VIETNAM EXPERIENCE IN THE IAEA INTEGRATED NUCLEAR INFRASTRUCTURE REVIEW MISSIONS Vienna, 18 September 2013 1 HOANG Anh Tuan, PhD Director General Vietnam Atomic Energy Agency Ministry of Science and Technology, Vietnam
2 MAIN CONTENT 1. Brief status of the Nuclear Power Programme in Vietnam 2. The INIR Missions 3. INIR Challenges 4. The IAEA assistance
3 1. Brief status of the Nuclear Power Programme in Vietnam
4 Important Events of Nuclear Power Programm in Vietnam 2002 2006 2008 2009 Working Group studying the possibility of nuclear power development in Vietnam (3/2002) Pre-FS (by Institute of Energy) Strategy for the Applications of Atomic Energy for Peaceful Purposes up to 2020 (1/2006) Atomic Energy Law (6/2008) State Appraisal Council (9/2008) National Assembly s Resolution on the Investment Decision for the Ninh Thuan NPP Project (11/2009) INIR Misssion 1 (11-12/2009)
5 Important Events of Nuclear Power Programme in Vietnam 2010 Party of Convention on Nuclear Safety (4/2010) Establishment of the National Nuclear Safety Council (4/2010) Establishment of the State Steering Committee of the Ninh Thuan Nuclear Power Project (NEPIO) (5/2010) Master Planning for the Peaceful Development and Utilization of Atomic Energy up to 2020 Approval of the National scheme on human resource development the field of atomic energy by the Prime Minister(08/2010) Inter-governmental agreement between Vietnam and Russia on the construction of the Ninh Thuan 1 NPP Project (10/2010)
6 Important Events of Nuclear Power Programme in Vietnam 2011 Inter-governmental arrangement between Vietnam and Japan on the construction of the Ninh Thuan 2 NPP Project (1/2011) Establishment of the Ninh Thuan Nuclear Power Project Management Board (EVNNPB) (4/2011) Establishment of the National Steering Committee on Human Resource Development in the Field of Atomic Energy (6/2011) Signing of the EVN-JAPC (Japan) Consulting Contract of 18 months on Site Approval Dossier Development & FS of the Ninh Thuan 2 NPP (09/2011) Signing of the EVN-Consortium E4 Group (Russia) Consulting Contract of 18 months on Site Approval Dossier Development & FS of the Ninh Thuan NPP (11/2011) Inter-governmental agreement between Vietnam and Russia on the credit loan for the construction of nuclear power plant in Vietnam (11/2011)
7 Important Events of Nuclear Power Programme in Vietnam 2012 NEPIO Seminar (8/2012) Ratification of the Convention of Physical Protection of Nuclear Materials and its Amendment (9/2012, in force since 3/11/2012) The Additional Protocol (9/2012) INIR Mission 2 (12/2012) Establishment of the Centre on Atomic Energy Information in cooperation with ROSATOM (12/2012)
8 Important Events of Nuclear Power Programme in Vietnam 2013 Approval of the National Project on Public Information and Communication on the Development of Nuclear Power in Vietnam u to 2020 by the Prime Minister (2/2013) List of legal documents to be promulgated up to 2020 approved by the Prime Minister (2/2013) Establishment of the National Atomic Energy Council (5/2013) Establishment of the Technical sub-committees (of the State Steering Committee) on nuclear safety and security; and on education, training, information and communication (5/2013) Feasibility Study and Siting Approval Dossier for Ninh Thuan 1 almost completed in 6/2013 Feasibility Study and Siting Approval Dossier for Ninh Thuan 2 to be submitted by the end of 2013
9 Vietnam is in the Phase 2 of developing nuclear power infrastructure IAEA Guidance on the development of national nuclear power infrastructure
10 Status of Nuclear Power Programme in Vietnam Development Planning Orientation for Nuclear Power in Vietnam up to 2030 (2010) 2020 1 st unit 1,000 MW (1.3 % domestic capacity) 2030 14 units 15,000 16,000 MW (10 % domestic capacity) Ky Xuan (Ha Tinh) Duc Thang (Quang Ngai) Duc Chanh (Quang Ngai) Hoai My (B Dinh) Xuan Phu Yen) Vinh Hai (Ninh Thu Phuoc Dinh (Ninh Thuan 1)
11 Status of Nuclear Power Programme in Vietnam Ninh Thuan Nuclear Power Project Ninh Thuan 1: Phuoc Dinh 2 x 1,000 MWe Technology: VVER-1000 Ninh Thuan 2: Vinh Hai 2 x 1,000 MWe Technology: not yet decided (LWR, proven, advanced) COD: Ninh Thuan 1: 2020-2021 Ninh Thuan 2: 2021-2022 Investment Owner: EVN Cooling: Sea water Fuel: Imported
12 Status of Nuclear Power Programme in Vietnam Establishment of the State Steering Committee for Ninh Thuan Nuclear Power Project (2010) and of 2/5 Subcommittees of the State Steering Committee (on Nuclear Safety and Security (MOST, 2013); Training, Information & Communication (MOST, 2013) ;Development of Nuclear Power Industry (MOIT); Nuclear Technology, Fuel and Radioactive Wastes (MOIT); Construction (MOC)); Establishment of the National Nuclear Safety Council (4/2010) and the National Atomic Energy Council (5/2013) Approval of the National Project on Public Information and Communication on the Development of Nuclear Power in Vietnam up to 2020 by the Prime Minister (2/2013) Feasibility Study and Siting Approval Dossier for Ninh Thuan 1 almost completed in 6/2013 Feasibility Study and Siting Approval Dossier for Ninh Thuan 2 to be submitted by the end of 2013; Development of the Draft of the National Master Plan for developing nuclear power infrastructure;
