UNIVERSITY HOSPITALS OF LEICESTER TRUST BOARD 2 MARCH 2017 PAGE 1 OF 6 Emergency Floor Project: Monthly Update

Similar documents
NHS England (London) Assurance of the BEH Clinical Strategy

Workforce Plan Update

Update on implementation of the PPI Strategy

Royal College of Paediatrics and Child Health Service Review Action Plan and Progress Report 26 th May 2016

EXECUTIVE SUMMARY REPORT TO THE BOARD OF DIRECTORS HELD ON 22 MAY Anne Gibbs, Director of Strategy & Planning

NHS England Congenital Heart Disease Provider Impact Assessment

FT Keogh Plans. Medway NHS Foundation Trust

November NHS Rushcliffe CCG Assurance Framework

NOTTINGHAM UNIVERSITY HOSPITAL NHS TRUST. PATIENT ACCESS MANAGEMENT POLICY (Previously known as Waiting List Management Policy) Documentation Control

Strategic Risk Report 12 September 2016

EAST KENT HOSPITALS UNIVERSITY NHS FOUNDATION TRUST

THE HEALTH SCRUTINY COMMITTEE FOR LINCOLNSHIRE

abcdefghijklmnopqrstu

Strategic Risk Report 4 July 2016

DRAFT BUSINESS PLAN AND CORPORATE OBJECTIVES 2017/8

is asked to NOTE the update provided on fragile services.

Aneurin Bevan University Health Board Stroke Services Redesign Programme

Paediatric Cardiac and Adult Congenital Heart Disease: Standards Compliance Assessment

Strategic Risk Report 1 March 2018

University Hospitals of Leicester NHS Trust. Regulation 23 Outcome 14: Supporting Workers

RESPONSE TO RECOMMENDATIONS FROM THE HEALTH & SOCIAL CARE COMMITTEE: INQUIRY INTO ACCESS TO MEDICAL TECHNOLOGIES IN WALES

The Role of The Consultant, The Doctor and The Nurse Mr Gary Kitching Consultant in Emergency Medicine Foundation Training Programme Director

DRAFT CONTINUING HEALTHCARE (CHC) CHOICE & EQUITY POLICY. Version 2

Monthly Nurse Safer Staffing Report May 2018

Debbie Vogler, Director of Business & Enterprise. Kate Shaw, Associate Director of Service Transformation

Performance and Quality Committee

SHEFFIELD TEACHING HOSPITALS NHS FOUNDATION TRUST EXECUTIVE SUMMARY BOARD OF DIRECTORS 17 MAY Kirsten Major, Deputy Chief Executive

TRUST BOARD Annual Operational Plan for 16/17. Author: Gino DiStefano Sponsor: Paul Traynor Trust Board 7 April 2016 updated paper I

LLANDUDNO HOSPITAL PROJECT CYCLE TWO REPORT FOR UNSCHEDULED CARE PROJECT TEAM: IDENTIFICATION OF PREFERRED SERVICE SOLUTIONS MAY 2010

Manchester Health and Care Commissioning Board. A partnership between Manchester. City Council and NHS Manchester Clinical Commissioning Group

Humber Acute Services Review. Question and Answer sheet February 2018

Board of Directors Meeting 6 April Agenda item 31/16

Rapid improvement guide to appointment slot issues

Norfolk and Waveney STP. Meeting with East Suffolk Partnership 27 September 2017

GREATER MANCHESTER HEALTH AND SOCIAL CARE STRATEGIC PARTNERSHIP BOARD

Decision-Making Business Case

Redesigning maternity services in Sandwell and West Birmingham

CONTINUING HEALTHCARE (CHC) CHOICE & EQUITY POLICY

Leicester, Leicestershire and Rutland s Sustainability & Transformation Plan (STP)

The Sustainability and Transformation Plan (STP) for Buckinghamshire, Oxfordshire and Berkshire West (BOB). A short summary.

Appendix 1: Integrated Urgent Care Service Update. 1. Purpose

Approval Discussion Assurance ( )

Trust Board Meeting: Wednesday 13 May 2015 TB

TRUST BOARD TB(16) 44. Summary of Lord Carter recommendations Operational productivity and performance in English acute hospitals

Supporting all NHS Trusts to achieve NHS Foundation Trust status by April 2014

Jo Mitchell, Head of Assurance & Compliance (EFM) Policy to be followed by (target staff) Distribution Method

New Trinity Centre Support Service Care at Home 7a Loaning Road Edinburgh EH7 6JE Telephone:

Welcome to the latest edition of the Accountable Care Network bulletin designed to keep you up to date with integrated care in County Durham.

