NAVSEA STANDARD ITEM. 2.1 S9AAO-AB-GOS-010, General Specifications for Overhaul of Surface Ships (GSO)

Similar documents
NAVSEA STANDARD ITEM CFR Part 61, National Emission Standards for Hazardous Air Pollutants

NAVSEA STANDARD ITEM CFR Part 61, National Emission Standards for Hazardous Air Pollutants

DISTRIBUTION STATEMENT A APPROVED FOR PUBLIC RELEASE DISTRIBUTION UNLIMITED

Ref: (a) Navy Shipyard Test Managers Meeting of 9-11 Dec 2008 (b) Navy Shipyard Test Managers Meeting of Dec 2009

NAVSEA STANDARD ITEMS FY-19 CH-2 (26 MAR 2018)

Chapter 12 Environmental, Safety and Health (ES&H) Regulatory Compliance and Contractor Oversight Program

JOINT FLEET MAINTENANCE MANUAL VOLUME I NEW CONSTRUCTION LIST OF EFFECTIVE PAGES. Page Numbers Change in Effect Page Numbers Change in Effect

NORTHWESTERN UNIVERSITY PROJECT NAME JOB # ISSUED: 03/29/2017

DEPARTMENT OF THE NAVY COMMANDER NAVY REGIONAL MAINTENANCE CENTER 9170 SECOND STREET, SUITE 245 NORFOLK, VA

A. General provisions and other electrical systems are specified in other Sections of Division 26.

Naval Sea Systems Command Did Not Properly Apply Guidance Regarding Contracting Officer s Representatives

NAVSEA STANDARD ITEM. 1.1 Title: Prevention of Radiographic-Inspection Ionizing-Radiation Hazards; accomplish

A preventive maintenance program has been established to: A. Increase the life of a building and its mechanical system;

DEPARTMENT OF THE NAVY COMMANDER NAVY REGIONAL MAINTENANCE CENTER 9170 SECOND STREET, SUITE 245 NORFOLK, VA

DOD INSTRUCTION DEPOT MAINTENANCE CORE CAPABILITIES DETERMINATION PROCESS

FACILITIES MANAGEMENT

T6161-FB-FSE LP REVISION: 01

DEPARTMENT 20 OVERVIEW AND CONTRACTS FORECAST

US Navy Strategic Maintenance Process

DOD MANUAL DOD ENVIRONMENTAL LABORATORY ACCREDITATION PROGRAM (ELAP)

Old Island Restoration Foundation

DEPARTMENT OF THE NAVY COMMANDER NAVY REGIONAL MAINTENANCE CENTER 9170 SECOND STREET, SUITE 245 NORFOLK, VA

STANDARD ITEM. 1.1 Title: Prevention of Radiographic-Inspection Ionizing-Radiation Hazard; accomplish

Submission, Review, and Approval Procedures

DEPARTMENT OF THE NAVY COMMANDER NAVY REGIONAL MAINTENANCE CENTER 9170 SECOND STREET, SUITE 245 NORFOLK, VA

DOD INSTRUCTION DEPOT SOURCE OF REPAIR (DSOR) DETERMINATION PROCESS

UNCLASSIFIED. R-1 ITEM NOMENCLATURE PE N: RDT&E Ship & Aircraft Support

THE UNDER SECRETARY OF DEFENSE 3010 DEFENSE PENTAGON WASHINGTON, DC

DEFENSE LOGISTICS AGENCY DISPOSITION SERVICES LETTERKENNY LETTERKENNY ARMY DEPOT BUILDING S-2293 CHAMBERSBURG, PA 17201

Subj: FULL POWER AND ECONOMY TRIAL REQUIREMENTS FOR NON-NUCLEAR SURFACE SHIP CLASSES

S. ll. To provide for the improvement of the capacity of the Navy to conduct surface warfare operations and activities, and for other purposes.

OPNAVINST F N4 5 Jun 2012

WESTMINSTER SCHOOL DISTRICT NUTRITION SERVICES REQUEST FOR PROPOSAL FRESH PRODUCE 17/ For: July 1, 2018 to June 30, 2019

1. Definitions. See AFI , Air Force Nuclear Weapons Surety Program (formerly AFR 122-1).

Number: DI-MGMT Approval Date:

Is a dry-dock and internal structural exam required prior to the Coast Guard issuing the initial Certificate of Inspection?

