Lessons Learned from Prior Reports on Disaster-related Procurement and Contracting

Similar documents
Insurance & Federal Claims Services (IFCS)

Office of Inspector General Audit Tips for FEMA Public Assistance Grant Recipients and Subrecipients

Averting a Second Disaster: Leading Financial Oversight Practices in Mitigation and Disaster Grant Programs ASFPM 2016 June 14, 2016

Office of Inspector General Annual Work Plan

Department of Homeland Security

Coast Guard IT Investments Risk Failure Without Required Oversight

North Carolina Department of Public Safety Division of Emergency Management

Delayed Federal Grant Closeout: Issues and Impact

Department of Homeland Security Office of Inspector General

Department of Contracts, Grants and Financial Administration, Texas Education Agency 1/26/18

TEXAS GENERAL LAND OFFICE COMMUNITY DEVELOPMENT & REVITALIZATION PROCUREMENT GUIDANCE FOR SUBRECIPIENTS UNDER 2 CFR PART 200 (UNIFORM RULES)

OIG AUDIT A GRANTEE S PERSPECTIVE

Averting a second disaster: avoiding grant deobligation

This appendix provides the following Federal and State Regulations related to the Hazard Mitigation Planning process.

Department of Homeland Security Office of Inspector General. The United States Coast Guard's Program for Identifying High Interest Vessels

Hurricane Harvey s Fiscal Impact on State Agencies PRESENTED TO HOUSE APPROPRIATIONS COMMITTEE LEGISLATIVE BUDGET BOARD STAFF

- Thank you for participating in the viewing of the Texas General Land Office s Community Development and Revitalization Program s, or GLO-CDR video

Civic Center Building Grant Audit Table of Contents

February 1, Dear Mr. Chairman:

FEMA Reimbursement Will They or Won't They?

CHAPTER 1. Chapter 1 Introduction Mobile County Multi-Hazard Mitigation Plan. 1.1 Background. 1.2 Authority

Office of Inspector General

HAZARD MITIGATION GRANT PROGRAM. Federal Emergency Management Agency

Topics 6/28/2017. U.S. Department of Transportation Office of Inspector General (OIG) OIG Audits Impact DOT Oversight. Heads Up on Future Issues

Using Internal Audits for Successful Grant Administration

Mississippi Financial Management Support Annex

Updated Hurricane Harvey s Fiscal Impact on State Agencies PRESENTED TO SENATE FINANCE COMMITTEE LEGISLATIVE BUDGET BOARD STAFF

Federal Grants-in-Aid Administration: A Primer

OFFICE OF AUDIT REGION 9 f LOS ANGELES, CA. Office of Native American Programs, Washington, DC

All Commonwealth of Pennsylvania State Agencies, Counties and Municipalities. By Direction of:

Agency Information Collection Activities: Proposed Collection; Comment Request; AGENCY: Federal Emergency Management Agency, DHS.

Office of Inspector General Annual Report

Program Management Plan

Rebuilding Texas after Hurricane Harvey Operational Plan

Federal Grant Guidance Compliance

HOMELAND SECURITY GRANT PROGRAM (HSGP) State Project/Program: DIVISION OF EMERGENCY MANAGEMENT

HOMELAND SECURITY GRANT PROGRAM (HSGP) State Project/Program: HOMELAND SECURITY GRANT PROGRAM

OVERSIGHT OF GULF COAST HURRICANE RECOVERY

DCMC PARTNERS. Alternative Procedures for Permanent Work (428) In Puerto Rico March 29, 2018

Department of Homeland Security Office of Inspector General

Presentation. I. HMGP Overview II. III. IV. Application Review Process Post Obligation Information Common Errors

PUBLIC ASSISTANCE: PURCHASING GOODS OR SERVICES THROUGH COOPERATIVE PURCHASING PROGRAMS

The Office of Innovation and Improvement s Oversight and Monitoring of the Charter Schools Program s Planning and Implementation Grants

Hurricane Matthew October 10, 2016 Categories A & B

FINANCING THE FLOOD. FEMA Public Assistance (PA) and Hazard Mitigation Grant Programs (HMGP) Facilitator: Corey Thomas Thompson Consulting Services

