Vietnam BOT power projects: MOIT imposes tougher statutory remedies for delays

Similar documents
VIETNAM EXPERIENCE IN THE IAEA INTEGRATED NUCLEAR INFRASTRUCTURE REVIEW MISSIONS

INTERNATIONAL ENGLISH PROGRAM

Shortlisted Candidates (Hanoi) for Singapore Scholarship Academic Year 2013/2014

Press Release. Press Release SAVILLS VIETNAM REPORT ON NHA TRANG REAL ESTATE MARKET 1. APARTMENT SECTOR 4, , ,800. projects.

Draft PPP Regulations

Vietnam: HIV/AIDS Prevention Project (Grant No.H152-VN) Amendment to the Development Grant Agreement

Vietnam Agency for Radiation and Nuclear Safety (VARANS), 113 Tran Duy Hung, Hanoi, Vietnam Corresponding author: Luu Nam Hai

FEED-IN TARIFF POLICY APPLICATION AND IMPLEMENTATION GUIDELINES

Van Don Special Administrative and Economic Zone: Sustainable City and Investment Opportunities. 16h00-17h30

2015 East Asia and Pacific (EAP) PPI 1 Update

AMENDMENT NO.: III INVITATION FOR MULTI-STEP BID NO.: GPA FOR

Procurement Process of PPP Projects in Korea

Nigeria PPP Review. Where are we? The ICRC and its Retinue. Milestones. Volume 1, Issue 1 July, 2012

PART I: PROJECT INFORMATION 1. PROJECT LINKAGE TO NATIONAL PRIORITIES, ACTION PLANS AND PROGRAMS

Nuclear Law and Malaysian Legal Framework on Nuclear Security AISHAH BIDIN FACULTY OF LAW UKM

Executive Council approves CLP Power s Five-Year Development Plan New Tariff and Monthly Fuel Cost Adjustment Come into Effect on 1 October

Attention: Suncorp Solar Potential Investors and Shareholders SMALL IPP PROGRAM SOUTH AFRICA RENEWABLE ENERGY MARKET

Human Resource Development for Nuclear Power of Vietnam

BOLD IDEAS AND FRESH THINKING IN ASIA S LEGAL INDUSTRY. TIME OF RECKONING Singapore s legal market at the crossroads

13 Sep Daily Procurement News of Vietnam

UNDERGROUND STRUCTURES

EIC TRADE MISSION TO VIETNAM November 2010

CITY OF LANCASTER REVITALIZATION AND IMPROVEMENT ZONE AUTHORITY

Greatearth Uniting every strength Transforming skylines and landscapes in Asia Engineering a greater future

Renewable Energy Grants and Incentives for Higher Education Institutions. Baker Tilly refers to Baker Tilly Virchow Krause, LLP,

Alberta Indigenous Green Energy Development Program Guidelines

Curriculum Vitae (CV) of DINH THI ANH TUYET (MRS.)

I 2 Program Frequently Asked Questions

PROCUREMENT PLAN. Date of First Procurement Plan: 22 October 2010 Date of this Procurement Plan: 6 July 2016, Version 5

AUSTIN ENERGY REQUEST FOR PROPOSALS (RFP) FOR THE PURCHASE OF RENEWABLE CAPACITY & ENERGY FROM RENEWABLE ENERGY RESOURCES

Commercializing Renewable Energy Technology

Hanoi, Viet Nam 17/9/ /9/2014. Canada

CLP CLIMATE ACTION BOND

SOLAR PV TRADE MISSION INDONESIA

Professional financing advice for meso-scale renewable energy projects in sub-saharan Africa.