SUBJECT: MAIN ROTOR HUB ASSEMBLY SPINDLE ASSEMBLY, P/N , MANDATORY REVISION OF INSPECTION AND OVERHAUL REQUIREMENTS.

SERVICE BULLETIN TRANSMITTAL SHEET HC-SB Blade - Secondary Windings on ( )7690 and ( )7890 Composite Blades

Code 25 Submarine Network Support Services. Pre-Solicitation Conference

NOTICE OF DISCLOSURE

CFAO RANGE SAFETY OFFICERS

1 Customer and Contact Information

CNRMCINST Code Jun 13. Subj: CONDITION FOUND REPORT (CFR) AND LETTER OF TRANSMITTAL (LOT)

OHIO TURNPIKE AND INFRASTRUCTURE COMMISSION

DRAFT RML-V-6A OPERATOR MAINTENANCE AGREEMENT FOR LINE AND BASE MAINTENANCE BETWEEN. Swedish Armed Forces Air Operator AND N.N AB, FOR HELICOPTER

Department of Defense INSTRUCTION

Brachytherapy-Radiopharmaceutical Therapy Quality Management Program. Rev Date: Feb

Practice Review Guide April 2015

Department of Defense MANUAL

Omega Psi Phi Fraternity, Inc. International Graduate Chapter of the Year Award Application. International Achievement Week Committee

REQUEST FOR PROPOSALS PROFESSIONAL SERVICES FOR THE BRIDGE REHABILITATION PROJECT. Issued by:

DEPARTMENT OF THE NAVY HEADQUARTERS UNITED STATES MARINE CORPS WASHINGTON, DC MCO C SEP 99

Navy ManTech Program. ManTech Update. Tom Hite CTC 15 October 2014

Title: Reliability-Centered Maintenance (RCM) Class Maintenance Plan (CMP) Number: DI-SESS Approval Date:

Housing Rehabilitation Program Administration

HTNA SUPPLIER QUALITY MANUAL

SUBPART ORGANIZATIONAL AND CONSULTANT CONFLICTS OF INTEREST (Revised December 29, 2010)

Ammunition and Explosives related Federal Supply Classes (FSC)

DEPUTY SECRETARY OF DEFENSE 1010 DEFENSE PENTAGON WASHINGTON, DC

ASSIGNMENT 1. Textbook Assignment: "Maintenance Administration." Pages 1-1 through 1-29.

Department of Defense INSTRUCTION. Registration and End-Use Monitoring of Defense Articles and/or Defense Services

Department of Defense INSTRUCTION

Documents and Records Management ISO 14001:

GUIDE FOR ASME REVIEW TEAMS FOR REVIEW OF APPLICANTS FOR ASME CERTIFICATES OF AUTHORIZATION (V, HV, UD, UV, UV3, UD3, TD, TV)

Department of Defense INSTRUCTION

Oxford Downtown Development Authority Façade Grant Improvement Program

Rear Admiral Joe Carnevale

(111) VerDate Sep :55 Jun 27, 2017 Jkt PO Frm Fmt 6601 Sfmt 6601 E:\HR\OC\A910.XXX A910

AIR FORCE CONTRACT CONSTRUCTION

COMPANY PRESENTATION. Broadreach Marine Technical Consultants BY PETER BROAD. CEO & Managing Director

(1) USS Ardent (MCM 12) 2001 Command History (2) 3 54" disk containing 2001 Command History

DOD MANUAL , VOLUME 1 DOD MANAGEMENT OF ENERGY COMMODITIES: OVERVIEW

Command Logistics Review Program

Guidelines on the Keeping of Records in Respect of Medicinal Products when Conducting a Retail Pharmacy Business

Linda Pruitt, RN, MS Associate Professor Eastern Shore Community College Member VCCS PDC Committee Chairperson of Grants Sub-Committee

Environmental & Munitions Center of Expertise (EM CX) Information Fact Sheet US Army Corps of Engineers