U.S. Department of Housing and Urban Development Office of Housing Counseling

Report No. DODIG U.S. Department of Defense SEPTEMBER 28, 2016

REQUEST FOR PROPOSALS CITY OF PORT LAVACA

Proposal for Comprehensive Disaster Recovery, Financial and Grant Management Support, and Pre- Disaster Cost Recovery Planning Services

Company Profile Phillips & Jordan, Inc. Key Markets

To Chairman Johnson, Ranking Member McCaskill, Chairman Shuster, and Ranking Member DeFazio:

FLOOD MITIGATION ASSISTANCE PROGRAM State Project/Program: N.C. MITIGATION

PEACE CORPS INSPECTOR GENERAL. Annual Plan. Mission

A-133 Single Audits: Common Audit Findings & Ways to Mitigate and Prevent Them

FEDERAL TRANSIT TECHNICAL STUDIES GRANTS. U. S. Department of Transportation. N. C. Department of Transportation Public Transportation Division

EMERGENCY MANAGEMENT. Implementation of the Major Disaster Declaration Process for Federally Recognized Tribes

LA14-11 STATE OF NEVADA. Performance Audit. Department of Public Safety Division of Emergency Management Legislative Auditor Carson City, Nevada

EMERGENCY SHELTER GRANTS PROGRAM EMERGENCY SHELTER GRANTS PROGRAM. U. S. Department of Housing and Urban Development

Improper Payments for Recipients No Longer Enrolled in Managed Long Term Care Partial Capitation Plans. Medicaid Program Department of Health

GUIDANCE. Funds for Title I, Part B of the Rehabilitation Act of 1973, as amended. Made Available Under

Navigating the New Uniform Grant Guidance. Jack Reagan, Audit Partner Grant Thornton LLP. Grant Thornton. All rights reserved.

COMMUNITY DEVELOPMENT BLOCK GRANT- DISASTER RECOVERY ORIENTATION WEBINAR PRESENTED BY: HEATHER MARTIN

Safeguarding Federal Funds

Community Development Block Grant Disaster Recovery Funding. During the 2004 hurricane season, four major hurricanes devastated many areas of

Ohio Enterprise Grants & Common Grants Compliance Issues

Housing Authority of the City of Comer, GA

Emergency Supplemental Appropriations for DoD Needs Arising From Hurricane Katrina at Selected DoD Components

EMERGENCY SHELTER GRANTS PROGRAM EMERGENCY SHELTER GRANTS PROGRAM. U. S. Department of Housing and Urban Development

Summary of the Office of Management and Budget s Uniform Guidance for Federal Grants and its Impact on Federal Education Programs

REQUEST FOR PROPOSAL Comprehensive Disaster Recovery, Financial and Grant Management Support, and Pre-Disaster Cost Recovery Planning Services

Have we had any Disasters lately? 10/17/2017. City of Los Angeles Emergency Management Department

Oversight of Gulf Coast Hurricane Recovery

Report No. D-2011-RAM-004 November 29, American Recovery and Reinvestment Act Projects--Georgia Army National Guard

CORPORATION FOR PUBLIC BROADCASTING

Playing by the Rules

STATE OF NORTH CAROLINA OFFICE OF THE STATE AUDITOR BETH A. WOOD, CPA

FEMA Grant Program Comparison

Department of Homeland Security Office of Inspector General

FINAL AUDIT REPORT DEPARTMENT OF COMMUNITY AFFAIRS WEATHERIZATION ASSISTANCE PROGRAM ARRA IMPLEMENTATION FEBRUARY 14, 2009 THROUGH JANUARY 31, 2010

FRANKLIN AYETIN ATTORNEY ADVISOR FEMA PROCUREMENT DISASTER ASSISTANCE TEAM (PDAT)

HIGHWAY PLANNING AND CONSTRUCTION SAFE ROUTES TO SCHOOL PROGRAM (SRTS) U. S. Department of Transportation

