Alteration of Bridges

Similar documents
GAO RECOVERY ACT. Project Selection and Starts Are Influenced by Certain Federal Requirements and Other Factors. Report to the Republican Leader

FEDERAL TRANSIT CAPITAL IMPROVEMENT GRANTS CAPITAL PROGRAM. U. S. Department of Transportation

GUIDANCE. Impact Aid Section 8007 School Construction Funds. Made Available Under. The American Recovery and Reinvestment Act of 2009

FOR REINVESTMENT ACT. NILAH DEVANEY NWRO, AWARDING OFFICIAL

Stakeholder Guidance American Recovery and Reinvestment Act (ARRA) of 2009 March 3, 2009

GUIDANCE. Funds for Title I, Part B of the Rehabilitation Act of 1973, as amended. Made Available Under

HIGHWAY PLANNING AND CONSTRUCTION RAILROAD STATION IMPROVEMENT PROGRAM. N. C. Department of Transportation Rail Division

REQUEST FOR PROPOSALS (RFP) FOR TROUBLED BUILDINGS INITIATIVE CONDOMINIUM PROGRAM ACQUISITION AND DISPOSITION SERVICES

GAO RECOVERY ACT. As Initial Implementation Unfolds in States and Localities, Continued Attention to Accountability Issues Is Essential

ACTION: Temporary final rule; request for comments. SUMMARY: The Coast Guard is establishing a temporary safety zone on navigable

Local Nonprofit Agency Risk Assessments

Financial Grants Management. Session Outline. Grants Management Roles 4/19/10

ARRA Overview. ATTWG Symposium Anchorage, AK April 7, 2009

2010 Mauldin & Jenkins Single Audits for for Auditees

Administrative Regulation SANGER UNIFIED SCHOOL DISTRICT. Business and Noninstructional Operations FEDERAL GRANT FUNDS

STATE OF NORTH CAROLINA OFFICE OF THE STATE AUDITOR BETH A. WOOD, CPA

Objectives for Financial Control over Grant Programs

Wake Forest University Financial Services: Grants Accounting and Compliance

Projects from the American Recovery and Reinvestment Act of 2009 (ARRA) Enacted February 17, 2009

Lessons Learned from Prior Reports on Disaster-related Procurement and Contracting

RESOLUTION NUMBER 2877

POLICIES RELATING TO FEDERAL HIGHWAY FUNDING

Commitment, CHDO Reservation, and Expenditure Deadline Requirements for the HOME Program. Table of Contents

Delayed Federal Grant Closeout: Issues and Impact

Report No. D-2011-RAM-004 November 29, American Recovery and Reinvestment Act Projects--Georgia Army National Guard

Navigating the New Uniform Grant Guidance. Jack Reagan, Audit Partner Grant Thornton LLP. Grant Thornton. All rights reserved.

U. S. DEPARTMENT OF TRANSPORTATION. Safe, Accountable, Flexible, Efficient Transportation Equity Act: A Legacy for Users (SAFETEA-LU), 49 U.S.C.

THE ARRA AND SRF QUESTIONS AND ANSWERS Volume 1 March 17, 2009

ATTACHMENT A GARDEN STATE HISTORIC PRESERVATION TRUST FUND PROGRAM REGULATIONS. (selected sections)

SUMMARY OF THE GROW AMERICA ACT As Submitted to Congress on April 29, 2014

HOUSE OF REPRESENTATIVES BUY AMERICAN AMENDMENTS TO THE FY 2004 DEFENSE AUTHORIZATION BILL

North Carolina Department of Public Safety Division of Emergency Management

HIGHWAY CONSTRUCTION PROGRAM. N. C. Department of Transportation (Research and Development) (Construction and Maintenance)

Special Report - Senate FY 2013 Department of Homeland Security Appropriations and California Implications - June 2012

Funding Principles. Years Passed New Revenue Credit Score Multiplier >3 years 0% % % % After Jan %

California Department of Public Health Safe Drinking Water State Revolving Fund. The American Recovery and Reinvestment Act of 2009 (ARRA)

ADDITIONAL AMENDMENTS RELATING TO TOTAL FORCE MANAGEMENT (SEC. 933)

Updated Hurricane Harvey s Fiscal Impact on State Agencies PRESENTED TO SENATE FINANCE COMMITTEE LEGISLATIVE BUDGET BOARD STAFF