OVERVIEW OF THE CFP PROCESS Co-Financing Grants for Commercial Renewable Energy Projects in Indonesia. Jakarta, 3 rd February 2015

State of Qatar. Kahramaa Solar PV. Independent Power Project. Pre-Qualification Questionnaire ( PQQ ) for Applicant

International Seminar on Disaster and Risk Management for Roads 1 st announcement

Investment Reforms in Africa - JICA s Approach Ministerial Forum Fifth Ministerial Meeting NEPAD-OECD Africa Investment Initiative

ADVOCACY REPORT WHITEBOOK 2018 BRIEFING DANANG, 14 JUNE 2018

Background Report: Thayer Consultancy ABN #

IMMPROVEMENT OF POLICY ON OCCUPATIONAL SAFERTY AND HEALTH

29 Mar Daily Procurement News of Vietnam

SPEECH BY MINISTER FOR TRADE AND INDUSTRY (TRADE) LIM HNG KIANG,

Application for Funding

MADHYA PRADESH GAZETTE (Extraordinary) Notification

NCC Infrastructure Holdings Limited

LIST OF PROJECTS CALLING FOR INVESTMENT IN HA GIANG HA GIANG PEOPLE'S COMMITTEE PERIOD ĐỊA CHỈ LIÊN HỆ:

Developing Cross-Border Economic Zones between the People's Republic of China and Viet Nam

International Energy Demonstration Fund Program Guidelines

Proposed Acquisition of Bukit Batok Connection. 14 June 2016

November 4, 2013 Office of Transportation Public Private Partnerships

Annual Report. Fiscal Year

White Blouse and Tiger Striped Uniform

Protocol. This trial protocol has been provided by the authors to give readers additional information about their work.

non-technical aspects of Upstream and Downstream markets. The first day is focused on Up-

NEWSLETTER. With the new appointments, NTU now has 3 Vice-rectors: Mr. Phan VOL 4 ANNOUNCEMENT OF THE DECISION TO APPOINT NTU S VICE-RECTORS

Project Report: Achieving Value for Money Charles Jago Northern Sport Centre

Northline Solar Project

4RE Resource Efficiency Waste Prevention Implementation Fund

CO-LOCATES WITH: MINI & OFF GRID SUMMIT. Taking energy to the greatest destination on earth

Tender 1/2018 Request for Existing Plant Pre-Qualification for the Power 2022 Procurement Process

OIL SPILL RESPONSE IN VIETNAM

Sustainability of Mining Impacted Communities in Papua New Guinea

Northeast Asia EXIM Banks Association

GLOBAL EDUCATION DIALOGUE UK-VN PARTNERSHIP

A STRATEGIC public private partnership

The Outlook for US- Vietnam Relations. Carlyle A. Thayer Presentation to East-West Center Washington, DC March 23, 2011

World Energy Transition

STRUCTURE AND ORGANISATION OF LANGHAM HOSPITALITY INVESTMENTS AND THE COMPANY

LOW-CARBON INNOVATION FUND (LCIF) Program Guidelines

Newsroom 2013 Feed in Tariff Program Independent Electricity System Operator

COPY REGULATION OF THE MINISTER OF FINANCE OF THE REPUBLIC OF INDONESIA NUMBER 223/PMK.011/2012

U.S. Trade and Development Agency (USTDA) USAEE Annual Conference. Washington, DC, July 9, 2004

Process for Establishing Regional Research Institutes

Viet Nam Annual Report 2012

Request for Proposals and Specifications for a Community Solar Project

ANNEX II SCHEDULE OF BRUNEI DARUSSALAM

PPEA Guidelines and Supporting Documents

CAPITALS. What are the Capitals that sustain our business?

INTRODUCTION TO SAIGON HI-TECH PARK

Metro West Inter-Municipal Business Licence Pilot Program

Subrecipient Monitoring Under 2 CFR 200. Kris Rhodes, MS Director, Higher Education Practice

CONSUMERS ENERGY COMPANY REQUEST FOR PROPOSALS SOLAR GENERATION PROJECTS. Bids Due: July 28, :00 noon EPT (Jackson, MI) Issued.