The Uniform Guidance and Procurement TEXAS ASSOCIATION OF COUNTY AUDITORS

Alteration of Bridges

Report No. DODIG U.S. Department of Defense MARCH 16, 2016

OMB Uniform Guidance: Cost Principles, Audit, and Administrative Requirements for Federal Awards

GAO. EMERGENCY MANAGEMENT Actions to Implement Select Provisions of the Post- Katrina Emergency Management Reform Act

Subrecipient Profile Questionnaire

Procurement Requirements for State and Entitlements CDBG-DR Grantees

CHAPTER 20: DISASTER RECOVERY (CDBG-DR)

History of Flood and Flames: Emergency Preparedness of Yuba County

HIGHWAY CONSTRUCTION PROGRAM. N. C. Department of Transportation (Research and Development) (Construction and Maintenance)

GAO MILITARY BASE CLOSURES. DOD's Updated Net Savings Estimate Remains Substantial. Report to the Honorable Vic Snyder House of Representatives

Report No. DODIG Department of Defense AUGUST 26, 2013

GOVERNMENT RESPONSE FUNDING

FISCAL YEAR FAMILY SELF-SUFFICIENCY PROGRAM GRANT AGREEMENT (Attachment to Form HUD-1044) ARTICLE I: BASIC GRANT INFORMATION AND REQUIREMENTS

GULF COAST ECOSYSTEM RESTORATION COUNCIL COMPREHENSIVE PLAN COMPONENT PROGRAM

FLOOD MITIGATION ASSISTANCE PROGRAM

Maximizing Hazard Mitigation Grant Funds for Post Irma Recovery. Florida Hospital Association. Thursday, February 22, 2018 WELCOME!

FLOOD MITIGATION ASSISTANCE PROGRAM

Community Development Block Grant Applicant Guide

Transcription:

Lessons Learned from Prior Reports on Disaster-related Procurement and Contracting December 5, 2017 OIG-18-29

DHS OIG HIGHLIGHTS Lessons Learned from Prior Reports on Disaster-related Procurement and Contracting December 5, 2017 Why We Did This Report This is a Department of Homeland Security Office of the Inspector General (OIG) special report on Federal Emergency Management Agency (FEMA) and FEMA recipient and subrecipient disaster-related procurements. This report describes lessons learned regarding disasterrelated procurements based on issues and observations from previous DHS OIG reports. What We Recommend This report contains no recommendations. For Further Information: Contact our Office of Public Affairs at (202) 254-4100, or email us at DHS-OIG.OfficePublicAffairs@oig.dhs.gov What We Found FEMA is currently responding to some of the most catastrophic disasters in U.S. history Hurricanes Harvey, Irma, Maria, and the October 2017, California wildfires. Because of the massive scale of damage and the large number and high-dollar contracts that will likely be awarded, there is a significant risk that billions of taxpayer dollars may be exposed to waste, fraud, and abuse. The issues and observations we have described in our previous reports clearly point to FEMA s ongoing failures to oversee its grant recipients (grantees). FEMA is responsible for monitoring recipients to ensure they are performing proper grant administration. Grant recipients, in turn, must manage subrecipients to ensure grant fund expenditures comply with Federal procurement requirements. Noncompliance can result in high-risk contracts that may lead to excessive and ineligible costs. In addition, failure to follow these requirements can hinder many of the socioeconomic goals Congress intended. During the initial recovery phase of these disasters, it is imperative that FEMA ensures that grant recipients (states and tribal governments) effectively manage their disaster relief grants. In doing so, the states must also ensure that their subrecipients have adequate procurement policies and procedures and fully comply with Federal procurement requirements. These measures should provide reasonable, but not absolute, assurance that the grant funds are spent properly and mitigate the risk of taxpayers bearing ineligible and excessive costs. www.oig.dhs.gov OIG-18-29

