CNL-CNSC Administrative Protocol for the Renewal of the Whiteshell Laboratories Licence and the Proposed In Situ Decommissioning of the WR-1 Reactor

Similar documents
Canada. Record of Decision. In the Matter of. University of Alberta. Applicant

Life Extension of Nuclear Power Plants

Canada. Record of Proceedings, Including Reasons for Decision. In the Matter of. Applicant. Atomic Energy of Canada Limited

SRP-2.01-SP-11NNNN-026

MEMORANDUM OF UNDERSTANDING (MOU) BETWEEN THE CANADIAN NUCLEAR SAFETY COMMISSION AND ENVIRONMENT CANADA

Minutes of the Canadian Nuclear Safety. Commission (CNSC) Meeting held on. January 26, 2017

Minutes of the Canadian Nuclear Safety. Commission (CNSC) Meeting held on. September 21 and 22, 2016

An Overview of the Canadian Nuclear Safety Commission

Record of Proceedings, Including Reasons for Decision

Nuclear Regulatory Compliance: Enhancing Safety and Security Through a Clear Regulatory Framework

Plan NK38 PLAN I ;W;'s

Certification of Persons Working at Nuclear Power Plants

MEMORANDUM OF UNDERSTANDING BETWEEN THE CANADIAN NUCLEAR SAFETY COMMISSION AND HEALTH CANADA

CANADIAN NUCLEAR SAFETY COMMISSION S RISK BASED APPROACH TO REGULATING FUEL FACILITIES IN CANADA

Record of Proceedings, Including Reasons for Decision

ASSE International Seal Control Board Procedures

Proposed Amendments to Regulations Made Under the Nuclear Safety and Control Act. Discussion Paper DIS-13-02

RULES OF PROCEDURE FOR TESTING LABORATORY ACCREDITATION

Nuclear in a Low-Carbon Future:

VERIFICATION OF READINESS TO START UP OR RESTART NUCLEAR FACILITIES

IAEA Safety Standards for Regulatory Bodies Overview and Recent Development

Office for Nuclear Regulation (ONR) Quarterly Site Report for Springfields Fuels Limited

Overview of the Regulatory Framework for the Safety of Nuclear Power Plants in Romania

Department of Defense INSTRUCTION. Occupational Ionizing Radiation Protection Program

Standard Operating Procedures for Processing Municipal and Residual Waste General Permit Applications. Bureau of Waste Management

RULES OF PROCEDURE FOR CALIBRATION LABORATORY ACCREDITATION

Fundamental Principles

NRC INSPECTION MANUAL IRIB

Radiation Safety Code of Practice

Bureau of Waste Management

Detroit Renewable Power Consent Judgment Schedule

Security Programs for Category I or II Nuclear Material or Certain Nuclear Facilities

Nuclear Law and Malaysian Legal Framework on Nuclear Security AISHAH BIDIN FACULTY OF LAW UKM

PRIMARY MEDICAL CARE/PRIMARY CARE NETWORKS CONSULTATION AGREEMENT BETWEEN

Inspector Training and Qualifications Program

Measures to Strengthen International Co-operation in Nuclear, Radiation and Transport Safety and Waste Management

REGULATORY DOCUMENTS. The main classes of regulatory documents developed by the CNSC are:

DOD MANUAL DOD ENVIRONMENTAL LABORATORY ACCREDITATION PROGRAM (ELAP)

THE IAEA FUKUSHIMA REPORT AND THE IMPLICATIONS FOR NUCLEAR SAFETY AND EMERGENCY PREPAREDNESS

TANZANIA CIVIL AVIATION AUTHORITY AERODROMES AND AIR NAVIGATION SERVICES. Foreword

Radiotherapy Licence Application Form

NRC Public Meeting October 27, 2014

Licensing of Nuclear Installations

COMMISSION IMPLEMENTING REGULATION (EU)

MDUFA Performance Goals and Procedures Process Improvements Pre-Submissions Submission Acceptance Criteria Interactive Review

