Standard Development Timeline

Similar documents
Standard FAC Facility Ratings. A. Introduction

Standard FAC Assessment of Transfer Capability for the Near-term Transmission Planning Horizon

COM Operating Personnel Communications Protocols

CIP Cyber Security Incident Reporting and Response Planning

Standard EOP System Restoration Coordination

WECC Standard VAR-002-WECC-2 Automatic Voltage Regulators

Standard CIP 004 4a Cyber Security Personnel and Training

4.2.2 Transmission Owners Transmission Planners Transmission Service Providers Balancing Authorities.

5. Effective Date: See the Implementation Plan for IRO B. Requirements and Measures

To ensure system protection is coordinated among operating entities.

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION ) )

Standard NUC Nuclear Plant Interface Coordination

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION. NORTH AMERICAN ELECTRIC ) RELIABILITY CORPORATION ) Docket No.

Northeast Power Coordinating Council, Inc. Regional Standards Process Manual (RSPM)

Future Development Plan:

Northeast Power Coordinating Council, Inc. Regional Standard Processes Manual (RSPM)

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION. North American Electric Reliability ) Corporation ) Docket No.

Implementation Plan Set Two of Phase III & IV Reliability Standards

ERO Enterprise Strategic and Operational Planning and 2018 Business Plan and Budget Preparation Schedule (2017 Development Year)

PER-005 System Personnel Training

November 13, Ms. Kimberly Bose Secretary Federal Energy Regulatory Commission 888 First Street, N.E. Washington, D.C

VIA ELECTRONIC FILING

130 FERC 61,211 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION

TRANSMISSION TRANSMISSION SYSTEM OPERATIONS DIVISION

Appendix 5A. Organization Registration and Certification Manual

WECC Standard VAR-STD-2a-1 Automatic Voltage Regulators

BC Hydro writes to provide the BCUC with its second errata to the Addendum to Assessment Report No. 6 (Addendum) filed on September 30, 2013.

Generator Interconnection Impact Study Report Bladen County, NC 75.0 MW Solar Farm Queue #377

NERC SPCTF Supplemental Assessment Addressing FERC Order 693 Relative to:

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION ) ) )

Generator Interconnection System Impact Study Report Carteret County, NC MW Queue #297 Original Submittal Revision 1

Project Laura Anderson, NERC Standards Developer August 18, 2016

Minutes Board of Trustees

WICF GOTO Focus Group Update

Generator Interconnection Facilities Study Report Franklin County, NC 50.0 MW Solar Farm Queue #384

April 13, 2015 VIA ELECTRONIC FILING. Veronique Dubois Régie de l'énergie Tour de la Bourse 800, Place Victoria Bureau 255 Montréal, Québec H4Z 1A2

Electric Reliability Organization Event Analysis Process Phase 2 Field Test Draft May 2,

NERC SPCTF Supplemental Assessment Addressing FERC Order 693 Relative to PRC System Protection Coordination

Appendix 5A. Organization Registration and Certification Manual. WORKING DRAFT-August 26, 2014

Meeting Notes Project Phase 2 of Relay Loadability: Generation Standard Drafting Team December 11-14, 2012

Generator Interconnection Impact Study Report Wayne County, NC 20.0 MW Solar Farm Queue #364

107 FERC 61,053 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION

Pilot Project Initiative

Project Phase 2 Undervoltage Load Shedding: Misoperations UVLS Standard Drafting Team. Industry Webinar February 3, 2015

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION

NPCC Tasks Related to NERC Blackout Recommendations Timeline

Attachment A. Procurement Contract Submission and Conflict of Interest Policy. April 23, 2018 (revised)

NPCC Tasks Related to NERC Blackout Recommendations Timeline

NERC BES Kickoff Webinar. May 2, 2014

March 30, Ms. Kimberly D. Bose Secretary Federal Energy Regulatory Commission 888 First Street, N.E. Washington, DC 20426