Washington, D.C. 20528 / www.oig.dhs.gov DEC 5 2017 MEMORANDUM FOR: Jeffrey Byard Associate Administrator Office of Response and Recovery Federal Emergency Management Agency FROM: SUBJECT: John E. McCoy II Acting Assistant Inspector General for Audits Lessons Learned from Prior Reports on Disaster-related Procurement and Contracting Attached is our final report, Lessons Learned from Prior Reports on Disasterrelated Procurement and Contracting. This report was prepared under the Inspector General Act of 1978, as amended, and more specifically, Section 2-2, to provide leadership and coordination and recommend policies for activities designed to promote economy, efficiency, and effectiveness in the administration of, and to prevent and detect fraud and abuse in, such programs and operations. This report is based on issues and observations described in previous Office of Inspector General (OIG) audits of subrecipients procurement performance since 2015. We are providing this report to reemphasize to Federal Emergency Management Agency (FEMA) leadership the potential procurement challenges that will likely arise during the recovery phases of Hurricanes Harvey, Irma, Maria, and the October 2017, California wildfires. It contains no recommendations but highlights the need for FEMA to maintain and, where necessary, implement effective controls to ensure grant recipients effectively manage their disaster relief grants. FEMA is responsible for monitoring grant recipients to ensure they are performing proper grant administration. Grant recipients, in turn, must manage subrecipients to ensure grant fund expenditures comply with Federal procurement requirements. Consistent with our responsibility under the Inspector General Act, we will provide copies of this report to appropriate congressional committees with oversight and appropriation responsibility over the Department of Homeland Security. We will post the report on our website for public dissemination. Please call me with any questions, or your staff may contact Paul Wood, Acting Deputy Assistant Inspector General for Audits, at (202) 254-4100 or Paige Hamrick, Director, Disaster and Immigration, at (214) 436-5200. www.oig.dhs.gov

Background The Federal Emergency Management Agency (FEMA) is currently responding to Hurricanes Harvey, Irma, Maria, and the October 2017, California wildfires which are considered to be some of the most catastrophic disasters in U.S. history. On August 25, 2017, Hurricane Harvey made landfall in the Gulf Coast portion of Texas as a Category 4 hurricane. It caused catastrophic flooding and widespread destruction. Two weeks later, Hurricane Irma devastated the Caribbean region as a Category 5 hurricane, before making landfall in Florida as a Category 4 hurricane. Shortly thereafter, Hurricane Maria hit Puerto Rico as a Category 4 hurricane, leaving 100 percent of the territory without power. Many lives have been lost to these disasters and hundreds of thousands have been displaced from their homes. As FEMA responded to three major hurricanes on the east coast, on the west, the most destructive wildfires in California s history devastated northern California. During October 2017, wildfires that ignited in California destroyed more than 245,000 acres, an estimated 8,400 structures, and resulted in the loss of 42 lives. In response to the hurricanes and wildfires, the President signed seven major disaster declarations, providing Individual Assistance, Public Assistance, and Hazard Mitigation to affected communities within the designated areas. Because of the massive scale of damage and the large number and high-dollar contracts that will likely be awarded, there is a significant risk that billions of taxpayer dollars may be exposed to waste, fraud, and abuse. Each year, our audit reports identify significant procurement-related issues representing millions of dollars of Federal funds. These reports also contain recommendations to assist FEMA in addressing the issues identified and improving related controls. The majority of our audits focus on grants under FEMA s Public Assistance (PA) program and Hazard Mitigation Grant Program (HMGP), both funded from the Disaster Relief Fund. 1 To assist in the recovery from major disasters such as Hurricanes Harvey, Irma, Maria, and the California wildfires, FEMA provides grants to states, tribal and local governments, and certain types of private nonprofit organizations. Our audit reports have continually identified significant procurement-related issues that stem from failures by grant recipients to provide adequate guidance and grant management to subrecipients on following Federal requirements. 1 The Disaster Relief Fund (DRF) is an appropriation against which FEMA can direct, coordinate, manage, and fund eligible response and recovery efforts associated with domestic major disasters and emergencies that overwhelm state resources pursuant to the Robert T. Stafford Disaster Relief and Emergency Assistance Act, Public Law 93-288, as amended, 42 United States Code (U.S.C.) 5121 et seq. www.oig.dhs.gov 2 OIG-18-29