QIKIQTANI INUIT ASSOCIATION AND KAKIVAK ASSOCIATION PROGRAM GUIDELINES BUSINESS CAPACITY AND START UP FUND

Report Documentation Page

STATEMENT OF PRINCIPAL REASONS FOR ADOPTION OF RULES

Federal Grants-in-Aid Administration: A Primer

SENATE, No. 123 STATE OF NEW JERSEY. 217th LEGISLATURE PRE-FILED FOR INTRODUCTION IN THE 2016 SESSION

KANSAS CITY REGIONAL TIGER PROJECT PMOC PROGESS REPORT 2014 Fiscal Quarter 1 October 1 December 31, 2013

Report to Congress on Distribution of Department of Defense Depot Maintenance Workloads for Fiscal Years 2015 through 2017

The Stimulus Plan. Our Perspective. Al Gordon Chief Executive Officer, NSI.

Executive Office of the Governor Business Participation Plan Fiscal Year

Grant Review and Pre-Award Process Elisa Gleeson Senior Grants Management Specialist

GULF COAST ECOSYSTEM RESTORATION COUNCIL COMPREHENSIVE PLAN COMPONENT PROGRAM

Recovery Act Stimulus Funds: New Opportunities and Complexities

The American Recovery and Reinvestment Act of Enacted February 17, 2009

SUMMARY: By this direct final rule, the Coast Guard is removing. the regulation for the safety zone at Snake Island, also known as

IMPLEMENTATION PLAN PRESIDENTIAL MEMORANDUM ON MODERNIZING INFRASTRUCTURE PERMITTING FOR THE

CAPITALIZATION GRANT FOR STATE REVOLVING FUND. U.S. Environmental Protection Agency

FINAL AUDIT REPORT DEPARTMENT OF COMMUNITY AFFAIRS CALHOUN COUNTY WEATHERIZATION ASSISTANCE PROGRAM - ARRA SUBGRANT AGREEMENT

SECTION 3 POLICY & PROGRAM

CAPITALIZATION GRANTS FOR CLEAN WATER STATE REVOLVING FUNDS. U.S. Environmental Protection Agency

NON-INSTRUCTIONAL SERVICES: Purchasing

COMMUNITY PLANNING AND DEVELOPMENT MONITORING HANDBOOK. Departmental Staff and Program Participants HANDBOOK REV-6

Orange County. EECBG Kick-Off Meeting October 1, U.S. Department of Energy

U.S. Department of Energy Office of Inspector General Office of Audit Services

General Procurement Requirements

U. S. Virgin Islands Compliance Agreement

Executive Office of the Governor Business Participation Plan Fiscal Year

San Francisco County Transportation Authority Proposition K Sales Tax Program Allocation Request Form

2009 American Recovery and Reinvestment Act (ARRA)

World Bank Iraq Trust Fund Grant Agreement

Non-Federal Cost Share Match Program Grant Implementation Checklist

DEPARTMENT OF THE TREASURY

PUBLIC BEACH & COASTAL WATERFRONT ACCESS PROGRAM. NC Department of Environmental Quality Division of Coastal Management

WHEREAS, the Transit Operator provides mass transportation services within the Madison Urbanized Area; and

SUMMARY: The Coast Guard is establishing a temporary safety zone on the Upper Mississippi

BOCC POLICY: SECTION NUMBER COUNTY COASTAL CANAL GRANT PROGRAM EFFECTIVE DATE: February 15, 2017 SUPERSEDES:

Defense Acquisition: Use of Lead System Integrators (LSIs) Background, Oversight Issues, and Options for Congress

Safety Zone; MODU KULLUK; Kiliuda Bay, Kodiak Island, AK to. SUMMARY: The Coast Guard is establishing a temporary safety

EMS Systems Act of 1973

CENTERS FOR DISEASE CONTROL AND PREVENTION AFFORDABLE CARE ACT (ACA) COMMUNITIES PUTTING PREVENTION TO WORK

PROCUREMENT POLICY FOR FEDERAL GRANTS

Guidance for Locally Administered Projects. Funded Through the NJDOT/MPO Program Funds Exchange. August 27, Revised September 15, 2014

Robinson & Cole is a full service law firm with eight offices throughout the eastern United States. Anticipating

HIGHWAY PLANNING AND CONSTRUCTION SAFE ROUTES TO SCHOOL PROGRAM (SRTS) U. S. Department of Transportation