WECC Criterion PRC-006-WECC-CRT-3

Explanatory document for the Nordic synchronous area proposal for coordination actions aiming to reduce FRCE as defined in Article 152(14) and

The Narragansett Electric Company d/b/a National Grid

Small and Large Generator Interconnection Procedures

Business Requirements Specification

Public Service Commission

Enduring Connection Policy Stage 1 (ECP-1)

Colorado Board of Pharmacy Rules pertaining to Collaborative Practice Agreements

Root Cause Analysis. Chris Bills Compliance Enforcement Attorney

Provider Service Expectations Transportation Services SPC 107 Provider Subcontract Agreement Appendix N

UCF SOLAR FARM-UCF 584 Solar Developer Project Fact Sheet

AUSTIN ENERGY REQUEST FOR PROPOSALS (RFP) FOR THE PURCHASE OF RENEWABLE CAPACITY & ENERGY FROM RENEWABLE ENERGY RESOURCES

The State of Interconnection in NYS:

SA 610 (REVISED) USING THE WORK OF INTERNAL AUDITORS. Contents

PEAK RELIABILITY. Enhanced Curtailment Calculator Task Force (ECCTF) Charter. Enhanced Curtailment Calculator Charter Final Draftv3.

Attachment Actively Monitored Standards.17. Attachment Audit Schedule..18. Attachment 4 - Future Years Audit Schedule 19

Teaching the Smart Grid

The Code of Conduct on the Safety of Research Reactors

ATTACHMENT B. 1. Intent to Bid/Bidder Contact Information Form. 2. Executive Summary. 3. Proposal Characteristics and Term Sheet

1.4 On 19 May 2011 the WA State Government announced a reduction in the Subsidy rate from 40c/kWh to 20c/kWh effective from 1 July 2011.

REPORT OF THE SYSTEM RELIABILITY, PLANNING, AND SECURITY COMMITTEE

Request for Proposals and Specifications for a Community Solar Project

Guidance for Industry ANDA Submissions Prior Approval Supplements Under GDUFA

FUNDAMENTALS OF ELECTRICITY TRANSMISSION COURSE

DEPARTMENT OF ENVIRONMENTAL CONSERVATION SELECTED ASPECTS OF THE DAM SAFETY PROGRAM. Report 2006-S-61 OFFICE OF THE NEW YORK STATE COMPTROLLER

Creation Date: 1/30/15 Title: Patient Right to Access, Inspect and Copy Revision History:

TITLE 11. CALIFORNIA BUREAU OF GAMBLING CONTROL NOTICE OF PROPOSED RULEMAKING

July 1, 2006 Revision 2

Last updated on April 23, 2017 by Chris Krummey - Managing Attorney-Transactions

Comprehensive Interconnection Process Improvements

Banking Regulation and Policy Department Bangladesh Bank Head Office Dhaka

Consideration of Comments

1. Research Customer Research the various types of renewable energy systems available and decide which system best fits your consumption needs.

PART 1 - Rules and Regulations for the Renewable Energy Development Fund Programs

Southern California Edison Original Cal. PUC Sheet No E Rosemead, California (U 338-E) Cancelling Cal. PUC Sheet No.

Code. of CONDUCT R E L I A B I L I T Y COORDINATOR

The Narragansett Electric Company d/b/a National Grid

Section VII Provider Dispute/Appeal Procedures; Member Complaints, Grievances, and Fair Hearings

Topic: CAP s Legislative Proposal for Laboratory-Developed Tests (LDT) Date: September 14, 2015

Energy. Request For Proposals for Renewable Power Supply Resources

COMPLIANCE WITH THIS PUBLICATION IS MANDATORY

UNITED STATES MARINE CORPS HEADQUARTERS UNITED STATES MARINE CORPS 3000 MARINE CORPS PENTAGON WASHINGTON, DC

Review of compliance. The Birth Company The Birth Company Limited. London. Region: 137 Harley Street London W1G 6BF.