Recurrent Improper Procurement-Related Issues During fiscal years 2015 through June 2017, we questioned more than $256 million in ineligible contract costs because subrecipients did not follow Federal procurement regulations (see table 1). Additionally, we identified more than $191 million in ineligible costs that subrecipients may have incurred had we not identified the procurement problems before FEMA obligated disaster assistance grant funds. Our reports clearly point to ongoing failures by subrecipients to comply with Federal procurement requirements. We also noted that grant recipients (grantees) failed to provide subrecipients with adequate guidance and grant management. These findings highlight that FEMA does not effectively monitor grant recipients or effectively enforce procurement rules. 2 Table 1: FY 2015 2017 Questioned Costs and Cost Avoidance Fiscal Year Questioned Costs Cost Avoidance 2015 $ 130,262,235 $ 50,510,883 2016 86,182,478 121,703,365 2017 40,505,093 19,148,472 Totals $256,949,806 $191,362,720 Source: Office of Inspector General (OIG) compilation and analysis of issued reports These questioned and avoided costs resulted from multiple procurementrelated failures, including but not limited to the following: Failure to provide full and open competition (2 Code of Federal Regulation (CFR) 200.319(a)) o As a result, FEMA had no assurance that incurred costs were reasonable, and there was an increased risk for fraud, waste, and abuse. Failure to take all affirmative steps to assure the use of disadvantaged businesses when possible (2 CFR 200.321) o As a result, small and minority firms, women s business enterprises, and labor surplus area firms may not have received sufficient opportunities to bid on federally funded work. Failure to include all required contract provisions (2 CFR 200.326) o As a result, there was an increasing risk of misinterpretations, errors in pricing, scopes of work, and contract disputes. Failure to verify whether contractors were suspended, debarred, or otherwise excluded or ineligible (2 CFR 200.213) 2 For example, over the 6-year period ended September 30, 2014, our audits questioned $352.3 million in PA grant costs for noncompliance. FEMA officials subsequently ruled that $321.7 million, or 91.3 percent, of those costs were eligible. We questioned those costs because subrecipients did not follow Federal procurement rules when awarding contracts (see FEMA Can Do More to Improve Public Assistance Grantees and Subgrantees Compliance with Federal Procurement Rules, OIG-16-126-D). www.oig.dhs.gov 3 OIG-18-29

o As a result, U.S. taxpayers were not protected from potential financial risks posed by such contractors. In recent years, FEMA implemented a Procurement Disaster Assistance Team to provide procurement-specific training to its grant recipients (grantees) as well as offer other procurement-related resources such as a contracting checklist. However, we continue to identify instances in which the states, as grant recipients, failed to ensure that their subrecipients comply with the Federal procurement requirements. These failures can result in high-risk contracts that, in turn, may lead to excessive and ineligible costs. In addition, failure to follow Federal procurement requirements hinders many of the socioeconomic goals intended by Congress to provide disadvantaged firms with sufficient opportunities to compete for federally funded work. Without full and open competition, the risk of favoritism, collusion, fraud, waste, and abuse are increased. Therefore, it is critical that FEMA ensure its grant recipients and subrecipients are fully aware of, and comply with, all Federal procurement requirements during all disaster-related events, particularly Hurricanes Harvey, Irma, Maria, and the California wildfires. Subrecipients Should Be Made Aware of Federal Procurement Requirements Before Contracting It is imperative that FEMA ensure grant recipients provide subrecipients with timely, accurate, and complete procurement guidance. Furthermore, grant recipients must ensure subrecipients are fully aware of all Federal procurement requirements before subrecipients award contracts for disaster-related work. Compliance with Federal procurement requirements is especially important during the early days of disaster recovery. Procurement practices that do not comply with Federal requirements can lead to high-risk contracts that can result in U.S. taxpayers bearing excessive and ineligible costs. We repeatedly identify procurement-related issues in which the subrecipient fails to fully and openly solicit from all qualified bidders, including small and minority businesses and women s business enterprises. However, when we have questioned costs for noncompliance with Federal standards, FEMA has ruled the costs to be eligible 91.3 percent ($327.1 million) for the 6 years ended September 30, 2014. For example, in January 2017, we recommended FEMA disallow more than $31.7 million awarded to a subrecipient who failed to follow the Federal procurement requirements. FEMA officials agreed with our recommendation because they would not have assurance that the costs were reasonable or that the subrecipient had selected the most qualified contractors to perform the disaster-related work. These issues resulted, in part, from failures by the grant www.oig.dhs.gov 4 OIG-18-29