19 th April The purpose of this paper is to outline the costs, risks and benefits of the above proposals.

Source Question Summary response Action Proposal to set up a review of community services:

REFERRAL TO TREATMENT ACCESS POLICY

Report on actions you plan to take to meet CQC essential standards

West Hertfordshire Hospitals NHS Trust. Operational Plan 2016/17. Summary

MEETING OF THE GOVERNING BODY IN PUBLIC 7 January 2014

DELIVERING THE LEFT SHIFT IN ACUTE ACTIVITY THE COMMUNITY MODEL

NHS TRAFFORD CLINICAL COMMISSIONING GROUP GOVERNING BODY 27 February 2018

21 March NHS Providers ON THE DAY BRIEFING Page 1

2017/2018 Financial Planning Savings Plan

Lincolnshire County Council: Councillors Mrs W Bowkett, R L Foulkes, C R Oxby and N H Pepper

Quality & Safety Sub-Committee

OUTLINE BUSINESS CASE FOR THE DEVELOPMENT OF A&E SERVICES AT ANTRIM AREA HOSPITAL

Leeds West CCG Governing Body Meeting

SuRNICC Full Business Case. Benefits Realisation Strategy and Framework

Supporting all NHS Trusts to achieve NHS Foundation Trust status by April Ipswich Hospital NHS Trust NHS East of England Department of Health

Date of publication: 25/04/2014 Tel: / Date of inspection visit: 12th February 2014

NHS Equality Delivery System for Isle of Wight NHS Trust. Interim baseline assessment against the

REFERRAL TO SECRETARY OF STATE FOR HEALTH Report by Devon County Council Health and Wellbeing Scrutiny Committee Torrington Community Hospital

Primary Care Commissioning Next Steps to Delegated Commissioning September Board Paper. 2.0 Delegated Opportunities, Benefits and Risks

Visit Report on NHS Grampian

Surrey Downs Clinical Commissioning Group Governing Body Part 1 Paper Acute Sustainability at Epsom & St Helier University Hospitals NHS Trust

CQC IMPROVEMENT ACTION PLAN. Page 1 of 86 CQC Improvement Plan (Published 10/8/15)

NHS Northern, Eastern and Western Devon Clinical Commissioning Group

RBCH Actions to meet CQC Essential Standards

Trust Key Performance Indicators

NHS Highland Plan for rebalancing of Primary Care Dental Services

Written Response by the Welsh Government to the report of the Health, Social Care and Sport Committee entitled Primary Care: Clusters

NHS North West London

Eastercroft House Nursing Home Care Home Service Adults Airdrie Road Caldercruix Airdrie ML6 8NY Telephone:

Five Reconfiguration Tests Self-assessment (Path to Excellence Phase 1a)

Full Business Case. County Hospital Outpatients (Executive Summary) May Contents

17. Dementia: John s Campaign

RTT Assurance Paper. 1. Introduction. 2. Background. 3. Waiting List Management for Elective Care. a. Planning

Care of Critically Ill & Critically Injured Children in the West Midlands

SUBJECT: Medical Staffing Update Report 1. PURPOSE

APPENDIX 7C BENEFITS REALISATION PLAN

PERTH AND KINROSS COUNCIL. Housing and Health Committee. 2 November Integrated Health and Social Care Model for Dalweem Care Home, Aberfeldy

Policy and Resources Committee 13 February 2018

Meeting of Bristol, North Somerset and South Gloucestershire Clinical Commissioning Group Governing Body Meeting In-Common

A concern means any complaint, claim or reported patient safety incident.