MISSION REPORT ON THE INTEGRATED NUCLEAR INFRASTRUCTURE REVIEW (INIR)

DIRECTIVES. COUNCIL DIRECTIVE 2009/71/EURATOM of 25 June 2009 establishing a Community framework for the nuclear safety of nuclear installations

Human Performance Management Personnel Certification: Exposure Device Operators REGDOC-2.2.3

BY-LAW #3 (Under Section 40(2) of The Medical Act)

Memorandum of Understanding between MHRA and the General Pharmaceutical Council

REQUEST FOR PROPOSAL INDEPENDENT CONSULTANT EXPERT OYSTER CREEK SAFETY ADVISORY PANEL

Procurement Processes Policy

INTEGRATED REGULATORY REVIEW SERVICE (IRRS)

The Characteristics of an Effective Nuclear Regulator

Topical Peer Review 2017 Ageing Management of Nuclear Power Plants

Françoise De Bois,, VP Nuclear Safety & Licensing, Reactors & Services, AREVA. April 21 st, 2015

NOT PROTECTIVELY MARKED

ANNEX Q HAZARDOUS MATERIALS EMERGENCY RESPONSE

LEGISLATIVE ACTS AND OTHER INSTRUMENTS COUNCIL DIRECTIVE establishing a Community framework for the nuclear safety of nuclear installations

Commission canadienne de sûreté nucléaire. Canadian Nuclear Safety Commission. 9BMinutes of the Canadian Nuclear Safety

INTEGRATED REGULATORY REVIEW SERVICE (IRRS)

Standard Operating Procedure (SOP) 1 for Chapter 105 Dam Safety Program Review of Chapter 105 New Dam Permit November 2, 2012

MEMORANDUM OF UNDERSTANDING LEGAL AID ONTARIO ("LAO") and. COMMUNITY LEGAL CLINIC (the "Clinic")

Summary Decision. In the Matter of. Ontario Power Generation Inc.

Policy for Special Rate/Charge Schemes in Retail/Commercial Precincts or Centres April 2014

Record of Proceedings, Including Reasons for Decision

Periodic Review. Quick and easy guidance on the when and how to update your comprehensive plan

Radiation Protection Program Updates

Practice Review Guide April 2015

AC291 Special Inspection Agencies ACCREDITATION CRITERIA FOR IBC SPECIAL INSPECTION AGENCIES AC291

DOE B, SAFEGUARDS AGREEMENT WITH THE INTERNATIONAL ATOMIC SYMBOL, AND OTHER CHANGES HAVE BEEN BY THE REVISIONS,

SERVICE LEVEL AGREEMENT: University of Arkansas for Medical Sciences OFFICE OF SPONSORED PROGRAMS ADMINISTRATIVE NETWORK (OSPAN)

AGREEMENT BETWEEN DEPARTMENT OF DEFENSE, DEPARTMENT OF THE AIR FORCE, AND MARIAH PHASE 2 ENERGY HOLDINGS LLC

Regulatory inspection of nuclear facilities

GDUFA II: Requests for Reconsideration

COMPLIANCE WITH THIS PUBLICATION IS MANDATORY

Department of Defense Human Research Protection Program DOD INSTITUTIONAL AGREEMENT FOR INSTITUTIONAL REVIEW BOARD (IRB) REVIEW (IAIR)

NUCLEAR EMERGENCY MANAGEMENT IN CANADA AND THE UNITED STATES

Assessment of the readiness of the GDA Requesting Party (RP) and ONR to commence GDA

INTEGRATED REGULATORY REVIEW SERVICE (IRRS)

Fingerprinting and Criminal History Records Check Requirements for Unescorted Access to Certain Radioactive Material

201 KAR 26:171. Requirements for supervision.

Regulatory Approach for License Renewal for Commercial Nuclear Power Reactors in the USA

IAEA SAFETY STANDARDS SERIES. GENERAL SAFETY REQUIREMENTS No. GSR Part 1 (Rev.1)