COMPLIANCE WITH THIS PUBLICATION IS MANDATORY

Navy Aegis Cruiser and Destroyer Modernization: Background and Issues for Congress

NAVY SHIP MAINTENANCE

Us Navy Shipboard Electrical Tech Manuals READ ONLINE

NAVSEA STANDARD ITEM. 1.1 Title: Physical Security at Private Contractor's Facility; accomplish

ALABAMA SkillsUSA STATE PROGRAM COVER CONTEST Submission deadline Jan. 26 th

As required by the Small Business Act (15 U.S.C. 637(e)) and the Office of Federal Procurement Policy Act (41 U.S.C. 416), Contracting Officers must

EQUIPMENT PURCHASE ORDER ADDENDUM BETWEEN UNIVERSITY OF NORTH CAROLINA HOSPITALS AND. Purchase Order Number

FOR OFFICIAL USE ONLY. Naval Audit Service. Audit Report

REQUEST FOR PROPOSALS. For: As needed Plan Check and Building Inspection Services

Worker Injured Elbow by Lifting Shaft

Ship Maintenance: Provider Perspective. VADM Paul Sullivan Naval Sea Systems Command

RESTORE & Access to Home Programs Exit Conference Webinar 2016 Funding Round. February 27, 2017

Home Health Agency or a Home Care Agency?

UNIFIED FACILITIES GUIDE SPECIFICATIONS

GAO DEFENSE INVENTORY. Navy Logistics Strategy and Initiatives Need to Address Spare Parts Shortages

ST. VINCENT AND THE GRENADINES

This publication is available digitally on the AFDPO WWW site at:

Department of Defense DIRECTIVE

DDG 1000 Class Destroyer

COMPLIANCE WITH THIS PUBLICATION IS MANDATORY

ANNEX 2 RESOLUTION MSC.216(82) (adopted on 8 December 2006)

GUIDE FOR ASME REVIEW TEAMS FOR REVIEW OF APPLICANTS FOR ASME CERTIFICATES OF AUTHORIZATION {A, M, PP, S, E, H, HLW, U, UM, U2, U3, PRT and T}

Duties of a Principal

Transcription:

NAVSEA STANDARD ITEM ITEM NO: 009-67 DATE: 17 JAN 2013 CATEGORY: I 1. SCOPE: 1.1 Title: Integrated Total Ship Testing; manage 2. REFERENCES: 2.1 S9AAO-AB-GOS-010, General Specifications for Overhaul of Surface Ships (GSO) 2.2 S9095-AD-TRQ-010/TSTP, Total Ship Test Program 3. REQUIREMENTS: 3.1 Prepare and manage a Comprehensive Test Plan (CTP) in accordance with Section 092c of 2.1, using 2.2 for guidance. 3.1.1 Define and document the responsibility, lines of authority, and interrelation of personnel who manage, perform, or verify work. 3.1.2 Include a schedule of the restoration of ship's installed services to support completion of Stage 5 testing. 3.1.3 Include a procedure for reporting problems in delivery dates of the Contractor furnished material (CFM), Government furnished material (GFM), Government furnished equipment (GFE), and Government furnished information (GFI) for ship's systems. 3.1.4 Include organizational responsibility for equipment and system installation, repair, maintenance, start-up, operation, and test. 3.1.5 Submit one legible copy, in approved transferrable media, of the CTP to the SUPERVISOR not later than 15 working days prior to availability start date. 3.2 Develop an Integrated Total Ship Test Plan, using contracted work package and available GFI. 3.2.1 Include a shipyard Test Sequence Network (TSN) and test schedule, with Government and Contractor responsibilities defined. 1 of 5 ITEM NO: 009-67