TRANSPORTATION ALTERNATIVES (TA) SET ASIDE PROGRAM July 2016

STATE AID TO AIRPORTS PROGRAM NC DEPARTMENT OF TRANSPORTATION DIVISION OF AVIATION

HOGANSAC th Annual Harbor Safety Committee Conference Seattle, Washington. Good Afternoon I am TF, chair of HOGANSAC

EPA SRF Webcast Training Series. Please remember to call the audio conference center so you can listen to today s presentation: PIN: 7563

Uniform Grants Guidance. Colorado Charter School Institute Cassie Walgren, Controller

Office of Business and Financial Services Procurement and Contracts Division Section SUBJECT: PROCUREMENT OF CONSTRUCTION SERVICES

HUD Q&A. This is a compilation of Q&A provided by HUD regarding relevant issues affecting TCAP and the Tax Credit Exchange Program.

Hurricane Harvey s Fiscal Impact on State Agencies PRESENTED TO HOUSE APPROPRIATIONS COMMITTEE LEGISLATIVE BUDGET BOARD STAFF

Felipe Lopez, Vavrinek, Trine, Day & Co., LLP

BOARD OF COUNTY COMMISSIONERS SARPY COUNTY, NEBRASKA

STATE OF NEW JERSEY. SENATE, No SENATE BUDGET AND APPROPRIATIONS COMMITTEE STATEMENT TO. with committee amendments DATED: NOVEMBER 9, 2015

Accounting and Administrative Manual Section 100: Accounting and Finance

POLICY 6800 PROCUREMENT

Department of Contracts, Grants and Financial Administration, Texas Education Agency 1/26/18

Request for Qualifications (RFQ) for Engineering/Architectural/Surveying Services

APRIL 2009 COMMUNITY DEVELOPMENT BLOCK GRANTS/STATE S PROGRAM NORTH CAROLINA SMALL CITIES CDBG AND NEIGHBORHOOD STABILIZATION PROGRAM

Program Management Plan FTA Section 5310

Suffolk COUNTY COMMUNITY COLLEGE PROCUREMENT POLICY

Community Development Block Grant Applicant Guide

Transcription:

Alteration of Bridges Program Specific Recovery Act Plan May 14, 2009 United States Coast Guard

Message from the United States Coast Guard ARRA Senior Accountable Official 14 May 2009 I am pleased to present the following report, Alteration of Bridges Program-Specific Recovery Act Plans, which has been prepared by the United States Coast Guard. This document has been compiled in response to a requirement included in the American Recovery and Reinvestment Act (P. L. 111-5) which appropriated $240 million ($142 million for Alteration of Bridges, $98 million for AC&I) to the United States Coast Guard. The following pages set forth the Alteration of Bridges Program-Specific Recovery Act Plan for $142 million (AC&I is provided in a separate report). Senior Accountable Official Approval Date: Mr. Martin J. Rajk United States Coast Guard Deputy Assistant Commandant for Resources/CFO/ARRA SAO (202) 372-3476 i

Executive Summary The American Recovery and Reinvestment Act (P.L. 111-5) provided Alteration of Bridges, $142,000,000 for alteration or removal of obstructive bridges, as authorized by section 6 of the Truman-Hobbs Act (33 U.S.C. 516): Provided, That the Coast Guard shall award these funds to those bridges that are ready to proceed to construction: Provided further, That no later than 45 days after the date of enactment of this Act, the Secretary of Homeland Security shall submit to the Committees on Appropriations of the Senate and the House of Representatives a plan for the expenditure of these funds. The funds will allow for completion of the bridge alteration construction projects shown in the table below. Completion of these projects facilitates safe and efficient navigation along the Nation s waterways, creates or retains jobs in the construction sector, and leverages $120.4 million of previously obligated appropriations for the alteration of bridges allocated to these projects. This will create a $262 million stimulative impact on the construction industry in four different states. Bridge owners have not solicited bids for these projects. All information contained in this report is considered For Official Use Only - Bridge Alteration Sensitive and shall not be distributed outside of the Federal Government. ii