CLINICAL STRATEGY IMPLEMENTATION - HEALTH IN YOUR HANDS

Hard Truths Public Board 29th September, 2016

NAME SPECIALTY PLEASE NOTE THAT THE CONSULTANT SURGEONS RUN A 4 WEEK ROLLING ROTA OF ACTIVITY. (HENCE THE 'BUSY' JOB PLAN)

Operational Plan 2018/19

Procurement of Prevention and Wellbeing Training

Recommendations for safe trainee changeover

Supporting children and young people with healthcare needs in schools

PRIMARY CARE COMMISSIONING COMMITTEE MEETING

Sussex Community NHS Trust Action Plan in Response to Recommendations Made by CQC

An Outline Business Case for the New Emergency Centre (Phase 1) at New Cross Hospital

Better Healthcare in Bucks Reconfiguring acute services

Transcription:

UNIVERSITY HOSPITALS OF LEICESTER TRUST BOARD 2 MARCH 2017 PAGE 1 OF 6 Emergency Floor Project: Monthly Update Author: Jane Edyvean Sponsor: Richard Mitchell EXECUTIVE SUMMARY Paper J Context Construction of Phase 1 of the Emergency Floor Project will be completed within the next week. The Trust will take possession of the building from 6 th March 2018. We will then mobilise our final preparations for the opening of the new facility on April 26 th 2017. The primary focus of this paper is to provide the Trust Board with an update on delivery of the detailed plans in order that our staff, our partners across the Health and Social Care Community and our patients are informed and ready for the move. Information is also provided on closure of the Balmoral entrance to the LRI and progress made towards developing Phase 2 of the project. Questions 1. Does this report provide the Trust Board with sufficient and appropriate assurance on progress that is being made to safely open the new department on 26th April 2017? 2. Is the Trust Board satisfied that the high rated risks are being managed in such a way that there will be no delays in the date of opening Phase 1 and start of Phase 2? Conclusion 3. This report provides an overview of the significant progress that continues to be made in preparation for the opening of Phase 1 and the work that is now beginning on the development of Phase 2. The attached detailed report focusses on the key project issues and risks and how they are being mitigated. These continue to be: Single Front Door for Childrens Emergencies; Operational commissioning state of readiness for the move; IT; Workforce ; Getting ready for the start of Phase 2; Finance. Input Sought The Trust Board is requested to note:

UNIVERSITY HOSPITALS OF LEICESTER PAGE 2 OF 6 That the Trust will take possession of the new building in a few days and on time; That the focus will shift to undertaking preparatory activities at pace from within the new building (staff familiarisation, training and equipping); The progress that has been made in recruiting to vacancies The actions to address IT and financial matters; Note the status of Phase 2 and next steps. For Reference Edit as appropriate: The following objectives were considered when preparing this report: Safe, high quality, patient centred healthcare Effective, integrated emergency care Consistently meeting national access standards Integrated care in partnership with others Enhanced delivery in research, innovation & ed A caring, professional, engaged workforce Clinically sustainable services with excellent facilities Financially sustainable NHS organisation Enabled by excellent IM&T This matter relates to the following governance initiatives: Organisational Risk Register Board Assurance Framework No Related Patient and Public Involvement actions to be taken: Access and Way finding Results of any Equality Impact Assessment relating to this matter: Completed Scheduled date for the next paper on this topic: April 2017 Executive Summaries should not exceed 1 page. My paper does not comply Papers should not exceed 7 pages. My paper does not comply 2

UNIVERSITY HOSPITALS OF LEICESTER PAGE 3 OF 6 Emergency Floor Project Update UPDATE FROM LAST MONTH 1. Phase 1 of the Emergency Floor Development continues to progress to plan. The contractors will hand over the new building to the Trust on 6 th March 2017. 2. The revised date for opening, 26 th April 2017 will also be the day on which the Balmoral entrance to the LRI site will close. The same date has been chosen for specific reasons, particularly the need to have communications to our staff, patients, members of the public and others that is not conflicting or confusing. In closing the Balmoral entrance simultaneously with the opening of the new ED we are only asking people to change what they do once. New internal and external wayfinding/signage throughout the and a clear communications and engagement campaign will support this. Works are underway to alter to the Havelock Street Car Park and Winsdor entrance which will be complete by the 26th April 2017. There is also a necessity to close the Balmoral entrance at this time in order to allow for the decommissioning of the existing emergency department in readiness for Phase 2 works to start. 3. This delay is based on the need to allow sufficient time for all the essential preparatory activities to be undertaken to support a safe and successful move into the new department. This will delay the start of Phase 2. The financial consequences of this have been reported to the EF Project Board, Reconfiguration Board and the Capital Monitoring and Investment Committee. 4. The detailed plans that will lead to the opening of a safe and fully functioning new Emergency Department are now being implemented with no reported delays. Delivery continues to be monitored weekly through the delivery group to provide the necessary level of confidence that the new department will open on time and that out teams are well prepared for the move. 5. Once the Trust takes possession of the building substantial amounts of time will be spent in the building both to train and familiarise staff with their new environment as well as to make sure that the department is fully equipped and ready for use. 6. An extensive procurement, equipment and logistics plan was presented to the Emergency Floor Project Board in early February detailing the scale of daily activities required in order to receive, install and test equipment ready for use. The depth of detail within the plan provided a high level of assurance to project Board members. The coordination of the plan will be crucial for the effective execution of the plan. Individuals have been assigned to ensure this happens and that there are no delays in the execution of the plan. 7. A detailed programme of staff training and familiarisation activities has been developed. There is a risk that sessions get cancelled due to on-going operational pressures. To prevent this from happening staff on duty have been doubled up over a precise period of time to make sure that staff have time to attend sessions that will be held within the new building. Organisational Development (OD) specialists and the Training and Development team will provide support throughout this period. The clinical leadership team are also expected to deliver these sessions. 8. An interim model to support the implementation of the Single Front Door for Children s Emergency services has been agreed. As previously explained this is to allow time for new processes to be put into place in the Children s Hospital to create sufficient bed base for admitted children once the Childrens Assessment Unit (CAU) closes. It is 3