Duquesne Light Our Energy...Your Power

II. Accuracy: Professional work is completed with due diligence and is accurate.

Upcoming Changes to the Solar Photovoltaic Incentive Programs December 15, 2006

SECURITY and MANAGEMENT CONTROL OUTSOURCING STANDARD for NON-CHANNELERS

Conflict of Interest with Grants Policy DRAFT

Chapter 19 Section 3. Privacy And Security Of Protected Health Information (PHI)

SECTION 4. Construction Site Runoff Control Program

Transcription:

FAC-001-23 Interconnection Requirements Standard Development Timeline This section is maintained by the drafting team during the development of the standard and will be removed when the standard becomes effective. Description of Current Draft This is the first posting of the draft standard for a 45 day formal comment period with an initial ballot. Completed Actions Date Standards Committee approved SAR for posting June 10, 2014 SAR posted for comment July 16, 2014 Anticipated Actions 45 day formal comment period with parallel ballot Date August/September 2015 Final ballot October 2015 NERC Board adoption November 2015 Draft #1 of Standard FAC 001 3: July, 2015 Page 1 of 11

FAC-001-23 Interconnection Requirements New or Modified Terms Used in NERC Reliability Standards This section includes all new or modified terms used in the proposed standard that will be included in the Glossary of Terms Used in NERC Reliability Standards upon applicable regulatory approval. Terms used in the proposed standard that are already defined and are not being modified can be found in the Glossary of Terms Used in NERC Reliability Standards. The new or revised terms listed below will be presented for approval with the proposed standard. Term: None Draft #1 of Standard FAC 001 3: July, 2015 Page 2 of 11

FAC-001-23 Interconnection Requirements A. Introduction 1. Title: Interconnection Requirements 2. Number: FAC-001-23 3. Purpose: To avoid adverse impacts on the reliability of the Bulk Electric System, Transmission Owners and applicable s must document and make requirements available so that entities seeking to interconnect will have the necessary information. 4. Applicability: 4.1. Functional Entities: 4.1.1 Transmission Owner 4.1.2 Applicable 4.1.2.1 with a fully executed Agreement to conduct a study on the reliability impact of interconnecting a third party to the s existing that is used to interconnect to the Transmission system. 4.1.3 Load Serving Entities 5. Effective Date: See Implementation Plan for FAC-001-3. B. Requirements and Measures R1. Each Transmission Owner shall document requirements, update them as needed, and make them available upon request. Each Transmission Owner s requirements shall address requirements for: [Violation Risk Factor: Lower] [Time Horizon: ] 1.1. generation Facilities; 1.2. transmission Facilities; and 1.3. end-user Facilities. M1. Each Transmission Owner shall have evidence (such as dated, documented requirements) that it met all requirements in Requirement R1. R2. Each applicable shall document requirements and make them available upon request within 45 calendar days of full execution of an Agreement to conduct a study on the reliability impact of interconnecting a third party to the s existing that is used to interconnect to the Transmission system. [Violation Risk Factor: Lower] [Time Horizon: ] M2. Each applicable shall have evidence (such as dated, documented requirements) that it met all requirements in Requirement R2. Draft #1 of Standard FAC 001 3: July, 2015 Page 3 of 11