Practice Review Guide

Last updated on April 23, 2017 by Chris Krummey - Managing Attorney-Transactions

PART I - NURSE LICENSURE COMPACT

REQUEST FOR PROPOSALS RFP No IBM Software Subscription and Support Renewal

Regulatory challenges in nuclear safety

Delayed Federal Grant Closeout: Issues and Impact

SPECIFICATION 13.BRAND TLD PROVISIONS

Accelerated Translational Incubator Pilot (ATIP) Program. Frequently Asked Questions. ICTR Research Navigators January 19, 2017 Version 7.

REQUEST FOR PROPOSALS RFP No IBM Software Subscription and Support Renewal

(a) Article 1. Awards Covered by Research General T&Cs. REFERENCE: ARTICLE 2(a)

General Contractor Services - Small Projects

LCA Escalation Policy. April 2013

Universal Safety Oversight Audit Programme Continuous Monitoring Manual

General Permit Number. Description

Minutes of the Canadian Nuclear Safety. Commission (CNSC) Meeting held on. May 9, 2017

Record of Proceedings, Including Reasons for Decision

Transcription:

CNL-CNSC Administrative Protocol for the Renewal of the Whiteshell Laboratories Licence and the Proposed In Situ Decommissioning of the WR-1 Reactor May 2017 e-doc 5072448

CCM: 2017-000087 e-doc 5072448 Table of Contents Preamble... 4 Purpose... 5 Part I - Framework... 6 1. Parties... 6 2. Duration... 7 3. Communication/timing... 7 4. Issue resolution... 8 5. Reporting... 8 6. External communications... 9 7. Future revisions... 9 Part II Requirements for the renewal of the Whiteshell Laboratories decommissioning licence and the proposed In Situ decommissioning of the WR-1 Reactor... 10 1. Environmental assessment... 10 2. Licence renewal application... 10 3. Details added as project progresses... 10 Part III Approval by signatories... 11 CNL-CNSC Administrative Protocol for the Renewal of the Whiteshell Laboratories Licence and the Proposed In Situ Decommissioning of the WR-1 Reactor Page 2 of 11

Summary of Changes Section Change Date Decommissioning of the WR-1 Reactor Page 3 of 11

CNL-CNSC Administrative Protocol for the Renewal of the Whiteshell Laboratories Licence and the Proposed In Situ Decommissioning of the WR-1 Reactor Preamble Canadian Nuclear Laboratories (CNL) is decommissioning the Whiteshell Laboratories (WL), located near Pinawa, Manitoba, under Nuclear Research and Test Establishment Decommissioning Licence NRTEDL-W5-8.04/2018, which expires December 31, 2018. The decommissioning approach for the site, which was approved by the Commission in 2002, is set out in volume one (program overview) of twelve of the Whiteshell Laboratories Detailed Decommissioning Plan. With this licence renewal, CNL is proposing 1 to change the previously approved decommissioning approach for the WR-1 reactor from complete dismantlement to an approach referred to as in situ decommissioning and to accelerate the decommissioning timelines associated with the rest of the site. This would result in advancing site closure to 2024/2025. However, the current licence does not authorize in situ decommissioning of the WR-1 reactor, or any activities associated with this approach. While accelerating the decommissioning schedule does not require a change to the authorized activities permitted by the licence, in situ decommissioning of the WR-1 reactor was not being considered when the decommissioning licence was issued in 2002, or when the licence was renewed in 2008. This approach was also not considered in the environmental assessment (EA) comprehensive study report that was conducted in support of the application for a decommissioning licence in March 2001. CNL has indicated that it plans to: advance decommissioning and site closure to 2024/2025 remove buildings, spent nuclear fuel and radioactive materials as described by the current decommissioning plans with the exception of the subsurface components of building B100 containing the WR-1 reactor manage wastes arising from decommissioning as described by current decommissioning plans with the exception of wastes associated with in situ decommissioning of the WR-1 reactor conduct in situ decommissioning of the WR-1 reactor by filling subsurface voids with a concrete-based grout, demolishing above-surface portions of building B100 and covering the remaining monolith with an engineered cap In relation to in situ decommissioning of the WR-1 reactor, Canadian Nuclear Safety Commission (CNSC) staff have determined, in accordance with the Canadian Environmental Assessment Act, 2012 and the Nuclear Safety and Control Act and their associated regulations, that an EA and a licensing decision to authorize this new decommissioning approach are required. 1 As defined in the CNL document, In Situ decommissioning of the WR-1 Reactor at the Whiteshell Laboratories Site, WLDP-03700-ENA-001, Revision 0, April 2016, e-doc 4997341. Decommissioning of the WR-1 Reactor Page 4 of 11

