later than 12/6/14, (within 30 days after AQD receives the revised Odor Management Plan from the Company), AQD shall notify the Company in writing as to whether the submitted changes are approved or rejected. (CJ paragraph 3.16) Milestone: On 11/24/2014, AQD sent a letter to the company requesting the company to amend the odor control plan to make it precise & clear. Furthermore, AQD requested the company to submit the revised odor control plan by 12/15/14. On 12/15/14, AQD received the company s revised Odor Management Plan. On 1/13/15, AQD approved the revised Odor Management Plan of 12/15/2014. RDF Control Program and Installation Schedule 6. No later than 4/1/15, (within 160 days after the Company submits the notification required by CJ paragraph 3.1), the Company shall submit to the AQD Detroit District Supervisor detailed engineering plans and specifications that depict the design of the RDF Control System. (CJ paragraph 3.2) Milestone: On 1/9/15, 2/10/15, & 3/10/15, the company updated the AQD about the Odor Reduction Project. The company anticipates they are on schedule to submit detailed plans and specifications as required by the consent judgment schedule. On 3/31/2015, the company submitted a detailed engineering plans and specifications that depicted the design of the RDF Control System. 7. If the company submits the engineering plan on 4/1/15, no later than 5/1/15 (within 30 days after the Company submits the plans and specifications required by CJ paragraph 3.2), the Company shall notify the AQD Detroit District Supervisor in a signed writing that a contract for construction of the RDF Control System has been awarded. (CJ paragraph 3.3) Milestone: On 4/28/15, the company submitted in writing that a contract for construction of the RDF Control System has been awarded. 8. If the company notifies AQD Detroit District Supervisor that a contract for construction has been awarded on 5/1/14, no later than 7/1/15 (within 60 days after the Company submits the notification required by CJ paragraph 3.3), the Company shall begin on-site construction of the RDF Control System and shall notify the AQD Detroit District Supervisor in writing that construction has begun. (CJ paragraph 3.4) 2

Milestone: On 6/27/15, the company informed the AQD in writing that DRP had begun on-site construction of the RDF Control System. 9. If the company notifies AQD that they begin on-site construction of RDF control system on 7/1/15, no later than 1/27/16 (within 210 days after the Company submits the notification required by CJ paragraph 3.4), the Company shall have completed the construction of the RDF Control System, shall have connected the RDF Control System to one or more of the three existing boilers at the facility (Boiler No. 11, Boiler No. 12, and/or Boiler No. 13), and shall notify the AQD Detroit District Supervisor in writing that initial operation of the system has commenced. (CJ paragraph 3.5) Milestone: On 1/22/16, the company informed AQD in writing that DRP has completed the construction of the RDF Control System, & has connected the RDF Control System to one or more of the three existing boilers at the facility. 10. If the company notifies AQD that initial operation of the system has commenced on 1/27/16,) no later than 7/25/16 (within 180 days after the Company submits the notification required by CJ paragraph 3.5), the Company shall have connected the RDF Control System to the remaining boilers at the facility and shall notify the AQD Detroit District Supervisor in writing that all three boilers have been connected. (CJ paragraph 3.6) Milestone: On 7/20/16, the company informed the AQD in writing that DRP connected the remaining boilers to the RDF Control System. 11. If the company notifies AQD that all three boilers have been connected, no later than 9/23/16 (within 60 days after the Company submits the notification required by CJ paragraph 3.6), the Company shall have completed the integration of the controls for the RDF Control System into stoker boiler combustion controls in the existing Distributed Control System and shall notify the AQD Detroit District Supervisor in writing that integration of the RDF Control System has been completed. (CJ paragraph 3.7) Milestone: On 9/20/16, the company informed the AQD in writing that integration of the controls for the RDF Control System has been completed. RDF Control System Verification 12. If the company notifies AQD that integration of the RDF Control System has been completed on 9/23/16,) no later than 10/23/16 (within 30 days after the Company submits the notification required by CJ paragraph 3.7), the Company shall conduct testing to reasonably determine that the RDF Control System has been constructed and is operating as designed. Testing under this paragraph shall be conducted in accordance with the following sub-paragraphs (CJ paragraph 3.8): a. A qualified engineer shall examine the RDF Control System and verify in writing in a signed writing that the system has been constructed in accordance with the engineering plans and specifications submitted pursuant to CJ paragraph 3.2. Within ten (10) days of the date of the signed writing by the qualified engineer, a copy of that signed writing shall be forwarded to the DEQ, AQD, Detroit Field Office, Detroit District Supervisor. Examination and verification shall include the integrity and sealing of system ductwork and plenums; closure and/or control of 3