United States Coast Guard Program-Specific Recovery Act Plan-Alteration of Bridges Table of Contents I. Legislative Requirement 1 II. Funding Table 2 III. Objectives 3 IV. Activities 4 V. Characteristics 6 VI. Delivery Schedule 7 VII. Environmental Review Compliance and Federal Infrastructure Investments 7 VIII. Measures 8 IX. Monitoring/Evaluation 10 X. Transparency 12 XI. Accountability 12 XII. Barriers to Effective Implementation 12 iii

I. Legislative Requirement The American Recovery and Reinvestment Act of 2009 appropriated $142 million for the Alteration of Bridges Appropriation as quoted below. The appropriation will be executed in accordance with OMB M-09-15. COAST GUARD ALTERATION OF BRIDGES For an additional amount for Alteration of Bridges, $142,000,000 for alteration or removal of obstructive bridges, as authorized by section 6 of the Truman- Hobbs Act (33 U.S.C. 516): Provided, That the Coast Guard shall award these funds to those bridges that are ready to proceed to construction. 1

II. Funding The $142 million of ARRA funds will allow for the completion of four alteration of bridges projects to alter bridges found to be unreasonably obstructive to navigation. Completion of these construction projects facilitates safe and efficient navigation on U.S. waterways, creates or retains jobs in the construction sector and local communities, and leverages an additional $120.4 million of previously obligated Bridge Alteration appropriations allocated to these projects. As such, the ARRA appropriation results in a $262.4 million stimulative impact on the economies of four different states as well as national suppliers of equipment and materials associated with the projects. The diagram below outlines the process by which the Coast Guard reimburses the Bridge owner of a Truman-Hobbs unreasonably obstructive bridge for completing Coast Guard alteration work. The work is performed pursuant to an alteration construction contract between the Bridge owner and the Contractor. 2

III. Objectives Section 3 of the Truman-Hobbs (T-H) Act, Title 33 U. S. Code Section 513, provides for the use of federal funds to alter bridges found to be unreasonable obstructions to navigation under the Truman-Hobbs Act. Typically, each year, Congress provides small appropriations, available until expended, for the Coast Guard Bridge Alteration Program. The Coast Guard disburses and obligates the yearly appropriations to specific Truman-Hobbs Bridge Alteration projects. Funds are then accumulated once the design of the alteration is complete but not expended until the Government s share of the construction cost is reached and the Coast Guard authorizes the Bridge Owner to proceed to construction. Due to this funding mechanism the duration between the Order to Alter and the construction contract award is often long. For example, the four bridge alteration projects selected for receipt of ARRA funds have the following durations based on the estimated construction award dates contained in this report: 1) Mobile Bridge- 10 years, 2) EJ&E Bridge- 14 years and 5 months, 3) Burlington Bridge-18 years and 5 months, 4) Galveston Causeway Bridge- 8 years and 3 months. ARRA funds facilitate the quick completion of the alteration of these unreasonably obstructive bridges, thus providing for safe and efficient navigation and facilitating movement of funds along the Nation s waterways, a key statutory objective of the Coast Guard Bridge Program. 3

IV. Activities Summary of the Four Bridge Alteration Construction Projects 1. Mobile Bridge (Mobile River), Alabama Background: CSX Transportation, owners of the Mobile Bridge, was issued a Coast Guard Order to Alter (OTA) which requires Bridge owners to correct the obstructive nature of the bridge in June 1999. The estimated government share of the total project cost, from the start of the design phase through the end of the construction phase, is 92.5 percent. Construction estimated to start ten years after the Coast Guard OTA was issued. Execution Strategy: Following Coast Guard approval, it is estimated the bridge owner will award a construction contract by the end of June 2009. The project s construction is estimated to be completed by June 2011. Competitive Bid Process: Has not been completed. Accomplishments to Date: o Plans, Specifications, and Engineers Estimate are 100 percent complete. o National Environmental Policy Act (NEPA) and Section 106 under the National Historic Preservation Act (NHPA) Requirements have been completed. o On April 16, 2009, the Coast Guard authorized CSX Transportation to advertise the bid solicitation 2. EJ&E Bridge (Illinois Waterway), Illinois Background: Owners of the EJ&E Bridge were issued a Coast Guard OTA in February 1995. Effective January 2009, the Canadian National Railway Company became the owners of this bridge. The estimated government share of the total project cost, from the start of the design phase through the end of the construction phase, is 94.8 percent. Construction estimated to start 14-years and five months after the Coast Guard OTA was issued. Execution Strategy: Following Coast Guard approval, it is estimated the bridge owner will award a construction contract by the end of July 2009. The project s construction is estimated to be completed by July 2011. Competitive Bid Process: Has not been completed. Accomplishments to Date: o Plans, Specifications, and Engineers Estimate are 100 percent complete. o Both NEPA and NHPA Section 106 requirements have been completed for the EJ&E Bridge. 3. Burlington Bridge (Upper Mississippi River), Iowa Background: The Burlington Northern Santa Fe Railroad Company, owners of the Burlington Bridge, was issued a Coast Guard OTA in August 1991. The estimated government share of the total project cost, from the start of the design phase through the end of the construction phase, is 89.5 percent. Construction estimated to start 17-years and ten months after the Coast Guard OTA was issued. Execution Strategy: Following Coast Guard approval, it is estimated the bridge owner will award a construction contract by the end of June 2009. The project s construction is estimated to be completed in June 2011. 4