UNIVERSITY HOSPITALS OF LEICESTER PAGE 4 OF 6 proposed that the full model will be implemented from 1st July 2017. Delivery of the action plans to achieve this will continue to be monitored by the Oversight Group. 9. The IT solutions to support the delivery of new ways of working continue to be progressed. The biggest development concerns the integration of 2 systems, Nervecentre and SystemOne MIU module. This exciting development will enable a single booking in process for our patients and will also provide GP s working within the Blue Zone access to patient s records within GP practice. Currently there are challenges on timescale, the technical requirements to achieve integration and fulfilment of NHS Digital requirements in order that integration between the 2 systems can happen. Executive level support is being provided to facilitate this. 10. The appraisal of costs for the next phase of development, Phase 2 of the Emergency Floor Scheme, are going through final confirm and challenge. The final capital costs for Phase 2 (including costs associated with the delays to the start date) will now be presented to the Emergency Floor Project Board and the Capital Monitoring and Investment Committee in March 2017 for approval. CURRENT ISSUES Closure of Balmoral entrance 11. Opening the new department will have a significant impact on the way in which staff, patients, visitors and others enter the hospital and go to and from their required destination. Work continues to progress at pace to redirect traffic away from the Balmoral entrance and to re-create a new main entrance at the Windsor end of the hospital site. Essential works to improve way finding, signage, pathways and the facilities at the Windsor reception will be in place by 26 th April 2017. This will mean that the Balmoral entrance to the LRI site can close on the same day as the new ED opens. The timings of the closure are to be confirmed. There is a clear communications and engagement plan to support the closure which includes changes to the way in which our patients and staff access the LRI site will also mean changes to maps and letters that are sent to patients about their in-patient, day case or outpatient appointments.. Phase 2 12. Phase 2 building works will now start on 8 th May 2017. A revised programme has been developed which suggests that the scheme will be completed in March 2018. The costs for Phase 2 have now been received and are undergoing the final stages of confirm and challenge. Currently there is an overall reported cost pressure for this phase of the scheme which is due for further financial scrutiny before costs can be confirmed. It is anticipated that the final schedule of costs will be presented to the Emergency Floor Project Board and the Capital Monitoring and Investment Committee in March 2017 for approval. Operational commissioning 13. A comprehensive master plan that will lead to the opening of a safe and fully functioning new Emergency Department is now in place. Delivery of the detailed daily and weekly tasks is being monitored weekly through a weekly held delivery group. This pulls together and coordinates work across of a number different workstreams such as Estates and Facilities, Equipment, Procurement, communications, workforce and Organisational Development (OD).There is now a high level of assurance that all the necessary actions are identified in order that the new department will be opened on time on 26 th April 2017. 4