Commission approval of the EA is required to allow the CNSC to consider the licensing application for in situ decommissioning of the WR-1 reactor, which would be heard in the context of a licence renewal hearing for the Whiteshell Laboratories. CNSC staff have determined that the EA should be heard by the Commission immediately prior to the hearing for the licence renewal planned for fall 2018. The hearing to consider the EA should be heard during the same Commission proceeding. However, the decision related to the scheduling of the Commission s proceeding will be determined by the Secretariat at a later date. In relation to licence renewal, it is anticipated that if granted, the renewed licence would cover the period through to site closure and, consequently, the activities associated with Phase 3 of the existing decommissioning program. It will not cover the post-closure period (i.e., institutional control). To facilitate the preparation and review of documents required for these two decisions, the CNSC and CNL have mutually decided to formally document the various steps in this administrative protocol. Important note Nothing in this protocol fetters the powers, duties or discretion of CNSC designated officers, CNSC inspectors or the Commission respecting regulatory decisions or regulatory actions. Also, this protocol does not change in any way any applicable laws or regulations, application requirements or hearing process as set by the CNSC Rules of Procedure 2. Purpose The purpose of this protocol is to outline the administrative framework, milestones and service standards for the EA and licensing activities in relation to the renewal of the Whiteshell Laboratories decommissioning licence and the proposed in situ decommissioning of the WR-1 reactor, CNL s submission of the technical information associated with the licence renewal application, and the CNSC s review of this technical information. This protocol aims to provide efficient project management for the regulatory review of information submitted by CNL associated with these two proposals. The milestones included in this document have been established using a number of assumptions, some of which relate to the activities of project participants who are not signatories to this protocol. If events unfold differently from what has been assumed in this protocol, the milestones will be revised accordingly. The remainder of this protocol is divided into three parts: Part I Definition of the framework (parties, duration, communication/timing, issue resolution, reporting, external communications and future revisions) Part II Requirements for the renewal of the Whiteshell Laboratories licence and the proposed in situ decommissioning of the WR-1 reactor Part III Approval by signatories Appendix A to this protocol specifies timelines for CNSC staff review of the EA and licensing submissions 2 Canadian Nuclear Safety Commission Rules of Procedure, SOR/2000-211. Decommissioning of the WR-1 Reactor Page 5 of 11