13 Status of Nuclear Power Programme in Vietnam Legislative and regulatory framework: Amending the Law on Atomic Energy (2008), Many legal related documents issued and list of legal documents relating nuclear power to be promulgated up to 2020 approved by the Prime Minister (2/2013) Being Party to most of the relevant international legal instruments adopted under IAEA auspices, in particular: CNS (in force since 2010), Convention on Early Notification of a Nuclear Accident (in force since 1987), Convention on Assistance in the Case of a Nuclear Accident or Radiological Emergency (in force since 1987), Convention on the Physical Protection of Nuclear Material (in force since 10/2012), Comprehensive Safeguards Agreement (CSA) with the IAEA (in force since 1989), Additional Protocol to the CSA (in force since 10/2012) Studying the Joint Convention and relevant international legal instruments on civil liability for nuclear damage
14 Status of Nuclear Power Programme in Vietnam Human Resource Development Approval of the National scheme on human resource development in the field of atomic energy by the Prime Minister (08/2010); MOST-ROSATOM Practical Arrangement on specialist training (6/2012) Vietnam Electricity s Project on Human Resource Development for Ninh Thuan Nuclear Power Project; Training in Japan, Russia and other countries: >100 students at MEPhI Obninsk (2012) to study Nuclear power plant and installations Training course in JNES, MEXT, METI, JAIF, JAEA, JAERI, RADA, ROSATOM, Rostechnadzor, etc. Agreement with Hungary on education and training in the field of atomic energy
15 2. The INIR Missions
16 The 1 st INIR Mission (Phase 1) Self Assessment Report, 10/2009 Preparation Organization 30/11 4/12/2009 8 Experts Office of Gov., MOST, MOIT, MOET, MOPS, MOC, EVN, Unis, others Vietnam achieved the Milestone 1 with most of Phase 1 activities completed and numerous activities of Phase 2 under implementation Detailed assessment for 19 issues; 12 recommendations and 22 suggestions Conclusion
17 The 1 st INIR Mission (Phase 1) v The INIR Report was translated into Vietnamese to send to relevant organizations for studying. v Report to the Prime Minister on results of INIR Mission and IAEA s recommendations. v Directive by the Prime Minister on: Establishment of NEPIO Follow-up actions after the 1 st INIR Mission Establishment of Nuclear Power Project Management Board Facilitating the negotiation with the Russian Federation Development of the Master Planning for the Peaceful Development and Utilization of Atomic Energy up to 2020
18 The 2 nd INIR Mission (Phase 2) Self- Assessment Report, 8/2012 Preparation Organization 5-14/12/2012 12 Experts Office of Gov, SSC, MOST, MOIT, MOFA, MIC, MOET, MONRE, MOJ, MOC, EVN, Ninh Thuan Province, Unis Interviews for each issue and condition Formation of Key Findings/Recommendations/S uggestions/good Practice Vietnam had achieved significant improvement since the 1 st INIR Mission, there are a lot of work needed to be done to complete the Phase 2 7 key areas 42 recommendations, 12 suggestions, 2 good practices Conclusion
19 The 2 nd INIR Mission (Phase 2) Follow-up actions after the 2 nd INIR Mission v Reporting to Chairman of the SSC and relevant ministries on the conclusion of the 2 nd INIR Mission Report (including full report in English and Vietnamese) and submission of the suggestions by MOST; v Draft of the Master Plan for developing the national nuclear power infrastructure in Vietnam up to 2020 revised considering the recommendations of INIR Mission and based on practical situation in Vietnam; v Reviewing and planning activities under the Integrated Work Plan for the development of Nuclear power infrastructure for 2013 and 2014-2015 design considering recommendations of INIR Mission; v Planning the implementation of the National Project on PI&C for nuclear power programme up to 2020 v Cooperating with IAEA to organize Expert Mission to support in developing the National Integrated Plan on Human Resource Development for nuclear power programme (8/2013)
20 The IAEA INIR Mission in Hanoi, Vietnam, 5 14/12/
21 3. INIR Challenges
22 INIR Challenges Difficulties in understanding and applying the IAEA s recommendations to certain circumstances of countries Workforce in key organizations directly working on nuclear infrastructure development has not been trained systematically. There is a need on capacity building for key organizations in developing nuclear infrastructure, ex. on-job-training overseas. Guides and recommendations of IAEA are only general requirements, which do not indicate the implementation measures.
23 4. The IAEA assistance
24 IAEA Assistance Assisting in providing countries with related guidance, documents to develop self-assessment report, to prepare for and to conduct INIR Mission; IAEA and international experts in expert missions are excellent and enthusiastic; In case of Vietnam, Vietnam received the draft of INIR Mission report soon after the Mission for providing comments on the draft so that the report could be finalized and sent to the official channel in April 2013; Assistance through TC Projects and the IWP proves to be effective, timely and comprehensive.