STATE OF NEW HAMPSHIRE PUBLIC UTILITIES COMMISSION DE RENEWABLE ENERGY INCENTIVE PROGRAM FOR COMMERCIAL AND INDUSTRIAL SOLAR PROJECTS

Similar documents
The Narragansett Electric Company d/b/a National Grid

STATE OF NEW HAMPSHIRE PUBLIC UTILITIES COMMISSION DE Residential Renewable Electric Generation Incentive Program

NEW HAMPSHIRE RENEWABLE ENERGY FUND. Annual Report

The Narragansett Electric Company d/b/a National Grid

Southern California Edison Original Cal. PUC Sheet No E Rosemead, California (U 338-E) Cancelling Cal. PUC Sheet No.

STATE OF NEW HAMPSHIRE PUBLIC UTILITIES COMMISSION DE

Illinois Power Agency Long-Term Renewable Resources Procurement Plan. What s Next?

REVISOR RSI/BR RSI-ENERGY

AMSP Guidebook. February 2017

New Solar Homes Partnership Program Webinar

Multifamily Affordable Solar Housing. Semi Annual Progress Report. July 30, 2012

Multifamily Affordable Solar Housing. Semi Annual Progress Report. July 31, 2013

FY2016 RENEWABLE ELECTRIC STORAGE INCENTIVE PROGRAM STRAW PROPOSAL MAY 07, 2015

2018 RENEWABLE ENERGY GROWTH PROGRAM

DE GRANITE STATE ELECTRIC COMPANY, NEW HAMPSHIRE ELECTRIC COOPERATIVE, PUBLIC SERVICE COMPANY OF NEW HAMPSHIRE and UNITIL ENERGY SYSTEMS

Upcoming Changes to the Solar Photovoltaic Incentive Programs December 15, 2006

Energy Efficiency Alberta Residential and Commercial Solar Program Terms and Conditions

Feed-in Tariff Scheme: Guidance for Licensed Electricity Suppliers

DE NUCLEAR EMERGENCY PLANNING

POLICIES, RULES AND PROCEDURES

Refer to section 2.C. for more information on the evaluation criteria.

Energy Efficiency Alberta Residential and Commercial Solar Program Guidebook

Request for Proposals and Specifications for a Distributed Generation Solar Project entitled The Freeman Coliseum Solar Project


New Solar Homes Partnership. Web Tool Application Guide

Request for Proposals and Specifications for a Community Solar Project

RFP No. FY2017-ACES-02: Advancing Commonwealth Energy Storage Program Consultant

Rhode Island Renewable Distributed Generation Standard Contract Enrollment Application and Enrollment Process Rules

Renewable Portfolio Standard Planning and Development Process

Large Energy User Program Pre-Qualification Application July 1, June 30, 2017 Customer Information

Ground Source Heat Pump - July 1, 2016 through June 30, 2017

SOUTH CAROLINA ELECTRIC & GAS COMPANY REQUEST FOR PROPOSALS FOR SOLAR PHOTOVOLTAIC DISTRIBUTED ENERGY RESOURCES AT TWO DESIGNATED SITES

BEFORE THE PENNSYLVANIA PUBLIC UTILITY COMMISSION

Solar Photovoltaic. Standard Offer Program (SVPSOP) 2018 Program Manual. Rev # Final

1 Customer and Contact Information

New Solar Homes Partnership Program. Maggie Dimitrova Pacific Gas and Electric Company

Request for Proposals ( RFP ) Under the SREC-Based Financing ( SREC-II ) Program

2012 Request for Proposals Solar On-site Renewable Energy Credits (REC)

RESIDENTIAL AND SMALL COMMERCIAL STANDARD OFFER PROGRAM

PROGRAM OPPORTUNITY NOTICE EFFICIENCY MAINE TRUST CUSTOM INCENTIVE PROGRAM FOR DISTRIBUTED GENERATION PROJECTS PON EM

Renewable Energy Tax Incentives Program

Erosion Control and Water Management Policy

SENATE, No STATE OF NEW JERSEY. 218th LEGISLATURE INTRODUCED FEBRUARY 15, 2018

PROGRAM OPPORTUNITY NOTICE EFFICIENCY MAINE TRUST CUSTOM INCENTIVE PROGRAM FOR ELECTRIC EFFICIENCY PROJECTS PON EM

F I L E D :51 AM CALIFORNIA SOLAR INITIATIVE FINAL HANDBOOK APRIL Arnold Schwarzenegger, Governor