Competitive Bid Process: Has not been completed. Accomplishments to Date: o Plans, Specifications, and Engineers Estimate are 100 percent complete. o Both NEPA and NHPA Section 106 requirements have been completed for the Burlington Bridge. o On April 27, 2009, the Coast Guard will authorize Burlington Northern Santa Fe Railroad Company, to advertise the bid solicitation. 4. Galveston Causeway Bridge (Gulf Intercoastal Waterway), Texas Background: Galveston County, owner of the Galveston Causeway Bridge, was issued a Coast Guard OTA in June 2001. The estimated government share of the total project cost, from the start of the design phase through the end of the construction phase, is 92.0 percent. Construction estimated to start eight years and three months after the Coast Guard OTA was issued. Execution Strategy: Following Coast Guard approval, it is estimated the bridge owner will award a construction contract in early September 2009. The project s construction is estimated to be completed by September 2011. Competitive Bid Process: Has not been completed. Accomplishments to Date: o NEPA and NHPA Section 106 requirements have been addressed. The project s Environmental Assessment, which is estimated to be finished by the end of May 2009, will complete the NEPA process. 5

V. Characteristics The recipients of Alteration of Bridges ARRA funds are owners of unreasonably obstructive to navigation bridges who have received an Order to Alter from the Coast Guard. Actions to enforce the Truman-Hobbs Act and to execute appropriations are unique, and are not considered a public contract action, loan, or grant. There is no requirement to advertise these actions in accordance with the Federal Acquisition Regulations, nor do requirements for competitive acquisition procedures or the Buy American Act apply as a matter of law. However, the construction contracts between the Bridge owners and the Contractors will require compliance with the Buy American Act and Davis Bacon Act.. The $142 million Alteration of Bridges ARRA appropriation allows for the completion of four bridge alteration construction projects selected based on being shovel ready. and the level of previously appropriated funds. The completion of these projects facilitates safe and efficient navigation along the Nation s waterways, creates or retains jobs in the construction sector and local communities, and leverages an additional $120.4 million of previously obligated Alteration of Bridges appropriations, specific to the four bridges. The table below includes the bridge owners of the four bridges to be altered; the amount of ARRA funds to be used; and the previous appropriation for each project. 6

VI. Delivery Schedule Bridge Alteration Construction Project Schedules and Project Milestones Milestones Mobile EJ&E Burlington Galveston Advertise Bid Solicitation FY09 Q3 FY09 Q3 FY09 Q3 FY09 Q4 Contract Award FY09 Q3 FY09 Q4 FY09 Q3 FY09 Q4 Completion of the Project FY11 Q3 FY11 Q4 FY11 Q3 FY11 Q4 VII. Environmental Review Compliance and Federal Infrastructure Investments Environmental Review Compliance: 1. Mobile Bridge (Mobile River), Alabama: Both NEPA and NHPA Section 106 requirements have been completed for the Mobile Bridge. 2. EJ&E Bridge (Illinois Waterway), Illinois: Both NEPA and NHPA Section 106 requirements have been completed for the EJ&E Bridge. 3. Burlington Bridge (Upper Mississippi River), Iowa: Both NEPA and NHPA Section 106 requirements have been completed for the Burlington Bridge. 4. Galveston Causeway Bridge (Gulf Intercoastal Waterway), Texas: Both NEPA and NHPA Section 106 requirements have been addressed. The project s Environmental Assessment, which is estimated to be finished by end of May 2009, will complete the NEPA process. THE ARRA ENVIRONMENTAL AND SUSTAINABILITY REQUIREMENTS ARE NOT APPLICABLE TO THE FOUR BRIDGE CONSTRUCTION PROJECTS 7