CCS Consults on Proposed Amendments to the Competition Act

GEORGE MASSEY TUNNEL REPLACEMENT PROJECT

BI introduces FinTech sandbox to support innovation

KENYA INFRASTRUCTURE AND PPP PROJECT SOUTH EASTERN KENYA UNIVERSITY HOSTELS PPP PROJECT

SUBMISSION TO THE AUSTRALIA 2020 SUMMIT STIMULATING INNOVATION IN THE ICT SECTOR

W ORLD H ISTORY ASSOCIATION SYMPOSIUM

Federal Budget Firmly Establishes Manufacturing as Central to Innovation and Growth Closely Mirrors CME Member Recommendations to Federal Government

DECREE ON OCCUPATIONAL SAFETY AND HYGIENE

LICENCE APPLICATION FORM

TABLE OF CONTENTS. Request for Proposals (RBFF-18-C-387) STRATEGIC PLANNING FACILITATOR I. Request for Proposals. II.

Strategic Procurement Policies for Innovation: Korean Case, Firm Survey and Empirical Results

SESSION B: SPECTROSCOPY OF CONDENSED MATTERAND NANO MATERIALS November 27, 2012(Thuesday)

Corporate Governance Program East Asia and the Pacific. Annual Summary 2016 IN PARTNERSHIP WITH

International School ISM. Of Management U N L O C K I N G K N O W L E D G E. Certificate in IFRS. International Financial Reporting Standards

GLOBAL INFRASTRUCTURE FACILITY OPERATING GUIDELINES

Russia s Eastbound Policy

Transcription:

Legal Update April 2017 Vietnam BOT power projects: MOIT imposes tougher statutory remedies for delays The Ministry of Industry and Trade (MOIT) recently issued Circular No. 43/2016/TT-BCT (Circular 43) which entered into force on 15 February 2017. This legal instrument sets out the criteria under which the right to develop a Vietnam power project (Development Right) may be terminated on the ground of prolonged project delays. In this article, our lawyers examine the legal implications of these significant regulatory developments. Background Over the past two decades, there has been plenty of appetite for private sector investment in the development and financing of new, greenfield large-scale energy and infrastructure projects across Vietnam despite challenging market conditions. As interest gains momentum from international investors, the Government of Vietnam (Government) has continued efforts to improve the investment climate by formulating ambitious strategic energy development plans to develop its core power infrastructure assets. Central to the successful implementation of the 2016 Revised Power Development Master Plan VII (Revised PDP 7) would be that independent power producer plants (IPP) must be brought to completion within the required time period to ensure security of long-term national electricity production and supply, as the Prime Minister directed from a policy perspective. However, it is worth noting that Government authorities have lately expressed concerns about prolonged project delays and cost variations in the development of certain power projects. Several recent reported examples where sponsors fail to develop and achieve project completion include Quang Trach 1 (PetroVietnam), Quang Trach 2 (Russia s Inter RAO Group) and Kien Luong 1 BOO (Tan Tao Group/ITACO) coal-fired power projects. Further, there is a significantly 1

growing concern from local provincial authorities in respect of progressive works completion of the Hai Duong BOT power project. Circular 43 is intended to provide a mechanism that aims to ensure that power projects are to be delivered on budget in a timely manner. This is crucial to ensuring the Vietnam power industry can deliver on its potential. Signing of a MOU The Development Right of a BOT power project is typically awarded to sponsors by way of a written consent of the Prime Minister. Significantly, Circular 43 introduces a statutory requirement for sponsors and MOIT to sign a memorandum of understanding (MOU) within 90 working days from the date on which the Development Right is granted. An MOU must include a plan for project development setting out certain key project milestones as follows: schedule to formulate and approve a site planning (if applicable); schedule to formulate and approve a feasibility study (FS); plan to negotiate a concession agreement and other project documents; schedule to negotiate project documents, including a power purchase agreement (PPA), a land lease agreement (LLA), an engineering, procurement and construction contract (EPC Contract), fuel supply contract(s) (i.e. coal supply agreement (CSA) or gas sales agreement (GSA)) and other contracts; schedule to initial project documents; the date for submission of an application for issuance of an investment registration certificate (IRC) and the date for formal execution of project documents; schedule for financial contributions; and schedule for ground breaking and construction, including the date for ground breaking, the commercial operation date (COD) for each electrical generating unit (Unit) and COD for the entire power plant. Key Impact of Circular 43 Circular 43 places an emphasis on project delays, including a statutory obligation of sponsors to develop a project within the time stated in the MOU. It imposes numerous compliance and reporting obligations on sponsors. This new legal instrument specifically states that if a BOT power project falls behind the agreed timeline of certain key project milestones and project documents have not been signed with Vietnam project counterparties, the consequences are: First reminder letter MOIT will issue a first reminder letter to sponsors requiring them to immediately undertake and complete the delayed project work in the case of a delay of more than 30 working days compared to the project milestone set out in the MOU. 2