Trade Ally WPS Bonus Bid Program

May 6, 2002 Revision 2

ADVERTISEMENT OF PUBLIC NOTICE

PART 1 - Rules and Regulations for the Renewable Energy Development Fund Programs

THE REHABILITATION ACT OF 1973, AS AMENDED (by WIOA in 2014) Title VII - Independent Living Services and Centers for Independent Living

Suffolk COUNTY COMMUNITY COLLEGE PROCUREMENT POLICY

Appendix B-1. Feasibility Study Task Order Template

2017 Solar*Rewards Large Request for Proposals Solar On-site Renewable Energy Credits (REC)

Carbon Neutral Adelaide

CENTRAL MUNICIPAL POWER AGENCY/SERVICES

HUD Q&A. This is a compilation of Q&A provided by HUD regarding relevant issues affecting TCAP and the Tax Credit Exchange Program.

New Renewable Energy System Incentive Program

RULE-MAKING ORDER EMERGENCY RULE ONLY. CR-103E (October 2017) (Implements RCW and )

Carbon Neutral Adelaide

DRAFT RPS Rules Revision Stakeholder Meeting Notes

Commonwealth Solar II Photovoltaic Rebate Program. Program Manual. Solicitation No CSII-Version 20.0 NOTICES:

Incentive Guidelines Start-Up Finance

Residential- and Small-Scale Solar Hot Water Program Manual

Agenda Date: 11/21/17 Agenda Item: 8B CLEAN ENERGY ) ) ) ) )

Commercial Scale. Direct Ownership-Application. Renewable Energy Projects over 10kW. Commercial Block program details can be found at:

California Solar Initiative California Public Utilities Commission Staff Progress Report January 2008

DRAFT PROPOSAL REQUIREMENTS

Community Solar Garden Program Form

Removing Disincentives: Efforts to Promote Electric Utility Efficiency

October 31, Customer Onsite Renewable Energy Program. Market Manager Operations Manual. New Jersey s Clean Energy Program CORE Operations Manual

BEFORE THE FLORIDA PUBLIC SERVICE COMMISSION. The following Commissioners participated in the disposition of this matter:

The following are the procedural steps required for a customer to apply for and receive a Steam Chiller Incentive payment:

PacifiCorp 2017S SOLAR Request for Proposals. Bidder s Conference Portland November 21, 2017

2013 Photovoltaic Solar White Paper. Geography: Tennessee, Mississippi and Alabama TVA Footprint

Application for Distributed Solar Solutions

TULSA PUBLIC SCHOOLS Policy 3407 CHARTER SCHOOLS. To establish guidelines for Charter Schools under the Oklahoma Charter

Enduring Connection Policy Stage 1 (ECP-1)

Incentive Guidelines Start-Up Finance

NOW THEREFORE, the parties enter into the following Agreement:

Renewable Energy Incentive Program. Guidebook

Lands and Investments, Office of

Oregon Community Solar Program + U.S. DOE SunShot In Your Community Challenge

SmartStart Buildings Program Performance Lighting Application FY18 July 1, 2017 June 30, 2018

Farm Energy and Agri-Processing Program Terms and Conditions

5.7 Low-Income Initiatives

COM/LYN/ALJ/MEG/hkr Mailed 3/29/2001

CONSUMERS ENERGY COMPANY REQUEST FOR PROPOSALS SOLAR GENERATION PROJECTS. Bids Due: July 28, :00 noon EPT (Jackson, MI) Issued.

Single-family Affordable Solar Homes (SASH) Program. Semi-annual Program Status Report

National Grid System Reliability Procurement DemandLink Pilot Update

Solar PV Pilot Program Guidebook

Finding Funding for Energy Efficiency

BROWNFIELDS TAX ASSISTANCE / REHABILITATION GRANT PROGRAM GUIDE

CHAPTER RENEWABLE ENERGY TECHNOLOGIES AND ENERGY EFFICIENCY. This part implements the Florida Renewable Energy Technologies and Energy

Implementation of HB 2941, Section 3 Community Solar Program Design August 11, Reminder Please add your name to the sign in sheet.