VIII. Measures The alteration of the four bridges funded by the ARRA will improve navigation in the nation s waterways by allowing safe and unencumbered passage of marine traffic beneath bridges presently constituting choke points to the waterways they span. As a result of the alteration of these bridges, the Coast Guard expects a significant reduction in allisions (a vessel striking a fixed object) between vessels and bridges with a concurrent decline in associated repair costs, time required for vessels to transit these bridges, and delays caused to rail traffic. The following are the Coast Guard s expectations for the improvement of marine and land transportation at the four bridges. After completion of the projects the program will collect data annually for each bridge to compare actual versus expectation. The data shown below is based on information contained in the Truman-Hobbs Detailed Investigations Report for each bridge. 1. Mobile River Bridge The Mobile River Bridge averages 8 allisions per year at an annual cost to maritime users and the bridge owner of more than $220,000. Alteration of the bridge is expected to reduce these allisions and damage costs to less than $11,000 per year. The average time to accomplish a safe transit of the Mobile River Bridge is 6 to 7 hours. Alteration of the bridge is expected to reduce this transit time to between 25 and 30 minutes and result in a savings to the mariner of more than $6,000,000 per year. An average of 8 trains per day are delayed at an annual cost to the railroad of more than $1,050,000. Alteration of the bridge is expected to reduce these costs to less than $53,000 per year. 2. EJ&E Railroad Bridge The EJ&E Railroad Bridge averages over 20 allisions per year at an annual cost to maritime users and the bridge owner of more than $664,000. Alteration of the bridge is expected to reduce these allisions and damage costs to less than $34,000 per year. The average time to accomplish a safe transit of the EJ&E Railroad Bridge under ideal conditions is 30-35 minutes. Alteration of the bridge is expected to reduce this transit time to 12-20 minutes in most conditions and result in a savings to the mariner of more than $620,000 per year. The average time for a mariner to double-trip a larger tow is 6 to 7 hours. Alteration of the bridge is expected to eliminate the need for double-tripping and save the mariner more than $490,000 per year. 8

3. Burlington Northern Railroad Bridge The Burlington Northern Railroad Bridge averages over 12 allisions per year at an annual cost to maritime users and the bridge owner of more than $232,800. Alteration of the bridge is expected to reduce these allisions and damage costs to less than $12,000 per year. The average time to accomplish a safe transit of the Burlington Northern Railroad Bridge is 50 minutes. Alteration of the bridge is expected to reduce this transit time to about 18 minutes and result in a savings to the mariner of more than $1,400,000 per year. On average 8 trains per day are delayed at an annual cost to the railroad of more than $264,000. Alteration of the bridge is expected to reduce these costs to less than $14,000 per year. 4. Galveston Causeway Bridge The Galveston Causeway Bridge averages over 10 allisions per year at an annual cost to maritime users and the bridge owner of more than $560,000. Alteration of the bridge is expected to reduce these allisions and damage costs $28,000 per year. The average time to accomplish a safe transit of the Galveston Causeway Bridge under ideal conditions is 21 minutes. Alteration of the bridge is expected to reduce this transit time to about 15 minutes in most conditions and result in a savings to the mariner of more than $212,000 per year. Trains are delayed an average of two hours per week at an annual cost to the railroad of more than $283,284. Alteration of the bridge is expected to reduce these costs to less than $15,000 per year. It should be noted that the Galveston Causeway Bridge provides the only railroad service to Galveston, TX. The specific program mission performance measures to be used are: Twelve-month average for Distinct Allision Events. Five-year average for Distinct Collision, Allision, and Grounding Events. These measures are reported quarterly in the Fiscal Year Homeland Security Plan and annually in the DHS Annual Performance Report. 9

