Abstract. Presented at the 2018 ICEAA Professional Development & Training Workshop - Proactive estimating June 2018 QinetiQ 2018

Similar documents
Simon Gadd. US / UK Interoperability - the Importance of an International Defence Industry

D/PUS/11/7/1(626) 20 October 2017 COMMITTEE OF PUBLIC ACCOUNTS (PAC) CARRIER STRIKE: WRITTEN RESPONSES

REQUIREMENTS TO CAPABILITIES

UNCLASSIFIED R-1 ITEM NOMENCLATURE

We acquire the means to move forward...from the sea. The Naval Research, Development & Acquisition Team Strategic Plan

UNCLASSIFIED UNCLASSIFIED. EXHIBIT R-2, RDT&E Budget Item Justification RESEARCH DEVELOPMENT TEST & EVALUATION, NAVY / BA-7

MEDIA CONTACTS. Mailing Address: Phone:

THE UNDER SECRETARY OF DEFENSE 3010 DEFENSE PENTAGON WASHINGTON, DC

(111) VerDate Sep :55 Jun 27, 2017 Jkt PO Frm Fmt 6601 Sfmt 6601 E:\HR\OC\A910.XXX A910

Report to the Public Accounts Committee on the basis for a possible acquisition of combat aircraft. March 2009

Telephone (am) (pm) (fax)

Spectrum contest: RAAF boosts electronic warfare capabilities

UNCLASSIFIED FY 2016 OCO. FY 2016 Base

CHAPTER 4 : VALUE SYSTEM AND VALUE CHAIN OVERVIEW 4.1 THE VALUE SYSTEM FOR SOUTH AFRICAN NATIONAL DEFENCE

UNCLASSIFIED R-1 ITEM NOMENCLATURE FY 2013 OCO

Building an Air Manoeuvre Capability: The Introduction of the Apache Helicopter

ARMY RDT&E BUDGET ITEM JUSTIFICATION (R2 Exhibit)

Combined Aerial Target Service (CATS)

UNCLASSIFIED. R-1 ITEM NOMENCLATURE PE F: Joint Strike Fighter Squadrons

United States Government Benefits as a Result of Foreign Military Sales Programs

Delivering Carrier Strike

Terma and F-35 Global supplier to the Joint Strike Fighter program

UNCLASSIFIED. FY 2016 Base FY 2016 OCO

Ottawa, Canada March 23, 2011

First Announcement/Call For Papers

STATEMENT OF. MICHAEL J. McCABE, REAR ADMIRAL, U.S. NAVY DIRECTOR, AIR WARFARE DIVISION BEFORE THE SEAPOWER SUBCOMMITTEE OF THE

A European Net Assessment of the People s Liberation Army (Navy)

GAO TACTICAL AIRCRAFT. DOD Needs a Joint and Integrated Investment Strategy

Defense Acquisition: Use of Lead System Integrators (LSIs) Background, Oversight Issues, and Options for Congress

Disruption in Aerospace/Defense

UNCLASSIFIED R-1 ITEM NOMENCLATURE

UNCLASSIFIED FY This program develops and demonstrates advanced technologies, including Electromagnetic (EM) Rail Gun for naval weapon systems.

UNCLASSIFIED R-1 ITEM NOMENCLATURE FY 2013 OCO

DoDI ,Operation of the Defense Acquisition System Change 1 & 2

UNCLASSIFIED. R-1 ITEM NOMENCLATURE PE N: Consolidated Afloat Network Ent Services(CANES) FY 2012 OCO

Navy-Marine Corps Strike-Fighter Shortfall: Background and Options for Congress

UNCLASSIFIED. R-1 ITEM NOMENCLATURE PE A: Joint Air-to-Ground Missile (JAGM) FY 2012 OCO

NAVAIR International Programs. NAVAIR International Programs

UNCLASSIFIED. UNCLASSIFIED Navy Page 1 of 8 R-1 Line #77

DEPARTMENT OF DEFENSE PRESENTATION TO THE SENATE ARMED SERVICES COMMITTEE UNITED STATES SENATE

UNCLASSIFIED FY 2016 OCO. FY 2016 Base

PROGRAM ELEMENT TITLE: Airborne Reconnaissance Advanced Development (ARAD)