openings in the RDF Storage Building and RDF Conveyor Gallery; calibration of flow measurement instrumentation; and a functional test of the Distributed Control System. b. A qualified third party contractor shall conduct performance testing (per USEPA Methods in Title 40 Code of Federal Regulation Part 60, Appendix A-1) to verify that the RDF Control System collects exhaust air from the RDF Storage Building and RDF Conveyor Gallery and conveys the air to the stoker boiler forced draft fan combustion air intakes. Performance testing shall be conducted during normal operation of the system over a period of not less than one hour and shall consist of air flow measurements at RDF Storage Building and RDF Conveyor Gallery exhaust air collection inlets to verify that the RDF Control System operates as specified on the engineering plans and specifications. The testing shall specify the number of boilers in service when the air flow is measured. Milestone: The company informed the AQD in writing that a qualified engineer has examined the RDF control system and verified that the system has been constructed in accordance with the engineering plans and specifications. The correspondence included performance testing results verifying that the RDF Control System collects exhaust air from the RDF Storage Building and RDF Conveyor Gallery and conveys air to the to the boiler forced draft fan combustion air intakes. 13. If the company notifies AQD that the Company shall conduct testing to reasonably determine that the RDF Control System has been constructed and is operating as designed on 10/23/16, no later than 11/22/16 (within 30 days after completion of the testing required by CJ paragraph 3.8), the Company shall submit a written report of the testing to the AQD Detroit District Supervisor. The report shall document the examinations and measurements required by CJ paragraph 3.8 and shall verify that RDF Control System is constructed in accordance with the engineering plans and specifications and is operating as designed. (CJ paragraph 3.9) Milestone: A written report dated October 28, 2016 was received by the AQD. The report documents the examinations and measurements required by CJ paragraph 3.8 and includes verification that the RDF Control System is constructed in accordance with the engineering plans and specifications and is operating as designed. Additional Measures 14. If the company submits the report of examinations & measurements of the RDF control system performance on 11/22/16), No later than 11/22/18 (within two (2) years after the Company submits the written report required by CJ paragraph 3.9), AQD makes the determination of the odor control measures from the facility. AQD may provide written notice of its determination to the Company. The written notice shall state, based on available information: (i) the number and type of odor complaints received by AQD and attributed to operation of the Facility, (ii) the estimated time duration of each odor incident that AQD alleges constituted a violation of Rule 901, (iii) field observations of each odor incident that AQD alleges constituted a violation of Rule 901, and (iv) the basis for AQD s belief that the odors were from the Facility. (CJ paragraph 3.17) Milestone: A written Notice of Determination of Necessity for Additional Measures was provided to the company s attorney on July 31, 2018. The written notice states that the measures described in Section III of the Consent Judgement have proven insufficient to control odors from the facility. The notice included, the number and type of odor complaints received by the AQD and attributed to 4

operation of the facility, the estimated time duration of each odor incident, field observations of each odor incident that the AQD alleges constituted a violation of Rule 901, and the basis for AQD s determination that the odors are attributable to the facility. 15. If the Company does not dispute the AQD s determination, the Company shall comply with the subparagraphs below. If the Company disputes the AQD s determination, the Parties shall resolve the dispute pursuant to Section V of this Consent Judgment, and the Company shall be required to comply with subparagraphs a. and b. below only in the event, and to the extent that, the Company does not prevail on the dispute. (CJ paragraph 3.18): a. If AQD provides written notification on 11/22/18, no later than 2/21/19 (within 90 days after receiving the written notice specified in CJ paragraph 3.18 or receiving a final decision from the Court on a petition for resolution, as applicable), the Company shall submit to the AQD Detroit District Supervisor (i) plans and/or operational commitments that describe additional measures for controlling odors from the Facility; and (ii) a schedule for review and approval by AQD for implementing the plans and/or commitments. (CJ paragraph 3.18a) b. If the Company submits the plan for additional measures for controlling odors from the facility on 2/21/19, no later than 3/23/19 (within thirty (30) days after completing the implementation of plans and/or commitments specified in CJ paragraph 3.18a above), the Company shall notify the AQD Detroit District Supervisor in writing that the plans and/or commitments have been implemented. (CJ paragraph 3.18b) 5