IX. Monitoring/Evaluation The Alteration of Bridges Program will follow its established procedures to closely monitor and evaluate the use of the ARRA funds, maintain project schedules, and ensure accountability objectives of the law are followed. In addition, procedures have been established to allow for the immediate identification and resolution of project related problems or low performance. The following are the procedures that will be followed to monitor and evaluate progress of the bridge projects: Recovery funds are awarded and distributed in a prompt, fair, and reasonable manner: The criteria used by the Coast Guard to select the four Truman-Hobbs bridge projects are: 1. The project is Shovel Ready. 2. The amount of previously appropriated funding for the project and ability to leverage those funds to create a greater economic impact. Application of the above criteria allows the Coast Guard to complete the maximum number of bridge alterations projects, leverage $120.4M of previous appropriations to the selected projects, and create a $262.4 million stimulative impact on the economies in four different states. In addition, the alteration of these four bridges will have a longer term impact on the economy by ensuring safe navigation on the nation s waterway system and facilitating improved trade and movement of cargo. The recipients and uses of all recovery funds are transparent to the public, and that the public benefits of these funds are reported clearly, accurately, and in a timely manner: Bridge owners will provide a monthly report to the Coast Guard which includes all requirements of the ARRA Act as prescribed in Section 1512 of the Act and OMB Memorandum M-09-10. Based on the contract between the contractors and the bridge owners, contractors will submit certain information to the bridge owners to facilitate development of the monthly reports. No later than the first day of the month, contractors will provide bridge owners with a detailed list of all activities completed during the previous month and the payment received from the bridge owners for each activity including the following: 1. The name of each activity 2. A description of the activity 3. An evaluation of the completion status of the activity 4. Types of jobs (e.g., job titles or broader labor categories) created for these activities 5. An estimate of the number of jobs created and the number of jobs retained by the Contractor during the month to conduct the project s activities 6. Name of any subcontractor participated in the activities and the number of jobs created and retained by subcontractors to conduct the project s activities. 7. The total cost of each activity, payment received, and balance remained to complete the activity 10

8. Copies of all invoices charged to the project during the month 9. Copies of the receipts of all material ordered during the month. 10. Copies of payrolls and Statement of Compliance with the requirements of Davis Bacon Act 11. Steps taken by the Contactor to comply with the requirement of the ARRA to use American iron, steel, and manufactured goods Recovery funds are used for authorized purposes and every step is taken to prevent instances of fraud, waste, error, and abuse: The Coast Guard assigns a qualified Project Manager / Professional Engineer for each bridge project to monitor closely all the activities of the contract and ensure work is completed as planned. No advance payment will be made to the bridge owners. The payment will be authorized after the Project Manager visits the construction site and ensures the work is completed. Projects funded under the recovery legislation avoid unnecessary delays and cost overruns: The Coast Guard reviews all the contract documents and ensures their compliance with the most current bridge engineering specifications to avoid change orders or overruns during constructions. Any change order arising during construction for unexpected site or construction condition must be reviewed and approved by the Coast Guard. The bridge owners are not authorized to approve any change orders without Coast Guard approval. Programs meet specific goals and targets, and contribute to improved performance on broad economic indicators: The Coast Guard expects these projects will create immediate jobs and stimulate the condition of many manufactures and suppliers of construction materials throughout the United States. In addition, the alteration of these bridges will have a long-term effect on the economy by improving navigation on the nation s waterway system and facilitating trade and the movement of goods and cargo between states. 11

X. Transparency The recipients and uses of all recovery funds are transparent to the public. Public benefits of these funds are reported clearly, accurately, and in a timely manner: Internal USCG Transparency The project managers will provide a weekly report to the Coast Guard program offices that include all the requirements of the ARRA Act as prescribed in Section 1512 of the Act and OMB Memorandum M-09-10. The weekly reports will include the following: 1. The name of each activity 2. A description of the activity 3. An evaluation of the completion status of the activity 4. An estimate of the number of jobs created and the number of jobs retained by the Contractor during the month to conduct the project s activities 5. The total cost of each activity, fund obligations or commitments, and balance remaining to complete the activity External Transparency Project information will be made available to the public and to the private sector via Recovery.gov. Coast Guard spending information (by project) will be posted on Recovery.gov. XI. Accountability The Coast Guard Alteration of Bridges Program will assign licensed professional engineers, who will also be certified as project managers (Level I), to manage the four bridge projects. The Program developed a spend plan for the four bridge alteration construction projects which reflects obligation of ARRA funds during FY09 and expenditure of those funds by Sept 30, 2010. The obligation and expenditures will be managed by the project managers and Coast Guard staff. Projects Manager will ensure that each construction phase will be completed on time and as scheduled to avoid undelivered orders. XII. Barriers to Effective Implementation There are no expected barriers to effective implementation. 12