FAC-001-23 Interconnection Requirements R3. Each Transmission Owner shall address the following items in its requirements: [Violation Risk Factor: Lower] [Time Horizon: Long- Term ] 3.1. Procedures for coordinated studies of new or materially modified existing s and their impacts on affected system(s). 3.2. Procedures for notifying those responsible for the reliability of affected system(s) of new or materially modified existing s. M3. Each Transmission Owner shall have evidence (such as dated, documented requirements addressing the procedures) that it met all requirements in Requirement R3. R4. Each applicable shall address the following items in its requirements: [Violation Risk Factor: Lower] [Time Horizon: Long- Term ] 4.1. Procedures for coordinated studies of new s and their impacts on affected system(s). 4.2. Procedures for notifying those responsible for the reliability of affected system(s) of new s. M4. Each applicable shall have evidence (such as dated, documented requirements addressing the procedures) that it met all requirements in Requirement R4. R5. Each Transmission Owner with Transmission Facilities operating in an Interconnection shall confirm that each Transmission is within a Balancing Authority Area s metered boundaries. [Violation Risk Factor: Medium] [Time Horizon: Long-Term ] M5. Each Transmission Owner shall have evidence (such as dated, documented requirements addressing the procedures) that it met all requirements in Requirement R5. R6. Each with generation Facilities operating in an Interconnection shall confirm that each generation is within a Balancing Authority Area s metered boundaries. [Violation Risk Factor: Medium] [Time Horizon: Long-Term ] M6. Each shall have evidence (such as dated, documented requirements addressing the procedures) that it met all requirements in Requirement R6. R7. Each Load-Serving Entity with Load operating in an Interconnection shall confirm that each Load is within a Balancing Authority Area s metered boundaries. [Violation Risk Factor: Medium] [Time Horizon: Long-Term ] M7. Each applicable Load Serving Entity shall have evidence (such as dated, documented requirements addressing the procedures) that it met all requirements in Requirement R7. Draft #1 of Standard FAC 001 3: July, 2015 Page 4 of 11

FAC-001-23 Interconnection Requirements C. Compliance 1. Compliance Monitoring Process 1.1. Compliance Enforcement Authority As defined in the NERC Rules of Procedure, Compliance Enforcement Authority (CEA) means NERC or the Regional Entity in their respective roles of monitoring and enforcing compliance with the NERC Reliability Standards. 1.2. Evidence Retention The following evidence retention periods identify the period of time an entity is required to retain specific evidence to demonstrate compliance. For instances where the evidence retention period specified below is shorter than the time since the last audit, the CEA may ask an entity to provide other evidence to show that it was compliant for the full time period since the last audit. Owner and applicable shall keep data or evidence to show compliance as identified below unless directed by its CEA to retain specific evidence for a longer period of time as part of an investigation: The responsible entities shall retain documentation as evidence for three years. If a responsible entity is found non-compliant, it shall keep information related to the non-compliance until mitigation is complete and approved or for the time specified above, whichever is longer. The CEA shall keep the last audit records and all requested and submitted subsequent audit records. 1.3. Compliance Monitoring and Assessment Processes: Compliance Audit Self-Certification Spot Check Compliance Investigation Self-Reporting Complaint 1.4. Additional Compliance Information None Draft #1 of Standard FAC 001 3: July, 2015 Page 5 of 11

FAC-001-23 Interconnection Requirements Table of Compliance Elements R # Time Horizon VRF Violation Severity Levels Lower VSL Moderate VSL High VSL Severe VSL R1 Lower N/A Owner documented requirements and updated them as needed, but failed to make them available upon request. Owner documented requirements, but failed to update them as needed and failed to make them available upon request. Owner did not document requirements. OR OR Owner documented requirements and made them available upon request, but failed to update them as needed. OR Owner documented requirements, updated them as needed, and made them available upon request, but Owner documented requirements, updated them as needed, and made them available upon request, but failed to address requirements for two of the Facilities as specified in R1, Parts 1.1, 1.2, or 1.3. Draft #1 of Standard FAC 001 3: July, 2015 Page 6 of 11