OPNAVINST DNS-3/NAVAIR 24 Apr Subj: MISSIONS, FUNCTIONS, AND TASKS OF THE COMMANDER, NAVAL AIR SYSTEMS COMMAND

1. Purpose. To implement the guidance set forth in references (a) through (e) by:

UNCLASSIFIED UNCLASSIFIED

PARLIAMENTARY RESEARCH BRANCH DIRECTION DE LA RECHERCHE PARLEMENTAIRE

ARS 2004 San Diego, California, USA

Unmanned Aerial Vehicle Operations

World-Wide Satellite Systems Program

Number: DI-MGMT Approval Date:

UNCLASSIFIED FY 2018 OCO. FY 2018 Base

The Royal Navy and its equipment support

UNCLASSIFIED. FY 2017 Base FY 2017 OCO

Project ALEXANDER Industry Briefings

RE: Alarm from an Industry Professional over Australia s Procurement of the F-35 Lightning II Joint Strike Fighter.

F-35 JOINT STRIKE FIGHTER. Development Is Nearly Complete, but Deficiencies Found in Testing Need to Be Resolved

F-35 Lightning II Program Status June 2017

UNCLASSIFIED R-1 ITEM NOMENCLATURE FY 2013 OCO

Naval Command. Royal Navy. British Royal Navy fleet lists for use with the Naval Command wargame rules. By Rory Crabb

Environmental Impact Statement/Overseas Environmental Impact Statement (EIS/OEIS) for the Northwest Training Range Complex (NWTRC). An EIS/OEIS is con

UNCLASSIFIED. UNCLASSIFIED Navy Page 1 of 19 R-1 Line #71

Canadian Industrial Participation in the F-35 Joint Strike Fighter Program. Summer 2014

Total Ownership Cost. CAPT Tom Ryan OPNAV N414

The Coastal Systems Station Strategic Perspective

UNCLASSIFIED R-1 ITEM NOMENCLATURE FY 2013 OCO

UNCLASSIFIED R-1 ITEM NOMENCLATURE. FY 2014 FY 2014 OCO ## Total FY 2015 FY 2016 FY 2017 FY 2018

The Fifth Element and the Operating Forces are vitally linked providing the foundation that supports the MAGTF, from training through Operational

F-35 Lightning II. 5 th Generation True Stealth for Korea From 2016 and Beyond

UNCLASSIFIED R-1 ITEM NOMENCLATURE

Beaufort. Brits at UK F-35 TRAINING

F-35 Lightning II A New Generation of Fighter

UNCLASSIFIED. FY 2017 Base FY 2017 OCO

ARMY RDT&E BUDGET ITEM JUSTIFICATION (R-2 Exhibit)

Facts on the Bilateral Cooperation Program between Thailand and Sweden by the Swedish Government

Number: DI-MGMT Approval Date:

DSEI DSEI 2015 is now two weeks away. DSEI 2015 is now two weeks away

Cost and Software Data Reporting Training

Canadian Industrial Participation in the F-35 Joint Strike Fighter Program. Fall 2014

2016 Major Automated Information System Annual Report

DEPARTMENT OF THE NAVY OFFICE OF THE CHIEF OF NAVAL OPERATIONS 2000 NAVY PENTAGON WASHINGTON DC

Subj: MISSION, FUNCTIONS AND TASKS OF DIRECTOR, STRATEGIC SYSTEMS PROGRAMS, WASHINGTON NAVY YARD, WASHINGTON, DC

UNCLASSIFIED UNCLASSIFIED

UNCLASSIFIED FY 2016 OCO. FY 2016 Base

UNCLASSIFIED. UNCLASSIFIED Navy Page 1 of 5 P-1 Line #58

Exhibit R-2, RDT&E Budget Item Justification

Department of Defense DIRECTIVE

resource allocation decisions.

DEPARTMENT OF THE NAVY CHIEF OF NAVAL OPERATIONS 2000 NAVY PENTAGON WASHINGTON DC

DOD INSTRUCTION DEPOT MAINTENANCE CORE CAPABILITIES DETERMINATION PROCESS

H-60 Seahawk Performance-Based Logistics Program (D )

UNCLASSIFIED UNCLASSIFIED

WHITE PAPER FACILITIES MANAGEMENT OUTSOURCING: South Africa and The United Kingdom

2016 Major Automated Information System Annual Report

UNCLASSIFIED. R-1 ITEM NOMENCLATURE PE N: Air Control

Task Force Innovation Working Groups

UNCLASSIFIED R-1 ITEM NOMENCLATURE

NDIA Ground Robotics Symposium

Subj: CHEMICAL, BIOLOGICAL, RADIOLOGICAL, AND NUCLEAR DEFENSE REQUIREMENTS SUPPORTING OPERATIONAL FLEET READINESS

JOINT STRIKE FIGHTER ACQUISITION

Capability Integration

Transcription:

Abstract Fed up with being reactive to cost estimating and forecasting requests? Had enough of being last in the queue for time and resources? Dismayed at being consulted at the last minute for an opinion on the cost? Seeking a new approach to cost predictions? Consider the proactive approach! Rather than waiting for requests for an estimate at the end of a bid or study it is time to start leading. Cost staff are a value-adding commodity, they have the ability to predict the future; well, almost! This paper will explore some of the options and alternatives which as a cost community we should be pursuing. It will examine the programme, procurement and technical options that we should present ahead of the remainder of the engineering and project management scrum. It will examine the big, first order assumptions which we should be considering to ensure that we have a voice and that the cost is considered at the forefront of the decision process. As an example the paper will consider the options for a sixth generation fighter capability. It will explore the alternatives from a cost perspective and set a direction for the future direction of travel with regards to the air domination capability. In short, it will set a proactive estimating case study to ensure that the cost community is forward leaning and not the last people to be asked an opinion on the topic. Though based upon an air project the approach will be equally applicable for land, sea and space capabilities. 1

Proactive estimating: an analysis of sixth generation aircraft Dale Shermon QinetiQ Fellow & Managing Consultant ICEAA Conference, Phoenix June 2018 QINETIQ/18/01131

Agenda 1 QinetiQ and Advisory Services 2 Proactive estimating 3 Options analysis 4 Case study 6 th Generation air capability 5 Summary 3

QinetiQ and Advisory Services Dale Shermon QinetiQ Fellow

Our vision and strategy The chosen partner around the world for mission-critical solutions, innovating for our customers advantage UK International Innovation Lead and modernise the UK Defence Test and Evaluation enterprise, by working in partnership with Government and Prime contractors Build an international company that delivers value to our customers by developing our home markers, creating new home markets and exporting Invest in and apply our core competence for customer advantage in defence and commercial markets 5

QinetiQ Advisory services Diagnose Analyse Advise Support A range of products and tools designed to assist customer in understanding and defining the problem, identifying weaknesses, risks and gaps and highlighting strengths. Impartial and robust analysis of the evidence, assumptions, data and factors surrounding an issue to optimise customer s evidence-based decision making Delivery of knowledge and expert advice by providing key specialists and subject matter experts to support customers in the conduct of specific tasks Provision of training, mentoring, coaching to transfer skills or the provision of skilled or expert staff to enable customer to deliver a task successfully. 6

QinetiQ Advisory services Australian Force Structure Review Application of high level cost estimating methodology to review budgets and generate independent cost estimates (ICE) CDM Cost Challenge Review of the budget of the top UK MOD projects to align budget with requirements for the Chief of Defence Material (CDM). CCG Fleet Review Created a robust audit trail and evidence for a revised Fleet Renewal Plan (FRP) 2017 across 119 vessels in 43 home ports of the Canadian Coast Guard (CCG) 7

Proactive estimating Dale Shermon QinetiQ Fellow Text

Proactive Estimating the problem Pricing review, Design review, Analysis of Alternatives, Proposal scrutiny Cost Engineer Cost Estimator Cost Analyst Proposal manager, Bid Manager, Project Manager Design Manager, Systems Engineering Technical team 9

Proactive Estimating Frequently the cost estimate is the last activity in a bid / study / project schedule. This has some justification as you need a design to estimate; you can t estimate a requirements. However, it is often too late to influence the technical, programmatic and procurement decisions that have been made. At the Bid review, preliminary design review or critical design review stage the solution is frozen. There needs to be an agile approach; design cost design cost To ensure value for money (VfM) there needs to be a balance and cost needs to be heard.

Proactive Estimating The balance Proposal manager, Bid Manager, Project Manager Design Manager, Systems Engineering Technical team Cost Engineer Cost Estimator Cost Analyst 11

Options analysis Dale Shermon QinetiQ Fellow Text

Options analysis - Capability Capability is the continuing ability to generate a desired operational outcome or effect which is relative to the threat, physical environment and the contributions of coalition partners. Threat Capability is not a particular system or equipment. Capability is delivered by Force Elements combined into packages by Joint Force Commanders and tailored for particular operations or missions. Physical Environment Capability Coalition Contribution Joint Capability Packages Force Elements Source: Centre for Defence Acquisition, Cranfield University, Innovative UK Approaches to Acquisition Management, dated May 2009 13