Guidelines and Instructions to Fill out UI Application for Small ZREC Tariff YEAR 6

This matter comes before the Council on Affordable. Housing ("COAH" or "Council") on the application of Mendham

FREQUENTLY ASKED QUESTIONS

March 2, ADVICE 2327-E (Southern California Edison Company U 338-E) ADVICE 3429-E (Pacific Gas and Electric Company U 39-E)

Funding Renewable Energy Projects on Tribal Lands

AEP Texas - North Division AEP Texas - Central Division

Transcription:

STATE OF NEW HAMPSHIRE PUBLIC UTILITIES COMMISSION DE 10-212 RENEWABLE ENERGY INCENTIVE PROGRAM FOR COMMERCIAL AND INDUSTRIAL SOLAR PROJECTS Order Modifying Program Terms and Reopening Program O R D E R N O. 26,111 March 8, 2018 In this Order, the Commission approves modifications to the existing incentive program for solar energy projects undertaken by commercial and industrial electric customers and reopens the program. The changes include reduction in the amount of the rebate to $0.40 per watt up to a maximum of $50,000, or 25 percent of total project cost, whichever is less; and consolidation of Category 1 and 2 photovoltaic (PV) projects into a single program that would allow applications for projects with capacities up to and including 500 kilowatts AC. No change is made to the program terms and conditions applicable to solar thermal projects. I. PROCEDURAL HISTORY In 2010 the Commission approved a commercial and industrial (C&I) solar rebate program pursuant to RSA 362-F:10, VIII. See Establishing a Commercial and Industrial Renewable Energy Rebate Program, Order No. 25,151 (October 1, 2010). The program provides incentive funds to C&I electric customers for solar photovoltaic and solar thermal energy projects. The program is funded by the Renewable Energy Fund (REF) created by RSA 362-F:10. Application for incentive funds is made through a two-step process in which an initial Step 1 application is typically submitted prior to construction and a final Step 2 application is submitted once the project has become operational.

DE 10-212 - 2 - The program was expanded and modified pursuant to Order No. 25,764 issued on February 20, 2015, in which the Commission created two separate categories of eligible projects: Category 1, consisting of solar electric and thermal systems rated less than or equal to 100 kilowatts (kw) (AC) or thermal equivalent, and Category 2 consisting of solar electric systems greater than 100 kilowatts (AC) but less than or equal to 500 kilowatts (AC). That Order also modified numerous terms and conditions applicable to the program, but essentially left unchanged the two-step application and approval process. Since 2010, the Commission has made relatively minor modifications and clarifications to the program. The program was further modified by Order No. 25,878 (April 6, 2016), with rebate amount reductions and other modifications effective as of May 6, 2016. Pursuant to that Order, the program incentive levels currently are $0.65 per watt (AC) for Category 1 new electric projects, and $0.55 per watt (AC), but not in excess of $175,000, for Category 2 new electric projects, in each case subject to a limit of 25 percent of the total project cost if less than the incentive payment otherwise calculated. Due to high demand and a lack of funds, the program was closed to new applications effective as of July 14, 2017. Following allocation to the program of additional funds for fiscal year 2018 (FY 2018), the Commission by secretarial letter dated September 20, 2017, reopened the program only for waitlisted applications, while keeping the program closed to new applicants. On February 13, 2018, Commission Staff (Staff) filed a memorandum recommending that the program be reopened with modifications to further reduce the applicable incentive levels and to consolidate Category 1 and 2 projects into a single program that would allow applications for projects with capacities up to and including 500 kw AC. The Commission conducted a

DE 10-212 - 3 - public comment hearing regarding the proposed program modifications on February 23, 2018, and provided an opportunity for submission of written comments. This Order and prior docket filings, other than any information for which confidential treatment is requested of or granted by the Commission, are posted at http://www.puc.nh.gov/regulatory/docketbk/2010/10-212.html. II. STAFF S RECOMMENDATION According to Staff, after accounting for the release of funding under expired reservations and projects that were unable to advance, the available funding for new program applications during the remainder of FY 2018 is expected to be a minimum of $660,000. Staff recommended that the program be reopened with that additional funding and with certain program modifications. Based on the limited funding available and anticipated high program demand, Staff recommended that the program incentive level be reduced to $0.40 per watt, with an overall maximum rebate amount of $50,000, or 25 percent of the total project cost, whichever is less. According to Staff, this reduced incentive level and maximum rebate amount would allow a greater number of projects to participate in the program. Regarding the combination of Category 1 and Category 2, Staff said combining the two categories would reduce program administration time, while continuing to allow for funding of a broad range of projects with limited available funds. Staff recommended that the program modifications become effective on a specified future date in order to allow sufficient time for revision of the program application forms, as well as to ensure that applicants will have time to gather and submit the required information. Staff proposed that, upon selection of the reopened program eligibility date, projects that are installed and operational prior to that date would not be eligible for incentives through the modified program. Staff also recommended that the Commission approve a lottery and queue position