recipient to provide the subrecipient with adequate guidance and grant management. This lack of compliance with Federal regulations increases the risk of favoritism, collusion, fraud, waste, and abuse. Therefore, it is imperative that FEMA ensure its recipients and subrecipients are made fully aware of all Federal requirements before they procure for these and all disaster-related services; and that they closely monitor its recipients grant management activities. Conclusion During the initial recovery phases of Hurricanes Harvey, Irma, Maria, and the California wildfires, it is imperative that FEMA ensure its grant recipients provide subrecipients with timely, accurate, and complete procurement guidance and ensure they are made fully aware of all Federal procurement requirements. Subrecipients must have adequate procurement policies and procedures in place to reduce the risk of losing Federal funding due to improperly procured contracts. FEMA must closely monitor its recipients grant management activities. Doing so should provide reasonable, but not absolute, assurance that Federal disaster assistance grant funds are spent properly and that the risk of ineligible and excessive costs borne by taxpayers is mitigated. The Office of Audit major contributors to this report are: Paige Hamrick, Director; John Polledo, Audit Manager; David B. Fox, Audit Manager; Dana Smith, Auditor-in-Charge; Josh Welborn, Auditor; Evette Fontana, Auditor; Victor Du, Independent Reference Reviewer; and Kevin Dolloson, Communications Analyst. www.oig.dhs.gov 5 OIG-18-29

Appendix A Objective, Scope, and Methodology Our objective of this special review was to proactively remind FEMA of the potential procurement challenges that will likely arise during the recovery phases of Hurricanes Harvey, Irma, Maria, and the California wildfires. To accomplish our objective, we compiled and summarized disaster assistance reports issued in fiscal years 2015 through 2017; analyzed findings and recommendations in those reports; identified and quantified types of frequently reported procurement findings in grant reports; quantified the potential monetary benefits of report findings related to non-compliance with Federal procurement regulations; and performed other procedures we considered necessary to accomplish our objective. In addition, we reviewed: DHS Summary and Key Findings of Fiscal Year 2015 FEMA Disaster Grant and Program Audits, issued November 29, 2016; and DHS Summary and Key Findings of Fiscal Year 2016 FEMA Disaster Grant and Program Audits, [draft]. This report was prepared under the Inspector General Act of 1978, as amended, and more specifically, Section 2-2, to provide leadership and coordination and recommend policies for activities designed to promote economy, efficiency, and effectiveness in the administration of, and to prevent and detect fraud and abuse in, such programs and operations. The work performed in this review does not constitute an audit in accordance with generally accepted government auditing standards. www.oig.dhs.gov 6 OIG-18-29

Appendix B Fiscal Years 2015 to 2017 Disaster Grant and Subgrant Reports Fiscal Year Issued Report Number Questioned Amount Cost Avoidance FY 2015 OIG-15-03-D $ 0 $ 13,768,371 FY 2015 OIG-15-30-D 0 13,477,236 FY 2015 OIG-15-34-D 0 22,540,761 FY 2015 OIG-15-35-D 3,597,189 0 FY 2015 OIG-15-48-D 395,032 0 FY 2015 OIG-15-65-D 82,360,247 0 FY 2015 OIG-15-101-D 3,749,440 0 FY 2015 OIG-15-106-D 21,740 0 FY 2015 OIG-15-111-D 4,845,106 0 FY 2015 OIG-15-113-D 4,010,222 0 FY 2015 OIG-15-119-D 0 724,515 FY 2015 OIG-15-123-D 353,154 0 FY 2015 OIG-15-126-D 994,224 0 FY 2015 OIG-15-131-D 21,711,231 0 FY 2015 OIG-15-132-D 1,551,884 0 FY 2015 OIG-15-135-D 973,778 0 FY 2015 OIG-15-141-D 1,496,131 0 FY 2015 OIG-15-148-D 4,202,857 0 FY 2015 Subtotal $130,262,235 $50,510,883 www.oig.dhs.gov 7 OIG-18-29