Part I - Framework 1. Parties The signatories to this protocol have the following roles and responsibilities: The CNSC is the responsible authority under the Canadian Environmental Assessment Act, 2012 for the proposed in situ decommissioning of the WR-1 reactor and is responsible for making a recommendation to the Commission for the EA under this act. The CNSC has regulatory and statutory responsibilities under the Nuclear Safety and Control Act and its regulations. The CNSC is responsible for assessing the application from CNL for the renewal of the Whiteshell Laboratories licence and the proposed in situ decommissioning of the WR-1 reactor, and for making a recommendation to the Commission. CNL is the licensee for the Whiteshell Laboratories decommissioning licence. CNL is responsible for submitting adequate and complete information associated with the renewal of the Whiteshell Laboratories licence and the proposed in situ decommissioning of the WR-1 reactor, per regulatory requirements. Managers For this protocol, the following managers represent each party: Program Supervisor, Directorate of Nuclear Cycle and Facilities Regulation, CNSC Manager, Whiteshell Laboratories Licensing & Quality Management, CNL The CNSC and CNL will identify an alternate if a primary manager is unavailable Executive Management Committee The CNSC and CNL will form an Executive Management Committee composed of senior management representatives who will receive and review progress reports and resolve issues. The members of the Executive Management Committee are: Director General, Directorate of Nuclear Cycle and Facilities Regulation, CNSC Director General, Directorate of Environmental and Radiation Protection and Assessment, CNSC Vice-President, Decommissioning and Waste Management, CNL Whiteshell Laboratories Site Head and General Manager Head, Whiteshell Laboratories Decommissioning and Waste Management The CNSC and CNL will identify an alternate if a primary Executive Management Committee member is unavailable. Decommissioning of the WR-1 Reactor Page 6 of 11

2. Duration This protocol will come into effect on the date of the last signature. It will terminate on the latter date that the Commission announces its EA and licensing decisions on the renewal of the Whiteshell Laboratories licence and the proposed in situ decommissioning of the WR-1 reactor. 3. Communication/timing As stated previously, the CNSC has determined that Commission approval is required to authorize the renewal of the Whiteshell Laboratories decommissioning licence and the proposed in situ decommissioning of the WR-1 reactor. CNL therefore needs to conduct an EA for the proposed in situ decommissioning. It must also submit the required documentation associated with the licence renewal application for consideration by CNSC staff in order to make a recommendation to the Commission and for the Commission to make a decision. This documentation includes but is not limited to: Information associated with the proposed in situ decommissioning of the WR-1 reactor an environmental impact statement for the project, which includes both an operational and post-closure safety analysis report a revised Whiteshell Laboratories Detailed Decommissioning Plan Volume 1 - Overview Program (or addendum) a revised Whiteshell Laboratories Detailed Decommissioning Plan Volume 6 - Whiteshell Reactor #1: Building 100 Information associated with the licence renewal information required by sections 3, 5, 6, 7 and 15 of the General Nuclear Safety and Control Regulations information required by sections 3 and 7 of the Class I Nuclear Facilities Regulations a regulatory compliance matrix associated with the licence renewal for the Whiteshell Laboratories any new or revised (with changes identified) operational programs that are relevant to the activities associated with in situ decommissioning of the WR-1 reactor To meet the agreed upon deliverables as scheduled in appendix A to the protocol, CNL will need to submit complete, sufficient and high-quality information to CNSC staff as early as possible. This will allow adequate time for the CNSC staff review and satisfactory resolution of issues. In addition to this correspondence, the parties will meet as necessary to clarify intentions and facilitate mutual understanding, with the aim of achieving the targets. Within three working days of receiving technical information submitted by CNL under this protocol, CNSC staff will first perform a cursory review (for conformity with the information requirements of content sufficiency and completeness) to identify any obvious deficiencies and communicate any such problems to CNL. Decommissioning of the WR-1 Reactor Page 7 of 11