DE 10-212 - 4 - determination process to be implemented following the reopening of the program, unless it becomes apparent that the aggregate amount of new project rebates applied for will not exceed available program funds. III. PUBLIC COMMENTS The Commission received comments from interested stakeholders, including solar electric system installers. Commenters were generally supportive of the proposed reduction in the incentive level and the consolidation of Category 1 and Category 2 to effectively create a single program category with one applicable incentive structure and amount. Two commenters objected to the proposed restriction that projects installed and operational prior to the program reopening date not be eligible for incentives under the modified program. Granite State Solar s representative indicated that it had installed a system for a municipal customer during the period that the program was closed and that system owner would be ineligible if the restriction were imposed. He suggested that result would be inequitable given the lack of notice provided when the program was closed. Standard Power s representative expressed concern regarding the potential effect of the proposed restriction on non-profit organizations that had built systems prior to the program reopening date. IV. COMMISSION ANALYSIS The C&I solar energy rebate program, like other rebate programs administered by the Commission, is funded by the REF created under RSA 362-F:10. Pursuant to RSA 362-F:3, providers of electric service must serve a certain percentage of their load with renewable energy, which is represented by renewable energy certificates (REC), assigning one REC for each megawatt-hour or megawatt-hour equivalent of renewable power generated. If the electric service provider is unable to acquire a sufficient number of RECs to meet its compliance

DE 10-212 - 5 - obligation, then the provider must make an alternative compliance payment (ACP) into the REF pursuant to RSA 362-F:10, II. The REF monies collected are to be used to support thermal and electric renewable energy initiatives. RSA 362-F:10. Under RSA 362-F:10, X, the Commission must, over each biennial period, reasonably balance the overall amounts expended, allocated, or obligated from the REF between the residential and nonresidential sectors, with reference to the amount of retail electricity sales made to customers in each sector. We have reviewed Staff s proposed modifications to the program, as well as the comments received from system installers and other interested stakeholders. We find that modification of the program is warranted in light of the continuing levels of interest in the program and budgetary limitations. We therefore approve and adopt Staff s proposed modifications to the program, including the reduction of the incentive amount, setting a maximum rebate amount, and the consolidation of Category 1 and Category 2 into a single program structure and design. With respect to the proposed restriction that projects installed and operational prior to the program reopening date not be eligible for incentives under the modified program, we see no reason to diverge from the precedent previously set in this docket when the program has been reopened following a period of closure. For example, in 2016 we directed that, [f]or each program category, the eligibility date will be May 6, 2016, and projects that are installed and become operational prior to such date will not be eligible for the modified program, when Category 2 of the program had been closed for some time prior to that date. See Order No. 25,878 (April 6, 2016) at 28. Project developers that installed and interconnected systems during the period when the program was closed and its future funding was uncertain may be

DE 10-212 - 6 - presumed to have had a less pressing need for the rebate than those that wait to build until the program is reopened. We acknowledge that the residential renewable electric generation incentive program was recently reopened without any date restriction on system eligibility, including for those systems installed during the time period when the program was closed to new applications. See Order No. 26,075 (November 20, 2017) at 10. That decision was made consistent with the statutory requirement to provide a one-time incentive payment per facility to any residential owner of a qualified small renewable generation facility. See RSA 362-F:10, V. By contrast, Commission administration of the C&I program is not required by statute, but has been adopted and approved by Commission order under RSA 362-F:10, VIII. That statute does not require payments to specific classes of renewable energy system owners, but rather provides the Commission the opportunity to create incentive programs for the development of renewable energy facilities, with greater flexibility afforded for determining the timing and availability of any payments to be made through those programs. Staff has recommended that the program modifications become effective on a specified future date to allow enough time for the program application forms to be revised, as well as to ensure that applicants have sufficient time to gather and submit the required information for the modified program applications. We have considered the relevant issues and have determined that the following transition process and timeline should be implemented. The modified program terms and conditions approved in this Order will become effective on March 19, 2018, and the program will be reopened on that date. All applications received on or after that date will be processed under the program terms and conditions as modified by this