Options analysis Capability Air superiority 14

Options analysis - Force Element Force Elements are typically ships, aircraft or ground force sub-units (company / battery / squadron). The Force Elements are: Ships Aircraft Army formations other Military Units Force Enablers. Each Force Element is delivered by either: a single service, or by a joint organisation. Source: Centre for Defence Acquisition, Cranfield University, Innovative UK Approaches to Acquisition Management, dated May 2009 Joint Capability Packages Force Element Defence lines of Development (DLoDs) Ships Aircraft Army Formations Joint Force Enablers Other military units Training Equipment Personnel Information Doctrine Organisation Infrastructure Logistics 15

Options analysis Capability Air superiority Element Manned Unmanned 16

Options analysis - Source The options are geographical in terms of consideration. It considers the source of the intellectual property (IP), design or ownership: Sovereign the Force Elements will be acquired from a business within the home country, for example, United Kingdom International the Force Elements will be acquired from a business outside the home country. Sovereign International 17

Options analysis Capability Air superiority Element Manned Unmanned Source US Non-US UK Only Programme Non-UK UK Only Programme 18

Options analysis - Collaboration Next there is the consideration on the collaborative nature of the options. In this sense the options need to consider: Independent the Force Elements will be acquired from a single entity. Sovereign International Joint the Force Elements will be acquired from multiple entities. Independent Joint Independent Joint 19

Options analysis - Collaboration This leads to the following examples: Independent could be: Sovereign - which could lead to indigenous design and build programme (Buccaneer), or International - could involve a Foreign Military Sale (FMS) or a military off-the-shelf (MOTS) solution (Phantom). Sovereign Independent Joint International Independent Joint Joint could be: Sovereign - which could lead to a indigenous design, built by a partner overseas (Harrier AV-8B), or International - which could be a solution designed and built as part of a partnership with workshare understood (F-35). Indigenous design and build UK design, build under licence Foreign Military Sales (FMS) Design and build Partnership 20

Options analysis Capability Air superiority Element Manned Unmanned Source US-led Partner Non-US Partnership UK Only Programme Partnership UK Only Programme Collaboration International International Build under license New design and build International New design and build System. 21

Options analysis - System The final option is the solution that will contribute to the Force Element. The platform or system that will satisfy the need expressed in the Capability Statement. The Systems can have different performance, design, technology year and so forth. 22

Options analysis Capability Air superiority Element Manned Unmanned Source US-led Partner Non-US Partnership UK Only Programme Partnership UK Only Programme Collaboration International International Build under license New design and build International New design and build System 6 th Generation 1a F-35 evolved 1b F-35 2a 5 th Generation 3a F-35 evolved 4d. 6 th Generation 4e. 6 th Generation 4a Strategic UAV 3c Strategic UAV 4c 23

Options analysis - High level Alternatives Option ID Description Source / Procurement Example 0. Current state Status Quo Baseline 0. F-35 1. Do minimum International 1a. 6 th Generation 1b. F-35 evolved 2. Do same as current International 2a. F-35 in-service 3. Do non-sovereign International 3a. Non-US 5 th Generation 3b. Strategic UAV 4. Do sovereign UK Design and build 4a. 6 th Generation 4b. Strategic UAV Build under license 4c. F-35 evolved 4d. 6 th Generation 24 AS Cost Overview Sept 2017 QinetiQ Ltd.

Case study 6 th Generation air capability Dale Shermon QinetiQ Fellow Text

Option 0. F-35 Baseline Capability Element Source Air superiority Manned US-led Partner approach The Joint Combat Aircraft (JCA) is the requirement for a multi-role aircraft to be operated jointly by the Royal Air Force and the Royal Navy from both fixed and deployable land bases and the new Queen Elizabeth Class aircraft carriers. In 2001 the F-35 Lightning II design by Lockheed Martin was selected as the aircraft to meet the JCA requirement and provides the UK with a fifth generation air system. Collaboration System International F-35 0. The UK is the only Level 1 Partner Nation within the System Development and Demonstration (SDD) phase of the Joint Strike Fighter programme, along with the US Services and is able to decide and agree the Requirements. Source: NAO Major Projects Report 2015 and the Equipment Plan 2015 to 2025, 22 October 2015 26