CNSC staff will prepare and submit their Commission member document (CMD) to the Commission Secretariat according to the timeline in appendix A to the protocol, on the basis that CNL has been proactive in submitting the information outlined in this protocol and that CNSC staff have deemed this information complete and sufficient, such that by the time CNSC staff prepare their CMD: CNSC staff have had sufficient time to perform their review all technical issues have been resolved 4. Issue resolution The parties to this protocol will make their best efforts to resolve any differences of opinion in the interpretation or application of this protocol in an effective and timely manner. The following review and dispute resolution mechanism will be used during the review to assist timely completion. Step 1: Issue identification It is the intention of both parties to resolve issues related to the submission of the technical information and the regulatory review through direct discussions and collaboration between the managers. The managers will hold monthly meetings to review progress and highlight any potential major issues or disputes. Additional meetings may be called for urgent matters as required. If an issue cannot be resolved at this level, the managers will document the situation (typically with a brief factual summary of the issue and a paragraph representing each organization s view) and forward it to the Executive Management Committee within three working days of the impasse. Step 2: Meeting of Executive Management Committee Where the managers cannot resolve an issue, the Executive Management Committee agrees to meet within three working days of notification of the dispute, with the intention of expeditiously resolving the impasse. Issue resolution is to be documented by the Committee. If an issue cannot be resolved at this level, it will be referred to the protocol signatories within three working days of the Executive Management Committee s meeting, supported by the original or revised documentation from step 1. Step 3: Meeting of signatories to this protocol If an issue remains unresolved after step 2, it will be referred with documentation to the signatories to this protocol for resolution. A meeting will be called, typically within five working days, to resolve the issue and document its resolution. 5. Reporting The managers will jointly produce a brief dashboard-style report on a monthly basis, demonstrating progress, status of activities, and items of concern or at risk of incompletion. The report shall be submitted to the Decommissioning of the WR-1 Reactor Page 8 of 11

Executive Management Committee within three working days of the end of each calendar month that this protocol remains in effect. 6. External communications Throughout this protocol s duration, all parties agree to open, transparent communications and that information destined for public release will be coordinated through the managers (or alternates, where designated), with support from each party s communications division. Furthermore, these communications will be done in coordination with, and in consideration of, each party s current communication guidelines. 7. Future revisions Revisions of this protocol that are limited to adjustments to appendix A to the protocol shall be coordinated and approved by the managers and include the monthly report to the Executive Management Committee. Significant material revisions of this protocol (beyond revision to appendix A to the protocol) shall be coordinated by the managers and approved by the signatories (R. Jammal and K. Kehler) of this protocol. Decommissioning of the WR-1 Reactor Page 9 of 11

Part II Requirements for the renewal of the Whiteshell Laboratories decommissioning licence and the proposed In Situ decommissioning of the WR-1 Reactor CNL is to submit information to the CNSC before CNSC staff can prepare a recommendation to the Commission on the EA and on the licence renewal application. This information will need to address the following areas: 1. Environmental assessment CNL is required to prepare an environmental impact statement that meets the requirements of the Generic Guidelines for the Preparation of an Environmental Impact Statement pursuant to the Canadian Environmental Assessment Act, 2012. CNL will require an approval from the Commission for the acceptance of the EA for in situ decommissioning of the WR-1 reactor. 2. Licence renewal application The decommissioning licence for the Whiteshell Laboratories expires on December 31, 2018 and authorizes decommissioning activities in accordance with the plans referenced therein. It does not authorize in situ decommissioning of the WR-1 reactor. Consequently, the licence renewal application must also account for in situ decommissioning of the WR-1 reactor. CNL will require approvals from the Commission for: revision to the detailed decommissioning plans (Volumes 1 and 6) and of any associated plans and programs authorizing in situ decommissioning of the WR-1 reactor renewal of the Whiteshell decommissioning licence Appendix A to the protocol lists the licensing documentation that CNL is expected to submit. The regulatory review and associated licensing approvals for the institutional controls required for the long-term care and maintenance of the WR-1 in situ decommissioning end-state are outside the scope of this protocol and will be addressed at a later licensing stage. 3. Details added as project progresses For clarity, as additional details related to this project and relevant to this protocol are developed and agreed upon, the CNSC and CNL agree to document them in this section and incorporate them into this protocol. Decommissioning of the WR-1 Reactor Page 10 of 11

Part III - Approval by signatories The protocol has been approved, on the dates indicated below. Executive Vice-President and Chief Regulatory Operations Officer Canadian Nuclear Safety Commission Date: ~1?-'&t;. lz f I I Kurt Kehler Date: I Z \li.,.v, < 20/7 Vice-President, Decommissioning and Waste Management Canadian Nuclear Laboratories Decommissioning of the WR-1 Reactor Page 11of11