FAC-001-23 Interconnection Requirements failed to address requirements for one of the Facilities as specified in R1, Parts 1.1, 1.2, or 1.3. R2 Lower The applicable failed to document requirements and make them available upon request until more than 45 calendar days but less than or equal to 60 calendar days after full execution of an Agreement to conduct a study on the reliability impact of interconnecting a third party to the s existing that is used to interconnect to the Transmission system. The applicable failed to document requirements and make them available upon request until more than 60 calendar days but less than or equal to 70 calendar days after full execution of an Agreement to conduct a study on the reliability impact of interconnecting a third party to the s existing that is used to interconnect to the Transmission system. The applicable failed to document requirements and make them available upon request until more than 70 calendar days but less than or equal to 80 calendar days after full execution of an Agreement to conduct a study on the reliability impact of interconnecting a third party to the s existing that is used to interconnect to the Transmission system. The applicable failed to document requirements and make them available upon request until more than 80 calendar days after full execution of an Agreement to conduct a study on the reliability impact of interconnecting a third party to the s existing that is used to interconnect to the Transmission system. Draft #1 of Standard FAC 001 3: July, 2015 Page 7 of 11

FAC-001-23 Interconnection Requirements R3 Lower N/A N/A Owner addressed either R3, Part 3.1 or Part 3.2 in its requirements, but did not address both. Owner addressed neither R3, Part 3.1 nor Part 3.2 in its requirements. R4 Lower N/A N/A The applicable addressed either R4, Part 4.1 or Part 4.2 in its requirements, but did not address both. The applicable addressed neither R4, Part 4.1 nor Part 4.2 in its requirements. R5 Medium N/A N/A N/A Operator with Transmission Facilities operating in an Interconnection failed to ensure that those Transmission Facilities were included within metered boundaries of a Balancing Authority Area. Draft #1 of Standard FAC 001 3: July, 2015 Page 8 of 11

FAC-001-23 Interconnection Requirements R6 R7 Medium Medium N/A N/A N/A The Generation Operator with generation Facilities operating in an Interconnection failed to ensure that those generation Facilities were included within metered boundaries of a Balancing Authority Area. N/A N/A N/A The Load-Serving Entity with Load operating in an Interconnection failed to ensure that those Loads were included within metered boundaries of a Balancing Authority Area. D. Regional Variances None. E. Interpretations None. F. Associated Documents None. Draft #1 of Standard FAC 001 3: July, 2015 Page 9 of 11

Application Guidelines Guidelines and Technical Basis Entities should have documentation to support the technical rationale for determining whether an existing was materially modified. Recognizing that what constitutes a material modification will vary from entity to entity, the intent is for this determination to be based on engineering judgment. Requirement R3: Originally the Parts of R3, with the exception of the first two bullets, which were added by the Project 2010-02 drafting team, this list has been moved to the Guidelines and Technical Basis section to provide entities with the flexibility to determine the requirements that are technically appropriate for their respective Facilities. Including them as Parts of R3 was deemed too prescriptive, as frequently some items in the list do not apply to all applicable entities and some applicable entities will have requirements that are not included in this list. Each Transmission Owner and applicable should consider the following items in the development of requirements: Procedures for requesting a new or material modification to an existing Data required to properly study the Voltage level and MW and MVAR capacity or demand at the point of Breaker duty and surge protection System protection and coordination Metering and telecommunications Grounding and safety issues Insulation and insulation coordination Voltage, Reactive Power (including specifications for minimum static and dynamic reactive power requirements), and power factor control Power quality impacts Equipment ratings Synchronizing of Facilities Maintenance coordination Operational issues (abnormal frequency and voltages) Inspection requirements for new or materially modified existing s Communications and procedures during normal and emergency operating conditions Page 10 of 11

Application Guidelines Version History Version Date Action Change Tracking 0 April 1, 2005 Effective Date New 1 Added requirements for Generator Owner and brought overall standard format up to date. 1 February 9, 2012 Adopted by the Board of Trustees 1 September 19, 2013 A FERC order was issued on September 19, 2013, approving FAC-001-1. This standard became enforceable on November 25, 2013 for Transmission Owners. For s, the standard becomes enforceable on January 1, 2015. 2 Revisions to implement the recommendations of the FAC Five- Year Review Team. 2 August 14, 2014 Adopted by the Board of Trustees 2 November 6, 2014 FERC letter order issued approving FAC-001-2. Revision under Project 2010-07 Revision under Project 2010-02 Page 11 of 11