Second reminder letter If sponsors fail to achieve such project milestone after 30 working days from the date of the first reminder letter, MOIT will issue a second reminder letter. There will be no more than two reminder letters issued by MOIT with respect to a failure by sponsors to achieve any project milestone. A new development is the power of MOIT to request the Prime Minister to consider termination of the Development Right in circumstances in which sponsors fail to achieve a project milestone within 12 months from the date of MOIT s first reminder letter and the overall project schedule has accumulated delays of 12 months compared to their agreed timeline in the MOU. The message is therefore clear in respect of BOT power projects which sponsors have not secured the execution of project documents: MOIT will no doubt focus greater scrutiny on those projects with its more frequent investigative and enforcement action on project delays. A failure by sponsors to develop a BOT power project in accordance with the agreed timeline can prove costly giving rise to termination of the Development Right and such project may be awarded to another investor, subject to the exceptions enumerated in Circular 43. If the Development Right is terminated in such event and an investment certificate previously issued in favour of sponsors in respect of a BOT power project is revoked, all costs and expenses incurred by sponsors prior to termination of such right will not be refunded. Exceptions to the general rule Circular 43 prescribes a number of limited exceptions to which the mandatory provisions of the general rule do not apply. Technically, project delays caused by sponsors would be non-excusable. Those exceptions include (a) force majeure, (b) excusable delays caused by a competent State authority and (c) excusable delays caused by the conduct of a third party which directly relates to achieving specific project milestone(s). The application of an exception will give sponsors an opportunity to agree with MOIT on an extension of time in respect of certain key project milestones initially agreed in a MOU. Transitional provisions Circular 43 provides a transition regime pursuant to which a BOT power project for which a MOU was signed prior to 15 February 2017 but project documents have not been signed, then MOIT and sponsors must sign another MOU setting out remaining project milestones. The practical effect of this provision is that all BOT power projects which sponsors have not secured the execution of project documents with Vietnam project counterparties will be subject to statutory remedies in Circular 43 for prolonged project delays.

Reporting obligations Sponsors are required to submit a monthly report to the General Department of Energy (GDE) and the relevant provincial people's committee on the progress of works completion in accordance with the agreed project development schedule. Market trends Looking forward, we believe that the Revised PDP 7 provides significant investment opportunities for foreign investment in the IPP power generation. Especially notable was the growing significance of BOT structures under the regulatory framework on public private partnerships (PPP), and we expect this trend continues to grow in popularity. The Vietnam power generation markets have expanded and evolved significantly. Following success stories of Phu My 2.2 (715 MW) and Phu My 3 (716.8 MW) gas-fired power projects, commercial operation was achieved in May 2015 in respect of the US$1.95bn 1,240MW Mong Duong 2 coalfired power project where AES Corporation, POSCO Power Corp. and China Investment Corporation are sponsors. MOIT forecasted that Vietnam BOT power projects involving foreign equity investment will hold a total installed capacity of 24,000MW by 2030. A strong pipeline of BOT projects With international investor appetite growing, strong deal flow looks set to continue over the coming years with a greater shift in project finance activities towards a wider array of new BOT power projects coming into the market. The big question is the extent to which debt finance will be made available by international lenders to finance those Vietnam projects. To our knowledge, MOIT currently holds discussions with numerous sponsors to develop 15 greenfield BOT power projects, which we set out below. BOT Power Projects Installed Capacity Sponsors COD 1. Vinh Tan 1 1,200MW CSG, CPIH and Vinacomin (project documents signed on 12 December 2013) 2. Hai Duong 1,200MW Jaks Resources Bhd and CPECC (project documents signed in August 2011) 3. Nghi Son 2 1,200MW Marubeni Corporation and Korea Electric Power Corporation (KEPCO) (investment agreement signed on 15 November 2016) 2019 2019 (Unit 1) 2021 (Unit 2)