UNIVERSITY HOSPITALS OF LEICESTER PAGE 5 OF 6 14. An external desktop review of the final draft master plan was commissioned in order to provide a final level of assurance. This work has bene completed. A report on the outcome was presented to the EF Project Board on 6 th February 2017. A RAG rating of amber/green was given along with further assurances that there were no significant concerns. The recommendations from the report have been addressed within the refresh of the master plan. 15. Given the importance of getting this right for our staff and patients delivery of the master plan on time and with the right engagement continues to be the top priority for the Project. 16. Resources within the EF project team continue to be focussed on supporting the teams in getting ready for the opening. The Head of Operations and the senior management Team, supported by the dedicated OD specialist are actively engaged in delivering this programme of activities. Flexible support is being offered to ensure that the understood operational pressures do not impede delivery of the master plan. Staffing rotas have been developed to make sure that staff can be released when required to complete training, induction, simulation and familiarisation activities. Pulse check surveys and other wellbeing and engagement initiatives are being used to help support staff to prepare for the transition from the old to the new. 17. The frequency of visits to the new ED will increase considerably after 6 th March 2017 so that all members of staff have the opportunity to become familiar with their new working environment. A temporary suspension of visits, on the grounds of safety and the need for the contractors to complete on time, has not impacted on delivery of the master plan. 18. The current reported risks to the delivery of the master plan concern IT, finance and logistics associated with the equipping and procurement plans. The first risk remains an issue but mitigation is in place. The logistics risk has been addressed and there is now a comprehensive plan in place to ensure that the coordination of supplies, receipt of orders, installation and staff familiarisation and training happens by zone. Updates on how the plan is being delivered will be discussed at future EF Project Board meetings. 19. Days for training and familiarisation with our partners in the wider community to make sure they are well prepared to support the hospital in opening the new department have been scheduled. This should help the Trust ascertain what support is needed and inform these services of any access and procedural changes they will need to adopt. Workforce 20. Recruitment to vacant posts was a previous area of concern. This situation has changed due to the impact of a concerted recruitment campaign. The number of reported vacancies has reduced considerably with further recruitment initiatives underway. Currently there are 41.69wte registered nursing and 10.28 wte Healthcare Assistant (HCA) vacancies within the ED. The successful recruitment campaign has reduced this to 12.69wte registered nursing and 2.71 wte HCA vacancies over the forthcoming weeks. These figures include overseas recruitment where there have been unforeseen delays. The ED will continue to progress these appointments as it is likely that some vacancies will remain and there will be natural turnover. Single front door for Children Emergency Pathway 21. The new Childrens Emergency Department is designed to provide a single point of entry for all children presenting with an emergency condition. Currently this is 5

UNIVERSITY HOSPITALS OF LEICESTER PAGE 6 OF 6 delivered in three different locations. This model is supported by our Commissioners. For the model to be implemented safely and effectively, processes need to be in place to ensure the availability of beds within the children s hospital to receive the sickest children who require admission to hospital. An interim model has been agreed by the clinical teams and members of the Oversight Group to allow adequate time for these processes to be put in place. This will mean that the Childrens Assessment Unit (CAU) will remain open between 26 th April 2017 and 1 st July 2017 and that the Children s Emergency Department will open 8 Paediatric Observation Ward Beds between 12midday and midnight. This facility will care for those children who need a longer period of observation (up to 18 hours) and who do not need admission. The EF Project Board have been advised that this interim solution can be delivered within the agreed financial plan for the new department. The Single Front Door will become fully operational on 1st July 2017.Our commissioners have been informed of this decision. Capital cost pressures 22. As reported in the previous month the EF Project was facing IT Capital cost pressures as a consequence of the EPR business case being unfunded resulting in a mismatch between the IT equipment requested and the budget for this. Approval was given by the CMIC to support these cost pressures with the understanding that the allocation of IT costs identified within the full business case for the whole EF Project will be fully used in Phase 1. There are emerging concerns that additional funding may be required for Phase 2, however this is subject to further work. The full extent of the capital requirements for the remainder of the project are being re- evaluated and a final capital cost confirmed in early March. Revenue consequences of Phase 1 23. The revenue consequences following the opening of Phase 1, above and beyond the workforce costs, have been reassessed against the original FBC assumptions. Some of the revenue consequences have been addressed through confirmation of the funding available to support the workforce plan. Work is now being undertaken by the ESM CMG to review the workforce plan and to agree what controls need to be in place so that expenditure in 2017/18 does not exceed the level of funding available. This includes plans to minimise vacancies and reduce premium spend. RECOMMENDATIONS The Trust Board is requested to note: That the Trust will take possession of the new building in a few days and on time; That the focus will shift to undertaking preparatory activities at pace from within the new building (staff familiarisation, training and equipping); The progress that has been made in recruiting to vacancies The actions to address IT and financial matters; Note the status of Phase 2 and next steps. 6