DE 10-212 - 7 - Order. The eligibility date will be March 19, 2018, and projects that are installed and become operational prior to such date will not be eligible for the modified program. In anticipation of robust demand for and potential oversubscription of the reopened program, we will conduct a public lottery to allocate initial queue positions for applications received by the close of business (4:30 p.m.) on April 23, 2018. The public lottery will be held on April 30, 2018, at 1:00 p.m. If it becomes apparent that the aggregate amount of new project incentives applied for will not exceed available program funds, then the lottery will be cancelled. We have previously implemented a lottery process for the C&I program and also for the residential renewable rebate program, and we believe that process should facilitate an orderly and equitable means of administering applications for a limited amount of funds. In the interest of increased administrative efficiency, we encourage Staff to implement an automated process for conducting the lottery. Notwithstanding an application s initial or subsequent queue position in the lottery, incentive funds will be reserved and ultimately paid to the project owner only if budgeted monies are available for such reservation and payment. If the initial application and lottery process results in a significant number of waitlisted applications, we may again consider closing the program to new applications. We therefore direct Staff to implement application submission, processing, review, and approval procedures consistent with this Order. To facilitate administration, we authorize Staff to make clerical, administrative, and other modifications to program application forms and processes without further Commission approval, provided that such modifications are consistent with this Order.

DE 10-212 - 8 - Based upon the foregoing, it is hereby ORDERED, that the Commission's commercial and industrial solar rebate program shall be modified as described in the body of this Order; and it is FURTHER ORDERED, that Staff is directed to implement program application submission, processing, review, and approval procedures consistent with this Order; and it is FURTHER ORDERED, that Staff is authorized to make clerical, administrative, and other modifications to program application forms and processes without further Commission approval, provided that such modifications are consistent with this Order. By order of the Public Utilities Commission of New Hampshire this eighth day of March, 2018. Attested by: ~~ 0\. ~~Q~Q_ Debra A. Howland Executive Director

SERVICE LIST - EMAIL ADDRESSES- DOCKET RELATED Pursuant to N.H. Admin Rule Puc 203.11(a) (1): Serve an electronic copy on each person identified on the service list. Executive.Directorpuc.nh.gov alien.desbiens@eversource.corn amanda.noonanpuc.nh.gov azanna.wishart@puc.nh.gov barbara.bernsteinpuc.nh.gov callnanb@nhec.com christopher.gou1dingeversource.com david.wiesnerpuc.nh.gov ddrisco11concordnh.gov deandra.peffucciopuc.nh.gov palma@unitil.com richard.1abrecqueeversource.com sharon.rivarddes.nh.gov Stephen.Eckbergpuc.nh.gov Stephen.Ha111ibertyuti1ities.com tanya.way1andpuc.nh.gov tom.ftantzpuc.nh.gov tony.buschur@trane.com debski@unitil.com dona1d.kreisoca.nh.gov e1izabeth.nixonpuc.nh.gov epler@unitil.com j ames.brennanoca.nh.gov ji11.fitzpatrick1ibertyuti1ities.com karninski@nhec.com karen. cramtonpuc.nh.gov 1emaygnhec.corn matthew.fossum@eversource.com mdean@mdeanlaw.net michae1.sheehan1ibertyuti1ities.com michae1.sistopuc.th.gov oca1itigationoca.nh.gov Docket #: 10-212-1 Printed: March 08, 2018 FILING INSTRUCTIONS: a) Pursuant to N.H. Admin Rule Puc 203.02 (a), with the exception of Discovery, file 7 copies, as well as an electronic copy, of all documents including cover letter with: DEBRAA HOWLAND EXEC DIRECTOR NHPUC 21 S. FRUIT ST, SUITE 10 CONCORD NH 03301-2429 b) Serve an electronic copy with each person identified on the Commission s service list and with the Office of Consumer Advocate. c) Serve a written copy on each person on the service list not able to receive electronic mail.