4. Vung Ang 2 1,200MW VAPCO (One Energy Asia Limited jointly owned by Mitsubishi Group and CLP Holdings) (project documents signed on 16 January 2017) 5. Nam Dinh 1 1,200MW Taekwang Power Holdings and ACWA Power International 6. Duyen Hai 2 1,200MW Janakuasa Sdn Bhd (project documents signed on 29 December 2015) 7. Song Hau 2 3,000MW Toyo Ink Group Bhd (project documents expected to be signed by August 2017) 2021 (Units 1 & 2) 8. Long Phu 2 1,320MW Tata Power Co. Ltd 9. Vinh Tan 3 1,980MW VTEC (One Energy Ventures Limited (CLP), EVN and Pacific Group Corporation) VTEC and CDB signed a MOU on 5 November 2015 2022 (Unit 1) 2023 (Units 2 & 3) 10. Van Phong 1 1,320MW Sumitomo Corporation 2022 (Unit 1) 2023 (Unit 2) 11. Quang Tri 1 1,200MW EGAT International Co., Ltd. (EGATi) 2023 (Unit 1) 12. Dung Quat 1 1,500MW (gas fired) Sembcorp Utilities Pte. Ltd. (MOU signed on 13 September 2013) 2024 (Unit 2) 2023 (Unit 1) 2024 (Unit 2) 13. Vung Ang 3 1,200MW Samsung C&T Corporation 2024 (Unit 1) 2025 (Unit 2) 14. Quynh Lap 1,200MW to be specified 2026 (Unit 1) 15. Son My 1 2,250MW (gas fired) GDF SUEZ, Sojitz and Pacific Group Corporation 2027 (Unit 2) 2026 (Unit 1) 2027 (Unit 2) 2028 (Unit 3)

Other potential projects By way of an update, South Korea s Korea Western Power Co. (KOWEPO) signed a memorandum of cooperation in early February 2017 with Quang Tri People's Committee on a potential development of a proposed US$1.85 billion 1,200MW Quang Tri 2 BOT power project in Southeast Economic Zone, Quang Tri province. This project will require formal approval to be added to the Revised PDP 7. With respect to the proposed 2,250MW Son My 2 gas-fired power plant, there have been recent highlevel discussions by OMC with Binh Thuan People s Committee though this project is intended to be developed by PetroVietnam. Recently, KEPCO also expressed interest in the development of the 2,000 MW Song Hau 3 power plant. Gazprom International (acting through VietGazprom entity) contemplates major investment in an integrated gas-to-power project which aims to commercialise natural gas from Bao Vang gas field (Block 113) offshore Quang Tri province. Finally, the Prime Minister has recently approved a master plan to develop a 3,000MW gas-fired power complex located in Nui Thanh district (Quang Nam province) and Binh Son district (Quang Ngai province) to utilise natural gas to be brought ashore from ExxonMobil s Blue Whale gas discoveries offshore central Vietnam. We will continue to monitor market developments in this area and welcome any queries you may have.

Key contacts If you have any questions, or would like to know how this might affect your business, please contact these key contacts. Pham Ba Linh Managing Partner Head of Finance, Projects, Energy and Infrastructure Ho Chi Minh City, Vietnam +84 8 3936 5018 linh.pham@lexcommvn.com Luu Thi Xuan Trang Counsel Finance and Projects Ho Chi Minh City, Vietnam +84 8 3936 5018 trang.luu@lexcommvn.com Legal notice The contents of this publication, current at the date of publication set out above, are for reference purposes only. They do not constitute legal advice and should not be relied upon by any party for any purpose. Lexcomm Vietnam LLC 2017