Appendix B (Continued) FY 2015 to 2017 Disaster Grant and Subgrant Reports Fiscal Year Issued Report Number Questioned Amount Cost Avoidance FY 2016 OIG-16-09-D $ 2,072 $ 0 FY 2016 OIG-16-21-D 0 40,247,846 FY 2016 OIG-16-24-D 874,055 0 FY 2016 OIG-16-38-D 0 0 FY 2016 OIG-16-52-D 312,117 0 FY 2016 OIG-16-66-D 1,284,600 0 FY 2016 OIG-16-67-D 0 26,627,208 FY 2016 OIG-16-78-D 2,898,831 7,230,911 FY 2016 OIG-16-97-D 51,174,297 0 FY 2016 OIG-16-99-D 0 8,367,654 FY 2016 OIG-16-103-D 0 16,506,222 FY 2016 OIG-16-114-D 0 1,381,560 FY 2016 OIG-16-118-D 0 2,626,623 FY 2016 OIG-16-116-D 0 3,300,000 FY 2016 OIG-16-120-D 130,089 55,000 FY 2016 OIG-16-125-D 668,430 0 FY 2016 OIG-16-133-D 0 3,722,500 FY 2016 OIG-16-136-D 0 10,846,666 FY 2016 OIG-16-140-D 4,894,551 791,175 FY 2016 OIG-16-143-D 23,943,436 0 FY 2016 Subtotal $ 86,182,478 $121,703,365 FY 2017 OIG-17-06-D $ 1,563,780 $ 0 FY 2017 OIG-17-18-D 967,963 0 FY 2017 OIG-17-25-D 31,713,569 0 FY 2017 OIG-17-34-D 0 2,009,971 FY 2017 OIG-17-46-D 4,786,736 0 FY 2017 OIG-17-48-D 0 3,240,646 FY 2017 OIG-17-57-D 0 458,150 FY 2017 OIG-17-77-D 1,473,045 0 FY 2017 OIG-17-62-D 0 12,854,705 FY 2017 OIG-17-83-D 0 585,000 FY 2017 Subtotal $ 40,505,093 $ 19,148,472 Total $256,949,806 $191,362,720 DHS OIG reports can be found under the Reports tab at http://www.oig.dhs.gov/. www.oig.dhs.gov 8 OIG-18-29

Appendix C Report Distribution OFFICE OF INSPECTOR GENERAL Acting Secretary Acting Deputy Secretary Chief of Staff General Counsel Executive Secretary Director, GAO/OIG Liaison Office Assistant Secretary for Office of Policy Assistant Secretary for Office of Public Affairs Assistant Secretary for Office of Legislative Affairs DHS Component Liaison Federal Emergency Management Agency Administrator Chief of Staff Acting Chief Financial Officer Chief Counsel Acting Associate Administrator for Policy and Program Analysis Director, Program Analysis and Evaluation Division Director, Risk Management and Compliance Chief Procurement Officer Audit Liaison, FEMA (Job Code 17-108-EMO-FEMA) Office of Management and Budget Chief, Homeland Security Branch DHS OIG Budget Examiner Congress Congressional Oversight and Appropriations Committees www.oig.dhs.gov 9 OIG-18-29

Additional Information and Copies To view this and any of our other reports, please visit our website at: www.oig.dhs.gov. For further information or questions, please contact Office of Inspector General Public Affairs at: DHS-OIG.OfficePublicAffairs@oig.dhs.gov. Follow us on Twitter at: @dhsoig. OIG Hotline To report fraud, waste, or abuse, visit our website at www.oig.dhs.gov and click on the red "Hotline" tab. If you cannot access our website, call our hotline at (800) 323-8603, fax our hotline at (202) 254-4297, or write to us at: Office of Inspector General, Mail Stop 0305 Attention: Hotline 245 Murray Drive, SW Washington, DC 20528-0305