3.2.2 Include required external services, with Government and Contractor responsibilities. 3.2.3 Include a list of necessary test equipment and software, with required dates and responsible provider. 3.2.4 Include organizational responsibility for equipment operation and accomplishment of testing, including Government and Contractor manning requirements. 3.2.5 Include a list of SUPERVISOR, contractor, Alteration Installation Team (AIT), and Ship's Force key test team personnel, with test sign-off authority. 3.2.6 Include administrative procedures for submittal of Test Problem Reports (TPRs), Test Procedures (TPs), Test Failure Reports (TFRs), and test status. 3.2.7 Include identification and display of the combat system critical path for testing. 3.2.8 Include provision for completion of total ship testing through Stage 5 prior to dock trials. 3.2.9 Define the requirements of both Contractor and Government for general and special purpose test equipment, weapon test shapes, dummy loads, and test weights, to accomplish total ship testing. Identify known and anticipated deficiencies in required type, quantity, calibration, or availability, to support the production or test schedule. 3.2.10 Submit one legible copy, in approved transferrable media, of the Test Plan to the SUPERVISOR at the start of the availability. 3.3 Develop and manage a Total Ship Testing Task Group. 3.3.1 The group shall consist of representatives of the SUPERVISOR, Contractor, AIT Team(s) on scene, Ship's Force, and shall meet as requested by the SUPERVISOR. 3.3.2 The SUPERVISOR s representative shall act as Chairman. 3.3.2.1 Provide an updated Total Ship Test Plan and status of Total Ship Testing including growth and new work. Document problems impeding progress of meeting scheduled dates or of satisfying technical requirements. 3.3.2.2 Maintain minutes and agendas. Minutes shall include a list of attendees, action items with assignments, highlights of proceedings, and identified problems with their potential impact. 2 of 5 ITEM NO: 009-67

3.3.2.3 Submit one legible copy, in approved transferrable media, of the minutes and updated Test Plan to the members not later than 2 working days after each meeting. 3.4 Manage Total Ship Testing. 3.4.1 Accomplish the requirements of the Test Plan of 3.2. 3.4.2 Coordinate testing in accordance with the Test Plan. 3.4.3 Coordinate stationing of test personnel in accordance with the Test Plan. Provide test procedures and test data sheets to test personnel. 3.4.4 Coordinate the performance of each test procedure and the recording of each test result on data sheet provided in Attachment A. 3.4.4.1 Ensure sufficient information is provided on the comment sheet for any identified discrepancy, including corrective action. 3.4.4.2 Submit one legible copy, in hard copy or approved transferrable media, of completed data sheets and test procedures for each test in accordance with the Test Plan to the SUPERVISOR within 5 working days of test completion. Include the documentation of each test procedure not completed, and reasons for incompletion. 3.4.5 Coordinate preparations for sea trials. 3.4.6 Develop a test status program completion report that summarizes the results of the Total Ship Test Plan (TSTP) in accordance with Paragraph 3.6 of 2.2. 3.4.6.1 Provide the rationale for test procedures not attempted, incomplete, or failed. 3.4.6.2 Provide details and status of test procedures that were completed with discrepancies. 3.4.7 Submit one legible copy, in hard copy or approved transferrable media, of the test status report to the SUPERVISOR not later than 5 working days after completion of availability. 4. NOTES: 4.1 The ship's Commanding Officer will provide personnel for recording data during Ship's Force/Government responsible total ship testing. 4.2 GFI required to develop the Test Plan may include: Integrated Test Package (ITP), Total Ship's Test Requirements Index (TSTR), Test Index, Test Summary, and known AIT test requirements. 3 of 5 ITEM NO: 009-67

4.3 Stage 5 testing is that testing normally conducted between 2 or more sub-elements within the combat, mobility, support, or containment areas of the ship. 4 of 5 ITEM NO: 009-67

ATTACHMENT A TEST PERFORMANCE, RESPONSIBILITY/WITNESS RECORD TEST PROCEDURE: SHIP'S NAME: TITLE: HULL NO.: TEST PERFORMANCE TEST RESULTS / STATUS (Check all that apply) Complete Complete w/discrepancies Incomplete Failed Not attempted Aborted If TPR issued TPR #: Comments: TEST RESPONSIBILITY / WITNESS Test performed by: Contractor Ship s Force Government If SF/GOV: Ship/Agency Name: Dept/Code: Test witnessed by: Contractor Ship s Force Government If SF/GOV: Ship/Agency Name: Dept/Code: Test record reviewed by: SUPERVISOR (Only) 5 of 5 ITEM NO: 009-67