Assumptions Total production of F-35B will be 508 UK will acquire 138 F-35B STOVL variants Technology standard 2003 at F-35 Preliminary Design Review (PDR) Technical Payload 15,000 lb 6,800 kg Basic mass empty 32,300 lb 14,648 kg Development Status All new design Number of pilots One Number of variants (in addition to basis design) Two Production rate 145 per year Service life 30 years Production Manufacture Italy United Kingdom US Marine Corp Total Production 30 a/c 138 a/c 340 a/c 508 a/c 27

Calibration cost data F-35 Life Cycle Cost Then Year $B Research Development Test and Evaluation 55.1 Procurement 319.1 Military Construction (MILCON) 4.8 Operating and Support Costs 1,123.8 Total Life Cycle Costs(LCC) 1,502.8 Procurement Cost Then Year $M F-35A (1,763) 100.6 F-35B (340) 122.9 F-35C (340) 110.7 Average Procurement Unit Cost (APUC) 130.6 RDT&E MILCON Procurement O&S Source: F-35 Lightning II Program Fact Sheet Selected Acquisition Report (SAR) 2015 Cost Data 28 Presentation title Month Year

Calibration cost data F-35 Then Year $Bn Total Life Cycle Cost = 1,502.8 29

Calibration cost data F-35 Then Year M Unit Production Cost (UPC) = 90.0 (or $122.9) 30

Constant capability 5 th Generation Payload capability for the F-35 is circa. 6,800 kg Technology standard 1996 5 th Generation evolved Payload capability for the F-35 is circa. 6,800 kg Technology standard 1996 + 15 years 6 th Generation Payload capability for the F-35 is circa. 6,800 kg Technology standard 1996 + 30 years Strategic UAV Global hawk: Universal Payload Adapter The UPA will support 540kg Description System Total Quantity (platforms) all partners 5 th Generation 3,109 5 th Generation evolved 3,109 6 th Generation 3,109 Strategic UAV 39,150 Tactical UAV Mirach 26 The payload is 50kg It would require 136 UAV for each aircraft, or over 422,000 tactical UAV to deliver the equivalent payload for all partners. 31 AS Cost Overview Sept 2017 QinetiQ Ltd.

Macro-parametric cost model 32

Comparison of Alternatives Baseline Alternatives Target 900 800 Then Year $ Bn 700 600 500 400 300 200 100-0. F-35 - UK only 1a. 6th Generation 1b. F-35 evolved 2a. F-35 inservice 3a. 5th Generation Options 3b. Strategic UAV 4a. 6th Generation 4b. Strategic UAV 4c. F-35 evolved 4d. 6th Generation 33

Comparison of Alternatives 600 Baseline Alternatives Target Constant 2018 $ Bn 500 400 300 200 100-0. F-35 - UK only 1a. 6th Generation 1b. F-35 evolved 2a. F-35 inservice 3a. 5th Generation Options 3b. Strategic UAV 4a. 6th Generation 4b. Strategic UAV 4c. F-35 evolved 4d. 6th Generation 34

Comparison of Alternatives Constant 2018 $ Bn 500.00 450.00 400.00 350.00 300.00 250.00 200.00 150.00 100.00 50.00-0. F-35 - UK only 1a. 6th Generation 1b. F-35 evolved 2a. F-35 inservice 3a. 5th Generation 3b. Strategic UAV Options 4a. 6th Generation 4b. Strategic UAV 4c. F-35 evolved 4d. 6th Generation RDT&E Prod. Invest. Production Crew Maintenance 35

Analysis observations No deviation of the systems capability over time, for example, the same payload is assumed No mixed fleets are considered, for example, manned and unmanned systems in combination No attrition of fleet numbers have been considered No consideration of project specific risks As a first level ROM analysis the exercise can avoid some dead-ends This high level analysis can highlight some problem areas The analysis will provide ROM costs for first level assumptions The analysis assumptions and input parameters are recorded for future scrutiny and debate A cost engineer has prompted a logical discussion regarding future air capability 36

Summary Dale Shermon QinetiQ Fellow Text

Summary Cost needs to be heard, Proactive Estimating promotes the generation of options which will stimulate the demand for cost engineering services. There is a logical approach to options analysis for cost modelling. Macro-parametric cost modelling lends itself to the quick and plentiful generation of costed alternatives. The application of a unmanned system fleet would seem expensive due to quantities required to deliver a constant capability. 38

Any questions? Dale Shermon QinetiQ Fellow Managing Consultant Mobile +44 (0)7785 522 847 DShermon@QinetiQ.com Building 240, The Close Bristol Business Park Coldharbour Lane Bristol BS16 1FJ United Kingdom www.qinetiq.com 39

40